Case Law[2023] ZAWCHC 276South Africa
Cape Peninsula University of Technology v Ma-Afrika Hotels (Pty) Ltd - Counter-Application (4899/23) [2023] ZAWCHC 276 (10 November 2023)
High Court of South Africa (Western Cape Division)
10 November 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2023
>>
[2023] ZAWCHC 276
|
Noteup
|
LawCite
sino index
## Cape Peninsula University of Technology v Ma-Afrika Hotels (Pty) Ltd - Counter-Application (4899/23) [2023] ZAWCHC 276 (10 November 2023)
Cape Peninsula University of Technology v Ma-Afrika Hotels (Pty) Ltd - Counter-Application (4899/23) [2023] ZAWCHC 276 (10 November 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2023_276.html
sino date 10 November 2023
IN
THE HIGH COURT OF SOUTH AFRICA
WESTERN
CAPE DIVISION, CAPE TOWN
Case
No: 4899/23
Date
Heard: 9 November 2023
Delivered
on: 10 November 2023
In
the counter-application between:
CAPE
PENINSULA UNIVERSITY OF TECHNOLOGY
Counter-Applicant
and
MA-AFRIKA
HOTELS (PTY) LTD
Respondent
In
the main application between:
In
the matter between:
MA-AFRIKA
HOTELS (PTY) LTD
Applicant
and
CAPE
PENINSULA UNIVERSITY OF TECHNOLOGY
First
Respondent
PARK
CENTRAL LIFESTYLE (PTY) LTD
Second
Respondent
PROFESSOR
NKOGWANE STOFFEL NHLAPO
Third
Respondent
PIETER
DU PLESSIS
Fourth
Respondent
JUDGMENT
DELIVERED ON 10 NOVEMBER 2023
HOLDERNESS,
AJ:
Introduction
[1]
This is the resumed hearing of an urgent counter-application for
vindicatory relief, entailing
the eviction of the respondent in the
counter application, Ma-Afrika Hotels (Pty) Ltd (‘Ma-Afrika’)
and security for
costs, which was postponed on 25 October 2023, by
agreement between the parties, for hearing in the Fast Lane of the
Third Division
on Thursday 9 November 2023. The court file was
delivered to me on 7 November 2023 for hearing two days later. This
judgment has
therefore been prepared in haste.
[2]
The applicant in the counter-application is the Cape Peninsula
University of Technology
(‘CPUT’). The immovable property
to which the counter-application relates, are units in the
Welgevonden sectional title
scheme, situated in District 6,
Zonnebloem (‘the premises’), which are used for the
purposes of student accommodation
for CPUT students and were
originally also leased to Ma-Afrika for running its Best Western Cape
Suites Hotel, restaurant and conference
centre.
[3]
The history of litigation between these parties is long and
torturous, dating back to 2021.
It has resulted in four judgments by
different Judges of this Division, all substantively in favour of
CPUT.
[4]
The factual background is set out in detail in the judgment of
Binns-Ward J in
Ma-Afrika
Hotels (Pty) Ltd v Cape Peninsula University of Technology.
[1]
It is
not necessary to repeat these facts in this judgment, particularly in
light of the limited time available and the various
applications
which have presented before this Court where the factual matrix has
been dealt with in great detail.
[5]
The counter-application presently before the court was brought in
response to an urgent
contempt application launched by Ma-Afrika in
June 2023, in relation to an order granted by Gamble J on 31 March
2023.
[6]
On 29 June 2023 Francis J dismissed the second contempt application
and struck CPUT’s
counter-application from the roll, with
costs.
[7]
The counter-application was struck due to certain procedural
shortcomings
inter alia
relating to the omission in such
application of time periods for the delivery of answering papers. It
was not struck due to lack
of urgency, nor were the merits of the
counter-application determined by Francis J.
[8]
On 4 September 2023 CPUT re-enrolled the counter-application for
hearing on an urgent basis on
25 October 2023, and filed a
supplementary affidavit. Ma-Afrika has not suggested that this Court
is precluded from hearing the
counter-application on the merits due
to it having previously been struck from the roll. However it
contends that the counter-application
is not urgent, and that any
alleged urgency is self-created.
