Case Law[2025] ZAWCHC 191South Africa
Raaleborg Environmental (Pty) Ltd v Cape Winelands District Municipality and Another (2024/142404) [2025] ZAWCHC 191 (5 May 2025)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2025
>>
[2025] ZAWCHC 191
|
Noteup
|
LawCite
sino index
## Raaleborg Environmental (Pty) Ltd v Cape Winelands District Municipality and Another (2024/142404) [2025] ZAWCHC 191 (5 May 2025)
Raaleborg Environmental (Pty) Ltd v Cape Winelands District Municipality and Another (2024/142404) [2025] ZAWCHC 191 (5 May 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2025_191.html
sino date 5 May 2025
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
Number: 2024-142404
REPORTABLE
In
the matter between
RAALEBORG
ENVIRONMENTAL (PTY) LTD
APPLICANT
and
CAPE
WINELANDS DISTRICT MUNICIPALITY
FIRST RESPONDENT
CITY
MANAGER OF
CAPE
WINELANDS DISTRICT MUNICIPALITY
SECOND RESPONDENT
JUDGMENT
Date
of hearing: 18 February
2025, 17 March 2025
Date
of judgment: 5 May 2025
BHOOPCHAND
AJ:
1.
The Court heard the application and a counterapplication. The
parties
moved the urgent Court on 18 February 2025 to hear the matter. The
applications did not meet the threshold for urgency,
but the hearing
was expedited to 17 March 2025. The facts that inform the
applications are largely common cause.
2.
On 29 November 2024, Raalenborg Environmental (Pty) Ltd (‘the
Applicant’) issued an urgent application to, among others,
review and set aside the Cape Wineland’s District
Municipality’s
(“the Municipality”) repudiation and
withdrawal of the award of a tender (T2023/23) to the Applicant. The
Applicant
tendered for the operation and management of the
Municipality’s regional waste disposal facility at Worcester
for approximately
R270 million over ten years.
3.
The Municipality advertised the tender on 28 July 2023. The
Applicant
submitted its bid on 6 October 2023. The Municipality received seven
bids in total. The Municipality requested extensions
of the bid
validity period on three occasions: 26 February 2024 until 30 April
2024, 25 April 2024 until 30 June 2024, and 25 June
2024 until 30
August 2024. The bidders agreed to the extensions.
4.
On 26
August 2024, the Applicant was informed by the Municipality’s
Supply Chain Management Practitioner (‘SCM practitioner’),
Ms Niemand (‘Niemand’), writing for the Municipal
Manager, that the Municipality had conditionally awarded the tender
to the Applicant.
[1]
The
unsuccessful bidders were notified simultaneously of the decision.
The letter states, "Letters of notification were sent
to all
unsuccessful bidders during the week following the approval of this
bid by the Bid Adjudication Committee” (‘BAC’).
The
award of the tender was subject to a 14-day objection period as per
the Supply Chain Management (‘SCM’) Regulation
49, as
well as to 21 days for appeals as per section 62 of the Municipal
Systems Act 32 of 2000 (‘MS Act’) against
the decision
made. The Applicant was informed that they would be officially
notified as the successful bidder after the expiry
of the relevant
periods.
5.
On 17 September 2024, Niemand, writing for the Municipal Manager,
informed the applicant that the Municipality had awarded the tender
to the Applicant. The award was further conditional on the
Applicant
complying with the conditions, requirements, and specifications as
set out in the tender document (the contract). By
signing the form of
offer and acceptance, the Applicant agreed to perform all the
obligations and liabilities under the contract
and comply with all
the terms and conditions of the contract. A fully completed copy of
the contract was attached to the letter.
The Applicant signed the
contract on 18 September 2024.
6.
Nine days later, on 27 September 2024, Niemand sent an email
addressed to Leon Grobbelaar (‘Grobbelaar’), the
Applicant's director, regretting that the award letter had been
withdrawn
due to an administrative error. At the Applicant’s
request for an explanation, Siphokazi Manel (‘Manel’),
the
Senior Manager of Acquisitions and a member of the BAC, responded
on 30 September 2024. The email was copied to Ronel Leo, the Deputy
Director of Supply Chain Management and sent to Grobbelaar and
Niemand. The Municipal Manager was not copied on this email. Manel
explained that the award letter was sent out prematurely and
incorrectly due to an administrative error. Manel explained that the
BAC considered and recommended the tender, but the Municipality’s
Accounting Officer did not award it. The validity period
of the
tender had lapsed on 30 August 2024. In terms of the applicable
legislation, the Municipality could not legally proceed
with making
the award, as it would be unlawful and constitute irregular
expenditure. Manel advised the Applicant that the Municipality
was
taking immediate steps to rectify the situation. The tender would be
cancelled and readvertised as soon as possible. They were
conducting
a review to ensure that the correct procedures were followed.
7.
On 1 October 2024, Grobbelaar wrote to the Municipal Manager.
He
emphasised that the correspondence of 26 August 2024 and 18 September
2024 emanated from the Municipal Manager, who is the Municipality’s
Accounting Officer. The contract was signed on behalf of the
Municipality on 26 August 2024. Grobbelaar informed the Municipal
Manager that the Applicant considered the letters a repudiation. The
Applicant intended to accept the repudiation and recover damages
of
R61 778 838. The damages were calculated as 25% of the
contract price. The Applicant invited the Municipality to reconsider
its position by 4 October 2024 and suggested how the matter could be
resolved. The Applicant preferred that the contract, signed
on 16
August 2024, by F van Eck, the Municipality's Executive Director of
Technical Services, before the expiry of the validation
period,
remain.
8.
On 10
October 2024, the Municipal Manager, Henry Frederick Prins (‘Prins’),
responded to the Applicant and a letter
sent to the Municipality by
the Applicant’s lawyers. Prins explained that the tender's
validity period was 180 days.
[2]
The validity period is when the bidders' offers remain open for
acceptance. Prins referred to caselaw that spoke of the validity
period as one of the fundamental rules of tendering, the period
within which the process should be finalised.
[3]
He stated that by the time the tender's validity period had expired,
the Accounting Officer had made no decision, and the validity
period
had not been extended for a second time.
[4]
The Accounting Officer could no longer make an award as the
tender process was complete, and resuscitating it was impossible.
A
new bid process had to be initiated to ensure that all interested
parties were provided a further opportunity to tender.
9.
Prins
referred to further caselaw, which dealt with the legal consequences
of a public body's failure to accept a tender within
the stipulated
validity period.
[5]
He
reproduced the four interrelated propositions the Supreme Court of
Appeal referred to favourably in another case considered
before
deciding the issue.
[6]
The
decision to award a tender is an administrative action, and the
Promotion of Administrative Justice Act 3 of 2000 (‘PAJA’)
applies. Once a contract has been entered into following the award of
the tender, the law of contract applies. A contract entered
into
contrary to prescribed tender processes is invalid. Even if no
contract is concluded, all steps taken following a process
which does
not comply with the tender processes are also invalid.
[7]
10.
Prins
referred to section 29(1)(b)(i) of the Supply Chain Management
Regulations.
[8]
He stated that a
BAC must, depending on its obligations, make a final award or a
recommendation to the Accounting Officer, who
then makes a final
award. In terms of section 5(2) (a) of the Supply Chain Management
Regulations, an Accounting Officer may not
subdelegate the power to
make a final award above R10 million (VAT included). A tender
falling into that category serves in
the BAC only for recommendation
purposes.
11.
Prins then explained that, unfortunately, partly due to an
administrative oversight,
it was mistakenly assumed that the BAC
awarded the tender. The award letters were erroneously sent to the
Applicant, and the subsequent
agreement was signed. At the time, the
Accounting Officer considered the recommendation by the BAC to make
an award, the validity
period had already expired, and the Accounting
Officer was no longer entitled to make any award. Relying on
Takubiza
Trading
, Prins informed the Applicant that the agreement entered
into was invalid. The contract between the Municipality and the
Applicant
was contrary to the prescribed tender processes.
12.
The Applicant contended that it was Prins who had extended the
validity period
to 30 August 2024. The Applicant referred to the
extension letters that Niemand signed for the Municipal Manager. The
Applicant
asserted that it is unfathomable that Prins was not
acquainted with the tender process and the roles and authority of the
Accounting
Officer and the BAC, under sections 5(2)(a) and
29(1)(b)(i) of the SCM regulations. The Applicant submitted that a
municipality
does not have the authority to correct its own
administrative errors and acted unlawfully in doing so, to the
Applicant’s
severe prejudice and detriment. The Respondents
should have initiated a legality review of their administrative
oversight, incorrect
procedure, or decision.
13.
The Applicant contended that Prins had a duty of care to ensure that
the applicable
procedural steps were properly taken and that the
tender was properly awarded by 30 August 2024, which the Applicant
maintained
had been done. The Municipal Manager should have ensured
proper compliance with the Municipality’s procurement policies.
