Case Law[2025] ZAGPPHC 508South Africa
Lonerock Spartan Group JV v Minister of National Department of Public Works and Infrastructure and Others (2023/067555) [2025] ZAGPPHC 508 (16 May 2025)
High Court of South Africa (Gauteng Division, Pretoria)
16 May 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 508
|
Noteup
|
LawCite
sino index
## Lonerock Spartan Group JV v Minister of National Department of Public Works and Infrastructure and Others (2023/067555) [2025] ZAGPPHC 508 (16 May 2025)
Lonerock Spartan Group JV v Minister of National Department of Public Works and Infrastructure and Others (2023/067555) [2025] ZAGPPHC 508 (16 May 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_508.html
sino date 16 May 2025
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
CASE NO: 2023-067555
1.
REPORTABLE: NO
2.
OF INTEREST TO OTHER JUDGES: NO
3.
REVISED: YES
DATE:
16 May 2025
In the matter between:
LONEROCK
SPARTAN GROUP JV
Applicant
and
THE
MINISTER OF THE NATIONAL DEPARTMENT OF
PUBLIC
WORKS AND INFRASTRUCTURE
First Respondent
ZIMBINI
HILL
NO
Second Respondent
TIMOTHY
SUKAZI
NO
Third Respondent
MICHAEL
SUTCLIFFE
NO
Fourth Respondent
RAYMOND
NKANDO
NO
Fifth Respondent
KARABO
SIYILA
NO
Sixth Respondent
LERATO
KUMALO
NO
Seventh Respondent
NTHABISENG
MKHWANAZI
NO
Eighth Respondent
MPILO
MBAMBISA
NO
Ninth Respondent
KRISHEN
SUKDEV
NO
Tenth Respondent
LUFUNO
NEVONDWE
NO
Eleventh Respondent
REHANA
PARKER
NO
Twelfth Respondent
(in their capacity as the
trustees for the time being of the INDEPENDENT DEVELOPMENT TRUST
(REGISTRATION NUMBER: IT 669/91))
JUDGMENT
HF
OOSTHUIZEN AJ
THE CONTRACT
[1.]
The applicant, a joint venture between two
companies, claims payment from the first respondent of two extension
of time claims pursuant
to a construction contract relating to the
upgrading of certain civil engineering services at the Pretoria
Waterkloof Air Force
Base (“the contract” and “the
project” respectively).
[2.]
The contract consists of the applicant’s
tender and an offer of appointment, in which the General Conditions
of Contract for
Construction Works (2015) Third Edition, published by
the South African Institute of Civil Engineering (“the GCC
2015”)
and contract specific data, being amendments, additions
and omissions of the GCC 2015 (“the contract data”) were
incorporated.
[3.]
The offer of appointment was signed on
behalf of the first respondent by the Independent Development Trust
(“the IDT”),
whose trustees are cited in the application
as the second to twelfth respondents. No relief is sought against the
IDT and the IDT
abides the decision of the Court.
[4.]
The first respondent, as the custodian and
manager of all the National Government’s fixed assets,
concluded a memorandum of
agreement with the IDT as an agent to
assist the first respondent with the implementation of the so-called
Infrastructure Programme
Plan. The IDT accordingly manages the
project on behalf of the IDT in return for the payment of a
market-related management fee
and disbursements.
[5.]
The IDT is accordingly the implementing
agent on behalf of the National Department of Public Works, who is
described in the offer
of appointment as the “
Employer
”.
[6.]
The IDT is, somewhat confusingly, also
described in the contract data (and accordingly also in the GCC 2015)
as the “
Employer
”.
[7.]
It is common cause that the IDT fulfilled
the role of “
Employer
”
in terms of the GCC 2015, as amended by the contract data, save that
the IDT is not liable for the payment of any amounts
to which the
applicant is entitled in terms of the contract - the first respondent
remains liable to make payment to the applicant
of any amounts to
which it is entitled.
[8.]
The GCC 2015 moreover provides for an
“
Employer’s Agent
”,
who is identified in the offer of appointment as Endecon Ubuntu (Pty)
Ltd (“Endecon”).
[9.]
I will, to prevent possible confusion,
refer in this judgement to the “
Employer
”
/ implementing agent as the IDT and to the “
Employer’s
Agent
” as Endecon.
