begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2022
>>
[2022] ZAGPPHC 268
|
Noteup
|
LawCite
sino index
## GD Irons Construction Proprietary Limited v Thumos Properties (Pty) Ltd and Others (35401/2013)
[2022] ZAGPPHC 268 (25 April 2022)
GD Irons Construction Proprietary Limited v Thumos Properties (Pty) Ltd and Others (35401/2013)
[2022] ZAGPPHC 268 (25 April 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2022_268.html
sino date 25 April 2022
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION PRETORIA
CASE
NO: 35401/2013
NOT
REPORTABLE
NOT
OF INTEREST TO OTHER JUDGES
REVISED
25
April 2022
In
the matter between:
GD
IRONS CONSTRUCTION PROPRIETARY LIMITED
Plaintiff
and
THUMOS
PROPERTIES (PTY) LTD
First Defendant
THUMOS
PROPERTIES 1 (PTY) LTD
Second Defendant
THOMAS
GEORGE NELL
N.O.
Third Defendant
NEUKIRCHER
J:
Background
1.
The plaintiff’s
claim has its origin in a Principal Building Agreement (the
Agreement) entered into on 1 December 2008. The
claim is for the
balance due in respect of certain interim payments certificates which
were issued, but have not been paid –
the amount the plaintiff
alleges is owing is R249 440 879-45. The contentious issue
is which of the first and/or second
defendants is liable for payment
under the Agreement and whether or not the plaintiff is entitled to
rectification of the Agreement
of 1 December 2008. Although the
defendants admit the failure to pay the amount of R249 440 879-45,
they deny liability.
Certain
common cause facts and the disputes
2.
On
1 December 2008 the plaintiff entered into the Agreement with the
first defendant
1
.
The Agreement was to the effect that the plaintiff would construct a
suburban shopping mall in the east of Pretoria, at the intersections
of De Villebois Mareuil Drive and Delmas Roads, known as “The
Villa”
2
.
The plaintiff’s claim is this one in respect of remuneration
for work done and materials supplied on the construction of
the Mall.
It is common cause that the plaintiff gave notice to suspend the
building works on 27 August 2010 because of the defendants’
failure to make payment of the interim payment certificates issued by
the principal agent.
3.
It
is common cause that the principal agent was a company known as Osglo
Pretoria (Pty) Ltd (Osglo) and that, under the hand of
Ronell
Scheepers, it issued a series of interim payment certificates to the
plaintiff. It is also common cause that the first 6
interim payment
certificates reflect Capicol as the employer, whereas the remainder
of the interim payment certificates reflect
the second defendant
3
as the employer.
4.
It
is common cause that the plaintiff has received payment in the amount
of R578 321 731-91 in respect of the work carried
out by it
and that it is claiming an amount of R249 444 435-45
4
in respect of the balance owing on the issued interim payment
certificates and the latter then founds the claim against the
defendants.
The plaintiff also claims default interest in terms of
clause 31.11 of the Agreement in an amount which is equivalent to the
capital
balance owing.
5
The interest is
capped by virtue of the
in
duplum
rule, from April 2018.
5.
In
the meantime, Capicol 1 has been placed in business rescue with
effect from 15 March 2021. The third respondent (Nell) was appointed
as the business rescue practitioner (BRP). On 15 June 2021, the BRP,
through his attorneys, consented to the action continuing
6
and indicated
7
that he abided by the decision of this court. Thus, any reference to
the defendants in this judgment is a reference only to the
first and
second defendants.
6.
At the time that the
Agreement was entered into, the “face” of both Capicol
and Capicol 1 was a Kyriacou (Kyriacou).
He was the director of both
companies and remained so throughout the period of the Agreement was.
The
dispute
7.
