Case Law[2022] ZAWCHC 78South Africa
Motlhabane N.O. and Others v Wolfaardt N.O. and Others (A118/2021) [2022] ZAWCHC 78 (12 May 2022)
High Court of South Africa (Western Cape Division)
12 May 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2022
>>
[2022] ZAWCHC 78
|
Noteup
|
LawCite
sino index
## Motlhabane N.O. and Others v Wolfaardt N.O. and Others (A118/2021) [2022] ZAWCHC 78 (12 May 2022)
Motlhabane N.O. and Others v Wolfaardt N.O. and Others (A118/2021) [2022] ZAWCHC 78 (12 May 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2022_78.html
sino date 12 May 2022
In
the High Court of South Africa
(Western
Cape Division, Cape Town)
REPORTABLE
Case
No: A118/2021
In
the matter between:
KUTLWANO
MOTLHABANE N.O.
First Appellant
PHENYO
MOTLHABANE N.O.
Second Appellant
KUTLWANO
MOTLHABANE
Third Appellant
THANDOKAZI
MOTLHABANE
Fourth Appellant
and
GEORGE
WOLFAARDT N.O.
First Respondent
STEVE
BROEKMANN N.O.
Second Respondent
EMILY
HITEFIELD N.O.
Third Respondent
ALEX
FERGUSON
N.O
Fourth Respondent
TAMASEN
MAASDORP
Fifth Respondent
AMANDA
LLOYD-SIM N.O
Sixth Respondent
SEAN
DAYTON
N.O
Seventh Respondent
TRACY
LEE
PAULSEN
Eighth Respondent
JUDGMENT
DELIVERED : 12 MAY 2022
(Electronically)
NDITA;
MANTAME JJ
[1]
We have had time to consider the signed minority judgment by our
colleague Gamble
J. It is unfortunate that this judgment has changed
markedly from the judgment which was presented to us and the basis on
which
we dissented. As a result thereof, we were unable to agree
whether we now needed to reply to the new judgment, but finally we
resolved
to deliver our judgment “
as is
”,
notwithstanding the substantial differences between the two versions.
What appears below is our original dissenting judgment.
[2]
We have
read the eloquent judgment of our colleague, Gamble J, and we find
ourselves in respectful disagreement with the conclusion
reached and
the resultant order.
The reasons for such disagreement will
appear herein below. Although our Colleague has ably summarised the
facts, we find it necessary
to expatiate on them so that our points
of disagreement are properly discerned. For the purposes of
convenience, the appellants
would be referred to as the appellants,
save where it is necessary to specifically identify a particular
appellant and the respondents
would be referred to as the body
corporate.
[3]
The main issue before this
Court
,
is whether the Court a
quo
erred in dismissing an application by the appellants in which they
sought an interdict pending proceedings to be launched in terms
of
the Community Schemes Ombud Service Act 9 of 2011 (“
CSOS
Act
”).
[4]
The interdict was two-fold,
firstly,
that the body corporate be
interdicted from permitting any contractors from walking on or
generally accessing the roof of the Sakalengwe
Trust’s property
(“the property”).
Secondly
,
that the body corporate be ordered to ensure that the building works
being conducted in the section immediately below the property
comply
with the contractor policy of the body corporate and in particular
that noisy building work be carried out between 08h30
– 13h00
and between 15h00 – 17h00 on weekdays.
[5]
The appellant conceded that the
latter relief sought in respect of building works in the
Court a
quo
has been overtaken by events, as the building works have been
completed. However, notwithstanding the mootness of the issues, the
appellants seek that this Court deal with the costs award of the
court a
quo
which relates to that interdict as well as the one
in respect of the access to the roof of the property (which is still
a live
issue). This judgment will proceed on such basis.
Factual
background
[6]
The Sakalengwe Trust
(“the Trust”)
owns a
property, being section number 353 in The Adderley Street Sectional
Title Scheme (scheme number 212/2003). The body corporate
is a body
corporate in respect of the sectional title scheme in which the
property is situated on. Mr Kutlwano Motlhabane
(“Mr
Motlhabane”)
, the third appellant, represented the trust in
dealings with the body corporate.
[7]
As can be discerned from Mr Motlhabane’ s founding affidavit,
during 2017 and
2018 there were waterproofing issues in the building
and some leaks on the walls of the property. He states that the body
corporate
undertook to deal with the issue and repair the damage to
the walls of the property. However, despite the undertaking, it
failed
to do so. In 2018, Mr Motlhabane complained to Ms Paulsen, the
managing agent of the body corporate that there was a leaking roof
gutter leading to the garden. The appellants contended that that was
as a result of work conducted by Skysite, a rope access window
cleaning company mandated by the body corporate to clean the windows
of the sectional title units. According to the appellants,
the leak
from the gutter caused water to enter the property and damage the
wooden floors. The appellants aver that the leaking
gutter was
repaired but not the damage to the wooden floors in the property
notwithstanding Ms Paulsen’s commitment to send
her maintenance
team to repair it after inspecting the damage. Mr Motlhabane also
undertook to provide the wood for the floors,
which he did.
[8]
Mr Motlhabane states that the number of times Skysite worked on the
building increased
over time and in order to access the exterior of
the building, the contractors walked over the property’s roof
to hang ropes
over the side of the building. As a result of the
contractors walking on the roof, it caused the ceiling to crack.
According to
Mr Motlhabane, this can only be because the weight and
vibration on the roof caused the ceiling boards to move and crack the
plaster
and paint. Mr Motlhabane duly informed Ms Paulsen that the
contractors had caused cracks. Ms Paulsen acknowledged this and
inspected
the damage to the ceiling. The body corporate then arranged
for the cracks to be filled and painted. However, so avers Mr
Motlhabane,
in 2018, the cracks returned after Skysite was on site
and had performed additional work.
[9]
Mr Motlhabane further states that he became frustrated by the lack of
action and response
from the body corporate, and in February 2019, he
walked into the eighth respondent’s office and they discussed
the need
for repairs, and it was agreed that same would be carried
out. That too did not happen, instead, the eighth respondent neither
got back to him, nor returned his calls. Eventually, Mr Motlhabane
decided to deal with the building’s managing agent, Mr
Dereck
de Reuck
(“Mr de Reuck”)
, of Permanent Trust. The
latter informed Mr Motlhabane that Ms Paulsen was on leave and
arranged for someone to go and inspect
the cracks in the ceiling.
