Case Law[2023] ZAGPPHC 601South Africa
Xstream Holdings (Pty) Ltd and Others v Chicky Investments (Pty) Ltd and Another (2023/066319) [2023] ZAGPPHC 601 (21 July 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 601
|
Noteup
|
LawCite
sino index
## Xstream Holdings (Pty) Ltd and Others v Chicky Investments (Pty) Ltd and Another (2023/066319) [2023] ZAGPPHC 601 (21 July 2023)
Xstream Holdings (Pty) Ltd and Others v Chicky Investments (Pty) Ltd and Another (2023/066319) [2023] ZAGPPHC 601 (21 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_601.html
sino date 21 July 2023
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
CASE
NO: 2023/066319
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
E
LABUSCHAGNE
DATE:
21 JULY 2023
In
the application between:
XSTREAM
HOLDINGS (PTY) LTD
First
Applicant
MANNINGSTRAAT
EEN EEN TWEE (PTY) LTD
Second Applicant
ANTONIE
JOHANNES BOTES
Third Applicant
LINDA
BOTHA
Fourth Applicant
and
CHICKY
INVESTMENTS (PTY) LTD
First Respondent
CITY
OF TSHWANE METROPOLITAN MUNICIPALITY
Second Respondent
JUDGMENT
[1]
The applicants approach the court on the basis of urgency, seeking an
order stopping
construction on a communal right of way over the first
and second applicants' immovable property.
[2]
The applicants and the first respondent are neighbours, owning
properties contiguous
to a right of way servitude. The first
applicant is the owner of Portion 3 of Erf 140 Queenswood Ext. 1. The
second applicant is
the owner of the Remaining Extent of Erf 1040
Queenswood Ext. 1. The Boteses are the joint owners of Portion 1 of
Erf 1041 Queenswood
Ext. 1 and the first respondent is the owner of
Portion 2 of Erf 1041 Queenswood Ext. 1.
[3]
By virtue of
the provisions of the respective Title Deeds, the first
respondent is entitled to a right of way over Portion 3. The
applicants
contend that there is clear dispute as to what rights,
titles, and powers the first respondent has in respect of the right
of way
and that that dispute should be determined in action
proceedings. However, in the interim the applicants seek an order
inter alia
restraining the first respondent from continuing with its
"unlawful conduct and construction activities on the
servitude area, to mitigate the damages that the applicants may
suffer,
and are currently suffering, as a result of the conduct of
the first respondent, and finally to seek restoration of the property
damage caused to the applicants boreholes and borehole pumps,
restoration and repositioning and installation where respondents
caused removal and/or displacement of electric cables, waterpipes and
fibre cables, removal of the main sewerage pipe serving Portion
3 and
Portion R and to restore the applicants' rights to, and use of these
amenities."
[4]
The first respondent's property is subject to a 1,89-metre-wide
servitude in favour
of the local authority for sewerage and other
municipal purposes. Portion 2 is subject to the condition that
boundary walls or
approved fences have to be erected simultaneously
with, or prior to the erection of dwelling houses on Portion 2, with
the approval
only of the local authority. Portion 2 is further
entitled to a right of way with the width of 7,56 metres over Portion
R (Manningstraat
property), which right of way shall run next to and
parallel with the Western border of Portion 2. Portion 1 (the Botes
property)
is entitled to a right of way with the width of 7,56 square
metres over Portion R (Manningstraat property), which right of way
shall run next to and parallel with the Eastern border of Portion 2.
Portion R is subject to a right of way 7,56 metres wide in
favour of
Portion 1. Portion R is subject to a right of way7,56 metres wide in
favour of Portion 2. Portion 3 is subject to a right
of way3,78
metres wide in favour of Portion 1 and Portion 2.
[5]
The first respondent took transfer of Portion 2 on 2 March 2018.
Construction took
place for approximately six months thereafter and
halted until October 2022.
[6]
The parties have been involved in disputes since 2019 and contend
that the first respondent
has not complied with promises given.
[7]
As a result of grievances that arose, the applicants' appointed
Cawood Attorneys who
addressed a letter to the first respondent on 20
February 2023. In terms of the letter the first respondent was
afforded 7 (seven)
days to:
7.1
Refrain from using the right of way of Portion 3;
7.2
Provide approved building plans for the retaining wall on the
Southern portion of Portion
2 and to immediately commence with the
completion of the retaining walls only as per the approved building
specifications and engineer
specifications. Also the cavity behind
the wall should be filled up and compacted;
7.3
Do all things necessary to restore extreme and Manningstraat's
boreholes to a proper working
condition;
7.4
Replace all electrical cables and installations of XStream Holdings
(Pty) Ltd ("Xstream")
in a properly excavated trench as per
the building regulations and properly mark the installation for
further purposes;
7.5
Repair the driveway situated on the right of way of Portion 1 to a
state of good repair.
[8]
There was no adequate response. The applicants then appointed new
attorneys of record
and on 23 June 2023 they conducted a site
inspection with the right of way. Various irregularities were
detected, giving rise to
a letter of demand of 28 June 2023. An
undertaking was sought from the first respondent to refrain from
further building activities
within the servitude area and to
specifically refrain from removing, dismantling, replacing or
repositioning the sewer pipe of
Xstream and Manningstraat, failing
which the applicants would apply to the High Court for urgent relief.