The main dispute that
informs the present proceedings, the evidence and the remainder of
the arguments is:
7.1
who was the employer
under the Agreement? It is as a result of this dispute that the
plaintiff has sought rectification of the Agreement;
7.2
although the main claim is against Capicol 1, the plaintiff also
frames a claim in the alternative against
Capicol;
7.3
that the Agreement should be rectified
8
to reflect the employer as Capicol 1;
7.4
whether Capicol 1 was Capicol’s undisclosed principal when the
building contract was concluded;
7.5 if
Capicol 1 was the employer:
7.5.1 whether the amounts
paid by Capicol for the first 6 payment certificates should be
deducted from the amount owing by Capicol
1;
7.6 in
the alternative to the main claim, and in the event that it is found
that Capicol is the employer:
7.6.1 whether the
plaintiff repudiated the Agreement and whether Capicol has cancelled
the Agreement;
7.6.2 whether the
plaintiff is entitled to recover the total amount of R672 057 419-09
reflected in payment certificates
7 to 23, given that these reflect
Capicol 1 as the employer; and
7.6.3 whether Capicol is
estopped from relying on the fact that payment certificates 7 to 23
reflect Capicol 1 as the employer,
as a defence to the plaintiff’s
claim
alternatively
whether Capicol is bound by its election
to direct that these payment certificates reflect Capicol 1 as the
employer and accepting
some payments pursuant thereto.
7.7
whether, as pleaded by the defendants, the above alterative claims
are inconsistent and mutually destructive.
8.
Whilst the plaintiff
initially also claimed, in the alternative to its contractual claims,
that Capicol 1 had been unjustifiably
enriched at the expense of the
plaintiff, this claim was withdrawn shortly prior to trial.
9.
When
the action was instituted, plaintiff originally sued only Capicol. It
was only pursuant to an amendment to its pleadings on
30 November
2020 that this claim became the alternative to a main claim against
Capicol 1.
The
evidence
10.
The plaintiff called 3
witnesses:
10.1
David Pieterse, who was
the project manager on the project;
10.2 Ronell
Scheepers, who is an architect and a director of Osglo. She is the
author of the interim payment certificates;
and
10.3 Pieter Rüde,
a civil engineer and the managing director of the plaintiff. He
represented the plaintiff when the
Principal Building Agreement (the
Agreement) was concluded on 1 December 2008, and it is his signature
to be found on that contract.
11.
The defendants closed
their case without calling any witnesses.
12.
The
context within which the Villa Mall came to be developed is the
following: a feasibility study was conducted and according to
that
there was a need to develop a shopping mall on the eastern side off
Pretoria where residential development had flourished.
As a result of
this, Pieterse identified property on the corner of DeVillabois and
Delmas Roads. He was of the view that it would
be ideal to build a
mall there with international tenants to compete with the like of
Sandton City in Johannesburg.
13.
The
development would require the purchase of approximately 74 properties
and the acquisition of the properties would be in the
name of Capicol
1. The properties were transferred into Capicol 1’s name during
2008.
14.
The
idea was to put the construction of the Mall out on tender and for
that purpose, McLachlan Du Plooy Gauteng (Pty) Ltd were appointed
as
the Quantity Surveyors (QS) and they drew up the bill of quantities
for the Villa project. On 21 August 2008 the QS gave notice
of a site
inspection/meeting in respect of the bid, to be held at the offices
of Capicol
9
.
The completed bids had to be delivered to the offices of Capicol and
would be opened in the boardroom of Capicol. On 9 September
2008 the
QS then gave notice of certain changes to the tender and bill of
quantities. What is important regarding this is that
the notice (and
additions to the bid document and bill of quantities) was given “
on
behalf of the developer Capicol (Pty) Ltd”
and this addendum
10
had to be signed by the bidder. In fact, each addendum to the bid
documents reflected the developer as Capicol.
15.
The
plaintiff was the only bidder which indicated that it would be able
to complete the building works in the required 24-month
period, and
it was therefore awarded the bid.
16.
The
Agreement was signed on 1 December 2008. According to that document,
the plaintiff was represented by Mr Rüde and Kyriacou
represented Capicol. The Agreement defines the “employer”
as “
The
party contracting with the Agreement
or
for the execution of the
works
as named in the Agreement
data
.”
Pieterse stated that he was also present when the Agreement was
signed.
17.
The
Agreement also sets out who the contracting parties are: they are
specifically described as follows: Capicol as ‘the employer’
and the plaintiff as the contractor.
18.
Nowhere
in the Agreement is the name of Capicol 1 to be found.
19.
On
12 January 2009 the plaintiff took occupation of the site and as work
progressed Scheepers (on behalf of Osglo) started issuing
the interim
payment certificates which initially reflected the name of Capicol in
accordance with the Agreement.
