Case Law[2024] ZAWCHC 275South Africa
Asante Body Corporate v Portland Beleggings (Pty) Ltd and Another (14495/2023) [2024] ZAWCHC 275 (20 September 2024)
Headnotes
an excipient has the duty to persuade the court that on every reasonable interpretation
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 275
|
Noteup
|
LawCite
sino index
## Asante Body Corporate v Portland Beleggings (Pty) Ltd and Another (14495/2023) [2024] ZAWCHC 275 (20 September 2024)
Asante Body Corporate v Portland Beleggings (Pty) Ltd and Another (14495/2023) [2024] ZAWCHC 275 (20 September 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_275.html
sino date 20 September 2024
IN THE HIGH COURT OF
SOUTH AFRICA
(WESTERN CAPE
DIVISION, CAPE TOWN)
CASE NO: 14495/2023
In the matter between:
ASANTE BODY
CORPORATE
Plaintiff
(SS: 231/2019)
and
PORTLAND BELEGGINGS
(PTY) LTD
First Defendant
(Registration no.
2008/001357/07)
REMEY CONSTRUCTION
(PTY) LTD
Second Defendant
(Registration no.
2000/007960/07)
Coram: Parker, AJ
Matter heard on Friday 30
August 2024
Judgment delivered on
Friday 20 September 2024
, electronically b
y
circulation to the parties’ representatives via email.
JUDGMENT
PARKER,
AJ
Introduction
[1]
This is a delictual action for damages wherein the First Defendant
has raised an exception
after it was put under a bar by Plaintiff,
alleging that the Plaintiff has failed to plead sufficient facts to
sustain a cause
of action against it. The claim by the Plaintiff is
for pure economic loss emanating from a construction to a residential
sectional
title scheme, known as Asante “
the scheme
”
which manifested defects in the common property of the scheme.
[2]
According to Plaintiff, First Defendant was responsible for the
development of the
scheme including the design and construction, had
a legal duty to guard against causing the losses that confront the
Plaintiff
in its failure to discharge the duty, First Defendant is
liable for damages quantified with the reference to the cost of
repairing
the common property in the sum of R3 122 410.00 being
Plaintiffs reasonable and necessary costs of attending to the
defects.
[3]
According to Plaintiff the Second defendant is a building contractor
who was appointed
by the First Defendant to construct the scheme.
Plaintiff has withdrawn its claim and action against the Second
Defendant.
The
exception
[4]
At the outset I need to mention that the exception did not contain
relief to allow
Plaintiff to remove the cause of the complaint. The
First Defendant attacks clauses 5, 6, 7, 11 and 13 of the Plaintiff’s
Particulars of Claim (“POC”) and has raised three
exceptions, namely
4.1
Plaintiff failed to provide sufficient facts to sustain the legal
conclusion that the First
Defendant’s alleged conduct was
negligent and wrongful and that it caused damages.
4.2
The Plaintiff is said to have failed to give sufficient facts to
sustain the legal conclusion
that the First Defendant was responsible
for developing the scheme including the design and construction and
that it owed it a
legal duty to Plaintiff.
4.3
The Plaintiff is said to have failed to sustain the conclusion that
the reasonable and necessary costs
of attending to the defects are
the damages for which Plaintiff contends.
The
legal principles
[5]
In
Theunissen
v Transvaalse Lewendehawe Koop Bpk
,
the Supreme Court of Appeal (SCA) has held that an excipient has the
duty to persuade the court that on every reasonable interpretation
the impugned pleading does not disclose a cause of action.
[1]
An excipient must show that the Plaintiff’s claim is-not may
be- bad in law having a regard to the allegations made in the
particulars of claim and any other document upon which the
Plaintiff's claim is based.
[2]
It is trite that a party has to plead – with sufficient clarity
and particularity – the material facts upon which he
relied for
the conclusion of law he wishes the Court to draw from those
facts.
[3]
It is not sufficient,
therefore, to plead a conclusion of law without pleading the material
facts giving rise to it.
[4]
[6]
It has been quoted in a plethora of case law following
Telematrix
that exceptions are a useful mechanism to weed out cases without
legal merit however they should not be approached in an overly
technical manner but dealt with sensibly.
[5]
[7]
Thus the court should not be looking at the pleading with a
magnifying glass of too
high a power, for it is the duty of the court
when an exception is taken to see if there is a point of law which
will dispose of
the case in whole or in part. The judgment by Van
Heerden J (as she then was) in
South
African National Parks v Ras
[6]
is instructive:
“
The court
should not look at a pleading with a magnifying glass of too high a
power. It is the duty of the court when an exception
is taken to a
pleading first to see if there is a point of law to be decided which
will dispose of the case in whole or in part.
