Case Law[2023] ZAGPPHC 1928South Africa
Mavhungu v Passenger Rail Agency of South Africa (83450/14) [2023] ZAGPPHC 1928 (20 November 2023)
Headnotes
the shipping companies owe a duty to the public to have safe gangways and they cannot escape liability if a passenger or visitor does not exercise the utmost care. The court further continued to find that the appellant was negligent since he had knowledge that the gangway was dangerous, however with this knowledge he proceeded to use the gangway. With that being said, the defendant’s witnesses as I read the papers, they testified that the passengers embarked the train using gainsay which is not allowed, I therefore believe that the proper terms to be used is gangway.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 1928
|
Noteup
|
LawCite
sino index
## Mavhungu v Passenger Rail Agency of South Africa (83450/14) [2023] ZAGPPHC 1928 (20 November 2023)
Mavhungu v Passenger Rail Agency of South Africa (83450/14) [2023] ZAGPPHC 1928 (20 November 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_1928.html
sino date 20 November 2023
REPUBLIC
OF SOUTH AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
Case
No: 83450/14
REPORTABLE: NO
OF
INTEREST TO OTHER JUDGES:NO
REVISED:
NO
Date:
20 November 2023
In
the matter between:
FHATUWAMNI
MAVHUNGU
Plaintiff
And
PASSENGER
RAIL AGENCY OF SOUTH AFRICA
Defendant
Delivered: This judgement
was prepared and authored by the Judge whose name is reflected and is
handed down electronically by circulation
to the Parties /their legal
representatives by email and by uploading it to the electronic file
of this matter on Case Lines. The
date for hand-down is deemed to be
20 November 2023
JUDGMENT
BOTSI-THULARE
AJ
Introduction
[1]
This is a personal injury claim brought by
Fhatuwani
Mavhungu (plaintiff), an adult male in his legal capacity,
against
Passenger Rail Agency of South Africa (PRASA) (defendant), a South
African State-Owned Enterprise responsible for passenger
rail
services in the Republic.
The
claim arises from the damages incurred when the plaintiff sustained
injuries in an incident at Mears Station, Pretoria. The
matter was
initially scheduled for trial on 24 April 2023; however, it underwent
multiple postponements, and at one juncture, it
was removed from the
trial roll. Subsequently, on 21 August 2023, it was reinstated on the
roll and successfully concluded.
[2]
The merits and quantum in this matter were separated and I am called
to proceed on merits only.
Background
Facts
[3]
On 22 April 2014 at approximately 06h30, on Metrorail train no 9110,
the plaintiff was passenger
holding a valid ticket for the journey,
travelling from Koedoesport to Bosman station. The journey would take
the plaintiff through
Devenish Station and Mears to Saulsville
Station. On the day of the incident, the train came to a standstill
for approximately
30 minutes between Devenish and Mears station.
Whilst the train was in motion, the doors of the coach the plaintiff
was a passenger
in were open, that was when the plaintiff was
allegedly pushed by passengers on the train and got injured. As a
result, the plaintiff
is claiming for personal injuries, alleging
that the defendant’s negligence caused his injuries.
Plaintiff’s
evidence
[4]
It is the plaintiff’s version that he was passenger travelling
from work to home, on Metrorail
train 9110 with a valid ticket. He
was travelling from Koedoesport station to Saulsville station
Gauteng, Pretoria. He is a security
guard who was working nightshift.
The plaintiff testified that the train he was travelling in was
overcrowded from Koedoesport
onwards, the train was also behind
schedule. As it made its usual stops it became more overcrowded as
the other passengers alighted
to this particular coach and there were
no security personnel on sight to prevent overcrowding while the
plaintiff’s coach
kept being more overcrowded along the
journey. It is the plaintiff’s version that he was standing in
the middle of the coach
holding onto to a plastic strap intended for
the use of standing passengers to keep their balance. The carriage
was full, and the
plaintiff suspected that the full carriage was the
reason the train doors were not closing, both sides of the train were
open.
[5]
The plaintiff further testified that between Devenish station and
Mears Station, the train came
to a standstill for a period of
approximately 30 minutes. The passengers started disembarking through
open doors and started walking
next to the train in the direction of
Mears. During this event there were no security personnel or
employees of the defendant trying
to stop the commuters from
disembarking the train at the point where the train came to a stop,
no communication was conveyed to
any commuters for the unscheduled
stop between two stations. There was a sound described by the
plaintiff as a hooter where the
train started moving again, the doors
on both sides of the train were still open.
The
plaintiff testified that he never heard a sound made by the doors to
indicate that they were closing, thereby implying that
the doors
remained open.