20.
On
15 January 2009, Capicol 1 concluded a Sale of Business Agreement
with Brookfield Investments 246 (Pty) Ltd
11
(the January 2009 agreement). In terms of this agreement, Capicol 1
sold “
the
rental enterprise conducted by the Seller
12
as
a going concern and income earning activity of the Property as at the
Closing Date and which Business comprises of - the Property
13
;
the Leases
14
,
all fixtures and fittings on the Property of a permanent nature…”
to Brookfield for the amount of R2,9 billion.
21.
On
8 May 2009 an email was received from Lizelle Tromp, the personal
assistant of Kyriacou, in which she informed all stakeholders
and
agents as follows:
“
Invoices
to Capicol
Please
note:
From
this month [your] invoices must be made out to the correct Company
name, Reg nr and Vat nr in order for us to do payment;
For
projects;
Zambesi
Ph 3 and Erf 310
Capicol
(Pty) Ltd
Reg
nr: 2007/010860/07
VAT
nr: 4850201478
The
Villa
Capicol
1 (Pty) Ltd
Reg
nr: 2007/014113/097
VAT
nr: 4840245262
Zivania
Village
Capicol
2 (Pty) Ltd
Reg
nr: 2007/014071/97
VAT
nr: 4870245265”
22.
Accordingly,
as from May 2009 the invoices issued by the plaintiff reflected the
name of Capicol 1 instead of Capicol – and
until the project
ran into funding issues, the plaintiff was paid.
23.
In
2010 the project ran into funding issues and funding dried up and
although they were contractors on site because there was an
occupation deadline, there was no funding with which to complete the
construction.
24.
On
2 February 2011, Brookfield (now known as Villa Retail) entered into,
what they termed, a “Settlement Agreement”
(the
Settlement Agreement) in order to settle disputes which had arisen
between them. The core function of the Settlement Agreement
was to
cancel the January 2009 agreement and to allow Capicol 1 to register
a second covering bond in favour of Brookfield over
a 37,4% undivided
share in the properties
15
in the amount of R1,590 billion. Capicol 1 also undertook to complete
the development of the Mall with further development funding
of R1,4
billion which it was still to secure.
25.
However,
on 14 July 2011, Capicol 1 and Brookfield then entered into a “Sale
of Business Amendment Agreement” (the July
2011 agreement) in
terms of which the January 2009 agreement was revived, and Capicol 1
sold 80% undivided share to the property
and business enterprises
conducted by it in respect of the property to Brookfield.
Interestingly enough, in the July 2011 agreement
it appears that a
large portion of the payment to be made by Brookfield was to be put
to use in paying what the July 2011 agreement
refers to as “Capicol
1 contractors”. It is specifically recorded in par 7.1.2.2.2 of
the July 2011 agreement that
an amount of R300 million would be paid
to the plaintiff, and this payment is specifically referred to in the
July 2011 agreement
as “
the
GD Irons R300 million payment”
and the contract specifically states that “…
the
rand value of the indebtedness in respect of the GD Irons R300
Million payment will remain capped at such amount of R300 Million
and
will reduce upon any portion or portions thereof being paid…”.
26.
But
it was prior to the latter two agreements that the issue of whether
Capicol or Capicol 1 was the employer raised its head. By
this stage,
the funding of the construction had become problematic and dried up.
On 11 October 2010, Bredells
16
sent a letter of demand, in terms of Section 345 of the Companies
Act, 1973, to Capicol. It was met with a response from Bert Smith
Inc
17
dated 18 October 2010 which states the following:
“
Our
instructions are to advise that our client disputes being indebted to
your client as alleged, or at all, and to record that
Capicol 1 (Pty)
Ltd is in fact the party that your client had contracted with.
We
hold firm instructions that should your client elect to proceed to
take action or bring an application against our client with
respect
to the indebtedness that you elude to in your said letter we will
bring an application for rectification of the said Agreement.”
27.
On
2 November 2010, Bredells replied as follows:
“
Our
client contracted with Capicol (Pty) Ltd. Our client denies that it
was the true intention of the parties that the building
contract
should have been concluded with Capicol 1 (Pty) Ltd. Hence an
application for rectification will be opposed.”