[9]
Ma-Afrika delivered its answering affidavit in the
counter-application on 26 September 2023.
CPUT delivered its reply
thereto on 19 October 2023.
[10]
The counter-application came before Fortuin J on 25 October 2023. By
agreement between the parties,
the counter-application was postponed
for hearing on 9 November 2023. The parties reserved their rights to
argue the issue of urgency
on such postponed date.
The
issues for determination
[11]
I indicated at the hearing that I was not inclined to entertain the
application for security for costs
in the fast lane, particularly in
light of the change in circumstances relating to the current status
of other matters pending
between the parties, and in light of the
fact I was requested not to read the record in the pending review
application. The prospects
of success in such application would be
one of the factors to be taken into account in determining whether or
not Ma-Afrika should
be provided to provide security for costs.
[12]
Moreover, Mr Andre Pieterse (‘Mr Pieterse’) who deposed
to the answering affidavit in the
counter-application on behalf of
Ma-Afrika, alleged that Ma-Afrika’s financial position has
improved significantly since
he deposed to the affidavit in support
of the second contempt application on its behalf. Mr Magardie, who
appeared on behalf of
CPUT, accepted that in view of the
Court’s view regarding the relief for security of costs hereof,
an appropriate order
in respect of the relief in respect of security
for costs would be for it to be postponed
sine die.
The
application for security for costs can be re-enrolled, on proper
notice, prior to the determination of Part B of the review
application.
[13]
Therefore the only remaining issues for determination are whether the
counter-application is urgent
and the merits of the eviction or
vindicatory relief.
Urgency
[14]
Professor Nkogwane Stoffel Nhlapo (‘Professor Nhlapo’),
the Vice-Chancellor of CPUT, has
deposed to affidavits on behalf of
CPUT in the present proceedings.
[15]
In an affidavit deposed to on 25 June 2023, which served as the
founding affidavit in support of the
counter-application, Professor
Nhlapo averred that the counter-application for eviction and security
for costs was urgent, and
that CPUT would not be afforded substantial
relief at a hearing in due course, for
inter alia
the
following reasons:
15.1
On 15 June 2023 when Ma-Afrika’s second contempt application
was delivered,
it became clear that the eviction of Ma-Afrika from
the premises was urgent.
15.2
Until such time, CPUT had been unaware until then that essential
services such as
sanitation, electricity and security services were
at imminent risk of disconnection and termination due to non-payment
by Ma-Afrika.
On its own version, Ma-Afrika was at that stage unable
to even pay for the delivery of toilet paper for the student
accommodation.
15.3
CPUT had an appointed service provider, Park Central Lifestyle (Pty)
Ltd (‘Park
Central’) who was immediately able to take
over the student accommodation services but was unable to do so while
Ma-Afrika
was occupying the premises.
15.4
Ma-Afrika was unlawfully holding over the premises purchased by CPUT
for R131 million,
for student accommodation in the public interest,
using public funds. In this regard, it was clear that from 23 May
2023 when Sher
J handed down his judgment in part A, the interim
interdict part of the main review application, that Ma-Afrika had no
legal right
to continue occupying the property.
[16]
CPUT’s assertions regarding urgency in respect of the present
counter-application were elaborated
on in its supplementary affidavit
filed in support of the re-enrolment of the counter-application. In
that affidavit, Professor
Nhlapo stated that the matter was urgent
and CPUT would not get substantial redress at a hearing in the normal
course, for the
following reasons:
16.1
CPUT would not be afforded substantial redress at a hearing in due
course on the
normal opposed motion roll. At 23 August 2023 the
earliest available dates on the semi-urgent and opposed motion rolls
were 8 February
2024 and 7 October 2024 respectively.
16.2
The eviction proceedings were brought by CPUT as an institution
performing the public
function of providing higher education, created
for that purpose by the National Government and with its operation
substantially
subsidised from the National Revenue Fund.
16.3
Ma-Afrika continued to occupy the property and incur costs for
student accommodation
on the property without the consent of CPUT,
and simultaneously sought to hold CPUT responsible for such costs.