Subsequent thereto, Mr Motlhabane received an email denying that the
cracks were as a result of the
contractors, it suggested that they
were as a result of ‘
settling’
. He became
increasingly frustrated by the conduct of the body corporate as it
had become clear that they would not deal with his
queries. On 19
June 2019, Mr Motlhabane sent an email to Mr de Reuck to which he
attached a quotation in respect of the repairs
to the property. Mr de
Reuck did not respond to the email at all. Neither did he respond to
the follow up email.
[10]
Against this backdrop, on 4 July 2019, Mr Motlhabane received an
email notifying him that Skysite
would be on site to do the work. On
the stated day, the Skysite contractors walked on the roof as they
have done before. He states
that he went to them and asked that they
cease from walking on the roof until the impasse with the body
corporate regarding the
repairs was dealt with. Mr Motlhabane states
that he then called Mr de Reuck and asked him to communicate with the
trustees and
thereafter the contractors moved off the roof. However,
they moved back onto the roof based on the directives of Ms Paulsen.
Ms
Paulsen’s assistant, Mr Imraan Bux, informed Mr Motlhabane
that the roof was common property and that the only way he could
stop
the contractors from walking on the roof was to call the police. Mr
Motlhabane states that he then suggested that the contractors
should
leave the roof to avoid further damage until the issues could be
resolved by all the parties involved. The contractors then
left the
roof.
[11]
On 8 July 2019, the Trust’s attorneys sent a letter to the
seventh respondent wherein they
set out the background to the
interactions between Mr Motlhabane and the body corporate and the
fact that the latter’s communications
had been blatantly
ignored. It concludes thus:
“
Our
client notes with deep regret that this letter was entirely avoidable
and ought not to have been necessary but for the fact
that the body
corporate has simply refused to engage with our client in a
meaningful way and has now taken to ignoring it altogether.”
[12]
Mr Motlhabane states that on 11 October 2019, he received an email
from Mr de Reuck stating that
Skysite would be attending to the
building on 14 October 2019 to inspect the windows and downpipes
around the property where there
is water ingress. He responded on
that very same day and enquired as to the purpose of the inspection
and highlighted that the
notice was unsatisfactory. He further stated
that he would not subject the property to any further damage and
enquired as to what
steps would be taken to avoid further damage. He
did not receive any response to his query and on 14 October 2019, he
heard a noise
coming from the roof. He states that he went upstairs
to the contractors and asked them to leave the roof, which they did.
However,
about two hours later, he again heard a noise coming from
the roof where the contractors were walking and he went back to the
roof
and asked them why they were back. They informed him that they
had been told by the building supervisor, Mr Warren de Bruin, and
the
building assistant, Mr Imraan Bux, that he (Mr Motlhabane) had
discussed the matter with the sixth respondent and had consented
to
the workers being on the roof. Mr Motlhabane emphatically denies that
such a conversation ever took place. He further states
that the
Skysite contractors told him that they could conduct their inspection
using the fan room in order to avoid access to the
roof. He further
states that when he returned to the property, he found a fresh crack
on the roof, which he undoubtedly believes
that it was caused by the
contractors on the roof.
[13]
On 16 October 2019, the Trust’s attorneys sent a letter to the
body corporate, care of
the managing agent in which they recorded
their frustration at the lack of response and threatened legal
action. They stated that:
“
.
. . it is regrettable in the extreme that legal intervention should
be required in circumstances such as these, but your unfortunate
and
irrational response approach to this matter cannot be tolerated any
further. “
[14]
On 17 October 2019, the Trust’s attorneys received a response
from Mr de Reuck in which
he stated that the letter had been
forwarded to the trustees of the body corporate for their comments
and reply. No comments or
reply ever came. However, on 29 October
2019, Mr Motlhabane received a message from the managing agent of the
property that Skysite
would be on site in order to repair leaks
entering the F-level in the Singer building and unit 401 Adderley
Terraces. In his response
to the message, Mr Motlhabane voiced his
astonishment that the body corporate would authorise contractors to
carry out work in
the light of the Trust’s attorney’s
correspondence. In response, the respondents stated that the
contractor needed
to attend to and deal with water ingress into the
property and denying access would not resolve the matter. Mr
Motlhabane responded
on the very same day and stated that the issue
of access to the roof should be dealt with, for the reasons outlined
in the Trust’s
attorneys’ letter. It is common cause that
despite the aforegoing exchange, the contractors on 30 October 2019
accessed the
roof, and when Mr Motlhabane protested they informed him
that they were instructed by the trustees and if he had any issue
with
that he should call the police.
[15]
Regarding the interdict pertaining to the noise, Mr Motlhabane states
that construction work
had been conducted in the apartment unit below
the Trusts property for some time and the noise emanating therefrom
was considerable
as it involved drilling and banging. According to Mr
Motlhabane, the noise was so intense that one could feel the
vibrations and
it was very disturbing. His wife, who is a student
also found the noise very disturbing when she was trying to study. He
further
states that the noise started on weekdays at 08h00 and
continued until 16h00. To this end, Mr Motlhabane states that he sent
an
email on 3 October 2019 to Ms Paulsen and copied Mr de Reuck
enquiring how long the drilling and banging in the apartment below
would continue. He did not receive any response. He further states
that he would have expected that the Trust would have been given
notice that noisy work was to commence in the apartment below. Mr de
Reuck responded to Mr Motlhabane’ s email of 3 October
2019 and
on 30 October 2019 and advised that the building noise was likely to
continue for a further two months. The time frames
are according to
him, in violation of the body corporate’s contractor policy,
which provides that where building operations
generate excessive or
continuous noise, such work may only be undertaken on weekdays
between 08h00 and 13h00 and between 15h00
and 17h00 and should not
unreasonably interfere with the use and enjoyment of the property of
other occupants of the building.
According to Mr Motlhabane, the
noise started in about September 2019 and continued for a long period
of time. Furthermore, the
present application, launched on 15
November 2019 was due to the non-responsiveness of the body
corporate.
[16]
Mr Motlhabane further explains that after the
application was launched, there was engagement between the
parties
and various proposals and undertakings were made. In order to assist
with the technical aspects of those discussions, the
appellants
appointed Alphadrone to provide a report regarding rope access.
