Case Law[2024] ZAGPPHC 425South Africa
Air Cycle Engineering CC v ATW Construction (Pty) Ltd (A211/2023) [2024] ZAGPPHC 425 (6 May 2024)
Headnotes
judgment granted by the Regional Court on 6 June 2023 in the amount of R259 752.57, together with interest and costs. The parties shall be referred to as a quo.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 425
|
Noteup
|
LawCite
sino index
## Air Cycle Engineering CC v ATW Construction (Pty) Ltd (A211/2023) [2024] ZAGPPHC 425 (6 May 2024)
Air Cycle Engineering CC v ATW Construction (Pty) Ltd (A211/2023) [2024] ZAGPPHC 425 (6 May 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_425.html
sino date 6 May 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
APPEAL CASE NO: A211/2023
COURT
A QUO
CASE
NO: PTA REGIONAL COURT-964/2022
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
6 May 2024
In
the matter between:
AIR
CYCLE ENGINEERING
CC
Appellant
(Defendant
a quo)
and
ATW
CONSTRUCTION (PTY) LTD
Respondent
(Plaintiff
a quo)
This judgment was
prepared and authored by the Judge whose name is reflected and is
handed down electronically by circulation to
the parties’ legal
representatives by e-mail and by uploading it to the electronic file
of this matter on CaseLines.
The date for hand-down is deemed
to be 6 May 2024.
JUDGMENT
HASSIM
J
1.
The appellant, the defendant in the court
a
quo
,
appeals the summary judgment granted by the Regional Court on 6 June
2023 in the amount of R259 752.57, together with interest
and
costs. The parties shall be referred to as
a
quo
.
2.
The plaintiff’s cause of action is
the
locatio conductio operis
(the
letting and hiring of work). The appeal rests on two issues,
namely whether the plaintiff’s affidavit complies
with the
requirements of rule 14(2)(b) of the Magistrates’ Court Rules
and whether the defendant has demonstrated a
bona
fide
defence to the plaintiff’s
claim.
Amendments to the
rules – Summary judgment
3.
The Magistrates’ Court rules as well
as the Uniform Rules of Court (“URC”) dealing with
summary judgments were
amended in 2020. Rule 14 of the
Magistrates’ Court Rules (which came into effect on 9 March
2020), largely mirrors
rule 32 of the URC (which came into effect on
1 July 2019). The decisions on the latter rule would hence
apply to rule 14
of the Magistrates’ Court Rules.
4.
In
Tumileng
Trading
CC
v National Security and Fire (Pty) Ltd,
[1]
Binns-Ward J held-
“
[13]
…, our procedure, …, even in its amended form, remains
true to that in which summary judgment was originally
introduced in
the English civil procedure in the mid-19th century. Rule 32(3),
which regulates what is required from a defendant
in its opposing
affidavit, has been left substantively unamended in the overhauled
procedure. That means that the test remains
what it always was: has
the defendant disclosed a bona fide (i.e. an apparently genuinely
advanced, as distinct from sham) defence?
There is no indication in
the amended rule that the method of determining that has changed. The
classical formulations in
Maharaj
and
Breitenbach v Fiat SA
as to what is expected of a defendant seeking to successfully oppose
an application for summary judgment therefore remain of application.
A defendant is not required to show that its defence is likely to
prevail. If a defendant can show that it has a legally cognisable
defence on the face of it, and that the defence is genuine or bona
fide, summary judgment must be refused. The defendant’s
prospects of success are irrelevant.”
5.
Hence,
although the requirements for an affidavit supporting summary
judgment have changed, the requirements for an affidavit resisting
summary judgment have not, nor has its purpose. The affidavit
must “disclose fully the nature and grounds of defence
and the
material facts relied upon therefor” to demonstrate that the
defendant “has a
bona
fide
defence to the action”. However, because the plaintiff’s
supporting affidavit must engage the content of the
plea,
[2]
the
defendant has to deal with the plaintiff’s averments regarding
the pleaded defence.
6.
Binns-Ward J further considered the effect
of a plea preceding an application for summary judgment. He
found –
“
[15] What
the amendment requiring an application for summary judgment to be
brought only after a plea has been delivered is
identifiably directed
at achieving, and should succeed in doing, is the avoidance of
speculative summary judgment applications.
