Case Law[2024] ZAGPPHC 111South Africa
South Africa Post Office SOC Limited v Koninklijke and Another (33460/2020) [2024] ZAGPPHC 111 (13 February 2024)
High Court of South Africa (Gauteng Division, Pretoria)
13 February 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 111
|
Noteup
|
LawCite
sino index
## South Africa Post Office SOC Limited v Koninklijke and Another (33460/2020) [2024] ZAGPPHC 111 (13 February 2024)
South Africa Post Office SOC Limited v Koninklijke and Another (33460/2020) [2024] ZAGPPHC 111 (13 February 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_111.html
sino date 13 February 2024
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
CASE NO: 33460/2020
(1)
REPORTABLE: YES/NO
(2)
OF INTEREST TO OTHER JUDGES: YES/NO
3.
REVISED.
DATE:
13/02/2024
In the matter between:
SOUTH AFRICA POST
OFFICE SOC LIMITED
APPLICANT
and
KONINKLIJKE JOH.
ENSCHEDE B.V
1ST RESPONDENT
JOHAN FREDERICK VAN
WYK
2ND RESPONDENT
This
judgment was handed down electronically by circulation to the
parties’
representatives
by email. The date and time of hand-down is deemed to be 12
February
2024
JUDGMENT
#
# Khumalo N V J
Khumalo N V J
# Introduction
Introduction
[1] This
is a review application in which the Applicant, the South African
Post Office SOC Limited
(SAPO) seeks the following relief:
[1.1] Condonation
for the late launching of this review application;
[1.2] That the
decision of 2nd Respondent taken on 20 January 2014 to procure 4
(four million souvenir commemorative
folders being stamps depicting
the late former President Nelson Mandela ("folders ) from first
Respondent be declared invalid,
reviewed and set aside;
[1.3] That the
agreement entered into between the Applicant and 1st Respondent to
procure 4 (four) million folders be
declared void ab initio;
[1.4] That
the 1st Respondent be ordered to repay an amount of € 743
270.40 (seven hundred and
forty three thousand, two hundred and seventy euros) to the
Applicant;
[1.5] That
it be declared that the Applicant is not liable to pay the 1st
Respondent an amount of €
869 729-60;
[1.6] Costs
including costs of two counsel.
# Parties
Parties
[2] The
Applicant is the South African Post Office SOC Limited (SAPO), a
state owned company duly registered
in terms of the repealed Post
Office Act 44 of 1958 and continues to exist in terms of section 3 of
the South African Post Office
SOC Limited Act 22 of 2011, read with
the Companies Act 71 of 2008 (the
Companies Act) and
a major public
entity listed under Schedule 2 of the
Public Finance Management Act 1
of 1999
. For convenience henceforth referred to as “SAPO.”
[3] The
1st Respondent is Koninklijke Joh. Enschede BV (Enschede), a private
limited company pursuant
to the two-tier company's Article of
Association, registered in terms of the laws of the Kingdom of the
Netherlands and situated
in the Netherlands. The 2nd Respondent,
Johan Frederick Van Wyk (Van Wyk) is a former employee of SAPO and at
the time of the conclusion
of the impugned agreement was a Senior
Manager in the Philately section of SAPO. The 2nd Respondent does not
oppose this application.
[4] For
the sake of convenience the 1st Respondent Koninklijke Joh. Enschede
BV is henceforth referred
to as “Enschede” and the 2nd
Respondent as “Van Wyk.”
# Background facts
Background facts
[5] The
review is a reactive challenge to action proceedings instituted by
Enschede on 29 October 2015
claiming from SAPO damages in the amounts
of €743 270-40 and €869 729.60 for claim 1 and claim 2
respectively, on the
basis of an alleged breach of the impugned
agreement for the sale by Enschede of 4 million souvenir
commemorative folders depicting
the late former President of South
Africa, Mr Nelson Mandela (“Madiba folders”) to SAPO. The
claims were for the balance
or outstanding amount in respect of the 1
843 200 (one million eight hundred and forty three thousand, two
hundred) folders delivered
to SAPO. It is common cause that SAPO paid
for this delivery. The second claim is for 2 156 800 (two million one
hundred and fifty
six thousand eight hundred) folders which are
alleged to have been manufactured but not delivered. The amounts make
out the full
purchase price of the 4 million folders.
[6] SAPO
launched the review application subsequent to the proceedings in the
trial action being adjourned
for that purpose, alleging that it has
since been established that the impugned agreement which is the basis
of Enschede’s
claims was concluded under irregular
circumstances and in direct contravention of, inter alia section 217
of the Constitution of
the Republic of South Africa, 1996 ("the
Constitution") without a competitive procurement process or
request for proposal
process as required by SAPO’s Supply Chain
Management (“SCM”) and other policies. SAPO consequently
brought this
collateral review to declare the decision to procure the
million folders invalid and to be set aside and the resultant
agreement
entered into between SAPO and Enschede void ab initio.
SAPO, as a result claims a refund of the payment it made on the
partial
delivery of the order and an order that it is not obliged to
pay Enschede the remainder of the claim.
[7] SAPO
also seeks condonation for the delay in launching the application.
[8] The
interaction between the two started when SAPO’s Potgieter
firstly sought to obtain one
(1) million souvenir commemorative
folders from Enschede by sending a Request for a Quotation (“RFQ)
on 6 December 2013.
The tender was carried out by Mr Van Wyk. On 12
December 2013, Van Wyk sent a memorandum to Mr. Christopher Hlekane
(Hlekane) SAPO’s
previous Group Chief Operating Officer (GCEO)
in which he sought to deviate from the procurement policy and or the
SCM procurement
procedures by raising some kind of emergency or
urgent need for the 1 million Madiba folders. He stated that a
million folders
were to be delivered less than two months on 11
February 2014 which was the anniversary of Madiba’s release
from prison.
The procurement of the 1 million Madiba folders is not
in dispute but serves to give an understanding of the matter.
[9] In
addition, Van Wyk stated that the Madiba folders would have to be
imported from foreign suppliers
in view of quality and cost
considerations. He had sent the Request for Quote (RFQ) to several
suppliers and from the responses
he received, Enschede’s quote
was the best of all the potential suppliers. Van Wyk therefore asked
for the authorisation
to appoint Enschede as manufacturer of a
million folders.
[10] Hlekane
granted the request for one million folders on 17 February 2014.
Enschede agreed to produce
and deliver a million folders to SAPO.
There were delays in the delivery and in the same way, SAPO also
faced challenges with respect
to ensuring a complete purchase price.
The parties however agreed that there was full and adequate
performance of all obligations
in terms of the agreement by both
parties. The legitimacy and validity of that procurement process is
not challenged and all the
material facts pertaining to the
procurement process are seemingly common cause.
