Case Law[2023] ZAGPPHC 1837South Africa
Transnet (SOC) Limited v Tenova Mining and Minerals South Africa (Pty) Ltd and Another (2022/006083) [2023] ZAGPPHC 1837 (19 October 2023)
Headnotes
the exception and afforded Transnet an opportunity to amend its SOC. I do not expand on this first exception and the award given thereon, despite in the papers it forming part of the grounds for the removal of the arbitrator. This is so, because in oral argument it was submitted that this award does not form part of the reasons to terminate the appointment of the Arbitrator. This award will be referred to as the first award. The second exception raised
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 1837
|
Noteup
|
LawCite
sino index
## Transnet (SOC) Limited v Tenova Mining and Minerals South Africa (Pty) Ltd and Another (2022/006083) [2023] ZAGPPHC 1837 (19 October 2023)
Transnet (SOC) Limited v Tenova Mining and Minerals South Africa (Pty) Ltd and Another (2022/006083) [2023] ZAGPPHC 1837 (19 October 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_1837.html
sino date 19 October 2023
FLYNOTES:
ARBITRATION – Arbitrator – Removal for bias –
Agreement
involved Tenova’s contractual duty to supply Transnet with
valves – Complaint – Arbitrator made
factual findings
on expert matters contrary to express findings of expert reports –
Interpreted correspondence without
hearing evidence thereon –
Appeal Tribunal found arbitrator made determination without
necessary factual expert evidence
– Test for bias restated –
Arbitrator found that Transnet had no claim for damages or any
other claim and no
viable alternative to what it had it pleaded –
On this finding there is reasonable apprehension of bias –
Perception
of bias is good cause for setting aside of appointment
of arbitrator – Removal from office warranted –
Arbitration Act 42 of 1965
,
s 13(2)(a).
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
Case
Number: 2022-006083
REPORTABLE:
YES
OF
INTEREST TO OTHER JUDGES: YES
REVISED
Date
:
2023-10-19
In
the matter between:
TRANSNET
(SOC) LIMITED
Applicant
And
TENOVA
MINING AND MINERALS SOUTH
AFRICA
(PTY) LTD
First
Respondent
B
R SOUTHWOOD N.O.
Second
Respondent
(in
his capacity as arbitrator in the arbitration
proceedings
between the Applicant and First
Respondent)
This
judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically by circulation to
the
Parties/their legal representatives by email and by uploading it to
the electronic file of this matter on CaseLines.
The date for
handing down is deemed to be 19 October 2023.
JUDGMENT
POTTERILL
J
Background
[1]
The applicant, Transnet (SOC) Limited [Transnet] and the first
respondent, Tenova Mining and Minerals
South Africa (Pty) Ltd
[Tenova] concluded two agreements pursuant to Tenova being granted
two tenders and for ease of reference
the two agreements are referred
to as “the agreement.” The crux of the agreement
attracting a dispute was Tenova’s
contractual duty to supply
Transnet with 598 valves to be used in a pipeline valued at a cost of
approximately R16 million.
[2]
Transnet on 18 July 2018 submitted a written request for arbitration
to the Arbitration Foundation
of South Africa [AFSA] to claim damages
from Tenova. The parties agreed to withdraw its arbitration
application to AFSA and that
AFSA would not administer the
arbitration. To this end they concluded an arbitration agreement with
the parties directly appointing
an arbitrator. This is how the second
respondent, the honourable retired Judge Southwood [the Arbitrator]
was appointed. He has
not opposed the application.
[3]
The arbitration agreement recorded in clause 5.2 that if there was
any dispute about the appointment
of the arbitrator it shall be dealt
with by the Association of Arbitrators [AOA] rules. It was also
agreed that the arbitration
would be un-administered arbitration with
clause 6 of the arbitration agreement providing that the arbitration
process would be
in accordance with the AOA rules. The arbitration
agreement had a non-variation clause. The agreement also recorded
that the defendant
may take exceptions to the plaintiff’s
statement of claim [SOC] and it would be regulated in terms of Rule
23 of the Uniform
Rules of Court “and the rules applied by the
courts in deciding exceptions.”
The
issue
[4]
Transnet is in terms of
section 13(2)(a)
of the
Arbitration Act
[1
]
[the Act] seeking an order setting aside the appointment of the
Arbitrator and his removal on the grounds of bias or a reasonable
perception of bias. From this two issues arise; does Rule 9 of the
AOA Rules bar this Court from entertaining the matter; if not,
are
there grounds for removal based on a perception of bias in the awards
granted by the Arbitrator?
The
exceptions raised by Tenova
The
first exception raised
[5]
This exception was raised against the third set of amended SOC of
Transnet. The arbitrator upheld
the exception and afforded Transnet
an opportunity to amend its SOC. I do not expand on this first
exception and the award given
thereon, despite in the papers it
forming part of the grounds for the removal of the arbitrator. This
is so, because in oral argument
it was submitted that this award does
not form part of the reasons to terminate the appointment of the
Arbitrator. This award will
be referred to as the first award.
The
second exception raised
[6]
Transnet delivered its fourth amended SOC setting out five claims
against Tenova. Again
Tenova filed an exception against the SOC
as setting out no cause of action and it being bad in law.
[7]
I find it prudent to first set out the claims of Transnet in the
fourth amended SOC:
Claim 1
Transnet pleaded that
Tenova did not perform in terms of the agreement at all because at
the date of delivery, unbeknown to Transnet,
the valves were not fit
for purpose, were not what Transnet purchased from Tenova in terms of
the agreement and would constitute
unacceptable hazards if placed in
the pipeline. In the circumstances Tenova did not perform in terms of
the agreement.