[9]
As a basis for urgency, the applicants contend that the first
respondent is
continuing on its road of destruction, taking the law
into its own hands with no regard for the rights and entitlements of
the
applicants. It is alleged that the first respondent recently
constructed a wall over the servitude area and damaged waterpipes and
sewerage pipelines. When it became apparent that an undertaking would
not be given, the current application was formulated.
[10]
The first respondent denies that the application is urgent. In
support of this contention, the
following is advanced:
10.1
The first respondent is in the process of an extensive renovation of
the dwelling house and commenced construction
activities in 2018 on
Portion 2. During such construction the applicants' municipal
services and boreholes were damages by building
contractors. The
damage to the boreholes and municipal services was repaired in 2018.
There was no construction between April 2019
and October 2022.
Construction has been ongoing since 10 October 2022;
10.2
The respondent contends that the applicants has waited five years
after commencement of construction and
damage to services and
boreholes;
10.3
They have waited nine months after construction activities
recommenced and damage was again caused to the
relevant services and
boreholes;
10.4
They waited some five months after the letter of 20 February 2023 in
which the applicants threatened with
an interdict and sought
undertakings from the first respondent within a period of seven days;
There
has therefor been a significant delay in bringing this application.
[11]
By contrast, the first respondent was afforded only two days in which
to answer the answering
affidavit.
[12]
The first respondent contends that all municipal services are fully
functional and that the damage
to the first and second applicants'
boreholes have been repaired. Further, the municipal services and
boreholes have been restored
and replaced, deeper underground, within
the right of way. The respondents contend that the applicants took no
steps against the
first respondent in 2018, November/December 2022 or
February 2023. There are no new incidents or threats mentioned after
February
2023 that would justify the urgent application. By contrast
the applicants contend that they only became aware of illegal
structures
being built during the site inspection in June 2023.
[13]
The first respondent contends that the construction is aimed at
repositioning municipal services
at a suitable depth to avoid damage
by vehicles using the road of way during the construction process of
his dwelling.
[14]
.This doesn't appear to be a communication which the first respondent
had conveyed to its neighbours
prior to unilaterally commencing with
the construction on the right of way. The first respondent contends
that the applicants cannot
physically access the right of way by
vehicle from Edgehill Lane. Further it contends that pedestrians are
still using the right
of way unhindered.
[15]
The first respondent contends that the application is moot since none
of the activities referred
to in par 2 of the notice of motion are
being conducted by the first respondent. The only activities within
the right of way servitude,
that have practically been completed, are
those activities referred to in para 4 and 5 of the notice of motion.
Consequently, the
relief sought has become academic.
[16]
This is a matter in which the parties as contiguous neighbours have
rights and obligations in
respect of the right of way, which requires
a degree of cooperation between them, which has been strikingly
absent. The requirement
of utilisation of a right of way
civiliter modo
implies that the right of way is utilised,
taking into account the rights of others to the right of way.
[17]
The first respondent appears to be motivated by good intentions in
replacing municipal services
at an appropriate depth so that they are
not adversely affected by vehicles during construction. The right of
way is paved, and
the end result of the construction would be that it
would again be paved, but with municipal services at an adequate
depth.
[18]
Had this intention been disclosed to other rightsholders when
construction commenced in 2018,
a communication channel might have
opened, which would avoid precipitate conduct in rushing off to
court, rather than having meetings
amongst neighbours. Unilateral
action on a commonly used right of way is to be discouraged.
[19]
In my assessment of the issue of urgency, I am not satisfied that the
matter is sufficiently
urgent for purposes of Rule 6(12). Much of the
complaints arose prior to the appointment of Cawood Attorneys in
February 2023.
Nothing significant has happened thereafter, other
than the appointment of new attorneys and the inspection
in loco
in June 2023
.
[20]
I am therefore going to strike the matter for lack of urgency.
However, the first respondent
is at fault for not having communicated
his intention appropriately and courteously at a time prior to
commencement of construction.
Such unilateral conduct can also
not be commended. In the light thereof, I make the following order:
1.
The matter is struck from the roll for lack of urgency.
2.
No order as to costs.
E.
LABUSCHAGNE
ACTING
JUDGE OF THE HIGH
COURT
GAUTENG
DIVISION, PRETORIA
APPEARANCES
Applicant's
Counsel:
Adv.
JHF Le Reaux
Instructed
by:
E.Y
Stuart Incorporated
First
Respondent's Counsel:
Adv.
JA Venter
Instructed
by:
Weavind
& Weavind Inc.
sino noindex
make_database footer start
Similar Cases
Xeon Holdings (Pty) Ltd v Public Investment Corporation SOC Limited and Others (2024/101102) [2024] ZAGPPHC 945 (27 September 2024)
[2024] ZAGPPHC 945High Court of South Africa (Gauteng Division, Pretoria)98% similar
Nonxuba v South African Legal Practice Council and Another [2023] ZAGPPHC 168; 11897/22 (7 March 2023)
[2023] ZAGPPHC 168High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Mokgobi (13023/2020) [2023] ZAGPPHC 22 (20 January 2023)
[2023] ZAGPPHC 22High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Sebueng (18628/2022) [2023] ZAGPPHC 1167 (15 September 2023)
[2023] ZAGPPHC 1167High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Masingi (2023/077988) [2023] ZAGPPHC 1158 (13 September 2023)
[2023] ZAGPPHC 1158High Court of South Africa (Gauteng Division, Pretoria)98% similar