Case Law[2024] ZAWCHC 105South Africa
Noordhoek Enviroment Action Group v City of Cape Town and Others (4819/21) [2024] ZAWCHC 105 (23 April 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 105
|
Noteup
|
LawCite
sino index
## Noordhoek Enviroment Action Group v City of Cape Town and Others (4819/21) [2024] ZAWCHC 105 (23 April 2024)
Noordhoek Enviroment Action Group v City of Cape Town and Others (4819/21) [2024] ZAWCHC 105 (23 April 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_105.html
sino date 23 April 2024
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
number: 4819/21
In
the matter between:
NOORDHOEK
ENVIRONMENTAL ACTION GROUP
Applicant
and
THE
CITY OF CAPE TOWN
First
Respondent
MEC
FOR LOCAL GOVERNMENT, ENVIRONMENTAL AFFAIRS AND DEVELOPMENT
PLANNING: WESTERN CAPE
Second
Respondent
CHAND
ENVIRONMENTAL CONSULTANCY CC
Third
Respondent
INGRID
EGGERT
Fourth
Respondent
SADIA
CHAND
Fifth
Respondent
ZAAHIR
TOEFY
Sixth
Respondent
Heard:
8 NOVEMBER
2023
Delivered:
23 APRIL 2024 (Electronically)
JUDGMENT
Pillay
AJ:
# INTRODUCTION
INTRODUCTION
1.
The
challenge in this matter relates to certain decisions that were taken
in respect of the building of a road known as, Houmoed
Avenue
Extension 1, which is a 1.2 kilometre section road in the vicinity of
Sunningdale/ Noordhoek (also referred to as “
the
proposed road
”). The
proposed road is adjacent to a wetland in Noordhoek known as the Pick
‘n Pay reedbed or wetland.
The applicant, Noordhoek
Environmental Action Group, which is a non profit organisation with
an environmental focus argues that
the proposed road will disturb the
wetland as well as three breeding ponds used by the endangered
Western Leopard Toads (“
WLT
”)
and will potentially cause their extinction.
2.
As
a result, the applicant seeks to review and set aside decisions taken
by the sixth respondent (“
the
Director
”) and the second
respondent (“
the MEC
”)
to grant environmental authorisation to the first respondent (“
the
City
”) in terms of the
National Environmental Management Act No 107 of 1998 (“
NEMA
”)
and the Environmental Impact Assessment Regulations, 2014 (“
the
EIA Regulations
”) for the
construction of the proposed road.
3.
Environmental
authorisation was required for the proposed road because its
construction and the establishment of the road reserve
gives rise to
listed activities in respect of: (a) the infilling of more than 10 m³
of material into a wetland; (b) the removal
of an area of indigenous
vegetation exceeding 300 m².
4.
In
its original notice of motion dated 17 March 2021, the applicant
sought relief in terms of ten specific prayers. In its amended
notice
of motion (filed pursuant to Rule 53 (4)) certain further relief was
sought, which the applicant subsequently indicated
that it was
withdrawing.
5.
The
following substantive relief is accordingly sought in this
application:
5.1.
An
Order reviewing and setting aside the decision of the Director taken
on 22 November 2019 granting the City’s application
for
environmental authorisation for the proposed road.
5.2.
An
Order reviewing and setting aside the decision of the MEC taken on 18
September 2020, sitting as the appeal authority, refusing
the appeal
of the applicant against the environmental authorisation for the
proposed road.
5.3.
An
Order declaring that the failure to commission specialist anuran or
amphibian study into the impact of the proposed road on the
WLT in
particular constitutes a fatal flaw in the Basic Assessment Report
(also referred to as the “
BAR
”)
submitted by Chand Environmental Consultants (also referred to as the
“
Chand
”)
in the City’s application for an environmental authorisation to
construct the proposed road.
5.4.
An
Order declaring the submission of the aforesaid BAR by Chand, and not
by a single natural person is in contravention of the intention
of
the NEMA, and in particular of the definition of an Environmental
Assessment Practitioner (“
EAP
”)
in section 1 and, as such, constitutes a fatal flaw.
5.5.
An
Order declaring that the BAR was not conducted with the required
objectivity by the appointed EAP.
5.6.
An
Order declaring that the lack of objectivity of those involved in the
preparation of the BAR amounted to a fatal flaw in the
process.
5.7.
An
Order declaring that in terms of a proper reading of the NEMA EIA
Regulations, 2014, the traffic impacts associated with the
proposed
road required that a Traffic Impact Assessment be duly completed and
submitted.
5.8.
An
Order declaring that the traffic study by the HH0 dated June 2016 is
not a Traffic Impact Assessment as required by the NEMA
EIA
Regulations, 2014.
6.
The
applicant subsequently sought leave to amend its fourth prayer (as
set out in paragraph 5.4) by deleting the words “
a
single natural person
” and
replacing it with “
an
individual
”. I grant the
amendment as sought.
# THE
BACKGROUND
THE
BACKGROUND
## The
previous application process
The
previous application process
7.
The
subject application process was preceded by an earlier basic
assessment process which had been conducted during 2017 and 2018
but
had been subsequently withdrawn (“
the
previous BAR process
”).
The previous BAR process was initiated in December 2016 and occurred
pursuant to an earlier application for environmental
authorisation
(“
the previous application for
environmental authorisation
”).
8.
The
previous BAR process culminated in the submission of a final BAR to
the Department on 20 November 2018.
9.
The
previous application for environmental authorisation did not reach
conclusion because, ultimately, the City decided to withdraw
it.
## The
current application process
The
current application process
10.
On
14 May 2019
the City submitted an application for environmental authorisation to
the Directorate: Development Management in the Department
of
Environmental Affairs and Development Planning (“
the
Department
”).
11.
An
EAP, Chand, was appointed to undertake the basic assessment.
12.
A
draft BAR was submitted to the Department on 22 May 2019 (“
the
2019 DBAR
”). It was the
subject of a 30 day public participation process.
13.
A
final BAR was submitted to the Department on 14 August 2019.
14.
Much
of the information that was obtained during the previous BAR process
formed part of the current application process.
# THE
LEGAL FRAMEWORK
THE
LEGAL FRAMEWORK
15.
In
this section, I shall identify the relevant statutory and regulatory
provisions which bear on the determination of this matter.
## NEMA
NEMA
16.
Section
24(1) of NEMA provides (in relevant part) as follows:
“
(1)
In
order to give effect to the general objectives of integrated
environmental management laid down in this Chapter, the potential
consequences for or impacts on the environment of listed activities
or specified activities must be considered, investigated, assessed
and reported on to the competent authority or the Minister
responsible for mineral resources, as the case may be, except in
respect
of those activities that may commence without having to
obtain an environmental authorisation in terms of this Act.
(1A) Every
applicant must comply with the requirements prescribed in terms of
this Act in relation to-
(a) steps
to be taken before submitting an application, where applicable;
(b)
any
prescribed report
;
(c) any
procedure relating to public consultation and information gathering;
(d)
any
environmental management programme;
(e) the
submission of an application for an environmental authorisation and
any other relevant information;
and
(f)
the
undertaking of any specialist report, where applicable
.
…
.
(4) Procedures
for the investigation, assessment and communication of the potential
consequences or impacts
of activities on the environment-
(a) must
ensure, with respect to every application for an environmental
authorisation-
(i) coordination
and cooperation between organs of state in the consideration of
assessments where an activity
falls under the jurisdiction of more
than one organ of state;
(ii) that
the findings and recommendations flowing from an investigation, the
general objectives of integrated
environmental management laid down
in this Act and the principles of environmental management set out in
section 2 are taken into
account in any decision made by an organ of
state in relation to any proposed policy, programme, process, plan or
project;
(iii)
that
a description of the environment likely to be significantly affected
by the proposed activity is contained in such application
;
(iv)
investigation
of the potential consequences for or impacts on the environment of
the activity and assessment of the significance
of those potential
consequences or impacts
; and
(v) public
information and participation procedures which provide all interested
and affected parties, including
all organs of state in all spheres of
government that may have jurisdiction over any aspect of the
activity, with a reasonable
opportunity to participate in those
information and participation procedures; and
(b)
must
include, with respect to every application for an environmental
authorisation and where applicable
-
(i) investigation
of the potential consequences or impacts of the alternatives to the
activity on the environment
and assessment of the significance of
those potential consequences or impacts, including the option of not
implementing the activity;
(ii) investigation
of mitigation measures to keep adverse consequences or impacts to a
minimum;
(iii) investigation,
assessment and evaluation of the impact of any proposed listed or
specified activity
on any national estate referred to in section 3
(2) of the National Heritage Resources Act, 1999 (Act 25 of 1999),
excluding the
national estate contemplated in section 3 (2) (i) (vi)
and (vii) of that Act;
(iv) reporting
on gaps in knowledge, the adequacy of predictive methods and
underlying assumptions, and uncertainties
encountered in compiling
the required information;
(v) investigation
and formulation of arrangements for the monitoring and management of
consequences for or
impacts on the environment, and the assessment of
the effectiveness of such arrangements after their implementation;
(vi) consideration
of environmental attributes identified in the compilation of
information and maps contemplated
in subsection (3); and
(vii) provision
for the adherence to requirements that are prescribed in a specific
environmental management
Act relevant to the listed or specified
activity in question.”
(Emphasis
added)
17.
Section
24I of NEMA reads as follows:
“
24I
Appointment
of external specialist to review assessment
The
Minister or MEC may appoint an external specialist reviewer, and may
recover costs from the applicant, in instances where-
(a) the
technical knowledge required to review any aspect of an assessment is
not readily available within
the competent authority;
(b) a
high level of objectivity is required which is not apparent in the
documents submitted, in order to
ascertain whether the information
contained in such documents is adequate for decision-making or
whether it requires amendment.”
