Case Law[2025] ZAGPPHC 1181South Africa
Uzani Environmental Advocacy CC v BP Southern Africa (Pty) Ltd (Leave to Appeal) (CC 82/2017) [2025] ZAGPPHC 1181 (3 November 2025)
Headnotes
enquiry which is expressly provided for at the commencement of the section.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 1181
|
Noteup
|
LawCite
sino index
## Uzani Environmental Advocacy CC v BP Southern Africa (Pty) Ltd (Leave to Appeal) (CC 82/2017) [2025] ZAGPPHC 1181 (3 November 2025)
Uzani Environmental Advocacy CC v BP Southern Africa (Pty) Ltd (Leave to Appeal) (CC 82/2017) [2025] ZAGPPHC 1181 (3 November 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_1181.html
sino date 3 November 2025
GAUTENG DIVISION,
PRETORIA
CASE NO: CC 82/2017
(1)
REPORTABLE:
NO
(2)
OF INTEREST TO OTHER JUDGES:
YES
(3)
REVISED.
3
November 2025
SIGNATURE
In the matter between:
UZANI
ENVIRONMENTAL ADVOCACY CC
Prosecutor
And
BP
SOUTHERN AFRICA (PTY) LTD
as
represented in terms of s332(2)
of
Act 51 of 1977 by
Mr Thuto Gasealahwe
Accused
JUDGMENT
– LEAVE TO APPEAL
(Uzani
(5))
SPILG,
J:
3
November 2025
INTRODUCTION
1.
On 29 June 2017 the then Judge President of the Gauteng Division
granted the UZANI Environmental Advocacy
CC (“
UZANI
”)
leave to institute the private prosecution in the Gauteng Division
against BP Southern Africa (Pty) Ltd (“
BPSA
”). A
writ of summons and indictment was subsequently issued out of this
court and served on 3 August 2017.
2.
A number of
pre-trial issues were raised and dealt with
[1]
,
after which BPSA pleaded and the trial commenced.
3.
BPSA was found guilty under s 29(4) of the Environmental
Conservation Act 73 of 1989
(“ECA”)
for failing to
obtain the required written environmental authorisation to
construct filling stations, including associated
structures and
infrastructure, or other facilities for the underground storage of
petrol and diesel. Petrol and diesel fall within
the definition of
dangerous goods and their storage is a controlled activity which
required such authorisation under s 22(1)
of ECA.
The judgment was
delivered in April 2019 and is reported as
Uzani Environmental
Advocacy CC v BP Southern Africa (Pty) Ltd
[2019] ZAGPPHC 86 (see
also
2019 (5) SA 275
(GP);
[2019] 2 All SA 881
(GP)). The judgment
has been referred to as
Uzani (1)
.
4.
In terms of s 29(4) of ECA any person who contravenes s 22(1) is
guilty of an offence and liable on conviction
to a fine or to
imprisonment.
Aside from the imposition
of a sentence under s 29(4), in terms of s 34(3) of the National
Environmental Management Act 107 of 1998
(“
NEMA
“),
a person who is convicted of an offence under any provision listed in
Schedule 3 of that Act, and in addition to any other
punishment
imposed, is subject to pay damages, or compensation or a fine equal
to the amount which the court must assess is “
the monetary
value of any advantage gained or likely to be gained by such person
in consequence of that offence”,
or alternatively require
the offender to take remedial measures
.
This is the
current wording of the section.
The assessment is made
pursuant to a summary enquiry which is expressly provided for at the
commencement of the section.
5.
UZANI then applied for an order to hold a post-conviction s 34(3)
enquiry. BPSA argued that a contravention
of s 22(1) read with s
29(4) of ECA was not a listed Schedule 3 offence under NEMA and
therefore such an enquiry was not
competent in respect of the
offences at the time they were committed.
6.
In a judgment delivered during May 2020 and cited as
Uzani
Environmental Advocacy CC v BP Southern Africa
[2020] ZAGPPHC 222
(“
Uzani 2
”) the court held that such
an enquiry was competent under the legislation which prevailed at the
relevant time.
7.
An enquiry was held and a sentence imposed. The judgment is
cited as
Uzani Environmental Advocacy CC v BP Southern Africa
(Pty) Ltd
[2024] ZAGPPHC 1387 (“
Uzani 3
”).
The sentence imposed was
:
a.
In respect of the counts under s 34(3) of
NEMA, a fine of R 6 245 424
b.
