Case Law[2024] ZAGPPHC 719South Africa
Palomino Plant SA (Pty) Ltd v Dust-A-Side (Pty) Ltd and Others (86576/2019) [2024] ZAGPPHC 719 (16 July 2024)
Headnotes
liable as a joint wrongdoer with the first defendant. In terms of the third-party notice, the first defendant claims a contribution or indemnification from the third party on the ground that, at the time of the collision, the first defendant was in a contractual
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 719
|
Noteup
|
LawCite
sino index
## Palomino Plant SA (Pty) Ltd v Dust-A-Side (Pty) Ltd and Others (86576/2019) [2024] ZAGPPHC 719 (16 July 2024)
Palomino Plant SA (Pty) Ltd v Dust-A-Side (Pty) Ltd and Others (86576/2019) [2024] ZAGPPHC 719 (16 July 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_719.html
sino date 16 July 2024
# REPUBLIC
OF SOUTH AFRICA
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH
COURT
OF
SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
Case
Number: 86576/2019
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED
DATE: 16/7/2024
SIGNATURE:
In
the matter between:
PALOMINO
PLANT SA (PTY)
LTD
Plaintiff
and
DUST-A-SIDE
(PTY)
LTD
Respondent
/ First
Defendant
EXXARO
RESOURCES LIMITED
Second Defendant
EXXARO
COAL (PTY) LTD
Excipient/ Third Defendant/ Third Party
# JUDGMENT
JUDGMENT
BASSON,
J
Introduction
[1]
The plaintiff,
Palomino Plant (Pty) Ltd
,
was the lawful
and beneficial owner of a Bell 770G Motor Grader ("the grader
"
).
The plaintiff hired the grader to the first defendant/respondent
(Dust-a Side (Pty) Ltd)
,
for a monthly
fee of R 107
,
635
.
00
.
The grader was
delivered to the first defendant in August 2016
.
Claim
against the first defendant
[2]
On
or
about
17
May
2017,
whilst
the
grader
was
being
used
by
the
first
defendant at the site, the grader was involved in a motor vehicle
collision with an articulated dump truck ("the dump
truck) owned
by, or, alternatively, under the control
of the second
defendant, (EXXARO Resources Limited)
.
The grader was
damaged beyond repair and was written off. The salvage value of the
grader after the accident was about R 202 920.00.
[3]
The plaintiff
claims that as a result of the fact that the first defendant was
unable to continue using the grader, it therefore
was in breach of
its obligations under the agreement to return the grader to the
plaintiff, fair wear and tear excepted, in the
same condition as it
had been in when delivered by the plaintiff to the first defendant in
terms of the contract
of hire
.
As a result,
the
plaintiff
suffered
damages
for
R
3,365,261
,
75
Claim
against the second defendant
[4]
In the
alternative to the claim against the first defendant, the plaintiff
also claims damages from the second defendant (
"E
XXARO
Resources Limited") on the basis that the grader was involved in
the collision with a dump truck which was driven by
an employee of
the second defendant who, at the time
,
so it is
alleged, was acting in the course and scope of his employment
(vicarious liability)
.
Alternatively,
it is claimed that he drove
the dump
truck
as an agent of
the second
defendant,
who at all
material times was acting in furtherance of his mandate with the
second defendant. The plaintiff further claims that
the collision was
occasioned solely due to the negligence of the second defendant
and/or the employee acting in that capacity
,
alternatively,
as an agent of the second defendant.
[5]
In essence,
the plaintiff has therefore instituted a
contractual
claim
against the first defendant and, in the alternative,
the plaintiff
claims
delictual
damages
from the
second defendant flowing from an alleged collision with the grader.
[6]
On 9 July
2020, the first defendant delivered a third-party
notice against
the
third
party
(EXXARO
Coal (Pty)
Ltd
-
the
excipient).
The
first
defendant
claims
that the third
party is to be held liable as a joint wrongdoer
with the first
defendant.
