Case Law[2025] ZAWCHC 424South Africa
Contour Technology (Pty) Ltd v Bergrivier Municipality and Others (2025/139019) [2025] ZAWCHC 424 (15 September 2025)
High Court of South Africa (Western Cape Division)
15 September 2025
Headnotes
to the pain and duty of proper process. It must apply formally for a court to set aside the defective decision, so that the court can properly consider its effects on those subject to it.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2025
>>
[2025] ZAWCHC 424
|
Noteup
|
LawCite
sino index
## Contour Technology (Pty) Ltd v Bergrivier Municipality and Others (2025/139019) [2025] ZAWCHC 424 (15 September 2025)
Contour Technology (Pty) Ltd v Bergrivier Municipality and Others (2025/139019) [2025] ZAWCHC 424 (15 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2025_424.html
sino date 15 September 2025
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case no: 2025-139019
In the matter between:
CONTOUR
TECHNOLOGY (PTY) LTD
Applicant
And
BERGRIVIER
MUNICIPALITY
THE MUNICIPAL
MANAGER:
BERGRIVIER
MUNICIPALITY
THE EXECUTIVE
MAYOR:
BERGRIVIER
MUNICIPALITY
ONTEC
(PTY) LTD
First Respondent
Second Respondent
Third Respondent
Fourth
Respondent
Coram:
JUSTICE J CLOETE
Heard
:
10 September 2025
Delivered
electronically
: 15 September 2025
ORDER
1.
The application for the relief sought in Part A of
the applicant’s notice of motion is dismissed;
2.
The application for the relief sought in prayer 2
of the applicant’s notice of motion is postponed for hearing
simultaneously
with Part B and the costs incurred in respect thereof
shall be costs in the cause;
3.
The parties are directed to approach the Judge
President for an expedited date for the hearing of Part B (subject to
her overriding
discretion in this regard);
4.
In respect of the applicant and the first to third
respondents, each party shall bear their own costs in relation to
Part A; and
5.
The applicant shall pay the costs of the fourth
respondent in relation to Part A, including the wasted costs of 2
September 2025,
on scale C (party and party) and including the costs
of counsel.
JUDGMENT
CLOETE J:
[1]
The applicant (‘Contour’) has
approached this court for urgent final declaratory relief, as well as
interim interdictory
relief (Part A) pending, essentially, the
review of certain decisions taken by the first and/or second and/or
third respondents
(collectively, unless otherwise indicated, the
‘municipality’) in respect of a tender awarded to the
fourth respondent
(‘Ontec’) to supply the municipality
with an integrated pre-paid electricity vending and management system
for electricity
consumers within its municipal area of jurisdiction
(Part B). For convenience I refer to this as the ‘new
tender’
or the ‘new tender award’. Both the
municipality and Ontec oppose.
[2]
The application was launched on 15 August 2025 and
enrolled for hearing of the declaratory relief and Part A in the
‘fast
lane’ of motion court on 2 September 2025. It
did not proceed on that day because the papers were not complete and
their length warranted, in the opinion of the urgent duty judge
concerned, a special allocation before a judge outside of the fast
lane. The Deputy Judge President allocated the matter to me for
hearing on 10 September 2025.
[3]
The final relief sought is contained in prayer 2
of the notice of motion, for an order declaring that an agreement
concluded between
Contour and the municipality in respect of the same
services (the ‘2021 agreement’) did not terminate on 31
July 2025
and remains extant. The Part A relief is contained in
prayer 3 thereof and is for the following orders: (a) prayer 3.1,
that the
municipality and Ontec are interdicted from taking any steps
to implement the new tender; (b) prayer 3.2, that the municipality
is
interdicted from concluding any service level agreement with Ontec
pursuant to the award of the new tender; (c) prayer 3.3,
that in the
event of them having already concluded a service level agreement,
they are interdicted from giving effect to it; and
(d) prayer 3.4,
that the municipality is directed to permit Contour to continue
rendering services in terms of the 2021 agreement.