Alphadrone compiled a report wherein it set out a number
of options
available to access the exterior of the building without walking over
the roof of the property. It is common cause that
the report was
placed before the court a
quo
in an affidavit. The body
corporate also delivered a report compiled by Skysite as being
incorrect and incapable of implementation.
[17]
In respect of the issue of noise and contractor’s policy, the
respondents placed evidence
before court to the effect that the
building works should be completed during February 2020. Mr
Motlhabane also deposed to an affidavit
on 3 March 2020 stating the
following:
“
I
deny that the ‘remaining work’ which was to be completed
in February generated little noise. The work has continued
and
although it is less noisy than before, there still has been loud
banging and drilling and on 17 February, I had to go to the
unit
again to remind the builder that noisy work was permitted not between
1 pm and 3 pm. They stated that they would take longer
to finish the
work if they could not do noisy work during those times. I repeated
that it was not permitted in terms of policy.”
[18]
The sixth respondent also deposed to an affidavit on 9 March 2020,
prior to the hearing of the
matter stating that the renovations would
be completed by the end of March 2020. The matter was then heard on
10 March 2020 and
judgment was delivered on 8 May 2020.
[19]
Mr Motlhabane explained that the Trust, as set out in the notice of
motion was seeking, pending
the determination of relief before CSOS
an order to the effect that:
19.1 the body
corporate be interdicted from allowing contractors to access the roof
of the property;
19.2 the body
corporate be compelled to enforce the contractor’s policy and
cause the building works below the property
to be conducted in a
manner which complies with that policy.
[20]
According to Mr Motlhabane, CSOS makes no provision for urgent relief
and as such there is no
prospect of obtaining urgent relief in that
forum.
The
body corporates’ answering affidavit
[21]
The body corporate in their answering affidavit raise an issue that
the exclusive use area of
the appellant’s property contains an
illegal structure in the form of a habitable dwelling which covers
most of it, and which
was built without the consent of the body
corporate, nor has such consent ever been given subsequently. In an
affidavit deposed
by the first respondent, the body corporate
explains that it is the roof of the illegal structure that is being
complained of,
not the roof of the entire property.
[22]
With regard to the merits, the body corporate denies that contractors
have caused damage to the
ceiling of the property. Besides, so goes
the contention, whenever, contractors require access to the roof they
use wooden boards
placed on the roof in order to protect same.
According to the body corporate, the roof of the structure of the
exclusive use area
of the property consists of metal galvanised
sheeting divided by sharp metal edges approximately 25cm to 35cm
apart.
[23]
Regarding the noise emanating from the unit below the Trust’s
property, the body corporate
avers that it is not the owner of the
unit, and as such, there has been a form of misjoinder in that the
appellants have failed
to join the registered owner of the relevant
unit where the noise was emanating from. In addition, the sixth
respondent should
have been joined in her personal capacity.
According to the body corporate, it has a duty to maintain common
property and the appellants,
and any other owners are expected to
endure some inconvenience resulting therefrom. Furthermore, so aver
the respondents, the appellants
ought to have referred the matter in
terms of section 39 of the Community Schemes Ombud Service Act No 9
of 2011 to the CSOS as
the relief sought by the appellants on urgent
basis is incompetent.
The
replying affidavit
[24]
In response to the body corporate’s answering affidavit, the
Trust, through Mr Motlhabane
reiterates that there is no forum
established by CSOS for the bringing and adjudication of urgent
applications. Furthermore, whereas
the body corporate is required to
ensure that the property is maintained, it is not permitted to cause
damage to the Trust’s
property whilst doing so. With regard to
the alleged illegality of the structure, Mr Motlhabane states that as
far back as 2015,
the managing agents of the body corporate were
aware of the fact that the extent of the apartment needed to be
regularised and
did not have difficulty with the structures as built
or the Trust’s occupation.
[25]
Insofar as the body corporates’ averment that damage to the
roof could not have been caused
by the contractors as they put a
plank over the roof, Mr Motlhabane states that it is indeed so that
on occasion, wooden boards
were used, but they were placed in such a
way that they did not distribute the weight of the workers and in
fact probably made
things worse due to the added weight of the board.
He emphasised the fact that whenever they worked on the roof, the
ceiling was
damaged.
The
findings of the court a quo
[26]
In respect of the two interdicts, which were sought by the
appellants, the court
a quo
made the findings appearing below.
First in respect of the damage to the ceiling of the property, the
following are the relevant
findings:
26.1 The applicants
demonstrated a
prima facie
right not to have their property
damaged by the respondents and rejected the argument advanced by
respondents to the effect that
a portion of the property in question
was unlawfully constructed.
26.2 The appellants
did not fulfil the remaining requirements for an interdict.
26.3 The balance of
convenience does not favour the granting of relief sought in that the
body corporate had a duty to maintain
the building and the damage to
the applicants’ property was not extensive and could be
repaired. Furthermore, there is no
alternative means to access the
building.
26.4 There was an
alternative remedy available to the appellants in that they could
seek damages from the Body Corporate or
approach the Ombud
established in terms of CSOS for a remedy, and in fact the appellants
should have approached the CSOS before
launching the application.
[27]
With regard to the noise and building works, the court a
quo
reasoned as follows:
27.1 The appellants
had a
prima facie
right to seek the enforcement of the body
corporate’s contractor policy;
27.2 The appellants
did not fulfil the remaining requirements for an interdict;
27.3 The noise
levels were confined to the times suggested by the sixth respondent;
27.4 There should
have been little or no noise interruptions since March 2020 and thus
the issue is moot and;
27.5 The appellants
have thus not established irreparable harm nor that the balance of
convenience favours the granting of
the interdict.
