begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 1893
|
Noteup
|
LawCite
sino index
## Tusk Construction Support Services (Pty) Ltd and Another v Mayibongwe N.O and Others (27188/2012)
[2023] ZAGPPHC 1893 (6 October 2023)
Tusk Construction Support Services (Pty) Ltd and Another v Mayibongwe N.O and Others (27188/2012)
[2023] ZAGPPHC 1893 (6 October 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_1893.html
sino date 6 October 2023
HIGH
COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
CASE
NO: 27188/2012
(1)
REPORTABLE: NO.
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
DATE:
6 NOVEMBER 2023
SIGNATURE
In
the matter between:
TUSK
CONSTRUCTION SUPPORT
SERVICES
(PTY) LTD
First
Plaintiff
JOINT
EQUITY INVESTMENTS IN
HOUSING
(PTY) LTD
Second
Plaintiff
and
DR
SOMADODA PATRICK MAYIBONGWE
FINENI
N.O.
First
Defendant
DR
GCWALISILE CYNTHIA KABANYANE N.O.
Second
Defendant
MOROKA
ISAAC BUTCHER MATUTLE N.O.
Third
Defendant
MZAMO
MICHAEL MLENGANA N.O.
Fourth
Defendant
MATSHIPSANA
MERIAM MOLALA N.O.
Fifth
Defendant
TLHOSTE
ENOCH MOTSWALEDI N.O.
Sixth
Defendant
NANDISELE
FLAOUR THOKO MPUMLWANA N.O.
Seventh
Defendant
PHELISA
NKOMO N.O.
Eighth
Defendant
RASHID
AMOD ADECK PATEL N.O.
Ninth
Defendant
ZAKHELE
ALEX TUMMY ZITHA N.O.
Tenth Defendant
Summary
:
More than a
decade ago the Gauteng Department of Education (the Department)
embarked on a school building programme. The Independent
Development Trust (the IDT) was appointed as an implementation agent
for the programme and, in respect of two schools, Dlamini
Construction (Pty) Ltd (Dlamini) was appointed as the contractor.
During the construction of the schools, payment was made
to Dlamini
based on certificates issued by the appointed architect. The
plaintiffs had loaned and advanced monies to Dlamini
(who has
subsequently been deregistered) and sought to recover some R2,5
million from the IDT, being the balance of the loan repayments
they
could not recover from Dlamini itself. The plaintiff relied on
cessions which were precluded by the JBCC agreements
between the
Department and Dlamini. The claims were dismissed with costs.
ORDER
The
plaintiffs’ claim are dismissed, with costs.
JUDGMENT
This matter
has been heard in open court and is otherwise disposed of in terms of
the Directives of the Judge President of this
Division. The
judgment and order are accordingly published and distributed
electronically.
DAVIS,
J
Introduction
[1]
More than a
decade ago the Gauteng Department of Education (the Department)
embarked on a school building programme. The Independent
Development Trust (the IDT) was appointed as an implementation agent
for this programme and, in respect of two schools, Dlamini
Construction (Pty) Ltd (Dlamini) was appointed as the contractor and
Muhammad Mayet Architects & Urban Designers (Mayet) as
the
principal agent.
[2]
The two
schools, being the Steve Tshwete Secondary School (Steve Tshwete) and
Lotus Gardens Secondary School (Lotus Gardens) were
constructed and
the Department, through the IDT, had paid Dlamini the full contract
price during 2010 and 2011 based on payment
certificates issued from
time to time by Mayet.
[3]
While all the
above are common cause, the plaintiffs, being Tusk Construction
Support Services (Pty) Ltd (Tusk) and Joint Equity
Investments in
Housing (Pty) Ltd (Joint Equity), claim that they had loaned and
advanced some R4,3 million to Dlamini. They
had obtained
judgment against Dlamini in a separate case (23 789A/2011) on 21
August 2013, despite Dlamini having been deregistered
on 30August
2020 already. The plaintiffs apparently have succeeded in only
recovering a part of their loans.