16.4
CPUT’s appointed service provider, Park Central, which had
lawfully been appointed
as student accommodation operator for the
premises for a limited 18 month period with effect from 1 April 2023
to 30 September
2024, was unable to take over operational control of
the property due to Ma-Afrika’s unlawful occupation. Almost one
third
of that period had already elapsed.
16.5
CPUT was self-evidently suffering harm by being unable to use and
take control of
its own property. As a result, it was unable to plan
effectively for the use of the premises as long as it remained
occupied by
Ma-Afrika.
16.6
CPUT was unable to proceed with its plans to use the areas of the
property occupied
by Ma-Afrika’s hotel for student
accommodation operation for as long as Ma-Afrika was occupying the
property.
16.7
The effect of this is that CPUT will be unable to save approximately
R2,5 million
in student transport costs and unable to increase its
income by approximately R15 million per annum due to additional
student residence
fees and state funding allocations, which will only
occur when the hotel units are converted to additional student
accommodation.
16.8
The end of the year period and with it the upcoming student vacations
and students
exiting the student residence for the December and
January vacations, was an important period as it gave CPUT the
opportunity to
conduct planning for the residence, repairs and
upgrades during this period. CPUT had in this regard taken a decision
to decant
the student accommodation sections in stages in order to
conduct repairs and implement the conversion of the entire premises
for
CPUT’s needs, which do not include the operation of the
hotel on the premises. Those planning processes were being frustrated
by Ma-Afrika’s unlawful occupation of the property.
16.9
Ma-Afrika had instituted an action against CPUT in this court on 14
August 2023 under
case no. 13739/23, in which it
inter alia
claimed payment of an amount of R3 171 222, 15 from CPUT based on the
negotiorum gestio
and on the grounds that “…
Since
24 May 2023 to date, the plaintiff has managed the affairs of the
defendant by providing accommodation services to 370 students
at the
premises. The defendant is aware that the plaintiff is managing its
affairs and has ratified the plaintiffs conduct in this
regard.”
16.10
Ma-Afrika was consequently seeking to hold CPUT liable for
disbursements and expenses which
it was incurring to provide student
accommodation on the property notwithstanding that this was directly
contrary to CPUT’s
wishes and such services were being provided
without CPUT’s consent.
Is
the urgency self-created?
[17]
Mr Elliot SC, counsel appearing on behalf of Ma-Afrika, argued that
any urgency was self-created, as
CPUT had been aware of Ma-Afrika’s
defence since 26 June 2023, and subsequent to the striking out of the
counter-application
and the exchange of correspondence in July 2023
in terms of which CPUT demanded that Ma-Afrika vacate the property
within 15 days,
no further steps were taken to evict Ma-Afrika.
[18]
On 14 August 2023 Ma-Afrika instituted a separate action against CPUT
under case number 13739/23 in
which it seeks to recover monies under
five different claims. The allegations in claims 1 and 4 underpin
Ma-Afrika’s defence
that it has a debtor-creditor lien over the
premises, whilst the averments in claim 2 support its defence of
exercising either
a salvage or improvement lien over the property.
[19]
The main thrust of Ma-Afrika’s argument regarding self-created
urgency is that CPUT waited over
two months, from 30 June 2023, to
re-issue its counter-application, which was enrolled for hearing on 4
September 2023. According
to Ma-Afrika CPUT has failed to properly
explain the reasons for such delay.
[20]
In its supplementary affidavit dated 1 September 2023, CPUT explained
that a substantial amount of
time had been spent by CPUT’s
finance staff in the laborious process investigating and discussing
with its legal team the
various invoices submitted by Ma-Afrika which
it claimed to be due.
[21]
Ma-Afrika contends that this explanation does not pass muster.
However, in a letter to CPUT’s
attorneys, Norton Rose Fulbright
dated 12 July 2023, Ma-Afrika’s attorneys stated inter-alia
that “…
our client’s continued occupation of the
premises is based on liens that it holds over the property. The
nature of the liens
were explained by our client under oath and your
client is in possession of all the invoices which support such
claims, which invoices
remain unpaid to date.