Claim 2 (alternative to
claim 1)
The valves which were
supplied by Tenova were defective in that the valves were
manufactured in a way which substantially impaired
the utility of the
valves for the purpose for which the valves were purchased by
Transnet. In terms of clause 13 of the agreement
Transnet rejected
the valves in writing. In terms of Clauses 13.2 and 13.2.2 of the
Agreement, Tenova is liable to Transnet for
the replacement costs of
the valves including the overseas inland transportation costs,
freight and insurance charges and other
inland costs.
Claims 3, 4 and 5 are not
in issue before this court and need no addressing.
Tenova’s
exceptions against claims 1 and 2
[8]
Tenova stated that it was necessary for Transnet to plead its
compliance with clauses 9 and 13
of the agreement and it did not. It
could not escape the working of clauses 9 and 13 by relying on
non-performance and therefore
claim 1 was bad in law and did not set
out a cause of action.
[9]
As for claim 2 Tenova also excepted on the basis that Transnet had
not complied with clauses 9
and 13 which was destructive of
Transnet’s claim. But, in any event, clause 13 limits the claim
to defective valves only.
The
Arbitrator’s Award on claims 1 and 2 as set out in the 4
th
SOC
[10]
Transnet relied on the following paragraphs of the award as
reflecting bias, or a perception of bias on behalf
of the Arbitrator:
“
[47]
It is clear that neither Cladall nor Freddy Hirsch purported to lay
down a new principle of law that in the event
of ‘non-performance’
all the other clauses in the agreements governing the consequences of
supplying defective goods
must be ignored. In both cases the
court first made findings as to the facts pertaining to the
transactions and then decided
that on those facts the exemption
clauses did not apply. In the present case, where Transnet has
not cancelled the two agreements,
its right to claim damages (or any
other amounts) must be found in the terms of the two agreements.
[57]
In relevant part, Clause 13 of the Master Agreement (as amended)
provides as follows:
‘
DEFECTIVE
GOODS
Notwithstanding any
certificate and/or receipt that may have been issued by or on behalf
of Transnet either in the Republic of South
Africa or overseas, Goods
will be accepted at the place of delivery or at the port of shipment,
as specified in the Agreement,
only as regards outward condition
of packages
and
Transnet retains the right to reject the Goods
supplied,
on or after arrival at the place to which they were
consigned, or after they have been placed in use in the Republic of
South Africa,
should they be found to be defective.
13.1
The Supplier warrants that the goods shall contain al [sic] necessary
mechanisms and shall be fit and sufficient
for regular use in
accordance with the Supplier’s specifications but makes no
further warranty. The Supplier shall
not be liable for damages
resulting from specialists or unusual requirements of the purchaser
save as accepted in writing by the
Supplier.
The Supplier
shall at its option either compensate the purchaser or replace
without charge goods proven to be defective, the extent
of which
shall be determined by the Supplier. Claims arising out of this
warranty will only be recognized if written notice
is given to the
Supplier within 30 days of any defect or unsuitability becoming
apparent, and in any event (
the following words deleted:
‘within 6 months after delivery of the defective or
unsuitable goods’) 12 months from commissioning or 18 months
from
delivery, whichever is sooner.
No warranties or
representation, whether express or implied, other than those recorded
herein are given or made by the Supplier
in connection with the
goods. The warranties herein are given and accepted in lieu of
all other warranties,
including warranties of fitness for purpose
for a particular purpose, and whether oral, expressed, implied or
statutory.
13.2
If such goods are rejected, the Supplier will pay the following costs
–
13.2.1 …
13.2.2 for Goods
manufactured overseas, the Supplier shall pay all replacement costs
including the overseas inland transport cost,
freight and insurance
charges incurred plus railage or other inland transport costs from
the Republic of South Africa ports to
the place where the Goods have
been rejected by Transnet, including handling charges, storage,
landing charges, customs duty and
surcharges, if leviable.
13.3
If Transnet requires rejected Goods to be replaced, the Supplier
shall, when called upon to do so, arrange prompt replacement of
the
Goods, within the prescribed manufacturing lead times for such Goods,
as indicated in Annexure A.
13.4
If Goods are found to be defective but the defects are, in the
opinion of Transnet, not of such a serious
a nature as to warrant
total rejection of the Goods, the Supplier shall, when called upon to
do so, remedy or make good such defects
at his own cost, or Transnet
may remedy or make good such defects at the request of the Supplier,
and recover from the Supplier
all costs or expenses reasonably
incurred by it in doing so.
13.5
Should the Supplier fail, when called upon to remedy or make good
such defects within a reasonable time or to request Transnet to
do
so. Transnet may proceed to remedy or make good such defects
and thereafter recover from the Supplier all such costs and
expenses
as aforementioned.
13.6
Any amount recoverable from the Supplier in terms of this clause may,
without prejudice to any
other legal remedies available to Transnet,
and after 30 days written notice be deducted in whole or in part from
any monies in
the hands of Transnet which are due for payment to the
Supplier.’ (Tenova’s emphasis added.)
Clause 9 of the
General Conditions of Purchase also contains warranty. It
states:
‘
9
Warranty
Without prejudice to
any other rights of the Purchaser under these conditions,
the
Supplier warrants that:
·
all goods delivered will be free from
defective materials or workmanship;
·
this warranty shall survive any inspection,
delivery, acceptance or payment by the Purchaser;
·
the goods will remain free from defects for a
period of two year [sic] (unless another period is stated in the
Order) from acceptance
of the Goods by the Purchaser.
·
the warranty/guarantee will be effective
twelve (12) Months from date of commissioning or eighteen (18) months
from date of delivery,
whichever date comes first.’
