Case Law[2023] ZAGPPHC 1107South Africa
Eskom Holdings SOC Limited v Emfuleni Local Municipality and Others (94248/2019) [2023] ZAGPPHC 1107; [2023] 3 All SA 745 (GP) (5 July 2023)
High Court of South Africa (Gauteng Division, Pretoria)
5 July 2023
Headnotes
Summary:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 1107
|
Noteup
|
LawCite
sino index
## Eskom Holdings SOC Limited v Emfuleni Local Municipality and Others (94248/2019) [2023] ZAGPPHC 1107; [2023] 3 All SA 745 (GP) (5 July 2023)
Eskom Holdings SOC Limited v Emfuleni Local Municipality and Others (94248/2019) [2023] ZAGPPHC 1107; [2023] 3 All SA 745 (GP) (5 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_1107.html
sino date 5 July 2023
FLYNOTES:
MUNICIPALITY –
Electricity – Failure to pay Eskom – Duties in terms
of Constitution – To serves interests
of citizens by
providing access to affordable electricity – In breach of
its obligations in terms of Electricity Regulation
Act 4 of 2006
and its licence conditions – NERSA failing to exercise its
mandate and municipality’s debt increasing
– NERSA and
Emfuleni have acted in contempt of earlier order – Conduct
unconstitutional and unlawful –
Just and equitable relief
that Eskom undertakes the reticulation of electricity in Emfuleni.
HIGH
COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
CASE
NO:
94248/2019
REPORTABLE
OF
INTEREST TO OTHER JUDGES
REVISED
05.07.23
In
the matter between:
ESKOM
HOLDINGS
SOC LIMITED
Applicant
and
EMFULENI
LOCAL MUNICIPALITY
First
Respondent
MUNICIPAL
MANAGER OF
EMFULENI
LOCAL MUNICIPALITY
Second
Respondent
NATIONAL
ENERGY REGULATOR OF SOUTH AFRICA
Third
Respondent
PREMIER,
GAUTENG
Fourth
Respondent
ADMINISTRATOR
OF
EMFULENI
WILLY
BHILA NO.
Fifth
Respondent
MUNICIPAL
MANAGER OF
EMFULENI
LOCAL
MUNICIPALITY LUCKY SEANE
Sixth
Respondent
and
EMFULENI
FOR CHANGE NPC
First
Intervening Party
ATC
(PTY) LIMITED t/a CBT
ELECTRIC
AFRICAN CABLES
Second
Intervening Party
SCAW
SA (PTY) LIMITED
Third
Intervening Party
HALL
LONGMORE HOLDING (PTY) LIMITED
Fourth
Intervening Party
Summary
:
The
relief sought is for the Emfuleni Local Municipality and its
Municipal Manager to be declared in contempt of the Full Court’s
order issued on 18 November 2018, and to order just and equitable
remedy pending the hearing of Part B of the application that
was
before that Full Court. The interim relief will benefit entities that
have joined in as intervening parties in the contempt
application.
That will include a further 216 businesses that are represented by
the intervening parties.
The
relief obtained in the Full Court was primarily that the applicants
pay Eskom’s portion of the electricity bills issued
by Emfuleni
to its customers who are resident within its jurisdiction directly to
Eskom. Eskom’s complaint was that it is
unable to discharge its
constitutional obligations to generate and supply bulk electricity to
Emfuleni because of the ever escalating
debt owed to it due to
non-payment for bulk electricity by Emfuleni.
The
dispute between Eskom and Emfuleni was categorised as a dispute
between organs of state and subject to resolution under Chapter
4 of
the Constitution and subject to the Intergovernmental Relations
Framework Act. The National Electricity Regulator of South
Africa
(“NERSA”) is empowered by the Electricity Regulation Act
(“ERA”) to steer the resolution of this
dispute.
Held:
[1]
In the
circumstances, the following order is made:
1.1.
The following
parties are granted leave to intervene in the above application:
1.2.
Emfuleni for
Change NPC, as the first intervening applicant;
1.3.
ATC (Pty) Ltd,
trading as Cbi-Electric African Cables, as the second intervening
applicant;
1.4.
Scaw South
Africa (Pty) Ltd as the third intervening applicant;
1.5.
Hall Longmore
Holdings (Pty) Ltd as the fourth intervening applicant.
[2]
The first
respondent, ("Emfuleni"), is declared to be in contempt of
the Full Court order issued on 18 November 2018 and
the failure of
Emfuleni to pay the first applicant, ("Eskom"), for
continued provision of electricity is declared unlawful
and
unconstitutional.
[3]
The second
respondent, the Municipal Manager, is declared to be in contempt of
the Full Court order issued on 18 November 2018 and
the failure of
Emfuleni to pay the first applicant, Eskom, for continued provision
of electricity is declared unlawful and unconstitutional.
[4]
The third
respondent (“NERSA”) has failed to implement appropriate
measures to address Emfuleni’s non-performances
with its
license conditions and to safeguard the interests of Eskom and the
first to fourth intervening applicants, and such failures
are
declared to be unlawful and unconstitutional.
[5]
Emfuleni must
appoint Eskom as its service delivery agent and provider to perform
all functions and provide all services relating
to Emfuleni’s
electricity business on behalf of Emfuleni (the "Agency")
and as service delivery agent and provider:
5.1.
Eskom shall be
entitled to collect all revenues due to the Emfuleni in respect of
the electricity distribution function and ensure
that the funds are
paid into a separate ring-fenced account to be opened in the name of
Emfuleni (the "Account");
5.2.
Eskom shall be
authorised to charge to the Account all costs and expenses incurred
by Eskom in discharging its duties in terms of
the Agency and the
amounts which Emfuleni is liable to pay Eskom for the electricity
supplied by Eskom calculated at NERSA approved
tariffs.
5.3.
Emfuleni shall
pay Eskom, in relation to the services rendered by Eskom in respect
of the Agency, such amounts as NERSA may determine
from time to time
on application by Eskom;
5.4.
In relation to
the Agency, Eskom shall account to Emfuleni quarterly and pay the net
revenue (calculated as the difference between
the Eskom tariff and
Emfuleni’s municipal tariff less the costs envisaged in terms
of paragraphs 4.2 and 4.3 above) over
to Emfuleni.
[6]
Eskom and
Emfuleni, subject to appropriate oversight from NERSA, must finalise
the terms of the agreement established by this order
within six
months of the date of this order.
[7]
The agreement
which shall contain the provisions stipulated under 5 and details and
dates regarding how the electricity business
of Emfuleni will be
handed over to Eskom to enable Eskom to perform its functions as
service delivery agent of Emfuleni.
[8]
Pending the
finalisation and implementation of the Agreement between Eskom and
Emfuleni and with immediate effect:
8.1.
The 1st to 8th
applicants in the Cape Gate matter and the Emfuleni electricity
customers (listed in Schedule "A" to Eskom's
Notice of
Motion) are authorised and directed, subject to appropriate oversight
by NERSA, to discharge the debts which they incur
to Emfuleni in
respect of the ongoing supply of electricity to them by: -
8.1.1Making
payment directly to Eskom for the electricity they consume at the
rate of the Eskom tariff and furnishing to Emfuleni
proof of the
payments made to Eskom;
8.1.2
Continuing to pay the difference between municipal tariff and the
Eskom tariffs (i.e. the municipal portion) to Emfuleni.
8.2.
Eskom is
authorised and directed to issue invoices to the electricity
customers which specify the Eskom tariff (the amount to be
paid to
Eskom for the electricity supplied under the invoice) and the
Emfuleni tariff (the amount to be paid to Emfuleni for electricity
supplied under the invoice) separately and Emfuleni will assist and
cooperate with Eskom in this regard which includes furnishing
the
details of customers and allow Eskom to repair and install new or
parallel meters at the supply points of the customers.
[9]
Eskom's
appointment as service delivery agent may only be terminated by
agreement between Eskom, Emfuleni and NERSA, failing which
this
Court, after being satisfied that Emfuleni has developed sufficient
administrative, financial and technical skills and capacity
to
discharge its obligations under the licence efficiently, accurately
and sustainably to ensure access to a stable supply of electricity
to
residents of Emfuleni.
