Case Law[2025] ZAGPPHC 438South Africa
IPC Plumbing SA (Pty) Ltd v Azraprty (Pty) Ltd (079559/2023) [2025] ZAGPPHC 438 (9 May 2025)
Headnotes
if an amendment rectifies the defects complained of the exception falls away.[8] The reason being that once a pleading is amended the original pleading falls away, and any exception to the original pleading becomes moot.[9]
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 438
|
Noteup
|
LawCite
sino index
## IPC Plumbing SA (Pty) Ltd v Azraprty (Pty) Ltd (079559/2023) [2025] ZAGPPHC 438 (9 May 2025)
IPC Plumbing SA (Pty) Ltd v Azraprty (Pty) Ltd (079559/2023) [2025] ZAGPPHC 438 (9 May 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_438.html
sino date 9 May 2025
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
Case
Number: 079559/2023
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
9 May 2025
In
the matter between:
IPC
PLUMBING SA (PTY)
LTD
Plaintiff
and
AZRAPART
(PTY)
LTD
First Defendant
MOTA-ENGIL
CONSTRUCTION (PTY) LTD
Second Defendant
FOURWAYS
PRECINCT (PTY) LTD
Third Defendant
JUDGMENT
DOMINGO, AJ
Introduction
[1]
This is an application brought by the
plaintiff under Uniform Court Rule 28(4) for leave to amend its
particulars of claim after
the first defendant noted an exception to
the formulation of the plaintiff’s claim.
[2]
The first defendant has objected to the
plaintiff’s proposed amendment and opposes this application for
leave to amend on
the stated grounds that the proposed amendment does
not address the grounds of exception it raised, asserting that even
after amendments,
the particulars of claim would remain excipiable on
the same grounds.
Background
[3]
Having read the particulars of claim
(amended and unamended version), the plaintiff seeks to be paid an
amount of R13 970 320.85
in respect of what it terms as contractual
damages for the alleged breach of a subcontract agreement. In the
alternative the plaintiff
seeks the debatement of an account and
order that the first defendant pay the amount found to be due to the
plaintiff. This alternative
relief is premised on an oral agreement
entered into in September 2021, where it is submitted by the
plaintiff that the first defendant
would pay the plaintiff the amount
found to be due to it consequent upon the debatement process.
[4]
The plaintiff refers to itself as the “the
sub-contractor”, to the second defendant as “the
contractor”
and to the first defendant as “the employer.”
[5]
On the 23 June 2022 the plaintiff
instituted action under case number 33677/2022 against the second and
third defendant for the
same relief that it now seeks in the present
matter. One of the defences raised in the action under case number
33677/2022 is that
the second defendant in that action, which is the
third defendant in this action, ceded and assigned its rights and
obligation
under the contract relied on by the plaintiff to the first
defendant in this action. Instead of applying to join the first
defendant
in the action to the proceedings under case number
33677/2022, the plaintiff issued a new summons wherein it cites all
three defendants
and set out the same cause of action but its claim
against the first defendant is conditional on the success of the plea
of misjoinder
under case number 33677/2022.
[6]
The plaintiff in this case, submitted in
its particular of claims that any reference to the third defendant
“FP” and/or
the “the Employer” should be read
as referring to the first defendant (Azrapart) as if specifically
pleaded by way
of reference.
Issues
[7]
The issue to be determined in this matter
is whether the plaintiff’s particulars of claim disclose a
cause of action against
the first defendant, whether in their
unamended or amended form. In other words, in determining the two
matters before the court,
i.e the Rule 28(4) application for leave to
amend and the first defendant’s exception, the issue to be
determined is whether
the plaintiff’s particulars of claim
would remain excipiable after the intended amendments was effected,
if allowed.