Under the previous regime,
a plaintiff might bring the application in the genuine belief that
the defendant had entered an appearance
to defend only for the
purpose of delay, only to learn that the defendant was able to make
out a bona fide defence when the defendant’s
opposing affidavit
was delivered. …
Under
the new rule, a plaintiff would be justified in bringing an
application for summary judgment only if it were able to show
that
the pleaded defence is not bona fide; in other words, by
showing that the plea is a sham plea
.
[3]
[16] Of
primary interest …, are the changes in the stated requirements
for –
(i)
the content of the plaintiff’s supporting affidavit, and
(ii)
in relation to (i), the effect, if any, of the aforementioned changes
on what is expected of a defendant in respect
of its opposing
affidavit.”
7.
The
requirement that the plaintiff’s supporting affidavit must
“identify any point of law relied upon and state the
facts upon
which the plaintiff’s claim is based and explain briefly why
the defence as pleaded does not raise any issue for
trial”,
does not require a detailed affidavit on the merits of the
plaintiff’s pleaded claim. The requirement
that the
plaintiff must identify any point of law relied upon, would be
satisfied if the plaintiff’s pleaded claim is not
excipiable.
[4]
The
plaintiff’s supporting affidavit should explain briefly why the
pleaded defence “does not raise an issue
for trial” and
why it contends that the pleaded defence is a sham.
[5]
The plaintiff must engage with the content of the plea to
substantiate its averments that the defence is not
bona
fide
and that it has been raised merely for purposes of delay.
[6]
The pleadings -
particulars of claim
8.
The plaintiff, as the contractor, and the
defendant, as the employer, entered into a partly written partly oral
construction contract.
The plaintiff undertook to renovate
parts of an immovable property (“the property”).
The plaintiff issued a written
quotation in an amount of R278 921.93
for the work it had been requested to undertake (“
the
contract price
”).
9.
The
quotation listed the work to be done and itemised the costing, which
included, the swimming pool, the trampoline, the main bathroom,
the
children’s bathroom, the spare bathroom, and to supply
materials. It is not evident whether the plaintiff had
undertaken to supply the building material as well as materials such
as pipes, tiles, windows, and paint, to mention a few. The
particulars of claim are somewhat ambiguous but suggest that the
quotation included materials but excluded VAT.
[7]
This is supported by the purchase order which was issued by the
plaintiff after the defendant had accepted the quotation.
[8]
10.
The oral terms of the agreement pleaded by
the plaintiff were:
10.1.
The
plaintiff was appointed by the defendant as a contractor to renovate
a property situated in Queenswood, Pretoria.
[9]
10.2.
The
work listed on the quotation would be done within a reasonable time,
however the completion date depended upon additional services
rendered by the plaintiff.
[10]
10.3.
Additional
services and materials as the project progressed had to be approved
by a representative of the defendant after which
the plaintiff would
issue invoices and those invoices were immediately payable.
[11]
10.4.
Amounts
due to the plaintiff were immediately payable upon the completion of
the plaintiff’s services and the rendering of
invoices for
additional services.
[12]
11.
The plaintiff avers additionally that (i)
at the behest of the defendant’s representative, work commenced
three weeks later
than it ought to have; (ii) numerous additional
services were requested and they were discussed with, and approved
by, the defendant’s
representative; (iii) the defendant’s
representative was part of a team managing the project and was
therefore aware of the
progress on the work and the additional
services contracted for; (iv) the defendant had insisted that the
plaintiff employ sub-contractors
identified by the defendant under
circumstances where the plaintiff had not previously worked with
these subcontractors and could
not guarantee their workmanship or the
time frames within which the work would be completed.
12.
The
plaintiff pleaded that it “duly performed” the services
and supplied the material. However, when the defendant
denied
the plaintiff access to the property, the plaintiff was not able to
“finalize the services and the material to be
supplied as
agreed”.
[13]
13.
It conceded that there was in fact
outstanding work, namely the bath
, taps and
shower head
had not been fitted, and
two
square
meters
of
tiles (2m
2)
in the “maid’s room”
had not been laid. This according to
it was the extent of the outstanding work and would have been
finalised by the plaintiff
within a week.
14.
It averred that
on
3 May 2021, the defendant summarily cancelled the contract without
informing the plaintiff that it had not complied with its
obligations
and without calling on the plaintiff to remedy the non-compliance.