18.
Section
24O of NEMA reads as follows:
“
24O
Criteria
to be taken into account by competent authorities when considering
applications and consultation requirements
(1) If
the Minister, the Minister responsible for mineral resources or an
MEC considers an application for
an environmental authorisation, the
Minister, Minister responsible for mineral resources or MEC must-
(a)
comply
with this Act;
(b)
take
into account all relevant factors, which may include-
(i) any
pollution, environmental impacts or environmental degradation likely
to be caused if the application
is approved or refused;
(ii)
measures
that may be taken-
(aa) to
protect the environment from harm as a result of the activity which
is the subject of the application;
and
(bb) to
prevent, control, abate or mitigate any pollution, substantially
detrimental environmental impacts
or environmental degradation;
(iii) the
ability of the applicant to implement mitigation measures and to
comply with any conditions subject
to which the application may be
granted;
(iiiA) the
ability of the applicant to comply with the prescribed financial
provision;
(iv) where
appropriate, any feasible and reasonable alternatives to the activity
which is the subject of
the application and any feasible and
reasonable modifications or changes to the activity that may minimise
harm to the environment;
(v) any
information and maps compiled in terms of section 24 (3), including
any prescribed environmental
management frameworks, to the extent
that such information, maps and frameworks are relevant to the
application;
(vi) information
contained in the application form, reports, comments, representations
and other documents
submitted in terms of this Act to the Minister,
Minister responsible for mineral resources, MEC or competent
authority in connection
with the application;
(vii) any
comments received from organs of state that have jurisdiction over
any aspect of the activity which
is the subject of the application;
and
(viii) any
guidelines, departmental policies, and environmental management
instruments that have been adopted
in the prescribed manner by the
Minister or MEC, with the concurrence of the Minister, and any other
information in the possession
of the competent authority that are
relevant to the application; and
(c) take
into account the comments of any organ of state charged with the
administration of any law which
relates to the activity in question.”
## EIA
Regulations
EIA
Regulations
19.
The
Environmental Impact Assessment Regulations, 2014
GN R982 of 2014
published in GG 38282 of 4 December 2014 (“
the
EIA Regulations
”) requires
that applicants for environmental authorisation must follow one of
two procedures, a basic assessment or a full
scoping and
environmental impact assessment.
20.
Regulation
12 of the EIA Regulations provides:
“
12
Appointment
of EAPs and specialists
(1) A
proponent or applicant must appoint an EAP at own cost to manage the
application: Provided that an
EAP need not be appointed for an
application to amend an environmental authorisation where no
environmental impact assessment or
part thereof is required as part
of such amendment application.
(2) In
addition to the appointment of an EAP,
a specialist may be
appointed, at the cost of the proponent or applicant, if the level of
assessment is of a nature requiring the
appointment of a specialist
.
(3) The
proponent or applicant must-
(a) take
all reasonable steps to verify whether the EAP and specialist
complies with regulation 13(1)(a)
and (b); and
(b) provide
the EAP and specialist with access to all information at the disposal
of the proponent or applicant
regarding the application, whether or
not such information is favourable to the application.”
(Emphasis
added)
21.
Regulation
13 of the EIA Regulations sets out the general requirements for EAPs
and specialists and requires that they must:
21.1.
be
independent;
21.2.
have
expertise in conducting environmental impact assessments or
undertaking specialist work as required, including knowledge of
the
Act, the Regulations and any guidelines that have relevance to the
proposed activity;
21.3.
ensure
compliance with the Regulations;
21.4.
perform
the work relating to the application in an objective manner, even if
this results in views and findings that are not favourable
to the
application;
21.5.
take
into account, to the extent possible, the matters referred to in
regulation 18 when preparing the application and any report,
plan or
document relating to the application; and
21.6.
disclose
to the proponent or applicant, registered interested and affected
parties and the competent authority all material information
in the
possession of the EAP and, where applicable, the specialist, that
reasonably has or may have the potential of influencing: (i)
any decision to be taken with respect to the application by the
competent authority in terms of the EIA Regulations; or (ii)
the objectivity of any report, plan or document to be prepared by the
EAP or specialist, in terms of the EIA Regulations for submission
to
the competent authority, unless access to that information is
protected by law, in which case it must be indicated that such
protected information exists and is only provided to the competent
authority.
22.
In
terms of Regulation 13 (2), in the event where the EAP or specialist
does not comply with subregulation (1)(a), the proponent
or applicant
must, prior to conducting public participation as contemplated in
Chapter 6 of the Regulations, appoint another EAP
or specialist to
externally review all work undertaken by the EAP or specialist, at
the applicant's cost.
23.
A
specialist is defined as “
a
person that is generally recognised within the scientific community
as having the capability of undertaking, in conformance with
generally recognised scientific principles, specialist studies or
preparing specialist reports, including due diligence studies
and
socio-economic studies
”.
[1]
24.
In
terms of Regulation 18 of the EIA Regulations, when considering an
application, the competent authority must have regard to section
24O
and 24(4) of the Act, the need for and desirability of the
undertaking of the proposed activity, the requirements of the
Regulations,
any protocol or minimum information requirements
relevant to the application as identified and gazetted by the
Minister in a government
notice or any relevant guideline published
in terms of section 24J of the Act.
25.
According
to Regulation 19(3) a BAR must contain the information set out in
Appendix 1 to the Regulations or comply with a protocol
or minimum
information requirements relevant to the application as identified
and gazetted by the Minister in a government notice.
26.
Regulation
40 deals with the purpose of the public participation process.
It provides:
“
(1)
The
public participation process to which the … basic assessment
report… was subjected to must give all potential
or
registered interested and affected parties, including the competent
authority, a period of at least 30 days to submit comments
on each of
the basic assessment reports, …
(2)
The
public participation process contemplated in this regulation must
provide access to all information that reasonably has or may
have the
potential to influence any decision with regard to an application
unless access to that information is protected by law
and must
include consultation with … all potential, or, where
relevant, registered interested and affected parties”.
# THE
GROUNDS OF REVIEW
THE
GROUNDS OF REVIEW
27.
The
grounds of review that were ultimately relied on and advanced at the
hearing of the matter may be summarised as follows
[2]
:
27.1.
First
,
that the failure to commission and complete an expert study on the
WLT means that irrelevant considerations were taken into account
and
relevant considerations were not taken into account. As a
result, the applicant argues that it is impossible for a
decision-maker
to make a rational decision involving polycentric
factors which must be weighed up against each other. According
to the applicant,
the failure to have appointed an amphibian or
anuran specialist to specifically assess the impact that the proposed
road would
have on the WLT falls foul of NEMA Regulation 12(2),
particularly that the WLT is an endangered species. It is also
argued
in this regard that NEMA requires a risk averse and cautious
approach.
27.2.
Second
,
that there was an irrationality in appointing an expert after the
fact. The basis for the alleged irrationality is that:
(a)
there are no current data on the WLT population which uses the Pick
‘n Pay reedbed in general or the three known breeding
ponds in
particular; (b) if an anuran expert is needed to monitor the state of
the WLT
after
construction of the proposed road, it ought to have been important
enough for such an expert to monitor and establish the state
of the
WLT
before
construction; and (c) it makes no sense to recommend mitigation which
is untested and untried and then to monitor the effectiveness
of the
mitigation.
27.3.
Third
,
that cumulative impacts were not considered and that this omission
will “
inevitably lead to gaps
in knowledge which will lead to relevant facts not being taken into
account and irrelevant facts being taken
into account
”.
27.4.
Fourth
,
that there was an inadequate public participation process in that:
(a) the EAP failed to identify and consult with local knowledge
and
conduct focus groups at the right stage of the process coupled with
repeated requests for information; (b) the second application
process
contained no new specialist studies; and (c) the members of the
applicant did not have the resources to participate in
the second
application process.
27.5.
Fifth
,
that the traffic study which was commissioned by the City for
legitimate traffic and road planning purposes is not a NEMA compliant
expert study and does not consider the environment or alternative
routes for the proposed road.
27.6.
Sixth
,
that the EAP was biased and motivated by a preconceived imperative
that the proposed road had to be built. This, according
to the
applicant is “
the only
plausible explanation for the egregious failures
”
that it has identified.
27.7.
Seventh
,
that the EAP was improperly appointed in that: (a) it was appointed
by HHO Consulting Engineers and not the City as is required
by
Regulation 12(1); and (b) an entity as opposed to an individual was
appointed.
27.8.
Eighth
,
that the MEC did an about-turn in respect of the relevance of the
previous EIA process to the current approval process.
# REVIEW
GROUND 1: THE FAILURE
TO COMMISSION AND COMPLETE AN EXPERT STUDY ON THE WLT
REVIEW
GROUND 1
: THE FAILURE
TO COMMISSION AND COMPLETE AN EXPERT STUDY ON THE WLT
## The
challenge
The
challenge
28.
The
applicant argues that the advice and active involvement of an anuran
expert is necessary for the following reasons:
28.1.
Respected
amphibian experts called for an amphibian report.
28.2.
An
environmentalist called for a specialist amphibian report.
28.3.
Members
of the public, local inhabitants and interested and affected parties
called for an amphibian report.
28.4.
The
EAP appreciated the need for an anuran specialist report.
## The
consideration that was given to the WLT in the approval process
The
consideration that was given to the WLT in the approval process
29.
It
is common cause that an anuran specialist was not appointed as part
of the process but that two specialists who considered the
impact on
the WLT were appointed.
30.
In
what follows, I shall set out the focus that was given to the WLT in
the process.