The tender was properly awarded to the Applicant, and the terms of
the subsequent agreement concluded should bind the Respondents.
The
Applicant submitted further that there had been substantial
compliance on the Respondents' part and that they should be bound
by
the subsequent agreement concluded.
14.
Prins deposed to the Respondents' answering affidavit. The content
accorded
with the tenor of the correspondence between the Applicant,
Niemand, Manel, and him with a few nuances. Prins contended that the
BAC passed a resolution recommending that he, as Municipal Manager,
award the Applicant the tender to operate and manage the
Municipality’s
waste disposal facility. He contended that
Niemand’s conduct in erroneously informing the Applicant of the
BAC’s decision
and providing the Applicant with a signed
contract from the Municipality was unlawful, irrational, and
ultra
vires
the applicable legislation governing the procurement of
goods and services in the Municipality. He stated that the validity
period
had expired when the BAC’s recommendation served before
him.
15.
Prins contended that the Applicant had insisted on specific
performance despite
the ostensible contract and the purported award
being unlawful and invalid. The Municipality did not accept
that the Applicant
was entitled to institute the application as it
was bad in law. The Municipality was determining the correct course
of action when
the Applicant launched this application. The
Municipality had no option but to nullify Niemand’s actions
and/or review and
set aside the ostensible tender award and all
administrative acts purportedly concluded.
16.
Prins explained that the Bid Evaluation Committee (‘BEC’)
convened,
considered the bids, and recommended to the BAC to consider
and recommend to the Accounting Officer that this tender be awarded
to the Applicant, subject to section 33 of the Municipal Finance
Management Act (‘MFMA’). Prins acknowledged that he
is
the Municipality's Accounting Officer under the MFMA and that the
Applicant’s bid offered the lowest market-related price.
The
BAC convened to consider the BEC’s recommendation on 1 July
2024. The BAC directed the BEC to explain why it had excluded
Khabokedi Waste Management (Pty) Ltd, another of the bidders, and
recommended the Applicant. On 26 July 2024, the BEC, after
considering
the BAC’s enquiry, recommended to the BAC once
again that it award the tender to the Applicant, subject to section
33 of
the MFMA and the Municipal Council adopting a resolution in
which it approved the entire contract exactly as it was to be
executed.
On 23 August 2024, the BAC convened and recommended that
the tender be awarded to the Applicant, subject to section 33 of the
MFMA.
17.
On the day the BAC awarded the tender to the Applicant, it awarded
five other
tenders. After the meeting, Manel, who acted as the BAC's
secretary, went to Niemand to inform her of the outcome of the BAC’s
deliberations. Niemand sits opposite the room where the BAC
deliberates. Niemand handles most of the Municipality’s supply
chain management and administrative correspondence. Prins reiterates
that due to an inadvertent administrative error, Niemand
misunderstood Manel to mean that the tender be awarded to the
Applicant rather than that it had to serve before the Municipal
Manager
who would award the tender. Niemand had explained that she
did not know the BAC had not awarded the tender and could not do so
as a matter of law. Prins asserted that Niemand’s error was
understandable given that the Municipality rarely awards tenders
above R10 million. Niemand obtained Van Eck’s signature to the
contract based on the same error. The Municipality had not
made the
award, and there was no compliance with section 33 of the MFMA. Manel
sent the BAC’s signed approvals to Niemand
on 17 September
2024. Manel informed Niemand on the same day that the tender still
had to be approved by the Municipal Manager.
Niemand confirmed that
she did not see Manel’s email advising her that the tender had
to be approved by Prins. Niemand proceeded
on 18 September to inform
the Applicant that the Municipality had finally awarded the tender to
it.
18.
Prins alleged that a hard copy of the BEC and BAC recommendations was
delivered
to his office on 19 September 2024 for his final
consideration and award. Prins stated he does not sit in the same
building as
Niemand and Manel. He is not privy to or involved in the
BEC or BAC process. He relies on and acts upon written
recommendations
received from the two committees. He realised that
the bid was only valid until 30 August 2024 when he began reading the
recommendations.
He sought a legal opinion by referring the documents
to the Municipality’s head of legal services, Sarah Sanders
(‘Sanders’).
19.
Sanders advised Prins on 26 September 2024 that there was no valid
tender and
the process had concluded, albeit unsuccessfully. She
advised him that he could not award the tender to the Applicant.
Prins states
that he was advised on 30 September by Ms du
Raan-Groenewald, the Chief Financial Officer, that Niemand had
erroneously sent out
the award notifications to the Applicant.
Manel’s email of 30 September to the applicant followed. Prins
states that his
letter of 10 October 2024 was an attempt to avoid
litigation and legal costs and to settle the issue with the
Applicant.
20.
In its replying affidavit, Grobbelaar reiterated that on each
occasion a request
for an extension was made, the requests were made
by Niemand for and on behalf of the Municipal Manager. The Applicant
contended
that the documents were in template form, and although
physically signed by Niemand, it was intended to be from the
Municipal Manager.
F Van Eck was part of the BAC committee, which on
23 August 2024, resolved that the Municipal Manager was required to
award the
tender to the Applicant. Grobbelaar challenged the
Municipal Manager’s contention that the Municipality rarely
handled tenders
over R10 million. He referred to a tender awarded to
Burger & Wallace Construction for constructing a landfill in
Worcester.
The tender was awarded in March 2024, six months before
the Applicant received its notification of the tender award. That
letter
was also signed by Niemand and not Prins.
21.
The Applicant asserted that a Supply Chain Management Practitioner
oversees,
manages, and executes procurement and supply chain
activities. Niemand is expected to have a sound knowledge of all
relevant MFMA
supply chain management regulations. Prins did not take
issue with the letters sent to the unsuccessful bidders. The
Applicant
noted that the Municipality did not allege that Niemand
acted outside the scope of her employment terms and conditions or
that
she acted ‘on a frolic of her own’. The
municipality’s case is that the tender's award arose through an
administrative
error. The Applicant contended that Prins had
employed Niemand as SCM practitioner and having allowed her to act in
that
manner she did and impliedly created and established the
impression and made the representation to the parties including the
Applicant
that when Niemand purported to act in the way she did, her
actions were the actions of the Municipal Manager. In the
alternative,
Niemand acted within the course and scope of her
conditions of employment. In a further alternative, the Applicant
contended that
the Municipal Manager having known the fact that the
tender, a purported rarity in the Municipality could only be awarded
by him,
should have been more involved in the process, and ensured
that any correspondence emanating from the Municipality in respect of
the tender were prepared and signed by him, alternatively should have
contained some disclaimer as to Niemand’s lack of authority
and
should have approached the awarding of the tender with the required
degree of urgency to ensure that the award of the tender
was made
before the termination of the tender validity period.
22.
Having allowed Niemand to have acted in the manner that she did, the
Municipal
Manager created and established the representation that the
Municipal Manager had awarded the tender to the Applicant and that
all internal processes of the Municipality had been duly complied
with, specifically regarding the tender validity period on 30
August
2024. The representations to the knowledge of the Municipal Manager
were false in that he at all relevant stages was aware,
alternatively
should reasonably have been aware that Niemand signed the various
documents and correspondence carrying with it binding
legal
consequences and that unless told otherwise, third parties such as
the Applicant would assume and accept that the documents
and/or
correspondence emanated from the Municipal Manager and not from
Niemand. The representation was designed and intended to
mislead
third parties such as the Applicant, alternatively had the intended
or unintended consequences of third parties being addressed
by
Niemand and /or addressing correspondence to Niemand, received
communications from and or were communicating with the Municipal
Manager and not Niemand.
23.
The Applicant, having laboured under the representations described
above and
understanding therefrom, acted to its detriment in that,
bearing in mind the approaching expiry tender validity period on 30
August
2024, the Applicant did not question the correspondence of 26
August 2024 and was deprived of an opportunity to ensure that the
required steps that the Municipal Manager should have undertaken were
undertaken timeously.
24.
The Applicant contended that the Respondents should be estopped from
denying
the tender award to the Applicant on 26 August 2024. The
Applicant contended that the Municipal Supply Chain Management Policy
of the Municipality, specifically clause 5(2), and the purported
non-compliance are of no moment and do not constitute a material
deviation from the applicable legislative processes. The purported
non-compliance did not compromise the fair, equitable, transparent
and cost-effective requirements of section 217 of the Constitution.
This is so given that the tender conditions provided that an
award
would be made to the highest scoring tenderer. As the Applicant
scored the highest, the Municipal Manager had no discretion
but award
the tender to the Applicant. The Applicant contended that a refusal
to abide by or carry out a deviation from the recommendations
of the
BAC and BEC would have resulted in a contravention of the provisions
of section 217 of the Constitution.
25.