The
grounds of appeal
[28]
With regard to the building works, which gave rise
to damage to the ceiling of the appellants’ property,
the
grounds of appeal are as follows:
28.1 That the court
a
quo
erred in the application of authorities in respect of
the requirements for “irreparable harm” in that the harm
need
not be absolutely irreparable. All that the appellants needed to
show was that the
status quo
would be more difficult and
costly to restore at a later stage;
28.2 That the court
a
quo
erred in finding that the appellants had not established
that they would suffer irreparable harm. The appellants established
that
they would suffer irreparable harm as required by the relevant
authorities for the following reasons:
28.2.1
The harm caused by the contractors would recur several times each
year and would not be a once off event;
28.2.2
The
status quo
would be more difficult to restore in that it
would cause substantial inconvenience to the appellants, which would
occur repeatedly;
28.2.3
The costs in repairing the cracks in the celling, although not
large,
do not account for the unacceptable inconvenience, which would be
suffered as a result of the recurrent repairs;
28.2.4
The body corporate refused to pay the costs and an action to recover
the costs would not be practical or an adequate remedy, not least
because the Sakalengwe Trust would be liable for a portion of
those
costs as it is a member of the body corporate. Moreover, a
never-ending series of actions would inevitably be required due
to
the recurrent nature of the damage;
28.3 That the court
a
quo
erred in finding that the appellants had not established
that the balance of convenience favoured the granting of the interim
relief;
28.4 That the court
a
quo
erred in not dealing with the merits of the Alphadrone
report and making a determination on the methods available to access
the
portion of the building which was relevant;
28.5 Furthermore,
in particular:
28.5.1
The court a
quo
erred in not finding that only a small portion
of members of the body corporate would be affected if the relief
sought was granted;
28.5.2
The appellants tender that access could be granted for emergency
repairs or work would mitigate any potential prejudice and what
constituted an emergency could be reasonably and objectively
determined,
failing which the parties could approach the Court;
28.6 That the court
a
quo
erred in the application of the authorities in respect
of the requirement of alternative remedies and that the availability
of a
damages claim does not in itself constitute an adequate
alternative remedy.
28.7 That the
appellants established that they did not have an adequate alternative
remedy for the following reasons:
28.7.1
An action against the body corporate would take a long time, would
be
expensive in respect of the quantum of the claim and would not be
satisfactory in respect of the ongoing damage and inconvenience;
28.7.2
The Sakalengwe Trust would also be liable for a portion of those
damages as it is a member of the body corporate. It could not be
expected to pay for even a portion of the damages it has claimed.
28.8 That the court
a
quo
erred in holding that CSOS was an adequate alternative
remedy as:
28.8.1
The application was brought as one of urgency and there was no
urgent
procedure in respect of CSOS;
28.8.2
The proceedings before CSOS would take months if not longer which
was
not an adequate remedy on the facts of the matter;
28.8.3
There was already evidence before the Court that the body corporate
had disregarded and was continuing to disregard an existing CSOS
order.
Discussion
[29]
Setlogelo
v Setlogelo
[1]
continues
to be the leading authority in interim interdicts. The
well-established requirements for the granting of an interdict
were
then refined in
Webster
v Mitchell
[2]
and the test requires that the applicant that claims an interim
interdict must establish the following:
29.1 a
prima
facie
right, even if it is subject to some doubt;
29.2 a reasonable
apprehension of irreparable and imminent harm to the right if an
interdict is not granted;
29.3 the balance of
convenience must favour the granting of the interdict; and;
29.4 the applicant
must have no other satisfactory remedy.
[30]
This segment of the law has evolved throughout the years. In
National
Treasury and Others v Opposition to Urban Tolling Alliance and
Others
[3]
(“OUTA”)
the Constitutional Court stated:
“
It
seems to me that it is unnecessary to fashion a new test for the
grant of an interim interdict. The Setlogelo test, as adapted
by case
law, continues to be a handy and ready guide to the bench and
practitioners alike in the grant of interdicts in busy Magistrates’
court and High Courts. However, now the test must be applied
cognisant of the normative scheme and democratic principles that
underpin our Constitution. This means that when a court considers
whether to grant an interim interdict it must do so in a way that
promotes the objects, spirit and purport of the Constitution.
”
[31]
It should be recalled that the court a
quo
concluded that the ‘appellants accordingly have at least a
prima
facie
right not to have their property damaged by the respondents, or
contractors appointed by the respondents in order to conduct
maintenance
and / or repair work to the building’
[4]
.
However, the court a
quo
held that the appellants fall short on the remainder of the
requirements for an interim interdict. The balance of convenience
does not favour the granting of the relief sought in that the body
corporate had a duty to maintain the building and the damage
to the
appellants’ property was not extensive and could be repaired.
Further, there was no alternative means to access the
side of the
building. Furthermore, there was an alternative remedy available to
the appellants in that they could seek damages
from the body
corporate or approach the Ombud established in terms of the CSOS Act
for a remedy, and that the appellant should
have approached CSOS
before launching this application.
[32]
It is common cause that “…
The
right which the applicant must prove is also a right which can be
protected
.”
[5]
In our opinion, in circumstances where the appellants’
lamentations were brazenly ignored by the body corporate, the
appellants
were entitled to approach the Court for an urgent relief
for their rights to be protected. In the absence of an equivalent
procedure
and/or relief from the Ombud, it is unimaginable how the
appellants could have first approached the Ombud for an urgent
relief.
It appears that, the appellants had problems in their
property as there were some leaks in the walls in 2017 already. The
leak
from the gutter caused water to enter the appellants’
property and damage to the wooden floors. This was as a result of
Skysite,
a rope access company whose employees accessed the side of
the building using ropes and thereby caused damage to the gutter.
Skysite
seems to be the preferred service provider for the body
corporate on maintenance or repair work in The Adderley title scheme.
[33]
As the maintenance work on the building became
frequent, for the Skysite workers to have access to the exterior
of
the building, they walked over the appellants’ property roof in
order to hang ropes over the side of the building. This
resulted in
visible cracks on the appellants’ ceiling. As stated by the
appellants, the weight and vibration on the roof
caused the ceiling
boards to move and cracked the plaster and the paint. In my
understanding, this is not an inconsequential or
insignificant
damage. The fact that it induced a discomfort and later on a
complaint on the manner in which the roof of the penthouse
appeared,
suggest that the complaint was indeed legitimate. Hence, the body
corporate repaired the cracks and painted the ceiling
initially.
[34]
In 2019, the appellants became more frustrated as the cracks returned
after the Skysite was on
site, but the body corporate at this
juncture took no steps to investigate or repair them. Instead, the
body corporate kept on
notifying the appellants that Skysite would
return on the site to do work. The workers at that stage continued
walking over the
roof and drilling and banging with their tools and
machines, which additionally caused serious noise. This was despite
the fact
that they were advised that the fourth appellant is a
student and the noise was disturbing when she tried to concentrate on
her
studies.