[4]
There has regrettably been a series of material
administrative errors made by the municipality leading up to the
launching of this
application. It first awarded the new tender to
Ontec on 7 January 2025. Contour, the only other successful bidder,
timeously appealed
against that award. However, before Contour could
exhaust its internal remedies - and it was disputed by the
municipality at that
stage that it was entitled to do so in the
manner adopted - the municipality gave notice to Contour on 30
January 2025 that it
was cancelling the 2021 agreement as a result of
the new tender to Ontec.
[5]
On 6 February 2025 the municipality did an about
turn and rescinded the cancellation notice to Contour because of
concerns it had
in respect of one of the Ontec tender supporting
documents, and which had been brought to its attention by Contour (I
will refer
to this again later but for present purposes it is the
‘Phoenix letter’). On 10 February 2025 the municipality
cancelled
the award to Ontec as a result of those concerns with
immediate effect, and simultaneously informed it that Contour, as the
next
qualifying bidder, would be appointed instead (this much was
procedurally correct in terms of the earlier Bid Adjudication
Committee
recommendation accepted by the Acting Municipal Manager).
Ontec objected to the cancellation but was informed by the
municipality
on 14 February 2025, and again before Ontec could
exhaust its internal remedies, that its new tender award was
‘permanently
cancelled’.
[6]
On 17 February 2025 the municipality awarded the
new tender to Contour, and requested that it consequently withdraw
its earlier
appeal (which, as mentioned, it had already told Contour
was not competent in its view, and which was in turn disputed by
Contour).
Contour proceeded to withdraw its appeal in good
faith. Ontec however nonetheless pursued its internal remedies
against
the cancellation of the new tender to it as it was entitled
to do. This resulted in a referral of the dispute between Ontec
and the municipality, by the municipality itself, to Brasika
Consulting (Pty) Ltd (‘Brasika‘) in the person of Adv
Helen Venter (‘Venter’). In the meantime, and despite a
number of requests by Contour for the municipality to sign
its
service level agreement, a necessary pre-requisite for the new tender
award to be completed, the municipality declined, informing
Contour
that it would respond ‘pending the outcome of the aforesaid
process and based on what is legally feasible’.
Presumably the
municipality intended to say it would respond once the dispute
resolution process with Ontec was completed. That
process dragged on
from early March 2025 until Venter eventually responded to Contour on
12 June 2025. During this entire period
Contour continued to perform
in terms of the 2021 agreement which remained in force and the
municipality voiced no objection.
[7]
The upshot of Venter’s response was that she
had determined the difficulties with the Phoenix letter had not been
proven as
intentional on Ontec’s part ‘beyond a
reasonable doubt’. Venter had further determined that: (a) the
new tender
earlier awarded to Ontec was ‘functus officio in
nature’ and could not have been ‘unilaterally cancelled
by the
Municipality without following due course and having such
contract declared invalid and set aside by a court’; and
(b) the municipality was not able to ‘lawfully conclude a valid
and enforceable contract with Contour [i.e. the new tender
award] and that such award is regarded as invalid ab initio.’
[8]
In her report dated 20 May 2025, which Venter
declined to provide to Contour due to its confidentiality but which
the municipality
subsequently annexed to its answering affidavit,
Venter explicitly advised the municipality that it could ‘only
undo its
own administrative actions via a court of law’ and as
such its purported cancellation of the new tender with Ontec was
irregular.
She also advised that ‘as the award decision
was functus officio, i.e. rights have vested with Ontec, any
municipal
administrative act does not detract from the legal
consequences thereof and those rights remain binding until varied or
set aside
by a court.’