### The
Faunal Impact Study
The
Faunal Impact Study
31.
The
observations made in respect of the WLT in the Faunal Impact Study
include the following:
31.1.
Impacts
on the WLT potentially arise from three avenues: habitat loss;
habitat degradation; and roadkill.
31.2.
The
proposed road is likely to experience heavy traffic at times and as
roadkill is a major source of mortality of the WLT, it could
significantly increase mortality of toads moving in and out of the
wetlands. Specific mitigation in this regard is recommended
which
should be focused on minimising roadkill through preventing toads
from accessing and crossing the road on the one hand and
providing
alternative access routes under the road on the other.
31.3.
Habitat
degradation would result largely from increased pollution risk due to
run-off from the new road surface. The primary mitigation
that has
been recommended and included in the road design is to limit culverts
to more than 50 m from the open water bodies and
include swales to
clean the water before it reaches the vlei.
31.4.
The
construction of the proposed road would result in some loss of
habitat along the edge of the vlei. Habitat loss will result,
in some
measure, from the construction of the road along the edge of the
vlei. Roadkill of young toads leaving the breeding ponds
are of
particular concern and specific measures to limit or prevent toadlets
from climbing out onto the road should be implemented.
It was
noted that: (a) this may take the form of an overhanging curved
design that prevents toads from scaling the road barrier;
and (b)
this could take several forms, the final design of which should be
informed by input from a specialist.
31.5.
Preventing
toads from crossing the road is only one aspect of mitigation in this
regard as this would also prevent them from accessing
the adjacent
urban areas such as Milkwood Park where toads are apparently resident
outside of the breeding season. In order to
provide access to the
other side of the road, drive culverts under the road have been
recommended. These should be associated with
drift fences to direct
toads from the open water bodies towards the culverts. While it is
not clear whether or not the toads will
use such culverts, current
research indicates that such systems can be effective for some
species. While the success of such features
in other parts of the
world is variable, this has not been well established in South Africa
for the WLT. As such, follow-up monitoring
of the culverts is
recommended during and after the breeding season when firstly adults
and then later young toads are moving about.
Further details of the
recommended mitigation actions to reduce the impact of the WLT are
also dealt with.
32.
The
following findings and conclusions were reached:
32.1.
Impacts
associated with the loss of faunal habitat (including the WLT
breeding ponds) were rated as medium without mitigation and
low if
mitigation measures are implemented.
32.2.
WLT
mortalities (which were subsumed in a general rating for all faunal
mortalities) were rated as medium without mitigation and
low if
mitigation measures are implemented.
32.3.
Mitigation
measures were proposed for:
32.3.1.
Design
and construction phase impacts in relation to: (a) loss of
faunal habitat due to transformation of currently intact
habitat for
road construction; (b) direct faunal impacts due to road
construction.
32.3.2.
Operational
phase impacts in respect of direct faunal impacts due to road
operation.
32.3.3.
Cumulative
impacts in respect of cumulative habitat loss and fragmentation due
to the proposed road.
32.4.
Amongst
others, the following mitigation measures relating to the WLT were
recommended:
32.4.1.
The
fate of the open water bodies and whether they should be augmented or
moved, should be determined as part of the Wetland Rehabilitation
Plan, with input from a faunal and amphibian specialist. They
should be buffered from impact as much as possible.
32.4.2.
The
edge of the road and walkway should have a step that is designed
specifically to prevent toads from climbing the wall and accessing
the road, and the pavement should have an overhang of at least 50 mm
to prevent toads from getting onto the road.
32.4.3.
Any
side roads that connect with the Phase 1 section of Houmoed Avenue
from Milkwood Park should be constructed with gutters or
cattle grids
or some other feature to prevent toads from entering the road, which
feature must be designed in consultation with
an amphibian specialist
and must be aligned with the toad underpasses.
32.4.4.
Toad
underpasses must be constructed close to breeding ponds and should
take the form of dry culverts; the edge of the road must
be designed
to direct the toads towards the culverts; and drift fences must be
put in place to direct toads and other animals into
the culverts.
All these features must be designed in consultation with an amphibian
specialist.
32.4.5.
An
amphibian specialist must evaluate the effectiveness of these
measures.
32.5.
According
to the Conclusion and Recommendations:
“
The
Houmoed Avenue Extension would result in about 2 ha of habitat loss
along the margin of the Pick and Pay Wetland System. The
habitat loss
is not considered highly significant as the affected reedbeds are
homogenous and the loss would be a small proportion
of the extensive
‘Pick and Pay’ reedbeds. There are however three small
open water bodies along the edge of the wetland
that would
potentially be impacted to a greater or lesser degree by the road.
Due to the presence of these water bodies, Option
1 is considered
preferred to Option 2. The open water bodies are considered locally
significant as open water is not available
elsewhere in the affected
wetland and are also known to be used by the Western Leopard Toad
which is of specific concern. As the
water bodies would be adjacent
to the road, which would significantly reduce their utility for many
fauna. Specific mitigation
should be aimed to reduce the impact
of the road on the open water bodies as much as possible. This would
include planting indigenous
trees and other vegetation along the road
to screen the open water bodies from the road. In addition, the
habitat loss resulting
from the development should be partly offset
by rehabilitation of the in-filled areas of wetland that currently
exist along the
Houmoed Road Extension route. This is in accordance
with the freshwater study and is supported by the current study as
well. The
areas available for rehabilitation are estimated at 0.5 –
1 ha and would significantly reduce the overall impact of the
development.
The
major impacts associated with the construction phase of the
development would be habitat loss resulting from the road footprint
and disturbance resulting from construction activities. The loss of
habitat is considered of moderate significance and cannot be
effectively mitigated as the loss cannot be avoided if the road is
constructed in the current proposed alignment. Disturbance is
considered to be of moderate pre-mitigation significance which can be
reduced to a low level through mitigation. Potential impacts
on the
Western Leopard Toads are highlighted as a specific concern
associated with the development. Four avenues of mitigation
are
recommended to reduce the potential impacts on this species. This
includes the following areas of mitigation:
·
Run-off
management to ensure that dirty run-off water does not enter the open
water bodies. This is facilitated by placement of
drainage culverts
at least 50 m away from the open water bodies and use of swales to
filter the water before it enters the vlei.
·
Habitat
improvement and rehabilitation of in-filled sections of the wetland.
This is an outcome of the freshwater study and is supported
by the
current study as well. This could provide for increased habitat for
toads along the edge of the vlei in the area where the
rehabilitation
would take place.
·
Reducing
road mortality through design features which prevent toads from
climbing onto the road. The final design of the toad mitigation
features should be developed with specific input from an amphibian
specialist.
·
Enhancing
connectivity through the creation of toad underpasses with associated
drift fences. These should be monitored for at least
3 to 5 seasons
to evaluate their success and improve their design where necessary.
The
final design of the above features should be achieved with
collaboration and input from the freshwater specialist as well as
an
amphibian specialist to inform the design of the toad underpasses…..
During
the operational phase, the presence of the road will result in a
number of impacts related to disturbance of fauna along
the road.
These impacts include pollution due to run-off from the road surface,
increased light pollution due to street lighting,
increased levels of
noise and litter input to the wetland as well as increased exposure
and access of the wetland to people. These
impacts would persist for
the lifetime of the road and some of them would have cumulative
impacts up that are likely to result
in the long term degradation of
the wetland if not mitigated. Important mitigation measures include
limiting pedestrian access
to the wetland, reducing light pollution
from street lighting, measures to reduce litter inputs and any
measures to improve the
quality of the habitat along the road such as
clearing any woody aliens which become established and using
indigenous species to
re-vegetate the road verge.
The
construction of the road will increase cumulative impacts on the
larger Noordhoek Wetland System as well as connectivity in
the wider
Noordhoek- Sun Valley area. The contribution would however be low as
the road is positioned along the existing urban
fringe and as can
best be seen as urban creep along the margin of the current urban
boundary and not a novel impact into a currently
intact and
undisturbed ecosystem. Provided that the recommended mitigation
measures are implemented, the impacts of the road can
be reduced to
an acceptable level. The mitigation measures suggested in this report
are aimed at augmenting those outlined in the
specialist freshwater
study and as such those are supported by the current study as well.
Overall,
the majority of impacts associated with the development of the
Houmoed Avenue Road on fauna are likely to be low after
the effective
implementation of the recommended mitigation and there are no highly
significant impacts on fauna likely to be associated
with the
development and which represent a fatal flaw. As such, there
are no faunal ecological reasons to indicate that the
project should
not go ahead. However, due to the presence of the Western Leopard
Toad in the area, it is critical that the proposed
mitigation
measures are effectively implemented and the moderate to low post
mitigation impacts are contingent on the effective
implementation of
the required mitigation. Without the implementation of the suggested
measures, there is a high potential for
significant long term in
impact on the Western Leopard Toad and the Environmental
Authorisation should stipulate these measures
as essential for the
construction and operation of the road. To ensure that the suggested
mitigation measures are effectively implemented,
the design of the
toad mitigation measures should be developed in collaboration between
the project engineers and an amphibian
specialist.
With
the implementation of the required mitigation, the impacts of the
Houmoed Road Extension on fauna are considered acceptable.”
### The
Wetlands Report
The
Wetlands Report
33.
The
Terms of Reference of the Wetlands Report were to:
33.1.
Identify
and delineate the freshwater ecosystems present along the route for
the proposed road extension.
33.2.
Identify
the potential impacts on freshwater ecosystems that could result from
the construction of the proposed road and assess
the significance of
these impacts.
33.3.
Recommend
mitigation measures to minimise the potential negative impact on
freshwater ecosystems.
33.4.