[35]
On 16 October 2019, when the appellants returned
to their property, they found a fresh crack in the ceiling,
which was
without a doubt caused by the contractors on the roof. The
appellants’ attorney caused a letter of complaint to
be
dispatched to the Body Corporate, which was met with silence.
[36]
On 29 October 2019, the appellants instead
received a correspondence that workers would be on site to attend
to
repair some works. Throughout this interaction, there is no decency
to even request for permission. This stance was adopted
by the body
corporate despite the appellants’ request that this work be
postponed up until the appellants’ issues have
been resolved.
The said request was not heeded. The noise and the walking over the
roof continued unabated, even after the appellants
advised that their
action was in violation of the body corporates contractor’s
policy.
[37]
In circumstances where the appellants have
demonstrated that they have a
prima facie
right not to have
their property damaged, it is incomprehensible why the interim
interdict was not granted. In other words, the
appellants discharged
the onus, that they have a right to use and enjoy the property
unhindered. In my view, whether the cracks
are negligible or
extensive, that is irrelevant for purposes of the issues for
determination. The fact that the appellants were
offended and/or
seriously undermined by the actions of the body corporate
necessitated them to approach this Court on an urgent
basis on 15
November 2019.
[38]
Notwithstanding, in circumstances where a clear right has been
established, the requirement of
irreparable harm need not have been
established. In
Ferreira
v Levin NO and Others, Vryenhoek and Others v Powell NO and
Others
[6]
,
it was stated that:
“
1.
A prima facie right though open to some doubt exists when there is a
prospect of success
in the claim for the principal relief albeit that
such prospect that may be assessed as weak by the Judge hearing the
interim application.
2.
Provided that there is a prospect of success, there is no further
threshold which
must be crossed before proceeding to a consideration
of the other elements of an interim interdict.
3.
The strength of one element may make up for the frailty of another.
4.
The process of measuring each element requires a holistic approach to
the affidavits
in the case, examining and balancing the facts and
coming to such conclusion as one may as to the probabilities where
such disputes
exist.
”
[39]
It would appear that the onus is less stringent in
interim interdicts as compared to a final interdict.
In
Nieuwoudt
v Maswabi NO
[7]
,
it was held that where an applicant sought interlocutory relief to
protect his right pending the resolution of the dispute in
the main
action, he was required to prove not a clear right but a
prima
facie
right to payment for the work he had done. Likewise, the appellant
was supposed to have been granted an interim interdict pending
its
referral of the dispute to CSOS.
[40]
However, in
Setlogelo
[8]
(supra)
,
it was held that if the applicant can establish a clear right, which
in this case the appellants have established its right not
to have
its property damaged, its apprehension of irreparable harm need not
be established. The Court stated:
“
But
he does not say that where the right is clear the injury feared must
be irreparable. That element is only introduced by him
in cases where
the right asserted by the applicant, though prima facie established,
is open to some doubt. In such a case he says
the test must be
applied whether the continuance of the thing against which an
interdict is sought would cause irreparable injury
to the applicant.
If so, the better course is to grant the relief if the discontinuance
of the act complained of would not involve
irreparable injury to the
other party …
”
[9]
[41]
If regard is had to
Setlogelo
(supra),
‘a right clearly established’, is whether applicants have
a clear right or not is a matter of substantive law, and
whether that
right is clearly established is a matter of evidence.
[10]
[42]
The Constitutional Court had an opportunity to consider the issue of
protected rights (albeit
in the context of a final interdict) in
Masstores
(Pty) Ltd v Pick ‘n Pay Retailers
where it was held that ‘
[i]f
the conduct complained of is illegal or is not justified in law, then
the interdict may be granted to protect the applicant’s
rights.
Nobody is entitled to violate another person’s rights if the
law does not authorise the breach.’
[11]
[43]
Even though irreparable harm, strictly speaking does not find
application in this case, the appellants
have demonstrated that the
harm is recurring and the cracks would not only cost money, but the
appellants would be required to
seek damages against the body
corporate on a continuous basis. The unfortunate scenario is that the
first appellant would contribute
to those costs in the sense that it
had to pay a portion of such damages.
[44]
If the circumstances were to be allowed to continue without sanction
from this Court, the damage
to the appellants’ property would
continue in perpetuity and the damage would likely escalate to be
more serious. That would
mean therefore that the appellants are
deprived of the use and enjoyment of their property – the harm
would be more than
irreparable with time.
[45]
With regard to the balance of convenience requirement, the inquiry is
the one relating to prejudice
to the parties and third parties. That
is, the court must weigh the prejudice to the applicant if the
interlocutory interdict is
refused against the prejudice to the
respondents if it is granted – See
City
of Tshwane Metropolitan Municipality v Afriforum and Another
[12]
.
[46]
The appellants established that the prejudice to the body corporate
would be limited to certain
units, which would not have their windows
cleaned. With regard to maintenance work, there was no indication of
what would be required
from the appellant. In the event of an
emergency, access was tendered by the appellants upfront as a
condition of the relief sought.
[47]
It appears that the appellants established that there were in fact
other means of accessing the
side of the building without crossing
over the appellants’ roof. However, the court a
quo
rejected the appellants’ suggestion without the consideration
and analysis of the competing expert reports and the evidence
before
Court. The court a
quo
concluded that the building could only
be accessed in the same manner in which the body corporate’s
contractors had. The
court a
quo
failed to appreciate that the
appellant’s property, which is the subject matter of this
application, in particular the roof
structure, was not approved by
the body corporate and was not lawfully built. This means that the
illegal status of this roof should
be allowed to prevail. It boggles
one’s mind on whether these cracks are not caused by the bad
workmanship on that roof structure
that was not approved.
[48]
In essence, the appellants’ expert, Alphadrone opined that the
anchor bolts currently installed
adjacent to Longmarket Street are
situated too low for best practice methodologies and should be raised
to reduce the angle on
the ropes as a minimum. It is best practice to
refrain from walking on roof structures that are constructed from
formed sheet metal.
The clip in type sheet metal panel system is not
designed for frequent usage as an access way or walk way and that any
rope access
services should be done without accessing the roof. The
chemical anchors could be placed into the brickwork.