(Emphasis
added)
[59]
As pointed out in the Award ([25]), parties to a contract have the
right to regulate
,
limit or expand by arrangement between
themselves the consequences of any prospective breach (Thoroughbred
Breeders Association
v Price Waterhouse
2001 (4) SA 551
(SCA) at
583A: Victoria Falls & Transvaal Power Company Ltd v
Langlaagte Mines Ltd
1915 AD 1
at 46). This means that Transnet
cannot select from the two clauses the parts that are essential to
its claims and ignore
the remaining parts that regulate the
consequences of the Goods being proved to be defective and the
procedure that must be followed.
Both clause 13.1 and clause 9
contain provisions that in effect impose a time bar on claims based
on the Goods supplied being found
or proved to be defective.
Clause 13.1 further provides for the procedure to be followed by the
Purchaser to ensure that
a claim arising out of goods proved to be
defective is recognised.
[61]
With regard to the argument that the word ‘Goods’ in the
clauses refers to
the Goods purchased: i.e. valves that comply
with the specifications, the principal flaw in the argument is the
definitions
contained in the Master Agreement and the General
Conditions of Purchase. Clause 2.5 of the Master Agreement
defines ‘Goods’
as ‘the material/products as
specified in the Schedule of Requirements at Annexure A hereto’.
Since Transnet
has not attached the Schedule of Requirements to the
Master Agreement or even alleged that it exists, this definition is
meaningless.
Clause 1 of the General Conditions of Purchase
defines ‘the Goods’ as ‘the articles and things
described and
to be supplied under this Order’. Whatever
their legal force, these clauses show the goods did not have to
comply with
the specifications in order to be ‘Goods’.
The second flaw is that there would be no need for provisions to
dealt
with ‘defective Goods’ if they had to comply with
the specifications to qualify as ‘Goods’.
[62]
With regard to the second argument relating to the interpretation of
clause 13 and the
contention that clause 13.1 provides for a specific
remedy only applicable in the circumstances outlined in clause 13.1
and that
the provisions in clause 13.1 do not affect in any way the
right given by the Preamble to clause 13 to reject the Goods if they
are found to be defective, the problem is that it contradicts the
allegations in the 4
th
SOC that indicate that clause 13.1
is an essential element of the cause of action. On the strength
of Transnet’s own
allegations it follows that the procedure
prescribed in the clause must be followed and that this must happen
as stipulated.
[63]
A further consideration is that, although the Preamble to clause 13
gives a right to reject
the Goods if they are found to be defective,
this right is not limited in any way. In its terms it can be
exercised at any
time from the time that the Goods have arrived at
the place to which they were consigned and even after they have been
placed in
use. This could be many years. Clause 13.1, on
the other hand, provides that where Goods have been proved to be
defective
the Supplier (Tenova) shall at its option either compensate
the Purchaser (Transnet) or replace the Goods without charge.
The clause also provides for a time bar for a claim arising out of
the warranty. (Clause 9 also provides that the warranty
that it
records will only be effective for a period of time set out in that
clause.) Apart from the fact that the Preamble
to clause 13 and
clause 13.1 are both set out in the same clause, there is a
contextual and linguistic link between the two clauses.
They
both only come into operation when the Goods are found or proved to
be defective. The time bar in clause 13.1 must affect
the right
of Transnet to reject the Goods at any time after they have arrived
at the place to which they were consigned or have
been placed in
use. Clause 13.1 was specially negotiated and it was agreed
that it would replace the existing clause 13.1
which dealt only with
Goods that were rejected owing to latent defects becoming apparent
during operations or preparations necessary
to put the Goods into
use. Clause 13.1 deals with much more than that. It was
inserted into the printed Master Agreement
and although it is not
handwritten it must prevail when there is any contradiction between
it and the other provisions in the printed
Master Agreement.
The reason why Clause 13.1, which was specially inserted into the
Master Agreement and is called a ‘Special
Term and Condition’
in the Purchase Order (4
th
SOC 68/19 and 203/19) must
prevail was explained in Simmons v Hurwitz
1940 WLD 20
at 24-25:
‘
Where
a contract consists of written words superadded to a printed form the
written words while “subjects to be governed in
point of
construction by the language and terms with which they are
accompanied are entitled nevertheless, if there should be reasonable
doubt upon the sense and meaning of the whole, to have a greater
effect given to them than to the printed words, inasmuch as the
written words are the immediate language and terms selected by the
parties themselves for the expression of their meaning, and
the
printed words are a general formality adapted equally to their case
and that of all other contracting parties upon similar
occasions and
subjects”. … But it is of course, a rule of
construction applicable to all cases where a printed
form of contract
is employed. The rule requires the Court to attempt to
reconcile the writing with the print; and in the
case of a reasonable
doubt to allow the written words to prevail as the expression of the
intention of the parties. … I
am unable to effect any
reconciliation of the written with the greater portion of the printed
words of clause 25. I must
look at the matter as if the parties
had drawn their pen through so much of the printed matter as is
irreconcilable with the writing
– that is the whole of clause
25, with the exception of para. 5’. (See also Badenhorst
v van Rensburg
1985 (2) SA 321
(T) at 336I-J; Bull v Executrix
Estate Bull and Another
1940 WLD 133
at 136: Wessels’ Law
of Contract in South Africa Vol 1 paras 1981 and 1982.) The
Preamble to clause 13 must therefore
be read subject to the time bar
in clause 13.1. It must also be read subject to the time
constraints in clause 9. It
is clear that both clause 13.1 and
clause 9 were in force (as alleged in the 4
th
SOC)
and that the exclusion of other warranties in clause 13.1 referred to
other warranties in the Master Agreement. Clause
10 of the
Master Agreement contains such a warranty. But after the
amendment of the Master Agreement the parties agreed on
the new
warranty in the General Conditions of Purchase.’”