The cancellation was conveyed in a letter
from the defendant’s
attorney dated 3 May 2021 (Annexure “F”). Due to
the defendant’s failure to
allow the plaintiff access to the
property and its failure to comply with its obligations, the
plaintiff cancelled the contract,
in the alternative it pleaded that
in the event of a dispute, the summons constituted the cancellation.
In the premises,
the plaintiff claimed payment of R289 597.29
for services rendered including additional services and materials
supplied in
accordance with the agreement between the parties.
The defendant’s
plea and counterclaim
15.
The defendant does not dispute the written
quotation, the purchase order nor that it paid a deposit of
R138 220.43 on 11 March
2023. It however disputed that
amounts were payable to the plaintiff immediately upon the completion
of the services and
the rendering of invoices for the additional
works. Furthermore, it was pleaded, that the agreement was
subject to three
further terms:
15.1.
The work would be done within a reasonable
period of its commencement.
15.2.
it would be performed in a good and proper
workmanlike manner, and free from defects.
15.3.
Payment for work done would be due and
payable only after the defendant had approved the works and was
satisfied that the works
were completed in a good and proper
workmanlike manner, and free of defects.
16.
Consequently, the defendant raised the
exceptio non adimpleti contractus
.
It disputed that the plaintiff performed the work as undertaken.
It pleaded that the work was incomplete, not executed
in a good and
proper workmanlike manner and not free of defects.
17.
In
the counterclaim the defendant listed the work that the plaintiff
failed to complete which included the children’s bathroom
and
the spare bathroom; and the main bedroom.
[14]
Furthermore, the plumbing works were not executed in a good proper
workmanlike manner. It claimed compensation for the unfinished
work in an amount of R29 844.72 (being the amount it paid to a
third party to complete the work).
18.
The
defendant attached to its plea and counterclaim five (5) “pro-forma
invoices” from a third-party provider for plumbing
services,
which are identified with specific job numbers. Additionally,
proof of payment to the third-party for the services
rendered was
also attached. According to these invoices the work was done by
the third-party over the period 29 April 2021
to 19 May 2021 as well
on occasions thereafter.
[15]
19.
The plea and counterclaim were followed
with an application for summary judgment.
The parties’
affidavits
20.
The affidavit in support of summary
judgment –
20.1.
Identified the plaintiff’s cause of
action as a contractual claim based on a partly written, partly oral,
agreement in terms
of which the defendant appointed the plaintiff to
carry out renovations to the property.
20.2.
Verified the cause of action and the amount
claimed in the summons.
20.3.
Confirmed that the sum claimed (i.e.,
R289 597.29) was a liquidated amount and was immediately due and
payable.
20.4.
Stated that the plaintiff performed its
obligations under the agreement until the defendant’s
representatives unlawfully denied
the plaintiff access to the
property resulting in the plaintiff not being able to “finalize
the agreement” and the
plaintiff then cancelled the contract.
20.5.
It repeated the defences set out in the
plea.
20.6.
Averred that the defendant cancelled the
agreement without calling upon the plaintiff to rectify the
“non-performance”.
(Incidentally, the plaintiff did not
plead that the defendant’s cancellation constituted a
repudiation which it elected not
to accept and the agreement was
therefore
extant
).
20.7.
Its case for summary judgment was premised
on the following:
(a)
In the opinion of the deponent the
defendant did not have a
bona fide
defence to the action and had defended the action solely for purposes
of delay.
(b)
The plea “most certainly [did] not
raise issues for trial”.
(c)
The defences which the defendant raised
were not substantiated because prior to the delivery of pleadings,
the defendant had not
complained that the work had not been performed
in accordance with the terms of the contract, nor had the defendant
placed the
plaintiff in
mora
.
(d)
The
defendant hindered
[16]
the completion of the work. By that time the agreement was
almost finalised and “costs accumulated”.
[17]
(e)
The defendant was not entitled to cancel
the contract and had no right to hinder the performance of the work
by the plaintiff.
(f)
The amount which the plaintiff was claiming
is for “actual services rendered, and material supplied to
which the plaintiff
[was] entitled”.
(g)
The defendant’s damages claim was
limited to R29 844.72 for the completion of the works. The
plaintiff thereby
suggested that the value of the incomplete work was
R29 844.72.
(h)
The defendant had failed to provide
documentary proof of the plaintiff’s failure to execute its
obligations timeously, or
at all.
Defendant’s
defence
21.