[22]
The explanation referred to was that proffered by Ma Afrika’s
Mr Pieterse in his replying affidavit
dated 27 June 2023, where he
stated:
“…
Ma-Afrika
has a debtor-creditor lien, as well as a salvage and/or improvement
lien over the property. It is entitled to remain in
possession of the
property until CPUT makes payment of its claims or puts up acceptable
security.”
Ma-Afrika reserves the
right to deal more fully with its liens over the property in due
course, in the event that CPUT should persist
in seeking its eviction
from the property in a further application.”
[23]
When challenged by CPUT regarding the lack of details in support of
the alleged liens, Mr Pieterse’s
riposte was to merely state
that “…
there is nothing vague about my statement that
Ma-Afrika has liens over the property
.”
[24]
Mr Pieterse’s statements under oath about Ma-Afrika’s
alleged substantial liens (amounting
to over R4 million) are indeed
vague and unsubstantiated. He failed to provide any meaningful detail
regarding the nature of the
liens, the items replaced, what exactly
the improvements relate to or when and in what circumstances the
alleged expenses were
incurred.
[25]
In its plea filed in the action proceedings, CPUT pleaded
inter
alia
that Ma-Afrika failed to comply with an agreed Asset
Replacement Request Process, which required the express consent of
CPUT for
the replacement of assets and items needing replacement.
[26]
I accept, as contended on behalf of CPUT, that it was therefore
entitled to investigate and gather
the facts relating to the liens
relied on and acted reasonably in doing so before re-enrolling its
counter-application. CPUT has
set out in detail the steps it took to
investigate the liens and has satisfactorily explained the delay in
re-enrolling its counter-application.
[27]
In
East
Rock Trading 7 (Pty) Ltd and Another v Eagle Valley Granite (Pty) Ltd
and Others
[2]
the
Court held that:
“
..the delay in
instituting proceedings is not, on its own a ground, for refusing to
regard the matter as urgent. A court is obliged
to consider the
circumstances of the case and the explanation given. The important
issue is whether, despite the delay, the applicant
can or cannot be
afforded substantial redress at a hearing in due course. A delay
might be an indication that the matter is not
as urgent as the
applicant would want the Court to believe. On the other hand a delay
may have been caused by the fact that the
Applicant was attempting to
settle the matter or collect more facts with regard thereto.
It means that if there
is some delay in instituting the proceedings an Applicant has to
explain the reasons for the delay and why
despite the delay he claims
that he cannot be afforded substantial redress at a hearing in due
course.
…
.the fact the
Applicant wants to have the matter resolved urgently does not render
the matter urgent. The correct and the crucial
test is whether, if
the matter were to follow its normal course as laid down by the
rules, an Applicant will be afforded substantial
redress.’
[28]
The grounds cited for urgency by CPUT, as further expanded in their
supplementary affidavit, are persuasive.
CPUT has been deprived of
its property for a significant period of time and it is in the
interests of fairness and justice for
the vindicatory relief to be
urgently determined.
[29]
Furthermore, both parties have had more than adequate opportunity to
place their respective versions
before the court and Ma-Afrika cannot
argue, nor did it seek to, that it has been prejudiced in this regard
by the re-enrolment
of the counter-application in the fast lane. The
issues have been fully ventilated and it is appropriate for them now
to be finally
determined.
Does
Ma-Afrika have a valid claim to the vindicatory relief?
[30]
CPUT’s claim for ejectment is founded on the
rei vindicatio.
[31]
The requirements of the
rei vindicatio
are trite and are not
in dispute in the present matter. CPUT is the owner of the premises.
Ma-Afrika is in possession thereof,
and the property sought to be
vindicated is still in existence and clearly identifiable.
[32]
Ma-Afrika has repeatedly and persistently refused to vacate the
premises.
[33]
Ma-Afrika’s only defence to the ejectment relief is that its
possession of the premises is lawful
as it has a
ius retentionis,
namely a debtor-creditor lien and a salvage and/or improvement
lien over CPUT’s property.
