Case Law[2024] ZAWCHC 2South Africa
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2024] ZAWCHC 2 (2 January 2024)
Headnotes
paragraph 24.5 “regulated the manner in which the [Respondents] would be free to resume competition with the [Applicants]”.[1]
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 2
|
Noteup
|
LawCite
sino index
## Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2024] ZAWCHC 2 (2 January 2024)
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2024] ZAWCHC 2 (2 January 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_2.html
sino date 2 January 2024
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
Number: 17470/2014
In
the matter between:
TECHNICAL
SYSTEMS (PTY) LTD
First
Applicant
LAVIRCO
BELEGGINGS (PTY) LTD
Second
Applicant
and
RTS
INDUSTRIES
First
Respondent
C
QUIPTECH (PTY) LTD
Second
Respondent
CGC
INDUSTRIES (PTY) LTD
Third
Respondent
CHRISTIAAN
ARNOLDUS KURTZ
Fourth
Respondent
CARL
WILLIAM RICHTER
Fifth
Respondent
Coram:
Bishop, AJ
Heard:
6 November 2023
Delivered:
2 January 2024
JUDGMENT
BISHOP,
AJ
[1]
Augers are used to convey poultry feed.
They are made from flat wire that is coiled to form a type of spiral.
The process to turn
steel into flat wire, and then convert flat wire
into auger requires a production line with multiple machines and
steps. The steel
must be de-coiled, flattened by a flattening mill,
heat-treated through an austenitic and martensitic procedure, and
then tempered.
Each time it is heat treated, it must be quenched. The
wire must properly tensioned by a tensioner, and at the end of the
process,
coiled again. This produces coiled flat wire which can then
be fed through an auger coiling machine to make auger. If the process
is not perfect, the product will be too brittle or defective, and
will not convey the feed to the hungry poultry.
[2]
The First Applicant (
Technical
Systems
) manufactures flat wire and
turns that flat wire into auger. Until 2015, so too did the
Respondents. But in 2015, the parties agreed
to an order which
prohibited the Respondents from manufacturing either flat wire or
auger until they could convince the Applicants’
or this Court
that they could do so without violating the Applicants’
intellectual property in their manufacturing process.
[3]
The Respondents built a new production
facility to make flat wire and auger which the parties’ experts
evaluated. The Applicants
and their expert believe that line still
infringes their rights. The Respondents and their expert disagree.
The Applicants want
this Court to rule on that question. The
Respondents say they have abandoned that version of the facility and
that there is therefore
no point in a court ruling on whether it
improperly employed the Applicants’ drawings or confidential
processes.
[4]
I conclude that the Respondents’ long
history of dishonest dealing means their professed intent not to use
the inspected production
facility is not a sufficient basis to depart
from the process this Court set in 2015.
[5]
The matter has a long history and has
troubled several judges in Cape Town and Bloemfontein. Let’s
start at the very beginning,
a very good place to start.
###
### The Original Dispute and
the 2015 Order
The Original Dispute and
the 2015 Order
[6]
In 2014, the Applicants suspected that the
Respondents were infringing their trade secrets for machinery to
manufacture flat wire
and auger. They brought an application to
interdict them from doing so. The Respondents initially defended the
application on the
basis that Technical System’s processes were
not confidential, but were in the public domain.
[7]
It subsequently emerged, through discovery
and third party subpoenas, that Mr Kurtz (the Fourth Respondent) had
taken a number of
Technical Systems’ technical drawings and
given them to the First Applicant (
RTS
).
Kurtz had been employed by Technical Systems, but had gone to work
for RTS. RTS had supplied the Applicant’s technical
drawings to
third parties to manufacture components for its production line;
those were the drawings that the third parties supplied
to Technical
Systems in response to their subpoenas. In light of these
revelations, the Applicants amended their notice of motion
to also
seek relief based on the infringement of their copyright in those
technical drawings. The bottom line of these revelations
was that
Kurtz had stolen the Applicants’ copyrighted and confidential
information and given it to his new employer, who
had used it to make
flat wire and auger in competition with the Applicants.
[8]
Following this devastating discovery, the Respondents
abandoned their defence. The parties agreed on an order that was made
by Schippers
J (as he then was) on 2 June 2015. In the 2015 Order,
the Respondents recognised that the Applicants had a confidential
production
process to make augers from specially manufactured flat
steel wire. The order included a range of interdicts against the
Respondents.
Three are relevant to this application:
[8.1]
First, the order interdicted the Respondents from “employing
any facet of the applicant’s (sic) confidential process
in the
manufacture of flat wire or auger” for so long as the
Applicants’ process remained confidential. That interdict
is
effectively repeated in both paragraph 5 and paragraph 9.
[8.2]
Second, paragraph 7 interdicted the Respondents from
manufacturing, marketing or selling flat wire and auger
at all
for three years. The interdict applied to any process, even one that
did not employ the Applicants’ protected information.
[8.3]
Third, if, after the three-year period ended, the Respondents
wished to manufacture flat wire for the use in auger, they could only
do so if they changed their process so it did not breach the
Applicants’ rights. This interdict is repeated twice in the
2015 Order:
[8.3.1]
Paragraph 7 provides that the Respondents must “adapt/alter
their production process so as to avoid using the First Applicant’s
confidential information”.
[8.3.2]
Paragraph 23 provides that, after the three year period “in
the event that the Respondent or any of them, directly or indirectly,
manufacture flat wire or auger, or equipment for the manufacture of
flat wire or auger, such manufacture shall not infringe on
the
confidential information or copyright of the applicants.”
[9]
The difficulty that has precipitated the
current proceedings is how to determine whether any new production
line the Respondents
establish to manufacture flat wire and auger
infringes the Applicants’ copyright or uses their confidential
information.
The parties envisaged this problem and the 2015 Order
creates a process to make this determination. It seeks to balance two
competing
concerns: permitting the Respondents to manufacture flat
wire and auger, but only if they can do so lawfully.
[10]
The process the parties agreed to is set
out in paragraph 24, which is at the centre of the current dispute,
particularly paragraph
24.5. It is necessary to set out the paragraph
in full:
24.