Grounds of exception
raised
[8]
The first defendant noted an exception to
the plaintiff’s particulars of claim on three grounds, namely:
8.1
that there is no contractual nexus between the plaintiff and the
first defendant;
8.2
that Mr Swanepoel had no authority to conclude agreements on behalf
on the first defendant. There
is no allegation that Mr Swanepoel was
authorised to represent the first defendant and there is no
allegation that linked Mr Swanepoel
to the principal agent of the
first defendant;
8.3
that a non-variation clause in the subcontract results in any oral
agreement concluded between
the plaintiff and the first defendant
being null and void.
Legal framework
[9]
The
primary object of allowing an amendment is to obtain proper
ventilation of the disputes between the parties and to determine
the
real issues between them so that justice may be done.
[1]
Whether to grant or refuse leave to amend, is a matter that falls in
the court’s discretion, which is to be exercised judicially.
[2]
[10]
An
amendment should generally not be permitted if its introduction would
render the pleading excipiable.
[3]
In other words, the issue proposed to be introduced by the amendment
must be a triable issue.
[4]
[11]
Counsel
on behalf of the plaintiff has directed the court to the case of
R
M van de Ghinste & Co (Pty) Ltd v Van de Ghinste
[5]
where
the court explained that where an objection is raised to a proposed
amendment of a pleading on the ground that the pleading
would be
excipiable after amendment, the proper approach is not to consider
whether the pleading might be excipiable, or excipiability
is
arguable, but instead decide whether the amended pleading would be
excipiable. The court must thus decide the issue of excipiability.
[12]
This
view was based on the judgment in
Crawford-Brunt
v Kavnat and Another
[6]
where
the court states:
“
If
the pleading would appear to be possibly open to exception or even if
the Court is of the opinion that the question of whether
or not the
pleading is excipiable is arguable, it would seem to be the more
correct course to allow the amendment.
This approach is also, in
my view, consistent with the general principle that amendments should
normally be allowed unless the application
to amend is
mala fide
,
or unless such amendment would cause an injustice to the other side
which cannot be compensated by costs.”
[13]
Later,
in
YB
v SB and Others NNO
[7]
the
court formulated the test applicable to such circumstances as
follows:
“
It
is accepted law that a court will not allow amendments where their
effect would render such a pleading excipiable or where it
does not
cure an excipiable pleading.
The court must accept as
correct the allegations contained in the particulars of claim,
incorporating the proposed amendment, and
determine whether those
allegation are capable of supporting a cause of action in respect of
the assets of the Ruby Trust (
Stewart and Another v Botha and
Another
[2008] ZASCA 84
;
2008 (6) SA 310
(SCA) para 4).
The defect in the
pleading must appear
ex facie
the pleading and no extraneous
facts may be adduced to show that the pleading is excipiable
(Barbara
v Barnard
2000 (3) SA 741
(C) para 10).
It is for the excipient
(ie the trustees) to satisfy the court that the conclusion of law
pleaded by the plaintiff cannot be supported
by any reasonable
interpretation of the particulars of claim.”
[14]
The test on exception is whether, on all
possible readings of the facts, no cause of action may be made out.
It is for the excipient,
that is the first defendant in this matter
to satisfy the court that the conclusion of law for which the
plaintiff contends cannot
be supported on every interpretation that
can be put upon the facts.
[15]
Our
courts have consistently held that if an amendment rectifies the
defects complained of the exception falls away.
[8]
The reason being that once a pleading is amended the original
pleading falls away, and any exception to the original pleading
becomes moot.
[9]
Contractual Nexus
[16]
It is contended by the plaintiff that the
first defendant breached its obligations under an oral agreement (9
September 2021) between
the plaintiff and the first defendant. On
this basis the plaintiff submitted that it claims firstly, payment of
the damages that
flows from this breach, alternatively specific
performance in the form of a statement and debatement of the account.