[10]
If Eskom and
Emfuleni are unable to finalise the terms of the agreement within six
months:
10.1
Eskom and Emfuleni will file a Report to the Court within fourteen
days of the expiry of the six-month period which sets out
the steps
taken to conclude the agreement pursuant to the order, the aspects in
respect of which there are agreements and the aspects
in respect of
which there are disagreements.
10.2
Following the filing of the Report, any party is permitted to file a
supplementary affidavit and to set the application down
before the
Court for appropriate relief on not less than fourteen days' notice
to the other parties.
[11]
Emfuleni and
NERSA, jointly and severally, the one paying the other to be
absolved, are ordered to pay the costs of all the applicants,
and
such costs are to include the costs of two counsel.
JUDGMENT
This
judgment was handed down electronically by circulation to the
parties' and/or parties' representatives by email and by being
uploaded to CaseLines. The date and time for the hand down are deemed
on 17 June 2023.
The
Court (Coram Baqwa, Malindi JJ and de Vos AJ)
Introduction
[1]
We find it
regrettable when the judicial system becomes clogged up, and the
courts become preoccupied with cases which in terms
of the
Constitution ought to be resolved by state organs. As will become
apparent in this instance, there seems to be an unwillingness,
ineptitude, lack of capacity or inability to engage meaningfully in
order to bring about effective solutions to disputes concerning
the
provision of/or payment for electricity. The judiciary has also had
to deal with cases that are a result of the omnipresent
rampant
corruption and maladministration. When the issues become deadlocked
as a result of these factors and when an impasse is
reached, the
regrettable consequence is that it is the citizens and businesses who
suffer the inevitable failures with regard to
delivery of basic
services and commodities such as water and electricity.
[2]
The situation
has manifested itself in a long-running dispute between Eskom and
numerous municipalities such as Emfuleni Local Municipality
(“Emfuleni”) which is the first respondent in this
matter, and which is alleged not to be paying Eskom for the bulk
electricity it supplies to the municipality.
[3]
In
this regard, we share the sentiments expressed by Madlanga J writing
for the majority in
Eskom
Holdings SOC Limited v Vaal River Development Association
(Pty)Ltd
and Others
[1]
when
he stated as follows
:
“
It
is deeply disturbing that – through no fault of their own –
the residents of the Lekwa and Ngwathe Municipalities
(residents) are
subjected to a situation that violates several of their fundamental
rights protected in the Bill of Rights. A situation
that infringes
their right to dignity, their right of access to healthcare services,
their right of access to sufficient water,
their right to an
environment that is not harmful to health or well-being and the right
to basic education. The residents add that
there is even a threat or
real risk of infringement of the right to life. All this, as a direct
consequence of Eskom’s conduct.
I say all this is happening
through no fault on the part of the residents because they say that
the two municipalities have a prepaid
electricity system and that
they (the residents) do pay their dues. That notwithstanding, they
find themselves caught up in the
dispute between Eskom and the errant
municipalities. A dispute at the centre of which is the woeful and
reprehensible failure by
the municipalities to pay Eskom for the
electricity it supplies, and which I do not condone in the least. A
classic, practical
and painful manifestation of the saying, “When
two elephants fight, it is the grass that gets trampled.”
[2]
[4]
This matter is
not only about Emfuleni’s failures to pass on Eskom’s
portion of electricity bills but also about the
failures of organs of
state to act in terms of section 41(3) of the Constitution of the
Republic of South Africa which obliges
all spheres of government and
all organs of state within each sphere “to make every
reasonable effort to settle the dispute
by means of mechanisms and
procedures provided for that purpose …” The said
mechanisms and procedures are contained
in the Intergovernmental
Relations Framework Act, 13 of 2005 (“the IRFA”).
Parties
[5]
The first
applicant is Eskom Holdings SOC Ltd ("Eskom") which plays a
developmental role and must promote universal access
to electricity
at affordable prices as provided for in
section 6(5)
of the
Eskom
Conversion Act No 13 of 2001
.
[6]
The first
respondent is Emfuleni Local Municipality (“Emfuleni”) to
whom, in fulfilment of its legislative obligations
Eskom generates
and supplies electricity. Emfuleni, in turn, sells or supplies the
electricity to customers and/or end-users within
its municipal area
at marked-up tariffs to raise revenue to fund operations.
[7]
The second
respondent is the Municipal Manager of Emfuleni, Oupa Nkoane at the
relevant time, who is also cited in his personal
capacity as the
person responsible for the administration of the affairs of Emfuleni.
[8]
The third
respondent is the National Energy Regulator of South Africa (“NERSA”)
a regulating authority established in
terms of
section 3
of the
National Energy Regulator Act of 2004
.
[9]
The fourth
respondent is the Premier of the Gauteng Provincial Government, Mr
David Makhura, who is cited in his official capacity
as the person
responsible for the intervention by the Gauteng Provincial Government
into the affairs of Emfuleni, as provided for
in terms of section 139
of the Constitution.
[10]
Emfuleni for
Change represents its members who are various industries and
businesses operating within the municipal area of Emfuleni.
They also
represent many residents and ratepayers of Emfuleni and consumers of
electricity within the municipal area of Emfuleni.
[11]
African Cables
is a major employer in the Emfuleni region and a major consumer of
electricity. It conducts business as a manufacturer
and supplier of
electrical cables and conductors for use in bulk electrical
infrastructure.
[12]
Scaw is also a
major employer and consumer of electricity. It is a manufacturer.
Scaw conducts business as a manufacturer and supplier
of steel chains
for use in the mining industry, construction industry, oil and gas
industry, general industrial purposes, lifting
and rigging.
[13]
Similarly,
Hall Longmore is a major employer and conducts business as a
manufacturer of steel pipes and coating.
[14]
Emfuleni for
Change, African Cables, Scaw and Hall Longmore applied for leave to
intervene as parties. Their applications to intervene
were consented
to by the parties. At the commencement of these proceedings leave was
granted for the four intervening applicants
to be joined as
applicants in support of Eskom’s application. They will be
referred to collectively as the Intervening Applicants.
Relief
sought
[15]
The
relief sought from this Court has evolved during the course of
litigation. Eskom sought relief, stated broadly, for the Court
to
find Emfuleni in contempt of Court, terminate its agreement with
Emfuleni, mandate NERSA to investigate (and impose remedial
measures)
and permit the end-users in Emfuleni to pay Eskom directly - with
Eskom then paying Emfuleni's portion back to it.
[3]
[16]
The
Intervening Applicants proposed a different remedy, namely that Eskom
acts as agent of Emfuleni with necessary amendments to
Emfuleni's
license with NERSA.
[4]
[17]
At the
hearing, Eskom presented a draft order which, in the main, adopted
the relief proposed by the Intervening Applicants with
additional
prayers aimed at the practical implementation of the relief.
[18]
The relief
proposed by Eskom at the hearing in the draft order, broadly, is for-
18.1.
A declarator
that Emfuleni's failure to pay Eskom is unlawful and
unconstitutional.
18.2.
A declarator
that NERSA's failure to implement appropriate measures to address
Emfuleni's non-performance with its license conditions
and to
safeguard the interests of Eskom and the intervening applicants is
unlawful and unconstitutional.
18.3.
Emfuleni must
appoint Eskom as its service delivery agent, with NERSA's oversight,
within 6 months of the order. The draft spells
out what obligations
Eskom as a service delivery agent would have. The draft then provides
what happens in the event of the agency
agreement not being concluded
within 6 months and provides for the termination of the agency
agreement.
18.4.
Whilst the
agency agreement is being concluded, the bills of the electricity
users in Emfuleni must indicate the portion to be paid
to Eskom and
the portion to be paid to Emfuleni.
[19]
The core
difference between the relief proposed by the Intervening Applicants
in their papers and that presented to the Court by
Eskom was that
Eskom did not request the Court to alter Emfuleni's license. Instead,
Eskom's draft order proposed that Eskom and
Emfuleni are to agree on
terms for Eskom to act as a service delivery agent for Emfuleni
whilst Emfuleni got its house in order.