The determination of the Respondents’ compliance with paragraph
23 shall be as follows:
24.1
Suitably qualified experts, one appointed by the Applicants and one
appointed by the Respondents, are to
be granted access to the
proposed production facility in order to inspect the proposed
production facility and to compile a joint
report in respect of the
extent to which such production facility complies with paragraph 23
above;
24.2
The said experts are to state in the report the aspects on which they
agree and the aspects on which they
disagree;
24.3
The said report is to be handed to the Applicants and Respondents
within 5 (five) court days of it being
compiled and the Applicants
and Respondents are to submit their written comments and/or
disagreements on the said report within
5 (five) court days of so
receiving the report, to such experts.
24.4
The said experts are to file a final report within 5 (five) court
days of the expiration of the said 5(five)
day period referred to in
subparagraph 24.3 hereinabove;
24.5
In the event that the Applicants and/or the Respondents do not agree
with the final report of the experts
they shall be entitled to bring
a motivated application to Court within 5 (five) court days to have
the said final report varied
and/or corrected. The Court so hearing
the application will be entitled to determine what procedures are
necessary to determine
the application. In the event that such
application is not launched within the 5 (five) court days referred
to above, the report
shall for all intents and purposes be regarded
as final.
[11]
The
purpose of paragraph 24 is vital to resolving the current dispute.
The meaning of paragraph 24 has been considered previously
by this
Court, and the SCA (I explain why below). The SCA held that paragraph
24.5 “regulated the manner in which the [Respondents]
would be
free to resume competition with the [Applicants]”.
[1]
[12]
That is obviously correct. It serves as an
escape hatch from the interdicts in the rest of the 2015 Order. But
it also serves to
protect the Applicants. Ordinarily, the Applicants
would not be entitled to prohibit the Respondents from manufacturing
flat wire
and auger unless they could establish the Respondents were
infringing their rights. But the 2015 Order reverses that position.
It prohibits the Respondents from manufacturing until the Respondents
have established, through the paragraph 24 process, that they
can do
so lawfully. The parties agreed to that flip, presumably, because of
the Respondents’ prior dishonest and unlawful
conduct.
[13]
To complete the picture, paragraph 25
permits the Respondents to construct an auger production facility,
solely for the purposes
of the process in paragraph 24. It reads:
Notwithstanding
paragraph 7.3 above,
[2]
the
Respondents shall be entitled to construct an auger production
facility, which is, as a whole or in any of its constituent
parts,
not be sold, leased or otherwise made available to any third party,
solely for the purposes of commissioning same in terms
of what
follows below. The Respondents undertake not to commission the
proposed auger production facility until such time as the
Applicants
and Respondents are in agreement as set out in sub paragraphs 24.1 -
24.4 above or a Court has made such determination
in terms of
subparagraph 24.5 above.
[14]
‘
Commissioning’ in this context
means putting the production facility into commercial operation.
[15]
In
sum, the 2015 Order means that the Respondents cannot manufacture
flat wire or auger at all for three years. After three years,
they
can manufacture flat wire and auger only if the do so without
infringing the Applicants’ copyright or confidential
information. They can build a new production facility for the sole
purpose of proving their ability to manufacture flat wire and
auger
lawfully. Before they can put that new production facility into
commercial operation, the Applicants must go through the
process in
paragraph 24. If the parties and their experts agree the new
production facility is kosher, the Applicants can commission
it. If
not, either party can approach the Court for a ruling on whether the
Respondents’ new production facility infringes
the Applicants’
copyright and confidential. The bottom line, as the SCA explained, is
that absent agreement, “[
u]ntil
such time that a court had made a determination, the appellants would
not be entitled to commission the production facility.”
[3]
### Contempt of the 2015
Order and the 2020 Order
Contempt of the 2015
Order and the 2020 Order
[16]
The parties initially seemed to share this
understanding. The Respondents did not manufacture flat wire or auger
for the three years
after the 2015 Order. But they then indicated
that they wished to begin production, so the parties began the
paragraph 24 process
to assess whether the Respondents were able to
do so without breaching the Applicants’ rights. However, from
13 December
2018, the Respondents took the view that the 2015 Order
was unimplementable. They argued, for example, that the concession
that
the Applicants’ process was confidential had been wrongly
made in 2015. In 2019, they established a plant and proceeded to
manufacture flat wire and auger even though the paragraph 24 process
was incomplete.
[17]
Despite the Respondents resuming commercial
manufacturing, the parties continued with the paragraph 24 inspection
process of the
Respondents new production facility. Inspections were
held in August 2019. But when the Applicants’ expert – Mr
Broekhuizen
– requested further technical drawings, the
Respondents treated it as a delaying tactic, and refused to
cooperate.
[18]
In 2019, the Applicants became aware that
the Respondents had begun to sell their auger. The Second Respondent
issued an invoice
to an Egyptian company which was one of the
Applicants’ existing clients. This prompted the Applicants to
launch an urgent
application to interdict the Respondents from
breaching the 2015 Order until the paragraph 24 process was complete,
and to hold
them in contempt of court.
[19]
On 17 September 2019, two days before their
application was due to be heard, the Applicants became aware that the
Respondents had
also sold auger to a Thai company. The container of
auger was still in Cape Town, but was due to be shipped to Bangkok.
They filed
a supplementary affidavit and sought additional relief to
interdict the shipment.
[20]
The
shipment was temporarily interdicted by Myburgh AJ. But when the
application came before Sievers AJ, he struck it from the roll.
It
eventually came before Mangcu-Lockwood AJ (as she then was), who
delivered judgment in March 2020.
[4]
She dismissed the Respondents’ various challenges to the
meaning and status of the 2015 Order.
[21]
Mangcu-Lockwood
AJ concluded that the Applicants’ production processes remained
confidential and that the Respondents could
only resume production
after completing the paragraph 24 process. She rejected their
attempts to downplay the Egyptian invoice
as the Respondents admitted
they had issued it. Mangcu Lockwood AJ was “persuaded
that the respondents have not
only breached the terms of the Court
Order, but continue to do so, and in fact harbour an intention to
continue to do so.”
[5]
And she held that “the facts surrounding the Bangkok shipment
show, not only wilfulness to breach the Court Order, but also
mala
fides
on the part of the respondents” and that “the respondents
sought to mislead the court by concealing the factual circumstances
surrounding the transporting and loading of the shipment.”