[11] It
is also common cause that while Enschede was in the process of
producing the 1 million folders
SAPO requested Enschede to produce an
additional 4 million Madiba folders. The procurement procedure for
the additional 4 million
folders is the main reason SAPO launched a
collateral review application. In particular, the parties are at odds
as to the validity
of that procurement and resultant agreement. It is
also of importance to mention that a dispute also arose with regard
to whether
SAPO received the first part of the 4 (four) million
folders and therefore was obliged to pay for them. SAPO is also
applying for
a refund of the amount paid for the partial delivery.
# Validity of procurement
Validity of procurement
SAPO’s
submission
[12] SAPO
pointed out that, in order to acquire an additional 4 million copies
of Madiba folders, Van
Wyk and his colleague C Mooi presented a
proposal to the Executive Committee of SAPO (EXCO) on 20 January
2014. The EXCO gave provisional
approval to this proposal at its
meeting on 20 January 2014. The approval was subject to the following
conditions, firstly that
consideration ought to be given to the
procurement of a quality of folders at a price of R50 per folder,
that Van Wyk proposal
should be revised and presented to EXCO for
consideration and that Van Wyk should address in the final submission
to the EXCO the
endorsement of the initiative by the Nelson Mandela
Foundation. In essence, Van Wyk was to return to EXCO with a revised
proposal
or submission for final approval. However, Van Wyk acquired
4 million folders from Enschede despite not obtaining a final
approval.
Van Wyk acted without an empowered decision or
authorisation to do so and as a result, he had no delegated powers or
mandate.
[13] It
does not really matter whether Van Wyk may have considered, or even
confused the preliminary
or conditional approval by EXCO, final or
without conditions. EXCO simply did not have the required authority.
Van Wyk, as the
senior manager and long-serving employee of SAPO knew
this, alternatively ought to have known this. Van Wyk subsequently
resigned
on 5 March 2015. According to his resignation note, he had
been employed by SAPO for 36 years at the time of his resignation.
[14] SAPO
further refers to an email sent to Van Wyk by Philips, the SAPO Chief
Audit Executive Officer
expressing concerns regarding the purchase of
four million folders, in order to give a clear picture that the
procurement was contrary
to SAPO policies, lack of consent including
the absence of a formal agreement. Phillips discouraged such a sale,
seeing also the
cash constraints. Van Wyk brushed aside the serious
concerns raised by Philips and incorrectly asserted that the
procurement of
additional 4 million folders was approved by EXCO,
when it actually was provisionally approved.
[15] Enschede
was aware that a quote or bid was necessary for the supply of the 4
(four) million folders.
It had previously complied with this
requirement for the supply of the 1 (one) million folders. Therefore,
it ought not to have
agreed to supply the folders before submission
and acceptance of its bid or quote for the supply of the 4 (four)
million folders.
Enschede only submitted its quote in response to RFQ
on 27 January 2014 (FAl1) after it has already undertaken the
production of
the 4 (four) million folders.
[16] In
addition SAPO’s Group Executive Borotho Moalosi (Borotho)
warned Enschede in a letter
dated 26 February 2014, to first obtain
SAPO’s official or quoted order number before production of
additional folders. He,
on behalf of SAPO re- affirmed the fact that
the production of any additional folders should only be on receipt of
an official
order from SAPO. Borotho warned that any production done
by Enschede without an official order number will be done "at
Enschede’s
own sole risk." There was no response.
[17] Enschede
disregarded the letter and instead sent two invoices to Borotho and
Van Wyk. The first
invoice was for the first order of 1 million
folders and the second order of 4 million folders. But the issuance
of the purchase
orders did not comply with SAPO policies as Borotho,
even as GE: Supply Chain, did not have the necessary authority for
this transaction
which in terms of the delegation of authority could
only be approved by the SAPO Board. In that context, in so far as
Enschede
was warned not to make or supply any additional folders
which did not have a SAPO order number, Enschede should bear the
consequences.
The agreement was concluded under irregular
circumstances and policies and in direct contravention of inter alia,
s 217
[1]
of the Constitution of
the Republic of South Africa 1996 (“the Constitution”)
with no competitive procurement process
or request for proposal
process as is required by its supply chain management. The
procurement constitutes an irregular and fruitless
expenditure
because it was not a necessity for SAPO. Additionally, SAPO denies
that it received the folders from Enschede as a
result argue that it
should not be ordered to pay anything.
[18] In
addition SAPO submits that the abovementioned activities by Van Wyk,
his team and Borotho actually
bore the hallmarks of a procurement
'process that, apart from offending SAPO policies, does not appear
fair, equitable, transparent,
competitive and cost effective, as
envisaged in section 217 of the Constitution.
[19] Furthermore,
the RFQ sent by Enschede to manufacture the 4 million folders
amounted to €1
613 000 (one million six hundred and thirteen
thousand euros) which was equivalent to an amount between R23 531
573, 10 and R24
728 419 around 31 March 2014. In terms of SOPA's
delegations of authority contracts of above R20 million are only
authorised by
the Board of Directors. As a result, the appropriate
level of approval or authority for approval for the procurement of
the 4 (four)
million folders was the Board.
[20] In
addition, SOPA points out that in a post facto attempt to correct his
mistake and despite the
contractual commitments already made to
Enschede, on 04 February 2014, Van Wyk wrote a memorandum to Hlekane,
the then SAPO's Group
Chief Executice Officer, recommending, inter
alia, that four (4) million folders be purchased to increase the
total number of folders
to five (5) million. The recommendation or
the action plan in the memorandum was signed by Bernard Leeuw
(without indicating whether
he recommended or not recommended same);
supported by Mzozoyana and approved by Hlekane. It is significant
that in the memorandum
Van Wyk did not disclose to Hlekane or the
other persons who supported and/or approved the recommendation that
he had already instructed
Enschede to supply the additional 4 (four)
million folders. In fact, in the memorandum, Van Wyk gave an
impression that the 4 (four)
million folders have not yet been
ordered when this was clearly not the case, including when he stated:
"We would like to
recommend that an additional four million
folders be purchased to increase the total number of folders to five
million.”
[21] Accordingly
SOPA’ argued that whether the memorandum or action plan is
supported by Hlekane
and his colleagues is immaterial. The
appropriate approval level or authority was SAPO's Board in terms of
the delegations of authority,
and there was no approval by the Board.
[22] SAPO
proffers that as a just and equitable remedy, the Court should
declare that Enschede repay
SAPO an amount of €742 270.40 (money
paid for folders received), and that applicant is not liable to pay
Enschede an amount
of €869 729.60, or any portion thereof, as
claimed by Enschede.
On Condonation
[23] SAPO
detailed the sequence of events leading to its late launch of the
review application, to
explain the delay before the court.
Accordingly, that the procurement of 4 million folders took place in
the months from January
to about May 2014. In November 2015, Enschede
issued summons in the action proceedings. It was only on 22 September
2017 after
SAPO’s attorneys had, at the behest of Nemukongwe, a
manager in SAPO’s legal Services, handling the matter at the
time,
consulted with SAPO’s employees, Potgieter and Rapetswa,
in preparation for trial that SAPO decided to bring the reactive
review. Nemukongwe had taken over after Mofokeng left in March 2017
following also the departure of Borotho in January 2017. The
consultation had shed more light on the procurement process for the
additional folders. Potgieter had been involved in both procurement
processes for the 1 (one million and 4 (four) million folders.