Not surprisingly, the defendant contended
in its opposing affidavit that the application for summary judgment
was defective for
want of compliance with rule 14(2)(b) of the
Magistrates’ Court Rules in that the plaintiff firstly, failed
to identify the
point of law relied upon and secondly, failed to
“briefly explain why the defence as pleaded, [did] not raise
any issue for
trial”. On this basis it sought the
dismissal of the application for summary judgment together with the
costs thereof.
22.
The defendant’s complaint is not
without merit. It is correct that the plaintiff did not
identify any point of law relied
upon.
23.
Rule
14(2)(b) calls on the plaintiff to “explain” why the
defence as pleaded does not raise any issue for trial.
“Explain”
[18]
means something more than “state”. The rule itself
differentiates between “state” and “explain”.
It requires the plaintiff to “state” the facts upon which
its claim is based, and to explain “why”
[19]
the defence pleaded does not raise an issue for trial.
24.
In this instance, the plaintiff’s
supporting affidavit does not explain why the defences raised are a
sham. There is
no explanation why the defendant’s claim
that the work was incomplete, and defective, is not genuine.
Apart from repeating
the facts pleaded in the particulars of claim
and the plea, there are no factual averments in the plaintiff’s
affidavit which
cast doubt on the
bona
fides
of the defences raised by the
defendant.
25.
Considering that the defendant attached the
pro forma
invoices to the plea and counterclaim, one would have expected the
plaintiff to address the contents of the invoices and explain
why
they do not support the defendant’s claim that the work was
incomplete, or defective.
26.
The
plaintiff gave no explanation why it is implausible that the
agreement was subject to the additional terms considering that
the
onus rested on the plaintiff to prove that the defendant’s
obligation to pay was not conditional.
[20]
27.
I
am mindful that the plaintiff’s failure to explain why the
pleaded defence does not raise any issue for trial is not fatal
to
its application and is not a formal requirement which goes directly
to the validity of the application for summary judgment.
[21]
However, an explanation from a plaintiff is one of the elements that
a court considers when assessing whether there is a
triable
issue.
[22]
28.
This brings me to the defendant’s
affidavit. The defences raised in the plea and counterclaim
were repeated by the defendant
in its affidavit. The defendant
pointed out that on the plaintiff’s own version the work was
not completed. The
plaintiff’s response to this was that
prior to the delivery of pleadings, the defendant had not complained
that the work
had not been done in accordance with the agreement.
29.
In the letter dated 3 May 2021, the
plaintiff was notified that it had failed to perform its obligations
under the agreement and
that while the defendant was willing to pay
for work done, it refused to pay for work not done.
30.
In
the counter claim, the defendant identified the defective work,
[23]
and the incomplete work.
[24]
As mentioned above, four (4) pro forma invoices detailing the work
that was done by a third-party were attached to the plea
and
counterclaim. The incomplete and defective work can be
discerned from these invoices.
31.
Even on the plaintiff’s version,
performance was incomplete. This means that it would not be
entitled to payment of
the contract price. Notwithstanding
this, its pleaded case is for the payment of the full contract
price. While the
court may, in the exercise of its discretion
award a reduced contract price, the contractor must plead this, as
well as facts why,
despite the contractor’s failure to complete
the work
contemplated by the parties in the
contract,
it would be fair and reasonable
for the defendant to remunerate the plaintiff.
32.
In my view the plea discloses a defence to
the action, although it lacks the details contained in the plea.
It, read together
with the supporting documents particularises the
defective and incomplete performance sufficiently for the plaintiff
to refute
them in its affidavit.
33.
This gives rise to the question whether it
is permissible for the court to have regard to the averments in the
plea and counterclaim
notwithstanding that those are not made under
oath. In other words, is the court restricted to the
defendant’s affidavit
in its assessment of whether a
bona
fide
defence is disclosed, or may it
consider the averments in the plea and counterclaim, notwithstanding
that those averments are not
made under oath.
34.
Seen in isolation, the affidavit is
sketchy. It invites the criticism that it is “needlessly
bald vague and sketchy".
But is it “needlessly”
sketchy? After all, the defences identified are valid in law.
However, the material
facts are not set out in the affidavit.
They are set out in the plea and counterclaim, and the annexures
thereto.
35.