[4]
The plaintiffs
claim that, as security for repayment of their loans, Dlamini had
ceded all its right, title and interest in monies
due to it in terms
of construction works performed by it, including those to be received
in respect of the Lotus Gardens school,
to the plaintiffs.
Despite having been informed hereof, the IDT continued to make
payment to Dlamini in an amount of R 2 517 993,
84.
It is this amount which the plaintiffs sought to recover by way of
the action which only came before this court by way
of a stated case
on 19 May 2023.
The
background facts
[5]
As already
mentioned, the background facts are largely common cause and were
placed before the court by way of a state case.
This included
the incorporation of an extensive number of contract and documents.
I shall summarise those relevant to the
disputes, hereunder.
The school
building programme
[6]
During 2005
the Department resolved to implement a school building programme,
targeting various “clusters”. It
budgeted funds for
this purpose in three tranches of R 134 million each. For
purposes of managing and implementing the programme,
the Department
concluded a written Programme Implementing Agent Agreement (the
Implementation Agreement) with the IDT, represented
in this
litigation by its trustees, on 22 December 2005.
[7]
The
Implementation Agreement entailed that the IDT would manage the
financial side of the programme, after the presentation to it
and
approval of a “Programme Implementation Plan” by the
Department. The Implementation Agreement further envisaged
that
the Department would pay monies in terms of the budget into a
specified account of the IDT, whereafter the IDT would effect
payments “…
specifically
and only for the purpose of implementing the Programme
”.
[8]
The IDT in
turn, appointed Mayet as principal agent for three schools in Cluster
H of the Programme on 2 February 2006. It
also identified a
number of consultants such as quantity surveyors and civil-,
structural-, electrical- and mechanical engineers.
Steve
Tshwete and Lotus Gardens were two of the three schools. The
construction of the three schools each had an estimated
contract
value of R16 million.
The JBCC
contracts
[9]
After a
truncated or re-negotiated tender process had been concluded on 11
May 2006, the Department on 28 August 2006 concluded
two written
Joint Building Contracts Committee Services 2000 (JBCC) principal
building agreements with Dlamini for Steve Tshwete
and Lotus Gardens
schools respectively. Each agreement had a contract value of
R18 863 666, 01. In each of
the JBCC agreements
Dlamini was identified as “the Contractor” and Mayet as
“the Principal Agent”.
[10]
In each of the
JBCC agreements, at the relevant signature pages dealing with the
pre- and post-tender information (Clause 42.0)
“the Employer”
was indicated as being the Department. On the cover page of the
agreement in respect of the Steve
Tshwete school the IDT was denoted
as “employer” but nothing turns on this as the relevant
denotion is actually in
said clause 42.0 of the agreement.
Furthermore, in paragraph 13 of the signed stated case, it was
expressly recorded that
“
the
Defendants [the trustees of the IDT] were
not
the Employer as defined in the JBCC contracts
”
(my emphasis).
[11]
In respect of
payments to be made in terms of the JBCC agreements, they provided
that it may only be made after the Principal Agent
had issued payment
certificates and that all payments are to be made to the Contractor,
save in cases where, on certain conditions,
subcontractors may have
been used.
[12]
In addition to
the above, clauses 19.1 of the agreements are also relevant.
They both read as follows “
Neither
the employer nor the contactor shall assign or cede his rights or
obligations without the written consent of the other party,
which
consent shall not be withheld without good reason
”.
The payment
in question
[13]
Dlamini
proceeded with the construction of the schools and invoiced the IDT
from time to time. After progress payment certificates
had been
issued by Mayet, the IDT caused the following payments to be made to
Dlamini:
R 530 00,00 on
20 February 2011
R 960 177,81
on 26 June 2011
R1 027 815,21
on 25 August 2011
The stated case
did not itself indicate whether the payments were in respect of the
Steve Tshwete or Lotus Gardens agreements.