[24] The
trial was therefore, on 20 October 2017 postponed at the instance of
SAPO’s request
that the action be stayed pending the
determination of its reactive challenge. SAPO had first amended its
Plea to add a Special
Plea to reflect and to plead its correct
position. One of the defences raised by SAPO in the amended Plea was
that the conclusion
of the purported agreement contravened section
217(1) of the Constitution, the PFMA and SAPO'S SCM policy and that
it intends to
file a judicial review to set aside the resultant
contract with Enschede. The plea for an immediate challenge being a
dilatory
one.
[25] In
June 2018 Nemukongwe also left the employ of SAPO and the matter was
reassigned to Johan Naude
(Naude), SAPO's Senior Manager: Legal
Services. SAPO claims the reassignment contributed to the delay in
bringing this review and
its attorneys had to apprise Naude on the
facts of the matter in order for him to make an informed decision
regarding the institution
or decision to initiate the review, as
envisaged in the amended plea.
[26] The
instruction to Counsel on the review application was issued on 24
February 2020 following
a practice directive handed out in terms of
the Uniform Rules of the Honourable Court on 6 February 2020. It
follows that a period
of 34 months elapsed since the realisation and
launching of the review on 28 July 2020, taking into account the time
when SAPO
first received the information required to be reviewed
during the consultations held on 22 September 2017.
[27] SAPO
pointed out that the high turnover of workers, particularly in the
corporate units concerned
by the decision at issue, was also a
problem for SAPO. Van Wyk, for example, stepped down on 5 March 2015,
Borotho in January 2017,
Mofokeng in March 2017, Nemukongwe in June
2018..
[28]
During this period of 34 months, they were also activities like the
onset of
Covid 19 pandemics between March and July 2020. SAPO further
submits that challenges of a financial nature on its part also
significantly
contributed to the delay in bringing this review,
competing with other priorities.
[29] According
to SAPO save for 28 February and 20 March 2020 which were set as time
frames by Potterill
ADJP’s directive within which SAPO was to
take senior counsel’s advice and bring this review, Enschede
was never impeded
to proceed with its action proceedings in terms of
the Uniform Rules of Court. SAPOs defence of a reactive review did
not deter
Enschede from proceeding in accordance with the rules and
practices of the court. SAPO attorneys after obtaining an opinion
from
legal counsel confirming prospects of success, briefed senior
counsel on 24 February 2020 to proceed with the review application.
[30] The
consultation took place on 13 March 2020 when it became evident that
further documents were
required. Counsels were furnished with the
documents on 18 and 24 March 2020 respectively. The onset of Covid 19
delayed the finalisation
of the Application. The Supporting Affidavit
was eventually signed by Mr Nongogo on 25 June 2020.
[31] In
addition, SAPO points out that its mandate to distribute social
security grants on behalf of
the South African Social Security Agency
or SASSA was enlarged by the additional grants or transactions
announced by the President
of South Africa Mr Ramaphosa as part of
alleviation of the socio-economic impact arising from measures
imposed to combat COVID-I9.
From mid-March 2020 SAPO, particularly
the Acting Group Chief Executive Officer, became inundated with tasks
for ensuring distribution
of the social security.
[32] It
therefore considers that the explanation given in respect of the
delay, and the circumstances
under which it was delayed, are
sufficient.
Enschede
submissions
[33] Enschede
submits that it has produced 1 million folders, in accordance with
SAPO’s request.
The first part of 1 million folders was
received by SAPO and subsequently distributed to various branches for
sale and consumption
at a profit. Similarly, it disputes the
allegation that the procurement of the additional folders had to
follow another procurement
procedure. The request for the production
of an additional 4 million folders was not followed by a new contract
that is substantially
different from its initial one, it only
entailed the manufacture of additional folders in accordance with
SAPO’s earlier
acceptance of proper tender to produce 1 million
folders. There was no other competitor in an open and unrestricted
market that
had the capacity to manufacture another 4 million folders
at similarly high levels of quality with a better price and time.
Enschede
acceded to SAPO’s request, as it was willing and able
to manufacture the additional 4 (four) million folders.
[34] Moreover,
the SAPO Board agreed to buy an additional four million folders. This
is because none
of the key officials negated or challenged Philips’
emails specifically querying the process on lack of authority. For
example,
Enschede submits that, in the interim report dated 30
January 2014, in which Philips, SAPO’s Chief Audit Executive
asserts
unambiguously and unequivocally that “approval was
provided by SAPO’s Board of Directors for the total amount of 5
million folders to be sold @R50 each,” Hlekane and Mzozoyana,
the Chief Financial Officer, were both copied in the email,
including
Kotsi the Executive: Main Business and they did not negate or object
to the email. Hence, Enschede contends that Hlekane
and Mzozoyana’s
failure to object to the emails as members of the Executive Board of
SAPO at the time when this agreement
was concluded shows that the
Board was in agreement with the procurement of additional folders.
Phillips furthermore on 19 February
2024 addressed an e mail to Van
Wyk and Kotsi referring to internal audit raising serious concerns
specifically with the acquisition
of the 5 million folders.
Nevertheless, there is consequently no basis on which SAPO can deny
the existence of a valid agreement.
[35] There
is further reference by Enschede to emails by Business Manager Keswa
SAPO’s Manager:
Business Development - Philately that were sent
with a sense of urgency to Ravenzwaaii, copying Potgieter stating
that: "l
have just spoken to Paul Potgieter, yes you can go
ahead and prepare to print an additional 4 million stamps. On 24
January 2014,
Van Wyk sent an email to Ravenzwaaij and Keswa, copying
Potgieter, confirming Keswa's request to proceed with the printing of
an
additional 4 (four) million folders.
[36] Additionally,
Enschede submits that it dealt with SAPO in good faith. There is no
way it could
have presumed equivocally that SAPO did not comply with
all the formal and procedural requirements in terms of the relevant
company
laws, its memorandum of incorporation and any rules or
policies of SAPO. It received purchase orders by means of a screen
print
not the actual signed orders. The purchase order numbers were
450035646, 4500356647, 4500356648, 4500356649.
[37] Furthermore
Enschede manufactured the folders after receiving the screen print
purchase orders
because of the risk of being liable for breach of
contract had it not manufactured and supplied folders after they were
provided
with a purchase order number. The first and second batch of
folders were delivered as agreed, but no payments were made. As a
result,
Enschede had to take the stance that it would not ship the
third consignment before payment for the first consignment was made
which was conveyed to applicant on 29 December 2014. It did not
deliver the third batch and instituted an action to recover the
payments. On 30 March 2016, Potgieter sent an email wherein he
confirmed the first and second delivery and that applicant's purchase
orders are with applicant's Credit Officer. A special note is made to
the fact that the summary indicated that the orders were
"PROCESSED
ON SAP.” Eventually, SAPO made the two payments on 5 May 2016
and 22 August 2016 whilst the proceedings were
pending.