The Applicant then addressed the Respondents’ reliance on
section 33 of
the MFMA. There was no confirmation or resolution from
the Municipal Council, nor had there been publication before the
ostensible
conclusion of the contract. The Applicant asserted that
the purported irregularities, as far as Niemand and the confirmation
provided
by her on 26 August 2024, extend only to the granting of the
award. Suppose the Court were to find that the tender was timeously
awarded, i.e., before the expiration of the validity period. In that
case, the non-compliance with section 33 does not invalidate
the
awarding of the tender. The tender validity period does not extend to
the conclusion of the contract. The contract was not
required to have
been concluded within the 180 days initially set and extended to 30
August 2024. The only aspect that needed to
have been concluded
before 30 August 2024 was the acceptance of the Applicant's bid,
i.e., the awarding of the tender. The conclusion
of the contract
would have been competent at any time after granting the tender and
would still comply with, among others, section
33 of the MFMA.
26.
The Applicant contended further that the intended contract and the
terms and
conditions would have been tabled before the council for
public comment before the tender had been advertised. The
Municipality would have had to budget for the expense and comply with
section 33 of the MFMA before advertising the tender and inviting
tenderers. As the Municipality did not refer to the compliance with
section 33 by itself during the tender process, the Applicant
contended it was an afterthought.
27.
The Applicant states that the relief claimed by the Municipality, as
far as
the review is concerned, is sought without the Municipality
having filed the record of proceedings. The Applicant states that
examining
every meeting in which the tender was an agenda item would
be particularly interesting. The Applicant contends that under
section
172 (1) (b) of the Constitution, the appropriate order would
be to compel the Municipality to conclude the intended and required
contract with the Applicant. Alternatively, the Applicant would be
entitled to a review of the decision not to conclude the intended
contract with the Applicant. If there were no compliance with section
33, then the Applicant would be entitled to an order compelling
the
Municipality to do all such things and take all the steps required to
comply with section 33 of the MFMA and have the contract
subsequently
concluded.
28.
The Applicant filed its amended notice of motion simultaneously with
the replying
affidavit. It contended that the proposed way forward
suggested by the Municipality was untenable and unacceptable. The
suggestion
that a new tender process would be fair to all parties was
risible. Nothing about the tender process remained a secret. One of
the annexures records the Applicant’s total bid price,
including VAT. The competing bidders in the next round could adjust
their tender amounts to match or even beat the Applicant’s bid.
The prejudice suffered by the Applicant is a clear and unequivocal
violation of section 217 of the Constitution. An organ of state that
contracts for goods and services must follow a fair, equitable,
transparent, competitive and cost-effective system. The Applicant’s
tender was scrutinised twice by the BEC and once by the
BAC, after
which it was recommended to the successful bidder.
29.
The Applicant asserted that an internal administrative failure did
not automatically
invalidate the awarding of a tender and contract
that was concluded properly. It argued that there was substantial
compliance with
the prescribed legislation, and a procedural defect
should not avoid enforcing the contract. A municipality cannot
unilaterally
declare its administrative actions void. An
administrative decision, even if alleged to be defective, remains
valid until set aside
by a Court. The municipality’s assertion
that it could nullify Niemand’s actions without a Court order
is unlawful
and constitutes impermissible self-help. If the
Respondents genuinely believed that the award was unlawful, they were
duty-bound
to approach the court immediately for a legality review
rather than unilaterally withdrawing the award and attempting to
invalidate
a contract that had already been concluded. The
Municipality only resorted to review proceedings after the Applicant
instituted
its application. The timing of the review indicates that
The Respondents are pursuing a defensive measure, rather than a
genuine
concern about legality. The review application is not a
bona
fide
attempt to rectify an administrative mistake, but rather an
attempt to avoid compliance with an existing contract.
30.
The Applicant sought multiple forms of relief in its amended notice
of motion.
The first included a declaration that the tender was duly
awarded to the Applicant, the subsequent contract concluded between
the
Applicant and the Municipality is valid and binding on the
Municipality, and the latter is directed to give effect thereto. The
Applicant sought two alternatives to the declaratory order. The
Respondents are directed to concerning the intended contract, take
all such steps anticipated under section 33 of the MFMA,
alternatively that the Municipality’s failure to have
considered
and made a decision following the BAC’s
recommendations dated 23 August 2024, before the expiry of the tender
validity period
is reviewed and set aside under section 6(2)(g) of
PAJA (the administrative action concerned consisted of a failure to
take a decision).
The Applicant then sought a remedy under section
8(1)(c)(ii) of PAJA for the Municipal Manager’s failure to have
acted and
made a decision of replacement and substitution with a
decision awarding the tender to the Applicant. As an alternative
remedy
under section 8(1)(c)(i) of PAJA, the Applicant sought the
remittal of the tender to the Municipality for consideration and the
making of a decision within a period to be determined by the Court.
As a further alternative, the Applicant requested an extension
of the
tender validity period under section 172(b) of the Constitution.
31.
In its counterapplication, the First Respondent pursued a declaration
that the
Municipality’s ostensible award of the tender to the
Applicant as per the Municipality’s letters dated 26 August
2024
and 17 September 2024 is void, invalid, and of no effect,
alternatively, reviewing and setting it aside. The Municipality also
sought a further declaration that the contract concluded on 31 August
2024 is void, invalid, and of no effect, or to review and
set it
aside.
32.
Prins deposed to the founding affidavit in the counterapplication. He
was advised
that the Municipality could challenge the application
collaterally. The ostensible contract was concluded in breach of the
procurement
legislation. Prins labelled Niemand’s actions as
unauthorised, unlawful, and ultra vires the MFMA, and the
Municipality’s
Supply Chain Management Policy, thus in breach
of section 217 of the Constitution. Niemand’s actions were void
and unlawful.
The BAC had not awarded the tender to the Applicant as
it had no power to make the award. The conclusion of the
contract
was equally invalid as it followed Niemand’s unlawful
and invalid conduct relating to the tender award. There was no
confirmation or resolution from the Municipal Council, nor was there
publication before the ostensible conclusion of the contract
under
section 33 of the MFMA.
33.
Prins explained that he never withdrew the tender or the award, as
the Applicant
alleged. The award never took place, and the tender
process ended unsuccessfully. Prins contended that the Applicant is
the incumbent
service provider and will not be prejudiced
financially. It will be entitled to submit a bid for a new tender
process that the
Municipality intends to commence once the matter is
finalised.
34.
The Applicant contended that the Municipality cannot collaterally
challenge
its own decision while simultaneously seeking judicial
review. The Municipality should not have waited for the Applicant to
bring
its review application, nor wait for the Applicant to seek
enforcement. The counterapplication was only initiated after the
Applicant
sought specific performance, indicating it is a defensive
strategy rather than a
bona fide
review. A self-review must be
brought within a reasonable time, and the Municipality failed to act
promptly despite knowing of
the alleged irregularities before
litigation commenced. The Municipality cannot retroactively disown
its own administrative actions
to escape contractual obligations.
35.
The Applicant contended that section 33 of the MFMA did not prohibit
the contract
from being awarded. It merely required additional
oversight for financial planning. Any failure to comply with section
33 is an
internal governance issue which does not automatically
render the contract void. The Municipality should have remedied any
non-compliance
through proper internal procedures rather than
attempting a unilateral withdrawal of the tender. If there was a
failure in delegation
or internal approvals, it is solely the
Municipality’s responsibility. The legislative framework cannot
support the Municipality’s
attempt to invalidate the contract.
The award was properly concluded, and any procedural defects did not
justify its withdrawal.
36.
The Applicant contended that if the Municipality had concerns about
the bid
validity period, it should have extended it before disputing
the award. The Municipality’s request for declaratory relief
is
a reactive measure only pursued after the Applicant had sought
enforcement of the contract. The Municipality mischaracterised
the
principle of legality. It does not allow a public authority to evade
an award that was validly awarded and/or a binding contract
concluded
due to its own internal mismanagement. A just and equitable remedy
must balance the rights of the parties. In this case,
it favours
upholding a legally concluded contract rather than allowing a
government entity to escape liability due to alleged errors
of its
own making. The Municipality’s reliance on the principle of
legality is selective. It seeks to rely on legality to
invalidate its
own contract, but it ignores legality when it attempts to withdraw a
valid administrative decision without due process
unilaterally. The
Applicant alleges that the Municipality had full access to legal
remedies in the normal course. If the counterapplication
were
meritorious, it could have pursued it through ordinary review
proceedings. The doctrine of substantial compliance applies,
meaning
that technical noncompliance does not negate a contract that was
otherwise awarded.
37.