The commuters
started attempting to board the train after it started moving again
through open doors. The commuters started embarking
on the right side
of the coach, some commuters were assisting others by pulling them up
into the train by their arms. Whist these
events were taking place,
the train was in motion, the doors on both sides of the coach in
which the plaintiff was a passenger
were open. Just before the train
entered Mears station, the commuters on the coach that the plaintiff
was traveling were disembarking
by moving and pushing towards the
left side of the train, where the left side of the of the doors were
open and where they would
have to disembark. The pushing and shoving
towards the left side caused the plaintiff to lose his grip of the
plastic belt he was
holding onto, and he was being pushed towards the
open door of the left side of the coach. Eventually he was pushed out
of the
carriage through the open doors causing him to fall on the
platform on the platform where he sustained injuries to his head and
right leg.
[6]
The other source of evidence in this trial was an animated detailed
description the plaintiff
gave in his demonstration as to how he was
pushed and shoved to the point of losing his grip on the plastic
belt. He remembers
speaking to a female enquiring about his ticket
and personal details, he had no reason to disembark the train at
Mears station
when his intended destination was Bosman station and
then to Saulsville station, and that the plaintiff would never walk
from Mears
station to Bosman station, it would be far for him.
[7]
During cross examination, the plaintiff confirmed the issue of the
train being overcrowded as
well as doors being open while the train
was in motion and confirmed that other commuters started pushing and
shoving as the train
was about to enter Mears station.
[8]
The investigator’s testimony regarding the incident, and the
alleged version provided to
her and the interview with the plaintiff
was not clearly put before the plaintiff under cross examination.
[9]
The plaintiff admitted that he spoke to one of the defendant’s
employees and was asked whether
he had a ticket for the journey, he
further provided a name, address and telephone number on her request.
The plaintiff could not
remember any further conversation he had with
the defendant’s employee.
[10]
The evidence that the plaintiff attempted to board the train by
hanging between coaches and lifting his legs
just before they reached
the platform at Mears station to try and get onto the platform, as
testified by the investigator, was
never put to the plaintiff under
cross examination.
Defendant’
defence on the pleadings
[11]
The defendant is denying the plaintiff’s averments and pleads
specifically that at all material times,
the plaintiff placed himself
in danger. The plaintiff was hanging outside the train doors.
Therefore, the plaintiff failed to avoid the
incident.
The defendant further pleads that
in fact the train halted and once it started moving, the commuters
who have alighted from the
train including the plaintiff attempted to
board the train again hanging onto the side, this resulted in the
plaintiff being hit
by the station platform. The defendant pleads
that in providing rail services, it implemented reasonable and
required safety regulations.
The defendant pleads contributory
negligence
.
[12]
However, the defendant admits a duty of care to commuters, but denies
it had a duty to the plaintiff. The
defendant admitted liability in
the matter of a deceased person who died in the incident that
occurred the same day as the occurrence
of the plaintiff’s
incident.
[13]
Before I proceed, I will pause to give a definition of the word
‘gainsay’ as provided in the
defendant’s papers,
and ‘gangway’ in the context of the evidence before the
court.
Gainsay
in dictionary meaning refers to
denying
or contradicting a fact or statement
,
and ‘gangway’ refers to
a
raised platform or
walkway
providing
a passage. The court in
Chabot
v Master and Owners, S-S. "Umgeni
,
[1]
held that the
shipping
companies owe a duty to the public to have safe gangways and they
cannot escape liability if a passenger or visitor does
not exercise
the utmost care. The court further continued to find that the
appellant was negligent since he had knowledge that
the gangway was
dangerous, however with this knowledge he proceeded to use the
gangway. With that being said, the defendant’s
witnesses as I
read the papers, they testified that the passengers embarked the
train using gainsay which is not allowed, I therefore
believe that
the proper terms to be used is gangway.
Defendant’s
evidence
Mr
Kganyago
[14]
The defendant’s version through Mr Kganyago who was on duty on
the day of the incident, testified that
he was a Metro-Rail guard for
the train in which the plaintiff was a passenger, and as his duty to
ensure that doors are fully
closed before the train moves, in the
morning before the train was used it was examined and that all doors
were working in order
(closing and opening). He also indicated that
before the train moves (while it is still standing) he can see all
doors and observed
that they were closed before sending a signal to
the train operator that it is safe to proceed.
Between
Koedoespoort and Mears there are five stations, namely, Haartebees,
Rissik, Loftus, Walker and Devenish. All stations from
Koedoesport to
Mears used the left-hand side platform, the procedure to ensure that
the doors were closed at all the above-mentioned
stations including
Silverton station, which is a station just before Koedoesport was
performed.
[15]
He further testified that the signal was closed between Devenish and
Mears station for approximately 30 minutes.
Whilst the train was
stationary, he did not open the doors. Some passengers alighted from
the train and started walking towards
Mears station. The passengers
alighted between the coaches using gangway. He testified that
passengers are not allowed to embark
and disembark through gangway.
The gangway is corridor that links the coaches. After the signal
opened, they communicated with
the operator using the signals and the
train proceeded to move towards Mears. When the train moved from
Mears, he became aware
about the two passengers that fell and send a
please call message to the operator who then called, and he informed
her about the
incident.
[16]
He refuted the plaintiff’s version that the doors were open,
that the train was late, and it was overcrowded.