[9]
In
light of that advice, one would have thought that the municipality,
whose Municipal Manager is also an Advocate and thus presumably
versed in the law, would have realised that the same applied to the
subsequent award of the new tender to Contour in light of the
Oudekraal
principle
[1]
,
and that such award, if the municipality believed its decision was
defective, was likewise subject to self-review. As the
majority
of the Constitutional Court put it in
MEC
for Health, EC v Kirland Investments
[2]
:
‘
[64]
Can a decision by a state official, communicated to the
subject, and in reliance on which it acts, be set aside
by a court
even when government has not applied (or counter-applied) for the
court to do so? … Even where the decision is
defective …
government should generally not be exempt from the forms and
processes of review. It should be held to the pain
and duty of proper
process. It must apply formally for a court to set aside the
defective decision, so that the court can properly
consider its
effects on those subject to it.
[65]
The reasons spring from deep within the Constitution’s scrutiny
of power. The Constitution regulates
all public power. Perhaps the
most important power it controls is the power the state exercises
over its subjects. When government
errs by issuing a defective
decision, the subject affected by it is entitled to proper notice,
and to be afforded a proper hearing,
on whether the decision should
be set aside. Government should not be allowed to take shortcuts ...
Once the subject has relied
on a decision, government cannot, barring
specific statutory authority, simply ignore what it has done …’
[10]
However on 17 June 2025 the municipality, in the
person of the Municipal Manager, informed Contour that the double
award presented
the municipality with ‘an unfortunate situation
where we were exposed to the conundrum of having awarded two
contracts for
the same tender … because there was already a
lawful contractual relationship between Ontec and the Municipality
prior to
the subsequent “award” to Contour the principles
of legality dictate …’ that the award to Contour was
‘unlawful’. The Municipal Manager proceeded to inform
Contour that its ‘month-to-month contractual arrangement’
in terms of the 2021 agreement would expire on 31 July 2025. In
response, Contour pointed out that the 2021 agreement was valid
for a
minimum period of 3 years, was still extant, and could only be
terminated on 90 days notice; and further given that the municipality
had awarded it the new tender, this could not simply be unilaterally
revoked.
[11]
On 24
June 2025, Contour submitted its appeal against the decision to
revoke the new tender award to it. It recorded that an appeal
precluded the municipality from implementing its unilateral
‘cancellation’ or concluding a service level agreement
with Ontec until finalisation of the appeal process. It sought an
undertaking in these terms to be furnished by 27 June 2025, failing
which it would approach court for urgent relief. On 30 June 2025 the
Municipal Manager responded. She advised that because she
had made
the decision to revoke the new tender award to Contour, the appeal
authority would be the Executive Mayor, but that ‘the
Municipal
Finance Management Act
[3]
, by
implication prohibits councillors from making decisions regarding
procurement contracts and tenders’. She stated that
in the
circumstances the municipality required time to obtain external legal
advice and would respond to the request for an undertaking
by 11 July
2025. The external advisor turned out to be Venter.
[12]
On 15
July 2025 (4 days after her self-imposed deadline) the Municipal
Manager reverted to Contour with the advice received. It
was conceded
that the municipality had made ‘certain administrative errors’
but the matter was nonetheless considered
‘as having been
exhausted’ for two reasons. First, the internal appeal remedy
in terms of s 62 of the Systems Act
[4]
was not applicable since the Municipal Manager had not exercised a
delegated power but an original one in revoking the new tender
to
Contour. Second, the 90-day termination notice period - although
entrenched in the 2021 agreement - was not applicable because
that
agreement was now on a month-to-month basis.
[13]
As to the applicability or otherwise of s 62 of
the Systems Act, this is not an issue before me for either the final
declaratory
relief or the Part A relief, and counsel for Contour
confirmed this in argument. As to the alleged month-to-month
contractual arrangement
in respect of the 2021 agreement, the
following. On 25 February 2025 the municipality wrote to Contour,
apologising for the delay
in finalising the award of the new tender
to it, but confirming that the commencement date of the new tender
would remain as 1
March 2025 with a termination date of 30 June 2027.
