Case Law[2023] ZAGPPHC 618South Africa
Bila Civil Contractors (Pty) Ltd v Passenger Rail Agency of South Africa (21344/2019) [2023] ZAGPPHC 618 (31 July 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 618
|
Noteup
|
LawCite
sino index
## Bila Civil Contractors (Pty) Ltd v Passenger Rail Agency of South Africa (21344/2019) [2023] ZAGPPHC 618 (31 July 2023)
Bila Civil Contractors (Pty) Ltd v Passenger Rail Agency of South Africa (21344/2019) [2023] ZAGPPHC 618 (31 July 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_618.html
sino date 31 July 2023
THE
REPBLIC OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
HIGH COURT DIVISION, PRETORIA
Case
no:
21344/2019
1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
31
JULY 2023
DATE
SIGNATURE
In
the matter between:
BILA
CIVIL CONTRACTORS (PTY) LTD
PLAINTIFF
And
PASSENGER
RAIL AGENCY OF SOUTH AFRICA
DEFENDANT
JUDGMENT
MAKHOBA,
J
[1]
The plaintiff is Bila Civil Contractors (PTY LTD, a company
incorporated and registered
in accordance with the company laws of
South Africa.
[2]
The Defendant is the Passenger Rail Agency of
South Africa is a juristic entity established in terms of the
Legal
Succession of the South African Transport Services Act 9 of 1989, it
is an organ of State.
[3]
In 2011 the defendant invited tenders under Tender No.
HO/INF/304/03/2011 for the upgrade of the Mamelodi
Garden Station
above platform level (“
the tender”),
to which the
plaintiff submitted a proposal.
[4]
Part of the tender documents forming part of the tender was the
contract data for the Principal Building
Contracts Committee (
the
JBCC”)
Contract, Series 2000, Edition 5.0 (“
the
contract data
”).
[5]
On 9 September 2011 the Supply Chain Management of the defendant
approved the appointment of the plaintiff
and the contract was signed
by the plaintiff on 23 September 2011.
[6]
This is a matter in terms of Rule 33(1), (2) (3) and (5) of the
uniform Rules of Court, namely a special
case premised upon a written
statement of fact, to be decided by this court. Parties agree that
the following are the questions
of law and issues in dispute.
6.1
Whether an agreement was concluded between the Plaintiff and
the Defendant as pleaded by the plaintiff;
6.2
If indeed an agreement was concluded whether the Plaintiff’s
claim against the Defendant has become prescribed;
6.3
If the answer to the aforementioned questions are in favour of the
plaintiff, whether performance in term of the agreement by
the
Defendant became impossible and the contract therefore null and void;
6.4
The parties have agreed that the question of damages not be
determined as part of this stated case but will be determined
separately
dependant on the outcome of this stated case.
6.5
Costs.
[7]
The plaintiff contends that there is an agreement between it and the
defendant, the defendant repudiated
the upgrade agreement. The
defendant denies this.
[8]
The defendant raise the defence of prescription
and that there was no consensus between the parties and thus,
no
agreement.
[9]
The defendant contends further that insofar as it is found that
consensus was present, that it was impossible
for it to perform as in
order to perform it was required to obtain ownership of certain
properties and was unable to do do and
the plaintiff has suffered no
damages.
[10]
The matter was initially set down for the 1
st
of November
2022, but due to non-compliance on the part Plaintiff the matter did
not appear on the trial roll of the day. The parties
however utilized
the opportunity to prepare the agreed statement of facts, for special
adjudication by this court.
Whether
an agreement was concluded between the parties as pleaded by
plaintiff.
[11]
In
Command
Protection Services (Gauteng) (Pty) Ltd t/a Maxi Security v South
Africa Post Office Ltd
[1]
the facts of this case are slightly similar to the facts of this
matter before me.
[12]
In that matter
,
the appellant was advised that it had
been awarded the tender. Shortly thereafter the
respondent was provided with a
draft contract however the contract
was not finalized.
[13]
In paragraph 12 the court said the following:
“
[12]
The dispute thus arising is not novel. It frequently happens,
particularly in complicated transactions, that the parties reach
agreement by tender (or offer) and acceptance while there are clearly
some outstanding issues that require further negotiation
and
agreement. Our case law recognises that in these situations there are
two possibilities. The first is that the agreement reached
by the
acceptance of the offer lacked animus contrahendi because it was
conditional upon consensus being reached, after further
negotiation,
on the outstanding issues. In that event, the law will recognise no
contractual relationship, the offer and acceptance
notwithstanding,
unless and until the outstanding issues have been settled by
agreement. The second possibility is that the parties
intended that
the acceptance of the offer would give rise to a binding contract and
that the outstanding issues would merely be
left for later
negotiation. If in this event the parties should fail to reach
agreement on the outstanding issues, the original
contract would
prevail (see eg CGEE Alsthom Equipments et Enterprises Electriques,
South African Division v GKN Sankey (Pty) Ltd
1987 (1) SA 81
(A) at
92A-E; Namibian Minerals Corporation Ltd v Benguela Concessions Ltd
[1996] ZASCA 140
;
1997 (2) SA 548
(A) at 567a-c
[also
reported at
[1996] ZASCA 140
;
[1997] 1 All SA 191
(A) – Ed]).”