In reply, Prins said that he could not be expected to prove that he
did not
make the award. There was no merit to the Applicant’s
argument that the Municipal Manager is not a person, but an ‘office’
in that Niemand was somehow authorised to award the tender to the
Applicant as a part of that ‘office’. The MFMA, Supply
Chain Management Regulations and the SCM Policy require that an award
over R10 million, including VAT, may not be delegated and
may only be
made by him. Prins commented on the Applicant’s response to his
assertion that the Municipality rarely awards
tenders above R10
million. He explained that in the Burger & Wallace Construction
tender award to construct the landfill in
Worcester, he received a
recommendation from the BAC and made the award. He attached a copy of
the award, signed by him. He gave
the document to Niemand before she
sent out the notifications. Prins asserted that the Applicant’s
reliance on estoppel
is ill-conceived, as estoppel cannot be used to
enforce illegality. He dismissed the Applicant’s reliance on
substantial
compliance, which he reasoned could not circumvent or
overcome conduct that was
ultra vires
the prevailing
legislation.
38.
The Court has attempted to capture the allegations made by both
parties as comprehensively
as possible, leading regrettably to a
lengthy exposition of the application and counterapplication. The
Applicant, in particular,
endeavoured to interrogate the matter
extensively and repetitiously. The Court turns to evaluate the cases
of the Applicant and
the Respondents.
EVALUATION
The
Application
39.
The same facts and the applicable law inform the application and the
counterapplication.
The Applicant relies on an award and the
subsequent contract concluded for approximately R250 million over ten
years, made by the
Municipality to it. The Municipality has explained
that the Supply Chain Management Practitioner, Niemand, made the
award inadvertently
and as an administrative error. The
Applicant seeks validation of the award and the contract. The
withdrawal of the letter
of award occurred nine days after the
contract was concluded. The Applicant instituted this application
about six weeks after the
Municipal Manager refuted any award or
contract between the Municipality and the Applicant. The Applicant
knew that the Municipality
intended to review Niemand's actions when
it instituted its application.
40.
The Respondents premise their denial of the ostensible award made and
contract
concluded between the Municipality and the Applicant on four
grounds. Neither the BAC nor Niemand were authorised to award the
tender or conclude the contract. The Municipal Manager was the only
person authorised to award the tender. The bid validity period
had
expired at least three weeks before the Municipal Manager considered
the BAC’s recommendation that he award the tender,
provided the
section 33 requirements of the MFMA were met. The contract could not
have been concluded without compliance with section
33 of the MFMA.
41.
The material facts pertinent to the adjudication of the application
are that
the Municipality’s BEC and subsequently the BAC
recommended that the Applicant be awarded the tender to administer
and operate
its waste landfill in Worcester for approximately R250
million over ten years. The recommendation made by the BAC on 23
August
2024 was conveyed to Niemand, a Supply Chain Management
Practitioner, who then conditionally awarded the tender to the
Applicant
on 26 August 2024, four days before the bid validity period
for this tender expired. Niemand informed the unsuccessful bidders
that the award had been made to the Applicant and that they had a
right of appeal. Niemand facilitated the conclusion of the contract
between the Applicant and the Municipality, which van Eck signed on
26 August 2024. On 17 September 2024, Niemand awarded the tender
to
the Applicant on behalf of the Municipality. Niemand withdrew her
letter of award to the Applicant on 27 September 2024 due
to an
administrative error. These facts are common cause.
42.
The Municipality’s account of events that unfolded was that
Manel, the
Senior Manager of Acquisitions and secretary to the BAC,
informed Niemand on 23 August 2024 of the BAC’s deliberations
on
six tenders, which included the tender for the administration and
operation of the landfill. The BAC had recommended that
the
Municipal Manager award the latter tender in his role as Accounting
Officer, subject to compliance with the process prescribed
under
section 33 of the MFMA. Niemand misunderstood Manel and conditionally
awarded the tender to the Applicant on 26 August 2024.
Niemand also
procured van Eck’s signature for the contract. Manel reminded
Niemand on 17 September that the tender had to
be approved by Prins.
Niemand did not see the email sent by Manel. Niemand notified the
Applicant that the Municipality had
awarded the tender to it on 18
September 2024. The Applicant denied knowledge of the other tenders
approved by the BAC. It denied
the communications and correspondence
between Manel and Niemand and Niemand’s administrative error in
notifying it of the
tender award and her error in securing van Eck’s
signature. The Applicant admitted that the bid validity period had
expired
but denied that the tender process had been completed
unsuccessfully.
43.
Prins stated that he received the BAC’s recommendations on the
tender
from Manel on 19 September 2024. He is not involved in the BEC
or BAC deliberations. Upon perusal of the recommendations, he noticed
that the bid was only valid until 30 August 2024. He asked Binta to
send the documentation to Sanders. Sanders informed him there
was no
valid tender, and he refused to award it. Groenewald informed
him on 30 September 2024 that Niemand had erroneously
sent award
notifications to the Applicant. The Applicant denied these facts as
they did not fall within its knowledge, are legally
unsustainable, or
are at odds with its averments in the founding affidavit.
44.
The Applicant could not genuinely dispute the facts as related by
Prins, nor
could it provide any countervailing version. Niemand,
Manel, Binta, and Groenewald provided confirmatory affidavits.
Niemand provided
a more comprehensive confirmatory affidavit later.
If there had been any attempt to avoid awarding the tender
ex post
facto
to the Applicant, there would have had to be collusion
between five Municipal employees who would have sworn falsely under
oath.
Niemand withdrew her letter of award on 27 September 2024, days
before Prins heard from the Municipality’s legal department
and
from Groenewald, the Chief Financial Officer, who informed him of
Niemand’s error. The Applicant did not request a referral
to
oral evidence. There was no reason to refer any material or
genuine dispute of fact to oral argument. The Court would
not have
permitted the Applicant to conduct an inquisition if it truly
believed that a dispute was not foreseeable at the commencement
of
its application.
45.
The Court
is also not persuaded that the circumstances required separate and
comprehensive affidavits from Niemand and Manel.
[9]
It would not have taken their versions as related in the answering
affidavit any further. The Court notes that the Respondents
provided
a more detailed confirmatory affidavit of Niemand in their reply to
the counterapplication. The Applicant attached the
correspondence
from Niemand and Manel to its founding affidavit. Niemand’s
letter of withdrawal occurred on a Friday. Manel’s
response to
the Applicant’s enquiries about the meaning of Niemand’s
letter on the Friday occurred on the Monday. There
was no opportunity
to stage a conspiracy to deny the Applicant an award, had there been
compliance with the applicable legislation.
The Applicant chose to
proceed under Rule 6 rather than Rule 53. The latter may have
unearthed or refuted the type of evidence
it seemed to be looking
for. The Applicant has not persuaded the Court that the Municipal
Manager's account of events should be
rejected.
46.
The Applicant insisted that the tender award and contract were valid
and enforceable.
It considered the withdrawal of the letter of award
a repudiation and threatened to sue the Municipality for damages. The
Applicant
informed the Municipality that it should have initiated a
legality review of its administrative oversights, incorrect procedure
and decision. It contended that the Municipality had substantially
complied with the legislation, and it had already begun implementing
the contract. The Applicant requested an undertaking from the
Municipality that the funds earmarked for the tender be frozen. The
Applicant intended to apply to compel specific performance on a
lawfully awarded tender. The Respondents informed the Applicant
that
they would not freeze the tender amount and that they were in the
process of initiating a review application.
47.
The Court accepts that there are significant lacunae in the Municipal
Manager’s
account regarding what transpired with this tender.
He does not explain why he did not attend to the details of this
tender, like
the extension of the validity period, the coordination
of the BAC recommendations that required his decision, and compliance
with
the provisions of section 33 of the MFMA. There is no
explanation as to why the bid validity period for this tender was not
further
extended if the section 33 requirements were not met by 30
August 2024. To comply with section 33 of the MFMA, the bid validity
period would have had to be extended for at least another sixty days.
Prins does not explain why the BAC’s recommendation
was not
sent to him before the expiry of the bid validity period. Prins
denies that he is expected to prove he did not make the
award.
48.
The Municipality has raised three factors influencing the lawfulness
and validity
of the award and contract ostensibly made to the
Applicant. The first relates to the authority to award tenders above
R10 million.
Neither the BAC, Niemand, nor van Eck was authorised to
award the tender to or conclude the contract with the Applicant. That
is
the law. Niemand’s actions contravened section 5(2)(a) of
the Supply Chain Management Regulations and the Municipality’s
Supply Chain Management Policy. All tenders above R10 million,
including VAT, had to be awarded by the Municipal Manager. The
evidence before the Court is that Prins, the Municipal Manager, and
the Accounting Officer did not award the tender to the Applicant.
49.