28.
On
9 November 2010 and in response to this, Capicol’s attorney
records the following:
“
We…wish
to request that your client gives serious consideration to its
current stance on this matter.
It
is our submission that if your client had in fact contracted with
Capicol (Pty) Ltd, which fact we dispute, your client would
have no
builders lien on The Villa building works as same would not have been
contracted and the improvements to The Villa property
would have been
done at the expense of Capicol (Pty) Ltd at your client[s] expense
(Gouws v Chesterpools).
If
however your client persists and proceeds to bring an action to
[liquidate] Capicol (Pty) we will have no choice but to bring
an
application for rectification.”
29.
It is common cause that
plaintiff did launch the application for liquidation which failed.
There is no application, or counterclaim
for rectification brought by
either of the defendants that was placed before me and, in fact, they
oppose the claim for rectification
in this action.
The
action under case no 29072/2013
30.
This
is an action brought by Quebec Electrical Contractors CC (Quebec)
against Capicol 1 in 2013. Quebec was one of the subcontractors
on
the Villa project and it sued Capicol 1 for the amount of
R5 718 974-68 plus interest and costs for electrical work
done on the Villa project.
31.
The
context and relevance of this action is that Pieterse gave evidence
in this matter on behalf of Qeubec and, in cross-examination
of the
matter before me, the defendants used the judgment in Quebec to lay a
basis for their argument that rectification could
not be granted.
32.
In
Quebec, Kubushi J granted judgment in favour of the plaintiff against
Capicol 1. She did so based on, inter alia:
32.1
Capicol 1 was mentioned as the land owner and developer of the Mall
in the agreement between the engineer and the City of Tshwane;
32.2
performance guarantees were issued in the name of Capicol 1;
32.3
Quebec’s letter of appointment referred to Capicol 1;
32.4
although Pieterse testified there that “
the
professionals in respect of the Villa Mall project were appointed by
Capicol”
18
,
he also stated that “ …
he
was employed by Kyriacouyriacou as a project manager of Capicol and
duly authorized to act in all the projects, including The
Villa Mall
project which belonged to Capicol 1…”
;
32.5
In the context of all the relevant witness and documentary evidence,
she found that it was clear that Capicol 1 was liable
for the
payment.
The
evidence
Mr
Pieterse
33.
Mr
Pieterse testified that he attained an Advanced Project Management
diploma through UCT in 2017 and has been a project manager
and a
development manager for approximately 30 years. He was also a
director of Capicol for a period of approximately 10 months
from 14
June 2010 to 1 March 2011. His company, Daseeh Property Consultants
(Daseeh), had a written contract with Capicol in terms
of which he
managed all of Capicol’s projects including those regarding the
Villa Mall and the Zambesi Mall. He had no contract
with Capicol 1,
the developer and the owner of the land was in fact Capicol 1
34.
Upon
initiation of the Agreement in 2009 a mistake crept in in the
reflection of the employer’s name in the Agreement as the
employer is reflected as the Capicol instead of Capicol 1. He
admitted that this was, in all likelihood, his mistake. He stated
that it was an “honest mistake” and that it is clear from
the Brookfields agreement that Capicol 1 was the true contractor
because it is the owner of the properties. This mistake perpetuated
itself until May 2009 until it was rectified per the email
of 8 May
2009.
35.
It
would appear that the QS also missed this mistake and he conceded
that neither he, nor anyone else on behalf of Capicol or Capicol
1,
informed the plaintiff that they are contracting with Capicol 1 and
not Capicol
.
36.
Pieterse’s
evidence against the defendant was sought to be explained away by the
defendants in cross-examination as stemming
from the so-called “bad
blood” between them as he had not yet been paid for the
project.
37.
It
is indeed so that Pieterse has given contradictory evidence in the
Quebec matter and this matter. In the former, it appears that
he gave
evidence that Capicol was the responsible party; in this matter
whilst he conceded that the Agreement was in the name of
Capicol, he
sought to lay responsibility at the door of Capicol 1.
38.
Whilst
his evidence is contradictory, and he sought to absolve himself of
the blame of the confusion regarding the actual contracting
party,
his evidence cannot be seen in isolation of the remainder of the
evidence placed before me.