[17]
The plaintiff submitted that under the oral
agreement, the parties agreed that:
17.1
the Principal Agent (who represent the employer in the Principal
Building Agreement) previously incorrectly
certified payments due to
the plaintiff under the subcontract;
17.2
the first defendant, through it appointed agent, would debate the
plaintiff’s account dated 17 April
2020; and
17.3
following the debatement, the first defendant would pay the plaintiff
what the contractor (second defendant)
owed the plaintiff under the
subcontract, notwithstanding the first defendant not being a party to
the subcontract.
[18]
The plaintiff submitted that the first
defendant’s agent did not debate the plaintiff’s account
of 17 April 2020 nor
did the first defendant pay the plaintiff what
is due under the subcontract as undertaken.
[19]
It is averred by the plaintiff that the
contractual nexus that the plaintiff relies on is the nexus created
by the oral agreement;
not those emanating from either the Principal
Building Agreement or the subcontract. Thus, the plaintiff submitted
that its cause
of action (after amendment) is founded on the first
defendant’s breach of the oral agreement concluded between the
plaintiff
and the first defendant on 9 September 2021.
[20]
It is contended by the plaintiff that by
accepting the allegations pleaded in the particulars of claim as
true, the first defendant’s
contention that no privity of
contract exists between the plaintiff and the first defendant is
misguided and the first ground of
exception must therefore fail.
[21]
The first defendant contends that the
plaintiff’s main cause of action is encapsulated in paragraph
43 of the plaintiff’s
particulars of claim, which sets out that
the plaintiff is to be paid the amount of R13 970 320.85 as damages
arising from the
alleged breach of contract of a subcontract
agreement.
[22]
It is submitted by the first defendant that
the subcontract is identified and defined in paragraph 15.2 of the
plaintiff’s
particulars of claim as an agreement in writing
concluded between the plaintiff and the second defendant. The
agreement filed on
record by the plaintiff contains the letter in
terms of which the plaintiff was appointed, as well as the express
terms of the
the subcontract. The first defendant is not identified
or referred to as a party to the subcontract agreement.
[23]
In regard to the above, the defendant’s
counsel has succinctly summarised the pertinent aspects of the
subcontract as follows:
23.1
The letter of appointment was issued and signed by the second
defendant.
23.2
The cover page of the subcontract agreement identifies the second
defendant as “the Contractor”
and the plaintiff as “the
Sub-Contractor.”
23.3
The entity referred to as “the Employer” is identified in
clause 1.1 as “the party contracting
with the contractor.”
23.4
Clause 15.8 of the subcontract states that “there shall be no
privity of contract between the employer
and a subcontractor
appointed by the contractor.”
23.5
Clause 25.7 (as amended) obliges the second defendant, and not the
first defendant, to pay the plaintiff.
[24]
It is submitted by the first defendant that
the facts alleged by the plaintiff establishes that two contracts
exist between the
parties. The main contract was concluded between
the first defendant, as the employer, and the second defendant, as
the contractor.
The subcontract agreement was concluded between the
second defendant, as the contractor, and the plaintiff as the
sub-contractor.
[25]
It is therefore averred by the first
defendant that the plaintiff is not party to the main contract, and
the first defendant is
not a party to the subcontract agreement.
Given that the first defendant was not a party to the subcontract
agreement it has no
rights in terms of that contract and, more
importantly, it had no obligations arising from the contract. It is
contended by the
first defendant that it follows that the first
defendant could not have breached a contract to which it was not a
party and in
respect of which it had no obligations that it could
have failed to perform. The alleged breaches set out in paragraph 33
of the
plaintiff’s particulars of claim are not supported by
the the express terms of the subcontract or the facts alleged by the
plaintiff.
[26]
In the premises, it is clear that the first
defendant’s exception on the first ground that there is no
contractual nexus between
the plaintiff and the defendant pertains to
the subcontract agreement (main claim) and is not aimed at the oral
agreement. The
plaintiff does not address the the first defendant’s
contention that no privity of contract exists between the plaintiff
and the first defendant, because the plaintiff relies on the
contractual nexus created by the oral agreement. The plaintiff does
not deal with the contractual nexus set out in paragraph 43 of its
particular of claims, where I am in agreement with the first
defendant’s counsel, the main cause of action is encapsulated
which is the claim for damages arising from the alleged breach
of a
subcontract agreement.