[10.]
The relevant express terms of the GCC 2015,
as amended by the contract data, are as follows: (All references in
this judgement to
clauses are to clauses of the GCC 2015.)
[10.1.]
The functions of Endecon is to administer
the contract as agent of the IDT, in accordance with the provisions
of the contract (clause
3.2.1).
[10.2.]
The IDT shall have the right to reverse and
amend any certificate, instruction, decision or evaluation of Endecon
and to issue a
new one, and such certificate, instruction, decision
or evaluation shall for the purposes of the contract be deemed to be
issued
by Endecon (clause 3.2.3, as amended).
[10.3.]
The applicant shall deliver to Endecon a
monthly statement for all amounts it considers to be due and Endecon
shall, by signed payment
certificates certify the amount it considers
to be due to the applicant (clauses 6.10.1).
[10.4.]
Endecon shall deliver to the applicant the
payment certificate within 7 days after receipt of the applicant’s
statement and
the first respondent shall pay the amount due to the
applicant within 28 days of receipt of the payment certificate
subject to
the applicant submitting a tax invoice for the amount due
(clause 6.10.4).
[10.5.]
In
the event of failure by the first respondent to make payment by the
due date, the first respondent shall pay to the applicant
interest at
the rate determined by the Minister of Finance from time to time in
terms of section 80(1)(b) of the
Public
Finance Management Act
,
1999,
[1]
compounded monthly, on
all overdue payments from the date on which the same should have been
paid to the date when payment is effected
(clause 6.10.6.2, as
amended).
[10.6.]
Endecon may in a payment certificate make
any correction or modification of any previous payment certificate,
which has been issued
by it (clause 6.10.7).
[10.7.]
The applicant may, after giving 14 days
written notice to the IDT, with a copy to Endecon, suspend the
progress of the works where
the first respondent has failed to make
full payment of the amount certified in a payment certificate (clause
5.11.1).
[10.8.]
If the applicant considers itself entitled
to an extension of time that will extend practical completion of the
works beyond the
due completion date, the applicant shall claim in
accordance with clause 10.1 such extension of time as is appropriate
(clause
5.12.1).
[10.9.]
Circumstances which could justify an
extension of time include any disruption which is entirely beyond the
applicant’s control
(clause 5.12.2.4).
[10.10.]
If an extension of time is granted, the
applicant shall be paid such additional time related general items as
are appropriate (clause
5.12.3).
[10.11.]
The applicant shall, within 28 days after
the circumstance, event, act or omission giving rise to a claim for
an extension of time
has arisen or occurred, deliver to Endecon a
written claim, setting out the particulars of the circumstance,
event, act or omission
giving rise to the claim concerned; the
provisions of the contract on which it bases the claim; the length of
the extension of
time claimed on the basis of calculation thereof;
and the amount of money claimed on the basis of calculation thereof
(clause 10.1.1.1).
[10.12.]
If, by reason of the nature and
circumstances of the claim, the applicant cannot reasonably comply
with all or any of the provisions
of clause 10.1.1.1 within the said
period of 28 days, it shall within the said period of 28 days notify
Endecon, in writing, of
its intention to make the claim and comply
with such of the requirements of clause 10.1.1.1 as it reasonably
can; and as soon as
is practicable, comply with such of the
requirements of clause 10.1.1.1 as have not yet been complied with
(clause 10.1.1.2)
[10.13.]
If the applicant fails to comply with the
28 day notice period in clause 10.1.1, as read with clause 10.1.2, or
does not deliver
its final claim within 28 days after the end of the
events or circumstances, the due completion date shall not be
extended, the
applicant shall not be entitled to additional payment,
and the first respondent shall be discharged of all liability in
connection
with the claim (clause 10.1.4).
[10.14.]
The IDT shall, within 28 days after the
applicant has delivered its claim, deliver to the applicant its
written ruling on the claim.
The amount thereof, if any, allowed by
the IDT shall be included to the credit of the applicant in the next
payment certificate
(clause 10.1.5, as amended).
[10.15.]
If the IDT fails to give its ruling within
the prescribed period, the IDT shall be deemed to have given a ruling
dismissing the
claim (clause 10.1.6).
[10.16.]
Disputes are to be referred for final
settlement to litigation (clause 10.7, as amended).
