begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 336
|
Noteup
|
LawCite
sino index
## Road Accident Fund v Commissioner for the South African Revenue Service and Another (019721/2025)
[2025] ZAGPPHC 336 (26 March 2025)
Road Accident Fund v Commissioner for the South African Revenue Service and Another (019721/2025)
[2025] ZAGPPHC 336 (26 March 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_336.html
sino date 26 March 2025
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
CASE
NO:
019721/2025
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: YES
(3)
REVISED:
DATE:
26 March 2025
SIGNATURE
In
the matter between:
ROAD
ACCIDENT
FUND
Applicant
and
COMMISSIONER
FOR THE SOUTH AFRICAN
REVENUE
SERVICE
First Respondent
MINISTER OF
FINANCE
Second Respondent
ESKOM
Intervening Party
JUDGMENT
TOLMAY
J
INTRODUCTION
[1]
The Road Accident Fund (“the RAF”) is funded by the Road
Accident Fund
levies (“RAF levies”), which is levied in
terms of the Customs and Excise Act, 1964 (“the CEA”) on
diesel
purchases. Taxpayers may claim “diesel refunds” if
they comply with the requirements of the CEA. This entails that a
taxpayer is refunded the RAF levy and the fuel levy.
[2]
The dispute between the RAF and the South African Revenue Service
(“SARS”)
is about “diesel refunds” claimed by
Eskom, in terms of the CEA. SARS has the authority to decide whether
diesel refunds
(which include the RAF levies) claimed by taxpayers,
such as Eskom, should be paid to taxpayers. SARS decided that Eskom
is not
entitled to the diesel refunds for a period of approximately
30 months (2019 to 2021). A dispute arose between SARS and Eskom.
SARS and Eskom then entered into a settlement agreement in terms of
which SARS contends it is obliged to pay Eskom an amount of
approximately R5.1 billion (five point one billion rand).
[3]
SARS and Eskom entered into a settlement agreement on 17 October
2024. SARS informed
the RAF about this settlement agreement on 12
November 2024. SARS informed the RAF that it will recoup/deduct the
R5.1 billion
from the RAF levies over a 2-month period. This period
was then extended to five months.
[4]
On 14 March 2025, Eskom filed an application to intervene, this
application was not
opposed by any of the parties and was granted.
URGENCY
[5]
The matter was set down for 24 February 2025, but on that day the
parties agreed that
the matter should proceed for facilitation in
terms of the Inter-Governmental Relationship Framework Act, 13 of
2005 (“IRF
Act”). During December of 2024, the RAF
declared a dispute in terms of the IRF Act. This was acknowledged in
SARS’
email of 31 January 2025. The matter stood down until 28
February 2025 for purposes of facilitation before retired Justices
Ngcobo
and Nugent. The process started on 28 February 2025.I was
requested to avail myself to hear the application on 14 March 2025 if
the dispute was not resolved.
[6]
On 14 March 2025 Eskom filed the application for intervention and the
affidavit and
the settlement concluded between Eskom and SARS
attached thereto impacted the approach of the parties significantly.
The RAF and
Eskom agreed to a time restricted interim interdict, but
SARS was not amenable to the proposal.
[7]
It also transpired that despite the declaration of the dispute, the
ongoing dispute
resolution process in terms of the IRF Act, SARS has
recouped/deducted the first tranche of approximately R1.2 billion
(one point
two billion rand). The RAF became aware of this on 26
February 2025. To add insult to injury, I was informed by counsel
representing
SARS that the certificate to Treasury regarding the
second tranche will be issued on the same day that I was hearing the
matter.
This led to me granting an interim order pending the judgment
which I undertook to deliver on or before 28 March 2025. The attitude
of SARS, which I find rather difficult to comprehend, created even
more reason to hear this matter on an urgent basis.
[8]
SARS submitted that it had no choice but to proceed
deducting/recouping the money
because if it did not, Treasury’s
records will not be accurate. It must be noted that the Minister of
Finance is the second
respondent in this application but chose not to
partake in these proceedings. At this stage, I was informed that
neither Treasury
nor the Minister of Finance have joined the
proceedings in terms of the IRF Act.