However, he conceded
that he did not know which coach the plaintiff was, and he could not
tell if that particular coach was overcrowded.
However, he explained
that due to his experience most passengers disembark at Koedoesport
and accordingly it is not possible that
the train was overcrowded.
[17]
Also refuted that the train only stops for few seconds hence the
people were pushing to get out before the
train stops. He explained
that he is the person who opens and closes the doors and only closes
the doors and signals the operator
to move only after it is safe.
There is no time limit at the station.
[18]
During cross-examination he testified that it is not possible to
force open the doors. They can only be open
when the train is turned
off and the train was never turned off between Devenish and Mears. He
further confirmed that he kept observing
whilst the train was moving,
and he could not see anyone hanging outside the train. Furthermore,
there was a curve where he saw
all the doors on the left and they
were closed.
Ms
Nkosi
[19]
The defendant’s version was further supported by Ms Nkosi, the
train operator, who testified that she was a train
operator in the
train that the plaintiff got injured. It travelled from Mamelodi to
Pretoria station. She confirmed that
it was the metro guard’s
duty to ensure that the doors were closed. The signal was closed
between Devenish and Mears and
passengers got off the train and
started walking towards Mears station. When the signal opened, she
hooted to disperse the people
who disembarked and were walking next
to the tracks. She also confirmed that the passengers disembarked
whilst using the gangway
when the train was stationary between
Devenish and Mears.
[20]
She further conceded that she could not see anyone hanging as she was
focused ahead. During cross examination
she confirmed that passengers
use gangway in between the coaches. She further testified the people
hanging in between the coaches
will not be visible to her or the
metro guard. She further confirmed that it is impossible for a person
to keep the doors open
as they work with pressure. Lastly, when the
train moves it starts slow and picks up the speed to the maximum of
30 km/h.
Ms
Ndhlovu (now Mahlangu)
[21]
Testified that at the time of the incident she was a protection
officer. There were technical problems that
led to train to be
stopped between Devenish and Mears. She received the call from JOC
that the tracks were down between Koedoespoort
and Pretoria station.
She then accompanied the technician to signal point on the other end
of Mears platform towards Bosman.
[22]
She then received another call from JOC informing her about injured
people at Mears. She walked from the
signal point to the incident it
took her about 4 minutes because she had to walk on the other side of
the platform to avoid the
irritated people who were walking towards
Bosman.
[23]
When she got to the plaintiff, she asked his name and his ticket. At
the time he was with another person
referred to as his supervisor and
that person showed her the train ticket.
[24]
She then asked the plaintiff what happened and was informed by the
plaintiff that he alighted from the train
whilst it was stationary
between Devenish and Mears because he was in a hurry to catch another
train at Pretoria station to Saulsville
station. Whilst walking
between Devenish and Mears, the train started moving and he decided
to ride the train by holding on the
handle between the coaches. It
would have been faster and quicker for them to catch another train
and Pretoria station.
[25]
During the cross examination she stated that it is illegal for people
to surf the train and hang outside
between the couches. She was then
asked why the plaintiff was not fined at the scene and her response
was that she used humanity
as the plaintiff was injured and her
concern was to get him medical assistance. She refuted the
plaintiff’s version about
people pulling each other between
Devenish and Mears as the train is elevated and the doors would have
been closed.
[26]
She further confirmed that people hanging in between coaches would
not be seen by the operator and the guard.
Ms
Mphaka
[27]
She testified she received a call from JOC that two people were hit
by train at Mears. When she arrived at
Mears she met Ms Ndhlovu and
she handed over the scene to her and explained what had happened. She
explained to her that two people
fell from the train and they were
not hit by train.
[28]
She then saw the deceased and the plaintiff. She approached the
plaintiff and asked what happened. The plaintiff
told her that he was
hanging from the train that had stopped between Devenish and Mears.
He alighted from the train because he
did not know when it was going
to move. He then heard the bell and the train started moving but it
was moving slow.
[29]
He then decided to ride the train by hanging between the coaches and
when he tried to disembark, he hit the
platform wall and fell. Could
not take a written statement from him, because he was injured and
decided not to take the statement
at that time.
[30]
During cross examination the witness demonstrated that the height of
the train is high, and as for a person
almost her height, it would
not have been impossible for the passengers to pull people outside
the coach, taking into account that
the train was in motion.
Inspection
in loco
[31]
The
inspection
in
loco
[2]
assists
the courts in achieving the following purposes, namely:
to
follow the oral evidence including observing real evidence which is
additional to the oral evidence. At the inspection in loco,
the
parties agreed that the platform where the incident occurred would be
referred to as the Unisa side platform, the opposite
side would be
referred to as the trackside or ticket station platform. The parties
agreed that the plaintiff was found on the Unisa
side platform after
the incident occurred and towards the beginning of the platform. The
beginning of the platform would refer
to the side of the platform
from which a train would enter the station.
Issues
for determination
[32]
32.1 The issues to be determined here by this court
are the two conflicting versions of
the plaintiff and the defendant.