[38] Enschede
points out that there is no dispute that purchase order numbers
4500356646, 4500356647,
4500356648 and 4500356649 were delivered to
the applicant. There can be no basis for a refund, the applicant
received the mentioned
orders and even sold same to the general
public.
[39] |n
the event that the review is upheld, Enschede submits that a just and
equitable remedy is to
order that the invalidity of the agreement
will not have the effect of divesting Enschede of its rights which,
but for the declaration
of invalidity, it is entitled to.
[40] They
submit that Enschede has produced and delivered the folders in
accordance with the contract
for which the expenditure and the hired
labour were incurred. Enschede will suffer directly from a loss of
income if it is not
granted the accrued rights. Whilst SAPO will
suffer no prejudice as it has received and sold the folders. However,
if a court grants
the relief sought, SAPO will be exempted from
paying for the folders received whilst still making money on them.
This could have
an unduly beneficial effect. They have also made it
clear that the delay in delivery is not worth taking into account.
Enschede on
Condonation
[41] Enschede
claims that because SAPO knew they had a baseless and unmeritorious
defence, it failed
to submit the review application on time. Only for
the purpose of seeking an exemption from liability they decided to
seek review
at this stage. The explanation that the collateral review
had not yet crossed the applicant's mind during the Summary Judgment
stage falls short on merit and is nothing but an attempt to raise an
ill-founded excuse to the inordinate delay.
[42] Further,
Borotho, on advice of Mofokeng from SAPO’s Legal Services
Department and SAPO’s
attorneys, deposed to an Affidavit
resisting Summary Judgment Application stating that the information
and documentation that were
included in his affidavit were not made
available to SAPO's attorneys for inclusion in the answering
affidavit even on the drafting
of a plea delivered on behalf of SAPO.
Even at that stage the idea of institution of this collateral
judicial review had not yet
crossed the collective mind of SAPO which
was only to be a few years later. But in its plea filed on 20 June
2016 it indicated
that: "The information used to draft the plea
was essentially the same as what was available when resisting summary
judgment.”
Enschede refers to passages in the resisting
Affidavit where Borotho has under the
‘
heading
RESPONDENT'S SUPPLY CHAIN MANAGEMENT LANDSCAPE), 'ISSUES AND FACTORS
THAT ARE RELEVANT TO THE PROCUREMENT ACTIVITIES OF
THE RESPONDENT...',) made
submissions addressing SAPO’s alleged concerns as to the
procurement process. It argues that on
SAPO’s own version, as
far back as 22 January 2016, Borotho had already addressed the
alleged concerns. Enschede allege that
SAPO did not pursue that
aspect because it was aware that it is a baseless and unmeritorious
defence to escape liability.
[43] Enschede
argues that SAPO relies on the resignation of its officials as one of
the explanations
for the delay to bring the review application.
However, Borotho and Mofokeng had together communicated with SAPO's
lawyers prior
to their resignation. In addition, from 12 November
2015, Mofokeng is said to have been working on this issue for 28
months prior
to his resignation. Lufuno Nemukongwe was appointed as a
substitute when Mofokeng left office in March 2017. For eight months,
Nemukongwe worked on SAPO’s behalf conducting an internal
investigation to identify potential witnesses.
[44] Furthermore,
Enschede maintains that, on 22 September 2017, SAPO engaged in
consultations with
Potgieter and Rapetswa. In addition, they submit
that SAPO commenced its investigation on 25 June 2018. Similarly, it
submits that
it is apparent from this delay that SAPO must have
intended to proceed with its request for a review. Only after
Enschede had secured
a judicial case management meeting forcing SAPO
to take action whilst failing to comply with the stipulated time
periods within
which it had to file its papers, did SAPO issue its
review which evidences a total disregard of the rules and directives
of the
court.
[45] Enschede
further submit that SAPO is acting opportunistically by arguing that
high turnover has
made it difficult for them to launch the review
Application. Consequently, Enschede submits that SAPO has failed to
provide an
explanation as to why it did not initiate the review
procedure from 22 September 2017. They further claim that if the
relief sought
by SAPO is granted it would result in a prejudice on
the part of the Enschede more than SAPO.
SAPO’s REPLY
[46] SAPO
pointed out in its reply that what is referred to by Potgieter as an
approval by the board
is reference to the EXCO resolution of 20
January 2014 when Van Wyk was told to revise his proposal for further
consideration which
was approved conditionally.
[47] SAPO
also points out that the procurement of 1 million folders and that of
4 million folders may
on the face of it seem to follow the same
process but denies the parallel procurement process suggested by
Enschede. It submits
that due to the monetary value of the
procurement of 4 million folders SAPO required a resolution of the
Board, and there is a
certain policy and process required for urgent
procurement, failing of which, the process is flawed.
# Issues to be determined.
Issues to be determined.
#
# (a)
Whether the applicants should be granted condonation for the
delay in
instituting the review application.
(a)
Whether the applicants should be granted condonation for the
delay in
instituting the review application.
(b)
Whether the procurement of 4 million folders was invalid and
not in
accordance with SAPO’s procurement policies.
(c)
If not, the correct order to be issued
# On Condonation Legal
framework
On Condonation Legal
framework
[48] In
Associated
Institutions Pension Fund v Van Zyl
,
[2]
the court made it clear that:
[46]
“
It
is a longstanding rule that courts have the power, as part of their
inherent jurisdiction to regulate their own proceedings,
to refuse a
review application if the aggrieved party had been guilty of
unreasonable delay in initiating the proceedings. The
effect is that,
in a sense, delay would "validate" the invalid
administrative action (see eg Oudekraal Estates (Pty)
Ltd v City of
Cape Town and others
[2004] 3 All SA 1
(SCA) at 10b–d paragraph
[27]). The raison d'être of the rule is said to be twofold.
First, the failure to bring a
review within a reasonable time may
cause prejudice to the respondent. Second, there is a public interest
element in the finality
of administrative decisions and the exercise
of administrative functions (see eg Wolgroeiers Afslaers (Edms) Bpk v
Munisipaliteit
van Kaapstad
1978 (1) SA 13
(A) at 41).
[47] The
scope and content of the rule has been the subject of investigation
in two decisions of this
Court. They are the Wolgroeiers case and
Setsokosane Busdiens (Edms) Bpk v Voorsitter, Nasionale
Vervoerkommissie en 'n ander
1986 (2) SA 57
(A). As appears from
these two cases and the numerous decisions in which they have been
followed, application of the rule requires
consideration of two
questions:
(a)
‘
Was
there an unreasonable delay?
(b) If
so, should the delay in all the circumstances be condoned?”.