[9]
The RAF says that if the application for the interim relief is not
granted on an urgent
basis, the RAF will not receive adequate redress
in the normal course. The intended deductions will render the RAF
unable to perform
its core statutory duty. The operations of the RAF
nationwide will also be severely prejudiced. The intended deductions
of R5,1
billion constitute approximately 10% of the RAF’s
annual income. The RAF says that the intended deductions will render
the
RAF unable to perform its core statutory duty. The operations of
the RAF nationwide will also be severely prejudiced. The intended
deductions of R5,1 billion (five point one billion rand) constitute
approximately 10% of the RAF’s annual income.
[10]
SARS says that the application is not urgent and that the RAF failed
to take the necessary steps
since 12 November 2024 to protect its
interests, if any urgency exists, it is self-created. SARS, however,
does not elaborate on
which steps the RAF were supposed to take.
[11]
The chronology of events leading up to the launching of the
application is important. On 13 January
2025, SARS acknowledged the
declaration of a dispute under the IRF Act. On 31 January 2025, a
meeting was held between the RAF
and SARS. On 3 February 2025 the RAF
sent an email to SARS proposing the names of three retired judges to
act as facilitator in
terms of the IRF Act. On 7 February 2025, the
RAF requested a response to the email. On the same day the RAF
requested an undertaking
from SARS that it would not proceed with the
intended deductions until the dispute declared in terms of the IRF
Act has been finalised.
On 10 February 2025, the RAF delivered a
notice in terms of s 96 of the IRF Act, because of SARS’
failure to respond to the
request to give the aforementioned
undertaking. The undertaking was not given and RAF filed the urgent
application.
[12]
The matter is urgent not only based on the reasons initially provided
by the RAF, but also due
to SARS’ conduct by
deducting/recouping the first tranche and insisting that it will
proceed doing so despite the pending
processes before court and the
ongoing processes in terms of the IRF Act.
THE
ARGUMENTS
[13]
In the initial affidavit filed by the RAF the position was taken that
it should have been part
of the settlement negotiations between SARS
and Eskom. In the supplementary affidavit and heads of argument filed
on 10 March 2025,
the RAF correctly disavowed that proposition. No
such right exists, but SARS could have and should have informed the
RAF well in
advance of the potential financial consequences,
especially seeing that the papers revealed that the dispute between
SARS and Eskom
is for the period between 2019 up to 2021.
[14]
When Eskom’s application for intervention was filed, the
settlement agreement between Eskom
and SARS was attached. This
changed the whole approach by the RAF. Counsel representing SARS was
highly critical of the new arguments
raised on behalf of the RAF and
insisted that the RAF should stand or fall based on what was raised
in the founding papers. However,
the RAF was unaware of the facts
until Eskom filed their papers. It needs mentioning that SARS on the
other hand was aware of these
facts and in my view was duty-bound to
reveal it to both the Court and the Justices involved in the
facilitation process but inexplicably
failed to do so, despite the
fact that SARS was empowered by the settlement agreement to disclose
it to the RAF.
[15]
In this context the settlement agreement makes for interesting
reading.
Clause
1.1.17 defines “’settle’ and ‘settlement’
as the meaning referred to in section 77J of the
CEA”. Section
77J of the CEA states:
“
For the purposes
of this part ‘settle’ means to resolve a dispute by
compromising any disputed liability, otherwise
than by way of either
the Commissioner or the person concerned accepting the other party’s
interpretation of the facts or
the law applicable to the facts, or of
both the facts and the law, and ‘settlement’ shall be
construed accordingly”
[16]
Clauses 2.1 to 2.4 of the settlement agreement sets out the issues in
dispute between the parties
and the processes followed to try and
resolve the issues in dispute which remained unresolved.
[17]
Clause 4.3 states:
“
The parties
agree to settle the dispute on the following basis:
ESKOM shall be paid a
final amount of 80% of the amount of the refund of levies claimed by
ESKOM in respect of all the periods from
February 2019 to the latest
period in which a diesel refund claim has been filed as at the
effective date of the agreement.”
[18]
Clause 4.4.1 states:
“
SARS and ESKOM
have performed a reconciliation of the amounts ESKOM has claimed and
SARS has refunded.”