[20]
During
argument, NERSA, broadly, accepted the relief set out in the draft
order. NERSA expressed its satisfaction with Eskom being
the service
delivery agent of Emfuleni. It became common cause that Eskom
frequently plays this role in other Municipalities subject
to the
signing of service level agreements - similar to what is being
proposed in this matter.
[21]
Initially,
Emfuleni's stance on the relief proposed in the notice of motion and
at the hearing was that this Court is not empowered
to grant this
relief because to do so would violate the principle of separation of
powers. Emfuleni's position was that Eskom had
other relief available
to and that the application ought to be dismissed with costs.
The
origins of the case
[22]
Eskom,
Emfuleni and NERSA fall within the definition of “organ of
state” in terms of section 239 of the Constitution
and they are
called upon to act in a manner that serves the interests of the
citizens by providing access to affordable electricity.
[23]
Eskom contends
that Emfuleni is failing to comply with its contractual and statutory
obligations in that it is failing to pay Eskom
for its bulk
electricity supply.
[24]
The said
failure, amongst others in respect of other municipalities, results
in Eskom not being able to comply with its constitutional
obligations
to generate and supply electricity to citizens.
[25]
Eskom further
contends that it has taken all conceivable steps to get Emfuleni to
settle its debt without any success. It has amongst
other steps
negotiated and concluded several Acknowledgements of Debt and
Repayment agreements with Emfuleni which have not been
honoured.
[26]
This case must
be considered in the preceding context where during 2018 Eskom
demanded that NERSA and the Provincial Government
take steps to
address Emfuleni’s omissions. None of those efforts bore any
fruits and by mid-2018, Eskom decided to interrupt
the electricity
supply of Emfuleni during certain hours of the day (“the
electricity interruption decision”). The electricity
interruption decision resulted in several large power users of
Emfuleni launching urgent applications during 2018 which were argued
in October 2018.
[27]
The urgent
applications were aimed at interdicting and restraining Eskom from
implementing the interruption decision pending the
review thereof.
NERSA was cited as one of the respondents.
[28]
The
urgent applications were consolidated and decided upon by the Full
Court sitting at the Johannesburg High Court. The bench comprised
of
Makume, Van der Linde and Keightly JJ, and is referred to as the Full
Court. The decision of the Full Court is reported as
Cape
Gate (Pty) Ltd and Others v Eskom Holdings SOC Ltd and Others
.
[5]
The applicants were a host of businesses
[6]
and
the respondents were Eskom, NERSA, Emfuleni and the Premier.
[29]
The relief
sought, as summarised by the Court was as follows -
29.1.
The Part A
interim relief included, apart from the primary prayer, three
alternative prayers. The first alternative prayer was for
an order
directing Eskom, pending the review, to supply electricity on an
uninterrupted basis to Emfuleni “
on
the basis that the applicant(s) will make direct payment to the
1
st
respondent
for the supply of electricity to it
”.
29.2.
The second
alternative prayer was to order Emfuleni and/or the 4
th
respondent
(“
the
Premier
”)
immediately to pay all outstanding amounts due to Eskom for the
supply of electricity to Emfuleni in order to ensure that
an
uninterrupted supply of electricity is provided to the 2
nd
respondent
from 6 August 2018.
29.3.
In the third
alternative prayer, the applicants asked for an order that Eskom,
Emfuleni, and/or the Premier are ordered to agree,
within three days,
a payment plan in respect of Emfuleni’s indebtedness to Eskom
so as to ensure that an uninterrupted supply
of electricity is
provided to Emfuleni. The 5
th
to
8
th
applicants
did not join in asking for the alternative relief.
[30]
The
applicants’ contended that they satisfied the test for a prima
facie right since the harm to them, if Eskom were permitted
to
implement its decision to interrupt the supply of electricity to
Emfuleni, was cataclysmic.
[31]
The Full Court
made an order in the following terms:
“
(174)
In the circumstances the following order is issued:
(a)
The dispute between the four respondents concerning the non-payment
by the second respondent to the first respondent for bulk
electricity
supply and the manner and timing of its resolution given the
intervention of the fourth respondent is, in terms of
section 41(4)
of the Constitution, referred back to the respondents for resolution
in terms of section 41(3) of the Constitution.
(b)
In the event that the said dispute is not resolved within six months
of the date of this order, any party may set down an application
for
determination of Part B.
(c)
The first respondent is interdicted from implementing interruptions
in electricity supply to the second respondent pending resolution
of
the aforesaid dispute within six months of date of this order or, if
the dispute is not so resolved, pending the outcome of
the final
determination of Part B of this application, whichever is earlier
(d)
For as long as the interim interdict ordered above applies:
(i)
the applicants are authorised, subject to appropriate oversight by
the third respondent in the discharge of its statutory obligations
pursuant to the judgment of this Court, to discharge the debts that
they incur to the second respondent in respect of the ongoing
supply
of electricity to them, by:
(aa)
making payment directly to the first respondent for electricity they
consume at the rate of the Eskom tariff, and furnishing
the second
respondent proof of such payments to the first respondent;
(bb)
continuing to pay, in the case of the second to eighth applicants,
the difference between the municipal tariff and the Eskom
tariff
(i.e. the municipal portion) to the second respondent;
(ii)The
second respondent is directed, invoicing the fifth to eighth
applicants, to specify separately the Eskom tariff which the
second
respondent would have paid to the first respondent in respect of
electricity supplied by the second respondent to the fifth
to eighth
applicants under that invoice, were not for this order, and the
municipal tariff in respect of such electricity;
(iii)
The second respondent is interdicted from interrupting the supply of
electricity to the applicants for any reason other than
the
applicants will not have complied with their payment obligations as
set out in this order;
(iv)
The respondents, including the third respondent, are directed to do
all things necessary and take all reasonable steps to give
effect to
this temporary order.
(e)
Nothing in this order shall detract from the existing obligations and
duties owed by the second respondent to the applicants
in terms,
inter alia, of their license granted to the second respondent by the
third respondent, or in terms of any other law.”
[32]
The
Full Court judgment and order were underpinned by a finding that
Emfuleni had failed to comply with Electricity Supply Agreement
("ESA") and its statutory obligations in terms of the
Electricity Regulation Act ("ERA"),
[7]
and its electricity licence.
[33]
The
relationship between Eskom and Emfuleni is governed by the ESA which
provides as follows:
“
9.2
Should payment not be received within a period of 10 (ten) days from
the date the account is deemed to have become due and payable
in
terms of subclause 9.1, Eskom may discontinue the bulk supply to the
Distributor and/or terminate the electricity supply agreement
after
having given the distributor written notice as required in terms of
section 11 of the Electricity Act. The amount outstanding
shall bear
interest compounded monthly from the due date to the date of payment,
at a rate per annum equal to the prevailing prime
overdraft rate
charged by First National Bank of Southern Africa Limited plus 5%
(give per centum).”
[8]
[34]
Further, the
Full Court authorised the applicants who were the large power users
to pay amounts which they owed to Emfuleni directly
to Eskom. The
authorisation was made to curb Emfuleni’s debt from spiralling.
The effect was that Emfuleni customers make
direct payment of Eskom’s
portion of the electricity bill to Eskom.
[35]
More
particularly the Full Court
[9]
said:
“
In
this case it would be unjust and inequitable to require of the
applicants to continue paying the Eskom margin to Emfuleni, when
Emfuleni does not pay that margin, or all of that margin, over to
Eskom. This is particularly so in view of both the applicants
and
Eskom supporting the direct payment relief ...”
[36]
The
applicant’s contention, as embraced by the Full Court, were
that instead of passing on Eskom’s portion, Emfuleni
was using
the money for its everyday operations to the detriment of Eskom’s
ability to discharge its own mandate.
[37]
The Full Court
in paragraph 174(d) (ii) made an order directing Emfuleni to issue
invoices to the fifth to eighth applicants which
specified the Eskom
tariff separately in order to facilitate the direct payment regime.
[38]
The said order
was made to enable the fifth to the eighth applicants to know what
amounts they had to pay Eskom and what amounts
they had to pay
Emfuleni.
Subsequent
to the Full Court Judgment
[39]
Significantly
Emfuleni refused to comply with the order of the Full Court. In an
attempt to justify their contemptuous stance, they
contended that the
direct payment regime could not be implemented due to NERSA’s
failure to provide the necessary oversight.