Provide
a summary of the findings in the form of a Freshwater Ecosystems
Impact Assessment Report.
34.
The
Wetland Study recognised that the Pick ‘n Pay reedbed was of
moderate-to-high conservation importance. However,
it rated the
specific impacts associated with the WLT as being of low
significance:
34.1.
The
impact associated with disturbance to habitat was rated as low in a
scenario without mitigation, and “very low”
if mitigation
measures are implemented.
34.2.
The
impact described as “trampling of Western Leopard Toads and
other fauna by vehicles” was rated as being of medium-to-high
significance without mitigation, but of very low significance with
mitigation.
35.
The
Wetland Study required the implementation of the following mitigation
measures:
35.1.
During
construction:
35.1.1.
Wetlands
and other natural areas outside the road reserve should be treated as
“no go” areas.
35.1.2.
Any
work that needs to be undertaken in the wetlands or other natural
areas outside of the road reserve should be closely monitored
by the
environmental control officer and should be carried out according to
an approved method statement.
35.1.3.
The
wetland areas adjacent to the road reserve should be inspected at
least weekly by the environmental control officer for signs
of
disturbance, sedimentation or pollution and immediate remedial action
should be taken. If necessary, a freshwater ecologist
should be
consulted for advice on the most suitable remediation measures.
35.2.
During
the operational phase:
35.2.1.
It
was noted that it is not really possible to mitigate the increase in
noise -related disturbance to fauna that would inevitably
result from
the establishment of a new road along the southern edge of the Pick
‘n Pay reedbed wetland system. In
the case of the
temporary bypass road however, some mitigation of this impact could
be achieved by only operating the bypass road
during the day. The
disturbances related to night-time lighting could (and should) be
mitigated to some degree by ensuring that
no lighting is directed
into the wetland area to the north of the road especially where there
are open water areas. This would
presumably only apply to the
permanent road, as street lighting is unlikely to be installed for
the temporary bypass road.
35.2.2.
To
reduce the vehicle -related mortality of the WLT on the proposed
road, it is strongly recommended that permanent barriers (drift
fences) should be erected along the edges of the road that lead frogs
and other small ground-based fauna to underpasses below the
road.
These barriers and underpasses should be carefully designed and
built, with substantial input and guidance from an amphibian
specialist and a freshwater ecologist, together with input from
engineers.
35.2.3.
The
erection of signage along the road warning motorists to beware of
frogs crossing the road during and after rain was a further
proposed
mitigation measure.
35.3.
Other
proposed mitigation measures include:
35.3.1.
A
range of rehabilitation wetland measures were proposed. It was
noted that the significance of the positive impact would
also be
enhanced if the proposed wetland rehabilitation interventions were to
be seen by a wetland ecologist and guided by a detailed
wetland
rehabilitation plan prepared by landscape architect with good
experience of working on wetland and rehabilitation projects.
35.3.2.
A
freshwater ecologist and a faunal specialist are to provide formal
input into the final detailed design of the stormwater management
measures for the proposed road.
35.3.3.
To
ensure that the mitigation and wetland rehabilitation measures were
properly carried out, follow up monitoring of the road reserve
and
adjacent wetlands was to be undertaken by a freshwater ecologist.
This should entail at least two site inspections each year
and an
annual report on the status of the potentially affected freshwater
ecosystems for at least five years after the construction
of the
permanent road.
35.3.4.
The
City must ensure that the open water areas along the southern edge of
the Pick ‘n Pay reedbed system, which are potential
(and in
some cases confirmed) breeding sites for the WLT, are not reduced in
size (this was emphasised as critical).
35.3.5.
It
contemplated that frog survey would be carried out in advance of road
construction to collect necessary data to inform the wetland
rehabilitation plan:
“
To
ensure
that the [WLT] and any other frog species that are present in the
affected wetlands are adequately protected, it is strongly
recommended that a frog survey in the road reserve and adjacent areas
be completed by an amphibian specialist during late winter
- early
spring, to confirm what frog and tadpole species are actually present
in and around the wetlands. This information, which
is not required
for the current (environmental assessment) stage of the project,
should be used to inform the formulation of the
finalized wetland
rehabilitation plans as part of the landscape planning for the
project.”
### Cape
Nature’s comments
Cape
Nature’s comments
36.
In
terms of section 24O(1)(c) of NEMA, the competent authority must, in
taking its decision, have regard to the comments of any
organ of
state charged with the administration of any law which relates to the
activity in question.
37.
Regulation
41(2)(b)(v) requires an applicant for environmental authorisation to
give notice of the proposal to any organ of state
having jurisdiction
in respect of any aspect of the activity.
38.
CapeNature
was one of the commenting authorities in the assessment process.
39.
Cape
Nature provided two comments in the process, in letters dated 7
September 2017 (“
the first
comment
”) and 6 June 2018
(“
the update comment
”),
respectively.
40.
CapeNature’s
updated comment concluded as follows:
“
In
conclusion, CapeNature does not object to the proposed project
subject to the implementation of all mitigation measures and
recommendations. As noted above, the potential impact of the Western
Leopard Toad is still of concern, and therefore, a requirement
should
be that there is written approval from both the freshwater specialist
and the faunal specialist of the final stormwater
management plan in
the final detailed road design, prior to commencement. The faunal
specialist must also be provided an opportunity
to provide inputs
into the Wetland Rehabilitation Plan.”
### The
review by Dr Burger
The
review by Dr Burger
41.
The
EAP appointed Dr Burger to provide an expert review of the Faunal
Impact Study. Dr Burger is a herpetologist.
42.
The
review by Dr Burger concluded as follows:
“
In
summary, the faunal impact report is deemed adequate and
comprehensive in terms of identifying the relevant impacts and
mitigation
measures in the context of the proposed Houmoed Avenue
extension project. These impacts can be partially (but not
completely)
mitigated, and the significance of the various impacts
may range from LOW/MEDIUM to LOW after implementation of mitigation
measures.
Although
the overall impact can be mitigated to a large degree, it must be
recognised that some of the impact will be unavoidable.
In the end it
comes down to weighing up priorities, i.e. that of the greater needs
and desirability of urban expansion versus an
objective to provide
absolute protection for WLT in this particular area. If it was likely
that the proposed road extension would
result in the local extinction
of the WLTs here, or if it would impair the WLT ecological viability
to a significant degree, then
the safeguarding up of WLTs would move
up on the scale of priorities. It is however also plausible to
achieve both goals, i.e.
to develop the road extension and at the
same time also maintain an adequate level of WLT ecological viability
in the long term.
With the various sensitivities and impacts and
mitigation measures already been identified, it is a case of planning
the finer
details and specifications of the various toad-friendly
features so that the overall efficiency of the proposed mitigation
measures
can be enhanced. This must be done in consultation with an
amphibian specialist at the detailed design phase of the project.”
### The
Environmental Authorisation granted by the Director and the regard
that was had to the WLT
The
Environmental Authorisation granted by the Director and the regard
that was had to the WLT
43.
The
Director granted the Environmental Authorisation to the applicant to
undertake the listed activities for which approval was
sought on 22
November 2019.
44.
The
following aspects of the Environment Authorisation as granted warrant
reference:
44.1.
Design
interventions to allow for safe passage of the WLT and toadlets which
have been aligned with the Faunal Impact Assessment
Report include
the following:
44.1.1.
Regular
portal culvert crossings will be provided. These have a rectangular
profile with smooth, flat floor, thus enabling safe
passage of the
toads beneath the road.
44.1.2.
Upstream
and downstream head walls will have flat invert slabs.
44.1.3.
A
continuous low brick wall will be constructed along the length of the
road (northern edge). This wall will be situated behind
the sidewalk.
The purpose of the wall is to prevent toads that have climbed the
full embankment from entering the roadway.
44.1.4.
The
low brick wall will gradually descend towards culvert openings, thus
guiding toads to safe places to cross.
44.1.5.
Along
the right hand side edge, a vertical retaining structure such as a
reinforced concrete wall will be constructed between the
open channel
and roadway. This structure will not be scalable by toads.
44.2.
The
relevant specific conditions that were imposed include the following:
44.2.1.
Condition
22 which required that the recommendations contained in the Wetlands
Report (“
the Freshwater
recommendations
”) must be
implemented. It is referred to in Annexure 4. The
recommendations included:
(a)
A
detailed Wetland Rehabilitation Plan should be drawn up for the
proposed rehabilitation of non-permanent wetlands along the edges
of
the road.
(b)
For
the mitigation of potential operational phase impacts, it is of
critical importance that a freshwater ecologist and fauna specialist
provide formal input into the final detailed design of the stormwater
management measures for the proposed road.
(c)
Drift
fences and underpasses should be installed for the frogs especially
the WLT and other fauna, under the guidance of an amphibian
specialist.
(d)
To
ensure that the potentially negative impacts of the proposed
development are minimised and that the recommended mitigation
measures
are successfully implemented during the operational phase,
and to ensure that the proposed Wetland Rehabilitation measures are
properly carried out, it is strongly recommended that follow-up
monitoring of the road reserve and adjacent wetlands should be
undertaken by a freshwater ecologist.
44.2.2.
Condition
25 which required that the recommendations contained in the Faunal
Impact Assessment Report (“
the
Faunal Impact Assessment Recommendations
”),
must be implemented. It is referred to in Annexure 7. The
recommendations include the following areas of mitigation:
(a)
Runoff
management to ensure that dirty run-off water does not enter the open
water bodies. This is facilitated by placement of drainage
culverts
at least 50 m away from the open water bodies and use of swales to
filter the water before it enters the vlei.