In
terms of the third-party
notice,
the first
defendant claims a contribution
or
indemnification from the third party on the ground that, at the time
of the collision, the first defendant was in a contractual
relationship with the third party in terms of
a
written
service agreement. It is claimed that, at the time of the collision
upon which the plaintiff's particulars of claim are
reliant, the
first defendant was the hirer of the said grader which belonged to
the plaintiff. It is further alleged that the first
defendant was
utilising the grader at the third party's Leeuwpan site for the
purpose of fulfilling the obligations of the first
defendant's
partnership in terms of the written service agreement between
them (first
defendant and the third party)
Exception
[7]
The
third
party
(the
excipient)
filed
its exception
on 4 September
2020.
The third
party excepted to the third party notice on the basis that as the
claim against the first defendant
is
purely
contractual
and
as
the
first
defendant
seeks
to
hold
the
third party
liable in delict as a joint wrongdoer such a claim is not recognized,
nor sustainable, and is in fact bad in law
.
Accordingly,
so it is
submitted,
the
Rule 13 notice is bad in law and cannot sustain a claim against the
third party
.
Rule 13 reads
as follows:
"(1)
Where party in
action claims
–
(a)
As against any
other person not a party to the action (in this rule called a
'third
party') that
such party is entitled, in respect of any relief claimed against him,
to a contribution or indemnification from such
third party, or
(b)
Any question
or issue in the action is substantially the same as a question or
issue which has arisen or will arise between such
party and the third
party, and should properly be determined not only as between any
parties to the action but as between any parties
to the action but
also as between such parties and the third party or between any of
the, such party may issue a notice, hereinafter
referred to as a
third party notice, as near as maybe in accordance with Form 7 of the
First Schedule, which notice shall be served
by the sheriff.
(2)
Such notice shall state the nature and grounds of the claim of the
party issuing the same, the question or issue to be
determined, and
any relief or remedy claimed. In so far as the statement of the claim
and the question or issue are concerned,
the rules with regard to
pleadings and to summonses shall
mutatis mutandis
apply.
(6)
The third party may plead or except to the third party notice as if
he were a defendant to the action. He may also, by
filing a plea or
other proper pleading, contest the liability of the party issuing the
notice on any ground notwithstanding that
such ground has not been
raised in the action by such latter party: Provided however that the
third party shall not be entitled
to claim in reconvention against
any person other than the party issuing the notice save to the extent
that he would be entitled
to do so in terms of rule 24."
[8]
In
broad
terms,
the
first
defendant
is
opposing
the
plaintiff's
claim
on
three grounds.
Firstly, the first defendant claims that it can only be held liable
ex
contractu,
for
damages
caused
to the grader
if such damage
was
not caused
by
the
wrongful and
culpable conduct of the third party or if the first respondent's
failure to return the grader to the plaintiff, fair
wear and tear
excepted, was objectively not possible. Conversely,
the first
defendant
can
only be held liable for damages to the said grader if such damage was
caused by the wrongful and culpable conduct of the first
defendant.
Secondly, it is claimed that the damage to the grader, and thus the
first defendant's inability to return the grader
to the plaintiff,
was not due to any fault of the first defendant and was objectively
impossible due to it having been damaged
due to the exclusive
negligence of the employee, or alternatively, agent of the third
party
.
Thirdly, and
in the alternative, the first defendant denies being liable for all
the plaintiffs damages and pleads that the plaintiff
'
s
damages were caused by both the first defendant and the third party.
In that event, the first defendant prays the first defendant
be held
liable for the plaintiff
'
s
damages but only to the extent of such damages remaining after the
first third party's negligence has been determined and an amount
commensurate with the third party's contributory negligence is
deducted from the plaintiffs damages
.
Discussion
[9]
Rule 13
contemplates the scenario where the defendant would be entitled, in
law, to a contribution or indemnification in circumstances
where any
question or issue in the action is substantially the same as a
question or issue which has arisen or will arise between
such party and
the third party
.
Rule
30 requires
that the
defendant
has
a valid cause of action against the third party.
[10]
In the present matter, the third party raised an exception that it
cannot be held liable as a joint wrongdoer
where
the plaintiff's claim against the first defendant is based on a
written agreement and therefore founded in contract. Joint
wrongdoers
are persons
who
are
jointly
and
severally
liable
in delict.
[1]
No provision
is
made in our law of contract for the concept of a joint wrongdoer.