32.2 More
specifically whether the defendant admits that the plaintiff fell
from a moving train which travelled with
open doors?
32.3. Whether the
defendants admit that the Metrorail General Operating Instructions
require that all train doors must be closed
prior to departure?
32.4
Ultimately, this court must determine whether the defendant was
negligent?
Law
applicable to facts
(i)
Conflicting versions
[33]
From the given versions, it is clear that
in
casu
,
the court is left with two mutually conflicting versions which cannot
co-exist, and the court has to determine which one of these
versions
should be accepted. A tendency generally accepted by courts in
resolving factual disputes of this nature is found in
Stellenbosch-Farmers’
Winery -Group Ltd and Another v Martell
and Others
[3]
which held the following:
“
To
come to a conclusion on the disputed issues a court must make
findings on: (a) the credibility of the various factual witnesses;
(b) their reliability; and (c) the probability or improbability of
each party's version on each of the disputed issues. In light
of the
assessment of (a), (b) and (c), the court will then, as a final step,
determine whether the party burdened with the onus
of proof has
succeeded in discharging it. The hard case, which will doubtless be a
rare one, occurs when a court's credibility
findings compel it in one
direction and its evaluation of the general probabilities in another.
The more convincing the former,
the less convincing will be the
latter. But when all factors equipoised, probabilities prevail.”
[4]
[34]
Further, the court in
National
Employers'
General Insurance Co Ltd v Jager
[5]
,
the court remarked as follows:
‘‘
It
seems to me, with respect, that in any civil case, as in any criminal
case, the onus can ordinarily only be discharged by adducing
credible
evidence to support the case of the party on whom the onus rests. In
a civil case the onus is obviously not as heavy as
it is in a
criminal case, but nevertheless where the onus rests on the plaintiff
as in the present case, and where there are two
mutually destructive
stories, he can only succeed if he satisfies the court on a
preponderance of probabilities that his version
is true and accurate
and therefore acceptable, and that the other version advanced by the
defendant is therefore false or mistaken
and falls to be rejected. In
deciding whether that evidence is true or not the court will weigh up
and test the plaintiff's allegations
against the general
probabilities. The estimate of the credibility of a witness will
therefore be inextricably bound up with a
consideration of the
probabilities of the case and, if the balance of probabilities
favours the plaintiff, then the court will
accept his version as
being probably true. If, however, the probabilities are evenly
balanced in the sense that they do not favour
the plaintiff's case
any more than they do the defendant's, the plaintiff can only succeed
if the court nevertheless believes him
and is satisfied that his
evidence is true, and that the defendant's version is false.
This
view seems to me to be in general accordance with the views expressed
by Coetzee J in Koster Ko-operatiewe Landboumaatskappy
Bpk v
Suid-Afrikaanse Spoorweë en Hawens (supra) and African Eagle
Assurance Co Ltd v Cainer (supra). I would merely stress
however that
when in such circumstances one talks about a plaintiff having
discharged the onus which rested upon him on a balance
of
probabilities one really means that the court is satisfied on a
balance of probabilities that he was telling the truth and that
his
version was therefore acceptable. It does not seem to me to be
desirable for a court first to consider the question of credibility
of the witnesses as the trial judge did in the present case, and
then, having concluded that enquiry, to consider the probabilities
of
the case, as though the two aspects constitute separate fields of
enquiry. In fact, as l have pointed out, it is only where
a
consideration of the probabilities fails to indicate where the truth
probably lies, that recourse is hard to an estimate of relative
credibility apart from the probabilities
.”
[6]
[35]
Lastly, in
Govan
v Skidmore
[7]
,
the Court held that, in trying the facts in a matter, one may, by
balancing probabilities, select a conclusion which seems to
be the
more natural or plausible conclusion from amongst several conceivable
ones, even though that conclusion may not be the only
reasonable one.
[36]
Based
on the above, the court will now turn to consider whether
the
plaintiff has adduced
evidence
on a balance of probabilities, having due regard to the credibility
and reliability of the witnesses, that the defendant
was negligent
and that his averment or version of the plaintiff testimony is true
and accurate, and therefore acceptable, and that
the version of the
defendant falls to be rejected. To avoid liability, the defendant
must produce evidence to disprove the inference
of negligence on his
part, failing which he/she risks the possibility of being found
liable for damages suffered by the plaintiff.
Evaluation
of evidence and submissions
[37]
To resolve a civil dispute such as the one
before this Court, one needs to turn to the probabilities of the
competing versions,
coupled with the evidence presented before this
Court by both parties. It’s either the plaintiff was pushed out
of the train
through open doors or the plaintiff, in terms of what
the defendant was pleading, was hanging on the side of the train.