[40]
The
refusal to comply with the Full Court orders prompted the first to
the fourth applicants in
Cape
Gate
to launch a contempt of court application on an urgent basis
[10]
to be heard on 4 February 2020.
[41]
The
application was argued before Adams J who found in favour of the
first to the fourth applicants on 6 February 2019.
[11]
[42]
Emfuleni
applied for leave to appeal against the judgment of the Full Court
but the application for leave to appeal was dismissed
with costs.
[43]
Emfuleni
petitioned the Supreme Court of Appeal for leave to appeal the
judgment and orders of the Full Court, but their petition
was refused
with costs.
[44]
Emfuleni’s
attempt to resist implementing the judgment and orders of the Full
Court has been unsuccessful for both the Municipal
Manager who is
cited as a second respondent in the present application and Emfuleni
even though they persist in their contemptuous
conduct.
[45]
Eskom’s
fears of Emfuleni’s electricity debt spiralling out of control
have become a reality. From the time the Full
Court interdicted Eskom
from exercising the electricity interruption decision on 8 November
2018, the electricity debt of Emfuleni
had escalated from R1 billion
in 2018 to R3,5 billion in 2021 and it continues to grow.
[46]
The debt of
Emfuleni is rising despite Emfuleni’s electricity customers
paying it for electricity. The payments which Emfuleni
pays in
respect of the Eskom debt have proved to be the proverbial drop in
the ocean and have made no visible dent in massive debt
over time.
This has occurred despite investigations showing that Emfuleni
collects about 90% of the charges it raises.
The
impact on Eskom
[47]
Emfuleni’s
failure to service its debt properly has contributed to a cash
shortfall in Eskom’s operational costs, causing
Eskom to recoup
the shortfall through borrowings or cash bailouts from Government.
This has proved to be not only unsustainable
but likely to cause a
liquidity crunch which is certain to plunge Eskom into a financial
crisis too ghastly to contemplate in terms
of consequences not only
for itself but also for the country’s energy generation
ability.
Approach
to NERSA
[48]
NERSA is fully
aware of Emfuleni’s crisis and the broader crisis involving
other municipalities in South Africa. Eskom approached
NERSA as the
custodian and regulator of the electricity industry with the hope
that it would intervene regarding Emfuleni’s
failure to comply
with the prescripts of ERA and its license conditions. NERSA contends
that it has been actively trying to intervene
but the absence of any
results as a consequence of such intervention seems to confirm
Eskom’s contention that NERSA has effectively
done nothing to
address the problem.
[49]
Subsequent to
the Full Court Judgment and the Adams J judgment, NERSA
delivered its affidavit in which it promised to produce
its decision
on how it was going to deal with the Emfuleni crisis. Eskom waited
with great hope for NERSA’s decision and
kept this application
in abeyance. NERSA's decision was to set in motion a tribunal process
to deal with Emfuleni and other municipalities.
NERSA has the power
to appoint a tribunal in terms of section 18 of ERA. During these
proceedings, NERSA’s counsel conceded
that the process fell
flat because Emfuleni refused to participate. One of the titles NERSA
holds in terms of ERA is that of being
“the enforcer”
with the power to compel errant municipalities to comply with the
prescripts of ERA and the conditions
of the licence issued by NERSA.
NERSA has nothing to show in this regard. One of the attempts at
deflecting accountability by NERSA
was to invoke the incomplete IRFA
process. It is common cause that Emfuleni frustrated this process and
that NERSA has not taken
decisive steps to force all relevant parties
to the table.
[50]
The
intervening applicants are electricity consumers under Emfuleni and
they have joined Eskom in their quest to avoid being left
without
electricity. The impact of lack of electricity will not only impact
their business operations but will also lead to loss
of invaluable
jobs in an already volatile period of unemployment. On 22 November
2019, some of the intervening applicants applied
to NERSA for the
amendment or revocation of the electricity licence issued by NERSA to
Emfuleni. The application was turned down
by NERSA without adopting
or suggesting any alternative solutions. The electricity management
in Emfuleni has continued to deteriorate
in full view of NERSA’s
watch.
[51]
It is under
these circumstances outlined above that Eskom has brought this
application which is being opposed by both Emfuleni and
NERSA.
The
law
[52]
The
Constitutional Court considered the obligation of local government to
supply the electricity in
Joseph
and Others v City of Johannesburg and Others
[12]
and said the following:
“
They
further maintained that any right to receive electricity as a basic
municipal service is qualified by Emfuleni’s constitutional
and
statutory obligations to provide public services in a financially
sustainable manner.”
[13]
"In
addition, rights entail responsibilities. Citizens who can, must take
responsibility for paying for services provided to
them in fulfilment
of government's statutory and constitutional obligations. Government
is entitled to require this of citizens.
Moreover, government
regulation is implicit in the notion of providing electricity."
[14]
[53]
The Court in
Joseph and
Others v City of Johannesburg and Others
elaborated on the right to receive electricity as follows:
"The
provision of basic municipal services is a cardinal function, if not
the most important function, of every municipal government.
The
central mandate of local government is to develop a service delivery
capacity in order to meet the basic needs of all inhabitants
of South
Africa, irrespective of whether or not they have a contractual
relationship with the relevant public service provider.
The
respondents accepted that the provision of electricity is one of
those services that local government is required to provide.
Indeed
they could not have contended otherwise. In Mkontwana, Yacoob J held
that “municipalities are obliged to provide water
and
electricity to the residents in their area as a matter of public
duty.” Electricity is one of the most common and
important basic municipal services and has become virtually
indispensable, particularly in urban society.”
[15]
"The
obligations borne by local government to provide basic municipal
services are sourced in both the Constitution and legislation.
Section 152(1) of the Constitution sets out the objects of local
government in general terms, and creates an overarching set of
constitutional obligations that are to be achieved in accordance with
section 152(2). Section 152 of the Constitution provides:
“
(1)
The objects of local government are to provide democratic and
accountable government for local communities; to ensure
the provision
of services to communities in a sustainable manner; to promote social
and economic development; to promote a safe
and healthy environment;
and to encourage the involvement of communities and community
organisations in the matters of local government.
(2)
A municipality must strive, within its financial and
administrative capacity, to achieve the objects set out in
subsection
(1).”
[16]
"In
addition to these objects of local government, the Constitution
specifically entrenches the developmental duties of municipalities.
Under section 153, a municipality is obliged to prioritise the basic
needs of the community and to promote the social and economic
development of the community.”
[17]
[54]
Chapter 4 of
the Constitution deals with cooperative-governance and more
particularly section 41 requires organs of state such as
Eskom,
Emfuleni and NERSA to secure the well-being of the people and to
exercise their powers and perform their functions in a
manner that
does not encroach on each other’s functional and institutional
integrity.
[55]
In
Eskom
Holdings SOC Ltd v Resilient (Pty) Ltd and Others
,
[18]
the Supreme Court confirmed that it was “beyond question”
that electricity is a component of basic services that municipalities
are constitutionally and statutorily obliged to provide to residents.
[56]
Section 2 of
ERA sets out the objects of the Act, which are to:
“
Achieve
the efficient, effective, sustainable and orderly development and
operation of electricity supply infrastructure in South
Africa;
Ensure
that the interests and needs of present and future electricity
customers and end-users are safeguarded and met, having regard
to
governance, efficiency and the long-term sustainability of the
electricity supply industry;
Facilitate
investment in the electricity supply industry and universal access to
electricity; and
Facilitate
a fair balance between the interests of customers and end-users,
licensees, investors in the electricity supply industry
and the
public”
[57]
Section
3 of ERA appoints NERSA as the “custodian and enforcer”
of the regulatory framework by ensuring that the objectives
of ERA
are achieved, that the interests of electricity customers are
protected, and the people of South Africa have access to affordable
electricity. The provisions contained in ERA impose constitutional
and statutory obligations on local government to provide basic
municipal services, which include electricity. The applicants are
entitled to receive these services. These rights and obligations
have
their basis in public law. Although, in contrast to water, there is
no specific provision in respect of electricity in the
Constitution,
electricity is an important basic municipal service which local
government is ordinarily obliged to provide. The
respondents are
certainly subject to the duty to provide it. Although
Joseph
and
Resilient
refer to the provision of electricity as a basic service to be
provided to residents the principle applies equally to business
entities that are resident within a municipality. They are entitled
to more than the basic measures as were provided for in
Mazibuko
.