If there is not, then
it must see if there is embarrassment which is real as a result of
the faults in the pleadings to which exception
is taken. Unless the
excipient can satisfy the court that there is such a point of law or
such real embarrassment the exception
should be dismissed.”
[8]
It follows that an excipient is required to show that the Plaintiff
has not pleaded
a cognizable or sustainable case. In order to succeed
with a no cause of action exception, the exception must persuade the
court
that upon every interpretation of the particulars of claim as
formulated can reasonably be that no cause of action is disclosed.
In
McKenzie
v Farmer’ Co-operative Meat Industries Ltd
[7]
“…
every
fact which it would be necessary for the plaintiff to prove, if the
traversed, in order to support his right to the judgment
of the
court. It does not comprise every piece of evidence which is
necessary to prove each fact, but every fact which is necessary
to be
proved.”
[9]
It is not sufficient therefore to raise a point of law without giving
rise to it if
the alleged complaint is merely arguable or can be
cured by the furnishing of particulars then it is appropriate to
dismiss the
exception. This means, that and excipient must make out a
clear and strong case before it should be allowed to succeed.
Pure
economic loss
[10]
Pure economic loss denote loss that does not arise directly from the
damage to the Plaintiff’s
person or property but rather in
consequence of the negligent act itself such as loss of profit, being
put to extra expenses or
the diminution in the value of the
property.
[8]
[11]
Thus, since Plaintiff’s claim is based on delict, the Plaintiff
is required to plead all
the elements of delict that being conduct,
negligence or fault, wrongfulness, causation and the loss suffered.
[12]
With the negligent causation of pure economic loss, the act or
mission is not
prima
facie
wrongful – more is needed.
[9]
Accordingly, a Plaintiff suing for the recovery of pure economic
loss, is in no position to rely on an inference of wrongfulness
flowing from an allegation of physical damage to property (or injury
to person), because the negligent causation of pure economic
loss is
prima
facie
not wrongful in the delictual sense and does not give rise to
liability for damages unless policy considerations require that the
Plaintiff should be recompensed by the Defendant for the loss
suffered.
[13]
Turning to wrongfulness, according to the First Defendant, Plaintiff
merely alleged wrongfulness
in its POC and that the First Defendant
had a legal duty not to cause such harm or loss. In this regard if
Plaintiff alleges that
First Defendant was negligent, it failed in
setting out the nature of conduct of the First Defendant was, in
addition wrongful.
[14]
Where liability is indeterminate, the SCA has warned against imposing
delictual liability in
instances where there is not a contractual
relationship between the parties due to the danger of indeterminate
liability.
[10]
What the
Plaintiff alleges is that the First Defendant knew, or ought to have
known that the negligence as aforesaid may result
in the defects
which were reasonably foreseeable.
[11]
[15]
As to the foreseeability of the harm, First Defendant submits that
Plaintiff’s POC is expiable
in that it does not meet the
allegations necessary to establish a delictual claim for pure
economic loss,
[12]
AB
Ventures Ltd v Siemens Ltd
:
“
Wrongfulness
functions in practice to distinguish cases in which there is
liability for negligence, from cases in which there is
no liability
for negligence. If such conduct is wrongful, the claim will succeed,
if such conduct is not wrongful, the claim will
fail. Wrongfulness is
incapable of performing its only practical function, which is to
distinguish cases of negligence from one
another, if its attributes
are the features of negligence. Thus, the fact, that a reasonable
person would have foreseen the harm,
or that a reasonable person
would have guarded against the harm, cannot be the measure of
wrongfulness.”
[16]
At paragraph 8 of the POC, the Plaintiff alleges that the First
Defendant owed the Plaintiff
a “
legal
duty to guard against defects, which duty the First Defendant
negligently and wrongfully breached”
.
According to First Defendant and the case law it relied upon, if
wrongfulness cannot naturally be inferred from the nature of
the
loss, which will certainly be the case where the Plaintiff’s
claim for loss resulting from an omission or for pure economic
loss
(both of which apply in the present scenario), the First Defendant’s
legal duty towards the plaintiff must be “
defined”
and the “
breach”
alleged.
[13]
[17]
On close scrutiny of the POC, Plaintiff does not adequately allege a
legal duty owed to the Plaintiff
by the First Defendant and instead
as argued by First Defendant, makes a bald legal conclusion regarding
the existence of such
duty.