[27]
The particulars of claim, in its amended
and unamended form does not remedy the first defendant’s
exception on the ground
that there is no contractual nexus in terms
of the cause of action for the main relief claimed by the plaintiff
as set out in paragraph
43 of the the plaintiff’s particulars
of claim. I therefore find that in this respect the particulars of
claim, accordingly,
fails to disclose a cause of actions against the
first defendant.
Lack of authority
[28]
The second ground of exception by the first
defendant contests Mr Swanepoel’s authority to bind the first
defendant in concluding
the oral agreement. It is also contended by
the first defendant that there is no allegation that Mr Swanepoel was
authorised to
represent the first defendant and there is no
allegation that linked Mr Swanepoel to the principal agent of the
first defendant.
[29]
The plaintiff in its amended particulars of
claim pleads the following regarding the first defendants second
ground of exception:
“
On
or about the 9 September 2021 and at or near Fourways the plaintiff,
there and then represented by Jason van Wyk and FP, there
and then
represented by Dawie Swanepoel (of the quantity surveyor of FP)
orally agreed that the dispute about the incorrect payment
certification would be resolved as follows (“the September 2021
agreement”):
41.1
The previous payment certifications by FP of what is the plaintiff in
terms of the sub-contract is incorrect;
41.2
The plaintiff and FP would debate the account dated 17 April 2020 of
the plaintiff; and
41.3
Upon conclusion of the debate account of the plaintiff, FP would make
payment to the plaintiff of what is
due to the plaintiff in terms of
the sub-contract.
44.B After
the dispatch of Annexure “POC7” and leading up to as well
as after the dispatch of Annexure “POC9”,
various virtual
meeting and meetings in person were held between the plaintiff, duly
represented, and
inter alia
the defendants, duly represented,
in order to resolve the dissatisfaction with the certification of the
plaintiff’s work
in terms of the subcontract as well as the
quantification of the value thereof
inter alia:
44.B.1 On 15 October 2020
at Boogertman & Partners at approximately 12h00, which meeting
was
inter alia
attended by Mr Nico Rivetti of the Project
Manager, Mr Dawie Swanepoel of the Quantity Surveyor, Messrs Jury
Wickham and Brent
Jachs of MECSA as well as Mr Opperman and Mr Janna
van Wyk of the plaintiff;
44.B.2 A meeting on 17
June 2021 attended by the aforementioned individuals in their
representative capacities.
44.B.3 In any one and or
all of the aforementioned meetings, the first, alternatively third
defendant, duly represented by an authorised
representative and/or
the principal agent, duly represented by Mr Nico Rivetti, duly
authorised the Quanitity Surveyor to enter
into negotiations with and
settle with the plaintiff, the dispute relating to the
dissatisfaction with the certification of the
plaintiff’s
subcontract works and the quantification thereof.
44.C.1 By virtue of the
authority granted by the first, alternatively, third defendant and/or
the principal agent to the Quantity
Surveyor, Mr Dawie Swanepoel was
duly authorised to enter into negotiations with the plaintiff as well
as the September 2021 agreement.
44.C.2 The Plaintiff is
not in possession of written authority granted by the first,
alternatively third defendant and/or principal
agent to the Quanity
Surveyor, which document, alternatively documents constituting such
authority, ought to be in possession of
the first, alternatively
third defendant and/or principal agent.”
[30]
It is contended by the plaintiff that by
accepting the factual statements above as true for the purpose of
deciding the exception,
the claim is properly pleaded. Whether or not
Mr Swanepoel had the authority to represent the first defendant is a
question of
fact to be determined at trial.