[19]
Clause 5.5 of the settlement agreement states:
“
The Settlement
does not in any way constitute an admission by any Party as to the
true nature or the proper interpretation of any of the issues
or
applicable legal principles
and may not be used by the Parties in
relation to any other matter or transaction other than the Settlement
of this Dispute”
(own underlining).
[20]
Paragraph 6.3 states:
“
The Commissioner
undertakes to adhere to the secrecy provision contained in the CEA
with regard to information relating to the persons
concerned but
ESKOM acknowledges that information concerning this Settlement may be
required to be disclosed to inter alia National
Treasury and/or the
Road Accident Fund and consents to such reasonable disclosure in
terms of section 4(3D) (b)of the CEA
” (own underlining).
[21]
It was argued on behalf of the RAF that from the provisions of
section 77J and the settlement
agreement, it is apparent that SARS
and Eskom are not admitting either party’s interpretation of
the law or the facts, or
both. The nature of the settlement agreement
between SARS and Eskom is one that is concluded “because the
rights of the parties
are uncertain, and they choose not to resolve
that uncertainty”, as stated in
Wilson
Bayly Holmes (Pty) Ltd v Maeyane and Others
[1]
.
[22]
It was held in
Wilson
Bayly Holmes
that “
By
the very nature of such a contract, there can be little room for
finding that the parties must have intended their contract to
depend
upon the existence of one or other of the factors relevant to their
respective rights.
[2]
”
[23]
The above principles were confirmed by the Constitutional Court in
inter alia
Mafisa v RAF
where the Constitutional Court held:
“
[33]
A
compromise is an agreement between the parties to prevent or
terminate a dispute by adjudicating their differences by mutual
consent. It is trite that the comprise gives rise to new
contractual rights and obligations which exist independently of the
original cause of action. Once a compromise is reached, the
parties are precluded from proceeding on the original cause of
action
(unless, of course, the compromise provides otherwise)
[3]
.”
[24]
In paragraph [42] of the
Mafisa
judgment, the Court held:
“…
In
its judgment the Supreme Court of Appeal reiterated the principles
outlined in Eke and confirmed that a compromise extinguishes
disputed
rights and obligations, puts an end to the litigation and has the
effect of res judicata
.
[4]
”
[25]
It was argued on behalf of the RAF that the original cause of action
of Eskom was to claim diesel
refunds in terms of the CEA. This
original cause of action has been extinguished by the compromise
agreement as stated in paragraph
[42] of the
Mafisa
judgment.
[26]
It was argued that in these circumstances SARS cannot contend that it
entered into the settlement
agreement because it had a liability to
refund Eskom the RAF levies. The settlement agreement was
entered into to avoid having
the issue being resolved by a Court of
law. Furthermore, the settlement agreement gives rise to new
contractual rights and obligations
and the parties are precluded from
proceeding on the original cause of action. The original cause of
action of Eskom was to claim
diesel refunds in terms of the CEA This
original cause of action has been extinguished by the compromise
agreement as stated in
paragraph [42] of the Mafisa judgment.
[27]
SARS, so says the RAF, is therefore not entitled to deduct the
settlement amount from the RAF
levies, as the settlement amount does
not constitute a diesel refund of the RAF levies as envisaged in the
CEA. Consequently, SARS’s
decision to deduct/recoup the amount
it undertook to pay Eskom in terms of the settlement agreement,
cannot be in terms of the
provisions of the CEA as the settlement
agreement extinguished the original cause of action.
[28]
It was argued on behalf of the RAF that the dispute between the RAF
and SARS about the deduction/recoupment
of the amount of R5.1 billion
does not affect Eskom’s right to receive payment in terms of
the settlement agreement.
The settlement agreement between
Eskom and the RAF created new rights and obligations which are
totally independent from the previous
cause of action (the claim in
terms of the CEA), which was extinguished by the settlement
agreement.
[29]
The RAF was also, and rightly so, aggrieved by the non-disclosure of
the taxpayer and the content
of the settlement agreement. SARS
refused to provide the agreement to the RAF and contended that the
secrecy provision applies
to the settlement agreement and that SARS
is not entitled to disclose it to the RAF. This is directly contrary
to clause 6.3 that
makes specific provision therefore that the
contents of the settlement agreement may be disclosed to the RAF.