[18]
First Defendant in its heads of argument is of the view that
Plaintiff made allegations that
First Defendant was under a duty of
care which itself is insufficient because the existence of a duty to
prevent loss is a conclusion
of law which depends on the
circumstances of the case particularly that which Plaintiff had
pleaded at paragraph 17 of POC being
“
The Plaintiff’s
damages are quantified with reference to the reasonable and necessary
costs of attending to the defects”
.
[19]
Much was made of the First Defendant’s failure to appreciate
the implications of the nature
of the Plaintiff’s claim and the
basis on which it relies for the reasonable costs of “
attending
to the defects”
. The Plaintiff sues in delict. As such, and
all else being equal, it seeks to be put in the position in which it
would have been
in had the delict not been committed. The measure of
damages the Plaintiff relies upon to quantify it’s loss is,
essentially,
the cost of repairs. Plaintiff says that is quite
permissible. Furthermore, that it need not plead or prove that it
actually paid
or intends paying the claimed amount (or any amount). I
do not agree. On the contrary, First Defendant needed more
particulars
to support this claim for damages.
[20]
Plaintiff misconstrues what the First Defendant is alleging. What the
First Defendant is excepting
to, is that the Plaintiff need to plead
sufficient facts to sustain the cause of action which in their view
is not apparent from
the POC. Plaintiff remains firm that the
Exception as raised is the language of a vague-and-embarrassing
exception, not a no-cause-of-action
exception. Moreover, argues that
the First Defendant seeks to particularise it’s new complaint
with reference to considerations
that are irrelevant to the
Plaintiff’s cause of action, such as “
When exactly”
the scheme was built and “
how
” the Defendant’s
came to design the scheme. This, says the Plaintiff is for trial.
[21]
Moving to wrongfulness, First Defendant states it is of no assistance
to the Plaintiff to merely
allege wrongfulness in it’s POC and
that the First Defendant had a legal duty not to cause such harm or
loss, without setting
a basis for it.
[22]
First Defendant argue that most of the complaints levelled against it
are repeated against the
Second Defendant, however the action against
Second Defendant has been withdrawn. Furthermore, that Plaintiff has
not pleaded sufficient
facts or any facts at all, to sustain the
conclusion that the First Defendant was responsible for the
development of the scheme
including the design and construction.
Damages
[23]
According to the First Defendant the POC, do not contain any facts to
sustain the conclusion
that the reasonable and necessary costs of
repair to rectify the defects or damage suffered by the Plaintiff.
The Plaintiff must
allege and prove the extent of the loss suffered
as a result of the unlawful conduct.
[24]
First Defendant relied on Rule 18(10) states that
:
“
A plaintiff
suing for damages shall set them out in such a manner as will enable
the defendant reasonably to assess the quantum
thereof’
[25]
The object of Rule 18(10) is that the plaintiff should provide the
First Defendant with reasonably
sufficient information to enable it
to assess the quantum of the claim and to make a reasonable tender or
payment into court which,
upon acceptance, will bring the litigation
to an end.
[14]
[26]
In its POC, the Plaintiff fails to prove that it has suffered any
damage and has failed to set
out the quantum thereof or provide any
proof, to enable the First Defendant to reasonably assess the quantum
thereof.
Conclusion
[27]
It is so that the POC do not contain sufficient averments that would
justify the extension of
the aquillian liability to cover a claim for
pure economic loss for breach of the alleged legal duty as alleged by
the Plaintiff.
[28]
Whilst it is so that certain facts are plainly matters for evidence,
I disagree that what Plaintiff
has pleaded is sufficient, as material
facts have not been pleaded sufficiently to sustain a cause of action
and in the circumstances
fails to disclose vital
facta probanda
to sustain a cause of action against the First Defendant.
[29]
In instances where substantial exceptions against POC are upheld on
the basis that the pleadings
concerned are bad in law, an invariable
rule of practice has been adopted by our Courts, to order that the
pleadings be set aside
to allow the party whose pleadings is struck
down an opportunity to amend.
[15]
The First Defendant, from the wording of the exception, shows no
indication that the First Defendant requested Plaintiff to consider
an amendment.
[30]
As for costs, this was not a complex matter warranting an award of
fees higher than scale A.
[31]
In the circumstances, having duly considered that arguments it is
ordered that:
a. The
First Defendant’s exception is upheld.
b. The
Plaintiff is given leave to deliver its amended Particulars of Claim
within 10 (ten) days from the date
of this order.
c. The
Plaintiff is to pay the cost of this exception, such costs to include
the costs of counsel where so employed
on scale A.