[19]
Section 152(1)(c) states one of the objects of local government
to be “to promote social and economic development”.
Emfuleni cannot be allowed to undermine economic development in its
jurisdiction by starving industry of the electricity that they
pay
for, let alone as a basic service to the residents in the area.
[58]
In
order to achieve the objectives of ERA, NERSA is authorised to issue
licences for the generation, transmission or distribution
of
electricity and to enforce performance and compliance with ERA and
licence conditions.
[20]
[59]
NERSA is also
empowered in terms of section 16 of ERA to vary, suspend or remove
any licence condition, or include additional conditions
if a licensee
fails to comply with its licence conditions or if it is necessary for
purposes of achieving the objects of ERA in
terms of section 17, to
remove the licence of a licensee if another person is willing and
demonstrably able to assume the rights
and obligations of the
licensee.
[60]
If the
licensee does not comply with its licence conditions or has
contravened or failed to comply with any provisions of ERA, NERSA
may
in terms of section 18 sit as a tribunal and decide upon the
matter and if the allegations are proved to be true to take
steps to
force the licensee to comply with its licence conditions and ERA.
[61]
NERSA may
also, in terms of section 19 apply to a court for an order suspending
or revoking a licence if there are “any grounds
justifying such
suspension or revocation.
The
Duties of Municipalities
[62]
Section 27
deals with the duties of municipalities and determines that each
municipality must exercise its authority and duty by
progressively
ensuring access to basic reticulation services through appropriate
investments in its electricity infrastructure;
by ensuring
sustainable reticulation services through efficient and effective
management and adherence to national norms and standards;
and by
keeping separate financial statements, including a balance sheet of
the reticulation business.
Emfuleni
License
[63]
The licence
issued by NERSA to Emfuleni contains specific provisions to the
effect that it is supposed to keep its electricity distribution
business separate from its other affairs so that the revenue, costs,
assets, liabilities, reserves and provisions made for its
electricity
business are separately identifiable on its books from those of its
other business; it is supposed to annually submit
audited copies of
its statements to NERSA; it must pay Eskom for the electricity that
it purchases from Eskom; it must prepare
and adhere to plans which
protect customers and ensure the effectiveness of the industry and
those plans must include a maintenance
schedule, standards of
service, enquiries and complaints management, licence compliance
management and consumer/public and staff
safety education.
[64]
Upon failure
by Emfuleni to comply with the above licence conditions the licence
determines that NERSA may serve Emfuleni with a
notice requiring it
to meet its obligations within 30 days or such longer period as NERSA
might determine and if Emfuleni fails
to comply with the notice,
Emfuleni would be guilty of an offence and would be punishable as
provided for in terms of ERA.
[65]
NERSA is also
authorised to recommend to the Minister to authorise an appropriate
undertaker to enter upon and take possession of
the business of
Emfuleni and NERSA may also withdraw Emfuleni’s licence at any
time; NERSA also has the power in terms of
Licence Condition 7 to
amend Emfuleni’s licence or in terms of Licence Conditions 8,
to revoke the licence.
Conduct
and failures of Emfuleni
[66]
Based on the
pronouncement by the Constitutional Court in
Joseph
and the Supreme Court of Appeal regarding electricity as a basic
commodity and the people’s entitlement to have access to
it,
Eskom has a constitutional duty to ensure that municipalities can
discharge their obligations in terms of the Constitution.
[67]
To ensure
access to electricity, Eskom and Emfuleni have a reciprocal duty to
work together to comply with their contractual and
statutory
obligations owed towards each other.
[68]
Emfuleni’s
conduct of failing to pay Eskom for the bulk electricity impedes
Eskom from complying with its developmental role
and constitutional
mandate of generating and supplying electricity to the citizenry and
businesses under its jurisdiction. Emfuleni’s
conduct resulted
in a shortfall in Eskom’s revenue causing it to resort to
borrowings and government bailouts. The catastrophic
consequences
thus engendered need no emphasis. Residents will be deprived of their
constitutionally entrenched right to basic electricity
and businesses
starved of much needed electricity to run their industries which
range from big to small. The consequent losses
of jobs will only add
to a dire state of unemployment in the Emfuleni region.
[69]
A brief
reference to Emfuleni’s financial statements and published
reports will suffice to demonstrate Emfuleni’s inept
management
of its financial affairs. Its revenue generated from electricity
sales in the 2019 financial year, increased by R450 million
whilst its equitable share from government increased by some
R70 million; for the last three years, Emfuleni had collected
R4.5 billion from its electricity customers at a collection rate
of about 90%.
[70]
Sadly, though,
Emfuleni’s financial statements show that Emfuleni’s
irregular expenditure amounted to R1 125 676 432.00
and its fruitless and wasteful expenditure amounted to
R486 097 380.00. Demonstrably therefore, Emfuleni is not
only
being mismanaged but worsened by its failure to comply with its
obligation to keep its electricity business separate from its other
affairs, and NERSA’s failure to enforce this obligation which
is part of Emfuleni ‘s licence. This obligation is also
prescribed in section 27(1) of ERA. The failure to pay Eskom by
Emfuleni is egregious in light of its increased sales whilst its
debt
to Eskom is ballooning.
NERSA’s
Conduct and Failures
[71]
NERSA is an
organ of state as defined in section 239 of the Constitution, and one
of the key role players mandated to ensure the
sustainability of the
electricity industry and the framework established in terms of ERA.
[72]
In terms of
its mandate, it is called upon to facilitate universal access to
electricity; to ensure that the interests of electricity
customers
and end-users (which include the interests and needs of Emfuleni’s
customers) are safeguarded and protected; to
ensure that electricity
supply infrastructure in South Africa is effectively managed and
operated in a sustainable and orderly
manner.
[73]
Despite the
extensive powers granted to NERSA to regulate and enforce all matters
related to access to electricity in terms of ERA
as set out above,
and despite its opposition to Eskom’s application, it is
regrettable that NERSA has dismally failed to
exercise its mandate.
[74]
To avoid
burdening this judgment with a detailed account regarding NERSA’s
omissions, it should suffice to summarise the common
cause facts
which highlight NERSA’s failure to execute its mandate:
74.1.
It is not
disputed that Emfuleni owes Eskom more than R3.5 billion for
electricity and that the debt continues to spiral;
74.2.
Eskom
concluded at least three Acknowledgement of Debt and Repayment
Agreements with Emfuleni and obtained a judgment against Emfuleni;
74.3.
When the
Emfuleni electricity debt reached R1billion in 2018, Eskom took the
electricity interruption decision;
74.4.
On 8 November
2018, the Full Court, sitting at the Johannesburg High Court,
delivered the
Cape
Gate
judgment.
74.5.
Emfuleni has
breached the terms and conditions of the ESA and it is operating in
breach of the provisions of ERA and its licence
conditions by,
amongst other things, not paying Eskom for electricity or making
ineffective sporadic payments, not maintaining
its electricity
network, and not keeping its electricity business separate from its
other affairs.
[75]
Evidently,
Emfuleni contravened and remains in breach of its obligations in
terms of ERA and its licence conditions. It is not disputed
that the
issue was reported to NERSA as far back as 2017/2018. Five years
later, NERSA cannot tender even a shred of evidence to
contradict the
allegation by Eskom that it failed to resolve the matter. It is not
sufficient for NERSA to plead that Emfuleni
was resistant to the
interventions in terms of IRFA. As stated above, NERSA has the
authority to enforce the ERA and pay its role
under section 41 of the
Constitution.
[76]
NERSA was
cited as a party in the
Cape
Gate
matter in which it was directed, together with other organs of state,
to proceed to find a solution to Emfuleni’s failures
to pay
Eskom for the bulk electricity it continues to supply Emfuleni. It is
common cause that both Emfuleni and NERSA have not
complied with the
said order about five years later and despite the order referring the
matter back to the state organs in terms
of section 41(4) of the
Constitution.