[6]
[22]
Mangcu-Lockwood AJ’s order included
the following relevant terms:
1) An interim interdict
is granted in the following [terms]:
1.1
Pending the finalisation of the process provided for in paragraphs 23
to 25 of the [2015 Order],
the respondents are interdicted and
restrained from-
1.1.1 manufacturing
and/or producing flat wire for purposes of manufacturing auger;
1.1.2 manufacturing
and/or producing auger;
1.1.3 marketing for sale
and/or selling any flat wire and/or auger produced by any of the
respondents;
1.2
The respondents are restrained and interdicted from removing, causing
or permitting the removal
of any of the unlawfully produced products
from the premises situated at 6 Distillery Way, BAT Building, Paarl,
Western Cape, or
from any other premises where same may be located.
1.3
Within 5 court days of the issue of this Order, the respondents are
directed to furnish the applicants
with the addresses of all premises
where the respondents are storing the unlawfully produced products;
2) It is declared that
the respondents are in contempt of the Court Order of 2 June 2015
[7]
[23]
Paragraph 1.1 of the 2020 Order was,
techincially, unnecessary. The Respondents were already interdicted
from performing any of
those acts by the 2015 Order. It was their
refusal to accept that and their contempt of the earlier order
that necessitated
the 2020 Order.
[24]
The
Respondents appealed against the 2020 Order to the Supreme Court of
Appeal. In a unanimous judgment of Molefe AJA, it dismissed
the
appeal on the basis that the 2020 Order was interim and therefore not
appealable. It explained that the consequence of the
2020 Order was
merely to enforce the 2015 Order “
until
the process ordained in paragraph 24 is completed”.
[8]
[25]
More
importantly for present purposes, the SCA confirmed
Mangcu Lockwood AJ’s interpretation of the 2015
Order.
In clear terms, it held: “
Until
such time that a court had made a determination [in terms of
paragraph 24.5], the [Respondents] would not be entitled to
commission the production facility. Evidently, and until such time
that the process had been completed, the [Respondents’]
proposed production facility would not be put into service for the
commercial production of auger.”
[9]
### The 2020 Action
The 2020 Action
[26]
Before I can turn to the actual dispute in
this application, there is a final piece of the puzzle. In 2020,
Technical Systems launched
an action against the Respondents under
Case No. 5288/20. This 2020 Action is based on the Respondents’
alleged use of the
Applicants’ confidential information and
copyright drawings to manufacture, market and sell flat wire and
auger after the
2015 Order. The 2020 Action seeks interdicts, damages
and an order that the Respondents are in contempt.
[27]
The
Respondents have defended the 2020 Action on a range of grounds,
including several preliminary objections. In 2021, Cloete J
dismissed
a
res
judicata
exception by the Respondents.
[10]
They claimed that the issue had already been determined by the 2015
Order. Cloete J held it was inappropriate to adjudicate the
claim on
exception as the pleadings indicated the 2020 Action went beyond the
2015 claim.
[28]
A hearing of the 2020 Action is not yet
trial ready. The parties could provide no clarity on when it would
likely be heard. But
it is likely still years from trial.
###
### The Present Dispute
The Present Dispute
[29]
While the litigation that led to the 2020
Order and the subsequent appeal were ongoing, the parties continued
with the inspection
process of the Respondents’ production
facility as envisaged in paragraph 24. The two experts –
Mr Broekhuizen
for the Applicants, and Mr Bowles for the Respondents
– produced their report on 9 November 2021. The parties then
commented
as provided for in paragraph 24.3 on 16 November 2021. The
expert’s final report, taking into account the commentary, was
produced on 23 November 2021. It consists of some 988 pages. It was
filed as an attachment to this application and was, with the
agreement of the parties, made subject to a confidentiality order
dated 13 November 2023.
[30]
The experts did not agree on whether the
production facility used the Applicants’ confidential
information and copyrighted
drawings. Mr Bowles repeated the
Respondents’ consistent line – the Applicants’ did
not use a confidential manufacturing
process worthy of protection. Mr
Broekhuizen took the opposite view. Mr Broekhuizen identified
multiple instances of copyright
infringement; Mr Bowles found none.
[31]
The two views were irreconcilable and could
only be resolved by the process envisaged in paragraph 24.5 of the
2015 Order –
an application to have the experts’ report
“varied or corrected”. Paragraph 24.5 provided that
the
Court “hearing the application will be entitled to determine
what procedures are necessary to determine the application.”
I
understood this to mean that a party dissatisfied with the experts’
report would apply immediately for its variation or
correction. The
Court seized with
that
application would decide how to determine it. There would be only one
application, not two.
[32]
The Applicants took a different approach.
They launched this application on 30 November 2021. It seeks only to
deal with the prior,
procedural issue of
how
the dispute between the experts should be resolved. The Applicants
pray for an order that the experts’ dispute “be
referred
to trial to be heard
pari passu
with
the” 2020 Action. The Applicants argue that the issues to be
resolved in the 2020 Action, and the facts necessary to
resolve the
experts dispute under paragraph 24.5 will cover similar terrain. They
have already filed an expert report by Mr Broekhuizen
in the 2020
Action which they argue mirrors his findings in the Expert Report
prepared under paragraph 24.5. It will be convenient
and efficient,
they argue, for the paragraph 24.5 dispute and the 2020 Action to be
determined together.
[33]
No point would now be served by refusing to
decide this application because I am not the court deciding the
actual dispute. Having
taken one step forward, I would force the
parties to take two steps back. The same dispute before me would
arise before that Court.
And it was not a point taken by the
Respondents. I am willing to determine how the experts’
disagreement must be resolved.
[34]
The Respondents oppose the present
application. Initially, their opposition was largely technical, or
concerned with how the experts’
dispute should be resolved, not
whether it required resolution. They argued that the application
should not have been brought under
the same 2014 case number as the
2015 Order. They contended it was inappropriate to join the paragraph
24.5 proceedings to the
2020 Action. They argued that the application
was premature because, at that time, the appeal against
Mangcu-Lockwood AJ’s
2020 Order was still pending. They
contended that the Applicants had failed to state the core
jurisdictional fact for invoking
the judicial resolution process in
paragraph 24.5 – that they disagreed with the experts’
report. Finally, the Respondents
argued that the affidavit supporting
the application relied on irrelevant or inadmissible evidence.