[14]
The bank
account of Dlamini into which the payments had been made, was that
indicated by Mr Dlamini in two written “payment
instructions”,
one in respect of each school, which the IDT had accepted. In
these “irrevocable” instructions,
it was indicated that
the account particulars may not be changed without the written
consent of Tusk.
The loan by
the plaintiffs
[15]
The
explanation for the mention of Tusk in these instructions can be
found in the following: on 17 July 2006 Dlamini as a defined
“borrower” entered into a written “FMO
Infrastructure (Emerging) Project Loan Agreement” with the
plaintiffs.
In terms of the agreement Joint Equity lent Dlamini
R1, 9 m and Dlamini ceded as security for the repayment thereof
certain “pledged
rights”. In terms of the
agreement, these rights included the “contract income” of
“approved projects”.
Lastmentioned was defined in
the schedule to the agreement as the Steve Tshwete school. Tusk
was defined as “the paymaster”
for the agreement. A
second exact same agreement was concluded with the only difference
being that Lotus Gardens school was
indicated as the “approved
project”.
[16]
The loan
agreements were preceded by a “General Covering Cession”,
issued by Dlamini to Tusk on 4 July 2006 and a separate
written
“Cession of Progress Payments” also issued by Dlamini in
favour of Tusk in respect of “
all
progress payments that become due and payable to me/us under Contract
Gauteng Schools Building Programme. Cluster H Schools
–
Lotus Gardens Secondary School
”.
There doesn’t appear to be a similar separate cession of
progress payments in respect of the Steve Tshwete
school.
The demands
[17]
On 28 October
2010 Tusk’s legal advisor wrote a letter to the IDT, advising
it of the two abovementioned cessions and claimed
and demanded as
follows: “
Please
note that in terms of receipt of this letter to acknowledge the
aforementioned cessions, as well as being obliged to make
all and any
payments due to Dlamini to Tusk in its capacity as cessionary of all
and any amounts due to Dlamini. Please note
that should you
proceed to make any payments to the contractor or any other
cessionary that obtained a cession after the 4
th
of July 2006, that Tusk will be entitled to hold you liable for such
payment as well …
”
Tusk’s bank account details were then furnished.
[18]
It is common
cause that the IDT continued to make those progress payments referred
to in paragraph [13] above to Dlamini.
[19]
The letter of
28 October 2006 was followed up by a letter of demand by the
plaintiff’s attorneys on 17 February 2011, referring
to payment
made in respect of the Lotus Gardens school (only).
[20]
The trial
bundles contain a further letter from Tusk’s Director:
Corporate & Legal Affairs, Adv P. C. De Villiers, dated
30
November 2011 pursuant to a meeting with the IDT, threatening with a
damages claim pursuant to the last two payments (one of
which was in
respect of the Steve Tshwete school) but as this letter did not form
part of the stated case, I need not say any more
about it. What
is contained in the stated case however, is a response thereto dated
18 January 2012 wherein the IDT claimed
that the cession of progress
payments was obtained without consent and in breach of clause 19.1 of
the JBCC agreement.
[21]
Pursuant to
the IDT’s denial of liability, the present action was
instituted on 15 May 2012.
The
contentions of the parties
[22]
The
plaintiffs’ contentions set out in the stated case, wherein the
contents of all the aforementioned documents were admitted,
were the
following:
“
29.1
Payment by the Defendants to Dlamini was contrary to the payment
instruction given by the Second Plaintiff to the
Defendants (which
payment instruction the Defendants accepted) and amounts to a breach
of a legal duty the Defendants owed to the
First and Second
Defendants …
29.3
When it made the payments to Dlamini … the Defendants had
knowledge of the cessions …
29.4
Payment by the Defendants to Dlamini of the said amounts that was
owing to it, did not discharge the debt
”
.
[23]
Based on the
above the plaintiffs claimed that they have suffered damages and that
the IDT is liable to it in the amount of the
total of the payments
listed in paragraph [13] above.