[30]
This conduct by SARS must have had an effect on the dispute
resolution process followed in terms
of the IRF Act, as the
settlement agreement could not be made available to the parties
during that process. The fact that
the settlement agreement is
now available to all the parties, will in the applicant’s view
make a significant difference
in the continuing negotiations to
follow in terms of the dispute resolution process under the IRF Act.
REQUIREMENTS
FOR AN INTERIM INTERDICT
[31]
The requirements for an interim interdict are trite, they are the
existence of a prima facie
right, a reasonable apprehension of
irreparable harm, that the balance of convenience favours the
applicant and the absence of
an appropriate alternative remedy.
[32]
The presence of a prima facie right was hotly contested by SARS.
Eskom initially also had reservations
about it, based on the fact
that the inter-governmental dispute would remain pending for an
indefinite period of time, or until
a prescribed result or final
resolution has been reached. Considering the time-restricted interim
order agreed on between the RAF
and Eskom, the objection by Eskom
fell away and during argument Eskom supported the existence of a
prima facie right as formulated
in the proposed order.
[33]
SARS strongly objected to the RAF’s developed argument because
of the new facts that belatedly
became known and insisted that the
RAF must stand or fall by the facts set out in the founding
affidavit. Ironically, SARS was
fully aware of the true
circumstances, and despite being empowered to reveal it to the RAF,
chose not to do so. The facilitators
in terms of the IRF Act was
apparently also kept in the dark and so was the Court until 14 March
2025, the day of the hearing.
It will be to put form over substance
and would be manifestly unjust not to allow the RAF to rely on these
new facts.
[34]
This is an application for an interim interdict. In
Webster
v Mitchell
[5]
it was held that:
“
The
right to be set up by an applicant for a temporary interdict need not
be shown by a balance of probabilities. If it is ''prima
facie
established though open to some doubt'' that is enough
.
[6]
”
[35]
In
Gool
v Minister of Justice
[7]
some qualification was seemingly applied to the principle set out in
Webster
when the following statement was made:
“
With
the greatest respect, I am of the opinion that the criterion
prescribed in this statement for the first branch of the enquiry
thus
far outlined is somewhat too favourably expressed towards the
applicant for an interdict. In my view the criterion on the
applicant's own averred or admitted facts is: should (not could) the
applicant on those facts obtain final relief at the trial.
Subject to
that qualification, I respectfully agree that the approach outlined
in Webster v Mitchell . . . is the correct approach
for ordinary
interdict applications
.
[8]
”
[36]
In
Zulu
v Minister of Defence and Others
[9]
the Court however quoted
Tony
Rahme Marketing Agencies
[10]
with approval as it held as follows:
“
The correct
test was, however, correctly and hopefully now finally expressed even
more correctly by Goldstein J in Tony Rahme Marketing
Agencies SA
(Pty) Ltd and Another v Greater Johannesburg Transitional
Metropolitan Council
1997 (4) SA 213
(W) D at 215C - 216C, where he
writes:
'The
applicants seek two interim interdicts pending the determination of
review proceedings they intend instituting against the
respondent. No
answering affidavit has been filed, the respondent arguing that the
application ought to be dismissed for reasons
of fact and law. Before
I address the issues I have to decide, it is necessary to refer to
the difference of approach in our case
law regarding the test I have
to apply to disputes of law. Of course, the principles to be applied
to disputes regarding interim
interdicts have long ago been
authoritatively laid down in such cases as Webster v Mitchell
1948
(1) SA 1186
(W); Ndauti v Kgami and Others
1948 (3) SA 27
(W) at 36 -
7 and Olympic Passenger Service (Pty) Ltd v Ramlagan
1957 (2) SA 382
(D). Are such principles to apply only in respect of factual and not
in respect of legal disputes? In Mariam v Minister of Interior
and
Another
1959 (1) SA 213
(T) Roper JA (as he then was) simply applied
Webster to a matter involving disputed legal issues. Viljoen J (as he
then was) criticised
this approach in Fourie v Olivier en 'n Ander
1971 (3) SA 274
(T). The decision in Webster was intended, he said at