[49]
The Skysite rejected the appellants’ expert opinion. In their
view, they considered the
feasibility of installing rope anchor
points below the level of the said roof, but are of the view that the
substrate there was
likely to be brickwork, which was unsuitable for
that purpose. It was strongly recommended that the rope anchor points
should not
be placed into brickwork, especially brickwork of the
quality in question, as it is unlikely to provide sufficient
strength.
[50]
The court a
quo
, it was stated merely rejected the appellants’
expert opinion on rope access without taking into account that
Skysite expressed
views on the unlikely suitability of brickwork
without conducting any tests to ensure that was in fact the case. In
fact, Skysite’s
finding was unsupported.
[51]
In any event, it was said that the court a
quo
ignored the
simple fact that it was not called upon to decide whether there was
an alternative means to access the side of the
building. That was the
issue to be determined by CSOS in the proceedings to be launched by
the appellants. The appellants merely
needed to demonstrate that
there was an issue, which could have been decided in their favour in
the proceedings to be launched
at a later stage. In the interim, the
court a
quo
should have granted the interdict to protect the
appellants’ property from damage pending the CSOS proceedings.
[52]
The court a
quo’s
finding that the appellants had an alternative remedy in that it
should have brought proceedings before CSOS was incorrect, so
it was
said. The damage to the appellants’ property was ongoing. That
involved a deprivation of the use and enjoyment of
their property in
the event that the crack remains unfixed. The CSOS does not grant
interdictory relief – See
Kinghaven
Homeowners’ Association v Botha and Others
[13]
;
where it was observed that the body corporate had ignored previous
orders by CSOS orders. Further, due to the attitude of the
body
corporate any conciliation proceedings required by CSOS would not
have been successful. The appellants addressed a plethora
of
correspondences to the body corporate and were ignored. If damages or
declaratory relief were to be sought before CSOS, it would
be a
futile exercise as such proceedings would be lengthy and damages to
the property would continue unabated. The appellants’
lamentations in this regard made sense.
[53]
It is therefore clear that the body corporate
decided to adopt a hostile attitude towards the appellants.
Despite
the fact that the appellants were willing to engage with the body
corporate in order to resolve the issues, the body corporate
in
return adopted an aloof attitude. In circumstances when the
appellants sought an urgent relief, it is inconceivable on how the
CSOS would have dealt with the appellants’ urgent complaints
having had no such procedure and remedy in place. The appellants
clearly have demonstrated more than what is expected in interim
interdicts, that is a
prima facie
right. Having had regard to
the aforementioned authorities, the appellants had a clear right to
be protected, and in our view, there
is no valid reason why the
appellants should be mulched with a cost order.
[54]
It remains to be said that Counsel for the body corporate, as pointed
out in the main judgment,
contended that the attitude adopted by the
Trust in failing to lodge a complaint with CSOS suggests a complete
lack of
bona fides
on its parts. The judgment of Gamble J
holds that:
“
But
what its tardiness does demonstrate is that the initial urgency in
respect of the roof issue has undoubtedly dissipated and
the downside
which it must now tolerate in enduring occasional cracks to the
ceiling is not as bad as it suggested. It must now
bear the
consequences of its decision (or more properly its indecision).”
If
regard is had to the excerpt from the judgment of Gamble J, it seems
that the basis of the dismissal of the application is that
the
appellants had failed to lodge a complaint with the CSOS from 2020 up
until the appeal was heard by this Court. In addition
to our view
that the appellants satisfied the requirements of an interdict, we
are in respectful disagreement with the court’s
approach to the
evidence elicited during the hearing of the appeal, namely, that
because of its tardiness, the Trust must suffer
the consequences. The
general principle is that in deciding an appeal, the court decides
whether the judgment appealed from is
right or wrong according to the
facts in existence at the time it was given, not in accordance with
new circumstances, which came
into existence afterwards. That said, a
court may elicit facts relevant for the determination of an issue in
the appeal. The overriding
principles applicable in such
circumstances are set out in
Donelly
v Barclays National Bank Ltd
[14]
:
“
Secondly,
it is a wholly new defence line that is being taken. It was not
mentioned in the summary judgment proceedings, nor in
the plea. It
was never referred to in evidence or argument at the trial, its mere
novelty, of course, is no ground per se for rejecting
it. However,
generally speaking, a Court of Appeal will not entertain a point not
raised in the court below. In this regard I need
do no more than to
refer to Herbstein and Van Wissen The Civil Practice of the Superior
Courts in South Africa 3
rd
ed at 736-737. In principle, a Court of Appeal is disinclined to
allow a point to be raised for the first time before it, Generally,
it will decline to do so unless
(1)
The
point is covered by the pleadings;
(2)
There
would be no unfairness to the other party
(3)
The
facts are common cause or well-known and incontrovertible; and
(4)
There
is no ground for thinking that the other or further evidence would
have been produced that could have affected the point.”
In
Fischer
v Ramahlele
[15]
the
Court explained thus:
“
[13]
Turning to the nature of civil litigation in our adversarial system,
it is for the parties, either in the
pleadings or affidavits (which
sere the function of both pleadings and evidence), to set out and
define the nature of their dispute,
and it is for the court to
adjudicate upon those issues. That is so even when the dispute
involves an issue pertaining to the basic
human rights guaranteed by
our Constitution, for (i) it is impermissible for a party to rely on
a constitutional complaint that
was not pleaded. There are three
cases where the parties may expand those issues by the way in which
they conduct the proceedings.
There may also be instances where the
court may mero motu raise a question of law that emerges fully from
the evidence and is necessary
for the decision of the case. That is
subject to the proviso that no prejudice will be caused to any party
by its being decided.
Beyond that it is for the parties to identify
the dispute and for the court to determine that dispute and that
dispute alone.”
In
the matter at hand, although the elicited facts are incontrovertible,
it is our considered view that when those facts form the
basis of an
adverse finding against a party, unfairness results. Furthermore, it
may well be that had the Trust been made aware
of that a finding
would be based on its failure to lodge a complaint with CSOS from
2020 until the appeal was heard, could produce
evidence that could
have affected the point.
[55]
The Constitutional Court in
SAPS
v Solidarity obo Barnard
[16]
,
restated this principle thus:
“
[217]
The general principle of our law is that it is the parties themselves
who identify and raise issues to be determined
by a court. The
parties may have their own reasons for not raising an issue which the
court finds interesting or important to determine.