Contour was clearly under the bona fide impression, created by the
municipality
itself, that the new tender was replacing the 2021
agreement, but could not yet be implemented per the new tender
because of Ontec’s
objection process. Contour thus responded on
27 February 2025 that ‘considering the circumstances which have
presented themselves
we shall continue to render services … on
a month-to-month basis under the [2021] agreement’. In other
words, Contour
had only offered to assist the municipality by
continuing to provide the essential services in the interim in terms
of the 2021
agreement on a month-to-month basis because otherwise it
would be performing these services in a vacuum. The municipality must
have understood it in the same way because as a fact Contour
continued to perform those services.
[14]
Reverting to the chronology of events, on 17 July
2025, Contour responded to the Municipal Manager’s letter of 15
July 2025.
It disputed that s 62 of the Systems Act was not
applicable; reaffirmed its previous position; and urged the
municipality to reconsider
its stance and revert with an appropriate
undertaking by 21 July 2025. That undertaking was not forthcoming. In
addition, Contour
wrote to the Western Cape Provincial Treasury on 25
July 2025, requesting that it exercise its constitutional and
statutory oversight
by issuing guidance to the municipality, but to
which it appears no response was received. Instead, on 1 August 2025
the municipality
informed Contour that it was to cease all services
on that same day. On 5 August 2025 Contour advised the municipality
that it
would be approaching court for relief. The application was
launched eight working days later.
[15]
Against this background I do not agree with the
contentions of the municipality and Ontec that Contour’s
urgency is self–created.
Given the particular factual
matrix of this matter, it would be placing form above substance to
find that Contour knew of
the municipality’s final position by
15 July 2025 (on the municipality’s version) or even as early
as 12 June 2025
(on Ontec’s version). Had Contour rushed off to
court shortly after 12 June 2025 without even attempting to exhaust
what
it believes to be its internal remedies, it risked being told by
a court to first do so. Had Contour acted in similar vein
shortly after 15 July 2025, without first requesting the municipality
to reconsider its stance, and bearing in mind it was providing
an
essential service to it, it risked damaging that relationship. This
was not a situation of equal bargaining power and in addition,
the
manner in which the municipality had flip-flopped about, not only
with Contour but also Ontec, made it prudent, in my view,
to first
adopt a conciliatory and cautious approach. In addition, Contour
needed to afford the municipality and Ontec a reasonable
time to
oppose and file answering papers.
[16]
Returning again to the chronology of events, on 11
August 2025 the Municipal Manager wrote to Contour, demanding it
refrain from
continuing to provide services ‘without any legal
contract supporting such’. At that time the municipality was
aware
that Contour disputed: (a) the revocation of the award of the
new tender to it; (b) the termination notice period given in respect
of the 2021 agreement; and (c) that it was not entitled to an
internal appeal. Contour was also informed the municipality
would be publicly notifying its electricity consumers that only Ontec
was authorised to supply the services in question. This the
municipality proceeded to do. It thereafter forged ahead and actively
engaged with Ontec in the transfer process, continuing to
do so even
while it knew this application was pending. On 1 September 2025, the
day before the matter was initially enrolled for
hearing, the
municipality refused to renew Contour’s key access to the Eskom
system, thereby preventing it from performing.
[17]
The Municipal Manager deposed to the
municipality’s answering affidavit on 1 September 2025. In
paragraph 94.4 she alleged
that the service level agreement with
Ontec had not yet been signed since ‘feedback from Ontec on
changes is still outstanding’.
This was demonstrated to
be a blatant untruth, because it emerged in a supplementary affidavit
deposed to by the self-same
Municipal Manager, handed up at the
hearing, that Ontec had already signed the service level agreement on
20 August 2025 without
any changes. The service level agreement was
signed by the municipality, again without any changes, only on 8
September 2025, thus
two days before the matter was argued.