Findings
by the Appeal Tribunal
[11]
Transnet appealed against the second award of the Arbitrator to the
Appeal Tribunal. On claim 1 the Appeal
Tribunal found that to make a
finding on complete non-performance could only be made on trial after
hearing expert evidence. Such
evidence may well have brought the case
squarely within the
Cladall
[2]
and
Freddy
Hirsch
[3]
matters. The Appeal
Tribunal found the exception to claim 1 should have been dismissed.
[12]
Pertaining to claim 2 the Appeal Tribunal found that the Arbitrator
had interpreted clauses 9 and 13 without
the aid of any extrinsic
evidence. Claim 1 was based on complete non-performance with no
reference to clauses 9 and 13.1 of the
agreement: i.e. Transnet
had not made these clauses part of its claim. The proviso in clause
20 was a question of interpretation
which could not be done at
exception stage.
[13]
In respect of Claim 2 which was based on Clause 13’s Preamble,
13.1 and 13.2 the Arbitrator held that
because Transnet had not
alleged material facts which justify the conclusion that there was
factual non-performance it was not
necessary to deal with the
argument that the goods supplied were not the “
goods”
bargained for, Clauses 9 and 13.1 did not apply. The Arbitrator
did however proceed to interpret the clauses and found the clauses
could not apply to defective goods. The Appeal Tribunal found that
this issue could not be decided on exception without the aid
of
extrinsic evidence. Evidence relevant to context could well inform
the meaning of the contract and clause 13. It further found
that the
direction in which the law relating to the interpretation of written
contracts had of late moved militated against the
interpretation of
such contracts at exception stage.
[14]
The Appeal Tribunal thus found that the exceptions to claim 1 and 2
was to be dismissed.
The
issues to be decided
The
Rule 9 issue
[15]
I find it prudent to deal with the submissions of Tenova first. The
argument went that the mechanism to challenge
the appointment of the
Arbitrator was in terms of the AOA rules. This was expressly agreed
in the Arbitration agreement in clauses
5 and 6 of the Arbitration
Agreement which provide as follows:
“
5.1
The Parties agree to appoint Retired Judge B Southwood (‘Southwood’)
as Arbitrator once AFSA’s
mandate has been withdrawn.
5.2
Any disputes arising out of the appointment of the Arbitrator shall
be dealt with in accordance with
the Association Rules.
6
The Parties agreed that the Arbitration procedure will be in
accordance with the Association
Rules.”
[16]
Rule 9 of the AOA rules reads as follows:
“
9
Challenge
9.1
If any Arbitrator:
9.1.1
falls seriously ill, or becomes unable or unfit to act; or
9.1.2
lacks the necessary independence; or
9.1.3 for
any other reason ought not to continue as Arbitrator (e.g. lacks
impartiality); the Chairman of the Association
or his nominee from
time to time shall, upon application as provided below, subject to
Rule 9.7, convene a committee consisting
of not less than three
members (‘the Committee’) who may revoke the Arbitrator’s
appointment and appoint another
Arbitrator.
9.2
A party who intends to challenge an Arbitrator in terms of Rule 9.1,
shall make written application
to the Chairman of the Association
within 10 days of him becoming aware of any circumstances referred to
in Rule 9.1, which application
will set out fully the reasons for the
challenge, failing which such party shall forfeit the right to make
such challenge.
A copy of the application shall simultaneously
be served on the other party.
9.3
Within 10 days of the date of receipt by the applicant of notice from
the Association as to the relevant
fee, the applicant shall lodge
with the Association the relevant fee as determined by the executive
committee of the Association
from time to time.
9.4
Failure to lodge the fee shall render the challenge invalid.
9.5
Any other party to the reference who receives an application referred
to in Rule 9.2 and who wishes
to oppose such application shall within
10 days of receipt by him of the application submit a written
response fully motivating
its opposition.
9.6
A copy of the application and any reply shall be served by the
respective parties on the Arbitrator
who shall be entitled within 10
days of receipt thereof to reply in writing.
9.7
Unless the parties agree to the withdrawal of the Arbitrator, the
Committee will decide the challenge.
9.8
Where an Arbitrator is to be replaced and the parties are unable to
agree on the replacement arbitrator,
the Committee shall decide
whether or not to follow the original nominating process or to
appoint a replacement arbitrator.
9.9
The Committee shall give directives regarding the costs of the
challenge and, if the challenge is successful,
the amount of fees and
expenses to be paid for the former arbitrator’s services, but
shall only give directions regarding
the costs of the arbitration
proceedings if the parties so agree.
9.10
Unless otherwise agreed by the parties or determined by the new
Arbitrator, after giving the parties the
opportunity to address him,
the Arbitrator shall continue with the proceedings as if he had been
the Arbitrator from the commencement
of the reference.”
[17]
It was submitted that it was incumbent on a Court to respect the
choices made by parties to refer a matter
to arbitration.
[4]
Reliance was also placed on the judgment of Rogers J in
Hyde
Construction CC v Deuchar Family Trust
and
Another
2015
(5) SA 388
(WCC) at par [69]:
“
In any event,
and if rule 9 were intended to be exclusive, the court a quo was
nevertheless in my view justified in exercising its
residual
jurisdiction to entertain the removal application. Even in relation
to the main arbitral dispute, the court has the jurisdiction
to
determine the dispute on good cause shown (s3(2) of the Act) …
a court will not lightly entertain a dispute which the
parties have
agreed to submit to arbitration. The party seeking to invoke the
court’s residual jurisdiction must make out
a ‘very
strong’ case or provide ‘compelling reasons’…”
Tenova argued that
Transnet had not provided any reasons for refusing to abide by the
Arbitration Agreement, let alone compelling
reasons.