[34]
According to Ma-Afrika, the total amount in respect of which
Ma-Afrika exercises its liens over CPUT’s
property is R
4 863 859.63. Ma-Afrika maintains that for as long as
CPUT refuses to pay Ma-Afrika this amount alternatively
refuses to
provide acceptable security for its claims, its continued occupation
of the premises is lawful.
[35]
CPUT has tendered security in the form of a bank guarantee for
payment of the full amount of the liens
asserted by Ma-Afrika, in the
amount of R4 863 859.63.
[36]
CPUT contends that this tender and form of security disposes entirely
of Ma-Afrika’s defence
to the ejectment relief. It was argued
on behalf of CPUT that if it is eventually established in the action
proceedings under case
no. 13739/23 that Ma-Afrika has valid claims
based on its liens, which form the subject of claims 1, 2 and 4 of
the particulars
of claim, the bank guarantee tendered by CPUT will
provide it with the necessary security to enable its claims to be
fully paid.
[37]
Ma-Afrika of course cannot dispute that should adequate security be
put up by CPUT, it will no longer
have a lien or liens in terms of
which it is entitled to lawfully remain in occupation. It has been
well established for over a
century that the court can order that a
lien be relinquished against adequate security being furnished by the
owner.
[3]
[38]
In respect of any right of retention based on the liens claimed by
Ma-Afrika, CPUT has tendered security
by way of a bank guarantee in
the amount of R 4 863 859.63 for payment of the total
amount in respect of the liens claimed
by Ma-Afrika.
[39]
The principle that a right of retention based on a lien is defeated
by the owner
furnishing
to the lien holder security in the form of a banker’s guarantee
is legally sound.
[4]
[40]
Mr Magardie argued that CPUT’s tender of security in the form
of a bank guarantee in the total
amount of the liens asserted by
Ma-Afrika is proper and adequate, and disposes entirely of
Ma-Afrika’s defence to the ejectment
relief. If it is
eventually established in the action proceedings under case no.
13739/23 that Ma-Afrika has valid claims based
on its liens which
form the subject of claims 1, 2 and 4 of the particulars of claim,
the bank guarantee tendered by CPUT will
provide it with the
necessary security to enable its claims to be fully
paid.
[5]
[41]
Mr Elliot SC, relying on the authority of
Myers
v Gearbox Centre (Pty) Ltd
[6]
argued
that South African courts have persistently followed the course
adopted in
Campbell
v Muller, Smith and Co
[7]
,
namely
to order the release of goods held as security for monetary claims
against payment of the sum claimed to a third party or
the
furnishing
of an adequate and proper banker’s guarantee.
[42]
Ma-Afrika argues that CPUT’s failure
to furnish
, as
opposed
to tender
, ‘an adequate and proper banker’s
guarantee’ is fatal to its claim for ejectment.
[43]
In the heads of argument delivered on behalf of Ma-Afrika, reliance
is placed on the
Pheiffer
decision
supra
and
FirstRand
Bank Limited t/a Wesbank v Abandoned Solutions SA (Pty) Ltd
[8]
as authority for the proposition that it is standard practice for the
bank guarantee to be described in the order in a matter of
this
nature.
[44]
Based on the aforementioned authorities Ma-Afrika contends that it is
axiomatic that it and the Court
is entitled to have sight of the
guarantee to ascertain whether it is proper and adequate security for
its lien, and that judicial
oversight is required to determine
whether the guarantee is ‘adequate and proper.’
[45]
This is not how I understand the authorities on substitution of the
right of retention. Indeed Davis
J in this Division held in
Standard
Bank of South Africa Ltd v D Florention Construction CC and
Others
[9]
:
‘
Relief can be
crafted to provide adequate security for first respondent. Ultimately
a lien is a form of security for the claim.
If first respondent
satisfies his claim he must be in the position where the claim is
paid in full and therefore his right is not
rendered illusory.’
[46]
I was not referred to any authority in which it was expressly
provided that security
must
be provided prior to judgment
being granted, and that a tender for adequate and proper security
will not suffice.
[47]
In
Firstrand
Bank Limited t/a Wesbank v Abandoned Solutions SA (Pty) Ltd,
[10]
to
which I was referred by counsel for Ma-Afrika, the Court referred to
a guarantee which had already been furnished by the applicant,
however this does not appear to be authority for the contention that
the furnishing of security (as opposed to the tendering thereof)
is a
prerequisite to defeat a lien.