The second factor relates to the bid validity period. If the BAC was
not authorised
to award this tender, it could not instruct Niemand to
do so, nor could Niemand on her own accord or through an error award
a valid
tender to or conclude a valid contract with the Applicant. In
effect, no award was made or contract concluded during the bid
validity
period of this tender. A bid validity period ensures bidders
remain committed to their offers in public procurement for a set
time,
preventing changes or withdrawals. It provides enough time for
evaluation, ensuring government entities can assess bids fairly
without alterations. This maintains fairness and transparency among
all bidders. It helps in the smooth finalisation of contracts.
50.
On the
authority of
Takubiza
Trading
,
the tender process had been completed once a tender's validity period
expired, even if the tender was not awarded.
[10]
The evidence before the Court is that the bid validity period had
expired without a valid award being made or a contract concluded.
The
legal consequences are that the tender lapsed. The tender award
cannot be retroactively validated as the process is not open-ended
and has to conclude with certainty. The procuring entity must
readvertise the tender and initiate a new bidding process.
Municipalities
must adhere to the MFMA, which requires financial
oversight and transparent procurement processes. Any attempt to
revive an expired
tender could be considered procedurally unfair.
[11]
The Municipal Manager lawfully declined to make the award.
Trencon
does not assist the Applicant in circumstances where an award has not
been made during the bid validity period. An unauthorised
person
making an award amount to no award being made during the bid validity
period.
[12]
51.
The third reason why the ostensible award of the tender militates
against its
validity is that the peremptory provisions of section 33
were not met. No contract could be concluded with the Applicant until
there was compliance with section 33. Section 33 of the MFMA concerns
tenders having future budgetary implications. It imposes obligations
on the Municipal Manager and the Municipal Council. The Municipal
Manager had to provide certain information to the Municipal Council
sixty days before the Council approved the contract. The
Municipal Manager failed to explain this omission, but it is
immaterial
to determining the issues in these applications. Section
21A of the MSA required the Municipal Manager to publicise the draft
contract,
accompanied by an information statement outlining the
Municipality’s obligations under the contract. He had to
consider the
representations and comments of the local community and
other interested persons. The Municipal Manager had to solicit the
views
of the National and relevant provincial treasury, the national
department responsible for local government, and, where applicable,
the national department responsible for overseeing the effects of the
tender, like Environmental Affairs. There is no indication
that the
Municipal Manager performed any of these obligations. His responses
indicate that he did not.
52.
Section 33 requires the Municipal Council, among other things, to
consider the
projected financial obligations for each financial year
covered by the contract, the impact on municipal tariffs and revenue,
and
the resolution to authorise the Municipal Manager to sign the
contract on behalf of the Municipality. None of these obligations
were met when the ostensible award was made and the contract
concluded by Niemand. Awarding a multi-million contract over a
protracted
period requires meticulous attention to detail.
53.
On the
authority of
Merifon
,
where the peremptory provisions of section 19 of the MFMA relating to
capital projects were considered, the Supreme Court of Appeal
determined that an agreement that did not comply with its prescripts
was legally unenforceable. There is no reason why a failure
to comply
with the peremptory provisions of section 33 of the MFMA should not
follow the same fate. The Municipal Manager and the
Municipal Council
did not comply with their obligations under the provisions of section
33 of the MFMA. Given the tenor of the
provisions of sections 217 and
172 of the Constitution, issuing a retroactive order for the
Municipal Manager and the Municipal
Council to comply with section 33
of the MFMA is not feasible. Nor can the Court order specific
performance of the ostensible contract,
as it would offend the
principle of legality.
[13]
54.
The
Applicant’s reliance on
Allpay
concerning the materiality of a deviation under section 217 of the
Constitution is misplaced. The Constitutional Court specified
that
the correct approach is to factually establish whether an
irregularity has occurred. This irregularity must then be legally
assessed to determine if it constitutes grounds for review under
PAJA. Where appropriate, this legal assessment should consider
the
materiality of any deviation from legal requirements by connecting
the issue of compliance to the purpose of the provision
before
concluding that a review ground under PAJA has been established.
The applicant asserted that the process
was done
according to the book. The BEC and BAC made their recommendations,
and the other bidders lodged no appeals. The process
was competitive,
transparent, and cost-efficient. Prins did not say that he would not
have awarded the tender. The Applicant contended
that the
irregularity was not material.
[14]
The latter contention cannot be sustained. Niemand was not authorised
to award the tender or conclude the contract. The bid validity
period
had expired before Prins considered the BAC’s recommendation,
and even if he were disposed to award the tender, non-compliance
with
the provisions of regulation 33 of the MFMA would have been fatal to
concluding the contract in circumstances where the bid
validity
period had expired. The materiality of the deviation was significant
for the reasons already canvassed.
55.
Allpay
reminded us that the strict mechanical approach to
‘peremptory’ and ‘directive’ provisions had
been discarded,
and the issue was whether the Applicant complied with
the statutory provisions viewed in the light of their purpose. The
Applicant
argued that it did what it had to do. The problem
in
casu
was that the Respondents did not do what they were supposed
to. There is no quarrel with that argument except to say that the
Respondents
have raised their non-compliance with the mandatory
provisions as a defence to the Applicant’s case and are before
the Court
to seek relief in that regard.
56.
To
the extent that the Applicant invoked estoppel,
Merifon
repeated the general rule that estoppel cannot be invoked in
circumstances where upholding it would be tantamount to a court
giving
its
imprimatur
to not one but a few illegalities that permeated the process after
the BAC made its recommendation.
[15]
The Constitutional Court, in upholding the Supreme Court of
Appeal’s decision in
Merifon,
stated
the trite
principle
that void acts cannot be resuscitated through the
Turquand
rule. The rule is a species of estoppel and therefore cannot be
raised to cure an
ultra
vires
action, as opposed to
intra
vires,
within
one’s legal powers, but suffers from some other defect. The
doctrine of legality is applicable and decisively trumps
the
Applicant’s reliance on the rule because it lacks knowledge of
the internal processes of the Municipality.
[16]
57.
The
Applicant contended in a rambling argument that regulation 5(2)(a)
which is repeated verbatim in the clause 5(2)(a) in the
Municipality’s supply chain management policy which requires
the Municipal Manager to award the tender as it was above R10
million, cannot defeat the prescripts of section 217(1) of the
Constitution. The argument is directed at why
Merifon
and
RPM
Bricks
are not applicable to the Applicant’s reliance on estoppel.
[17]
The Applicant concludes this argument by asserting that the Municipal
Manager’s ‘experience of personal attacks’
may lead
to a refusal to confirm the award of the tender in a rerun process.
It is unclear whether the Applicant referred to personal
attacks on
its part against the Municipal Manager or any emanating from him.
Apart from no evidence being placed before the Court
of any personal
attacks made by the Municipal Manager, it is unclear how the Court
can go beyond the dicta in the cited cases.
The
relief sought by the Applicant
58.
The Applicant sought multiple forms of relief in its amended notice
of motion.
The first order it sought was a declaration that the
tender was duly awarded to it, and the subsequent contract concluded
between
it and the Municipality was valid and binding on the
Municipality. The Applicant prayed that the Municipality be directed
to give
effect thereto. This prayer must fail as Niemand was not
authorised to award the tender or conclude the contract. The tender's
award and the contract's conclusion were unlawful,
ultra vires
,
invalid, and void. In making this finding, the Court accepts that the
sequence of events involving Manel and Niemand from when
Manel
informed Niemand of the BAC’s deliberations, the award of the
tender, the conclusion of the contract, and Niemand’s
withdrawal of the award letter, as outlined by the Respondents, is
credible. The award of the tender, which was one of six that
were
determined on 23 August 2024, thereby confused Niemand as to which
tenders the BAC had the authority to award and which it
did not. It
is a reasonable explanation. The Court also accepts that the
Municipal Manager did not have sight of the tender after
the BAC
awarded it until a hard copy was presented to him on 19 September
2024, when the bid validity period had expired. No other
version was
placed before the Court, and the Applicant was unable to counteract
any of this evidence with facts.
59.
The second prayer is premised upon a valid award and contract
emanating from
Niemand’s actions. As the Court has found that
no lawful award had been made, and the award and contract was
invalid,
ultra vires
and void, the second prayer, as an
alternative to the first, where the Applicant requested that the
Respondents be directed to
take all steps anticipated under section
33 of the MFMA contract, has to fail.
60.
The following order sought was premised upon the Applicant failing to
persuade
the Court that Niemand’s award notifications and the
contract were valid. In the alternative, it asked the Court to review
and set aside the Municipal Manager’s failure to consider and
decide the BAC’s recommendation of 23 August 2024 before
the
expiry of the bid validity period. The Applicant relied upon section
6(2)(g) as amplified by section 6(3)(a) of PAJA for this
relief. The
Applicant thus asserted that the Municipal Manager had a duty to take
a decision in circumstances where the period
within which the
decision had to be taken is not prescribed by law, and he failed to
take the decision. The Applicant is thus before
the Court as far as
this order is sought, for a review of the Municipal Manager’s
failure to make the decision on the grounds
that there has been an
unreasonable delay in making the decision.