[18]
As for Transnet’s response that the AOA had no inkling about
this arbitration as the parties did not
subject them to the oversight
of the AOA, or approach the AOA for the appointment of the
Arbitrator, it was submitted that a non-administered
arbitration does
not imply that Rule 9 of the AOA Rules does not apply. A
self-administered arbitration does not imply that parties
cannot
through application of the AOA Rules mandate the AOA to execute
certain functions such as a challenge to the Arbitrator.
[19]
The reliance by Transnet on the matter of
Hyde
is misplaced as
the facts are distinguishable. The distinguishable fact is that the
application of the AOA Rules was the doing
of the Arbitrator and not
as a result of an agreement between the parties. In this matter the
parties agreed to the AOA Rules being
applicable. As a result, all
the remaining remarks of Rogers J were
obiter
. And, no
compelling reasons have been set out why Rule 9 was not invoked.
Transnet’s
argument on the Rule 9 issue
[20]
It was submitted that Rule 9 should be read with Rule 8 which
provides as follows:
“
8
Appointment
of Arbitrator
8.1
Except as provided in Rule 8.2, when any agreement requires the
Association to appoint or nominate an
Arbitrator the Association may
appoint or nominate an Arbitrator.
8.2
Should a dispute arise as to whether the Association has authority to
make an appointment or nomination
of an Arbitrator or should it
appear form the application to the Association that the Association
may not have the authority to
appoint or nominate an Arbitrator, the
Association will, in its sole discretion, decide whether or not to
make the nomination or
appointment.
8.3
Upon accepting appointment, a prospective Arbitrator shall sign a
statement to the effect that there
are no grounds known to him which
are likely to give rise to justifiable doubts regarding his
independence and impartiality, and
the Arbitrator must further
disclose in writing any facts or circumstances which may be of such a
nature as to call into question
the Arbitrator’s independence
or impartiality in the eyes of the parties. A copy of this
statement must be transmitted
to each party ..
8.3.1
Within 5 days of the receipt of such disclosure, the parties shall
state in writing if they intend to challenge
the Arbitrator;
8.3.2 The
provisions of Rule 9 shall apply to the challenge of an Arbitrator on
the basis of circumstances disclosed
by the Arbitrator;
8.3.3 A
party who fails to challenge an Arbitrator within the period of time
specified in Rule 8.3.1 shall not be permitted
to challenge the
Arbitrator based on the circumstances already disclosed by the
Arbitrator.
8.4
Where an Arbitrator, duly appointed or nominated by the Association
dies, the Association, may, unless
the Parties otherwise agree,
appoint another Arbitrator to continue with the arbitration.
8.5
Rule 9.10 applies to a new Arbitrator appointed under Rule 8.4.”
From a reading of Rule 8
and 9 it is plain that only when the power to appoint an Arbitrator
is given to the AOA it has the power
to remove the Arbitrator it so
appointed. Axiomatically where the Arbitrator was not appointed by
the AOA, the AOA has no power
to remove the Arbitrator. The AOA has
no
locus standi
in this matter.
[21]
It was further submitted that Rule 9 neither replaces nor ousts
s13(2) of the Act. Rule 9 is not mandatory,
only permissive. A party
that does not lodge a Rule 9 application timeously cannot proceed in
terms of Rule 9, but it does not
imply that that party has eschewed
its rights in terms of s13(2) of the Act.
[22]
Support for the above submission was found in the
Hyde
-matter
where the issue was whether the parties had concluded an arbitration
agreement incorporating the rules excluded the operation
of s13(2) of
the Act. In that matter both the Arbitrators were appointed by
the AOA. The Deuchar Family Trust launched an
application for the
second Arbitrator’s removal in terms of s13(2) of the Act. The
Court found:
“
On balance,
therefore, I think Blignaut J was right to find that rule 9 was not
inconsistent with the parallel operation of the
Act and that it did
not serve to exclude the operation of s 13(2).”
[5]
Decision
on Rule 9
[23]
The surrounding circumstances to this arbitration is that the parties
did not want to incur fees and costs
by involving the AOA or AFSA.
The parties agreed to self-administer the arbitration. I thus
understand this arbitration not to
be administered by the AOA; it is
unaware of this arbitration and the arbitration is not under its
auspices. The parties did not
utilise the AOA rules to appoint the
Arbitrator.
[24]
The only clause in the agreement that can support Tenova’s
interpretation that the removal is governed
by the AOA rules is
clause 6: “
the Arbitration procedure will be in
accordance with the Association Rules.”
I accept that as
first blush there could be scope for such interpretation, but not
when the surrounding circumstances are taken
into account, when the
arbitration agreement is interpreted and upon a reading of Rule 8 and
Rule 9 of the AOA rules.
[25]
Upon an interpretation of the arbitration agreement between the
parties it is clear that it is a self-regulated
arbitration with the
arbitration to only follow the format or process of the AOA rules.
The only rule of the AOA that the parties
specifically invoked was if
there was a dispute arising from the appointment of the Arbitrator.
The agreement did not invoke Rule
9 to remove the arbitrator. If the
intention of clause 6 was to invoke all the rules of the AOA then
clause 5.2 would have been
redundant. If the AOA rules as a whole was
to govern this arbitration, agreeing to this clause pertinently,
would have been unnecessary.
The only inference is that the only rule
of the AOA that was specifically incorporated was the appointment of
the Arbitrator.
[26]
This conclusion is fortified by a reading of rules 8 and 9 of the AOA
where the power to appoint an Arbitrator
is in the hands of the AOA,
then it has the power to remove the Arbitrator. When the Arbitrator
was not appointed by the AOA it
would be extraordinary to have the
power to remove the Arbitrator, more so when the AOA is not
administering the arbitration process.
Where the AOA removes an
Arbitrator and the parties cannot agree to an appointment of a
replacement Arbitrator the committee of
the AOA shall decide whether
or not to follow the original nominating process or to appoint a
replacement Arbitrator.