In respect of the counts under s 29(4) of
ECA, an initial fine of R 6 187 650
c.
In respect of the additional fine under s
29(4) of ECA, an amount of R
47 112 970.
The total amount of fines
was therefore R59 546 044
8.
As explained in
Uzani
(3)
, the court wished to reconsider the
costs issue and subsequently delivered a separate judgment. It
is cited as
Uzani Environmental Advocacy
CC v BP Southern Africa (Pty) Ltd
[2025]
ZAGPPHC 263 and was referred to as
Uzani
(4)
. The order provided that BPSA was
to pay:
a.
the costs of the private prosecution
including the section 34(3)(g) inquiry on the attorney and client
scale save that it shall
not be liable for the following costs;
a.
all costs associated with the application to
compel of 10 November 2017
b.
all costs associated with the fraud charges which
were subsequently withdrawn
c.
The postponements occasioned on 20 March 2018, 19
February 2019, 25 March 2019 and 18 March 2022.
d.
The costs payable by BPSA included the qualifying
fees of certain experts engaged by the prosecution, the costs
attendant on the
engagement of senior counsel and, if applicable,
junior counsel.
APPLICATIONS
FOR LEAVE TO APPEAL AND CROSS APPEAL
BPSA’s
application
9.
BPSA applied for leave to appeal in respect
of both conviction and sentence. It submitted that the court
erred in finding;
a.
that the private prosecutor had title to
prosecute, whereas it should have found that:
1.
Section 33(2) of NEMA as read
with s 8 of the CPA had not been complied with;
2.
Section 33(1) of NEMA had not been complied
with since it had not proven that the private prosecution was
instituted in the public
intertest or in the interests of protecting
the environment;
b.
that the s 24G applications submitted by
BPSA were admissible as evidence in that they violated its right
against self-incrimination,
absent forewarning that evidence of
the commission of the offences contained in the applications may be
used against it in
criminal proceedings or absent of any use
indemnity in s 24G or the s 24G process;
c.
that an enquiry under s 34(3) of NEMA was
competent having regard to the legislation prevailing at the relevant
time
in relation to the charges upon which BPSA was convicted;
d.
on sentence. BPSA submitted that the
sentence imposed was based on misdirections, a failure to take
relevant considerations into
account or to afford them sufficient
weight and that the sentence was disproportionate in the
circumstances and created a sense
of shock.
10.
In its application for leave to appeal BPSA
submitted that if granted the appeal should be referred to the
Supreme Court of Appeal
(“
the
SCA
”
) .
UZANI’s
opposition and cross-appeal application
11.
UZANI gave notice opposing BPSA’s
application for leave to appeal and brought an unconditional
cross-appeal.
12.
In respect of BPSA’s application for
leave to appeal against the conviction, UZANI disputed that BPSA had
demonstrated reasonable
prospects of success on appeal.
13.
UZANI however supported BPSA’s
submissions that the court had erred in respect of sentence. It
contended that the court
had;
a.
failed to impose an adequate fine having
regard to the factors set out in para 2 of its cross-appeal
application;
b.
erred in its legal interpretation of s29(4)
of ECA read with item 1(c) of GN R1182 of 5 September 1997,
contending further that
the court had failed to apply the SCA
decision of
Fuel Retailers Association
which was binding on it;
c.
erred in its interpretation of s 34B of
NEMA.
14.
UZANI added a further ground for its
cross-appeal. It sought leave to cross-appeal:
“
Against
BP’s use of a SLAPP and Stalingrad-inspired strategy to escape
and delay appropriate sentences
”
.
It was assumed that this
was an additional factor which should have been taken into account in
aggravation of sentence and therefore
be reflected in a severer fine.
This was confirmed by the contents of para B3 of UZANI’s Draft
Court Order presented on 8
August 2025.
15.
UZANI in its application also submitted
that if leave was granted that the matter be directed to the SCA.
AGREEMENT BETWEEN THE
PARTIES AT THE HEARING
16.
At the hearing the parties confirmed that
leave be granted to appeal and cross-appeal. They also agreed that
the appeal should be
to the SCA.
17.
The court accepted that it would not
be in the interests of justice, having regard to expedition, costs
and avoiding a piecemeal
disposal of the appeal, if certain grounds
which it considered did not meet the requirement of having reasonable
prospects of success
on appeal were excluded from the grant of leave.
It is evident that the unique issues raised by the legislation in
respect of sentencing
requires a decision by an appellate court able
to set binding precedent nationally.
18.