[35]
The Applicant filed a replying affidavit
and heads of argument addressing these grounds of opposition. The
battle lines seemed drawn.
But by the time of the hearing, save for
the dispute about whether the paragraph 24.5 application should be
joined to the 2020
Action, the Respondents’ original bases of
opposition fell by the wayside.
[36]
On 23 October 2023, just 10 days before the
hearing, the Respondents brought an interlocutory application to file
an additional
affidavit. The affidavit stated that “the
respondents have abandoned their intention to use a production line
consisting
of the items of equipment which formed the subject of the
joint technical report.” Those elements of the production line
that Mr Broekhuizen objected to would “be completely redesigned
or … replaced by other machines which were purchased
on the
open market.” The Respondents would, moreover, only manufacture
flat wire and then purchase a third party machine
to convert that
into auger. The Respondents argued that, as a result, there was no
need to resolve the dispute between the experts
about a production
facility they did not intend commissioning.
[37]
The Respondents explained that they had
decided to redesign the inspected production facility for strategic
reasons. There had been
another, unrelated, trial between the parties
concerning a different product – feed chain – which had
run for 50 days
and cost tens of millions of Rands. They preferred to
avoid further, costly litigation against the Applicants and instead
sought
to develop a production facility they could use without having
to go to court. The Respondents, instead, sought an order which would
effectively restart the paragraph 24 process for their new flat wire
“production line”. The respective experts would
exchange
reports and, if they could not agree, the matter could be
re-enrolled.
[38]
The Respondents also contended that the
Applicants knew there was no longer a live dispute and ought not to
have persisted with
their application. To unravel the merits of that
submission it is, unfortunately, necessary to consider the
correspondence and
interactions between the parties:
[38.1]
On 16 May 2023, the Respondents’
attorneys wrote to the Applicants’ attorneys informing them
that the Respondents had
decided to “re-design” and
“re-engineer” their production line. They invited Mr
Broekhuizen to inspect
the new components.
[38.2]
After a follow-up letter, the Applicants’
attorneys responded on 26 May 2023. They argued that the Respondents
were unable
to manufacture auger or flat wire without breaching the
Applicants’ rights. Nonetheless, they agreed to Mr Broekhuizen
inspecting
the machines and their components. They emphasised that
this was “not an inspection as contemplated in the 2015 Order”
and that the Respondents’ intention did not affect the pending
application set down for November.
[38.3]
Further correspondence was exchanged
between the parties. It is not necessary to detail each letter.
Essentially, the Respondents
insisted that, given their intention not
to use the inspected production facility, the paragraph 24.5
application was moot. They
also indicated that they no longer
intended to manufacture auger using their own machines at all, but
only flat wire. They would
purchase a third party machine to convert
the flat wire to auger. The Applicants persisted in their position –
the Respondents’
change of plan did not remove the need for the
paragraph 24.5 application to be determined.
[38.4]
Mr Broekhuizen eventually visited the
Respondents’ premises to look at their new machines on 2 August
2023. However, the Respondents
did not hear from Mr Broekhuizen or
the Applicants thereafter. Nor did they follow up to request a
response.
[39]
The Respondents therefore took it on
themselves to bring this new information to the Court’s
attention. They argued for a
punitive costs order, or even costs
de
bonis propriis
against the Applicants’
legal representatives, for persisting with the application in the
face of the Respondents indication
they would not use the inspected
production facility.
[40]
The Applicants had a very different view of
the Respondents’ promise to abandon the inspected production
facility. They
claim that “there is no production
facility other than” the one which was subject of the expert
report. The “production
line” Mr Broekhuizen considered
on 2 August 2023 was “a shambolic collection consisting of 13
drawings of mostly bolts,
nuts and spacers, as well as shells of
machines missing virtually every essential component.” It was
not capable of producing
anything, and could not be inspected as
envisaged in paragraph 24. I note that the Respondents do not contest
that the new production
facility is incomplete and cannot, yet,
produce flat wire.
[41]
This conclusion was supported by an
affidavit from Mr Broekhuizen who set out his observations in some
detail. He explained that
it was impossible to determine from the
limited machines, and the limited drawings whether the Respondents
had designed a functional
production line. A great deal of “trial
and error” was still required. Drawings often do not work as
planned in practice,
and adjustments often have to be made to a line
before it works. According to Mr Broekhuizen, it was only “once
a production
line exists in three-dimensional format” that it
can be assessed, because it is only then that all the components can
be
said to work together. Mr Broekhuizen was “not convinced
that what [he] saw could be workable”.
[42]
The Applicants point out that the
Respondents never demanded a report from Mr Broekhuizen following the
2 August 2023 visit, and
can therefore hardly complain now that they
never received one. Mr Broekhuizen confirmed that he had never
undertaken to provide
a report.
[43]
They argue that the Respondents’ mere
“intention” not to use the existing production line could
never be a sufficient
basis for the court to decline to make a
determination under paragraph 24.5. In their view, the late
submission of the supplementary
affidavit and the
“misrepresentations” in that affidavit were part of the
same pattern of dishonest conduct. It was
merely a last minute
attempt to avoid or delay the paragraph 24.5 proceedings.
[44]
The
Respondents provided an email from their expert, Mr Bowles, to
respond to Mr Broekhuizen.
[11]
He opined that it was not for Mr Broekhuizen to assess whether the
new line was functional or not, but only to assess whether its
components violated the Applicants’ copyright or confidential
information. As most of the components had been purchased or
repurposed, they could not infringe those rights. He disagreed with
Mr Broekhuizen’s assessment of several of the components
of the
new line.
[45]
Mr Bowles also alleged that, on 2 August
2023, Mr Broekhuizen had undertaken to review the joint report and
share his comments based
on what they had seen of the new line. Mr
Broekhuizen filed a further affidavit denying this.
[46]
Although they initially opposed the
application to introduce the supplementary affidavit, at the hearing,
the Applicants abided.
But they persisted in arguing that its
contents were irrelevant, and that the Court should decide their
initial application for
this court to determine the procedure to
resolve the experts’ dispute about the inspected production
facility. They argued
that the Court had no power to vary paragraph
24 of the 2015 Order which was a final order. Even if the Court could
do so, it should
resolve the experts’ disagreement because the
Respondents mere “intent” not to use the inspected
production facility
was, in the context of their prior conduct,
insufficient to adequately protect the Applicants’ rights. They
also complain
that the Respondents have not agreed to an interdict to
prevent them from using the inspected production facility, and refuse
to
even disclose where the components of that facility are now
located (they were not at the facility Mr Broekhuizen visited in
August
2023).