THE FIRST CLAIM
[11.]
The applicant’s first claim arose in
consequence of the suspension of works by the applicant from 5 July
2021 to 29 September
2021 following on the first respondent’s
non-payment of payment certificates.
[12.]
On 17 June 2021, the applicant sent a
notice to Endecon (and not to the IDT) of its intention to suspend
the progress of works due
to non-payment of payment certificates.
[13.]
On 5 July 2021 (the date on which the
suspension of the progress of works commenced), the applicant sent a
notice to Endecon of
its intention to claim extension of time with
associated costs as a result of the suspension of works, setting out
the particulars
prescribed by clause 10.1.1.1 insofar as it was
possible. It specifically indicated that it would only be entitled to
finally calculate
the costs once it had received full payment.
[14.]
Between 29 July 2021 and 22 February 2022
the applicant sent further notices to Endecon on a monthly basis,
which notices were similar
to the notice of 5 July 2021 and which
notices included updated calculations of the claimed costs. The
applicant indicated in notices
that its claim could only be finally
calculated once all outstanding payments are paid in full.
[15.]
On 2 March 2022, the applicant submitted a
final claim for extension of time for 86 calendar days with
associated costs in the amount
of R2 505 969.05 (excluding
VAT) being preliminary and general cost; plant standing time and
interest on late payment.
[16.]
Endecon considered the claim and
recommended approval of the extension of time claim for 86 calendar
days with associated costs
in the reduced amount of R2 046 272.88
(excluding VAT). Endecon specifically found that the applicant had
given the necessary
notification of intention to claim in the
specified time frames.
[17.]
On 30 June 2022, the IDT recommended
approval of the extension of time claim for 86 calendar days with
associated costs in the total
amount of R2 057 790.10
(excluding VAT) to the first respondent. The applicant accepted the
ruling of the reduced amount.
[18.]
The first respondent approved the extension
of time claim but refused to make payment of associated costs,
relying on clause 10.1.4,
due to the applicant’s alleged
failure to comply with the following provisions of the contract:
[18.1.]
the applicant gave written notice to
Endecon (and not to the IDT) of its intention to suspend the progress
of the works, as required
by clause 5.11.1; and
[18.2.]
the applicant did not submit its claim
within 28 days after the circumstance that gave rise to the claim had
occurred, as required
by clause 10.1.1.1.
[19.]
I am of the view that there is no merit in
either defence:
[19.1.]
The failure by the applicant to give
written notice to the IDT of its intention to suspend the progress of
the works (as required
by clause 5.11.1), cannot discharge the first
respondent from liability in connection with a claim in terms of
clause 10.1.4. The
first respondent could only be discharged of
liability if the applicant failed to comply with the 28 day notice
period in clause
10.1.1 (for an extension of time for practical
completion) or if the applicant did not deliver its final claim
within 28 days after
the end of the relevant events or circumstances.
[19.2.]
As I indicated in paragraphs [13] to [15]
above, the applicant submitted written claims throughout the period
of suspension of works,
which set out the prescribed information in
terms of clauses 10.1.1.1.1 to 10.1.1.1.4 insofar as the applicant
was able to. The
applicant thus complied with the requirements of
clause 10.1.1.1, read with clause 10.1.1.2,
alternatively
complied substantially with such provisions.
[20.]
I am in the alternative of the view that
the first respondent is bound by the ruling of the IDT, the agent of
the first respondent,
to approve the applicant’s claim:
[20.1.]
It
is trite that a principal is bound by juristic acts which its duly
authorised agent has performed on its behalf.
[2]
[20.2.]
It is common cause that the IDT was duly
authorised by the first respondent to perform all functions as the
“
Employer
”
in terms of the contract, including the right to reverse and amend
any certificate, instruction, decision or evaluation
of Endecon. The
first respondent on the other hand is merely obliged to make payment
of all claims in terms of the contract.
[20.3.]
Although the first respondent would be able
to terminate the authority of the IDT to act on its behalf, the first
respondent could
not simply take over the powers and functions of the
IDT in terms of the agreement. The powers and functions of the IDT
did not
accrue to the first respondent, as argued by Ms Nodada on
behalf of the first respondent.
[20.4.]
The amount of any allowed claim shall, in
terms of clause 10.1.5, as amended, be included to the credit of the
applicant in the
next interim payment certificate.