The one defence referred to in the
defendant’s affidavit is that the contract was subject to
additional terms. The two
additional terms of relevance for
present purposes being (i) payment was conditional upon the defendant
having approved the work
and being satisfied that it had been
completed in a good and proper workmanlike manner, and free of any
defects; and (ii) the work
being done in a good and proper
workmanlike manner, and free of defects.
36.
The
onus does not rest on the defendant to prove that the agreement was
subject to the additional terms. It rests on the plaintiff
at
the trial to prove that the contract was not subject to the
additional terms.
[25]
37.
The
other defence referred to in the defendant’s affidavit is that
the work was not completed, and was defective (i.e., the
exceptio
non adimpleti contractus
).
In this regard too, the onus rests on the plaintiff. To obtain
the contract price it will have to prove at the trial
that it
completed the work as it had undertaken to do.
[26]
38.
As
indicated earlier the defences raised by the defendant are valid in
law. The requirement that the affidavit resisting summary
judgment must set out the nature and grounds of the defence and the
material facts relied upon is aimed at assessing whether the
defence
is valid in law and that the defendant is
bona
fide
in raising it. For a court to make such an assessment
sufficient particularity must be provided by a defendant to satisfy
a
court that the statements of fact, if found to be correct at the
trial, should result in a judgment for the defendant.
[27]
If a defendant is
bona
fide
in the defence pleaded, it should be willing, and able, to set out
the material facts upon which its defence is based. The
unwillingness or refusal to do so, could be an indication that the
defence is not
bona
fide
.
Therefore, a valid defence in law which is set out in a needlessly
bald, vague, or sketchy manner places the
bona
fides
of a defendant into question.
39.
In the context of considering whether the
plaintiff’s affidavit complied with the requirements of rule
32(2) of the Uniform
Rules of Court, Corbett JA (as he then was)
remarked in
Maharaj v Barclays National
Bank Limited
1976 (1) SA 418
(A) at 423
H–
“
Where
the affidavit fails to measure up to [the requirements of rule 32(2)]
the defect may, nevertheless, be cured by reference
to other
documents relating to the proceedings which are properly before Court
(see
Sand and Co Ltd v Kollias
supra
at
p.165).
The principle is that, in
deciding whether or not to grant summary judgment, the court looks at
the matter ‘at the end of
the day’ on all the documents
that are properly before it
(ibid. p
165’)”.
[my underlining]
40.
The
intention of the summary judgment procedure was reaffirmed by the
Supreme Court of Appeal in
Joob
Joob Investments (Pty) Ltd v Stocks Mavundla ZEK Joint Venture.
[28]
Considering that the summary judgment procedure is aimed at
preventing a defendant from raising sham defences and thereby
delaying
the plaintiff from enforcing its rights. It is not
intended to deprive a defendant with a triable issue, or a
sustainable
defence, the opportunity to fully ventilate the dispute
at a trial. In the circumstances, the principle referred to by
Corbett
JA that a court “look at the matter ‘at the end
of the day’ on all the documents that are properly before
it”,
[29]
applies in this instance to a defendant’s affidavit.
41.
The defendant is obliged to file a plea and
the plaintiff’s supporting affidavit must engage the averments
therein.
Consequently, the plea and counterclaim and the
annexures thereto are properly before the Court, and should not be
disregarded.
42.
Moreover, there are three reasons peculiar
to this case why it would be harsh to disregard the plea. The
first is that in
its particulars of claim the plaintiff concedes that
the work was not completed. Notwithstanding this, it claims the
full
outstanding contract price, not a reduced contract price.
The plaintiff’s own averment supports the defendant’s
case that the work was not completed.
43.
The second is that the onus rests on the
plaintiff to prove that the contract did not include the additional
terms contended for
by the plaintiff. Additionally, the onus rests on
the plaintiff to prove that the work was complete and was free of
defects.
44.
The third is that
prima
facie
the defendant’s defence for
non-payment has been consistent. At all relevant times, the
plaintiff was informed that
the work was incomplete and defective.
The defence does not appear to be an afterthought, nor contrived.
45.
Consequently,
on all the documents before the court; the plea, counterclaim and the
pro
forma
invoices attached thereto, I cannot conclude that the defences raised
by the defendant are a sham. The fact that the plaintiff
elected not to respond to the various defects referred to in the plea
and counterclaim, and the pro-forma invoices suggests that
there is a
triable issue. If there was not, then the plaintiff would have
explained why the defences raised were a sham.