Ronelle
Scheepers
39.
She
is a registered and Practising architect at Osglo which was appointed
as the principal agents of the Villa project. They were
approached in
2007 by Kyriacou to put a together for the Mall - at the time, Osglo
were the principal agents for the Zambezi Mall
project
.
40.
She
put together draft drawings for the project, Kyriacou acquired the
land for the project, and the draft drawings were submitted
to the
City Council for approval. The pro forma title deed submitted to the
City Council also reflected Capicol 1 as the owner
of the land.
41.
The
principal agents are the “
employers
watchdog
“,
and Osglo had full authority to represent the employer. All the
interim payments made throughout the project were authorised
by her
and she had authority to issue them.
42.
Each
payment certificate
19
is issued in a standard format. The first 6 interim payment
certificates reflected the employer as Capicol and the plaintiff as
the contractor. From certificate number 7 the employer is reflected
Capicol 1.
43.
Her
evidence was that she had worked on various projects on behalf of
Kyriacou and Capicol, and back then she was only aware of
the
existence of Capicol. It was only when the land was purchased and
transferred into Capicol 1’s name that she became aware
of its
existence; and it was only in May 2009 when the payments were
allocated to different projects and they had instructions
to change
the payment certificates that she became aware of the various
entities within the Capicol group. She then began issuing
the interim
payment certificates in the name of Capicol 1. The clear import of
her evidence was that, were it not for the notification
on 9 May 2009
on the specific instructions of Kyriacou, she would have continued to
issue the interim payment certificates in Capicol’s
name
20
.
44.
Osglo
was paid from a Standard Bank account with the reference “Capicol”
but there was no specific indication other
than this as to which
company had made payment, and that a claim has been lodged with the
BRP’s for monies outstanding to
it. The claim has been received
but there’s no indication as yet as to whether it has been
approved.
45.
The
Agreement also makes provision for 160% interest to be charged on
amounts outstanding in respect of the interim payment certificates.
She used the Reserve Bank’s website for the rates to be applied
to calculate the interest and she applied the in duplum rule
as from
April 2018. She conceded that she has no personal knowledge of the
actual rates of interest and that she has not verified
the
correctness of the interest rates reflected on the reserve bank
website.
46.
I
found Scheepers to be a good witness. She did not prevaricate, she
was clear in her answers and made the correct concessions which
she
needed
21
to do so. I cannot find in any respect that her evidence was not
relevant or cogent, nor can I find that she was not a reliable
witness.
Mr
Rüde
47.
Mr
Rüde was the last witness called by the plaintiff. He is a civil
engineer with an Honors degree in Construction Project
Management
from the University of Pretoria. He has been the managing director of
the plaintiff for the past16 years. Prior to this
he worked at Murray
& Roberts for 30 years.
48.
His
evidence was that tenders were put out for the Villa project during
mid-2008 and the plaintiff submitted a bid. The Agreement
was signed
on 1December 2008 - he signed it on behalf of the plaintiff and
Kyriacou on behalf of the Capicol. The Agreement was
witnessed by the
commercial director of the plaintiff and Pieterse on behalf of
Capicol
.
49.
At
the time that he entered into the agreement he was unaware of the
fact that there were different companies within the Capicol
group.
50.
The
plaintiff’s VAT invoice was based on the interim payment
certificate issued by Scheepers. On receipt of the interim payment
certificate, the plaintiff would issue out a tax invoice and submit
it for payment.
51.
He
confirmed that pursuant to an email dated 8 May 2009, received from
Kyricaou’s personal assistant, the plaintiff’s
invoices
changed to reflect Capicol 1 (with Capicol’s VAT number) and no
longer Capicol. His evidence was that this change
was of no moment to
him as it often happens during the course of a contract that invoices
are changed to reflect a specific entity
- for plaintiff, whether it
was made out to Capicol or Capicol 1 was of no importance. And
indeed, plaintiff was paid (yp to a
point) on the interim payment
certificates issued by Capicol, and later Capicol 1.
52.