This
decision is quoted with approval in
Sivubo
Trading and Projects CC v Development Bank of Southern Africa
[2]
[14]
In
CGEE
Alsthom Equipment et Enterprises Electriques, South Africa Division v
GKH Sankey (Pty) Ltd
[3]
at
paragraph A the court said “…..
where
in the course of negotiating a contract the parties reach an
agreement by offer and acceptance, the fact that there are still
a
number of outstanding matter material to the contract upon which the
parties have not yet agreed may well prevent the agreement
from
having contractual force.”
[15]
It depends on the facts of a particular case whether the initial
agreement acquires contractual force or not. The
intention of the
parties is to be determined from their conduct.
[4]
[16]
In my view the failure by the plaintiff to attach the addendum which
was required resulted in a failure to reach
consensus by the parties.
[17]
Furthermore, In Prasa Steering Committee meeting NO 16, The following
was said: “ *
Finalization of the Bila Contract is critical.
*Construction
work on the non-station structure can commence as soon as
PRASA
conclude
their agreement with Bila Civil Contractors”.
[5]
In
my view this is indicative of the fact that the parties lacked
animus
contrahendi.
[18]
In addition the letter dated 26 July 2017
[6]
from the plaintiff reads as follows: “
Can
we now sign the contract of which the tender document is in your
possession”
[19]
It is clear from the conduct of the parties that they
did reach an agreement by tender however, there are clearly
some
outstanding issues that
require
further negotiations and agreement.
[20]
In my view there is no contract between the plaintiff and
defendant until the outstanding issues have been settled by
agreement.
[21]
In regard to the costs for 1 November 2022, counsel for the defendant
did come to court however the matter was
not properly placed before
court, and it ended up in the chambers of the Deputy Judge President.
[22]
In my view the defendant is entitled to the cost for 1 November 2022
since it is not the defendant’s fault
that the matter could not
proceed on said day.
[23]
I make the following order;
25.1
The plaintiff’s claim is dismissed with cost including cost of
1 November 2022.
______________________
MAKHOBA
J
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION, PRETORIA
HEARD
AND RESERVED JUDGMENT: 6 JUNE 2023
JUDGMENT
HANDED DOWN ON: 31 JULY 2023
Appearances
:
For
the Plaintiff: Ms J Harwood (instructed by) Hewlett Bunn
Incorporated
For
the Respondent: Adv C Erasmus SC (instructed by) Ngeno & Mteto
Incorporated.
[1]
[2013]
1 All SA 266 (SCA).
[2]
233/2018
[2019] ZASCA 28
( 28 March 2019) para 13.
[3]
1987
(1) SA 81
(A).
[4]
CGEE
Alsthom Equipment papa 92E.
[5]
CaseLines
074-6 to o74-7 para 27.
[6]
CaseLines 0020 – 32.
sino noindex
make_database footer start
Similar Cases
PS Software Contracting CC v Bright Alloys (Pty) Ltd (formerly Mogale Alloys (Pty) Ltd) (49562/2010) [2024] ZAGPPHC 513 (7 June 2024)
[2024] ZAGPPHC 513High Court of South Africa (Gauteng Division, Pretoria)97% similar
AL Mphago Civil Construction CC v HM Eyethu Construction & Plant Hire CC (22283/2019) [2022] ZAGPPHC 231 (11 April 2022)
[2022] ZAGPPHC 231High Court of South Africa (Gauteng Division, Pretoria)97% similar
Mapitsi Civil Works (Pty) Limited and Another v MEC for Roads and Transport for the Gauteng Provincial Government and Others (28418/22) [2023] ZAGPPHC 2067 (2 November 2023)
[2023] ZAGPPHC 2067High Court of South Africa (Gauteng Division, Pretoria)97% similar
South African Civil Aviation Authority v Civil Aviation Appeal Authority and Others (66128/2020) [2024] ZAGPPHC 988 (27 September 2024)
[2024] ZAGPPHC 988High Court of South Africa (Gauteng Division, Pretoria)97% similar
Kgalemo Construction CC and Others v Small Enterprise Finance Agency SOC Ltd (54791/2017) [2025] ZAGPPHC 215 (3 March 2025)
[2025] ZAGPPHC 215High Court of South Africa (Gauteng Division, Pretoria)97% similar