I
am satisfied that the facts are sufficiently full to conclude that
what the defendant has alleged, if proven at the trial, will
constitute a defence to the plaintiff’s claim.
[30]
46.
I can therefore not agree with the court
a
quo
that the defendant’s defences
are “bald and inexplicably opaque for lack of any detail.”
47.
The
court
a
quo found
that
the plea to paragraphs 11 and 16 of the particulars of claim was
contradictory and therefore doubted whether the defences raised
were
genuine. On a proper reading of the defendant’s response
to these paragraphs, I find no contradiction. The
defendant
admitted the averment in paragraph 11 of the particulars of
claim
[31]
that the
plaintiff received from the defendant’s attorney the letter
which is annexure “F” to the particulars
of claim.
The defendant denied the averments in paragraph 16 of the particulars
of claim which related to the same letter.
While both
paragraphs 11 and 16 deal with the same letter, the averments are not
the same.
48.
The averment in paragraph 11 of the
particulars of claim is that a letter (annexure “F” to
the particulars of claim)
was sent by the defendant’s attorney
to the plaintiff. The contents of the letter are summarised.
The defendant
admitted the averments.
49.
In paragraph 16 the plaintiff relies on the
letter to make out a case that by tendering to pay for work done by
the plaintiff, the
defendant admitted liability to the plaintiff and
that despite the admission, it failed to make payment and is liable
to the plaintiff.
The defendant does not dispute the letter; it
disputes that it is liable to pay the plaintiff. It pleads that
it is not liable
because the plaintiff had not completed the work.
50.
In my view the averments in the plea are
not inconsistent. They are responses to different averments.
51.
The court
a
quo
referred to other anomalies in the
plea read against the
pro forma
invoices. The anomalies, if any, are best challenged at the
trial. There is no reference to these anomalies in the
plaintiff’s affidavit. Had the plaintiff dealt with them
in its affidavit, the defendant would have had an opportunity
to deal
with them. This brings to mind, the following remarks of Colman
J in
Breitenbach v Fiat S.A. (Edms) Bpk
–
“
What
a defendant can reasonably be expected to set out in his affidavit,
depends, to some extent, upon the manner in which the plaintiff’s
claim which he is seeking to answer, has been formulated.
[32]
52.
Had the applicant complied with the
requirements of rule 14(2) regarding the supporting affidavit, and
the defendant thereby given
an opportunity to respond, that may have
exposed the defence as not being
bona
fide
. But the plaintiff elected
not to do so.
53.
In the result, I propose the following
order:
(a)
the appeal is allowed with costs.
(b)
The order of the court
a
quo
is set aside and substituted with
an order in the following terms:
“
Summary
judgment is refused with costs, and the defendant is granted leave to
defend the action.”
S.K. HASSIM
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
PRETORIA
I agree, and it is so
ordered.
H. KOOVERJIE
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
PRETORIA
Appearances
:
Counsel
for the
appellant
:
Adv.
R Kriek
Instructed
by:
Stroebel
Singh Theuissen Inc
Counsel
for the respondent:
Adv. W
Steyn
Instructed
by:
MW
Nothnagel Attorneys
Date
heard:
13
February 2024
Date
of Judgment:
6
May
2024
[1]
2020
(6) SA 624
(WCC) at para 13.
[2]
See
paragraph 7 below.
[3]
My
underlining.
[4]
Cf
.
Tumileng
Trading
at
para 18 and para 19.
[5]
Tumileng
Trading
at
para 18.
[6]
Tumileng
Trading
at
para 19.
[7]
Paragraph
5.2 of the particulars of claim reads as follows:
“
The
written part of the Agreement as per the Plaintiff’s quote
which is excluding VAT for the services that will be rendered
and
material to be purchased.”
[8]
The
purchase order which was issued is for R278 921.93 plus vat
reflected as R41838. 29. The total value of the purchase
order
is R320 760.22.
[9]
Para
5.1 of particulars of claim.
[10]
Para
5.5 of particulars of claim.
[11]
Para
5.6 of particulars of claim.
[12]
Para
5.7 of particulars of claim.
[13]
Para
8 of the particulars of claim.
[14]
The
defendant had failed to install
the
stainless shower waste, shower floor and walls, cemcrete basin slab
and floor, any of the accessories, and had failed to apply
a brick
sealer.
[15]
The
work executed was detailed in the invoices:
1.