[6]
The appointment of the Arbitrator by the AOA is exactly what the
parties wanted to avoid. The interpretation of Rules 8 and
9
militates against the interpretation Tenova is supporting.
[27]
Rule 9 is permissive and not mandatory. It does not exclude the
operation of s13(2) of the Act. I support
the Full Court decision of
Hyde
where Rogers J concludes as follows:
“
[67]
Rule 9 does not state that it operates to the exclusion of s 13(2).
It affords to a party the right to bring
an application to the
Association to appoint a committee to consider the removal of an
arbitrator on specified grounds. It
is probable that those
grounds are as wide as those which a court could take into
consideration in an application in terms of s
13(2) but this does not
give rise to a necessary inference that the rule 9 procedure was
mandatory and exclusive rather than permissive.
As I have said,
the matter with which rule 9 deals, namely the removal of an
arbitrator, is not concerned in any direct way with
the arbitral
dispute and matters truly interlocutory to the determination of the
dispute, and therefore the natural inference that
the parties
intended to exclude the court’s jurisdiction is not present.
If a party fails to lodge the rule 9 falls
away. Non constat
that he loses his right to approach the court in terms of s 13(2).
[28]
The argument that this finding was
obiter
because the facts are
distinguishable from this matter is unsound. I have already found
that the parties’ reference to the
AOA rules were agreed to by
the parties only to use as guide for the arbitration process, not to
render it applicable. The fact
that in the
Hyde
matter the Arbitrator
made the AOA rules applicable in fact supports the contention of
Transnet, because even if the Rules where
applicable, which it is
not, then Transnet could have used the parallel procedure of s13(2)
of the Act. In fact, Roger J finds
‘…
assuming
in favour of Hyde that the arbitration agreement between the parties
incorporated rule 9 …”
[7]
,
just as Tenova argues, the Court still found that s13(2) could be
used as a mechanism to remove the arbitrator.
[29]
I also align myself with Rogers J in the
Hyde
matter
and find that there is a strong case to invoke this Court’s
residual jurisdiction. Transnet is not asking this Court
to
adjudicate the main dispute or a procedural matter ancillary to the
main dispute, “
but
a more fundamental question as to the proprietary of Du Toit’s
continued role as the arbitrator.”
[8]
Another compelling reason
is that the parties did not agree that the removal of the Arbitrator
must be done in terms of the AOA
rules.
Decision
on the perception of bias
Arguments
on behalf of Transnet
[30]
The complaint is that the Arbitrator made findings on expert matters
contrary to the express findings of
the experts reports attached to
the SOC. He interpreted correspondence without hearing evidence
thereon. He found the claims were
not competent because he determined
that because the valves looked like valves and fitted into the
pipeline it was sufficient to
amount to compliance with the Agreement
and there was not complete non-performance. He thus interpreted the
contract on exception.
This has all led to the conclusion that he has
a final fixed view of the meaning of the Agreement and a final and
fixed view on
whether the valves were not at all what Transnet
bargained for. He made final findings of fact contrary to the express
wording
of the SOC and thus a final view on the merit of Transnet’s
claim.
[31]
He would not be able to divest himself from the factual findings he
made on the valves, being not defective
or non-compliant, simply
because he had made such a finding.
[32]
The application is not based on the incorrect findings as highlighted
by the Appeal Tribunal, but the Arbitrator’s
conclusions and
findings giving rise to a perception of bias if the matter is to
continue before him. He, contrary to his duty
when considering
exceptions, did not accept the pleaded case of Transnet on the SOC.
[33]
It was submitted that the bias of the Arbitrator is thus manifest in
expressing his absolute and final views
even before the pleadings had
closed. He in so many words said Transnet’s claim was hopeless.
He did not order that the SOC
might be amended but in fact dismissed
Transnet’s claims 1 and 2.
[34]
The fact that the matter now may proceed to trial with witnesses does
not alter the situation because it
would serve before the same
Arbitrator and Transnet cannot take comfort that the Arbitrator will
be rid of his views.
The
submissions on behalf of Tenova
[35]
The argument went that Transnet knew that to adjudicate an exception
would give rise to a final award on
the pleadings alone. This award
on the exception would be final, but appealable and thus the
arbitrator could be wrong. If an Appeal
Tribunal finds the Arbitrator
was wrong and his findings are set aside, the proceedings would be
referred back to the same Arbitrator.
[36]
Being wrong cannot be equated to bias or a perception of bias. The
Arbitrator would be guided by the finding
of the Appeal Tribunal in
his further awards. The Arbitrator found the allegation of
non-performance a conclusion of law and not
of fact. The Arbitrator
will now be taking the conclusion of the Appeal Tribunal into account
and will now regard the allegation
of non-performance as a factual
issue to be resolved through evidence.
[37]
The Arbitrator did not have the benefit of the decisions of
University of Johannesburg v Auckland Park Theological Seminary
and Another
2021 (6) SA 1
(CC) and
Capitec Bank Holdings Ltd
and Another v Coral Lagoon Investments 194 (Pty) Ltd
and
Others
2022 (1) SA 100
(SCA) that the Appeal Tribunal relied on
because these decisions were made after the Arbitrator had made his
award.
[38]
The Arbitrator’s determinations were only definitive in the
exception proceedings on whether the pleadings
made out a cause of
action, this cannot constitute a
prima facie
view. Evidence
will now be presented and he will make a decision on the evidence
led. The Arbitrator will thus make a decision
on a different basis.
[39]
Although a Court does not ordinarily dismiss a claim on exception,
but grants the unsuccessful party an opportunity
to amend its
pleading, there are limits to the rule. In this matter the Arbitrator
did so based on Transnet’s recurrent failure
to formulate a
valid cause of action.