(b)
Habitat
improvement and rehabilitation of infilled sections of the wetland
which could provide for increased habitat for toads along
the edge of
the vlei in the area where the rehabilitation would take place.
(c)
Reducing
road mortality through design features which prevent toads from
climbing onto the road. The final design of the road
mitigation
features should be developed with specific input from an amphibian
specialist.
(d)
Enhancing
connectivity through the creation of toad underpasses with associated
drift fences. This should be monitored for at least
3 to 5 seasons to
evaluate their success and improve their design where necessary.
(e)
The
final design of the above features should be achieved with
collaboration and input from the freshwater specialist as well as
an
amphibian specialist to inform the design of the toad underpasses.
Examples of potential design features were illustrated.
44.2.3.
It
was noted that during the operational phase, the presence of the road
will result in a number of impacts related to disturbance
of fauna
along the road. These impacts were identified and important
mitigation measures were imposed.
44.2.4.
It
was also noted that the construction of the road will increase
cumulative impacts but that the contribution would be low given
the
positioning of the road. It was observed in this regard that provided
the recommended mitigation measures are implemented,
the impacts of
the road can be reduced to an acceptable level.
44.2.5.
The
following concluding comment was made:
“
Overall,
the majority of impacts associated with the development of the
Houmoed Avenue road on fauna are likely to be low after
the effective
implementation of the recommended mitigation and there are no highly
significant impacts on fauna likely to be associated
with the
development and which represent a
red flag or
[reflected in the original] fatal flaw. As such, there are no formal
ecological reasons to indicate that the project should not
go ahead.
However, due to the presence of the Western Leopard Toad in the
area, it is critical that the proposed mitigation
measures are
effectively implemented and the moderate to low post mitigation
impacts are contingent on the effective implementation
of the
required mitigation. Without the implementation of the suggested
measures, there is a high potential for significant long
term in
impact on the Western Leopard Toad and the Environmental
Authorisation should stipulate these measures as essential for
the
construction and operation of the road. To ensure that the suggested
mitigation measures are effectively implemented, the design
of the
toad mitigation measures should be developed in collaboration between
project engineers and an amphibian specialist.
With
the implementation of the required mitigation, the impacts of the
Houmoed Road extension on fauna are considered acceptable.”
44.2.6.
Reasons
for the decision appear from Annexure 10. Among the key factors
affecting the decision to grant authorisation for the proposed
development is, that the Competent Authority took account of the
Faunal Impact and the Wetlands Reports, which have been referred
to
already.
### The
appeal decision of the Minister of Local Government, Environmental
Affairs and Development Planning and the regard that was
had to the
WLT
The
appeal decision of the Minister of Local Government, Environmental
Affairs and Development Planning and the regard that was
had to the
WLT
45.
On
29 January 2020
an appeal was lodged against the Environmental Authorisation granted
by the Director.
46.
In
support of the appeal, a report was provided by Dr Harding titled:
“
Review of the Ecological
Specialist Reports: Proposed Phase Extension of the Houmoed Avenue
(Sunnydale Noordhoek).
”
Dr Harding reviewed the Wetlands Report and the Faunal Impact Report
and raised certain concerns in respect thereof.
47.
On
18 September 2020, the MEC determined the appeal in the matter.
48.
The
MEC dismissed the appeal and confirmed the decision of the Director.
49.
The
MEC provided,
inter alia
,
the following reasons for his decision in respect of the Wetlands
Report and the Faunal Impact Report:
49.1.
As
to the Wetlands Report, the MEC recorded:
49.1.1.
The
appellant called into question the expertise of the Freshwater
Consultant (Mr Ollis) and the Faunal Consultant (Mr Todd) and
submitted a review by Dr Harding. Dr Harding’s review raised
concerns with the literature resources that were utilised or
underutilised in preparing the specialist reports. Mr Ollis confirmed
that key reports on the Noordhoek Wetlands cited by Dr Harding
were
in fact consulted and cited. He concedes that some of the citations
were omitted from the reference list. Mr Ollis confirms
further that
having read through the reports, his assessment and conclusions
remain unchanged.
49.1.2.
The
exclusion of the 17 year old Ratcliffe Report was also raised by Dr
Harding. Mr Ollis indicated that although he had not repeated
all of
the detailed information contained in that report, all relevant
information had been taken into consideration and he had
referred to
Ratcliffe’s findings where relevant. He points out that
Ratcliffe reached very similar conclusions to his report
as to the
likely significance of the potential impacts on the wetlands that
could result from the proposed road.
49.1.3.
Dr
Harding questioned the present ecological state rating assigned to
the Pick ‘n Pay Wetland as well as the ecological categories
assigned by Mr Ollis for the Present Ecological State (PES). In this
regard, Mr Ollis stands by his ratings while Dr Harding has
challenged these.
49.1.4.
The
existing roads are already exerting a major impact on the wetland.
The proposed road will add less than 1.7% to the total length
of
roads already present in the catchment of the wetland.
49.1.5.
The
Wetlands Report is clear that the Pick ‘n Pay reedbed which
forms an integral part of the greater Noordhoek Wetland System
has
been transformed through historical development and more recent urban
development of the Noordhoek Valley. As a result, the
Wetland System
was rated as largely modified relative to the perceived natural
reference date of this freshwater ecosystem, with
the present state
of the hydrology, water quality and vegetation of the wetland
considered to be especially impacted.
49.1.6.
The
wetland was still rated as being of moderate to high conservation
importance with only the endangered WLT being noted as being
of
conservation concern.
49.1.7.
It
is anticipated that approximately 3% of the total extent of the Pick
‘n Pay reedbed and 0.5% of the Greater Noordhoek Wetland
System
will be lost as a result of the establishment of the proposed road,
the impact of which is considered to be a negative impact
of low to
medium significance for the permanent wetland and of medium
significance for the seasonal wetland.
49.1.8.
Rehabilitation
of wetland areas along the edges of the proposed road will be
effected to compensate for the anticipated loss of
wetland associated
with the construction of the proposed road.
49.1.9.
The
report concluded that the proposed road would be acceptable in terms
of impacts on freshwater ecosystems, if all the recommended
mitigation measures are properly implemented and the proposed
rehabilitation of non-permanent wetland habitat is properly carried
out as an integral part of the proposed road.
49.1.10.
The
proposed road would not compromise the functioning of the wetland as
a whole, despite the fact that there would be impacts.
49.1.11.
With
respect to the value of a wetland as calculated by Dr Harding, it
would be dependent on many variables - he based his calculations
on
the Greater Noordhoek Wetland system as a whole whereas only a
section along the 800 m long proposed road will be impacted.
It
was noted that the accuracy of global estimates, as given by Dr
Harding and referred to by the appellant, have not been
substantiated.
49.2.
As
to the Faunal Impact Assessment Report, the MEC recorded:
49.2.1.
The
Faunal Impact Assessment Report concluded that the proposed road will
result in approximately 2 ha of habitat loss across the
margins of
the Pick ‘n Pay reedbed but that the loss is not considered
highly significant as the affected reedbeds are homogenous
and the
loss will be limited to a small portion of the extensive Pick ‘n
Pay reedbeds.
49.2.2.
Two
open water bodies were identified that would be impacted to a greater
degree by the proposed road which are considered locally
significant
and are not available elsewhere in the wetland system.
49.2.3.
The
endangered WLT identified as being of specific concern with regard to
the water bodies, as these are immediately adjacent to
the proposed
road. It is recommended that potential impacts on the WLT be
addressed through engineered mitigation measures,
which include toad
underpasses with associated drift fences. It is recommended that an
amphibian specialist should inform the design
of the toad
underpasses.
49.2.4.
It
is also recommended that the toad underpasses be monitored for at
least 3 to 5 seasons to evaluate their success and improve
their
design if necessary.
49.2.5.
The
majority of impacts associated with development of the proposed road
on fauna are considered to be low after the implementation
of
mitigation measures. Further, there are no highly significant impacts
on fauna likely to be associated with the proposed road
which would
prevent the project from going ahead as long as the mitigation
measures recommended with respect to the WLT are effectively
implemented.
49.2.6.
The
Harding review has raised particular concerns in respect of the
impacts of the noise generated by vehicles using the road. As
has
been pointed out, this road will be approximately 800 m in length
where there is at least 60 km of existing road in the catchment
of
the wetland.
49.2.7.
As
the Harding review points out, road effect impacts are not immediate,
which is why it was recommended that the monitoring be
undertaken for
at least 3 to 5 seasons.
49.2.8.
Mr
Burger of Sungazer Faunal Surveys has been commissioned in his
capacity as a herpetologist to review the Faunal Impact Assessment,
specifically as it related to the findings and recommendations
regarding the WLT. Mr Burger determined that the report was adequate
and comprehensive in terms of identifying the relevant impacts and
mitigation measures in respect of the proposed road. He concluded
that the overall impact can be mitigated to a large degree but that
some impact is unavoidable.
49.2.9.
Mr
Burger further expressed the view that since the proposed road is
unlikely to result in the local extinction of the WLT or impair
its
ecological viability to a significant degree, it is plausible to
develop the proposed road and also maintain an adequate level
of the
WLT ecological viability in the long term. He agreed that the
planning of the finer details and specifications of the various
toad
friendly features must be done in consultation with an amphibian
specialist at the detailed design phase of the project.
49.2.10.
A
separate herpetologist would thus not have come to a different
conclusion and was therefore not required.
49.2.11.
With
respect to the appellant not having been granted access to Mr
Burgers’s comments and recommendations during the withdrawn
EIA
process, it is reiterated that these were two separate processes and
as indicated by the City, it was not made available during
the first
process as it was not included in documents placed before the CA for
the consideration and therefore fell outside the
EIA process.