[47]
The Respondents argue that this Court has
the power to vary the process in the 2015 Order. They also contend
there is no need for
a further interdict because the Applicants are
already protected by the 2015 Order which prevents them from
manufacturing using
any production facility, including the one
inspected by the experts.
### The Issues
The Issues
[48]
This application has become both far more
complicated and far more simple than it was when it began. What
should have been relatively
straightforward debate about how to
resolve the experts’ disagreement became a heated debate with
allegations of ulterior
purpose and unreasonable behaviour flying
back and forth. The history between the parties has engendered mutual
hostility and suspicion.
They are no longer able to find reasonable
solutions to what are primarily procedural problems, and so rely on
the Court to resolve
them.
[49]
Mr Myburgh SC made clear in his oral
address that the Respondents no longer persisted with the objections
in their original answering
affidavit. They limited their objections
to the consequence of their intention to abandon the inspected
production line. And the
Applicants did not oppose the admission of
the supplementary affidavits (provided the further affidavits were
also admitted).
[50]
To my mind, the case raises the following
issues:
[50.1]
Is it open to this Court to refuse to
require a determination in terms of paragraph 24.5 of the 2015 Order?
[50.2]
If it is, is it still necessary to resolve
the clash between the experts about the existing production facility?
[50.3]
If it is, what process should be followed
to resolve that dispute?
[50.4]
Who should bear the costs and at what
scale?
[51]
In short, I hold: This Court has the power
to vary paragraph 24; but it should not exercise that power because
the Respondents cannot
be trusted; the experts quarrel should be
resolved separately from the 2020 Action; there should be no costs in
the interlocutory
application; and the Respondents should pay 50% of
the Applicants’ costs on an ordinary scale.
### The Power to Vary Orders
The Power to Vary Orders
[52]
The Applicants argued that the 2015 Order
was a final order and that this Court therefore had no power to
depart from it. Its only
role, Ms Robinson SC urged me, was to decide
what process should be employed to resolve the experts’
dispute. Even if the
Court accepted that the Respondents did not
intend to use the inspected production facility, it had no power to
depart from the
course already laid out for the resolution of a
dispute about that facility.
[53]
I
do not agree that this Court lacks the necessary power. The general
rule is that once a court makes an order, it cannot alter
its order.
This principle is vital to maintain the rule of law and certainty in
legal proceedings.
[12]
[54]
But
the general rule admits of certain exceptions. One of those is that
courts have the power to alter interlocutory or procedural
orders.
[13]
A court can alter those orders on good cause shown. The rationale for
permitting variation of interlocutory orders is that they
“do
not dispose of any issue or any portion of the issue in the main
action.”
[14]
So, for example, in
Sandell
Hoexter
J declined to give effect to an earlier order by a different judge
referring a dispute to oral evidence.
[15]
By the time the matter was argued before him, the referral was no
longer appropriate as “voluminous” affidavits had
been
filed and it would “inevitably result in a trial within a
trial, and a protracted and elaborate one to boot.”
[16]
[55]
While
courts have the power to vary these orders, “a Court will not
lightly exercise such a power.”
[17]
An invitation to alter even an interlocutory order should be
approached with “considerable diffidence.”
[18]
[56]
This seems right. Parties will regulate
their affairs based even on interlocutory or procedural directions.
That is certainly the
case here. A court should only depart from
procedural orders when the circumstances justifying those orders have
fundamentally
changed, where a party relies on the interlocutory
order to abuse the court’s process, or where the interests of
justice
otherwise demand it.
[57]
The next question is whether paragraph 24
generally, and paragraph 24.5 in particular, is an interlocutory
order that can be varied.
It plainly is. In 2015 the parties
envisaged that the Respondents may, after the three years were up,
seek to again manufacture
flat wire and auger. They agreed that the
Respondents would only be lawfully permitted to do so if they could
demonstrate that
they would do so without infringing the Applicants’
rights. Paragraph 24 determines the
process
for resolving that anticipated dispute. It does not finally determine
(nor could it) whether any new production line infringes
any of the
Applicants’ rights.
[58]
My view is fortified by the holding of the
Supreme Court of Appeal. It concluded that paragraph 1.3 of the 2020
Order was interim
in nature and therefore unappealable. That
paragraph interdicted the Respondents from “marketing for sale
and/or selling
any flat wire and/or auger produced by any of the
respondents” until “the finalisation of the process
provided for
in paragraphs 23 to 25 of the” 2015 Order. If that
interdict is interim, then surely so is the order regulating the
process
for how it might be lifted.
[59]
That is not the case for all parts of the
2015 Order. The three-year interdict, and the interdict on using the
Applicants’
copyrighted or confidential information are all
final in form and effect. But paragraph 24.5 is different. It sets a
process to
decide a process, it does not determine a substantive
right. It is within this Court’s power to determine that that
process
is no longer fit for purpose, is being abused, will have
negative consequences unforeseen at the time it was made, and should
be
altered.
### Paragraph 24.5 Should not
be Varied
Paragraph 24.5 Should not
be Varied
[60]
This Court has the power to vary paragraph
24. But should it? There are two fundamental considerations.
[61]
First
,
until a production line is approved through a paragraph 24 process,
the Respondents may not commission a production facility to
manufacture flat wire or auger
at all
,
even if the facility made no use of the Applicants’
intellectual property. That is the consequence of the interdict in
paragraph 25 read with paragraph 24. From a strictly legal
perspective, it is in the Respondents’ interest to complete a
paragraph 24 process because, until they do, they cannot legally
commission a production line. Even if their production line does
not
infringe any of the Applicants’ rights, until they convince the
Applicants’ expert or a court, they are prohibited
from
manufacturing.
[62]
From this formal perspective, there is no
need for the Applicants to insist on the completion of the paragraph
24 process. If the
process is abandoned without a final determination
– as the Respondents seek – they Applicants are no worse
off. The
Respondents will remain interdicted from commissioning a
production facility. There is no obvious legal advantage to the
Applicants
having a judicial determination on the legality of a
production line that the Respondents will not use.