During
approximately June 2009 the plaintiff was asked to work slower
because of financing issues experienced by the employer but
it could
not do so for two reasons: firstly, because of the timelines
contained in the Agreement itself and secondly, because equipment
and
materials had to be pre-ordered so that the building works were not
held up by a lack of necessary materials. To accommodate
the
financial issues experienced by the employer at the time, and because
plaintiff was assured that the cash flow issues were
only temporary
and would be resolved quickly, the plaintiff agreed to adjust the
interim payment certificates so that they would
be for a maximum
amount of R40 million each. The fact that plaintiff had a builder’s
lien over the property
22
also meant that its risk exposure was minimal.
53.
During
July 2018/August 2018 the plaintiff realised that all the finance
promises were no good and the plaintiff gave notice that
it needed an
extension of time within which to finalise the building project
because of the delays. On 27 August 2010 the plaintiff
gave final
notice that it was suspending the construction until the finance
issues were resolved. Plaintiff then exercised its
lien over the
property.
54.
Various
attempts have been made to recover the outstanding money from the
defendants both via letters of demand and via liquidation
proceedings
but, thus far, to no avail.
55.
As
the plaintiff’s legal representatives only consulted with
Pieterse in 2018 they only then became aware of the true position
as
regards which defendant was liable.
56.
Although
the plaintiff instituted a claim with the BRP’s, apparently
that claim has not been recognised but Rüde was
not sure why.
57.
Rüde’s
evidence is that, at the time the Agreement was concluded, he was not
aware of the existence of any other company
in the Capicol group
other than the first defendant. His evidence was that it was only in
October 2010 that he became aware of
the existence of Capicol 1 as a
result of the position the defendants had taken up as regards
liability on the Villa project in
the correspondence between the
respective attorneys. This was cemented in the abortive liquidation
proceedings against Capicol.
However, his position is that it is
either the one or the other of the defendants that remains liable for
payment to the plaintiff
and that the common mistake perpetuated by
the parties is that the Agreement should reflect Capcol 1 as the
employer.
58.
When
it was put to him in cross-examination that, in actual fact, the
plaintiff had never had the intention to conclude the Agreement
with
Capicol 1, his response was that the plaintiff had the intention to
conclude the Agreement with the owner of the property
and that the
developer that represented the owner was Capicol. As the owner of the
property was Capicol 1, the Agreement should
have reflected it as the
employer.
59.
Whilst
Rüde was, on occasion argumentative, that does not detract from
the overall impression of his evidence or him as a witness.
It is
very clear that he was not concerned with the nitty-gritty of the
name of the entity with which plaintiff was contracting
– he
was interested in entering into an Agreement with the owner of the
land. He was under the impression that Capicol owned
the land, and
this impression remained until evidence demonstrated the contrary.
60.
I
found Rüde to be a consistent witness in his evidence.
Evaluation
of the evidence
61.
In
my view, the direct and circumstantial documentary evidence presented
by the plaintiff in support of its claims cannot been seen
each in
isolation: each witness’s evidence either corroborated,
supplemented or enhanced the evidence of another or the documents
placed before me during the evidence. As such, it is this evidence
which must be evaluated as a whole to determine whether the
plaintiff
can succeed on either of its main or its alternative claims.
Re
: rectification
62.
To
succeed with a claim for rectification, the plaintiff must allege and
prove the following:
62.1
that an agreement was concluded between the parties and reduced to
writing;
62.2
that the agreement does not reflect the true intention of the parties
– this requires that the common continuing intention
of the
parties as it existed at the time when the agreement was reduced to
writing be established;
62.3
an intention by both parties to reduce the agreement to writing;
62.4
a mistake in drafting the agreement, which mistake could have been
the result of an intentional act of the other party or a
bona fide
common error;
62.5
the actual wording of the true agreement.
23
63.
The
defendants argue that rectification cannot be granted as:
63.1
Pieterse’s evidence was to the effect that Capicol 1 had
intended to be bound as the employer when the Agreement was
concluded
in 2008;
63.2
Rüde’s evidence was that the plaintiff had intended to
conclude the Agreement with Capicol;
63.3
as a result, Capicol 1 and plaintiff did not share a common
continuing intention to be bound at the time the Agreement was
concluded on 1 December 2008 and therefore the plaintiff had failed
to prove that the Agreement does not reflect the true intention
of
the plaintiff and Capicol 1;
63.4
that the case in the pleadings is that of a bona fide common error –
it is not one based on a mistake brought about by
the intentional act
by Capicol 1. The evidence was to the effect that the error was
brought about by confusion and this is insufficient
to found the
claim for rectification.