[3]
[49] The
first question on unreasonable delay has the same meaning as a value
judgment, but it also
calls for an investigation of facts. The
exercise of judicial discretion also comes into play in the other
question. The facts
and circumstances of the specific case must, of
course, be taken into account when answering both questions.
[4]
# Unreasonable delay
Unreasonable delay
[50] In
Department
of Transport v Tasima
(
Pty
)
Limited
(Tasima I),
[5]
the
court held that when an applicant seeks condonation for delay, a full
explanation that covers the “entire period”
must be
provided…The onus is thus on the Department to explain why the
delay of some five years was not unreasonable or
undue
.
[6]
Further,
the court in the matter of
Associated
Institutions Pension Fund supra,
[7]
said
that:
“
The
reasonableness or unreasonableness of a delay is entirely dependent
on the facts and circumstances of any particular case. The
investigation into the reasonableness of the delay has nothing to do
with the Court’s discretion. It is an investigation
into the
facts of the matter in order to determine whether, in all the
circumstances of that case, the delay was reasonable. Though
this
question does imply a value judgment it is not to be equated with the
judicial discretion involved in the next question, if
it arises,
namely, whether a delay which has been found to be unreasonable,
should be condoned.”
[8]
[51]
Gqwetha
v Transkei Development Corporations Ltd and others,
[9]
adds
that “whether there has been undue delay entails a factual
enquiry upon which a value
judgment
is called for in the light of all the relevant circumstances
including any explanation that is offered for the delay
.
A
material fact to be taken into account in making that value judgment
bearing in mind the rationale for the rule is the nature
of the
challenged decision. Not all decisions have the same potential for
prejudice to result from their being set aside”.
[10]
Simply, a delay cannot be evaluated in a vacuum but only relative to
the challenged decision, and particularly with the potential
for
prejudice in mind.
[11]
In
addition, the reasonableness of the delay, must be assessed on, among
others, the explanation offered for the delay. Where the
delay can be
explained and justified, then it is reasonable, and the merits of the
review can be considered. If there is an explanation
for the delay,
the explanation must cover the entirety of the delay.
[12]
# Should the delay be
overlooked?
Should the delay be
overlooked?
[52]
Khumalo
v Member of the Executive Council for Education: KwaZulu Natal,
[13]
says
that courts have a “discretion to overlook a delay”. In
paragraph 45 the court said that:
“…
a
court should be slow to allow procedural obstacles to prevent it from
looking into a challenge to the lawfulness of an exercise
of public
power. But that does not mean that the Constitution has dispensed
with the basic procedural requirement that review proceedings
are to
be brought without undue delay or with a court’s discretion to
overlook a delay”.
[14]
[53] Furthermore,
in
Department
of Transport v Tasima,
[15]
the
court explained that this discretion should not be exercised lightly.
It further stated that:
“
While
a court ‘should be slow to allow procedural obstacles to
prevent it from looking into a challenge to the lawfulness
of an
exercise of public power’, it is equally a feature of the rule
of law that undue delay should not be tolerated. Delay
can prejudice
the respondent, weaken the ability of a court to consider the merits
of a review, and undermine the public interest
in bringing certainty
and finality to administrative action. A court should therefore
exhibit vigilance, consideration, and propriety
before overlooking a
late review, reactive or otherwise
[16]
[54] The
court in
Buffalo
City Metropolitan Municipality v Asla Construction,
[17]
emphasised
the fact that there must however be a basis for a court to exercise
its discretion to overlook the delay. That basis
must be gleaned from
the facts made available or objectively available factors.
[18]
Additionally the court listed a number of factors that should be
considered when deciding whether to overlook delay. The court
stated
as follows:
[54]
“
The
approach to overlooking a delay in a legality review is flexible. In
Tasima I, Khampepe J made reference to the "factual,
multi-factor, context- sensitive framework" expounded in
Khumalo. This entails a legal evaluation taking into account a number
of factors. The first of these factors is potential prejudice to
affected parties as well as the possible consequences of setting
aside the impugned decision. The potential prejudice to affected
parties and the consequences of declaring conduct unlawful may
in
certain circumstances be ameliorated by this Court's power to grant a
just and equitable remedy and this ought to be taken into
account…
[55] A
second factor relevant to overlooking delay is the nature of the
impugned decision. This, in
essence, requires a consideration of the
merits of the legal challenge against that decision…
[59] A
third factor to consider when deciding to overlook delay is the
conduct of an applicant. This is particularly
true for State
litigants seeking to review their own decisions for the simple reason
that often they are best placed to explain
the delay. This was
recognised by Skweyiya J in Khumalo:
"The
fact that the MEC has elected not to account for the delay, despite
having had the opportunity to do so at multiple stages
in the
litigation, can only lead
one
to infer that she either had no reason at all or that she was not
able to be honest as to her real reasons. Had the matter been
brought
by a private litigant, this aspect of the test might weigh less
heavily. However, given that the MEC is responsible for
the decision,
that she is obliged to act expeditiously in fulfilling her
constitutional obligations, and that she should have within
her
control the relevant resources to establish the unlawfulness of the
decision she impugns, the unreasonableness of the unexplained
delay
is serious." (Emphasis added.)
[63] The
fourth principle stems directly from Gijima. Even where there is no
basis for a court to overlook an unreasonable
delay, the court may
nevertheless be constitutionally compelled to declare the State's
conduct unlawful. This is so because "[s]ection
172(1)(a) of the
Constitution enjoins a Court to declare invalid any law or conduct
that it finds to be inconsistent with the Constitution.
[131]
…
The
delay rule should not be viewed solely through the ancestor lens of
common law review, but through our constitutional lens in
which
legality review serves to promote open, responsive, and accountable
government.
[132] This
purpose-driven approach to procedure is very different to the
formalistic notion that the
delay rule must necessarily be assessed
as a point in limine (preliminary point) that precludes any
consideration of the merits
of the review. Rather, a careful weighing
up of two different aspects of the rule of law is required when
considering whether it
is in the interests of justice to condone or
overlook a delay: the importance of declaring (and correcting)
unlawful decisions,
and the importance of expeditious and diligent
compliance with constitutional duties so as to ensure certainty and
finality for
the parties relying on such decisions.”
[19]
[55] In
the case of
SA
National Roads Agency v Cape Town City
[20]
,
it was said as follows regarding the factor relating to consideration
of merits it was stated that:
“……
.It
cannot be read to signal a clinical excision of the merits of the
impugned decision, which must be a critical factor when a
court
embarks on a consideration of all the circumstances of a case, to
determine whether the interests of justice dictate that
the delay
should be condoned. It would have to include a consideration of
whether the non-compliance with statutory prescripts
was
egregious.”
[21]
[56] In
Buffalo
City supra
,
the court
per
the
minority judgment recognised that there are instances where
the
Court’s jurisprudence, and the deep constitutional imperatives
that underlie it, provide for instances where a public
authority’s
delay in bringing “self- review”– legal proceedings
to set aside its own decision – is
so prodigiously and
lamentably inexcusable that there is no public interest or
constitutional necessity for pronouncing on its
legality. Conceding
that those cases will be rare, for, as the Court’s decisions
show, there is a constitutional imperative
to locate and declare
unconstitutional conduct invalid under the Constitution.