49.2.12.
It
was also inferred that comments and inputs provided by ToadNuts had
not been considered. As pointed out by the City, a one-on-one
meeting
between the parties to obtain input from ToadNuts was declined by the
organisation.
49.3.
As
to need and desirability, the MEC recorded:
49.3.1.
According
to the Guideline, need and desirability will be determined by
considering broader community’s needs and interests
as
reflected in a credible IDP, SDF and EME for the area and as
determined by the EIA.
49.3.2.
According
to the BAR, the City considers the proposed road to be a priority
project given the urgency to resolve significant road
congestion in
the Valley. According to the City, current and future traffic
volumes necessitate take the proposed link (bypass)
road.
49.3.3.
The
proposed road is in line with the vision of the PSDF which promotes
connectivity in the Cape by ensuring that urban communities
are
inclusive, integrated, connected and collaborate, with a priority to
establish an access system within and between functional
regions.
49.3.4.
The
road corridor does not fall within an area classified as Critical
Biodiversity Area on terrestrial or aquatic grounds, though
the
wetland is considered aquatic Critical Ecological Support Area. The
impacts can however be mitigated to an acceptable level.
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
50.
In
my view this ground of challenge must fail for reasons set out
hereunder.
51.
It
is clear from the documents referred to that the impact of the
proposed road on the WLT was carefully considered and a range
mitigation measures were proposed. More particularly:
51.1.
First
,
the Wetlands Report and the Faunal Impact Study determined that the
proposed road would impact on the WLT and proposed mitigation
measures.
51.2.
Second
,
the Faunal Impact Study was prepared by Mr. Simon Todd (a faunal
specialist) and the Wetlands Report was prepared by Dr Dean Ollis
(a
wetland ecologist). Both authors are qualified as “specialists”
as the term is defined in Regulation 1.
In this regard:
51.2.1.
Mr.
Todd is: (a) an ecologist with more than 20 years’ relevant
experience; (b) has conducted over 200 specialist faunal studies,
four of which pertained to recent developments in the Noordhoek
Valley; and (c) Mr. Todd had a background in conservation biology
meaning that he was versed in the population dynamics which operate
in respect of endangered species.
51.2.2.
Mr
Ollis: (a) has an M.Phil in Environmental Science, and a M.Sc. in
Ecological Assessment; (b) he has 20 years of experience in
environmental sciences, approximately 16 years of which were spent
specialising in aquatic science; (c) he has provided specialist
input
in at least 18 major projects; and (d) has for several years been a
member of the Freshwater Ecosystems Committee for National
Biodiversity Assessment.
51.3.
Third
,
while it is common cause that neither Mr Ollis nor Mr Todd are anuran
specialists, Mr Burger (a herpetologist) was commissioned
to review
the Faunal Impact Assessment, specifically as it related to the
findings and recommendations regarding the WLT. Mr Burger
determined
that the report was adequate and comprehensive in terms of
identifying the relevant impacts and mitigation measures
in respect
of the proposed road. He concluded that the overall impact can be
mitigated to a large degree but that some impact is
unavoidable.
51.4.
Fourth
,
neither the statutory nor the regulatory framework prescribe the
particular specialists that must be appointed for specific
authorisations.
As stated, according to the Regulations a
particular specialist must be appointed where “
the
level of assessment is of a nature requiring the appointment of a
specialist
”. Ms Chand,
as an EAP was accordingly given a discretion as to which specialists
to appoint in the assessment process.
She exercised this
discretion by appointing Mr Ollis and Mr Todd, both of whom
considered the impact of the proposed road on the
WLT. She also
appointed Mr Burger who undertook the review as described.
51.5.
Fifth
,
although a range of concerns were raised by Dr Harding in respect of
the specialist studies, these were comprehensively addressed
with by
the MEC.
51.6.
Sixth
,
the Commenting Authority (Cape Nature), in its second comment did not
take issue with a further study, or report, by a more specialised
scientist in order that the impact of the proposed road on the WLT
may be understood or mitigated.
51.7.
Seventh
,
the applicant has not placed any admissible evidence before the court
from an appropriate specialist as to what a herpetologist’s
report might have revealed, which were not taken into account by the
appointed specialists.
51.8.
Eighth
,
the approval in respect of the proposed road accorded with the
threshold of need and desirability.
52.
The
failure to commission and complete an expert study on the WLT by an
anuran specialist does not, in my view, found a reviewable
irregularity. It also does mean that irrelevant considerations
were taken into account and that relevant considerations were
not
taken into account and nor does it mean that an irrational decision
was taken. The detailed evidence that I have referred
to shows
that the impact of the proposed road on the WLT was carefully
considered by the specialists who were appointed and that
the
decision-makers ultimately imposed a range of mitigation measures.
53.
It
appears that the applicant’s real difficulty is that the
decision-makers attached insufficient weight to the impact of
the
proposed road on the WLT. That, however, does not found a
reviewable irregularity:
53.1.
In
MEC for
Environmental Affairs and Development Planning v Clairison’s CC
2013 (6) SA 235
(SCA)
para 22 the SCA held:
“
The
law remains, as we see it, that when a functionary is entrusted with
a discretion, the weight to be attached to particular factors,
or how
far a particular factor affects the eventual determination of the
issue, is a matter for the functionary to decide, and
as he acts in
good faith (reasonably and rationally) a court of law cannot
interfere.”
53.2.
In
South
African National Roads Agency Ltd v Toll Collect Consortium
2013 (6) SA 356
(SCA)
para 20 C-D the SCA held (
albeit
in a procurement context):
“…
the
evaluation of many tenders is a complex process involving the
consideration and weighing of a number of diverse factors. The
assessment of the relative importance of these requires skill,
expertise and the exercise of judgment on the part of the person
or body undertaking the evaluation.”
54.
For
all of these reasons, I am of the view that this ground of review
cannot succeed.
REVIEW
GROUND 2
: THE
IRRATIONALITY IN APPOINTING AN EXPERT AFTER THE FACT
## The
challenge
The
challenge
55.
The
applicant argues that it is irrational to appoint an expert after the
fact for the following reasons:
55.1.
There
are no current data on the WLT population which uses the Pick ‘Pay
reedbed in general or the three known breeding ponds
in particular.
According to the applicant, there is therefore nothing against which
the anuran expert will be able to measure whether
the road is having
an impact or not.
55.2.
If
it is important enough for an anuran expert to monitor the state of
the WLT after construction of the road, it ought to be important
enough for such an expert to monitor and establish the state of the
WLT before construction.
55.3.
It
makes no sense to recommend a mitigation which is untested and
untried and then to monitor the effectiveness of the mitigation.
According to the applicant, if the road is catastrophically deadly to
the WLT no expert will be able to bring back the WLT population
and
one of the issues which needed to be addressed by specialist was the
cumulative effect of past developments and roads on the
WLT in the
area.
## The
law
The
law
56.
As
a point of departure, the legal principles dealing with irrationality
as a ground of review are well established. In
Democratic
Alliance v President of the Republic of South Africa and others
2012 (12) BCLR 1297
(CC) the Constitutional Court summarised the
approach as follows
:
“
[32]
The
reasoning in these cases shows that rationality review is really
concerned with the evaluation of a relationship between means
and
ends: the relationship, connection or link (as it is variously
referred to) between the means employed to achieve a particular
purpose on the one hand and the purpose or end itself. The aim of the
evaluation of the relationship is not to determine whether
some means
will achieve the purpose better than others but only whether the
means employed are rationally related to the purpose
for which the
power was conferred. Once there is a rational relationship, an
executive decision of the kind with which we are here
concerned is
constitutional.”
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
57.
I
am in agreement with the opposing respondents that this ground of
challenge must fail for the following reasons:
57.1.
First
,
as a point of departure NEMA does not require complete and absolute
knowledge of all potential consequences of a development
proposal before environmental authorisation may be granted.
This is supported by the fact that an applicant for
environmental
authorisation must indicate “
the
possible mitigation measures that could be applied and level of
residual risk
”
and describe “
any
assumptions, uncertainties, and gaps in knowledge which relate to the
assessment and mitigation measures proposed
.”
57.2.
Second
,
The WLT-related impacts were not at any stage assessed as a fatal
flaw (even prior to mitigation). In these circumstances, it
is not
irrational to develop the most appropriate mitigation when a detailed
design of the road is undertaken, and, thereafter
over the course of
five seasons (as prescribed by the conditions of approval), to assess
the efficacy of the mitigations in practice,
and revise and refine
them if warranted.
57.3.
Third
,
it would not have been practicable to ascertain the efficacy of the
mitigation measures in advance of the activity. It is
apparent
from the evidence that the road effect impacts are not immediate,
which is why it was recommended that the monitoring
be undertaken for
at least 3 to 5 seasons.
57.4.
Fourth
,
none of the mitigation measures have been identified as being
irrational. Notably, the applicant does not challenge the
efficacy of the mitigation measures. Instead, it argues that
these measures had “not been locally tested”. Reference
is made to certain foreign studies. According to the applicant, these
have not been tested on local toads and therefore hold up
“no
validity as effective mitigation measures.” In this
regard, the applicant asserts; “we simply do not
know if these
mitigation measures will work. In fact, the proposed mitigation will
most probably result in a dramatic drop in numbers
of WLT.”
58.
There
is, in my view, a rational connection between the mitigation measures
and the purpose for which they were imposed, namely
the preservation
of the WLT’s natural habitat, and the protection of that
species against the threat of road mortality.
59.
I
accordingly find that this ground of review must fail.
# REVIEW
GROUND 3: CUMULATIVE IMPACTS HAVE NOT BEEN CONSIDERED
REVIEW
GROUND 3: CUMULATIVE IMPACTS HAVE NOT BEEN CONSIDERED
## The
challenge
The
challenge
60.