[20.5.]
A
final payment certificate can only be challenged on very limited
grounds such as fraud and the like.
[3]
The
employer will not be bound if there has been fraud or if the agent
had acted in collusion with the contractor to the detriment
of the
employer or if the agent had exceeded its mandate.
[4]
[20.6.]
The
employer is not entitled to dispute the validity of a final payment
certificate
vis-à-vis
the
contractor merely because he alleges that the certificate was given
negligently.
[5]
The
employer’s remedy in such event is to claim damages from the
agent.
[6]
[20.7.]
Although the legal position in respect of
interim payment certificates differs in certain respects from that of
final payment certificates,
Endecon did not have the power to correct
or modify the IDT’s ruling in respect of the applicant’s
first claim in terms
of clause 6.10.7, which implies that the claimed
amount would in due course be included in the final payment
certificate.
[21.]
The applicant claims interest on the amount
of R2 057 790.10 (excluding VAT) calculated at the rate of
10.25% per annum
from 2 March 2022, being the date of the applicant’s
final claim.
[22.]
The claim for interest ignores the
following provisions of the contract:
[22.1.]
The amount of any allowed claim shall be
included to the credit of the applicant in the next interim payment
certificate.
[22.2.]
Endecon shall deliver to the applicant a
payment certificate within 7 days after receipt of the applicant’s
statement and
the first respondent shall pay the amount due to the
applicant within 28 days of receipt of the payment certificate
subject to
the applicant submitting a tax invoice for the amount due.
[22.3.]
In the event of a failure by the first
respondent to make payment by the due date, the first respondent
shall pay to the applicant
interest at the rate determined by the
Minister of Finance from time to time in terms of section 80(1)(b) of
the
Public Finance Management Act
,
1999, compounded monthly, on all overdue payments from the date on
which the same should have been paid to the date when payment
is
effected.
[23.]
The applicant has failed to present
evidence whether the allowed claim was included to the credit of the
applicant in a subsequent
interim payment certificate and whether the
applicant submitted a tax invoice for the amount due. I am
accordingly unable to determine
the date on which interest would
commence to run, being 28 days of receipt of such payment certificate
and subject to the applicant
submitting a tax invoice for the amount
due.
[24.]
I
am accordingly only prepared to order the first respondent to make
payment of interest from the date on which the application
was
instituted, being 11 July 2023, at which date the interest determined
by the Minister of Finance in terms of section 80(1)(b)
of the
Public
Finance Management Act
,
1999 was 11,75% per annum.
[7]
THE
SECOND CLAIM
[25.]
The applicant’s second claim is for
costs in relation to the Covid-19 pandemic’s mandatory safety
regulations, including
the actual costs of R107 477,54
(excluding VAT) for the appointment of a Covid-19 officer to perform
screening on all employees
to measure their temperatures and keep
record of traceability of the Covid-19 virus.
[26.]
On 30 September 2022, Endecon recommended
payment of R3 075 511.00 (excluding VAT) and confirmed that
a Covid-19 officer
was appointed to screen the applicant’s
employees on a daily basis.
[27.]
The IDT failed to make any ruling on the
second claim, which implies that the ruling was deemed to be
dismissed in terms of clause
10.1.5.
[28.]
The first respondent accepts that the
Covid-19 pandemic amounted to a disruption which was entirely beyond
the applicant’s
control, within the meaning of clause 5.12.2.4,
and that the applicant is entitled to claim costs pursuant thereto.
[29.]
The first respondent only disputes the
applicant’s entitlement to claim for a Covid-19 officer. It
argues that the duties
of the Covid-19 officer could have been
performed by the applicant’s appointed Occupational Health and
Safety Officer (“the
OHS Officer”), which implies that
the claimed costs amounted to an unwarranted duplication of costs.
[30.]
In the replying affidavit the applicant
indicated that the duties of the OHS Officer were extensive and
wide-ranging in view of
the size and extent of the construction site
and that it was impossible for the existing OHS Officer to double up
as the designated
Covid-19 officer.
[31.]
The deponent to the first respondent’s
answering affidavit is a project manager at the construction
management branch of the
Department of Public Works. He does not have
personal knowledge of the circumstances at the construction site and
relies on documents
and “
various
consultations with relevant officers who were involved in matters
relevant to the application
”,
without identifying them.