[77]
The only
logical conclusion to be drawn is that NERSA intentionally refuses
and/or fails to act against Emfuleni to address its
failures to
comply with ERA and its licence conditions.
[78]
Both NERSA and
Emfuleni are obliged to work with Eskom to secure the well-being of
all persons and to perform their functions in
a manner that does not
encroach on the functional and institutional integrity of Eskom. The
residents and businesses of Emfuleni
are entitled to have access to
electricity and if NERSA and Emfuleni are not making this possible
for Eskom to comply with its
obligations in terms of the
Constitution, they are violating the provisions of the Constitution.
[79]
In light of
the above, the Court concludes that both NERSA and Emfuleni have
acted in contempt of the
Cape
Gate
order
and that their conduct is both unconstitutional and unlawful.
Just
and equitable relief
[80]
The
Court is being called upon to engage its powers under section
172(1)(b) of the Constitution to grant just and equitable relief.
This Court's powers under the section are broad and intentionally so.
No legal principle is immune to a court's just and equitable
jurisdiction under section 172(1)(b). There is no legal stricture
which takes precedence over the obligation of the courts to do
justice between the parties.
[21]
The Court may grant just and equitable relief even at odds with
extant statutory provisions.
[22]
If a breach of rights has been established, Courts are not only
empowered to grant just and equitable relief but are mandated
to
grant appropriate relief.
[23]
[81]
Courts
have to forge new tools and shape innovative remedies if needs be, to
achieve this goal.
[24]
Fose
[25]
enjoins
Courts to afford litigants just and equitable remedies when the law
does not provide ready remedies.
[82]
As stated
above, the
Cape
Gate
Judgment granted Eskom interim relief pending the adjudication of
Part B. The interim relief was for 6 months. For the reasons
stated above, Part B was not prosecuted for nearly two years.
[83]
Emfuleni
accuses the applicants of seeking to bypass the adjudication of Part
B and obtain final relief in this Court, and secondly,
to extend the
number of the beneficiaries of the interim relief to include the 216
other businesses as annexed to the intervening
parties’ notice
of motion.
[84]
The
respondents, in particular Emfuleni, have argued vociferously that
the applicants are not entitled to bypass the prosecution
of Part B
and that to grant the orders prayed for would be tantamount to making
a contract on behalf of the parties and that such
an order would
violate the separation of powers between the judiciary and the
executive at the local government sphere.
[85]
On the other
hand, the applicants have submitted equally vigorously that this
Court is authorised to interfere in the circumstances
in view of the
respondents' conduct which has served only to frustrate the interim
relief, exacerbated by their failure to employ
their powers under
section 41 of the Constitution.
[86]
Despite what
the respondents have submitted, this Court has found and declared
that the respondents' conduct is inconsistent with
the Constitution
and therefore invalid to the extent of their non-compliance with the
Cape Gate
order in
terms of section 172(1)(a) of the Constitution.
[87]
The Court
must, therefore, not shy away from the challenge raised by the
litigants purely because another court had dealt with some
of the
facts. This will be the case where the facts are evolving and
presenting differently over a period of time.
A
state of disaster
[88]
Relief that is
just and equitable must, at its core, provide a practical and
workable remedy which strikes at the real challenge.
[89]
There
is no dispute that Emfuleni owes Eskom. The difficulty is finding
adequate language to describe the scale of the debt. For
comparison,
in
Eskom
Holdings SOC Limited v Letsemeng Local Municipality and Others
[26]
the Supreme Court of Appeal stated that the Letsemeng Municipality's
debt of R41 million was "astronomical". In this
case, the
debt was R2 billion when the case commenced and increased by more
than R1.5 billion during litigation. The current debt
is eighty-five
times what was described as an "astronomical" debt in
Letsemeng
.
[90]
Helpfully,
counsel for the Intervening Applicants highlighted the difference
between a million and a billion in a different metric.
If millions
were conceptualised in time units, then a million would be one day
and a billion would be three years. The real
challenge in this
case is the astronomical scale of the Emfuleni debt.
[91]
Emfuleni
concedes that it does not have billions to repay its historic
debt.
[27]
It also concedes that it has been "beseeched by lack of
financial discipline" and "maladministration".
[28]
Emfuleni says it will be not be able to repay this debt.
[92]
Not only is
the debt gigantic in scale, but it is also dynamic. It grows with
every month Emfuleni does not pay and compounds in
interest.
Emfuleni's payment due to Eskom is hundreds of millions of rands
every month.
[93]
Emfuleni does
not deny it is in debt but complains that Eskom must ring-fence the
debt. Emfuleni's stance, stripped to the bone,
is that it will not be
able to settle this debt, as to attempt to do so would leave it with
no money to run its other affairs.
Ring-fencing a debt of the
magnitude referred to above, in these circumstances, does not make
economic sense.
[94]
In light of
the sheer scale of the debt, the Court rejects Emfuleni's
characterisation of the dispute as one of a debt being owed
capable
of redress through a monetary judgment. Eskom may be perceived to be
at liberty to seize all of Emfuleni's assets to satisfy
the judgment,
but that is likely to compound the problem by worsening the
dysfunctional state which already exists within Emfuleni.
That
is unlikely to resolve Eskom's liquidity in light of the size of the
debt.
[95]
In any event,
Eskom has obtained money judgments which have resulted in the
attachment of Emfuleni's assets. This is not a feasible
way to settle
a R3 billion debt. Nor does it resolve the true issue between
the parties which is that Emfuleni is unable to
pay its debt.
[96]
The scale of
the debt has given rise to a state of disaster so grand that a money
order will not be appropriate relief. The
Court finds that
Emfuleni has yet to realistically confront the state of the disaster
it has created.
[97]
Whilst much of
the focus of the litigation is Emfuleni's non-payment for electricity
services, the case involves much more than
money. Eskom's ability to
provide electricity is threatened by Emfuleni's financial delinquency
but also by Emfuleni's broader
dysfunction.
[98]
Eskom is being
hampered in providing services to the rest of the country as Emfuleni
does not comply with requests to regulate electricity
as part of
load-shedding. When Eskom needs to shed the load, it requests
Emfuleni to do so. Emfuleni responds that it is not in
a position to
do so as it lacks the capacity to switch off the power. The effect of
a municipality failing or refusing to cooperate
with Eskom to ensure
load-shedding is a potential collapse of the entire national grid.
The threat, says Eskom, is
a national black-out.
[99]
The Court
accepts that the true challenge before it is to address the state of
disaster which extends beyond the mere inability
to pay a debt.
Constitutional
impact
[100]
The
impact of Emfuleni's dysfunction has apparent constitutional
dimensions. Electricity is a basic municipal service which is
virtually indispensable.
[29]
It is "one of the most common and important basic municipal
services".
[30]
The applicants before the Court range from NGO/residents associations
and businesses. Emfuleni's refusal to pay Eskom for electricity
places this right at risk for all within the area of the
jurisdiction.
[101]
Beyond
the everyday electricity users within Emfuleni are the businesses and
industries within Emfuleni. The Intervening Applicants
represent some
of these industries and businesses operating within the area of
Emfuleni. They rely on Emfuleni for electricity
which they need to
run their enterprises. Emfuleni's failure to pay Eskom places the
Intervening Applicants' businesses and the
industries they serve at
risk. The impact extends beyond the businesses as the non-viability
of these businesses affects the livelihoods
of those dependent on
businesses in the municipal area.
[102]
The
Intervening Applicants have set out
[31]
the various aspects of life affected by electricity. They contend
that the supply of electricity is central to the realisation,
promotion, protection and fulfilment of several rights in the Bill of
Rights, including dignity, trade and occupation, food security
and
healthcare, basic nutrition for children, schooling, equality and
housing. Electricity drives the supply of water and sewage
pumps. It
promotes health and safety. It is critical for education and
healthcare. It facilitates the very basic tenets of life
that the
Constitution protects.
[103]
Eskom
can only do its job if Emfuleni pays it for services. Eskom provides
the indispensable service of generating and supplying
electricity.
The Court in
Cape
Gate
held without controversy that this "country … cannot
exist and the economy cannot function without Eskom remaining
economically viable".
