Case Law[2022] ZAGPJHC 319South Africa
Strucstar Investments (Pty)Ltd vs Eskom Holdings Soc Ltd (2021/26409) [2022] ZAGPJHC 319 (10 May 2022)
Headnotes
judgment is granted against the defendant for:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 319
|
Noteup
|
LawCite
sino index
## Strucstar Investments (Pty)Ltd vs Eskom Holdings Soc Ltd (2021/26409) [2022] ZAGPJHC 319 (10 May 2022)
Strucstar Investments (Pty)Ltd vs Eskom Holdings Soc Ltd (2021/26409) [2022] ZAGPJHC 319 (10 May 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_319.html
sino date 10 May 2022
# IN THE HIGH COURT OF
SOUTH AFRICA,
IN THE HIGH COURT OF
SOUTH AFRICA,
# GAUTENG DIVISION,
JOHANNESBURG
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO: 2021/26409
Reportable:
NO
Of
interest to other judges: NO
10
May 2022
In
the matter between:
STRUCSTAR
INVESTMENTS (PTY) LTD
(Registration
No: 1998/021602/07)
Plaintiff/Applicant
and
ESKOM
HOLDINGS SOC LTD
Defendant/Respondent
(Registration
No: 2002/015527/30)
# JUDGMENT
JUDGMENT
MOORCROFT
AJ:
##
## Order
Order
[1]
I make the following order:
1.
Summary judgment is granted against the defendant for:
1.1.
Payment in the sum of R474 906.00 plus value added tax
calculated at 15%, the total being R546 141.90;
1.2.
Interest at the rate of 7% per annum on the amount of
R474 906.00 from 8
November 2019 to date of payment.
2.
Costs.
[2]
The reasons for the order are set below.
## Introduction
Introduction
[3]
The two questions to be decided in this summary judgment application
is
3.1
whether or
not the plaintiff’s claim is for a liquidated amount of
money
[1]
,and
if so
3.2
whether the plaintiff is entitled to summary judgment.
[4]
This first
question in turn depends on whether the defendant unequivocally
admitted the amount of the plaintiff’s claim in
the amount of
R474 906.00 exclusive of value added tax at the rate of 15%
[2]
.
## The lease
The lease
[5]
In 2012 the parties entered into a lease agreement
3
in
terms of which the plaintiff leased certain premises to the defendant
initially for a period of 5 years. After the expiry of
the initial
term, the lease was relocated on a monthly basis on the same terms.
The defendant finally vacated the premises in September
2019.
[6]
The plaintiff alleges that during the currency of the lease the
defendant caused material damage to the premises. This damage was
quantified in the amount of R474 906.00.
[7]
In terms of clause 9.3 of the agreement the defendant undertook to
make good and repair any damage or breakages. Should the defendant
fail to do so the plaintiff was entitled to perform the work
and
recover the expenditure from the defendant.
## The claim for
reinstatement of the premises
The claim for
reinstatement of the premises
[8]
The defendant was furnished with a spreadsheet setting out the costs
for the reinstatement of the premises in terms of the contract
following an inspection of the premises on 2 October 2021. The total
amounted to R474 906.00 for all works, to which was added various
additional amounts for supervision and project management. These
additional amounts are not claimed in the action.
[9]
On 25 October 2019 the plaintiff wrote to the defendant and provided
it with the aforesaid spreadsheet. This was done under cover of an
email, the relevant parts of which read as follows:
“
Please find
attached the pricing. Please bear in mind that Eskom did very little
if any maintenance over the leased term of 12 years
on this property
and this is clear given the poor state of the premises.
…
All risk will
be on us and there will be no comebacks to Eskom with regard to price
increases, quality of work, measurement discrepancies
or delays in
the time to complete the works ie this will be in full and final
settlement of reinstatement claims.”
[3]
[10]
On 31 October 2019, Eskom responded and wrote that:
“
The received
quotations for the required work appear reasonable and can be agreed
to; thank you.”
10.1
The correspondence then went on to query the project management fee
on the amount of the
works and made it clear that the defendant could
not accept the management fee “
as it is far beyond what we
normally pay for project management fees. We hereby propose 8%”
.
10.2
The defendant also queried other charges such as rental cost for
November 2019.
10.3
What was conceded was that there was required work, that the
quotations appeared reasonable,
and the amount could be agreed to.
This was a reference to the amount of R474 906.00.
[11]
On 4 November 2019 the defendant again wrote to confirm that the
management fee of
23% could not be agreed to and that rental for
November 2019 was also disputed. The letter then says:
“
We are of the
view that the quoted works, plus an 8% project management fee is
fair.”
[12]
The ‘quoted works’ is a reference to the quote for R474
906.00. The defendant
offered a 8% management fee on the amount of
R474 906.00.