[22]
It would be difficult to find these instances that would justify the
perpetuation and preservation of illegality especially the
wastage of
public funds when the majority still stay in poverty. The
amelioration of prejudice should be the key factor where such
delay
stands before correction of illegality.
# Application of the law to
the facts
Application of the law to
the facts
[57] The
review application commenced in the present case 34 months after SAPO
first received the information
required to be reviewed, which was
during the consultations held on 22 September 2017. SAPO’s main
explanation for the delay
in commencing the proceedings was the high
staff turnover, with some who were implicated in the debunked
procurement process whilst
others involved in defending the legal
action instituted thereafter by Enschede, leaving at an inopportune
time, Covid 19 and financial
issues that took place. In my view,
these reasons are persuasive and were all beyond SAPO’s
control. Even if the delay is
long the sound explanation given by
SAPO makes it reasonable and therefore excusable. Thus, l am of the
view that the delay can
be overlooked and or condoned, the importance
of declaring (and correcting) unlawful decisions being imperative.
# (b): Procurement of four
million folders Legal framework
(b): Procurement of four
million folders Legal framework
[58] Section
217 (1) of the Constitution states that when an organ of state in the
national, provincial,
or local sphere of government, or any other
institution identified in national legislation, contracts for goods
or services, it
must do so in accordance with a system which is fair,
equitable, transparent, competitive, and cost-effective.
[23]
[59] Clause
5 of the Supply Chain Management Procurement Policy (“SCM”
or “Supply
Chain” )
[24]
sets out the principles that govern SAPO’s procurement process.
The clause reads as follows:
“
Transparency-
South African Post Office shall have a procurement system that is
open and fair.
Effectiveness-South
African Post Office Group shall strive for a procurement system of
excellence that delivers on the principle
of doing it right the first
time. Efficiency-South African Post Office Group shall strive to
standardise and simplify procedures
where appropriate to optimise the
process.
Competition- South
African Post Office Group shall satisfy its procurement requirements
through open competition unless there are
justifiable reasons to the
contrary.
Fairness- All bidders
and suppliers shall be dealt with fairly and without unfair
discrimination…”
[60] Further,
Clause 10.15 of the SCM outlines the instances where SAPO can procure
services without
following the protocol for procurement. The Clause
states that:
Deviations from
normal bidding process (Limited Bidding)
“
SAPO
must only deviate from inviting competitive bids in cases of
emergency and sole supplier status.
−
An
emergency procurement may occur when there is a serious and
unexpected situation that poses an immediate risk to health, life,
property, or environment which
calls
an
agency
to
action
and
there
is
insufficient
time
to
invite
competitive
bids.
−
Sole
source procurement may occur when there is evidence that only one
supplier possesses the unique and singularly available capacity
to
meet the requirements of the institution.
−
Apart
from the two scenarios above, SAPO must invite as many suppliers as
possible and select the preferred supplier using the competitive
bid
committee system.
−
Any
other deviation will be allowed in exceptional cases subject to the
prior written approval from the relevant treasury.”
[61] Clause
10.3 of the SCM sets out the procurement method for bids of different
value. This clause
sets out the procedure for bids above R1 000 000
(one million rands). The Clause is read as follows:
“
Above
R1 000 000 (Vat included)
-SAPO must invite
competitive bids through the RFP process for all procurement above R1
000 000 (Vat inclusive).
-The bids referred to
above must be advertised in the National Treasury’s e- Tender
portal or in another medium and for a
period of 21 days, except in
urgent cases when bids may be advertised for such shorter period as
the GE: SCM may approve, provided
that such shorter period must be at
least 14 days.
- If considered
necessary, GE: SCM may, in addition to the medium referred to above,
also authorise the advertising of bids in other
appropriate media to
ensure greater exposure to potential bidders”.
[62] Clause
11 of the South African Post Office and its Subsidiaries Procurement
Policy provides as
follows:
”
The
South African Post Office and its subsidiaries shall conduct its
procurement activities through open competition unless there
are
justifiable reasons to the contrary, in which case the limited
bidding. process would be followed.”
[63] In
Merifon
(Pty) Limited v Greater Letaba Municipality and another
,
[25]
the court looked at the applicability of the Turquand rule
[26]
in situations where an innocent party contracts with the other party
not knowing whether the proper internal procedures were followed.
The
court stated that:
“…
Does
the Turquand rule apply in respect of Municipalities and where
innocent third parties are involved? It is trite that void acts
cannot be resuscitated through the Turquand rule. It is also trite
that it is a species of estoppel and therefore cannot be raised
to
cure an action that is ultra vires, as opposed to one that is intra
vires (within one’s legal powers) but suffers some
other
defect. The doctrine of legality is applicable and decisively trumps
Merifon’s argument.”
[27]
[64] Enschede’s
attempt to invoke the
Turquand
rule arguing not to have been
aware of SAPO officials’ non-compliance with the procurement
procedures and to have dealt with
it in good faith is ousted by the
doctrine of legality. The invalidity cannot be cured. This does not
change the fact that the
procurement was invalid.
[65] One
of the arguments by SAPO is that the procurement of the four million
folders was not approved
by SAPO’s board of directors. However,
it does not state exactly who forms part of the Board of directors.
Specifically,
there is no evidence to ascertain whether Hlekane and
Mzozoyana constituted the Board. However, even if
Hlekane
and Mzozoyana were copied on the emails pertaining to the procurement
of the four million folders, these two officials are
part of the
Board and do not constitute the whole Board of directors in SAPO.
Moreover, as part of the Board they were not fully
appraised of the
fact that EXCO had actually provisionally approved the procurement
with certain conditions to be fulfilled prior
any final approval. As
a result, Enschede’s submissions that SAPO’s Board of
directors approved the procurement of
the additional folders is
unsustainable.
[66] SAPO
has also indicated that the written memorandum by Van Wyk to Wallis,
Mzozoyane and Hlekane
was post facto the procurement, a fact which
was also not divulged to them.
[67] It
is clear from clause 10.15 of the SCMPP that an emergency procurement
will take place at the
time when there is a real and unforeseen
situation which endangers health, life, property, or the environment
immediately requiring
action by the urgency without sufficient time
for invitation to tender. In this case there is no evidence provided
by SAPO as to
whether there was a serious and unexpected situation
that needed urgent procurement of the additional folders. It is only
alleged
that there was an expected high demand of the folders from
both local and international customers. Even if this was true, this
reason still does not suffice as an emergency situation. Moreover,
the 1 million folders had not yet been sold out when the 4 million
folders were procured.
[68] it
is furthermore clear from the wording of Clause 10.3 that the
procurement of the four million
folders violated this clause.