[63]
But all this assumes the Respondents will
be honest, comply with the 2015 Order, and not again infringe the
Applicants’ rights.
That leads to the
second
fundamental consideration: The history of this matter demonstrates
that the Respondents cannot be trusted. Their deceit began with
the
unlawful use of the Applicants’ confidential information and
copyrighted drawings. It continued with trying to conceal
that
illegality, which was discovered only by subpoenaing third parties.
It was reproduced in 2019 when they produced and sold
products in
naked contempt of the 2015 Order, and “
sought
to mislead the court” about their activities
.
[64]
Even now, the Respondents have stated their
intention not to use the inspected production line. But they have
given no undertaking
not to do so. They will not agree to an
interdict prohibiting them from using that line. They will not reveal
where the components
of that line are located. They say they will
only now manufacture flat wire, but intend to manufacture auger in
the future, while
remaining in possession of a production facility to
convert flat wire into auger which the Applicants allege infringes
their rights.
As Mr Broekhuizen explains, even if the new production
facility uses none of the elements he found objectionable previously,
it
may not work without re introducing those offensive parts.
[65]
This is not the conduct of a party can be
trusted not to take advantage of any lingering uncertainty in the
future. As Ms Robinson
SC put it, the Respondents’ case “hinges
on a gossamer web of intention of proven liars”. I agree.
[66]
Absent the Respondents’ history of
dishonest and contemptuous conduct, I would likely have decided that
no purpose would be
served by allowing the Applicants to pursue the
paragraph 24.5 process for the inspected production facility. It
would be an abuse
of that process to achieve an end it never
intended. But it seems to me there is a real risk that the
Respondents will seek to
take advantage of the continued dispute
about whether they can lawfully use that line or not. How they might
do so is unclear.
But the Applicants’ fear that they will do so
is, to my mind, reasonable. And it would be allayed by this Court
determining
the legality of the facility under paragraph 24.5, as the
parties agreed eight years ago.
[67]
Resolving the disputes between Mr
Broekhuizen and Mr Bowles will cause both sides considerable expense.
But it lies in the Respondents’
own hands to avoid that
expense. They need merely grant an unequivocal undertaking not to use
the inspected production line in
that form, and agree to the
Applicants having that undertaking made an order of court. In those
very different circumstances, no
purpose could possibly be served by
resolving what would be a truly academic dispute. If they really have
no intention to use that
production facility, they lose nothing by
agreeing to such an order. But until the Respondents are willing to
assuage the reasonable
risk that exists, there is no sufficient
reason to depart from the protection paragraph 24.5 affords the
Applicants.
[68]
In sum: while the Applicants’ primary
legal interests are protected by paragraph 25, for so long as there
is a risk the Respondents
will use all or part of the inspected
production facility, the Applicants have an interest in a judicial
determination of whether
that use would be lawful. To avoid that, the
Respondents can agree to an interdict prohibiting the use of the
inspected production
facility. Once they have completed a new
production facility that works, it can be inspected. If the parties
and their experts
cannot agree on whether it is lawful, one would
hope they would agree to referral to court along lines similar to
what I order,
without another application to define the process.
[69]
Given that conclusion, it is not necessary
to consider the alternative to the paragraph 24.5 process proposed by
the Respondents.
But it may aid the parties, and hopefully limit
future disputes, to point out why it was inappropriate.
[70]
In a draft order attached to their
supplementary affidavit, the Respondents sought an order that
generally mirrored the process
in paragraph 24.5, starting with
requiring Mr Broekhuizen to file a supplementary report based on his
evaluation of the new production
line. At the hearing, Mr Myburgh SC
handed up a revised draft order. This began by treating Mr
Broekhuizen’s affidavit filed
in response to the Respondents’
supplementary affidavit as a “supplementary report” which
he could then further
supplement. The experts would then meet and
produce a joint report identifying areas of agreement and
disagreement. What would
follow is an iterative process where the
experts would examine each element of the production facility in turn
to seek agreement
that it does not violate the Applicants’
rights. If the experts could not reach agreement, either party could
refer the matter
to the Court for hearing.
[71]
There are three problems with the proposal.
[72]
First
, it
is inconsistent with paragraph 24. Paragraph 24.1 requires the
parties to appoint experts to “inspect the proposed production
facility”. I agree with the Applicants that the Respondents
must identify a complete production facility, and then make it
available for inspection. Paragraph 24 does not envisage piecemeal
inspection of each element of a production facility. As Mr
Broekhuizen explained, it is only when the facility is complete that
it is worthwhile inspecting it. Until then, there is no guarantee
that each piece in the puzzle will fit, and that the line as a whole
will work. Parts that work in isolation may need to be modified
to
work together. They will need to be re-inspected after alteration to
again ensure they do not violate the Applicants’
rights. This
would be an inefficient and tedious process.
[73]
Second
,
the Respondents’ proposed order rests on treating Mr
Broekhuizen’s affidavit as a report following an inspection in
terms of paragraph 24.1. But it was not an inspection. Not only did
the Applicants’ attorneys repeatedly make clear that
they were
not agreeing to an inspection, there was no “production
facility” to inspect. Unless there is a complete
production
facility that produces flat wire and/or auger, there can be no
inspection under paragraph 24.
[74]
Third
,
it is not the Applicants’ task to advise the Respondents on how
not to violate their rights. Ms Robinson SC referred me
to a
passing-off case:
Weber-Stephen
Products
.
[19]
EM Grosskopf JA endorsed the finding of an English court in a
decision concerning lemon juice containers: “[I]t is not for
the Court to tell the defendant how to solve the difficulty, or
indeed in my judgment even to consider whether the difficulty can
be
solved.”
[20]
By analogy, it was argued that it is not for the Applicants’
expert to tell the Respondents how to avoid infringing their
rights;
it is for the Respondents to present a production line and for the
experts – or ultimately the Court – to determine
whether
it violates the Applicants’ rights.
[75]
I agree. The violation originally conceded
in the 2015 Order was not limited to any particular machine, but to
the process of manufacturing
flat wire and auger. The Respondents
must devise a “production facility” that they will use to
manufacture flat wire
and auger that does not infringe any of the
Applicants’ rights. They can either do that or they cannot. But
it is not for
the Applicants to assist them to achieve that goal by
checking their process at each step along the way.