[32]
Emfuleni
is making Eskom's job impossible. Emfuleni's failure to pay Eskom
contributes to a shortfall in Eskom's operational
expenses. Eskom
must recoup that shortfall through borrowings and government
bailouts. The unsustainability of this model is a
concrete reality in
the life of every person living in South Africa. As cited by Eskom,
the consequences are catastrophic, and
the harm unquantifiable.
[104]
Eskom
has a constitutional duty to ensure that municipalities can discharge
their obligations. Eskom, as an organ of state, is obliged
to secure
the well-being of the people.
[33]
Eskom
cannot meet this constitutional obligation whilst Emfuleni does not
pay it. Emfuleni's conduct is placing Eskom in an
impossible
position. Eskom cannot fulfil its constitutional service delivery
obligations when its customers (municipalities) do
not pay it for the
electricity that they consume and which Eskom must supply. This
non-payment threatens Eskom's ability to service
the country's
electricity needs.
[34]
[105]
Emfuleni
is obligated to exercise its powers and perform its functions in a
manner that does not encroach on another organ of the
state's
functional and institutional integrity.
[35]
The Supreme Court of Appeal has found that it is irrational for an
organ of state to act in a manner that renders another
organ of state
unable to discharge its obligations to provide services, including
electricity, to residents.
[36]
It
is also responsible for ensuring the provision of services to
communities sustainably and promoting social and economic
development.
[37]
[106]
Emfuleni has
acted in a way that undermines the ability of Eskom to fulfil its
constitutional obligations of generating and supplying
electricity.
[107]
Emfuleni
is also under a constitutional duty to provide services sustainably
and manage its budgeting and plan to prioritise the
basic needs of
communities, including electricity supply.
[38]
The apex Court has identified the obligation to provide services,
including electricity, as "a cardinal function, if
not the most
important function, of every municipal government."
[39]
The
obligation carried by Emfuleni to provide electricity is a
constitutional obligation.
[40]
It is, furthermore, a statutory
[41]
and public duty.
[42]
[108]
The
dispute between Eskom and Emfuleni gains a constitutional dimension
in light of the right to electricity at play as well as
the
engagement between organs of state. The cooperation needed between
organs of state to be able to comply with their constitutional
obligations qualifies as a constitutional matter.
[43]
[109]
Emfuleni is
acting outside its statutory and constitutional obligations. Emfuleni
has also ignored carefully crafted judgments seeking
to avoid Eskom
having to approach the Court in this fashion. It is our courts' duty
to vindicate the rule of law. The case
is not one of debt
collection but rather one which calls on matters that affect the
country, prevent a national black-out, and
access to those
fundamental rights to which electricity is a conduit.
[110]
Emfuleni's
response to the applicants' reliance on section 172(1)(b) is that the
Court can only grant just and equitable relief
after a finding of
unconstitutionality in terms of section 172(1)(a). Emfuleni's
opposition is not born out by jurisprudence. The
position adopted by
the Constitutional Court is that a court may exercise its just and
equitable powers in section 172 even if
there was no finding of
unconstitutionality.
[44]
The
Court, therefore, rejects Emfuleni's principal objection to the Court
exercising its powers under section 172.
Just
and equitable
[111]
The relief
sought is an order permitting Eskom to take over the electricity
business from Emfuleni in terms of an agreement reached
with
Emfuleni. Whilst Eskom and Emfuleni iron out the agreement's
details, the end-users will pay Eskom directly.
[112]
It weighs with
the Court that Eskom has taken every conceivable step before
approaching this Court. It has sought governmental intervention
at
every level. It has obtained money judgments. It has negotiated and
renegotiated with Emfuleni. It has turned to NERSA. NERSA's
position
in this Court has been an acknowledgement of its failures as a
regulator. NERSA conceded, at the hearing, that its conduct
was
inappropriate. There is, at the date of the hearing, no basis for
hope that Emfuleni will comply with its obligations or that
NERSA
will hold it to account.
[113]
The relief
proposed means that Emfuleni still gets the percentage of markup it
is entitled to. Financially, the order will not be
to the detriment
of Emfuleni. Emfuleni's revenue stream is heavily reliant on this
markup. The relief proposed leaves the markup
due to Emfuleni intact.
It will merely appropriate what belongs to Eskom to Eskom.
[114]
Practically,
the order will mean that Eskom undertakes the reticulation of
electricity in Emfuleni. The parties before the Court
did not dispute
that this would be within Eskom's capabilities. The Court has also
been presented with the necessary factual foundation
that Eskom can
undertake this task. The Court is therefore satisfied that the relief
is possible of implementation.
[115]
The
relief leaves the nitty gritty to the parties. Leaving the execution
to of the order to the parties is in line with the Constitutional
Court's decision in
Ramakatsa
v Magashule
[45]
which
allows the operation of the just and equitable relief for
determination between the parties. The relief also means
the Court has not undone Emfuleni's licence or agreements. It forces
state organs to find the details amongst themselves within
the
confines of a practical and implementable solution. The relief is not
final but subject to a procedure to break any deadlock.
[116]
The
Intervening Applicants are private citizens and businesses who
incurred costs to come to Court. They have not received
a responsible
state response from Emfuleni nor from NERSA. They are successful in
their application before this Court. On this
basis, they are entitled
to their costs. Moreover, they have come to Court to assert
fundamental rights, which means they would
be entitled to their costs
on this basis also.
[117]
Eskom,
similarly, has come to Court to assert constitutional principles and
is successful in its application. It has taken every
conceivable step
to avoid litigation. It is also entitled to its costs.
Conclusion
ORDER
[118]
In the
circumstances, the following order is made:
[1]
The following parties are granted leave to intervene in
the above application:
1.1.
Emfuleni for
Change NPC, as the first intervening applicant;
1.2.
ATC (Pty) Ltd,
trading as Cbi-Electric African Cables, as the second intervening
applicant;
1.3.
Scaw South
Africa (Pty) Ltd as the third intervening applicant;
1.4.
Hall Longmore
Holdings (Pty) Ltd as the fourth intervening applicant.
[2]
The first respondent, ("Emfuleni"), is declared to be in
contempt of the Full Court order issued
on 18 November
2018 and the failure of Emfuleni to pay the first applicant,
("Eskom"), for continued provision of electricity
is
declared unlawful and unconstitutional.
[3]
The second respondent, the Municipal Manager, is declared to be in
contempt of the Full Court order issued on 18 November
2018 and the
failure of Emfuleni to pay the first applicant, Eskom, for continued
provision of electricity is declared unlawful
and unconstitutional.
[4]
The third respondent (“NERSA”) has failed to implement
appropriate measures to address Emfuleni’s non-performances
with its license conditions and to safeguard the interests of Eskom
and the first to fourth intervening applicants, and such failures
are
declared to be unlawful and unconstitutional.
[5]
Emfuleni must appoint Eskom as its service delivery agent and
provider to perform all functions and provide all services
relating
to Emfuleni’s electricity business on behalf of Emfuleni (the
"Agency") and as service delivery agent
and provider:
5.1.
Eskom shall be entitled to collect all revenues due to the Emfuleni
in respect of the electricity distribution
function and ensure that
the funds are paid into a separate ring-fenced account to be opened
in the name of Emfuleni (the "Account");
5.2.
Eskom shall be
authorised to charge to the Account all costs and expenses incurred
by Eskom in discharging its duties in terms of
the Agency and the
amounts which Emfuleni is liable to pay Eskom for the electricity
supplied by Eskom calculated at NERSA approved
tariffs.
5.3.
Emfuleni shall
pay Eskom, in relation to the services rendered by Eskom in respect
of the Agency, such amounts as NERSA may determine
from time to time
on application by Eskom;
5.4.
In relation to
the Agency, Eskom shall account to Emfuleni quarterly and pay the net
revenue (calculated as the difference between
the Eskom tariff and
Emfuleni’s municipal tariff less the costs envisaged in terms
of paragraphs 4.2 and 4.3 above) over
to Emfuleni.
[6]
Eskom and Emfuleni, subject to appropriate oversight from NERSA, must
finalise the terms of the agreement established
by this order within
six months of the date of this order.