Enschede argued that the procurement of the additional four million
folders was an extension of the
existing contract as it was already
in the middle of supplying the million folders. It could not have
been, the additional four
million way exceeds the value of the
initial order and in terms of the procurement policy a different
process was to be followed.
It also could not be procured by
extension or as part of the 1 million folder agreement. Although
objectively, one might be attempted
to agree with Enschede, on their
allegation that why Enschede was selected to supply the first million
folders is because there
was no other supplier other than Enschede
that could provide the folders of expected quality and price. This
implies that Enschede
was still going to be selected to produce the
additional four million folders. However, it is very significant that
there was no
tender
process. Such a
conclusion pre-empts a process that was not complied with.
Furthermore, there was still no approval from the board
of directors
as argued above, a proper procurement policy not followed in that
respect as well. Consequently, the procurement is
invalid and a
declaration as such appropriate.
[69] The
next question arises as to what a just and equitable remedy in the
present case will then
be,
# Just and equitable remedy
Just and equitable remedy
Applicant’s
Submissions
[70] As
a background to the just and equitable remedy, Enschede on 29 October
2015 instituted action
proceedings against SAPO for claim 1 and 2
respectively, arising from the alleged breach of contract. Both
claims emanate from
SAPO’s procurement of four million folders
from Enschede. As regards claim 1 for an amount of €743 270.40,
Enschede
sent SAPO, 1 843 200 (one million eight hundred and forty
three thousand two hundred) folders. It is common cause that SAPO
paid
for this delivery. Claim 2 is for an amount of €869 729.
This amount is the full purchase price for 2 156 800 (two million
one
hundred and fifty six thousand eight hundred) folders which were
manufactured but not delivered.
[71] As
a just and equitable remedy, Enschede argues in respect of claim 1,
that SAPO received folders
and distributed them to its various
branches for the purpose of selling them and generating profit.
Therefore, the amount of €743
270.40 is not to be recovered by
Enschede since SAPO through its branches selling the folders
continues to make a profit, paying
that amount would unjustifiably
enrich SAPO. Further, Enschede argues that it will be fair and
reasonable on the part of SAPO to
pay the
€
869
729 for the rest of the folders it had already manufactured.
According to Enschede, if SAPO does not pay, Enschede will suffer
a
financial loss because they have spent so much money on the
production of the folders.
[72]
Contrary,
SAPO submits that because the bid was awarded to Enschede in
violation of section 217 of the Constitution, a just and
equitable
remedy will be to order Enschede to pay back to SAPO the €743
270.40 because the resultant contract was invalid.
SAPO further
claims that, it does not have to pay Eschede either as regards the
amount of €869 729.60 or in respect of any
portion claimed by
Enschede. In addition, SAPO says that Enschede should bear the
consequences because it was aware or ought to
have known that the
procurement of the four million folders was invalid.
# Applicable law
Applicable law
[73] Section
172 (1) of the Constitution reads as follows:
When deciding a
constitutional matter within its power, a court -
a. must
declare that any law or conduct that is inconsistent with the
Constitution is invalid to the
extent of its inconsistency; and
b. may
make any order that is just and equitable, including -
I. an
order limiting the retrospective effect of the declaration of
invalidity; and
II. an
order suspending the declaration of invalidity for any period and on
any conditions, to allow
the competent authority to correct the
defect.
[74] In
Buffalo
City Metropolitan Municipality
,
[28]
the Chief Financial Officer of the city of Buffalo, has then given a
contract for Reeston East Works to the Respondent. Subsequently,
the
municipality failed to pay Asla for its services in respect of a
contract with
Reeston
.
In order to recover the amount due to be paid by the municipality,
Asla brought proceedings against the municipality. The municipality
submitted that, prior to the award of the
Reeston
contract,
it was necessary to carry out a different tender and procurement
procedure. Consequently, the agreement with
Reeston
is
null and void.
[29]
The court
held that the delay in the opening of the review proceedings by the
municipality was unexplained and therefore disproportionate.
In these
circumstances, justice and equity dictate that the Municipality
should not benefit from its own undue delay and in allowing
Asla to
proceed to perform in terms of the contract. Accordingly, the
majority judgment ordered an annulment of the
Reeston
Agreement
and did not set aside it with a view to preserving Asla's rights. In
paragraph 105, the court held that:
[104]
In these circumstances, justice and equity dictate that the
Municipality should not benefit from its own undue delay and in
allowing the respondent to perform in terms of the contract. I
therefore make an order declaring the Rees ton contract invalid,
but
not setting it aside so as to preserve the rights to that the
respondent might have been entitled.
It
should be noted that such an award
preserves
rights which have already accrued but does not permit a party to
obtain further rights under the invalid agreement”.
[30]
[75] In
Special
Investigating Unit v Phomella Property Investments (Pty) Ltd and
another,
[31]
the
SIU sought an order declaring a lease agreement between the
Respondents and an organ of State to be unlawful, and for the
Respondents
to pay the Minister of Public Works an amount of R103 880
357.65 representing wasteful expenditure incurred during the lease.
As
regards the right to a just and equitable remedy, SIU argued that
it could not benefit those parties where an agreement was found
unlawful. The court rejected this argument on the basis that it was
based on an incorrect reading of the dictum of the Constitutional
Court in
Allpay
Consolidated Investment Holdings (Pty) Ltd and Others v Chief
Executive Officer, South African Social Security Agency, and
Other.
[32]
In
paragraph 18 and 19 the court held that:
[18]
“
A
careful and contextual reading of Allpay 2 thus shows that the
Constitutional Court did not hold that a party could derive no
benefit from an unlawful contract. The approach in Allpay 2 of
allowing a party to retain payments, and thus to benefit, under
an
unlawful contract has been echoed in a number of matters. One such
example is found in Buffalo City, where the majority in the
Constitutional Court held:
". . .I therefore
make an order declaring the Reeston contract invalid, but not setting
it aside so as to preserve the rights
to [which] the respondent might
have been entitled. It should be noted that such an award preserves
rights which have already accrued
but does not permit a party to
obtain further rights under the invalid agreement."
There, too, the
contractor had performed its obligations under the contract. The
Constitutional Court held that the contractor was
entitled to payment
for the work which had been done.
[19] t
must be said that the “principle” relied upon by the SIU
as set out in Mott Macdonald
is no principle at all. The same must be
said of the following dictum in Central Energy Fund.
"The
second guiding principle is the 'no-profit-no-loss' principle which
the Court articulated as follows: 'It is true that
any invalidation
of the existing contract as a result of the invalid tender should not
result in any loss to Cash Paymaster. The
converse, however, is also
true. It has no right to benefit from an unlawful contract…”
[33]
[76] Moreover,
the court in
State
Information Technology Agency Soc Limited v Gijima Holdings (Pty)
Limited,
[34]
stated
that:
[54]
“Overall, it seems to us that justice and equity dictate that,
despite the invalidity of the award of the DoD agreement,
SITA must
not benefit from having given Gijima false assurances and from its
own undue delay in instituting proceedings. Gijima
may well have
performed in terms of the contract, while SITA sat idly by and only
raised the question of the invalidity of the
contract when Gijima
instituted arbitration proceedings. In the circumstances, a just and
equitable remedy is that the award of
the contract and the subsequent
decisions to extend it be declared invalid, with a rider that the
declaration of invalidity must
not have the effect of divesting
Gijima of rights to which – but for the declaration of
invalidity – it might have
been entitled. Whether any such
rights did accrue remains a contested issue in the arbitration, the
merits of which were never
determined because of the arbitrator’s
holding on jurisdiction”.