[48]
It is self-evident that were it to be left to the lien assertor to
debate and ultimately determine
the form of security, the parties
would in all probability be embroiled in a ‘death spiral’
of litigation.
[49]
The Court’s discretion to determine the form of security dates
back to
Voet
[11]
:
‘
'But is one who
has a right of retention held liable to restore the thing to his
opponent whenever the latter tenders sound security
for the refund of
expenses or the payment of wages? It appears that that ought to be
left to the E discretion of
a circumspect judge
according as it shall have become clear from circumstances either
that he who ought to restore is deliberately
aiming at holding back
possession of the thing too long under cover of expenses or wages; or
on the other hand that the person
owing the expenses has it in mind
to recover the thing under security, and then by a lengthy and
pettifogging protraction of the
suit to make the following up of the
expenses, wages and the like a difficult matter for his opponent.'
[50]
It goes without saying that in order to adequately secure Ma-Afrika’s
claims, the order would
need to be crafted in such a manner to ensure
that the security which CPUT is directed to provide is in a proper
and adequate form,
and that the ejectment will be conditional upon
the furnishing of security, in the form directed by the Court.
[51]
At the hearing counsel for CPUT sought to amend the Notice of Motion
to provide for the ejectment being
conditional upon delivery by the
counter-applicant to the respondent’s attorneys, of a bank
guarantee from one of the four
main commercial banks in South Africa,
in the amount of R4 863 859.63 on behalf of the Cape
Peninsula University of Technology,
as tendered by the
counter-applicant. Mr Elliot objected to such amendment. I cannot
conceive of how Ma-Afrika could be prejudiced
by such an amendment,
which clearly operates in its favour. The earlier amendment to
provide for final relief was not objected
to and is accordingly
allowed.
[52]
In any event, in my discretion I intend making an order in these
terms to enable CPUT to vindicate
its property whilst at the same
time ensuring that Ma-Afrika’s claims are adequately
substituted and secured. The amendment
is accordingly allowed.
Conclusion
[53]
In the circumstances, I am satisfied that this matter warranted an
urgent hearing and that subject
to the furnishing of proper and
adequate security, there is no valid defence by Ma-Afrika to the
vindicatory relief sought by CPUT.
[54]
A proper case has accordingly been made out for the ejectment of
Ma-Afrika from the premises. The 72
hour period within which
Ma-Afrika is to vacate, as sought by CPUT in the counter-application
is clearly inadequate. In my view
a reasonable period would be one
month from the date of this order.
[55]
There is no reason why costs should not follow the result.
[56]
In the result, the following orders issue:
1.
The
counter-applicant’s
non-compliance with the Uniform
Rules is condoned and leave is granted for this application to be
heard as one of urgency in terms
of Rule 6(12).
2. The
application for the amendment of the counter-applicant’s notice
of motion dated 26 June 2023 in terms of
the counter-applicant’s
Notice in terms of Rule 28(10) filed on 5 September 2023, is granted,
as follows:
2.1
By the deletion of the words “
That a rule nisi do issue
calling upon the Applicant (“Ma-Afrika”) to show cause on
Thursday 20 July 2023 why the following
order should not be made
final
” in paragraph 2.
2.2
By the deletion of paragraph 2.5 thereof;
2.3
By the deletion of the words “
Paragraph 2.5 of the rule nisi
shall operate as an interim interdict with immediate effect
”
in paragraph 3.
2.4
By the consequential re-numbering of paragraphs
2.1, 2.2, 2.3, 2.4,
2.5, 3, 4 and 5 of the counter-applicant’s notice of motion as
paragraphs 3,4,5,6,7 and 8 respectively.
2.5
By the replacement of the words “
CPUT
” and
“
Ma-Afrika
” as they appear in paragraph 2
(inclusive of sub-paragraphs) and 4 of the counter-applicant’s
notice of motion with
the words “applicant” and
“respondent” respectively.