[38]
During the evidence given the plaintiff was the single witness
regarding the events that occurred on the
day in question. However,
being a single witness does not put the plaintiff in a disadvantaged
position. His evidence still needs
to be considered holistically to
arrive at an objective conclusion. The single witnesses’
evidence should not merely be disregarded
or discounted on the basis
that the witness has an interest or is bias in the proceedings,
However, the evidence should be assessed
as a whole and with caution
taking into account all the relevant considerations. The Court, in in
S
v Saulus
and
Others
,
[8]
correctly found that:
“
There
is no rule of thumb test or formula to apply when it comes to a
consideration of the credibility of the single witness. The
trial
judge will weigh his evidence, will consider its merits and demerits
and having done so, will decide whether it is trustworthy
and
whether, despite the fact that there are shortcomings or defects or
contradictions in the testimony, he is satisfied that the
truth has
been told . . .”
[9]
[39]
Regarding the plaintiff’s testimony in so far as it relates to
the incident, the train was overcrowded,
especially in the coach that
he was traveling in, and kept being overcrowded along the stations,
while the doors were open. The
plaintiff testifies that on the same
day a person died due to the overcrowding in the train and the
defendant has accepted liability
of such.
[40]
During cross examination, the plaintiff remembers one of the
defendant’s employees who came to ask
him about his ticket and
the plaintiff provided more information about his address and name
.
The plaintiff cannot be criticized for failure to
recall every detail of what happened on that day, given the
circumstances at the
time of the incident he was from nightshift
work, probably looking forward to getting home and to rest. He would
not have gotten
off
Mears station when his intended
destination was Bosman station and then to Saulsville station, and.
would never walk from Mears station to Bosman as
it would be too far.
[41]
Regarding the sustained injuries which arise from the alleged shoving
and pushing from the left side of the
train, which caused the
plaintiff to lose the grip on the plastic belt he was holding,
therefore falling on the pavement next to
the platform and sustaining
injuries as a result.
I believe that this
happened as a result of the overcrowding of the coach the plaintiff
was on, and the pushing and shoving, otherwise
he would not have lost
his grip if he had not possibly been pushed by an enormous number of
commuters.
The plaintiff would not have fallen on the platform
if the doors of the train were closed.
[42]
On the other hand, the defendant’s pleading
is that the plaintiff was hanging outside the train doors,
and the
testimony through Mr Kganyago, the security guard who was on duty,
proves otherwise, as he confirms that he did not see
anyone hanging
outside the train. The other two witnesses
confirmed
it is illegal for people to surf the train and hang outside like
between the coaches, and that people hanging in between
coaches would
not be seen by the operator and the guard.
The court cannot
expect the security personnel to have knowledge of which coach the
passengers are travelling at all times, however,
their duty is to
ensure that doors are closed at all times when the train is in motion
and that the train is not overcrowded. The
security guard was not
sure about the overcrowding or whether the doors were closed or not,
also whether the plaintiff was indeed
hanging outside or not.
[43]
The plaintiff was a good and credible witness who relayed the
incident of the March 2021 in a clear and uncomplicated
fashion. He
answered questions put to him in a direct manner, and in my view was
steadfast under cross examination. I find that
his explanation as to
why he boarded the overcrowded train to be reasonable and logical. He
already bought the ticket and he needed
to board it to get home. This
is a plausible explanation.
[44]
The plaintiff was consistent in his explanation regarding passengers
alighting and new commuters boarding
the train at the various
stations along the way. There is nothing unusual in the explanation
that he stood at the door and gave
way to people boarding the train.
I am of the view that he did not attempt to exaggerate his evidence,
nor did he conjure up a
version that he saw people pushing and
desperately wanting to be out due to the accident that just happened
and rushing to get
home. In short, I agree with the submission that
the plaintiff was a credible, honest witness, who remained consistent
under cross
examination.
(ii)
The question of negligence
[45]
The railway system is a primary mode of transport for many, and users
are entitled to a railway system that
is safe, well - managed and
efficient within the constraints imposed by economic realities. The
breach of public law obligations
is wrongful for purposes of public
law remedies and for the purposes of determining delictual liability.
[46]
Operating a train under conditions where the doors remained open even
though the train was
travelling when
there is no platform onto which to step out is per se dangerous and
wrongful.
[47]
The classic test for negligence is set out in
Kruger
v Coetzee
,
[10]
which may be summarised as follows, would a reasonable person in the
position of the defendant foresee the reasonable possibility
of its
conduct injuring the plaintiff and causing him patrimonial loss. For
the purposes of liability culpa arises if:
[11]
(a)
a diligens paterfamilias in the position of the defendant-
(i)
would foresee the reasonable possibility of his conduct injuring
another in his person or property and causing him patrimonial
loss;
and
(ii)
would take reasonable steps to guard against such occurrence; and
(b)
the defendant failed to take such steps.
[48]
The plaintiff’s case for the negligence of the defendant and
its employees and agents was based solely
on the fact that the doors
were kept open on both sides of the carriage from Mears station and
then at Devenish station. While
the train was stationery one would
expect the doors to be at the platform side, but there was no
explanation for the open doors
on the far side. It was common cause
that on the platform side, the floor of the carriage was at the
approximate height of the
platform whereas on the other side, there
is an appreciable drop from the floor of the carriage to ground
level. Passengers are
not expected to embark or disembark on the far
side.