[18]
Counsel for Contour submitted that both the
municipality and Ontec had acted in bad faith by pushing ahead with
finalisation of
the new tender award in the face of pending
litigation. While the equities might lie in Contour’s favour,
the difficulty
which Contour faced by the time the matter was heard
was that, as a fact, the new tender award process with Ontec was
complete,
both in the contractual and practical sense, and Contour
was thus constrained to seek, not a preservation of the status quo,
but
a reversal thereof, which is not the purpose of interim
interdictory relief. Moreover, the law is not on Contour’s side
in
respect of the steps taken to finalise the new tender award to
Ontec in the face of pending litigation.
[19]
As
both counsel for the municipality and Ontec submitted, their clients
were entitled at law to have done so. This is clear from
the
Constitutional Court decision in
Tshwane
City v Afriforum and Another
[5]
where
the court stated:
‘
[71]
There is another issue of importance that requires attention. It is
the notion that the mere launch of an application for a
restraining
order or the review proceedings had the legal effect of automatically
restraining Council from erecting street signs
or removing old street
names …
[74] …It needs to
be stated categorically, that no aspect of our law requires of any
entity or person to desist from implementing
an apparently lawful
decision simply because an application, that might even be dismissed,
has been launched to hopefully stall
that implementation. Any
decision
[
ie. judgment in this context]
to that effect
lacks a sound jurisprudential basis and is not part of our law. It is
a restraining order itself, as opposed to
the sheer hope of one being
granted, that can in law restrain. To suggest otherwise reduces the
actual grant of an interdict to
a superfluity.
[75] For these reasons
there was no obligation on Council to desist from removing old street
names upon becoming aware that an urgent
application for a
restraining order had been filed. Only sheer choice or discretion,
but certainly not any obligation or legal
barrier, would lead to
action being desisted from in anticipation of a successful challenge
or application for an interdict.’
[20]
As I see it, there are potentially four reviewable
decisions taken by the municipality, namely: (a) the initial award of
the new
tender to Ontec; (b) the award of the new tender thereafter
to Contour; (c) the revocation of the award of the new tender to
Contour;
and (d) the award for the second time, or reinstatement, of
the new tender to Ontec. Some or all of these will come under
scrutiny
in Part B, including no doubt the domino effect of the
municipality’s decisions. There was a voluntary and frank
acknowledgement
by counsel for Ontec that a determination, one way or
the other, is required by way of Part B. Counsel for the
municipality
was more hesitant on this score, but accepted that a
self-review by the municipality in respect of some of these decisions
might
be necessary.
[21]
In any event, as was also stated by the majority
of the Constitutional Court
Kirland:
‘
[67]
In the face of government’s attitude, Kirland succeeded in the
high court and the Supreme Court of Appeal. The main
[ie
the minority]
judgment
would reverse this, on the basis that all the evidence about the
controversial approval is before us, and it shows the
approval was
defective. This outcome, and the reasoning supporting it, would have
untoward consequences for those subject to government
decision-making. The evidence is not all before us. And it would be
fundamentally unfair to Kirland to set aside that decision
now,
without requiring government to bring a proper application, in which
it explains the history of the decision, its shifting
attitudes
towards it and its delay in dealing with it. In response, Kirland is
entitled to be heard on whether it has been prejudiced
and why it
would be unfair to set the decision aside now. This is a protection
the Constitution itself affords Kirland. The main
judgment would
abrogate that protection. The court should not do so.’
[22]
The main complaint of Contour in relation to the
initial award of the new tender to Ontec pertains to the Phoenix
letter. The tender
specifications include that the supplier offers
must ‘comprise a complete and fully functional integrated
prepayment vending
and management system including all the operating
and database security needed to operate such a system’.
Importantly, the
supplier’s system must fully integrate with
the Municipality’s Phoenix ERP system; and the failure to
implement within
the required timeline ‘will result in the
cancellation of the tender’. There is no dispute that at
all material
times Contour has been able to fulfil these requirements
and already had such a system in place.