285, to apply to factual disputes and not legal ones. In the case of
the
former a final decision would be premature but not in the
case of the latter. In such a case the court was obliged to give
a
decision and conclude the matter finally. Viljoen J went to say the
following at 285F - :
''Die
Regter wat 'n aansoek om 'n interdik pedente lite verhoor wat
afgemaak kan word deur 'n regsbeslissing is myns insiens nie
geregtig
om te sê dat hy die regsvraag halfhartig gaan benader en dit
aan sy ampsbroer wat die verhoor waarneem gaan oorlaat
H om die
saak behoorlik te oorweeg en finaal te beslis nie. Dit sou strydig
wees met die beginsels in ons reg ten aansien van res
juidicata, dit
sou onnodige koste veroorsaak en dit sou die onsuksesvolle party in
die pedente lite-aansoek die reg van appèl
ontsê terwyl
die uitleg van die Regter op daardie stadium aan die regsvraag heg,
hoewel dit miskien nie bedoel is om die
Verhoorregter te bind nie,
hom in 'n groot verleentheid kan stel as hy voel dat hy met die
eersgenoemde Regter wil verskil. In
die hiëragie I van Howe
staan die Verhoorhof nie hoër as die Kamerhof waar die aansoek
van die interdik aanhangig gemaak
word nie. Dit is albei
een-Regter-Howe wat oor dieselfde aangeleentheid moet beslis.''
With
respect I differ from the learned Judge. Whilst there may be
situations where a Court having to decide an interim interdict,
has
sufficient time and assistance to arrive at a final view on a
disputed legal point - in which event it probably has to express
a
strong view in order to save costs - situations of urgency arise when
decisions on legal issues have to be made without the judicial
officer concerned having had the time to arrive at a final considered
view. In such a situation he is surely forced to express
only a prima
facie view. I cannot see how the expression of such a view and the
grant of interim relief would conflict with principles
of res
judicata. I also see no embarrassment in an urgent Court Judge being
overridden by a trial Judge. Each of us, privileged
to hold this high
and responsible office, owe, in the wielding of our considerable
power, a duty only to truth and justice. The
interlocutory decisions
of Colleagues, and indeed of our own, are not binding at later stages
of proceedings and should, and I
trust, do yield easily to persuasive
arguments indicating error or oversight.
[11]
”
[37]
SARS insisted that I was duty bound to not only determine the matter
based on the case made out
in the founding affidavit, but also to
make a final determination on the rights of SARS and the obligations
of the RAF in relation
to the recoupment/deduction of the levies in
terms of the CEA. This is not what the law requires.
[38]
I agree with the approach set out in
Zulu
above. This matter
and how it was conducted illustrates in what an unenviable and
difficult situation Judges often are in the urgent
court. There is
simply no way that this Court can arrive at a final view on what
exactly the parties’ rights are. SARS insisted
that I should do
just that. The best a court can do in these circumstances is to
express a prima facie view.
[39]
This matter was enrolled for 14 March 2025 as set out above on the
insistence of the parties.
Eskom filed their heads of argument late
in the afternoon of 13 March 2025 and the application for
intervention on 14 March 2025.
SARS filed further heads of argument
during the evening of 13 March 2025 and in response to this
application the RAF filed a third
set of heads of argument on 14
March 2025. This judgment must be delivered as quickly as possible.
The situation here is exactly
what was envisaged in
Tony Ramhe
Agencies
. The court is duty bound to act within the constraints
of the urgent court and is ill-equipped to come to any final
decision.
[40]
This matter does not only involve the interpretation of complex legal
issues but also will have
far reaching consequences not only for the
RAF, but more importantly for motor vehicle accident victims. In my
view this Court
is obliged, especially in circumstances where it is
only called upon to grant an interim interdict, to express only a
prima facie
view and on this basis, I am persuaded that the RAF
established the existence of such a right.
[41]
As far as the argument is that the RAF is limited to what was stated
in the founding affidavit
there simply is no merit in that argument.
SARS withheld crucial information from the RAF and the Court, and it
would make a mockery
of justice and fair play to uphold this
argument.