[49]
Neither the plaintiff nor the defendant dealt with the number of
guards and conductors (if any) on the train
or with the policies, the
procedures and practices of the defendant in operating an urban
passengers rail network, the measure
of control that the personnel
had over the doors, the extent to which personnel could interfere
when passengers impermissibly kept
the doors open , and the
mechanical or electronic systems used to manipulate the doors .
(iii)
Contributory negligence
[50]
In
Johnson,
Daniel James v Road Accident Fund
[12]
the
court held that in order to avoid liability, the defendant must
produce evidence to disprove the inference of negligence on
his part,
failing which he/she risks the possibility of being found to be
liable for damages suffered by the plaintiff. Where
the
defendant had in the alternative pleaded contributory negligence and
an apportionment, the defendant would have to adduce evidence
to
establish negligence on the part of the plaintiff on a balance of
probabilities.
[51]
There is no evidence of contributory negligence, it was suggested in
the pleadings that the plaintiff was
hanging outside the train doors,
while the testimony says that he was inside the train. The
plaintiff’s undisputed evidence
was that he was on his way home
and intended to disembark at Mears/ Devenish Station. He had no
reason to leave the train
or get off at said station because his
destination was far, he could not walk there. He has been using the
train since 2006, so
he knows these issues. There were no security
personnel on sight, and the train usually stops at various stations.
The coach in
which the plaintiff was travelling became overcrowded as
more passengers alighted to pick particular coach while he was
standing
in a middle of the coach holding on to a plastic belt for
balance. As the train got more overcrowded the plaintiff suspected
that
the doors did not close as he did not hear the sound they make
when they close. This court takes note of the demonstration the
plaintiff made to show how he was pushed and shoved out of the train.
There was also no evidence that his behaviour differed from
that of
the other passengers.
[52]
Section 1(1)(a) of the Apportionment of Damages Act 1(1)(a) gives a
discretion to the trial court to reduce
a plaintiffs claim for
damages suffered on a just and equitable basis and to apportion the
degree of liability. Where apportionment
is to be determined, the
court is obliged to consider the evidence as a whole in its
assessment of the degrees of negligence of
the parties. In this
instance in order to prove contributory negligence, it was necessary
to show that there was a causal connection
between
the
incident
and the conduct of the
plaintiff, this being a deviation from the standard of the
diligence
paterfamilias.
In this instance
there is no evidence of contributory negligence.
(iv)
Wrongfulness and the defendant ‘s duty to commuters
[53]
Wrongfulness is an essential element in delict.
[13]
The Constitutional Court held in this regard that the element of
wrongfulness acts ‘as a brake on liability’ and that
conduct is not to be regarded as wrongful if public or legal policy
considerations determine that it would be ‘undesirable
and
overly burdensome to impose liability’.
[14]
In
Le
Roux and
Others
v Dey
,
[15]
the Constitutional Court confirmed that the criterion of wrongfulness
depends on a judicial determination as to whether it would
be
reasonable to impose liability on the defendants, which
reasonableness has nothing to do with the reasonableness of the
defendant’s
conduct or omissions. Therefore, even if it were to
be found that there was negligence herein, the mere fact of such
negligence
may not make the omission wrongful. In order to prevent
the ‘chilling effect’ that delictual liability in such
cases
may have on the functioning of public servants, such
proportionality exercise must be duly carried out and the
requirements of
foreseeability and the proximity of harm to the
action or omission complained of, should be judicially evaluated.
[16]
[54]
In case of Organs of state, the Constitutional Court in
Rail
Commuters Action Group v Transnet Ltd t/a Metrorail
,
[17]
recognised that rail commuters in their thousands use the rail system
daily and once they board a train, find themselves in a vulnerable
position and even targeted by criminals on board the same train. The
Constitutional court held that Metrorail owed a positive duty
to
ensure that reasonable measures were in place to cater for the safety
and security of rail commuters. Significantly, the Constitutional
Court was clear that it mattered not who implemented these measures
as long as they were in place.
[55]
The defendant as an Organ of State established in terms of section 2
of the Legal Succession to the South
African Transport Services Act
provides rail commuters with its services, it has a duty and
obligation to protect the commuters’
bodily integrity. In
Mashongwa
v PRASA
[18]
the court held
that:
“
As its mandate
the defendant’s duty to safeguard the physical wellbeing of
passengers must be central obligation. It reflects
the ordinary duty
resting on public carriers and is reinforced by the specific
constitutional obligation to protect passenger’s
bodily
integrity, as an organ state. The norms and values derived from the
Constitution demand that a negligent breach of those
duties, even by
way of omission, should, absent a suitable non judicial, attract
liability to compensate injured persons in damages.
(own emphasis)
When account is taken
of these factors, including the absence of effective relief for
individual commuters who are the victims of
violence on Prasa ‘s
trains, one is driven to the conclusion that the breach of public
duty by Prasa must be transposed into
a private law breach in delict.
Consequently, the breach would amount to wrongfulness.