[31]
It is my finding that the amended
particulars of claim addresses the first defendant’s exception
in regard to the allegations
that it was not alleged that Mr
Swanepoel was authorised to represent the first defendant in the
plaintiff’s unamended particulars
of claims. In addition, the
plaintiff in the particulars of claims has also referenced the clause
6.1.1 of the subcontract agreement
and alleges that the “principal
agent has full authority and is obligated to act and bind the
employer” which deals
with the delegation of authority to act
on behalf of the employer. Furthermore, the full text of clause 6.1.1
reads as follows:
“
The
employer warrants that the principal agent has full authority and
obligation to act and bind the employer. The principal agent
has no
authority to amend the JBCC Principal Building Agreement or the JBCC
N/S Subcontract Agreement.
[32]
The first defendant submitted that
according to clause A5 of the contract data to the subcontract
agreement Mr Nico Rivetti of SIP
Project Managers is identified as
the principal agent.
[33]
The first defendant contends, in any event,
if it is assumed that Mr Swanepoel was the principal agent of the
Employer, clause 6.1.1
of the subcontract agreement clearly states
that the principal agent is not authorised to amend the terms of the
main contract
or the subcontract.
Non-variation clause
[34]
The plaintiff submitted that a term of the
September 2021 oral agreement was that the first defendant would pay
the plaintiff the
amount found due to it consequent upon the
debatement process.
[35]
The first defendant raises the exception
that clause 25.7 (as amended) of the subcontract agreement obliged
the second defendant,
and not the first defendant, to pay the
plaintiff, Consequently, the first defendant contended that the terms
of the September
2021 agreement purport to amend the terms of the
subcontract agreement in material respects, and even if Mr Swanepoel
was the principal
agent, which the first defendant has not conceded,
Mr Swanepoel did not have the authority to amend the terms of the
subcontract
agreement. The first defendant therefore submits that it
follows that the September 2021 agreement is not binding on the first
defendant nor is it enforceable against the first defendant. Thus, it
is contended by the first defendant that the oral agreement
amends
the terms of the subcontract agreement; and is therefore barred by
the non-variation clause rendering the oral agreement
null and void.
[36]
However, the plaintiff pleaded that the
parties to the oral agreement are the plaintiff and the first
defendant. The first defendant
is not a party to the subcontract and
the plaintiff is not a party to the Principal Building Agreement. On
this basis, the plaintiff
averred that there is no non-variation
clause agreed to between the plaintiff and the first defendant on the
pleadings. An oral
agreement between the plaintiff and the first
defendant is thus not barred by agreement between them and the third
ground of exception
must fail.
[37]
From the submission made by the plaintiff
they are pleading that the September 2021 oral agreement is a new
contract and that there
is no prohibition that precludes the
employer, the first defendant from entering into a contract with the
the subcontractor, the
plaintiff. However, in my opinion this cause
of action is not clear from the amended and unamended particulars of
claim.
Evaluation
and Discussion
[38]
Counsel for the plaintiff has asked the
court to look at the plaintiff’s particulars of claim as whole
and not for the court
to take an overly technical approach. Having
heard the arguments made by the counsels and having examined the
particulars of claim
as a whole, particularly in regard to the
amendments made to the particulars of claim, I am of the opinion that
the plaintiff only
addressed the second ground of exception (lack of
authority) raised by the first defendant.
[39]
The plaintiff’s amendments in the
particular of claims set out in paragraphs 44A, 44B, and 44C
addresses the issues raised
by the first defendant in its second
ground of exception regarding the allegation of the delegation of
authority to Mr Swanepoel
and lack of authority of Mr Swanepoel.
[40]
Regarding the first defendant’s first
and second ground of exception to the particulars of claim,
from a reading of
the plaintiff’s Heads of Argument and having
heard the plaintiff’s counsel, the main cause of action against
the first
defendant is based on the September 2021 oral agreement
which the plaintiff alleges is a new agreement which does not fall
within
the purview of the subcontract’s non-variation clause.