[23]
The
new tender was initially awarded to Ontec subject to these
requirements, failing which it would be cancelled and awarded to
the
tenderer with the second highest score, ie. Contour. When Contour’s
appeal process commenced, the municipality provided
it with a letter,
purportedly from Phoenix, in which it was stated that Ontec’s
system was not only compatible but was already
successfully
integrated. This letter was one of Ontec’s tender supporting
documents. It turned out that neither of
these representations
were true at the time of the new tender award to Ontec, although it
has by now apparently met these requirements.
It is the stance
of both the municipality and Ontec that this is good enough for the
new tender to have been validly awarded,
and it is Contour’s
stance that it is not. Ontec disavows any fraudulent conduct on its
part, whereas Contour maintains it
acted fraudulently in relation to
the Phoenix letter. These are issues for determination in Part
B. I am of the view that
were this not an application to temporarily
restrain the exercise of a statutory power, Contour would have met
the ordinary first
requirement of a prima facie right even if open to
doubt. However given this is indeed such an application, and having
given this
careful thought, I am unable to conclude that this is the
‘clearest of cases’ when regard is had to the
OUTA
[6]
test, or that the circumstances which present themselves are
‘exceptional’ when regard is had to the
Gordhan
test.
[7]
Contour itself does not claim this to be the case either.
Moreover, Contour also needs to satisfy the other requirements
for
interim interdictory relief, namely a well-grounded apprehension of
irreparable harm; the balance of convenience in its favour;
and the
absence of any other satisfactory remedy.
[24]
In this regard, the following. The municipality
and Ontec have already fully implemented the new tender award. They
have already
concluded a service level agreement. The proverbial
horse has now bolted and to grant the relief in prayers 3.1 to 3.3 of
Part
A will be to reverse the status quo. The only potential
way to stymie the continued implementation of the new tender to Ontec
is to grant the final declaratory relief which Contour seeks in
prayer 2 of its notice of motion, namely that the 2021 agreement
remains extant and did not terminate on 31 July 2025 as the
municipality contends it did. Herein lies another fundamental
difficulty
for Contour. On its own version, the municipality is
entitled to terminate that agreement on 90 days notice. Accordingly,
and even
assuming for present purposes that the notice previously
given by the municipality was irregular, there is nothing to prevent
the
municipality from giving 90 days notice tomorrow, and given its
past conduct, there is every reason to believe that is exactly what
it will do. There was certainly no undertaking forthcoming during
argument that it would not. I cannot bar the municipality,
as
Contour effectively seeks in prayer 3.4 of its Part A relief, from
giving 90 days’ notice of termination, since that would
be
making a contract for the parties, and this is legally impermissible.
Linked to this is my concern that a decision on
the final
declaratory relief in prayer 2 is probably premature and is better
dealt with in Part B when the court will have all
the evidence before
it.
[25]
Granting the prayer 2 relief at this
stage may have the following further consequences. The municipality
will have two service providers
for the same essential services for a
further 90 days. It will generate confusion for those whom the
municipality is constitutionally
bound to serve in an efficient
manner, ie. the end consumers. It will also result in considerable
additional expense to the fiscus
for that period because the
municipality will have to these two service providers. At the end of
that notice period there will
have to be a full transfer process back
to Ontec at least until determination of Part B, again with the
attendant cost, not only
to the municipality but also to Ontec. In
these circumstances I am compelled to conclude that the balance of
convenience is not
in Contour’s favour.
[26]
Turning
now to the requirements of a well-grounded apprehension of
irreparable harm and the absence of any other satisfactory remedy.
The services at issue are ongoing and will continue to be so, unlike,
for example, the construction of a road network or a hospital.