[19]
[56]
From the above paragraphs in the
Mashongwa
judgement, read
with its predecessor, the
Rail Commuters Action Group judgement
,
it is thus apparent that the defendant has a public duty to protect
rail commuters, but this does not mean that it has a legal
duty for
purposes of delict. For that legal duty to arise, the defendant is
required to take reasonable steps to provide for the
safety of
commuters and any failure to take such steps may render it liable in
delict. This leads to the next question, which is
whether the
defendant was negligent in relation to the plaintiff.
[57]
In
Mashongwa
, when considering the negligence of Prasa in the
circumstances of the commuter who was pushed from a moving train
while its doors
were open, the Constitutional court specified that
the test involves the reasonable organ of State test which recognizes
that an
Organ of State is in a different position to that of an
individual. The question thus, is whether a defendant had reasonably
foreseen
the harm befalling the plaintiff as a result of the train
doors being open while the train was in motion.
[58]
The reasonable man will foresee the possibility of injury or death if
a person fell out or were pushed out
the door on the far side and
fell onto the ground, and this would be the case irrespective of
whether the train was in motion or
not. There can be no doubt that
leaving the train doors open is a danger to commuters who board that
train, as he/she could slip,
be pushed, lose their balance, fall from
the train, and sustain injury.
[59]
The facts of this case echo those in
Centane
,
[20]
Metrorail and a host of other similar matters in relation to the
daily reality of overcrowded trains operated by the defendant.
Commuters pushing against each other in order to align at the
stations, a fact which the plaintiff testified about, seems to be
a
normal occurrence and part of the daily train journey for many South
African commuters. While this matter does not involve a
scenario
where the plaintiff was pushed from the train, the evidence, which
follows the pleading, is that the plaintiff fell through
the open
door of the train while it was in motion.
[60]
In my view, all that was required of the defendant was to comply with
its own operating instructions. Yet,
the defendant failed to do so
and operated its train from Mears and Devonshire stations with its
carriage doors open, put another
way, the defendant’s employees
being the security guards, omitted to close the train doors, and such
conduct is not acceptable.
In allowing the train doors to be and
remain open while the train was in motion. The defendant failed in
its legal duty towards
the plaintiff as a commuter. The resultant
finding is that the defendant failed to ensure that the safety
precaution (closing the
train doors) was complied with and such
failure amounts to negligence on its part. A reasonable Organ of
State in the defendant
‘s position, which owes a public duty to
commuters, would have ensured that the train doors were kept closed
to prevent the
plaintiff ‘s fall or slip from the train onto
the railway tracks or platform. Thus, the reasonable possibility of
the plaintiff,
a commuter, falling from the packing, moving train
whilst the doors were open, was foreseeable.
[61]
When the train is stationery at a designate stop next to a station
platform one would expect the rear side
doors to be open at some
stage so that passengers may embark or disembark. The reason for the
existence of a railway platform is
for the platform to be flush with
the doors and the floor of the railway carriage so passengers can
step from one to the other
in safety. On the far side there is a
considerable drop between the floor of the carriage and ground level.
There is no reason
for the doors on the far side to be open at any
time whether the train is stationery or in motion. The defendant
failed to take
reasonable care.
(v)
Causation
[62]
In approaching the element of causation, the court in
Maphela
v Prasa
[21]
on similar facts
as the ones before the court asked if there is a causal connection
between the defendant ‘s negligent conduct
and the plaintiff’s
injuries. In this regard, the court enquired whether the harm would
nonetheless have ensued even if the
omission (the failure to close
the train doors while it was in motion) has not occurred. A casual
nexus must exist between the
defendants conduct and the damage or
harm suffered by the plaintiff.
[63]
In Applying the
conditio sine qua non
test
and causation by omission, I have to ask what would probably have
happened had the defendant ensured that the train doors
were closed
on the journey which the plaintiff took.
[64]
The defendant’s conduct in failing to close the doors and in
circumstances where it takes upon itself
the duty to provide safe
passage to the plaintiff and other commuters, led me to conclude that
its negligent omission is closely
connected to the harm suffered by
the plaintiff as a result of the incident. Accordingly, the defendant
is liable to the plaintiff
for the harm he suffered.
[65]
I emphasize that it remained the defendant’s duty and
operational obligations to ensure that the train’s
doors were
closed when it left a station and when it was in motion The defendant
bears the onus in respect of proving that the
plaintiff was
negligent, and that the negligence was casually connected to the
damages which he suffered.
[66]
Furthermore, the defendant bears the onus of proving that the
plaintiff had knowledge of the risk associated
with standing at the
open door of train while it was in motion, that he appreciated the
extent of such risk and that he consented
to the risk. In this
regard, the defendant led no evidence which would cause me to
consider that the above essential elements of
the defence were
proved. Thus, the onus attached to a defence of
volenti non fit
iniuria
was not discharged and the submission by the defendant’s
counsel was unsubstantiated. In view of all the above conclusions,
I
find that the defendant is solely liable for the harm suffered by the
plaintiff, and that the plaintiff therefore succeeds with
his claim
on the merits.