[24]
The IDT’s
contentions were firstly that “…
the
monies which the Defendants paid to Dlamini were not paid to Dlamini
to settle a debt owed by the Defendants to Dlamini.
Such monies
were paid to settle debts owed by the Department to Dlamini in terms
of the JBCC contracts
”.
[25]
The IDT’s
contention was further that “
Dlamini
was not entitled to cede its claim for payment against the Department
without the Department’s prior consent
”
and therefore that the cessions are neither valid nor can they be
enforced against the IDT.
Evaluation
[26]
Despite the
formulation of the stated case, Adv Stoop SC, who appeared on behalf
of the plaintiffs, argued that the JBCC agreements
were never
“implemented”. This argument is not underpinned by
the facts agreed to in the stated case and it should
therefore be
impermissible. Even if it is to be entertained, all the facts
point to implementation of the agreements: the
monies to which the
plaintiffs now seek to lay claim were invoiced and claimed by Dlamini
in terms of those agreements, Mayet as
architect acted as Principal
Agent in terms of those agreements and evaluated the amounts claimed
by Dlamini and certified progress
payments from time to time in terms
of those agreements. There is no evidence, either in the stated
case or otherwise, that
Dlamini had been entitled to payments on any
other basis than in terms of the JBCC agreements.
[27]
In support of
his argument however, Adv Stoop SC referred to a letter dated 9
February 2006 wherein the Department had notified
the IDT that it had
resolved to appoint the IDT as “project manager” for a
number of infrastructure projects, including
the “fast-tracking”
of “slow moving” projects, construction of classrooms,
both permanent and mobile, as
well as numerous other schools, some of
which had gone out on tender. The Lotus Gardens and Steve
Tshwete schools were two
of those to be “fast-tracked”
and in respect of which the IDT was authorised to negotiate with
preferred tenderers
to lower their prices.
[28]
After this,
the IDT instructed Mayet on 21 February 2006 as follows: “
You
are hereby instructed to appoint the following contractors for
schools in Cluster 4 as per the adjudicating meeting in the 15
th
and 17
th
of January at the IDT Head Office in Pretoria … [then the
particulars of three schools followed, two of which were Lotus
Gardens and Steve Tshwete with Dlamini (under its previous name
Blackstone Projects (Pty) Ltd listed as contractor and with
approximated
contract prices of R16 million each]. The date of
the site handover must be on or before 28 February 2006. The
contractors
must supply sureties, priced bills of Quantities etc
as
per JBCC 2000 contract
”
(my emphasis)
[29]
Adv Stoop SC
argued that these two letters, i.e the appointment by the Department
of IDT (and its appointment of Mayet) and Mayet’s
letter of 21
February 2006, constituted “the agreements”. Adv
Stoop SC could offer no explanation for as to how
the JBCC agreements
came into being despite their admitted existence, the detailed
particulars contained therein and the fact that
they had been signed
by or on behalf of the parties mentioned therein. The only
inference however, is that those agreements
were indeed the contracts
contemplated in the underlined portion of the letter of 21 February
2006 on which Adv Stoop SC relied.
[30]
Based on all
of the above, the argument that the JBCC agreements were not the
agreements on which the parties had relied and that
these agreements
were never implemented, is rejected. On a balance of
probabilities, this contention is simply not being
not supported by
facts.
[31]
As a further
argument, consequential upon the above, Adv Stoop SC argued that the
IDT, and not the Department, was the employer
for the construction of
the schools. The express wording of the JBCC agreements however
refute this.
[32]
I considered
the construction which the plaintiffs seek to place on the whole
scheme of contracts from another angle as well.
Their
contention would mean that the Department disbursed monies from its
own coffers to the IDT and that the IDT, as principal,
would then
have built schools in its own name. Had this been the scheme, the
schools would then had to have been handed over or
transferred to the
Department. And what about existing Departmental contracts
which simply had to be fast-tracked by the
IDT or contracts where
mobile classrooms had to be built at existing Departmental schools?