61.
The
Applicant acknowledged the Respondent’s case that the Municipal
Manager was the only person with the authority to make
the final
award of the tender.
[18]
Applicant again, relying on the Respondent’s version, asserts
that the Municipal Manager failed to consider or make any decision
concerning the final award of the tender and instead allowed for the
tender validity period to expire on 30 August 2024. The Applicant
contends that the Municipal Manager allowed the tender validity
period to expire. The factual basis sketched by the Applicant for
the
order sought does not accord with the Respondents’ evidence.
The Municipal Manager stated in the answering affidavit
that he
received a hard copy of the BEC and BAC recommendations from Manel on
19 September 2024 for his consideration and award.
When he began to
peruse the recommendations, he noticed the bid was valid until 30
August 2024. He asked for a legal opinion, which
indicated that there
was no valid tender, and the process had been concluded. He could not
award the tender and “refused
to award the tender to the
Applicant.”
[19]
The
evidence in the answering affidavit is that the Municipal Manager
made a decision: he refused to award the tender to the Applicant.
[20]
The Applicant’s reply to the Municipal Manager’s
answer was that it did not fall within the Applicant’s
personal
knowledge, was at odds with what the Applicant stated in the founding
affidavit, or was legally unsustainable. That would
have been the end
of the request for judicial review, but for the content of the
Municipal Manager’s letter of 10 October
2024. In his letter to
the Applicant dated 10 October 2024, the Municipal Manager stated
that he was no longer entitled to make
any award after considering
the BAC’s recommendation, as the bid validity period had
expired. The evidence in the letter
would suggest a contrary
view, i.e., that he did not make any decision about the tender.
62.
The Court shall proceed on the Applicant’s assumption that the
Municipal
Manager failed to make a decision. The Applicant summarised
the consequences of the Municipal Manager’s alleged inaction.
The costs of the tender process, which included the employment of
Consulting Engineers, were wasted. The BEC and BAC recommendations
served no purpose. The Applicant progressed from being the successful
bidder with the unsuccessful bidders being notified, to having
to
compete again in a fresh bidding process. The Municipal Manager did
not explain his failure to act and to allow the tender validity
period to expire. The Applicant cited section 62(1)(a) of the MFMA
that requires the Municipal Manager to ensure that the Municipality
has and maintains an efficient and transparent supply chain
management system. Regulation 5(2) provides that the Municipal
Manager
must implement the supply chain management policy fairly,
equitably and transparently. The Applicant provided extensive written
argument as to why the Municipal Manager should have acted before the
bid validity period had expired.
63.
The Municipal Manager’s functions include ensuring compliance
with procurement
laws, overseeing the tender process, and approving
tenders above certain thresholds. He must ensure that the tender
process adheres
to principles of fairness, transparency and
competitiveness as outlined in section 217 of the Constitution. The
Municipal Manager
contended that he was not privy to or involved in
the BEC and BAC process. He relies on and acts upon written
recommendations received
from the BAC. The Applicant does not seek a
review of the Municipal Manager’s failure to extend the bid
validity period.
It had made out a case that the Municipal Manager
had extended the previous bid validity periods. Still, it does not
rely on this
aspect for judicial review under the order it seeks.
Section 22(h)(ii) of the Municipality’s Supply Chain Management
policy
requires the SCM Department to extend the bid validity period
provided the original period had not expired, and all bidders are
allowed to participate. Section 22 (h)(v) states that if the
validity of all bids expired without it being awarded within
the bid
validity period, including any extensions allowable in terms of
applicable legislation, the bid must be cancelled and published
in
the same media in which the original bid invitation appeared.
Section 53(1) and (3) states that successful and unsuccessful
bidders shall be notified in writing by the Supply Chain Management
once a bid has been accepted and awarded. A supply
chain
management unit of a municipality operates under the supervision of
the Chief Financial Officer
64.
There is no evidence before the Court that the Municipal Manager was
obliged
to ensure that he obtained the BAC recommendations
immediately after the BAC’s deliberations. The Municipal
Manager's evidence
is that he obtained the recommendations from
Manel, who served as the secretary of the BAC. He received the
documents twenty days
after the bid validity period expired.
According to the Municipality's supply chain management policy, the
Municipal Manager is
not responsible for extending the bid validity
period. There is thus no breach of any legal duty. The Municipal
Manager acted within
the law when he declined to make the award.
Furthermore, there is no evidence to suggest that the Municipal
Manager did not act
when he obtained the recommendations. His actions
were neither procedurally unfair, unlawful, nor unreasonable. To the
contrary,
his actions were lawful.
65.
The
following order sought by the Applicant is premised upon the Court
finding that the Municipal Manager failed to make a decision.
The
Applicant relied upon section 8(1)(c)(ii) of PAJA for the Court to
replace and substitute the Municipal Manager’s decision
awarding the tender to the Applicant. The second part of paragraph 5
of the notice of motion seeks orders in the alternative under
section
8(1)(c)(i) of PAJA to remit the matter to the Municipal Manager to
consider and make a decision within a period to be determined
by the
Court. In the third alternative, the Applicant seeks an extension of
the bid validity period under section 172(1)(b) of
the
Constitution.
[21]
66.
The
Applicant relied on
Trencon
for substituted relief.
[22]
A
Court has a discretion under section 8(1)(c)(ii)(aa) of PAJA to
make a substitution order in exceptional circumstances.
If the Court
is satisfied there are exceptional circumstances, it must still
determine whether it would be just and equitable to
make the
order.
[23]
Exceptional
circumstances comprise a three-stage enquiry. The first is whether
the outcome would be a foregone conclusion, and
it would be a waste
of time to order the tribunal or functionary to reconsider the
matter. The latter applies where a delay
would prejudice the
Applicant in circumstances where time is valuable, and any time lost
would be significant. The second consideration
is whether the
tribunal or functionary has exhibited bias or incompetence to such a
degree that it would be unfair to require the
applicant to submit to
the same jurisdiction again.
[24]
The third is whether the Court is in as good a position as the
administrator to make the decision.
67.
The Court is not in as good a position as the Municipal Manager or
the Municipal
Council to decide on the tender award and the contract.
The final decisions are polycentric and policy-laden. The outcome
depends
upon the Municipality’s financial obligations, tariffs
and revenue, and feedback from the public participation program.
National
and provincial interests, like budgets and environmental
issues, are invoked in the final decision-making. The remedy sought
in
circumstances where the Municipal Manager has made a decision,
albeit unfavourable to the Applicant, is not competent. Even
if
the Court were to suppose that the Municipal Manager did not make a
decision, the outcome would not have been a foregone conclusion,
as
the Municipal Manager’s decision on whether to award the tender
would have been influenced by the obligations inherent
in section 33
of the MFMA. Section 33(c) of the MFMA stipulates that the Municipal
Council must adopt a resolution in which it
authorises the Municipal
Manager to sign the contract on behalf of the Municipality.
68.
The Municipal Manager refused to award the tender to the Applicant as
the bid
validity period had expired. The Applicant is the incumbent
service provider administering and operating the Municipality’s
landfill site. The Applicant argued that it would be prejudiced if
required to bid once again. Its tender price is no longer a
secret,
as it is revealed in the papers, and would be exploited by other
bidders. The Applicant revealed its tender price in one
of the
annexures to its founding affidavit, and any prejudice suffered is of
its own making. The Applicant has not proven
that the
Respondents are biased towards it or incompetent to such a degree
that it would be unfair to submit it to the same jurisdiction
again.
It does benefit from working with the Municipality. The Applicant has
not found any fault with the evaluation and adjudication
of its bid.
The Municipality has explained that it does not handle bids over R10
million often and has explained how the error
occurred. The Court
accepts that explanation.
69.
The remedy sought by the Applicant in the alternative, i.e., to remit
the matter
to the Municipal Manager to consider and make a decision
requires the Court to go beyond
Takubiza Trading
regarding the retrospective extension of the bid validity period,
Merifon
relating to non-compliance of a mandatory statutory
provision, and the unlawfulness of Niemand’s actions. The
relief sought
by the Applicant must suffer the same fate as its
request for judicial review under section 6(2)(g) of PAJA. There is
nothing to
substitute, replace, or remit in circumstances that would
transgress the law. There are no grounds for the Court to entertain
the
remedies sought or the alternative to the latter, i.e., to extend
the bid validity period under section 172(1)(b) of the Constitution.
70.
The further orders sought by the Applicant that in the event this
Court remit
the matter to the Municipal Manager, and he awards the
tender to the Applicant, the Respondents are directed to give effect
to
the provisions of section 33 of the MFMA and that the purported
withdrawal of the tender on 27 September 2024 is reviewed and set
aside, cannot be granted. The Court declines the invitation to direct
the Municipality to give effect to section 33 of the MFMA
as an order
of that nature, which risks offending the separation of powers
doctrine.