[32.]
In view of his lack of knowledge of the
circumstances at the construction site, the allegation that the
duties of the Covid-19 officer
could have been performed by the
applicant’s OHS Officer is mere speculation.
[33.]
The uncontested facts are that the
applicant was obliged in terms of the relevant Covid-19 regulations
to appoint a Covid-19 officer;
the appointed Covid-19 officer
performed the prescribed functions; the applicant claimed actual
expenses which it incurred in compliance
with its statutory
obligations; and the IDT’s agent, Endecon, recommended that the
applicant be paid.
[34.]
I am accordingly of the view that the
applicant has proven its entitlement to the costs of the Covid-19
officer.
[35.]
The applicant claims interest on the amount
of R3 057 790.10 (excluding VAT) calculated at the rate of
10.25% per annum
from 22 June 2022, being the date of the applicant’s
claim.
[36.]
The applicant has failed to prove its
entitlement to such interest and I am accordingly only prepared to
order the first respondent
to make payment of interest on the same
basis as in the first claim.
[37.]
Ms Nodada has conceded that the applicant’s
appointment of two counsel was justified.
ORDER
[38.]
I accordingly grant the following order:
[38.1.]
The first respondent is ordered to pay to
the applicant the amount of R5 903 296.27 together with
interest calculated
on this amount at the rate of 11,75% per annum,
compounded monthly, from 11 July 2023 to date of final payment.
[38.2.]
The first respondent is ordered to pay the
costs of the application, including the costs of two counsel on scale
B.
HF
OOSTHUIZEN AJ
ACTING
JUDGE OF THE HIGH COURT
This
Judgment was handed down electronically by circulation to the
parties’ and or parties’ representatives by email
and by
being uploaded to CaseLines. The date and time for the hand down is
deemed to be 10h00
on this
16 May 2025
.
Appearances
Adv
C Acker and Adf J Hartman, instructed by Pagel Schulenburg Inc
appeared on behalf of the applicant.
Adv
B Nodada, instructed by the State Attorney, appeared on behalf of the
first respondent.
There
was no appearance on behalf of the second to twelfth respondents.
Date of Hearing: 7 May
2025
this Date of Judgment: 16
May 2025
[1]
Act
1 of 1999
[2]
Makate
v Vodacom Ltd
2016 (4) SA 121
(CC) para [45]
[3]
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC
[1993] ZASCA 41
;
1993
(3) SA 331
(A) at 344C
[4]
S
mith
v Mouton
1977
(3) SA (W) at 13A,
which
was confirmed in
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC supra
at
340F
[5]
Smith
v Mouton supra
at
13E
[6]
Smith
v Mouton supra
at
14D
[7]
National Treasury General Notice 1907 of 2023, published in
the
Government
Gazette
,
7 July 2023 number 48923 p 27
sino noindex
make_database footer start
Similar Cases
Lonerock Spartan Group JV v Minister of the National Department of Public Works and Infrastructure and Others (087460/2023) [2025] ZAGPPHC 1127 (10 October 2025)
[2025] ZAGPPHC 1127High Court of South Africa (Gauteng Division, Pretoria)100% similar
Lonerock Construction v South African National Roads Agency (SOC Limited) [2023] ZAGPPHC 527; 89831/2018 (27 June 2023)
[2023] ZAGPPHC 527High Court of South Africa (Gauteng Division, Pretoria)98% similar
Big Rock Construction 12 CC v Kaan Developments 2 CC (8964/2022) [2025] ZAGPPHC 888 (12 August 2025)
[2025] ZAGPPHC 888High Court of South Africa (Gauteng Division, Pretoria)96% similar
Servsol Software Solutions CC and Others v Emisha Software (Pty) Ltd (Leave to Appeal) (2023/069011) [2024] ZAGPPHC 950 (18 September 2024)
[2024] ZAGPPHC 950High Court of South Africa (Gauteng Division, Pretoria)96% similar
Rock Foundation Properties CC and Another v Dosvelt Properties (Pty) Limited and Another (20/28515) [2023] ZAGPJHC 408 (2 May 2023)
[2023] ZAGPJHC 408High Court of South Africa (Gauteng Division, Johannesburg)96% similar