Decision
on bias or perception of basis
[40]
When a court or Arbitrator is confronted with
an exception wherein it is averred that no cause of action is made
out in the summons
the Court must adopt the approach as set out by
Makgoka J in
Living Hands v Ditz
2013
(2) SA 365
(GSJ) at 374G as follows:
“
Before
I consider the exceptions, an overview of the applicable general
principles distilled from case law is necessary:
(a)
In considering an exception that a
pleading does not sustain a cause of action, the court will accept,
as true, the allegations
pleaded by the plaintiff to assess whether
they disclose a cause of action.
(b)
The object of an exception is not to
embarrass one’s opponent or to take advantage of a technical
flaw, but to dispose of
the case or a portion thereof in an
expeditious manner, or to protect oneself against an embarrassment
which is so serious as to
merit the costs even of an exception.
(c)
The purpose of an exception is to
raise a substantive question of law which may have the effect of
settling the dispute between
the parties. If the exception is not
taken for that purpose, an excipient should make out a very clear
case before it would be
allowed to succeed.
(d)
An excipient who alleges that a
summons does not disclose a cause of action must establish that, upon
any construction of the particulars
of claim, no cause of action is
disclosed.
(e)
An over-technical approach should be
avoided because it destroys the usefulness of the exception
procedure, which is to weed out
cases without legal merit.
(f)
Pleadings must be read as a whole and
an exception cannot be taken to a paragraph or a part of a pleading
that is not self-contained.
(g)
Minor blemishes and unradical
embarrassments caused by a pleading can and should be cured by
further particulars.” (footnotes
omitted)
The
Courts have also found that exceptions are not to be dealt with in an
over-technical manner and a court looks benevolently,
instead of
over-critically at a pleading. Courts as a general rule will not
decide exceptions on fact bound issues. Where an exception
is raised
on the ground that a pleading lacks averments necessary to sustain a
cause of action, the excipient is required to show
that upon every
interpretation that the pleading in question can reasonably bear, no
cause of action is disclosed. “
It
is trite that when pleading a cause of action, the pleading must
contain every fact which would be necessary for the plaintiff
to
prove, if traversed, in order to support his right to judgment (facta
probanda). The facta probanda necessary for a complete
and properly
pleaded cause of action importantly does not comprise every piece of
evidence which is necessary to prove each fact
(being the facta
probantia) but every fact which is necessary to be proved.”
[9]
[41]
The Appeal Tribunal found that the Arbitrator made a determination
without the necessary factual expert evidence
on Claim 1. After
hearing expert evidence, the matters of
Cladall
and
Freddy
Hirsch
may squarely address claim 1. Claim 1 had not invoked
clauses 13.1 and 9 of the Agreement for its claim for complete
non-performance.
The Arbitrator was wrong in concluding that those
clauses were invoked. Clause 20 requires interpretation which
could not
be done at exception stage. In relation to claim 2 the
Arbitrator interpreted clauses 13 and 9 without the aid of extrinsic
evidence
and context could well inform the meaning of the contract.
The Arbitrator dismissed these claims.
[42]
The question is whether the findings of the Arbitrator can create a
perception of bias. The test for bias
was set out in
by
Du Plessis J who held that an Arbitrator may be removed from office
if, on the proven facts, “‘
reasonably
and right-minded persons, applying themselves to the question and
obtaining thereon the required information’ would
conclude,
‘viewing the matter realistically and practically and having
thought the matter through’, that there is a
reasonable
apprehension that the Arbitrator is biased.”
[10]
An arbitrator will
thus be removed when a reasonable person lay litigant might consider
that there exists a possibility of prejudice.
[11]
[43]
In principle this test was endorsed in
President
of the Republic of South Africa and Others v South African Rugby
Football Union
[1999] ZACC 9
;
1999
(4) SA 147
(CC) where the test was formulated as: “…
whether
a reasonable, objective and informed person would on the correct
facts reasonably apprehend that the Judge has not brought
or will not
bring an impartial mind to bear on the adjudication of the case, that
is a mind open to persuasion by the evidence
and the submissions of
counsel.”
[12]
[44]
When an Arbitrator is confronted with an exception on whether a claim
sets out a cause of action or not,
deciding it does not set out a
cause of action, will not
per se
render the Arbitrator bias.
This is so, because that is what a determination on exception is
required from the Arbitrator. The
mere fact that the Arbitrator is
then on appeal found to be wrong in his determination will also not
per se
bring about a perception of bias.
[45]
Each case will have to be determined on its own set of facts. It has
to be factored in that Transnet had
amended it SOC after the first
award, in addition to the two previous versions of its SOC before the
first exception. Tenova submitted
these amendments is the reason why
the Arbitrator did not afford Transnet a further amendment to its
SOC, but dismissed the claim.
But therein lies the rub; this fact
renders it prejudicial to Transnet because the Arbitrator has
determined that Transnet do not
have competent claims and therefore
did not afford them an opportunity to amend the SOC of claims 1 and
2. He found as follows:
“
[97]
In view of the findings in the award, it is inexplicable why
Transnet, if not only out of a sense of excessive
caution, did not
allege the necessary facts to show that it is entitled in terms of
the relevant contractual provisions to claim
the general and special
damages claimed. The only reasonable inference is that it
cannot do so. In paragraph 60 of
the 4
th
SOC Transnet
alleges that it made payment for all the valves ordered and supplied
Tenova under the two agreements but it does not
allege when the
delivery of the valves took place. The agreements specify when
the delivery was to take place and when payment
was to be made.