R
K PARKER
ACTING
JUDGE OF THE HIGH COURT
Appearances:
Counsel
for Plaintiff
:
Adv. CJ Quinn
Instructing
Attorney
:
Rianna Willemse Solms Inc. – Ms R Solms
c/o
De Klerk en Van Gend Inc
Counsel
for First Defendant
:
Adv. PJ Rabie
Instructing
Attorney
:
Bornman & Hayward Inc – Mr JH Meyer
c/o
Walkers Inc
[1]
Theunissen
v Transvaalse Lewendehawe Koop Bpk
1988
(2) SA 493
(A) at 500 E – F.
[2]
Vermeulen
v Goose Valley Investments (Pty) Ltd
[2001] 3 All SA 350
(A) at para [7].
[3]
Mabaso
v Felix
1981 (3) SA 865
(A) at 875 A-H; Rule 18 (4))
[4]
Radebe
and Others v Eastern Transvaal Development Board
1988
(2) SA 785
(A) at 792 J-793G.
[5]
Telematrix
(Pty) Ltd t/a Matric Vehicle Tracking v Advertising Standards
Authority SA
2006
(1) SA 461
(SCA) at 465H.
[6]
South
African National Parks v Ras
2002 (2) SA 537
(C)
21
at 541 J-542A.
[7]
McKenzie
v Farmer’ Co-operative Meat Industries Ltd
1922
AD 16.
[8]
Telematrix
(Pty) Ltd t/a Matric Vehicle Tracking v Advertising Standards
Authority SA
2006 (1) SA 461 (SCA) 465 A-D.
[9]
Telematrix
surpra,
at
468 C-D referring to
BOE
Bank Ltd v Ries
2002 (2) SA 39
(SCA)
[2002] 2 All SA 247
paras [12] – [13].
[10]
Country
Cloud Trading v Department of Infrastructure Development
2014
(2) SA 214
SCA.
[11]
Bundle:
7 POC at para 14.
[12]
2011 (1) SA 586
(GNP) at 600 C-H.
[13]
See
the requirements postulated in Amler’s Precedents of Pleadings
for claims under the mantle of the Lex Aquila and the
cases cited
therein; refer also to
Smolka
v The Body Corporate of Ondangwa
2020 JDR 1620 (GJ) paras [14] – [17].
[14]
Durban
Picture Frame Co (Pty) Ltd v Jeena & Another
1976
(1) SA 329
(D&CLD) 333H-334B.
[15]
See, for instance,
Group
Five Building Ltd v Government of the Republic of South Africa
(Minister of Public Works and Land Affairs)
[1993] ZASCA 4
;
1993 (2) SA 593
(A) at 602C-D – as well as
Ocean
Echo Prop 327 CC v Old Mutual Life Assurance Co (SA) Ltd
2018 (3) SA 405
(SCA) para [8];
Constantaras
v BCE Foodservices Equipment (Pty) Ltd
2007 (6) SA 338
(SCA) paras [30] – [31];
Trope
and Others v South African Reserve Bank
[1993] ZASCA 54
;
1993 (3) SA 264
(A) at 269G-I.
sino noindex
make_database footer start
Similar Cases
Body Corporate of the Primavera Sectional Title Scheme v Godby (20545/2024) [2025] ZAWCHC 439 (29 September 2025)
[2025] ZAWCHC 439High Court of South Africa (Western Cape Division)99% similar
Body Corporate Of The Six Sectional Title Scheme No SS 4[....]9 v City of Cape Town (15732/2019) [2023] ZAWCHC 82; [2023] 3 All SA 136 (WCC) (26 April 2023)
[2023] ZAWCHC 82High Court of South Africa (Western Cape Division)99% similar
Body Corporate of the Sorronto Sectional Title Scheme, Parow v Koordom and Another (5439/2021) [2022] ZAWCHC 99; 2022 (6) SA 499 (WCC) (26 May 2022)
[2022] ZAWCHC 99High Court of South Africa (Western Cape Division)99% similar
Body Corporate of the Overbeek Building, Cape Town v Independent Outdoor Media (Pty) Ltd and Others (4838/2021 ; 3491/2016) [2022] ZAWCHC 2; 2022 (4) SA 167 (WCC) (21 January 2022)
[2022] ZAWCHC 2High Court of South Africa (Western Cape Division)99% similar
Metro Body Corporate v Diem and Others (7927/2022) [2024] ZAWCHC 372 (18 November 2024)
[2024] ZAWCHC 372High Court of South Africa (Western Cape Division)99% similar