64.
Mr
Hartzenberg argues that the mechanics of a mistake are irrelevant as
is whether the mistake is a reasonable error or not. Once
the court
is satisfied that the written agreement is not the same as the actual
agreement arrived at, the court will grant rectification.
24
The point is that
“
[T]he
broad underlying principle of the doctrine of rectification is that
in contracts regard must be had to the truth of the matter
rather
than to what has been written, and the mistake must yield to the
truth.”
65.
In
this matter, the totality of the evidence in my view supports the
argument that rectification should be granted as:
65.1
Pieterse’s evidence is that Capicol 1 was the employer,
Capicol1 was the developer and Capicol 1 owned the land on which
the
development was to be done;
65.2
the evidence was unchallenged that at the time the tender was put
out, the logo that was used was that of Capicol, the meetings
were
held at Capicol’s boardroom, the developer was stated to be
Capicol, the Agreement described the employer as Capicol.
It is
important to note that it was the defendants who were responsible for
issuing all the documentation;
65.3
all the events subsequent to par 65.2 supra pointed to Capicol 1 as
the employer ie the email of 8 May 2009, payment certificates
7 to
23, the invoices issued by the plaintiff subsequent to the email of 8
May 2009, the Brookfield Agreement, the Settlement Agreement
and
(especially) the July 2011 agreement;
65.4
Rüde’s evidence was that he had intended to conclude an
agreement with the owner of the property. It is not disputed
that
Capicol 1 was the owner of the property.
66.
In
Lazarus
v Gorfinkel
25
the court stated
“
In
the instant case the only available evidential material as to
defendant’s state of mind is circumstantial in nature. This
being a civil case, it is not necessary for plaintiff to prove that
the inference which he asks the Court to make is the only reasonable
inference. He will discharge the onus resting on him if he can
convince the Court that the inference which he advocates is the
most
obvious and acceptable from a number of conceivable inferences…
And
where there are several equally acceptable possible inferences,
defendant’s failure to testify would justify the selection
of
the one which was adverse to defendant, on the application of the
principle in Galante v Dickinson…”
67.
The
fact is that it was the defendants attorneys of record insisted that
Capicol 1 is the party that contracted with the plaintiff
and
repeated this assertion in the letters of 18 October 2010 and 9
November 2010.
68.
Of
course, the evidence of Kyriacou on this issue would have shed more
light – but he elected not to testify. In
Galante
v Dickinson
26
the court stated:
“
In
the case of the party himself who is available, as was the defendant
here, it seems to me the inference is, at least, obvious
and strong
that the party and his legal advisers are satisfied that, although he
was obviously able to give very material evidence
as to the cause of
the accident, he could not benefit and might well, because of facts
known to himself, damage his case by giving
evidence and subjecting
himself to cross-examination.”
69.
Thus
the failure of Kyriacou to give evidence as to the identity of the
employer and true contracting party in terms of the Agreement
with
the plaintiff must be seen in the context of
Lazarus
v Gorfinkel
and the facts of this matter.
70.
I
am satisfied that it was, in fact, Capicol 1 that was the employer in
terms of the Agreement dated 1 December 2008.
71.
The
question is now: how must the amounts of certificates 1 to 6 be dealt
with. These amount to R147 204 872-73. The evidence
was
that these certificates were paid during 2009 and no not form part of
the aggregate amount of unpaid certificates for which
plaintiff
claims. There is also no counterclaim for repayment. This being so,
there is no necessity to deal with this issue in
the determination of
the issues between the parties.
The
interest calculation
72.
Scheepers’
evidence as to the interest using the repo rate reflected on the
website of the Reserve Bank, was not truly challenged
by the
defendants. The highwater mark of the evidence was that she had not
sought to independently verify that information as correct.
No
evidence was put before me to challenge the evidence and the
in
duplum
rule capped the interest as of April 2018 – this was also not
challenged by the defendants. In any event, the manner in which
the
judgment is framed makes any challenge to her evidence superfluous.
The
claim
73.
There
was no challenge mounted to the calculation of the amount claimed by
the plaintiff in its pleadings.