All of this is not clear from the particulars of claim read as a
whole.
For example, paragraph 43 of the particular of claims deals
with the claim of damages arising from the subcontract and not the
alleged 22 September new oral contract. Paragraph 43 of the
particulars of claims state:
“
As
a direct consequence of the afore stated breaches by MECSA and FP of
the sub-contract, the plaintiff suffered contractual damages
in the
amount of R13 970 320.85, being the balance due for the sub-contract
works and site instructions which were performed by
and as reflected
in the plaintiff’s account dated 17 April 2020, amounting to
R37 086 498, less payment received in the amount
of R23 086 498.39.”
[41]
Paragraphs 8 to 43 of the particulars of
claim sets out the entire background of the first action (case number
33677/2022) brought
by the plaintiff against the second and third
defendant arising from the subcontract. It is this background that
forms the foundation
of the plaintiff’s main claim against the
respondent arising from the subcontract as set out in paragraph 43 of
the particulars
of claim. It is only from paragraph 44 onwards that
the alternative claim under the oral agreement is set out in terms of
which
it is alleged that payment would be made to the plaintiff upon
the conclusion of the debatement. Paragraph 44 sates:
”
In
the alternative to the claim of the plaintiff against MECSA and FP
for contractual damages,
the plaintiff
is entitled to the debatement of the account dated 17 April 2020 of
the plaintiff, with FP, in terms of the September
2021 agreement and
to payment of what is found to be due to the plaintiff upon the
conclusion of of such debatement.”
[42]
Thus, the agreements by the plaintiff that
the main cause of action against the plaintiff is based on the
September 2021 oral agreement,
which is pleaded as a new agreement by
the plaintiff is not concisely and clearly articulated as the main
cause of action against
the defendant in the particulars of claim,
both in its amended and unamended form.
[43]
I am in agreement with plaintiff’s
counsel that there is no prohibition that precludes the first
defendant (employer) from
entering into a new contract with the
plaintiff (the subcontractor). However, on a reading of the unamended
and amended particulars
of claim, the relief sought in terms of the
September 2021 oral agreement is founded and flows from the
performance of services
rendered in terms of the subcontract. For
example, paragraph 40 of the particulars of claims, it is stated:
“
In
terms of the notice of disagreement the plaintiff demanded from FP
that a meeting be held between the plaintiff and the quantity
surveyor of FP to resolve the dispute about the incorrect payment
certification.”
[44]
What followed from this demand for a
meeting by the plaintiff was the 9 September 2021 meeting as set out
in paragraph 41 of the
particulars of claim. The pleading that the
oral contract is a new contract being pleaded is unclear and
ambiguous from a reading
of the particulars of claim.
[45]
Furthermore, in paragraph 5 of the
particulars of claim the plaintiff alleges that:
“
the
second and third defendants are cited herein insofar as they may have
a real and substantial interest in the relief claimed
by the
plaintiff and no substantive relief and/or cost order is sought
against the second and third defendants herein save in the
event of
opposition hereto.”
[46]
I am in agreement with the first
defendant’s counsel that if no relief is sought against the
second and third defendant, then
by default the relief sought must be
directed against the first defendant. But that is not what is sought
in the first prayer of
the particulars of claim in its unamended and
amended form.
[47]
Looking at the totality of evidence
provided, the amended particulars of claim appears to be a “patchwork
of claims”
cobbled together; taken from the 33677/2022 case and
imported in this case and added thereto is the partial amendments
made to
address the first defendant’s exception. As a whole the
particulars of claim is not clear and concise in articulating that
the plaintiff’s main cause of action is founded on the first
defendant’s breach of an oral agreement concluded between
the
plaintiff and defendant on 9 September 2021, as averred by the
Plaintiff’s counsel.