[13]
There was correspondence about the question whether or not the
defendant was going
to do the work itself and on 5 November 2019 the
defendant informed the
plaintiff
that:
“
Kindly be
advised that we are not going to attend to the work ourselves. The
intention was to agree to costs and pay you as the
landlord for
actual quoted costs.”
[14]
On the same day the defendant wrote to say that:
“
We agree to the
work but we do not agree to the project management fee nor can we
agree to the contingency fee.”
[15]
The amount of R546 141.90 (inclusive of value added tax) is therefore
a liquidated
amount and one then turns to the question whether the
plaintiff is entitled to judgment for this amount. In its affidavit
resisting
summary judgment, the deponent to the affidavit stated
that:
“
the defendant
did not expressly agree to the cost of the alleged repairs. Eskom
acknowledged that repair work is needed to the premises
following
Eskom vacating the premises when the lease expired. Eskom, however,
did not agree on the proposed amount for the repairs.”
[4]
[16]
The affidavit then goes on to say that while the defendant
“
acknowledged that the quoted amount appears to be
reasonable and that it was prepared to agree to the amount, no actual
agreement
on the amount was ever reached”
. It is then
stated that the defendant “
had to first establish if the
amount proposed by the defendant was market-related and comparable in
relation to the alleged damages
in this instance”
.
[17]
When one has regard to the correspondence referred to above, it is
clear that there
was agreement on the amount of the damages in
respect of certain repairs, but not in respect of a management fee, a
contingency
fee, and rental for periods after termination of the
lease.
[18]
The work was also expressly agreed to.
[19]
Even if one were to interpret the correspondence to say that the
amount of the claim
was agreed but not the entitlement to have the
work done (an argument defeated by the very words used in the
correspondence) it
nevertheless follows that the amount was a
liquidated amount and the plaintiff set out its entitlement to
payment of the liquidated
amount satisfactorily in its affidavit
while the defendant fails to set out an arguable defence.
[20]
I conclude that the plaintiff is therefore entitled to summary
judgment.
[21]
The plaintiff made no attempt to prove the interest rate alleged and
is therefore
entitled only to
mora
interest in terms of the
Prescribed Rate of Interest Act, 55 of 1975
. The rate is 7%.
J
MOORCROFT
ACTING
JUDGE OF THE HIGH COURT OF SOUTH AFRICA GAUTENG DIVISION
JOHANNESBURG
Electronically
submitted
Delivered:
This judgement was prepared and authored by the Acting Judge whose
name is reflected and is handed down electronically
by circulation to
the Parties / their legal representatives by email and by uploading
it to the electronic file of this matter
on Caselines. The date of
the judgment is deemed to be
10 MAY 2022
.
COUNSEL
FOR THE PLAINTIFF/APPLICANT:
G H FERRAR
INSTRUCTED
BY:
FYFER
INC
COUNSEL
FOR DEFENDANT/RESPONDENT:
M
MUSANDIWA
INSTRUCTED
BY:
CHEADLE THOMSON & HAYSOM INC
DATE
OF THE HEARING:
3
May 2022
DATE
OF JUDGMENT:
10
May 2022
[1]
See
Rule 32(1)(b).
See also Van Loggerenberg and Bertelsmann
Erasmus:
Superior Court Practice
vol 2, D1-379.
[2]
It is common cause that the plaintiff is a registered VAT vendor.
3
Annexure “POC6” to particulars of claim (Caselines
001-39).
[3]
See Caselines 011-83.
[4]
See CaseLines 100-5 and para 13 of the affidavit.
sino noindex
make_database footer start
Similar Cases
Structra Group (Pty) Ltd v Van Niekerk and Others (06923/2019) [2022] ZAGPJHC 219 (11 April 2022)
[2022] ZAGPJHC 219High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Main Street 1613 (RF) and Others v Solar Capital Orange (RF) Proprietary Limited and Others (56709/2021) [2023] ZAGPJHC 109 (25 January 2023)
[2023] ZAGPJHC 109High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Stefanutti Stocks Housing (A Division of Stefanutti Stocks (Pty) Ltd) v Instratin Properties (Pty) Ltd (2022/032179 ; 2022/032192) [2023] ZAGPJHC 1109 (4 October 2023)
[2023] ZAGPJHC 1109High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Just Splendid (Pty) Ltd and Another v Khunou and Others (2023/103030) [2023] ZAGPJHC 1175 (17 October 2023)
[2023] ZAGPJHC 1175High Court of South Africa (Gauteng Division, Johannesburg)99% similar
S.T.T and Others v Minister Of Police (26369/2021) [2023] ZAGPJHC 150 (20 February 2023)
[2023] ZAGPJHC 150High Court of South Africa (Gauteng Division, Johannesburg)99% similar