The
Counterapplication
71.
The
Respondents raised the counterapplication to review and set aside
Niemand’s ‘series of administrative errors’
and
actions because they were unauthorised, unlawful, and
ultra
vires
of the MFMA and Municipalities Supply Chain Management Policy and
thus breached section 217 of the Constitution. The Respondents
sought
a legality review.
[25]
The
Respondents submitted that seeking such relief as a reactive
challenge to the application is appropriate.
[26]
Niemand’s decisions were in breach of the SCM policy and thus
in breach of sections 1(c) and 217, as well as section 195
[27]
of the Constitution. A local government may only act within the
powers lawfully conferred on it.
[28]
The exercise of public power which is at variance with the principle
of legality is invalid.
[29]
An
organ of state may seek a review of its own decision through the
principle of legality.
[30]
The
provisions of the MFMA ensure proper fiscal management of
municipalities.
[31]
The
Respondents contend that they correctly raised a reactive challenge
to the Applicant’s attempt to enforce an otherwise
unlawful
contract.
[32]
Out of an
abundance of caution and given the large and irregular expenditure of
public funds, the Municipality seeks in its counterapplication,
declaratory, or review relief of Niemand’s conduct and the
contract concluded with the Applicant. The Municipality alleges
that
since 30 October 2024 and 29 November 2024, it has had to decide how
best to address the administrative error, given that
the state organs
generally cannot proceed with the review under PAJA.
72.
The
Applicant pointed out that the Respondents should have sought a
legality review.
[33]
Surprisingly, it opposed the counterapplication. The Applicant
contended that the Municipality, as the original decision maker,
cannot collaterally challenge its decision while simultaneously
seeking a legality review.
[34]
The Municipality should have applied for a legality review and not
waited for the Applicant to seek enforcement. The Applicant
contended
that the counterapplication was only initiated after the Applicant
sought specific performance, indicating that it is
a defensive
strategy rather than a
bona
fide
review application. The Municipality failed to act promptly despite
knowing of the alleged irregularities before litigation commenced.
The Municipality could not disown its own administrative actions to
escape contractual obligations.
73.
The
Municipality asserted that it was entitled to raise a reactive
challenge to the application. The law relating to reactive and
collateral challenges is settled.
[35]
The facts of each case determine whether a reactive challenge should
be available where justice requires it to be.
[36]
The Respondents raised their reactive challenge as a defence to the
application to validate a patently unlawful award and contract,
as a
precaution against an invalid award and contract remaining valid.
[37]
The Respondents complied by initiating the counterapplication as due
process.
[38]
The evidence does
not support the Applicant’s assertion that the Respondents
reacted as a defensive strategy. The Applicant
also suggested that
the Municipality did not institute the self-review within a
reasonable time. The Applicant’s reliance
on
Gijima
to support the delay that ensued before the Municipal Manager
considered the BAC’s recommendations is misconceived. The court
in
Gijima
had to deal with a lengthy delay when ‘the ability to evaluate
an allegation of illegality fully is impaired’.
[39]
That is not the case in this matter. On 28 October 2024, the
Respondents informed the Applicant that they were initiating a
‘judicial’
review.
74.
The Applicant accused the Municipality of selectively relying on the
applicable
legislation to justify an unlawful attempt to undo a valid
and binding tender award. Section 33 did not prohibit the award of a
contract, as it merely required additional oversight for financial
planning. Any failure to comply with section 33 was an internal
governance issue which did not automatically render the contract
void. The Municipality should have remedied any non-compliance
through proper internal procedures rather than attempting a
unilateral withdrawal of the tender. The Municipality alleged a
breach
of section 217 of the Constitution but failed to explain how
the procurement process was unfair, inequitable or non-transparent.
A
mere procedural lapse did not equate to a constitutional violation.
It should have been corrected internally without seeking
to nullify a
validly concluded contract. The rule of law did not permit the
Municipality to evade its obligations under the guise
of financial
concerns or administrative errors.
75.
Again, the
submissions made by the Applicant do not reflect the evidence. Both
the BEC and BAC recommended the Applicant as the
successful tenderer,
subject to the process under section 33 of the MFMA. The award of the
contract remained in abeyance until
the Municipal Manager and the
Municipal Council discharged their obligations under section 33 of
the MFMA. The Municipal Council
could have only resolved to pass the
contract on completion of the process, as the BEC specifically
reminded it to approve the
contract as it is to be executed.
[40]
Without compliance with section 33, there was and is no valid
contract.
76.
The
Applicant argued ‘substantial compliance’ with the
applicable legislation to avoid the cancellation of the ostensible
award and the contract. A tender process tainted by unlawfulness and
lack of authority is invalid and not compliant with section
217 of
the Constitution.
[41]
Niemand's ostensible award of the tender and the contract by Niemand
and van Eck were unauthorised, unlawful,
ultra
vires
,
void and invalid. The Court has no hesitation in making the
declaratory orders sought by the Respondents.
Miscellaneous
Matters
77.
The application and counterapplication were enrolled as urgent
applications
and proceeded under Rule 6(12) of the Uniform Rules of
Court. The Court rejected the submissions that the application and
the counterapplication
were urgent, but agreed to hear them
expeditiously. Neither party sought the record under Rule 53 but
criticised the other for
failing to do so. The Applicant sought
amendments to its notice of motion twice. The Respondents objected to
the amendments. The
Court has allowed the Applicant’s second
set of amendments as Respondents’ Counsel acknowledged he had
prepared to
argue the matter based on the second set of amendments.
This is not to say that the Court accepted the Applicant’s
explanation
for the late notice of intention to amend or was
oblivious that the Applicant had materially changed its case from
that initially
formulated. The Respondents were justified in
objecting to the amendments, and as the outcome is in their favour,
they will be
entitled to the costs of their objection.
78.
As for the costs, there is no reason why they should not follow the
result.
The order that follows will reflect this.
CONCLUSIONS
79.
The Applicant tendered to administer and operate the First
Respondent’s
regional waste disposal facility. The First
Respondent’s BEC and BAC recommended the Applicant as the
favoured bidder, subject
to the award being made by the Second
Respondent following the section 33 process prescribed by the MFMA.
The Municipal Manager
was the only authorised person who could have
made the award.
80.
The BEC and BAC recommendations were submitted to the Second
Respondent beyond
the bid validity period. However, in the interim
between the BAC’s recommendation and before the bid validity
period expired,
the First Respondent’s Supply Chain Management
Practitioner awarded the tender conditionally to the Applicant. The
practitioner
subsequently confirmed the award after notifying the
unsuccessful tenderers and securing the signature of the First
Respondent’s
Executive Director of Technical Services and BAC
member to conclude the contract on behalf of the First Respondent.
Neither the
practitioner nor the director was authorised to perform
any of these administrative actions. The practitioner withdrew
the
letter of notification of the award once she realised her error.
81.
The Second Respondent referred the tender for legal opinion once he
realised
that the tender’s bid validity period had expired. In
the correspondence that ensued after the Supply Chain Management
practitioner
withdrew her letter of notification of the award, the
Applicant insisted that the award and contract were validly made and
demanded
specific performance of the contract. The Respondents
explained that the award and contract were erroneously made as the
practitioner
and Director were not authorised to do as they did, and
that the tender process was completed unsuccessfully once the bid
validity
period had expired. The Applicant threatened litigation to
enforce the contract. The Respondents informed the Applicant that
they
intended to review the tender's award and the contract's
conclusion to set them aside.
82.
The Court has considered and declined the relief pursued by the
Applicant but
has granted that sought by the Respondents with costs.
ORDER
In
the premises, the order is as follows:
1. The
Application is dismissed.
2. The
Counterapplication:
2.1
It is declared that the First Respondent’s ostensible award of
the tender T2023/023 for
the operation and management of the regional
waste disposal facility to the Applicant as per the First
Respondent’s letters
dated 26 August 2024 and 17 September 2024
is void, invalid, and of no effect.
2.2
It is declared that the ostensible contract concluded on 31 August
2024 between the Applicant
and the First Respondent is void, invalid,
and of no effect.
3. The
Applicant shall pay the Respondents' taxed or agreed party and party
costs and Counsel’s taxed
or agreed fees on scale C for the
application and counterapplication.
4. The
parties shall bear their own costs for the hearing scheduled for 18
February 2025.
Bhoopchand AJ
Acting Judge
High Court
Western Cape Division
Judgment
was handed down and delivered to the parties by e-mail on 5 May 2025
Applicant’s
Counsel: S
Aucamp
Instructed
by: Jacques Classen Inc.
Respondent’s
Counsel: L W Ackermann/ DM Lubbe
Instructed
by Rufus Dercksen Inc.