The parties were requested to prepare a
draft order and the court indicated that it wished to mention an
aspect or two in its reasons
for granting leave.
SUBSEQUENT EVENTS
19.
BPSA presented its draft of the court
order granting leave to appeal and cross-appeal on 7 August. UZANI
disagreed with the
formulation used to describe the grounds it relied
on for the cross-appeal on sentence. On the following day it
submitted its own
draft.
20.
The difference between the two drafts is
that UZANI wishes to flesh out its three grounds in more detail than
BPSA has done. It
contends that BPSA’s formulation of the draft
order enables it to add grounds not necessarily argued at the trial
while precluding
it from doing likewise.
21.
Due to the court’s other commitments
it regrettably did not address the competing drafts. On 27 October
2025 it received a
copy of a Rule 32 application by UZANI for leave
to appeal directly to the Constitutional Court.
22.
On the same date BPSA’s attorneys
requested the court for feedback or directions regarding the status
of the matter.
THE GRANT OF LEAVE TO
APPEAL AND CROSS-APPEAL TO THE SCA
23.
On 6 Augst 2025 and by agreement
between the parties this court granted BPSA leave to appeal on
conviction and sentence and UZANI
leave to cross-appeal on sentence.
This was done by way of a remote hearing with the parties.
24.
The manner in which the order should be
formulated does not derogate from the fact that an order was granted.
This court should
have adopted the position that it is adequate to
simply grant leave by describing the grounds generally, leaving it to
the reasons
for its grant to clarify what was actually before the
court. The parties can then convince the appellate court as to
whether an
issue had been raised during the proceedings, and if not
whether it is one of law or fact or both and if it is permissible to
raise
the point for the first time on appeal having regard to the
relevant considerations which would weigh with the appellate court.
I
regret failing to adopt this position earlier.
OBSERVATIONS REGARDING
THE GROUNDS OF APPEAL
25.
The court does not recall BPSA
arguing in relation to conviction that s 24G fails to forewarn a
person that the evidence of the
register of s 24G applications will
be admissible as evidence in subsequent criminal proceedings relevant
to the offences
with which BPSA was charged or that s 24G or its
process fails to provide a use indemnity, thereby violating (so it is
alleged)
an accused’s right against self-incrimination.
26.
The court also does not recall UZANI
arguing in relation to sentence that BPSA was adopting SLAPP tactics.
It may have argued that
BPSA’s strategy, particularly in
relation to the production of documents or the failure to do so, was
delaying and debilitating
the prosecution.
27.
The court does not have a transcript of the
arguments and accepts that it may be in error.
28.
Finally, if the grounds of appeal had been
confined;
a.
on BPSA’s behalf to non-compliance
with s 33(2) of NEMA read with s 8 of the CPA, this court would
not have granted
leave.
This
is for the additional reason that it is for the accused to show that,
if there had been any defect in the notification, the
prosecuting
authority would have itself prosecuted. Moreover the requirement of
enabling a private prosecution through the Judge
President of the
Division granting leave for the private prosecution would also have
to be undone, even if the decision of the
Judge President was
determined on a
prima facie
basis. The defence may also at best amount to a
dilatory defence. This is because there would first have to be
confirmation from
the prosecuting authority that it wished to
prosecute and secondly it would have to give an undertaking to do so
within a reasonable
time, failing which the private prosecution can
continue (if the object and purpose of the Act was to be given
meaning and effect);
b.
on BPSA’s behalf to contending that
UZANI had not instituted the prosecution in the public interest or in
the interest of
protecting the environment, this court would not have
granted leave to appeal.
In addition to the
grounds set out in the judgment, the evidence presented during the
subsequent s 34(3) enquiry and sentencing
phases revealed an abject
failure by the authorities to comply with their statutory
obligations, even when granting the s 24G applications.
In the result, in order
to ensure that environmental legislation served its intended objects,
a purposive approach is required
so as to enable civil society
organisations to secure the environmental rights guaranteed to
present and future generations under
s 24 of the Constution in cases
where both the authorities charged with securing compliance
with the very legislation enacted
pursuant to the provisions of s 24
and the prosecuting authority fail to do so;
c.
on UZANI’s behalf to contending that
s 34B is not limited to informers.
Aside
from the reasoning given in its judgement on sentencing, the
court cannot legislate for Parliament and intrude on the
separation
of powers. It will require Parliament to replace the references to an
informant if it’s intention was to enable
a civil society
organisation to obtain an award in terms of s 34B of NEMA or to make
separate provision for compensating organisations
which
prosecuted in the public interest or in the interest of protecting
the environment out of monies which otherwise would not
have been
received by the
fiscus
.