Reasons
for the decision
[67]
I therefore further find that, in the evidence given by the
defendant, none of the witnesses has seen the
plaintiff hanging on
the outside of the train doors or riding between the doors as the
defendant pleads. Arguably they confirmed
that it is not allowed to
ride through gangway, and it is impossible to see a passenger in that
instance.
[68]
Given the circumstances of the plaintiff, I find him to be a
responsible person with a stable employment,
who would not put
himself and his life at risk by surfing on the train between coaches
or hanging outside of the train doors as
the defendant’s
evidence suggests.
[69]
The plausible reason why none of the witnesses has
seen him hanging outside the doors was because he was
not riding the
train from outside, but inside holding onto the plastic handle until
he was pushed and fell on the platform due
to the pushing, shoving by
passengers overcrowding in his coach.
Conclusion
[70]
The plaintiff made out a prima facie case and the defendants failed
to lead evidence to discharge the evidentiary
burden. The defendant
is liable for the damages suffered by the plaintiff.
Order
[71]
1. The plaintiff ‘s claim on the merits is upheld.
2. The defendant is 100%
liable for the plaintiff ‘s proven damages
3. The defendant is
ordered to pay the plaintiff ‘s costs on an attorney and client
scale as taxed or agreed and including
the costs of senior counsel.
4.
The
trial on quantum is postponed
sine
die.
MD
BOTSI-THULARE AJ
ACTING
JUDGE OF THE HIGH COURT, PRETORIA
APPEARANCES:
Plaintiff’s
Counsel:
Adv
Pieter Venter
Instructed
by
Spruyt
Incorporated Attorneys
Defendant’s
Counsel:
Adv M
Vimbi
Instructed
by:
Jerry
Nkeli & Associates
DATE
OF HEARING:
14
April 2023
DATE
OF RESERVED JUDGMENT:
21
August 2023
DATE
OF JUDGMENT:
20
November 2023
[1]
(1914)
35 NPD 140
.
[2]
R
v Mokoena
1932
OPD 79
at
80.
[3]
2003
(1) SA 11
(SCA) at para 5.
[4]
Id para 5.
[5]
1984
(4) SA 437
(ECD).
[6]
Id at para
440D-441A.
[7]
1952
(1) SA 732 (N).
[8]
1981
(3) SA 172
(A).
[9]
Id para 180 E -G.
[10]
1966
(2) SA 428
(A) at para 491.
[11]
Ibid
[12]
Case
Number 13020/2014 GHC paragraph 17, confirming
Solomon
and Another v Musset and Bright Ltd
1926
AD 427
and
435.
[13]
Stedall
and Another v Aspeling and Another
[2017]
ZASCA 172
;
2018 (2) SA 75
(SCA) para 11.
[14]
Country
Cloud Trading CC v MEC, Department of Infrastructure Development,
Gauteng
2015
(1) SA 1 (CC).
[15]
Le
Roux and Others v Dey
[2011]
ZACC 4
;
2011 (3) SA 274
(CC) para 122
[16]
Carmichele
v Minister of Safety and Security
[2001] ZACC 22
;
2001
(4) SA 938
(CC) para 49.
[17]
[2004]
ZACC 20
;
2005 (2) SA 359
(CC);
2005 (4) BCLR 301
(CC) at para 82.
[18]
[2015]
ZACC 36; 2016 (2) BCLR 204 (CC); 2016 (3) SA 528 (CC)
[19]
Ibid
para
26 and 27.
[20]
Centane
v Prasa
Western
Cape High Court, case number 5672/2019, judgment
delivered
on 3 March 2023.
[21]
Maphela
v Passenger Rail Agency of South Africa
(834/021)
[2023] ZAWCHC 137
at para 58.
sino noindex
make_database footer start
Similar Cases
Masombuka v Passenger Rail Agency of South Africa (24617/2021) [2022] ZAGPPHC 594 (2 August 2022)
[2022] ZAGPPHC 594High Court of South Africa (Gauteng Division, Pretoria)99% similar
Phungula v Passenger Rail Agency of South Africa (12245/2021) [2023] ZAGPPHC 1200 (21 September 2023)
[2023] ZAGPPHC 1200High Court of South Africa (Gauteng Division, Pretoria)99% similar
Maphalle v South African Police Service and Others (B38945/2022) [2022] ZAGPPHC 875 (17 November 2022)
[2022] ZAGPPHC 875High Court of South Africa (Gauteng Division, Pretoria)99% similar
Mthembu obo S.S.Z v RAF [2023] ZAGPPHC 462; 81106/2017 (9 June 2023)
[2023] ZAGPPHC 462High Court of South Africa (Gauteng Division, Pretoria)99% similar
Mavuso and Another v Commission for Gender Equality (05581/23) [2025] ZAGPPHC 166 (17 February 2025)
[2025] ZAGPPHC 166High Court of South Africa (Gauteng Division, Pretoria)99% similar