When one compares this proposition
to the scenario indicated by the
Implementation and JBCC agreements, namely that the Department merely
contracted with the IDT
to implement the Department’s own
projects and to manage the building of schools on Departmental
property and for the Department
in terms of agreements where the
Department featured as principal, the plaintiffs’ proposition
becomes, if not absurd, then
at the very least not the one favoured
by the balance of probabilities.
[33]
On a
conspectus of all the facts set out in the stated case, it is clear
that the Department, as owner of the schools building programme,
was
the employer in respect of any and all agreements for the
construction of such schools. Even if the IDT had made payment
in respect of such construction projects from funds paid to it by the
Department, it at all times acted as implementing agent on
behalf of
the Department. The Programme Implementing
Agent
agreement puts this agency relationship beyond doubt, particularly if
regard is had to my underlining. IDT was clearly an
agent and
not a principal contracting party and did not act as “employer”.
[34]
I consequently
find that the IDT’s response to the letters of demand wherein
it, reliant on clauses 19.1 of the JBCC agreements,
contended that it
gave no consent to such cessions, could only have been made in its
capacity as agent of the Department.
It had no authority to act
otherwise. Even if the IDT believed it had the capacity to
consent, it is common cause that no
consent had been sought by
Dlamini and none had been given, neither by the Department, nor by
the IDT.
[35]
It further
follows from the above, that the IDT had never incurred any liability
against Dlamini in terms of the JBCC agreements
and, when it made
payments, it did so on behalf of its principal, the Department.
The IDT was never a debtor of Dlamini and
the payments were never in
respect of any own indebtedness to Dlamini. The IDT’s
contention in this regard, referred
to in paragraph [24] above, is
therefore correct.
[36]
Having reached
the above conclusion, one needs not consider whether the “General
Cession” was wide enough to cover both
the Lotus Gardens and
Steve Tshwete schools payments (in the absence of a separate progress
payments cession in respect of the
Steve Tshwete school) and whether
the letters of demand, referring only to Lotus Gardens, were
sufficient. One also need
not enter the debate as to whether
the first plaintiff, Tusk, indicated only as “paymaster”
in the loan agreements,
would be entitled to rely on any of the
cessions or not. The proverbial “bottom line” is
simply that Dlamini
was not entitled to cede any of the payments due
to it by the employer in terms of the JBCC agreements to any other
party without
the Department’s consent.
[37]
Furthermore
the IDT, acting as implementing agent for the Department, cannot be
held liable for any claim which the plaintiffs may
have had against
it principal, had there been such a claim.
[38]
The further
alternate contention raised in paragraph 29.1 of the stated case,
namely an alleged breach of a duty by the IDT, does
not, in the
absence of a duty, disclose a cause of action. The payment
instructions (incidentally issued by Dlamini and not
Joint Equity as
claimed in the stated case) are simply that: instructions.
Joint Equity had no
locus
standi
to
issue such instructions, the instructions could not be elevated to
supercede the JBCC agreements and the obligations that flowed
from
them did not create any self-standing legal (or even contractual)
obligations or duties.
[39]
It must follow
that the plaintiffs’ claims should be dismissed and I find no
reason why costs should not follow the event.
Order
[40]
The following
order is made:
The plaintiffs’
claims are dismissed, with costs.
N DAVIS
Judge of the High Court
Gauteng Division, Pretoria
Date
of Hearing:
19 May 2023
Judgment
delivered:
6 November 2023
APPEARANCES:
For the Plaintiffs:
Adv B C Stoop SC
Attorney for the
Plaintiffs:
Coetzer &
Partners Attorneys,
Pretoria
For the Defendants:
Adv N K Tsatsawane
SC
Attorney for the
Defendants:
Gildenhuys Malatji
Inc, Pretoria
sino noindex
make_database footer start