[35]
# Conclusion
Conclusion
[77] Based
on the facts and applicable principles set out above, SAPO’s
procurement of the four
million folders from the first respondent
indeed fell short of the procurement procedures. As a result, a just
and equitable outcome
would be that both parties should not benefit
from the unlawful contract. No further obligations or rights can flow
from the void
agreement although to ameliorate any prejudice an order
rather preserving that which had already accrued but does not permit
a
party to obtain further rights under the invalid agreement would be
just and equitable.
[78] Following
on the principle espoused in these authorities on just and equitable
remedy that parties
should not benefit from an unlawful contract, it
is logical that SAPO should not benefit from the first batch of
folders delivered
by Enschede and from its own undue delay in
instituting proceedings. This implies that SAPO should not be
refunded the €743
270.40 it paid for the folders it received
from Enschede. On the other hand, Enschede should not benefit from a
contract which
was unlawfully entered into. As well even if Enschede
claims that it has suffered the financial loss producing the
outstanding
folders not yet delivered it should not receive any
payment for those folders.
Costs
[79] Both
parties have been partially successful in that the decision to
procure has been found to
be invalid, therefore reviewable and to be
set aside and the resultant contract void ab initio, however, the
payment obligation
for the delivered folders have been preserved. For
this reason, an order that there should be no order as to costs would
be reasonable.
[80] Under
the circumstances the following order is made:
1.
The Application for condonation for the late launching of the review
Application is granted;
2.
The decision of the 2nd Respondent (“Van Wyk”) taken on
20 January 2014 to procure 4 (four
million souvenir commemorative
folders being stamps depicting the late former President Nelson
Mandela ("folders) from 1st
Respondent is declared invalid,
reviewed and set aside;
3.
The agreement for the procurement of 4 Million folders entered into
between the Applicant and the 1st
Respondent is declared void ab
initio;
4.
The claim that the 1st Respondent be ordered to repay the Applicant
an amount of € 743 270.40 (seven
hundred and forty three
thousand, two hundred and seventy euros) is dismissed.
5.
The Applicant is not liable to pay the 1st Respondent an amount of
€869 729-60 for the folders allegedly
manufactured but not yet
delivered;
6.
Each party to pay its own costs.
# N V Khumalo
N V Khumalo
Judge of the High
Court Gauteng Division, Pretoria
For the
Applicant: Mr KLAM MNAMELA
Instructed
by: MANAMELA MARUBELA & ASS
khashanem@manamelainc.co.za
NyikoN@manamelainc.co.za
For the 1st
Respondent: DB DU PREEZ S C
J VORSTER
Instructed
by:
GD FICQ Attorneys
C/O MACINTOSH CROSS
FARQUHARSON
fgficq@gdficq.co.za
[1]
Provides
that organs of state when contracting for goods and services should
do so in accordance with a system that is fair, equitable,
transparent, competitive and cost –effective.
[2]
2005
(2) SA 302.
[3]
Ibid
para 46-47.
[4]
Mandela
v Executors Estate Late Mandela and others
[2016] JOL 35772
(ECM)b
para 16.
[5]
2017
(2) SA 622 (CC).
[6]
Ibid
para 153.
[7]
2005
(2) SA 302.
[8]
Ibid
para 48.
[9]
[2006]
3 All SA 245
(SCA).
[10]
Ibid
para 24.
[11]
Ibid
para 33.
[12]
Buffalo
City Metropolitan Municipality v Asla Construction
2019 (4) SA 331
(CC) para 52.
[13]
2014
(5) SA 579 (CC).
[14]
Ibid
para 45.
[15]
2017
(2) SA 622 (CC).
[16]
Ibid
para 160.
[17]
2019
(6) BCLR 661 (CC).
[18]
Ibid
para 53.
[19]
Ibid
para 53,54, 59, 63, 131 and 131
[20]
2017
(1) SA 468 (SCA).
[21]
Ibid
para 81.
[22]
Footnote
17 para 110
[23]
Section
217 (1) of the Constitution of the Republic of South Africa, 1996.
[24]
Supply
Chain Management Procurement Policy of August 2016.
[25]
2022
(9) BCLR 1090 (CC).
[26]
The
Turquand rule is a common law rule, it has been incorporated in the
Companies Act, 71 of 2008 (“the Act”). Section
20 (7) of
the Act provides that a person dealing with a company in good faith,
other than a director, prescribed officer or shareholder
of the
company, is entitled to presume that the company, in making any
decision in the exercise of its powers, has complied with
all the
formal and procedural requirements in terms of the Act, its
Memorandum of Incorporation and any rules of the company
unless, in
the circumstances, the person knew or ought to have reasonably known
of any failure by the company to comply with
such requirements.
[27]
27
Ibid para 42.
[28]
Note
8 above.
[29]
Ibid.
[30]
Ibid
para 105.
[31]
[2023]
JOL 58437 (SCA).
[32]
Allpay
Consolidated Investment Holdings (Pty) Ltd and others v Chief
Executive Officer, South African Social Security Agency and
others
2014 (4) SA 179
(CC) (Allpay 2).
[33]
Note
23 above para 18-19
[34]
.[2017]
JOL 39257 (CC).
[35]
Ibid
para 24.
sino noindex
make_database footer start
Similar Cases
South African Professional Firearms Trainers Council NPC v Quality Council for Trades and Occupations and Others (097482/2024) [2024] ZAGPPHC 1388 (2 October 2024)
[2024] ZAGPPHC 1388High Court of South Africa (Gauteng Division, Pretoria)99% similar
South African Legal Practice Council v Koma (2023/023597) [2024] ZAGPPHC 1171 (5 November 2024)
[2024] ZAGPPHC 1171High Court of South Africa (Gauteng Division, Pretoria)99% similar
South African Legal Practice Council v Segaole (2977/2021) [2024] ZAGPPHC 1239 (28 November 2024)
[2024] ZAGPPHC 1239High Court of South Africa (Gauteng Division, Pretoria)99% similar
South African Legal Practice Council v Mashigo (101522/2023) [2024] ZAGPPHC 1307 (10 December 2024)
[2024] ZAGPPHC 1307High Court of South Africa (Gauteng Division, Pretoria)99% similar
South African Legal Practice Council v Manamela (2349/2022) [2024] ZAGPPHC 1057 (22 October 2024)
[2024] ZAGPPHC 1057High Court of South Africa (Gauteng Division, Pretoria)99% similar