[2]
A similar argument
was
raised
in
OK Bazaars (1929) Ltd and others v Stem and Ekermans
.
[3]
In
that matter, the plaintiff instituted a claim for damages on the
ground of breach of contract. Similar to this matter
,
the
defendant
served
third party notices on the first and second parties
claiming
that, in the event it being held that it had breached the contract,
that the first and second third parties were negligent
and therefore
joint wrongdoers in terms of section 2 of the Apportionment of
Damages Act 34 of 1956
.
The
third party took an exception
to
the
third
party
notice.
The
court
held
that the
legislature
did
not
in
this Act intend to introduce
the
principle
of
apportionment
of
damages in contractual claims
:
The
court held as follows:
"
To
sum up then, inasmuch as prior to the passing of the Act,
contributory negligence was not one of the recognised common law
defences
to a claim based upon a breach of contract it seems to me
unlikely that, had the Legislature intended to introduce a radical
change
in the law of the nature contended for by Mr.
Ipp,
it
would have done so in an oblique way and without using clear language
to express such intention
.
"
[4]
[11]
Although
counsel on behalf of the first defendant submitted that the
OK
Bazaar
decision
is distinguishable from the present matter, I am not persuaded that
this matter is distinguishable.
[12]
I therefore
conclude that the third party notice is bad in law and that the first
defendant has no legal basis to join the third
party
as such
.
Order
[13]
In the event,
the following order is made
:
1.
The exception
against
the
first
defendant's
third
party
notice
and
claim is
upheld
.
2.
The first
defendant is granted leave to amend their third party notice and
claim within 15 days of this order.
3.
The first
defendant is ordered to pay the costs of the exception according to
scale C.
# JUDGE
A.C. BASSON
JUDGE
A.C. BASSON
# JUDGE
OF THE HIGH COURT
JUDGE
OF THE HIGH COURT
# GAUTENG
DIVISION, PRETORIA
GAUTENG
DIVISION, PRETORIA
Delivered:
This judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically by circulation
to the
Parties/their legal representatives by email and by uploading it to
the electronic file of this matter on Caselines. The
date for the
reasons is deemed to be 16 July 2023
APPEARANCES:
For
the Excipient/ Third Party
AC
Bothma SC A Mabotsela
Instructed
by
WEBBER
WENTZEL
For
the Respondent/ First Defendant
TALL
Potgieter
Instructed
by
SC
SAVAGE JOOSTE & ADAMS INC
[1]
Visser
&
Potgieter
Law
of Damages
3
rd
ed at 289.
[2]
Christie's
Law
of Contract
in
South Africa,
(7ed)
at
294
et
seq.
[3]
OK
Bazaars
(1929)
Ltd
and others
v
Stem and Ekermans
1976
(2)
SA
521
(C)
.
[4]
Ibid
at 529F.
sino noindex
make_database footer start
Similar Cases
Palm Chrome (Pty) Ltd v 2 Glowing Sunset Trading 56 CC and Others (2023-080001) [2023] ZAGPPHC 760 (28 August 2023)
[2023] ZAGPPHC 760High Court of South Africa (Gauteng Division, Pretoria)98% similar
Ingrain SA Proprietary Ltd v Olowa N.O and Others [2023] ZAGPPHC 401; 8555/2022 (7 June 2023)
[2023] ZAGPPHC 401High Court of South Africa (Gauteng Division, Pretoria)98% similar
Sortetex (Pty) Ltd and Others v Van Der Westhuizen and Another (2025-209294) [2025] ZAGPPHC 1234 (20 November 2025)
[2025] ZAGPPHC 1234High Court of South Africa (Gauteng Division, Pretoria)98% similar
Palm Chrome (Pty) Ltd v 2 Glowing Sunset Trading 56 CC and Another (047429/2023) [2023] ZAGPPHC 714 (24 August 2023)
[2023] ZAGPPHC 714High Court of South Africa (Gauteng Division, Pretoria)98% similar
M. v Haywood N.O and Others (15781/15) [2024] ZAGPPHC 437 (29 April 2024)
[2024] ZAGPPHC 437High Court of South Africa (Gauteng Division, Pretoria)97% similar