If
Contour succeeds in Part B the court is at liberty to grant any order
that is just and equitable under s 8 (1) of PAJA
[8]
,
including a declaration of rights with regard to the 2021 agreement,
the new tender, and such consequential relief as that court
might
deem appropriate. Any interim harm to Contour is thus not
irreparable. Further, Contour retains the right to institute
action
for contractual damages if it so elects, and there is no serious
suggestion that, given the nature of the services, those
damages it
alleges it has already sustained, and will continue to sustain, are
not capable of quantification. Counsel for
Contour, relying on
Edrei
Investments
[9]
submitted that the election whether to claim specific performance or
damages was exclusively Contour’s. That may be
so, but in
Edrei
Investments
the
court was persuaded that the applicant’s other operational
requirements should prevail over an alternative claim for damages
in
granting an interim interdict. I do not understand the law to be
that, as a general principle, the mere election to claim specific
performance instead of damages means it follows that there is no
alternative satisfactory remedy.
[27]
For all these reasons the application before me
must fail. As far as Ontec is concerned, costs must follow the
result although
I make it clear that in awarding Ontec its costs, I
make no finding on the validity of its new tender award. Counsel
were
all in agreement that scale C is appropriate. As far as the
municipality is concerned, despite its success in fending off the
relief
sought by Contour at this stage, I am of the firm view that it
should not be entitled to its costs. Finally, it is in the interests
of all the parties that Part B be heard and determined on an
expedited basis and this is catered for in the order hereunder.
[28]
The following order is made :
1.
The application for the relief sought in Part A
of the applicant’s notice of motion is dismissed;
2.
The application for the relief sought in prayer
2 of the applicant’s notice of motion is postponed for hearing
simultaneously
with Part B and the costs incurred in respect thereof
shall be costs in the cause;
3.
The parties are directed to approach the Judge
President for an expedited date for the hearing of Part B (subject to
her overriding
discretion in this regard);
4.
In respect of the applicant and the first to
third respondents, each party shall bear their own costs in relation
to Part A; and
5.
The applicant shall pay the costs of the fourth
respondent in relation to Part A, including the wasted costs of 2
September 2025,
on scale C (party and party) and including the costs
of counsel.
J I CLOETE
Judge
of the High Court
Appearances
For applicant:
Adv Nick De Jager
Adv
Matt WIlliams
Instructed by:
Dirk Kotze Attorneys
For
1
st
–
3
rd
respondents:
Adv
Michael Bishop
Adv
Michael Tsele
Instructed by:
Enderstein Malumbete Inc
For
4
th
respondent:
Adv Adiel Nacerodien
Instructed
by:
Ward Brink Attorneys
[1]
Oudekraal Estates (Pty)
Ltd v City of Cape Town and Others 2004 (6) SA 222 (SCA)
[2]
2014
(3) SA 481 (CC)
[3]
Local
Government: Municipal Finance Management Act 56 of 2003
[4]
Local Government:
Municipal Systems Act 32 of 2000
[5]
2016 (6) SA 279
(CC)
[6]
National
Treasury v Opposition to Urban Tolling Alliance
2012 (6) SA 223
(CC)
at para 47
[7]
Economic
Freedom Fighters v Gordhan and Others; Public Protector and Another
v Gordhan and Others
2020 (6) SA 325
(CC) at para 42
[8]
Promotion of
Administrative Justice Act 3 of 2000
[9]
Edrei
Investments v Dis-Chem Pharmacies
2012 (2) SA 553
(ECP)
sino noindex
make_database footer start
Similar Cases
Contour Technology (Pty) Ltd v Theewaterskloof Municipality and Another (5729/2023) [2024] ZAWCHC 330 (23 October 2024)
[2024] ZAWCHC 330High Court of South Africa (Western Cape Division)100% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)99% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2025] ZAWCHC 292 (14 July 2025)
[2025] ZAWCHC 292High Court of South Africa (Western Cape Division)98% similar
Inospace Services (Pty) Ltd v Morris and Another (2025/124057) [2025] ZAWCHC 414 (8 September 2025)
[2025] ZAWCHC 414High Court of South Africa (Western Cape Division)98% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2024] ZAWCHC 2 (2 January 2024)
[2024] ZAWCHC 2High Court of South Africa (Western Cape Division)98% similar