3. The
respondent and all persons occupying the premises known as
sections
1-13, 15 -40, 43 -54, 56 -69, 78, 116 - 132, 134 -145, 147, 151-175,
177, 181 -187, 189 -194 and 196-202 in the Welgelegen
Sectional
Scheme No. 47/1997 (“the property”)
through
the respondent
, are evicted
from the property with effect from one (1) month from the date of
this order.
4. The
counter-applicant
is
authorised to have a writ of ejectment issued in order for the
eviction to be carried out by the Sheriff for the High Court,
Cape
Town or his deputy, assisted by the South African Police Service, if
necessary, should the respondent fail to vacate the property
within
one (1) month from the date of this order.
5. The
ejectment in terms of paragraphs 3 and 4 above shall take place, and
is conditional upon, after delivery by the
counter-applicant to the
respondent’s attorneys, of an irrevocable bank guarantee from
one of the four main commercial banks
in South Africa (namely
Standard Bank Ltd, First National Bank Ltd, Absa Bank Ltd or Nedbank
Ltd) in the amount of R4 863 859.63
on behalf of the
counter-applicant, Cape Peninsula University of Technology, as
tendered by it.
6. The
determination of the relief sought in paragraph 2.1 of the
counter-application for security for costs in the
amount of
R2,000,000 is postponed
sine die;
7. The
respondent is ordered to pay the counter-applicant’s costs.
HOLDERNESS,
AJ
APPEARANCES
For
the Applicant:
Adv
S Magardie
Instructed
by:
Norton
Rose Fullbright
Peter
Rogers
For
the Respondent(s):
Adv.
G Elliott SC
Instructed
by:
Thomson
Wilks Inc.
Anel
Bestbier
Date
of Hearing
:
9
November 2023
Judgment
delivered on
:
10
November 2023
[1]
2023
(3) SA 621 (WCC)
[2]
(11/33767) [2011] ZAGPJHC 196 (23 September 2011) at para 8 –
9
[3]
Spitz
v Kesting
1923 WLD 45
[4]
Pheiffer
v Van Wyk and Others
2015
(5) SA 464 (SCA)
[5]
Sandton
Square Finance (Pty) Ltd v Vigliotti
1997 (1) SA 826 (W)
[6]
1977
(4) SA 11
(WLD at 14F-G
[7]
4
SC 335
[8]
[2020]
ZAGPJHC 124 (8 May 2020)
[9]
2008
(5) SA 534
at [17]
[10]
Firstrand
Bank Limited t/a Wesbank v Abandoned Solutions SA (Proprietary)
Limited
(2019/31586) [2020] ZAGPJHC 124 (8 May 2020)
[11]
16.2.21
(
Gane’s
translation)
as cited in
Sandton
Square Finance (Pty) Ltd v Vigliotti
1997
(1) SA 826
at p 831
sino noindex
make_database footer start
Similar Cases
University of Cape Town v Villo and Others (2025/037004) [2025] ZAWCHC 262 (13 June 2025)
[2025] ZAWCHC 262High Court of South Africa (Western Cape Division)99% similar
Western Cape Provincial Minister of Local Government, Environmental Affairs and Development Planning v Central Karoo District Municipality and Others (Leave to appeal) (4835/2023) [2023] ZAWCHC 80; [2023] 7 BLLR 727 (WCC) (25 April 2023)
[2023] ZAWCHC 80High Court of South Africa (Western Cape Division)99% similar
Western Cape Provincial Minister of Local Government, Environmental Affairs and Development Planning v Central Karoo District Municipality and Others (4835/2023) [2023] ZAWCHC 66; [2023] 7 BLLR 717 (WCC); (2023) 44 ILJ 1832 (WCC) (3 April 2023)
[2023] ZAWCHC 66High Court of South Africa (Western Cape Division)99% similar
South African Legal Practice Council v Gonzales (1949/2024) [2024] ZAWCHC 412 (6 December 2024)
[2024] ZAWCHC 412High Court of South Africa (Western Cape Division)99% similar
South African Legal Practice Council v Beukman (17538/24) [2025] ZAWCHC 284 (11 July 2025)
[2025] ZAWCHC 284High Court of South Africa (Western Cape Division)99% similar