[76]
Accordingly, the only way for the
Respondents to lawfully manufacture flat wire or auger is to design
and build a “production
facility” that can in fact do
that, and then to subject that production facility to the paragraph
24 process. That is what
it agreed to. It may now seem onerous. But
that is no reason to depart from the 2015 Order.
###
### A Separate Process is
Appropriate
A Separate Process is
Appropriate
[77]
There were two options for how to resolve
the experts’ dispute about the inspected production facility:
join it to the 2020
Action; or refer it for separate resolution
through oral evidence.
[78]
There are pros and cons to both options.
[79]
In favour of separate referral, the dispute
between the experts is largely ready for hearing, and the issues will
be confined. There
is unlikely to be a need for discovery beyond what
is already in the lengthy joint report. By contrast, I was informed
that the
2020 Action is not ready for hearing, and it is unclear when
it will be. Even after the determination of the exception, there are
a range of preliminary disputes that may need to be resolved before
the merits of the action can be determined. Linking the one
to the
other will mean that the paragraph 24 dispute can only be resolved
when the 2020 Action is ready for determination. It may
be that the
2020 Action is never determined on the merits, because one of the
Respondents’ preliminary defences succeeds.
What then would
happen to the paragraph 24.5 issue that had been conjoined to the
2020 Action?
[80]
The Respondents have, for strategic
reasons, indicated they do not wish to use the inspected production
facility. That assessment
may change in light of this judgment. If it
does, the dispute should be resolved as quickly as possible. If Mr
Bowles is right
and the existing production line is lawful, the
Respondents should be allowed to commission it as soon as possible,
without also
needing to resolve the 2020 Action. Linking the two
would unfairly disadvantage the Respondents.
[81]
On the other hand, there are factors that
favour conjoining. There is likely to be a fair degree of overlap
between the issues.
It is not clear to me whether the production
facility that the Applicants allege the Respondents used to produce
flat wire and
auger was identical to the one the experts inspected.
Even if it was not, there will likely be significant similarities.
The testimony
of Mr Broekhuizen and Mr Bowles would be substantially
similar in both cases.
[82]
But, while there would undoubtedly be an
overlap, there may also be differences. The testimony in the
paragraph 24.5 dispute will
be limited to the joint report, whereas
the 2020 Action is more wide-ranging. The Respondents may or may not
choose to call Mr
Bowles in the 2020 Action, but joining the two
would effectively force them to do so.
[83]
There is also a risk that referring the
paragraph 24 dispute to separate adjudication would result in two
courts considering the
same issues of fact and law, and possibly
reach conflicting results. That may occur. Or it may not. If it does,
the latter court
(probably the one deciding the 2020 Action) will
need to determine how to deal with the earlier findings. It is only a
possibility
and, even if it occurs, it is not an insuperable problem.
[84]
It is impossible to look into the future
and determine exactly how each option will play out. Ultimately, I
take the view that separate
adjudication is more appropriate. It
seems almost certain that linking the two matters will delay the
resolution of the paragraph
24.5 dispute. The downsides of linking
the two involve predictions that may or may not play out. I prefer to
dodge the definite
downside, rather than avoid anticipated obstacles.
[85]
At the hearing Ms Robinson SC, undertook to
prepare a draft order reflecting the terms of a referral for separate
adjudication if
I determined that was appropriate. The Applicants
submitted such a draft order. The Respondents made no specific
objections. The
order I make tracks that draft.
[86]
I emphasise two elements of my order that I
have amended from the draft:
[86.1]
It endorses a semi-urgent hearing of the
matter. The urgency arises from the need to give the Respondents the
“green light”
to re-commence their operations. I accept
that they may not wish to have a final determination on the inspected
production facility.
But then they need just agree to an interdict
prohibiting its use, complete the new production facility, and
subject it to inspection.
[86.2]
It permits the parties by agreement, or the
Court that is seized with the merits of the experts’ dispute,
to alter the procedure.
It may become necessary to introduce other
elements of the ordinary rules for trials in order to resolve the
dispute. This procedural
order is intended to enable, not
straightjacket the parties or the future Court.
### Conclusion and Costs
Conclusion and Costs
[87]
That leaves costs. Both sides sought
punitive costs against the other. The Respondents argued the
Applicants were at fault for not
informing the Court of their intent
not to use the inspected production facility, and for persisting with
the application. The
Applicants argued the Respondents’
last-minute attempt to derail their application warranted a special
costs award.
[88]
As my judgment explains, the Applicants
were entirely entitled to persist with the application,
notwithstanding the Respondents’
approach. At the same time,
while it was late, it was not inappropriate for the Respondents to
introduce the new evidence which
was admitted and was necessary to
properly adjudicate the dispute.
[89]
I do not accept the Respondents’
criticism that it was incumbent on the Applicants to inform the Court
about the Respondents’
supposed change of heart. There was no
correspondence between the parties after August 2023. There was no
demand for a report from
Mr Broekhuizen, nor any demand that the
Applicants abandon the application. There is no reason the
Applicants, rather than the
Respondents, were obliged to notify the
Court of the developments.
[90]
The Applicants have been partly successful
– they have secured a process for the determination of their
dispute. But the Respondents
were successful in resisting tying it to
the 2020 Action.
[91]
I considered that costs should stand over
for determination when the merits of the paragraph 24.5 dispute are
decided. But that
may not occur. In my view, the Applicants have
achieved greater success than the Respondents. My order requires the
Respondents
to pay 50% of the Applicants’ costs on the ordinary
scale. That should not include the application to introduce further
evidence.
I granted that application. Although the Applicants opposed
the application, and then consented, their opposition was never
primarily
directed at admission of the new evidence, but the
consequences of the new evidence. They have been successful in
resisting what
the Respondents sought to achieve in introducing that
evidence. And they would have been entitled to file an answer to the
new
affidavit, even if they had not opposed its admission.
[92]
Accordingly, I make the following order:
1.
All the supplementary affidavits filed by
the parties are admitted. There is no order as to costs in the
Respondents’ application
to introduce further evidence.
2.