The
applicant argues that the failure to take cumulative impacts into
account will inevitably lead to gaps in knowledge which will
lead to
relevant facts not being taken into account and irrelevant facts
being taken into account.
61.
In
support of this argument, the applicant relies on a statement made by
the MEC in his answering affidavit which denies that the
proposed
road cannot be considered without considering the impact of the
further extension and that each application must be assessed
on its
own merits. The applicant argues that this is a classic case of
failing to take the cumulative impact into account.
62.
As
a point of departure, the EIA Regulations define “cumulative
impacts” as follows:
“
'cumulative
impact', in relation to an activity, means the past, current and
reasonably foreseeable future impact of an activity,
considered
together with the impact of activities associated with that activity,
that in itself may not be significant, but may
become significant
when added to the existing and reasonably foreseeable impacts
eventuating from similar or diverse activities;”
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
63.
I
am of the view that the evidence shows that the cumulative impact in
relation to the WLT was considered both in the assessment
process and
by the decision-makers as is apparent from the following:
63.1.
In
the portion of the Wetland Study, under the heading of “Cumulative
Impacts”, it concludes that: “
the
cumulative impact on freshwater ecosystems is thus considered,
without
any mitigation, to be a negative impact of medium significance for
both route alternatives”
. When
account is taken of the gains to be made by the rehabilitation
recommended interventions, the report concludes that such
impact
would be reduced to a low-to-medium level. It states further that
such impact would be reduced to a low level if “
the
wetland rehabilitation interventions were to be overseen by a wetland
ecologist and guided by a detailed wetland rehabilitation
plan that
was prepared by a landscape architect with good experience of working
on wetland rehabilitation projects, with the input
of a wetland
ecologist”
.
63.2.
The
Faunal Impact Study under the heading, “Cumulative Impacts”
notes:
63.2.1.
Cumulative
Impact 1 is described as “Cumulative habitat loss and
fragmentation due to the Houmoed Avenue Extension”.
63.2.2.
The
nature of the impact is described as “
the
road will
contribute to a cumulative habitat loss and fragmentation in the
Noordhoek -Sun Valley area, potentially impacting species
abilities
to disperse about the landscape or respond to environmental change”
.
The impact was assessed as being of “medium”
significance without mitigation, and “low” significance
with mitigation.
63.2.3.
The
proposed mitigation measures are described in detail, including:
ensuring that the development footprint is kept to a
minimum; the
removal of alien plant growth in the road verge, and edge of the
wetland, limiting human access to the wetland, as
well as the amount
of litter entering the wetland.
63.2.4.
It
is noted that the impact will persist for the life of the road and it
is not likely that it will be reversed.
63.2.5.
The
assessment of this impact concludes that “
although
there will be some long term habitat loss, it is not likely that this
would result in any loss of irreplaceable resources,
provided that
the suggested mitigation measures are applied”
.
63.3.
In
his reasons for the decision, the Director concluded that “
a
number of potentially negative cumulative impacts were also
identified that could result from the Phase 1 extension of Houmoed
Avenue. With the implementation of all the recommended mitigation
measures, it is anticipated that these cumulative impacts to
freshwater ecosystems will be of low significance”
.
63.4.
In
his appeal decision, the MEC stated as follows under “Need and
Desirability” heading, “
the
[Director] has complied with the obligation set out in terms of the
Need and Desirability guideline to consider both the environmental
and planning context. The department, having considered all the
relevant factors, concluded that all identified impacts and
cumulative
impacts had been found to be capable of adequate
mitigation and to have adequate regard to the socio-economic and
environmental
benefits”
.
64.
This
ground of review must accordingly fail.
# REVIEW
GROUND 4: INADEQUATE
PUBLIC PARTICIPATION PROCESS
REVIEW
GROUND 4
: INADEQUATE
PUBLIC PARTICIPATION PROCESS
## The
challenge
The
challenge
65.
The
applicant raises three main objections to the public participation
process:
65.1.
The
first application process was marred by repeated requests for
information by the applicant which were ignored by the EAP.
65.2.
The
second application process contained no new specialist studies and
carried over the deficiencies of the first process.
65.3.
By
the end of the first application process the members of the applicant
were “bankrupted and exhausted by the first process
and we
simply did not have the resources to take on the second process.”
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
66.
I
am of the view that there is no merit to this ground of challenge for
the following reasons:
66.1.
First
,
it is clear that there was extensive public participation in the
first process with comments having been received from some 284
interested and affected parties. These are referred to in the
FBAR.
66.2.
Second
,
notwithstanding the applicant’s assertion that it made repeated
requests for information, it is clear from the affidavits
filed on
behalf of the applicant that the applicant and all other interested
and affected parties, many of whom were members of
the applicant,
“spent a lot of time and invested a significant amount of money
in contributing to the public participation
process”. In its
supplementary affidavit, the applicant’s complaint was that it
was grossly unfair for all of this
time and money to be disregarded
and wasted because the City decided to withdraw the first process.
The complaint
was that the competent authority and
the MEC relied on selected comments from the withdrawn application
process, but not on all
comments.
66.3.
Third
,
as regards the second application process, it is clear from the
affidavits that the applicant refused to engage with the EAP
regarding the perceived shortcomings of the Wetland and Faunal Impact
Studies. According to the evidence, the EAP addressed correspondence
to the applicant advising that it was in the process of arranging
with the project team, particularly the faunal specialist to
meet
with ToadNuts as soon as possible to discuss the impact of the
proposed road on the WLT. In response, the applicant indicated
that
it would not attend this meeting because, it was asserted that it was
nothing more than a tick box exercise.
66.4.
Fourth
,
the applicants were given the opportunity for public participation by
way of the following:
66.4.1.
The
applicant participated extensively in the context of the first BAR,
both through their own representatives and offices bearers,
and
through the written representations of their agent, Mr van der Spuy.
66.4.2.
On
6 December 2018 the applicant was granted an audience with the
Department to ventilate its concerns with the process, which was
followed up with a 32 page letter from Mr van der Spuy.
66.4.3.
The
applicant and its members were registered I&AP’s in
relation to both the first and second basic assessment processes.
66.4.4.
As
such, notice was sent to them in a letter dated 23 May 2019 on the
availability of the BAR for review and comment.
66.5.
Finally
,
the applicant has not identified any respects in which the public
participation process failed to comply with NEMA and the EIA
Regulations.
67.
I
accordingly find that this ground of review must fail.
# REVIEW
GROUND 5: THE TRAFFIC
STUDY WHICH WAS COMMISSIONED BY THE CITY FOR LEGITIMATE TRAFFIC AND
ROAD PLANNING PURPOSES IS NOT A NEMA COMPLIANT
EXPERT STUDY AND DOES
NOT CONSIDER THE ENVIRONMENT OR ALTERNATIVE ROUTES FOR THE PROPOSED
ROAD
REVIEW
GROUND 5
: THE TRAFFIC
STUDY WHICH WAS COMMISSIONED BY THE CITY FOR LEGITIMATE TRAFFIC AND
ROAD PLANNING PURPOSES IS NOT A NEMA COMPLIANT
EXPERT STUDY AND DOES
NOT CONSIDER THE ENVIRONMENT OR ALTERNATIVE ROUTES FOR THE PROPOSED
ROAD
## The
challenge
The
challenge
68.
In
the applicant’s heads of argument, this ground of review is
reduced to a single paragraph. It is argued that it is
common
cause that the Traffic Study was commissioned by the City for
legitimate traffic and road planning purposes, in terms of
road and
traffic legislation. According to the applicant, it is not NEMA
compliant and does not consider the environment or alternative
routes
for the road.
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
69.
In
my view, this ground of challenge falls to be dismissed for the
following reasons:
69.1.
First
,
the Transport Study did not serve the purpose of a traffic impact
assessment under the EIA Regulations. Instead, the purpose
of
the Transport Study was to demonstrate the need for and desirability
of the proposed road. It did so by identifying the pressure
on the
Kommetjie/Sun Valley Rd network and the need for additional capacity
on the network. For that reason, it was not subject
to the
requirements of an impact assessment study under the EIA.
69.2.
Second
,
the applicant does not make out a case for a Traffic Impact Study to
have been provided. The basic assessment process for
the
proposed road did not warrant an assessment of traffic impacts
because the project does not present any potential for an adverse
impact on traffic. Instead, its purpose was to alleviate
congestion, to improve traffic circulation both in the Noordhoek
Valley generally, and around Masiphumele, and to
integrate
Masiphumelele into the Noordhoek / Kommetjie Valley as a whole.
70.
Accordingly,
in my view, this ground of review must fail.
# REVIEW
GROUND 6:THE
EAP WAS BIASED AND MOTIVATED BY A PRECONCEIVED IMPERATIVE THAT THE
PROPOSED ROAD HAD TO BE BUILT
REVIEW
GROUND 6:
THE
EAP WAS BIASED AND MOTIVATED BY A PRECONCEIVED IMPERATIVE THAT THE
PROPOSED ROAD HAD TO BE BUILT
## The
challenge
The
challenge
71.
The
basis for this ground of review is framed as follows in the
applicant’s heads of argument:
“
The
unfortunate conclusion to which the applicant, NEAG, is driven is
that the only plausible explanation for the egregious failures
set
out above is that the EAP was biased and was motivated by a
preconceived imperative that both extensions of Houmoed Avenue
H, A1
and HAE2 had to be built.”
72.
It
follows, in my view, that the only basis for the allegation of bias
is “the egregious failures” committed by the
EAP in the
process.
## The
law
The
law
73.