For example, clause 4 of the first agreement’s Contract Data
(4
th
SOC 70)
provides that the goods are to be delivered on or before 17 June 2010
and clause 3.1 of the General Conditions of Purchase
(4
th
SOC 63)
specifies the payment milestones: 90 % of the total purchase
order value upon satisfactory acceptance and confirmation
of delivery
of the Goods to the designated site and 10 % of the total purchase
order value on completion, approval and acceptance
of all the final
documentation and data books. The delivery date for the last
amendment was about 30 November 2011 (4
th
SOC 187 and
189) and the payment milestones did not change. The relevant
dates in the second agreement were 20 December 2010
for delivery in
terms of the Purchase Order (4
th
SOC 205 and
216-217) and approximately 31 July 2011 in terms of the last
amendment (4
th
SOC 260 and
262). The payment milestones remained the same as those for the
first agreement.
[98]
In all the circumstances outlined above it appears to be clear that
Transnet is unable to plead facts that
show that it is entitled to
claim damages or any other amount based on the failure to comply with
the warranties by delivering
valves that did not comply with the
specifications for the material to be used in the manufacture of the
valves and were therefore
defective. It has no viable
alternative to what it has already pleaded. As already
mentioned if leave to amend is not
given it follows that the claims
must be dismissed with costs.”
[46]
A reasonable objective person informed of this finding will apprehend
a bias of the Arbitrator if he is to
continue with this matter. The
Arbitrator had definitively found that Transnet had no claim for
damages or any other claim and
no viable alternative to what it had
it pleaded. Just on this finding alone I have to agree with Transnet
that there is a reasonable
apprehension of bias. I accordingly do not
find it necessary to address the other facts raised from which bias
can be perceived,
except to remark that the fact that he made factual
findings contrary to expert reports attached to the SOC will compound
this
perception as well as interpreting letters from which he
concluded there was no cause of action.
Does
this application comply with s13(2) of the Act?
[47]
Section
13(2)
of the Act provides:
“
(a) The court
may at any time on the application of any party to the reference, on
good cause shown, set aside the appointment of
an arbitrator or
umpire or remove him from office.
(b) For the purposes
of this subsection, the expression 'good cause', includes failure on
the part of the arbitrator or umpire to
use all reasonable dispatch
in entering on and proceeding with the reference and making an award
or, in a case where two arbitrators
are unable to agree, in giving
notice of that fact to the parties or to the umpire.”
[48]
I am satisfied that a perception of bias being found is good cause
for the setting aside of the appointment
of the Arbitrator, the
Second Respondent, and that he be removed from the Arbitration.
[49]
I accordingly make the following order:
49.1
The second respondent’s appointment as arbitrator is set aside
and the second respondent is removed
from his office as Arbitrator in
the arbitration proceedings between the applicant and the first
respondent;
49.2
The first respondent is ordered to pay the costs of this application.
S.
POTTERILL
JUDGE
OF THE HIGH COURT
CASE
NO: 2022-006083
HEARD
ON:
15
August 2023
FOR
THE APPLICANT:
ADV.
P. DANIELS SC
ADV.
A. GOVENDER
ADV.
A. KOHLER
INSTRUCTED
BY:
Cliffe
Dekker Hofmeyr Inc.
FOR
THE FIRST RESPONDENT:
ADV.
B.W. BURMAN SC
ADV.
A.T.W. ROWAN
INSTRUCTED
BY:
Edward
Nathan Sonnenbergs Inc.
DATE
OF JUDGMENT:
19
October 2023
[1]
42 of 1965
[2]
Cladall
Roofing (Pty) Ltd v SS Profiling (Pty) Ltd
(515/08)
[2009] ZASCA 92
;
[2010] 1 All SA 114
(SCA) (14 September 2009)
[3]
Freddy
Hirsch Group (Pty) Ltd v Chickenland (Pty) Ltd
2011
(4) SA 276 (SCA)
[4]
Lufuno
Mphaphuli & Associates (Pty) Ltd v Andrews and Another
2009
(4) SA 529
(CC) par [219]
[5]
Paragraph [68]
[6]
Rule 9.8
[7]
Paragraph [60]
[8]
Paragraph [71]
[9]
[9]
Merb
(Pty) Ltd v Matthews
(2020/15069)
[2021] ZAGPJHC 693 (16 November 2021)
[10]
Factaprops
(Pty) Ltd v Strydom Bouers CC en Andere
2003
JDR 0770 (T)
[11]
Orange
Free State Provincial Administration v Ahier and Another;
Parys Municipality v Ahier and Another
1991
(2) SA 608 (W)
[12]
Paragraph [48]
sino noindex
make_database footer start
Similar Cases
Transnet SOC Limited v Gijima Holdings (Pty) Ltd (Leave to Appeal) (2025-075722) [2025] ZAGPPHC 1367 (12 December 2025)
[2025] ZAGPPHC 1367High Court of South Africa (Gauteng Division, Pretoria)100% similar
Transnet SOC Limited v Gijima Holdings (Pty) Kimited (075722/2025) [2025] ZAGPPHC 1108 (16 October 2025)
[2025] ZAGPPHC 1108High Court of South Africa (Gauteng Division, Pretoria)100% similar
Transnet SOC Limited v Gijima Holdings (Pty) Kimited (075722-2025) [2025] ZAGPPHC 690 (30 June 2025)
[2025] ZAGPPHC 690High Court of South Africa (Gauteng Division, Pretoria)99% similar
Transnet SOC Limited v Mafahleni Engineers & Project Managers CC and Another (57163/2022) [2022] ZAGPPHC 184 (1 April 2022)
[2022] ZAGPPHC 184High Court of South Africa (Gauteng Division, Pretoria)99% similar
A.M v Transnet SOC Ltd (99978/2015) [2024] ZAGPPHC 361 (25 March 2024)
[2024] ZAGPPHC 361High Court of South Africa (Gauteng Division, Pretoria)99% similar