[42]
As far as the requirements of balance of convenience and irreparable
harm is concerned, the RAF’s
precarious financial position is
undeniable. The consequences thereof are illustrated in several
matters before our courts where
the courts have granted inter alia
moratoriums on writs of execution and warrants of attachments against
the RAF
[12]
. SARS submitted
that these moratoriums would assist the RAF and, if I understand the
argument correctly, will alleviate the financial
position of the RAF.
This argument does not consider the history and the financial
position that the RAF is in and which is public
knowledge. The
reduction/recoupment of R1,2 billion (one point two billion rand) per
month for the next remaining four months may
indeed lead to the
financial collapse of the RAF. SARS on the other hand will not suffer
any irreparable harm, as the amounts may
still be recouped/deducted
when the matter is resolved or the time limit set by this Court comes
to an end. If that happens, the
RAF will have to approach the courts
again for assistance as provided for in the order.
[43]
As far as an alternative remedy is concerned, SARS says that the RAF
should rather have approached
Treasury for assistance. The RAF says
that the process will take too long and will not prevent the
immediate problems that the
RAF faces. In any event, it was pointed
out that the RAF did declare a dispute in terms of s 96 and therefore
exhausted any other
available remedy. S 96 of the CEA provides as
follows:
(
1)(a) No
legal proceedings shall be instituted against the State, the
Minister, the Commissioner or an officer for anything
done in
pursuance of this Act until one month after delivery of a notice in
writing setting forth clearly and explicitly the cause
of action, the
name and place of abode of the person who is to institute such
proceedings this section referred to as (in “litigant”)
and the name and address of his attorney or agent, if any.
(ii)
such notice shall be in such form and shall be delivered in such a
manner and at
such places as may be prescribed by rule.
(iii)
no such notice shall be valid unless it complies with the
requirements prescribed in this section
and such rules
(b)
Subject to the provisions…’
[44]
SARS complained that the notice is defective and the notice should be
disregarded on that basis.
In
Mohlomi
[13]
the purpose for notification was explained and the following was said
in relation to prior notice to state organs:
“
The
conventional explanation for demanding prior notification of any
intention to sue an organ of government is that, with its extensive
activities and large staff which tends to shift, it needs the
opportunity to investigate claims laid against it to consider them
responsibly and to decide, before getting embroiled in litigation at
public expense, whether it ought to accept, reject or endeavour
to
settle them
.
[14]
”
[45]
In
Dragon
Freight
[15]
the
Court held:
“
The Supreme
Court of Appeal has been critical of the state and organs of state
raising technical hurdles instead of facilitating
the expeditious
finalisation of cases. In Safcor Forwarding (Pty) Ltd v NTC 1982 930
SA (A) at 672H to 673A (judgment of Corbett
JA as he then was) the
Court relying on the judgment of Shreiner JA in Trans – African
Insurance Co. Ltd v Maluleka
1956 (2) SA 273
at 278 F –G held
as follows:
“
there is no
indication that the Commissioner was in anyway prejudiced by the
alleged non-joinder of its Chairman. In the circumstances
it is to
me, a matter of some surprise that a public body like the Commission
should raise such a technical procedural hurdle to
the expeditious
despatch of what appears to have been an urgent review application.”
Although
the Court found that the appellant should have cited the Chairman,
the point was dismissed, for “technical objections
to less than
perfect procedural steps should not be permitted, in the absence of
prejudice, to interfere with the expeditious and,
if possible,
inexpensive decision of cases on their real merits
.
[16]
”
[46]
In the context of this matter, the same should apply and SARS should
not be allowed to rely on
a technical hurdle. SARS was at all times
aware of the RAF’s dispute and it did not suffer any prejudice
as a result of any
deficiency in the notice. The RAF met all the
requirements for an interim interdict as set out above.
DEVELOPMENTS
AFTER THE JUDGMENT WAS RESERVED.
[47]
On 24 March 2025, my Registrar informed me that SARS emailed an
application to file a further
supplementary affidavit. They were
informed that this will not be allowed. On the same day, a letter by
the RAF was emailed to
my Registrar by the attorneys of the RAF. I
then perused the affidavit and the letter. The essence of SARS’
affidavit is
that the facilitation process has been terminated and my
order will be rendered moot as a result. New factual issues were also
raised. The letter filed on behalf of the RAF indicated that the RAF
does not agree that the facilitation process should be terminated.