The scope of what
falls to be determined depends on what the pleadings contain. In CUSA
this court formulated the principle in
these terms:
‘
Subject
to what is stated in the following paragraph, the role of the
reviewing court is limited to deciding issues that are raised
in the
review proceedings. There is much to be said for the submission by
the workers that it is not for the reviewing court to
tell a litigant
what it should complain about. In particular, the (Labour Relations
Act) specifies the grounds upon which arbitral
awards may be
reviewed. A party who seeks to review an arbitral award may not, on
appeal raise a new ground of review. To permit
a party to do so may
well undermine the objective of the [Labour Relations Act] to have
labour disputes resolved as speedily as
possible.’
[
218]
However, this principle is subject to one exception. The point raised
mero motu by the court must be apparent from
the papers in the sense
that it was sufficiently canvassed and established by the facts, and
that its determination must be necessary
for the proper adjudication
of the case.”
Here,
whereas the parties readily disclosed the fact that the Trust had not
yet lodged a complaint, upon questioning by the Court,
the Trust had
a right to expect that no finding would be made on the basis of the
disclosure as the issues for determination were
crystallised on the
notice of appeal. The issue was raised quite inadvertently upon
engagement with the parties during the hearing.
It is in our view
impermissible for a court to decide a matter on the basis of such an
issue. Furthermore, as we emphasised, it
raises an issue of
procedural fairness. We are of the firm view that this constitutes an
irregularity as the party concerned had
not been forewarned that such
information may well form the basis of an adverse costs order.
[56]
We now turn to consider the issue of costs concerning the noise
interdict, which had become moot.
The
noise interdict
[57]
It
is trite that when the hearing of any civil appeal to the Supreme
Court of Appeal or any division of the High Court, an order
will have
no practical effect, the appeal may be dismissed on this ground
alone. However, notwithstanding the dismissal of the
appeal on the
basis that the order will have no practical effect, the court
concerned may still consider the question of law and
of fact and the
appropriate order as to costs
[17]
.
Put in another way, the merits of the interdict relating to the body
corporate’s responsibility to enforce the contractor’s
policy concerning the noise and disturbance experienced by the
appellants must be considered in determining the issue of costs.
It
will be recalled that the court
a
quo
correctly found that the body corporate is bound by the contractor’s
policy but dismissed the interdict on the basis that
it was moot as
noise during the prohibited times had not occurred or had stopped by
March 2020.
[58]
It is clear from the evidence that at the time the appellants
launched the interdict application, the
question of noise was very
much alive. Although the sixth respondent had stated that the work
would be completed by February 2020,
that did not occur. In the
supplementary affidavit deposed to by Mr Motlhabane, on 3 March 2020,
he stated that:
“
I
deny that ‘the remaining work’ which was to be completed
by during February 2020 has generated little noise. The work
has
continued and although it is less noisy than before there still has
been loud banging and drilling
...
On
17 February 2020 I had to go to the unit again to remind the builder
that noisy work was not permitted between 1pm and 3 pm.
They stated
that they would take longer to finish the work if they could not do
noisy work during those times. I repeated that
it was not permitted
in terms of the policy.
.
. .
I
point out that the work shows no sign of being completed during
February 2020. I have attached pictures of materials which are
presumably to be installed in the unit marked “S5”. It
seems clear that the work will not be completed by the end of
February 2020.”
[59]
The sixth respondent in an affidavit she deposed to on 9 March 2020
stated that the renovations
should be completed by the end of March
2020. That was a mere estimate. Mr van Reenen correctly contended
that the basis on which
the court
a quo
held that the noise
had ceased by March 2020 is not borne out by evidence. The evidence
that was before court clearly established
that the noise was
continuing and the appellants therefore were fully justified in
approaching the court for the relief they sought.
[60]
The court
a quo
found that the appellants had a
prima
facie
right to insist on the
enforcement of the Contractor’s Policy. Mr van Reenen further
contended that when regard is had to
the provisions of the Sectional
Titles Schemes Management Act
8 of 2011
and
Regulations thereof, the appellants had established a clear right. In
terms of Section 13 (1) (d), (e) and (f) of the Sectional
Titles
Schemes Management Act, an owner must use and enjoy the common
property in such a manner as not to interfere unreasonably
with the
use and enjoyment thereof by other owners or persons lawfully on the
premises. Regulation 30 reads thus:
“
30
The body corporate must take all reasonable steps to ensure that a
member or any other occupier
of a section or exclusive use area does
not: - use the common property so as to unreasonably interfere with
other persons lawfully
on the premises, in breach of section 13
(1)(d) of the Act; use a section or exclusive area so as to cause
nuisance, in breach
of section 13(1) (e) of the Act.”
[61]
The appellants therefore had a clear right to insist that the body
corporate take steps to ensure
that the nuisance emanating from the
unit below the property was properly dealt with.
[62]
With regard to irreparable harm, the court
a quo
found that it
had not been alleged. The facts as alluded to by Mr Motlhabane
establish that the noise would start at 08h00 and
end at 16h00 and
that its extent was unbearable. This evidence is uncontroverted.
Furthermore, the appellants specifically alleged
that the noise was
interfering with the use of the property, more so that the fourth
appellant was attempting to study. This version
is supported by the
sixth respondent who admitted in correspondence that the construction
work was very noisy as there was no buffer
between the floors. In my
view, these facts are sufficient to justify an interdict to stop the
nuisance.
[63]
Insofar as the balance of convenience is concerned, it is well to
remind oneself that this requirement
is only a requirement in cases
where an applicant has not established a clear right. The inevitable
result is that in the case
of a clear right, this need not be
established. In
Hydro
Holdings (EDMS) BPK v Minister of Public Works
and Another
[18]
, the court
said the following:
“
It
was argued somewhat tentatively that I should have regard to the
balance of convenience in this case before granting an interdict.
It
seems to me, however, that I need not discuss the respective
contentions in this regard. According to the authorities questions
of
the balance of convenience arise only if an applicant for an
interdict has not established a clear right, but only a right which,
though prima facie established, is open to doubt. (See e.g., Eriksen
Motors (Welkom) Ltd v Protea Motors, Warrenton and Another
1973 (3)
SA 685
(AD) at p. 691C-G)”.