In
Turnbull-Jackson v Hibiscus Coast
Municipality and Others
2014
(6) SA 592
(CC) at par 30, the Constitutional Court held that the
question of whether an administrator was biased is a question of
fact. On
the other hand, a reasonable suspicion of bias is tested
against the perception of a reasonable, objective and informed
person.
74.
In
S v Roberts
1999
(4) SA 915
(SCA)
(1999 (2) SACR 243
;
[1999] 4 All SA 285)
in paras 32
– 34, the Constitutional Court held:
74.1.
There
must be a suspicion that the administrator might — not would —
be biased.
74.2.
The
suspicion must be that of a reasonable person in the position of
the person affected.
74.3.
The
suspicion must be based on reasonable grounds.
74.4.
The
suspicion must be one which the reasonable person would — not
might — have.
75.
Regulation
13(1)(f)(ii) of the EIA Regulations requires the EAP to be
objective. Whether she is objective is a question of
fact.
An attack on her objectivity must be substantiated by facts, or an
inference that may properly be drawn from proven
facts, that
demonstrate an absence of objectivity.
76.
It
is trite that the inference that is sought to be drawn must be
consistent with all the proved facts; if it is not, then
the
inference cannot be drawn.
[3]
The position was summarised as follows in
S
A Post Office v Delacy and Another
(at par 35):
“
The
process of inferential reasoning calls for an evaluation of all the
evidence and not merely selected parts. The inference that
is sought
to be drawn must be “consistent with all the proved facts.
If it is not, then the inference cannot be drawn”
and it must
be the “more natural or plausible, conclusion from among
several conceivable ones” when measured against
the
probabilities.”
77.
‘
Plausible
’
in this context means ‘
acceptable,
credible, suitable
’.
[4]
Where one or more inferences are possible, a court must satisfy
itself that the inference sought to be drawn is the most
plausible or
probable, even if that conclusion may not be the only one.
[5]
If
there are no positive proven facts from which the inference can be
made, the method of inference fails and what is left is mere
speculation or conjecture.
[6]
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
78.
I
am in agreement with the opposing respondents that this ground of
challenge must fail.
79.
Notwithstanding
the well-established threshold that has to be met, the applicant
makes out no case for the inference it seeks to
draw. This, in
spite of the seriousness of the allegation.
80.
There
is however a more fundamental difficulty with this ground of
challenge, namely, I have found that there is no merit to the
applicant’s other grounds of challenge.
# REVIEW
GROUND 7: IMPROPER
APPOINTMENT OF THE EAP
REVIEW
GROUND 7
: IMPROPER
APPOINTMENT OF THE EAP
## The
challenge
The
challenge
81.
The
applicant argues that:
81.1.
Section
1 of NEMA defines “environmental assessment practitioner”
when used in Chapter 5, means the individual responsible
whereas
Chand Environmental Consultancy CC was appointed.
81.2.
The
appointment of Chand Environmental Consultancy was made by HHO
Consulting Engineers and, as such, was in contravention of Regulation
12 (1). Regulation 12 (1) states: A proponent or applicant must
appoint an EAP at own cost…) According to the applicant,
it is
not permissible for the appointment to have been made by HHO
Consulting Engineers as opposed to the City.
## The
applicant has not established a reviewable irregularity
The
applicant has not established a reviewable irregularity
82.
The
applicant cannot in reply seek to supplement this ground as it has
sought to do. It is trite that the applicant must stand or
fall on
the case made out in its founding papers.
[7]
83.
As
to the appointment of Chand, aside from it having been impermissibly
raised for the first time in reply, I am in agreement with
the
opposing respondents that the challenge must fail. I am in
agreement with the MEC’s reasoning in the appeal, more
particularly:
83.1.
The
contractual appointment is between Chand as the legal entity and the
City. It is for Chand to then designate individuals
as the EAP.
83.2.
In
this instance, Chand appointed both Sadia Chand and Ingrid Eggert.
83.3.
To
appoint more than one EAP is not uncommon, particularly in respect of
larger projects.
83.4.
In
the final BAR 2019, the BAR pro-forma report outline asks the
applicant to “
provide
the details of the lead EAP
”.
This means that more than one EAP may well work on the same project.
84.
In
any event, the purpose of having an independent EAP appointed is to
ensure that the BAR process is performed in an impartial
and reliable
manner by a registered EAP who is a trained professional to conduct
these processes independently. The manner
in which the two EAPs
(Sadia Chand and Ms Eggert) were appointed through Chand Consultancy
does not undermine this purpose.
85.
In
any event, the complaint amounts to a distinction without a
difference. Whilst Chand is a close corporation, its two employees
were appointed as EAP’s in their personal capacities and, as
such, both signed declarations of independence in August 2019.
86.
Finally,
both these challenges are in any event time barred and no extension
of time has been sought.
# REVIEW
GROUND 8: THE MEC DID AN ABOUT-TURN IN RESPECT OF THE RELEVANCE
OF THE PREVIOUS EIA PROCESS TO THE CURRENT APPROVAL
PROCESS
REVIEW
GROUND 8: THE MEC DID AN ABOUT-TURN IN RESPECT OF THE RELEVANCE
OF THE PREVIOUS EIA PROCESS TO THE CURRENT APPROVAL
PROCESS
87.
This
ground of challenge relates to the MEC having changed
his
approach on whether or not the comments of the previous BAR were
taken into account.
88.
This
ground of challenge has no merit. The MEC has explained that
t
here was no
volte
face.
The
MEC has explained that the intention of his statement in his appeal
decision in paragraph 3.1.2 was not to convey that he and
the
Competent Authority did not take into account the previous comments.
They quite clearly were taken into account as shown
by the
comprehensive comment and response table, which served before the
decision makers, and the MEC has stated that they were
taken into
account.
# ORDER
ORDER
89.
In
the circumstances, I am of the view that there is no merit to any of
the grounds of challenge and that this application must
fail.
90.
In
light of the well-established rule in respect of costs in matters
such as these as set out by the Constitutional Court in
Biowatch
Trust v Registrar Genetic Resources and Others
2009 (10) BCLR 1014
(CC)
,
I am of the view that each party must pay its own costs.
91.
I
do not accept that it is appropriate for the costs order to be
divided between constitutional relief and other relief and that
costs
should follow the result in respect of the so-called non
constitutional relief. In my view, this application relates,
in
its entirety to the vindication of constitutional rights and, as
such,
Biowatch
Trust
finds application.
92.
In
the circumstances, I make the following order:
92.1.
The
amendment sought by the applicant to paragraph 4 of its notice of
motion by deleting the words “
a
single natural person
” and
replacing it with “
an
individual
” is granted.
92.2.
The
application is dismissed.
92.3.
Each
party shall pay its own costs.
Pillay
AJ
Acting
Judge of the High Court
APPEARANCES:
For
the Applicant : Adv. M J M Bridgman
Instructed
by: Michalowsky Geldenhuys and Humphries Attorneys
For
the First Respondent: Adv. M D Edmunds & Adv. J Blomkamp
Instructed
by: Brink Thomas Cassiem Inc.
For
the Second and Sixth Respondents: Adv. A Toefy
Instructed
by: The State Attorney (Cape Town)
[1]
Regulation
1.
[2]
Certain additional grounds were advanced in the affidavits but not
persisted with in argument.
[3]
SA
Post Office v Delacy and Another
2009
(5) SA 255
(SCA)
at para 35.
[4]
Ocean
Accident and Guarantee Corporation Ltd v Koch
1963
(4) SA 147
(A)
at 159B-D.
## [5]Govan
v Skidmore1952 (1) 732 (N) at 734, approved inSmit
v Arthur1976 (3) SA 378 (A) at 386;Cooper
and Another v Merchant Trade Finance Ltd(474/97)
[1999] ZASCA 97 (1 December 1999) para 7.
[5]
Govan
v Skidmore
1952 (1) 732 (N) at 734, approved in
Smit
v Arthur
1976 (3) SA 378 (A) at 386;
Cooper
and Another v Merchant Trade Finance Ltd
(474/97)
[1999] ZASCA 97 (1 December 1999) para 7.
[6]
S
v Essack & another
1974
(1) SA 1
(A)
at 16C-E.
[7]
National
Council of Societies for the Prevention of Cruelty to Animals v
Openshaw
2008
(5) SA 339 (SCA)
paras
29 – 30.
sino noindex
make_database footer start
Similar Cases
Theewaterskloof Local Municipality v Council of Theewaterskloof Local Municipality and Others (23535/2024) [2024] ZAWCHC 407 (2 December 2024)
[2024] ZAWCHC 407High Court of South Africa (Western Cape Division)99% similar
Bezuidenhout NO and Others v Enable Capital Enterprise (Pty) Ltd (4735/2024) [2025] ZAWCHC 433 (18 September 2025)
[2025] ZAWCHC 433High Court of South Africa (Western Cape Division)99% similar
Theewaterskloof Municipality v Marais and Others (Appeal) (A223/24) [2025] ZAWCHC 355 (19 August 2025)
[2025] ZAWCHC 355High Court of South Africa (Western Cape Division)98% similar
Erf 1050 Paternoster (Pty) Ltd v Minister of Forestry, Fisheries and the Environment and Others (3454/22) [2025] ZAWCHC 416 (9 September 2025)
[2025] ZAWCHC 416High Court of South Africa (Western Cape Division)98% similar
Bezuidenhout and Others v Minister of Agriculture Land Reform and Rural Development and Others (2925/2024) [2024] ZAWCHC 184; [2024] 3 All SA 744 (WCC) (27 June 2024)
[2024] ZAWCHC 184High Court of South Africa (Western Cape Division)98% similar