[7]
The agreement which shall contain the provisions stipulated under 5
and details and dates regarding how the electricity
business of
Emfuleni will be handed over to Eskom to enable Eskom to perform its
functions as service delivery agent of Emfuleni.
[8]
Pending the finalisation and implementation of the Agreement between
Eskom and Emfuleni and with immediate effect:
8.1.
The 1st to 8th
applicants in the Cape Gate matter and the Emfuleni electricity
customers (listed in Schedule "A" to Eskom's
Notice of
Motion) are authorised and directed, subject to appropriate oversight
by NERSA,
to
discharge the debts which they incur to Emfuleni in respect of the
ongoing supply of electricity to them by: -
8.1.1.
Making payment directly to Eskom for the electricity they consume at
the rate of the Eskom tariff and furnishing
to Emfuleni proof of the
payments made to Eskom;
8.1.2
Continuing to pay the difference between municipal tariff and the
Eskom tariffs (i.e. the municipal
portion) to Emfuleni.
8.2.
Eskom is
authorised and directed to issue invoices to the electricity
customers which specify the Eskom tariff (the amount to be
paid to
Eskom for the electricity supplied under the invoice) and the
Emfuleni tariff (the amount to be paid to Emfuleni for electricity
supplied under the invoice) separately and Emfuleni will assist and
cooperate with Eskom in this regard which includes furnishing
the
details of customers and allow Eskom to repair and install new or
parallel meters at the supply points of the customers.
[9]
Eskom's appointment as service delivery agent may only be terminated
by agreement between Eskom, Emfuleni and NERSA,
failing which this
Court, after being satisfied that Emfuleni has developed sufficient
administrative, financial and technical
skills and capacity to
discharge its obligations under the licence efficiently, accurately
and sustainably to ensure access to
a stable supply of electricity to
residents of Emfuleni.
[10]
If Eskom and Emfuleni are unable to finalise the terms of the
agreement within six months:
10.1
Eskom and Emfuleni will file a Report to the Court within fourteen
days of the expiry of the six-month period which sets out
the steps
taken to conclude the agreement pursuant to the order, the aspects in
respect of which there are agreements and the aspects
in respect of
which there are disagreements.
10.2
Following the filing of the Report, any party is permitted to file a
supplementary affidavit and to set the application down
before the
Court for appropriate relief on not less than fourteen days' notice
to the other parties.
[11]
Emfuleni
and
NERSA, jointly and severally, the one paying the other to be
absolved, are ordered to pay the costs of all the applicants, and
such costs are to include the costs of two counsel.
SELBY
BAQWA
Judge
of the High Court
Gauteng
Division, Pretoria
G MALINDI
Judge of the High Court
Gauteng Division,
Johannesburg
I De Vos
Acting Judge of the High
Court
Gauteng Division,
Johannesburg
Date
of Hearing:
9 March 2023
Judgment
delivered: 15
June 2023
APPEARANCES:
For
the Applicant:
PL
Uys
Instructed
by
GMINC
For
the Intervening Applicants:
M
du Plessis SC with S Pudifin-Jones
Instructed
by
Couzyn
Hertzog and Horak
For
the First Respondent:
Mokhari
SC with J Langa
Instructed
by
Seleka
Attorneys
For
the Third Respondent:
A
Platt SC with T Charlie
Instructed
by
Mchunu
Attorneys
[1]
[2022]
ZACC 44.
[2]
Id
at para 189.
[3]
Notice of motion dated 18 December 2019 (Filed on 20 December 2019).
[4]
Notice of motion: Intervening Applicants dated 4 December 2020.
[5]
2019
(4) SA 14
(GJ) ("Cape Gate" or the "Full Court").
[6]
The
specific business are:
Cape
Gate (Pty) Ltd
;
ACT
(Pty) Ltd t/a CBI-Electric: African Cables; Scaw South Africa (Pty)
Ltd
;
Naledi
Ringrollers, a subsidiary of Naledi Holdings (Pty) Ltd; Consolidated
Wire Industries (Pty) Ltd; Glotan Steel (Pty) Ltd
;
South
African Role Company (Pty) Ltdand Emerald Safari Resorts.
[7]
4
of 2006.
[8]
CL
001-195.
[9]
Cape Gate (above) para 171.
[10]
CaseLines 001-3.
[11]
CaseLines 001-248.
[12]
[2009]
ZACC 30
;2010 (3) BCLR212 (CC);2010 (4) SA 55(CC).
[13]
Joseph
and Others v City of Johannesburg and Others
[2009] ZACC 30
;
2010
(3) BCLR 212
(CC) ;
2010 (4) SA 55
at para 50.
[14]
Id
at 51.
[15]
Id
at para 34.
[16]
Id
at para 35.
[17]
Id
at para 36.
[18]
2021
(3) SA 47
(SCA) para 13.
[19]
Mazibuko
and Others v City of Johannesburg and Others
2010 (4) SA 1
(CC) (8
October 2009) ("Mazibuko")
[20]
Section 4 of ERA.
[21]
Corruption Watch NPC and Others v President of the Republic of South
Africa and Others 2018 (2) SACR (CC) at para 77 ("Corruption
Watch").
[22]
Electoral Commission v Mhlope
2016 (5) SA 1
(CC) at para 130;
Corruption Watch NPC (above) at para 71.
[23]
Section 38 of the Constitution; President of the Republic of South
Africa and Another v Modderklip Boerdery (Pty) Ltd
2005 (5) SA 3
(CC) at para 52.
[24]
Fose
v Minister of Safety and Security
[1997] ZACC 6
;
1997 (3) SA 786.
[25]
Id
para 69.
[26]
[2022]
2 All SA 347
(SCA) (9 March 2022).
[27]
Answering Affidavit para 10.
[28]
Answering Affidavit para 62.
[29]
Joseph (above) at para 34.
[30]
Id.
[31]
Heads of Argument of the Intervening Applicants at para 24.
[32]
Cape
Gate (above) para 148.
[33]
Section 41(1)(b) of the Constitution.
[34]
Cape Gate (above) para 148.
[35]
Section 41(1)(b) of the Constitution.
[36]
Resilient (above) para 88.
[37]
Section 152(1)(b) of the Constitution.
[38]
Sections 152 and 153 of the Constitution.
[39]
Joseph (above) para 34.
[40]
Joseph (above) para 40; Resilient (above) para 13.
[41]
Joseph (above) para 40.
[42]
Mkontwana
v Nelson Mandela Metropolitan Municipality
2005 (1) SA 530
(CC)
para
13.
[43]
Cape Gate (above) para 55.
[44]
Head
of Department : Mpumalanga Department of Education and Another v
Hoërskool Ermelo and Another
2010 (2) SA 415
(CC)
para
97.
[45]
2013 (2) BCLR 202
(CC).
sino noindex
make_database footer start
Similar Cases
Eskom Holdings SOC Limited v Nqorile CC and Another [2023] ZAGPPHC 132; 47122/2021 (28 February 2023)
[2023] ZAGPPHC 132High Court of South Africa (Gauteng Division, Pretoria)100% similar
Eskom Holdings Soc Ltd v Rechavu Trading And Projects (Pty) Ltd (50873/21) [2023] ZAGPPHC 1776 (22 September 2023)
[2023] ZAGPPHC 1776High Court of South Africa (Gauteng Division, Pretoria)100% similar
Eskom Holdings Soc Ltd v Silicon Smelters (Pty) Ltd (34000/2022) [2023] ZAGPPHC 658; [2023] 4 All SA 661 (GP) (25 July 2023)
[2023] ZAGPPHC 658High Court of South Africa (Gauteng Division, Pretoria)100% similar
Eskom Holdings SOC Limited v Emfuleni Local Municipality and Others [2023] ZAGPPHC 497; 94248/2019 (5 July 2023)
[2023] ZAGPPHC 497High Court of South Africa (Gauteng Division, Pretoria)100% similar
Eskom Holdings SOC Ltd v Silicon Smelters Proprietary Limited (34000/22; A169/24) [2025] ZAGPPHC 1084 (7 October 2025)
[2025] ZAGPPHC 1084High Court of South Africa (Gauteng Division, Pretoria)100% similar