[1]
This is how the letters written
by Niemand were signed off, i.e., “For Municipal
Manager”
[2]
Part B: General Conditions and
Information of the tender document
[3]
Tactical
Security Services CC v eThekwini Municipality
2017 JDR 1558 (KZD),
Defensor
Electronic Security (Pty) Ltd v Centlec SOC Ltd and Another
(3372/2021)
[2021] ZAFSHC 315
(3 December 2021)
[4]
Prins is incorrect, as the
tender validity period was extended thrice. He seemed to
distinguish
the Municipal Manager from the Accounting Officer in his letter.
[5]
City
of Ekurhuleni Metropolitan Municipality v Takubiza Trading &
Projects CC and Others
(846/2021)
[2022] ZASCA 82
;
2023 (1) SA 44
(SCA) (3 June 2022)
(‘
Takubiza
Trading’
)
[6]
Telkom
SA v Merid Training (Pty) Ltd and others
;
Bihati
Solutions (Pty) Ltd v Telkom SA and others
(
Telkom
SA
)
[2011] ZAGPPHC 1
[7]
Takubiza
Trading
supra
at para 9
[8]
General Notice 868, GG 27636,
30 May 2005
[9]
Drift
Supersand (Pty) Limited v Mogale City Local Municipality and Another
(1185/2016)
[2017] ZASCA 118
;
[2017] 4 All SA 624
(SCA) (22
September 2017) at paras 31, 36-38
[10]
Takubiza
Trading
supra
[11]
Telkom
SA Limited v Merid Training (Pty) Ltd and Others
;
Bihati
Solutions (Pty) Ltd v Telkom SA Limited and others
[2011] ZAGPPHC 1,
Joubert
Galpin Searle Inc and Others v Road Accident Fund and Others
[2014]
ZAECPEHC 19;
[2014] 2 All SA 604
(ECP);
2014 (4) SA 148
(ECP),
SAAB
Grintek Defence (Pty) Ltd v South African Police Services and Others
[2015]
ZAGPPHC 1; 2015 JDR 0080 (GP)
;
Tactical Security Services CC v Ethekwini
Municipality
2017
JDR 1558 (KZD);
Secureco
(Pty) Ltd v Ethekwini Municipality and Others
[2016] ZAKZDHC 14 and
Ethekwini
Municipality v Mantengu Investments CC and Others
[2020]
ZAKZDHC 11,
Defensor
Electronic Security (Pty) Ltd v Centlec SOC Ltd and another
[2021]
ZAFSHC 315
para
8
[12]
Trencon
Construction (Pty) Limited v Industrial Development Corporation of
South Africa Limited and Another
(CCT198/14)
[2015] ZACC 22
;
2015 (5) SA 245
(CC);
2015 (10) BCLR
1199
(CC) (26 June 2015) (‘Trencon’) at paras 79-81
[13]
Merifon
at para 29
[14]
Allpay
at para 28
[15]
Merifon
at para 26,
Qaukeni
Local Municipality and Another v FV General Trading CC
,
[2009]
ZASCA 66
;
2010(1) SA 356 (SCA)
[16]
Merifon (Pty) Limited v Greater
Letaba Municipality and Another (CCT 159/21)
[2022] ZACC 25
;
2022
(9) BCLR 1090
(CC) (4 July 2022) (‘
Merifon
CC
’)
[17]
City
of Tshwane Metropolitan Municipality v RPM Bricks Proprietary Ltd.
(177/2006)
[2007] ZASCA 28
; [2007] SCA 28 (RSA);
2008 (3) SA 1
(SCA) (27 March
2007)
[18]
The Applicant resorted to linguistics to
escape acknowledging that the SCM regulations and policy
mandate the
Municipal Manager with the exclusive task of making the final award
in the tender involved in this case. The Applicant
stated that it
was common cause that this is what the Respondent contended.
[19]
Paras 41-44 of the Respondents’
answering affidavit
[20]
Para 44, answering affidavit
[21]
‘However, under section 172(1)(b) of
the Constitution, a court deciding a constitutional
matter has a
wide remedial power. It is empowered to make “any order
that is just and equitable”. So
wide is that power that
it is bounded only by considerations of justice and equity.’
Gijima
at para 53
[22]
Trencon
Construction (Pty) Limited v Industrial Development Corporation of
South Africa Limited and Another
(CCT198/14)
[2015] ZACC 22
;
2015 (5) SA 245
(CC);
2015 (10) BCLR 1199
(CC) (26
June 2015)
[23]
Trencon
supra at paras 34 and 35
[24]
Trencon
at para 38,
Livestock
and Meat Industries Control Board v Garda
1961
(1) SA 342
(A),
Johannesburg
City Council v Administrator, Transvaal, and Another
1969
(2) SA 72
(T)
[25]
State
Information Technology Agency SOC Limited v Gijima Holdings (Pty)
Limited (
CCT254/16)
[2017] ZACC 40
;
2018 (2) BCLR 240
(CC);
2018 (2) SA 23
(CC) (14
November 2017) (‘
Gijima
’)
at para 41
[26]
A reactive challenge is typically invoked
by a party seeking to defend itself against the enforcement
of an
administrative decision or action.
[27]
Steenkamp
v Provincial Tender Board, Eastern Cape
2007 (3) SA 121 (CC)
[28]
Fedsure
Life Assurance Ltd v Greater Johannesburg Transitional Metropolitan
Council
[1998]
ZACC 17
;
1999
(1) SA 374
(CC);
1998
(12) BCLR 1458
(CC) (
Fedsure
)
at para 58
[29]
Pharmaceutical
Manufacturers Association of SA: In re Ex Parte President of the RSA
[2000] ZACC 1
;
2000
(2) SA 674 (CC) at para 17
[30]
Gijima
at para 41
[31]
Merifon at paras 15-22
[32]
Merifon
at para 43-46,
Gobela
Consulting CC v Makhado Municipality
(910/19)
[2020] ZASCA 180
(22 December 2020) at paras 17-22,
Kunene
Rampala Inc v North West Province Department of Education and Sport
and Development
(460/2022)
[2023] ZASCA 120
(15 September 2023) at paras 21-27
[33]
The Applicant’s attorney suggested
this in a letter to the Municipal Manager on 22 October
2024
[34]
Collateral challenges allow a party to
argue the invalidity of an administrative action without
formally
applying for its review
[35]
Merafong
City Local Municipality v AngloGold Ashanti Limited
(CCT106/15)
[2016] ZACC 35
;
2017 (2) BCLR 182
(CC);
2017 (2) SA 211
(CC) (24
October 2016),
Gobela
Consulting CC v Makhado Municipality
(910/19)
[2020] ZASCA 180
(22 December 2020), ,
Department
of Transport and Others v Tasima (Pty) Limited
[2016]
ZACC 39
;
2017
(1) BCLR 1
(CC);
2017
(2) SA 622
(CC)
para 140
[36]
Merafong
at paras 43-45
[37]
Oudekraal
Estates (Pty) Ltd v City of Cape Town and Others
2004 (6) SA 222 (SCA)
[38]
Gijima
at
para 50,
MEC
for Health, Eastern Cape v Kirland Investments (Pty) Ltd t/a Eye and
Lazer Institute
[2014]
ZACC 6
;
2014
(3) SA 481
(CC);
2014
(5) BCLR 547
(CC) (
Kirland
)
[39]
Gijima
at para 43
[40]
See the deliberations of the BEC at 009-93
[41]
Gobela
supra,
Quaken
i
supra
sino noindex
make_database footer start
Similar Cases
Noordhoek Enviroment Action Group v City of Cape Town and Others (4819/21) [2024] ZAWCHC 105 (23 April 2024)
[2024] ZAWCHC 105High Court of South Africa (Western Cape Division)97% similar
Raubex Building (Pty) Ltd v Bitou Municipality and Another (13787/2024) [2025] ZAWCHC 405 (28 August 2025)
[2025] ZAWCHC 405High Court of South Africa (Western Cape Division)97% similar
Raubex Building (Pty) Ltd v Bitou Municipality and Another (13787/2024) [2024] ZAWCHC 378; [2025] 1 All SA 472 (WCC) (19 November 2024)
[2024] ZAWCHC 378High Court of South Africa (Western Cape Division)97% similar
Rauch and Another v Registrar of Deeds, Cape Town and Others (13312/2021) [2022] ZAWCHC 61 (28 April 2022)
[2022] ZAWCHC 61High Court of South Africa (Western Cape Division)97% similar
South African Renewable Green Energy (Pty) Ltd and Others v Coria (PKF) Investments 28 (RF) (Pty) Ltd and Others (6020/2023; 16391/2023) [2025] ZAWCHC 458 (9 October 2025)
[2025] ZAWCHC 458High Court of South Africa (Western Cape Division)97% similar