The goal posts in this matter is constantly being shifted. I have
heard the matter and I make an order based on what was argued
before
me. On 25 March 2025 Eskom withdrew from the application. I granted
the intervention application during the hearing, but
considering the
withdrawal, I’ve removed that from my order as well as any
reference to the status of the settlement between
SARS and Eskom.
The
following order is made:
1.
Condonation is granted to the applicant for its non-compliance
of the
Rules of Court relating to forms and service and the matter is
enrolled and heard as one of urgency in terms of Rule 6(12).
2.
The statutory one month notice period provided for in section
96(1)
(c) (ii) of the CEA is reduced to 13 February 2025.
3.
An interim interdict is granted against the first respondent
in the
following terms:
3.1 The first
respondent is interdicted and prohibited from deducting the amount of
R5.1 billion or any part thereof
which the first respondent is
obliged to pay to the third respondent (Eskom) in terms of the
settlement agreement between Eskom
and SARS of 18 October 2024, from
the monthly Road Accident Fund levies collected by it.
3.1.
SARS will still be entitled to make such statutory monthly deductions
as provided for in
section 5(2)
of the
Road Accident Fund Act, 56 of
1996
read with section 75(1) of the Customs and Excise Act, 91 of
1964, which are not related to the R5.1 billion which is in dispute.
4.
The interim interdict set out in paragraph 4 hereof will remain
operative until such time as the dispute that was declared between
the applicant and the first respondent in terms of
section 41
of the
Intergovernmental Relations Framework Act, 13 of 2005
, has been
resolved or the process has been terminated.
5.
The process to be followed in terms of the
Intergovernmental
Relations Framework Act, referred
to above, must be finalised within
45 business days from the date of this judgment.
6.
If the dispute is not resolved between the applicant and the
first
respondent within the 45-business day period referred to above, or
the process is terminated, then the applicant will be
entitled to
institute proceedings against SARS to prohibit it from
deducting/recouping the R5.1 billion from the applicant, along
with
any other legal proceedings to recover from SARS any
deductions/recoupments already made.
7.
The First Respondent is ordered to pay the costs of the Applicant,
including costs of two counsel on scale C.
R
TOLMAY
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION, PRETORIA
Appearances
Counsel
for applicant: Adv C Louw SC and Adv AJ Wessels instructed by
Mpoyana Ledwaba Inc.
Counsel
for first respondents: Adv J Peter SC and Adv B Ramela instructed by
VDT Attorneys.
Counsel
for Intervening party: Adv AP Joubert SC and Adv LJ Du Bruyn
instructed by Edward Nathan Sonnenbergs.
Date
heard: 14 March 2025
Date
of Judgment: 26 March 2025
[1]
1995 (4) SA 340
(T) at 345E.
[2]
Ibid.
[3]
2024 (4) SA 426
(CC) at paras [33].
[4]
Ibid at para 42. See also Road Accident Fund v Ngobane
2008 (1) SA
432
(SCA) at para [12] and Eke v Parsons
2016 (3) SA 37
(CC).
[5]
1948(1) SA 1186 (W).
[6]
Ibid at 1189.
[7]
1955 (2) SA 6829(C).
[8]
Ibid at 668E.
[9]
2005(6) SA 446 (T).
[10]
Tony Rahme Marketing Agencies SA Pty Ltd and Another v Greater
Johannesburg Transitional Metropolitan Council
1997 (4) SA 213(W).
[11]
Supra note 9 at para 41.
[12]
The latest of these is The Road Accident Fund v The Legal Practice
Council and Others (21 February 2025) Caseno.134420 (Gauteng
Division, Pretoria).
[13]
Mohlomi v Minister of Defence
1997(1) SA 124 (CC).
[14]
Ibid at para 9.
[15]
Dragon Freight (Pty) Ltd and Others v CSARS and Others [2021] 1 ALL
SA 553(GP).
[16]
Ibid at para 64.
sino noindex
make_database footer start