[48]
In the premises, I find that the
plaintiff’s particulars of claim even after amendment remains
excipiable, the Rule 28(4)
application is not granted, and the first
defendant’s exception is upheld.
Order
[49]
I hereby make the following order:
49.1
The plaintiff’s application brought against the defendants
under Uniform Court Rule 28(4) to amend
its particulars of claim is
dismissed and the first defendant’s exception is upheld.
49.2
The plaintiff is ordered to pay the costs of this application.
W DOMINGO
ACTING JUDGE OF THE
HIGH COURT
PRETORIA
Delivered: This judgment
was prepared and authored by the Judge whose name is reflected and is
handed down electronically by circulation
to the parties’ legal
representatives by email and by uploading it to the electronic file
of this matter on CaseLines. This
matter was heard in open court on
the 10 February 2025. The date for hand-down is deemed to be 9 May
2025.
APPEARANCES
For the
Plaintiff:
ADVOCATE BH STEYN
instructed
by
TINTINGERS INCORPORATED
For the First and Third
Defendant: ADVOCATE CJ Mc ASLIN SC
instructed
by
PINSENT MASONS SOUTH AFRICA INC.
Second
Defendant:
NO APPEARANCE
[1]
See
Nedbank
Limited v Ouderajh
(11969/2015)
[2022] ZAKZDHC 8 (29 April 2022);
Affordable
Medicines Trust and Others v Minister of Health and Others
[2005] ZACC 3
;
2006
(3) SA 247
(CC); and
Ascendis
Animal Health (Pty) Letd v Merck Sharp Dohme Corporation and Others
2020
(1) SA 327 (CC).
[2]
Embling
and Another v Two Oceans Aquarium CC
2000
(3) SA 691
(C) at 694G-H.
[3]
AC/DC
Dynamics (Pty) Ltd v Shrinik Retailing (Pty) Ltd and Another
2022
JDR (GJ) at para 12.
[4]
Trans-Drakensberg
Bank Ltd (under Judicial Management) v Combined Engineering (Pty)
Ltd
1967
(3) SA 632
(D) at 641A.
[5]
1980
(1) SA 250
(C) at 258H-259A.
[6]
1967
(4) SA 308
(C) at 310D-311A.
[7]
2016
(1) SA 47
(WCC) at para 11 to 12.
[8]
See
Trope
v South African Reserve Bank
1993
(3) SA 264 (A).
[9]
See
Madiro
v Madibeng Local Municipality
2021
JDR 2631 (GP) and
supra.
sino noindex
make_database footer start
Similar Cases
Kaj Pipes Fittings CC v Commissioner for South African Revenue Service (57062/2019) [2025] ZAGPPHC 1380 (22 December 2025)
[2025] ZAGPPHC 1380High Court of South Africa (Gauteng Division, Pretoria)97% similar
SEPCOIII (Pty) Ltd v Smecsouth Africa (Pty) Ltd (2024-061081) [2025] ZAGPPHC 943 (2 September 2025)
[2025] ZAGPPHC 943High Court of South Africa (Gauteng Division, Pretoria)97% similar
SPP Pumps (South Africa) (Pty) Ltd v Stoop (A189/2020) [2022] ZAGPPHC 200 (29 March 2022)
[2022] ZAGPPHC 200High Court of South Africa (Gauteng Division, Pretoria)97% similar
Interwaste (Pty) Ltd and Others v Broad-Based Black Economic Empowerment Commission and Others (34095/21) [2023] ZAGPPHC 1179; 2024 (1) SA 439 (GP) (5 July 2023)
[2023] ZAGPPHC 1179High Court of South Africa (Gauteng Division, Pretoria)97% similar
IX Engineers (Pty) Ltd v September and Another (48047/2021) [2023] ZAGPPHC 1829 (26 September 2023)
[2023] ZAGPPHC 1829High Court of South Africa (Gauteng Division, Pretoria)97% similar