One
last aspect
74.
A
month after the hearing and argument was concluded in this matter,
and on 13 October 2021 a Mr Myburgh addressed correspondence
to me
through my secretary. In this he informed me that he is an attorney
of this court and that he represents Villa Retail Park
Investments
(Pty) Ltd (ie Brookfield) and he is approaching me as “
amicus
curiae
”
in regard to this trial. It appears, from his letter that he has
intimate knowledge of the evidence led and the defences
mounted by
the defendants during this trial. As such, he wanted to bring certain
information to my attention as regards dealings
he had had with the
BRP’s and affidavits filed specifically on behalf of Capciol 1
and Kyriacou in the liquidation proceedings.
His email to me was not
copied to any of the parties in this action.
75.
Given
the irregular nature of this, I immediately caused my secretary to
forward the email, and its attachments to the parties for
their
comment.
76.
On
22 October 2021, the plaintiff sent a response in which it objected
to the email and the attachments. The defendants elected
not to
respond.
77.
In
my view, Mr Myburgh, on his own version, is an attorney and an
officer of this court. As such he is aware of the rules regarding
admitting further evidence once the matter has been finalized and
before judgment is handed down. He has brought no application
to be
admitted as
amicus
,
nor has he brought an application to re-open the trial and lead
further evidence. This is important as it affects the rights and
interests of the actual parties to the litigation of which he is not
one. As stated, Mr Myburgh is neither a party to the litigation,
nor
does he represent any of the parties in this litigation, nor has he
applied to be so joined and his clients (Villa Park Retail)
have also
never sought to be joined in these proceedings. It is therefore
unclear what mandate he has from his clients to direct
any
correspondence at all.
78.
In
my view, the emails and affidavits he placed before me are not
evidence and cannot be afforded that weight. They are, as is his
email, not taken into account for purposes of the evaluation of the
actual evidence presented.
Conclusion
and order
79.
I
am therefore of the view that the plaintiff must succeed on its main
claim against the second defendant and accordingly the following
order is granted:
79.1
judgment is granted in favour of the plaintiff against the second
defendant as follows:
79.1.1
an order that the building agreement between the plaintiff and the
second defendant is rectified in the following respects:
79.1.1.1
rectification of the JBCC Series 2000 agreement which forms part of
the building agreement between the plaintiff and the
second defendant
to record the name of the employer at page 1 thereof to be “Capicol
1 (Pty) Ltd”;
79.1.1.2
rectification of the name of the employer set out in paragraph 1.1 of
the Contract Data section of the agreement to be
recorded as “Capicol
1 (Pty) Ltd”;
79.1.1.3
rectification of the name of the principal agent set out in paragraph
1.2 of the Contract Data section to be recorded as
“Osglo
Pretoria (Pty) Ltd”;
79.1.1.4
rectification of the name of the developer/employer in each of the
documents, letters and addendums which formed part of
the building
agreement, to be recorded as “Capicol 1 (Pty) Ltd” and
not “Capicol (Pty) Ltd”;
79.1.2
payment of the amount of R249 444 435-45;
79.1.3
interest on the sum of R249 444 435-45 calculated and
compounded monthly at 160% of the repo rate of interest charged
by
the South African Reserve Bank to registered banks from time to time,
from 20 November 2010 to date of payment;
79.1.4
costs of suit.
B
NEUKIRCHER
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION
Delivered:
This judgment was prepared and authored by the Judges whose names are
reflected and is handed down electronically by
circulation to the
Parties/their legal representatives by email and by uploading it to
the electronic file of this matter on CaseLines.
The date for
hand-down is deemed to be 25 April 2022.
APPEARANCES:
For
The Plaintiff
: Advocate CJ Hartzenburg SC
Instructed
by
: WN Attorneys Inc
For
the 1
st
and 2
nd
Defendants
: Advocate PG Cilliers
Instructed
by
: Hills Incorporated
Date
of hearing (MS Teams)
:14 September 2021
Further
heads of argument filed by plaintiff on 27 September 2021 and by the
first and second defendants on 1 October 2021. Further
correspondence
between the plaintiff dated on 22 October 2021.
Date
of judgment:
25 April 2022
sino noindex
make_database footer start