ORDER
29.
The court therefore confirms that it made
an order on 6 August 2025 granting BPSA leave to appeal on conviction
and sentence and
granted UZANI leave to cross-appeal on sentence,
such appeals being to the Supreme Court of Appeal.
30.
The ordinary limitations in the grant of
such leave apply, being the basic grounds as identified and relied on
in the respective
notices for leave to appeal and cross-appeal, are
set out as follows:
A.
The accused is granted leave to appeal to the Supreme Court of Appeal
on the conviction of
the 17 counts and the sentence imposed on the
following grounds:
1.
Whether
s 33(2)
of
the
National Environmental Management Act 107 of 1998
(“
NEMA
“)
as read with s 8 of the Criminal Procedure Act had
been complied with;
2.
Whether s 33(1) of NEMA had been complied
with, the accused contending that the private prosecutor had not
proven that prosecution
was instituted in the public intertest
or in the interests of protecting the environment;
3.
Whether the s 24G applications submitted by
BPSA were admissible as evidence in that BPSA contends that they
violated its right
against self-incrimination, absent forewarning
that evidence of the commission of the offences contained in the
applications
may be used against it in criminal proceedings or absent
of any use indemnity in s 24G or the s 24G process;
4.
Whether an enquiry under s 34(3) of NEMA
was competent having regard to the legislation prevailing at the
relevant time in relation
to the charges upon which BPSA was
convicted;
5.
Whether the sentence imposed was based on
misdirections, a failure to take relevant considerations into account
or to afford them
sufficient weight and whether the sentence was
disproportionate in the circumstances and created a sense of shock.
B.
The private prosecution is granted leave to cross-appeal to the SCA
on the sentence imposed
on the following grounds:
1.
Whether the court failed to impose an
adequate fine having regard to the factors set out under the heading
“
ad fines imposed on the accused
”
and “
BP’s
use of SLAPP and Stalingrad-inspired strategy …”
;
2.
Whether the court erred in its legal
interpretation of s29(4) of ECA read with item 1(c) of GN R1182 of 5
September 1997, contending
further that the court had failed to apply
the SCA decision of
Fuel Retailers
Association
which was binding on it;
3.
Whether the court erred in its
interpretation of s 34B of NEMA.
C.
The costs to be awarded, if any, to the accused or to the private
prosecutor in relation to their
respective applications for leave to
appeal to be determined by the SCA.
SPILG J
DATES OF HEARING :
6 August 2025
DATE OF JUDGMENT:
3 November 2025
FOR PROSECUTION:
Attorney G Erasmus
FVS Attorneys,
Pretoria
FOR ACCUSED:
Adv B Roux SC
Adv AC McKenzie
Warburton Attorneys
[1]
For example
Uzani
Environmental Advocacy CC v BP Southern Africa (Pty) Ltd
[2017] ZAGPPHC 749 (14 November 2017)
sino noindex
make_database footer start
Similar Cases
Uzani Environmental Advocacy CC v BP Southern Africa (Pty) Ltd (Costs) (CC 82/2017) [2025] ZAGPPHC 263 (20 March 2025)
[2025] ZAGPPHC 263High Court of South Africa (Gauteng Division, Pretoria)100% similar
Uzani Environmental Advocacy CC v BP Southern Africa (Pty) Ltd (Sentence) (CC 82/2017) [2024] ZAGPPHC 1387 (6 September 2024)
[2024] ZAGPPHC 1387High Court of South Africa (Gauteng Division, Pretoria)100% similar
Uys N.O. and Others v National Credit Regulator and Another (A58/2021) [2023] ZAGPPHC 651 (10 August 2023)
[2023] ZAGPPHC 651High Court of South Africa (Gauteng Division, Pretoria)98% similar
Minister of Environmental Affairs v Trustees for the time being of the Groundwork Trust and Another [2023] ZAGPPHC 213; 39724/2019 (20 March 2023)
[2023] ZAGPPHC 213High Court of South Africa (Gauteng Division, Pretoria)98% similar
Ndziba N.O and Others v ABSA Bank Limited (Leave to Appeal) (13189/2014) [2025] ZAGPPHC 123 (14 February 2025)
[2025] ZAGPPHC 123High Court of South Africa (Gauteng Division, Pretoria)98% similar