The determination of the disputes and
difference of opinion evident from the report of Messrs Nicolaas
Theodorus Broekhuizen and
Helmut Bowles (
the
Report
) prepared pursuant to paragraphs
24.1 to 24.4 of this Court’s order of 2 June 2014, is referred
to oral evidence as envisaged
in paragraph 24.5 of that order, on a
semi-urgent date to be determined in consultation with the Acting
Judge President and the
Registrar of this Court.
3.
Subject to paragraph 4, the following
procedures shall apply to the determination by oral evidence:
3.1.
To the extent that any party intends to
rely on a document which does not form part of the Report, such party
is required to make
discovery on oath of those documents within one
month of this Order.
3.2.
Such discovery shall be made in accordance
with Rule 35 and the provisions of that Rule with regard to the
inspection and production
of documents discovered shall apply.
3.3.
Subject to what is stated below, the oral
evidence shall be that of Messrs Broekhuizen and Bowles.
3.4.
A party shall not be entitled to call any
witness other than Messrs Broekhuizen or Bowles unless a witness
statement, setting out
the evidence in question, has been filed by
the parties in respect of such witness at least eight weeks before
the hearing of the
oral evidence. In response to any witness
statement, each party may file a witness statement of further
evidence to be led at least
four weeks before the hearing of oral
evidence.
3.5.
A party shall not be entitled to call any
expert witness other than Messrs Broekhuizen or Bowles, unless such
party has filed:
3.5.1.
A notice as contemplated in Uniform Rule
36(9)(a), not later than 30 days from the date of this Order; and
3.5.2.
A summary of the expert’s opinion and
reasons as contemplated in Uniform Rule 36(9)(b) not later than
forty five days
from the date of this Order.
3.6.
Notwithstanding paragraph 3.4 above, the
Court may, at the hearing, on good cause shown permit a person to be
called despite the
fact that no statement has been served in respect
of his or her evidence.
3.7.
Either party may subpoena a person to give
evidence at the hearing whether or not such person has consented to
furnish a statement.
3.8.
The fact that a party has served a witness
statement or subpoenad a witness shall not oblige such a party to
call the witness concerned.
3.9.
If a deponent or witness is not called to
testify, the affidavit or statement of such deponent or witness shall
be disregarded in
the determination of the issues referred to oral
evidence.
3.10.
Witnesses called by the parties may be
examined and cross-examined with a view to resolving any factual
differences.
4.
The parties may agree to any departure or
addition to the above procedures. The Court hearing oral evidence
shall not be limited
to the procedures in this order, and will be
entitled to amend them if it considers it necessary to resolve the
dispute.
5.
The Respondents shall pay 50% of the
Applicants’ costs.
M
J BISHOP
Acting
Judge of the High Court
Counsel
for Applicants:
Adv
RM Robinson SC
Attorneys
for Applicants
De
Swart & Associates Inc t/a SWART Attorneys
Counsel
for Respondents:
Adv
GS Myburgh SC
Attorneys
for Respondents
Faure
and Faure Inc
[1]
RTS
Industries and Others v Technical Systems (Pty) Ltd and Another
[2022] ZASCA 64
at para 7.
[2]
Paragraph 7.3 reads: “Notwithstanding the provisions of
prayers 5 and 6 above, the Respondents, for a period of 3 (three)
years from the date of the granting this order, are interdicted and
restrained from: … 7.3 Manufacturing and/or producing
and/or
being involved in the manufacturing and/or production, whether
directly or indirectly and whether as proprietors, employees,
consultants, agents, members, directors or in any other capacity
whatsoever, of auger coiling machinery and/or parts or components
thereof or any business doing same.”
[3]
RTS
Industries
at
para 8.
[4]
Technical
Systems (Pty) Ltd and Another v RTS Industries and Others
[2020] ZAWCHC 69.
[5]
Ibid at para 32.
[6]
Ibid at para 52.
[7]
According to the SCA, the Applicants abandoned paragraph 2 of the
2020 Order.
RTS
Industries
(n
1 above) at para 25. I am not sure what that means. A finding of
contempt is made by the Court to assert its own authority.
It cannot
be abandoned by a party. It declares a state of affairs, without on
its own affording any rights to another litigant.
Fortunately, the
consequence of this “abandonment” does not arise in this
application, so I need make no decision
about its competence or
effect.
[8]
RTS
Industries
(n
1 above) at para 29.
[9]
Ibid at para 8.
[10]
Technical
Systems (Pty) Ltd v RTS Industries and Others
[2021] ZAWCHC 35.
[11]
No affidavit was provided because Mr Broekhuizen was out of the
country. I am willing to consider the contents of Mr Bowles’
email.
[12]
See, for example,
Zondi
v Member of the Executive Council for Traditional and Local
Government Affairs and Others
[2005] ZACC 18
;
2006 (3) SA 1
(CC);
2006 (3) BCLR 423
(CC) at para
27.
[13]
See
South
Cape Corporation (Pty) Ltd v Engineering Management Services (Pty)
Ltd
1977
(3) SA 534
(A) at 551H-552A.
[14]
Zondi
(n 12
above) at para 30.
[15]
Sandell
and Others v Jacobs and Another
1970 (4) SA 630 (SWA).
[16]
Ibid at 634F.
[17]
Ibid at 634D.
[18]
Ibid.
[19]
Weber-Stephen
Products Co v Alrite Engineering (Pty) Ltd And Others
1992 (2) SA 489 (A).
[20]
Reckitt
& Colman Products Ltd v Borden Inc and Others (No
3)
[1987] FSR 505
at 515, quoted in
Weber-Stephen
at
501B.
sino noindex
make_database footer start
Similar Cases
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2025] ZAWCHC 292 (14 July 2025)
[2025] ZAWCHC 292High Court of South Africa (Western Cape Division)100% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)100% similar
South African Legal Practice Council v Nonxuba and Another (16777/2023) [2024] ZAWCHC 410 (4 December 2024)
[2024] ZAWCHC 410High Court of South Africa (Western Cape Division)99% similar
South African Legal Practice Council v Gonzales (1949/2024) [2024] ZAWCHC 412 (6 December 2024)
[2024] ZAWCHC 412High Court of South Africa (Western Cape Division)99% similar
Technical systems v Feed Chain Industries and Others (7235/2017) [2024] ZAWCHC 204 (29 July 2024)
[2024] ZAWCHC 204High Court of South Africa (Western Cape Division)99% similar