Pro-forma Invoice dated 21 May 2021,
relates to Job No 0041336/150506 which was for replacing a leaking
“Galv pipe in the
roof with copper pipe”.
2.
Pro-forma invoice dated 31 May 2021,
relates to Job No 0041577 for a burst pipe. A leaking pipe
inside the shower wall was
repaired.
3.
Pro-forma Invoice dated 19 June 2021,
relates to Job No 0042118/151806/151810 to unblock a basin.
4.
Pro-forma invoice dated 1 July 2012,
relates to Job No 0040844 for the installation of a toilet pan, a
free-standing bath with
a mixer, shower mixer handles and shower
heads, “sit on basins” with mixers, and the supply of
copper tubing for
electrical wiring. This work was done over
the period 29 April 2021 – 19 May 2021. The taps and
sanitaryware
were supplied by the defendant.
5.
Pro-forma invoice dated 10 August 2021
relates to Job No 0043363 for the replacement of drain pipes over
two days.
[16]
The
plaintiff expresses this as “The defendant refrained the
plaintiff from performing its duties in terms of the agreement.”
[17]
The
plaintiff does not disclose what these “accumulated”
costs are. It might be that the plaintiff had “costs
incurred” as opposed to “costs accumulated” in
mind.
[18]
The
dictionary meaning of the word “explain”, when used as a
transitive verb, means to “make known in detail
(thing, that,
how, etc)”. See
The
Concise Oxford Dictionary
.
[19]
According
to
The
Concise Oxford Dictionary
the word “why” is an interrogative adverb. It is
an interrogative “on what ground? For what reason? With
what
purpose?”.
[20]
Pillay
v Krishna and Others
1946 AD 946
at 960.
[21]
Gauteng
Refinery (Pty) Ltd v Eloff
2023(2)
SA 223 (GJ) at para 15.
[22]
Ibid.
[23]
Paragraph
3.2 of the counterclaim.
[24]
Paragraphs
3.1.1 to 3.1.5, 3.1.6 and 3.1.7 of the counterclaim.
[25]
Cf.
Pillay v Krishna
at 960,
Kriegler
v Minitzwer
1949(1) SA 498 (A)
[26]
It
is worth remembering that the plaintiff has admitted that the work
was not completed, it claims the full contract price and
a reduced
contract price.
[27]
Arend
and Another v Astra Furnishers (Pty) Ltd
1974 (1) SA 298
(C) at 303H-304A.
[28]
2009
(5) SA 1 (SCA).
[29]
Cf.
Maharaj v Barclays National Bank Limited
at 423 H. See para 39
above.
[30]
Cf
.
Breitenbach v Fiat S.S (Edms) Bpk 1976 (2) 226 at 228D-E
[31]
“
On
3 May 2021 the plaintiff received a letter from the defendant’s
attorneys cancelling the agreement with immediate effect
and
informed the plaintiff that it failed to perform on its obligations
as settled in the agreement. Attached hereto marked Annexure
‘F’
a copy of said letter.”
[32]
At
p.299.
sino noindex
make_database footer start
Similar Cases
IX Engineers (Pty) Ltd v September and Another (48047/2021) [2023] ZAGPPHC 1829 (26 September 2023)
[2023] ZAGPPHC 1829High Court of South Africa (Gauteng Division, Pretoria)97% similar
Engineering Council Of South Africa v Madonsela and Others [2023] ZAGPPHC 265; 58061/2021 (28 March 2023)
[2023] ZAGPPHC 265High Court of South Africa (Gauteng Division, Pretoria)96% similar
Khumalo Engineering (Pty) Ltd v Step Up Engineering (Pty) Ltd (075138-2023) [2025] ZAGPPHC 182 (27 February 2025)
[2025] ZAGPPHC 182High Court of South Africa (Gauteng Division, Pretoria)96% similar
Professional Aviation Services (Pty) Ltd v City of Tshwane Metropolitan Municipality (37721/2021) [2024] ZAGPPHC 384 (16 April 2024)
[2024] ZAGPPHC 384High Court of South Africa (Gauteng Division, Pretoria)96% similar
Air Liquide Large Industries (Pty) Ltd v Lemnotho Catering CC (2024/006165) [2025] ZAGPJHC 249 (7 March 2025)
[2025] ZAGPJHC 249High Court of South Africa (Gauteng Division, Johannesburg)96% similar