[64]
It is clear that in respect of costs of the building works and
enforcement of the contractors’
policy, the appellants had
established a clear right that the body corporate has the
responsibility to enforce its own policy.
Therefore, the court a
quo
ought to have granted the interdict that was sought by the appellants
and the costs should have been borne by the body corporate.
Given
that an order reversing the order of the court a
quo
will have
no practical effect, it is our judgment that the body corporate
should pay the costs of the application.
Conclusion
[65]
We have in this judgment held that the appellants were fully
justified in approaching the court
for interdictory relief in respect
of both legs of the interdict application. However, with regard to
the noise and the enforcement
of the contractors’ policy, the
appellants may recover only the costs as the granting of the
interdict has no practical effect.
In the same vein, we have held
that the applicants are entitled to the interdictory relief
concerning damage to the roof of the
property. In the result, the
following order is issued:
65.1 The body
corporate is interdicted from permitting any contractors from walking
on or generally access the roof of Section
353 in the Adderley
Sectional Title Scheme (scheme number 212/2003) save for emergency
repairs or maintenance;
65.2 The interdict
shall operate as an interim interdict pending the determination of
the proceedings in terms of the CSOS
Act in which the appellants will
seek relief relating to the issue above within fifteen (15) days of
the granting of this order
failing which the interim interdict will
lapse.
65.3 The body
corporate is ordered to pay the costs of this application, including
the costs relating to the order of the
Supreme Court of Appeal
granting leave to appeal.
NDITA
J
MANTAME
J
MINORITY
JUDGMENT
GAMBLE,
J:
INTRODUCTION
1.
“
The Adderley” is a sectional
title complex situated at the top of Adderley Street in Cape Town’s
CBD. It is an amalgam
of historic buildings which have been
interlinked with each other for purposes of creating an urban complex
comprising residential,
business and retail units registered as “The
Adderley Sectional Title Scheme” (“The Adderley”)
under the
Sectional Titles Act, 95 of 1986
.
2.
The first and second appellants are the
trustees for the time being of the Sakalengwe Trust (duly registered
under Master’s
reference no. IT 2960/2012 and hereinafter
conveniently referred to as “the Trust”), which is the
registered owner
of
section 353
of The Adderley (“the unit”).
The unit comprises a penthouse apartment beneficially occupied by the
third and fourth
appellants, Mr. and Ms. Motlhabane, who are from
Gauteng and consequently spend only part of the year in Cape Town.
3.
The Adderley is managed, under the
Sectional Titles Schemes Management Act, 8 of 2011, by the seven
respondents herein who are the
trustees of its body corporate. I
shall accordingly refer to the respondents collectively as “the
body corporate”.
The body corporate appointed a local company,
Permanent Trust, as the managing agent for the scheme.
4.
The Trust purchased the unit in 2015. Upon
acquisition, says Mr. Motlhabane, the unit included an enclosed area
replete with internal
ceiling and lights, which covered an area
originally used as an external patio with the roof having been
extended to cover it.
As I understand it this area now forms an
integral part of the apartment. For the sake of convenience, I shall
refer to this part
of the apartment as “the extension”.
The body corporate’s suggestion that the extension had been
unlawfully constructed
by a prior owner of the unit is irrelevant to
this litigation.
5.
Given the integrated configuration of The
Adderley, it comprises various levels – the unit being located
at “Level HM”.
From time to time it is necessary for
workers employed by a contractor (“Skysite”) appointed by
Permanent Trust to
access the roof, gutters and side windows of the
scheme to effect maintenance and repairs thereto. To do their work,
these workers
are harnessed to anchor points on the building and they
then abseil down the sides thereof.
6.
One of the workers’ points of access
is via a parking area adjacent to the corrugated iron roof of the
unit. Having anchored
their ropes to concrete pillars in the parking
area, the workers sometimes access the side of the building by
walking over the
roof of the extension. On occasion, this pedestrian
traffic over the roof of the unit causes the ceiling below the
extension to
crack. While these cracks do not present any structural
danger to the building or the unit, they do result in unsightly
cracking
lines in the ceiling. This irks Mr. Motlhabane no end as he
is then required to attend to the cosmetic repair of the cracks.
7.
During the second half of 2019 matters came
to a head when fresh cracks appeared in the ceiling of the extension
after workers had
again allegedly walked across the roof. Attorneys’
letters bustled back and forth and eventually the Trust approached
this
Division for urgent interdictory relief designed to restrict the
access of the managing agent’s contractors over the roof
of the
unit (and the extension) pending a referral of a dispute for
determination under the auspices of an adjudicator appointed
under
the Community Schemes Ombud Services Act, 9 of 2011 (“CSOS”).
8.
What the Trust in essence sought to do was
to preclude workmen, who were otherwise lawfully going about their
contractual obligations
to Permanent Trust and the body corporate,
from walking over the roof of the extension while their entitlement
to do so was resolved
in an alternate forum specifically designed to
address the type of disputes ordinarily arising out of communal
living arrangements.
It was, in the circumstances, a classic
application for an interdict
pendente
lite
intended to suspend the passage of
the workmen over the unit while the real issue was resolved in that
other forum.
9.
Recently,
in
Heathrow
Property
[19]
Sher J considered the approach to litigation arising from the
application of CSOS and its interplay with other
fora
such
as the Magistrates’ and High Courts. He described the object of
the CSOS thus.
“
[35]
This Court has previously pointed out that the object of the CSOS Act
is to provide a mechanism for the expeditious, informal
and
cost-effective resolution of disputes between owners of units in a
sectional title scheme and its administrators via an Ombud,
who has
been given wide inquisitorial powers whereby such disputes can be
resolved as informally and cheaply as possible by means
of qualified
conciliators and adjudicators, without the need for legal
representation, save in certain limited circumstances.
[36]
In Coral Island
[20]
,
Binns-Ward J warned that the compelling constitutional and social
policy considerations which informed the introduction of the
Act,
including the promotion of quick and affordable access to justice to
those who live in sectional title schemes who are not
easily able to
afford to litigate in the courts, and the social utility to be
achieved by the provision of a relatively cheap and
informal dispute
resolution mechanism, were liable to be undermined if courts were to
indiscriminately entertain matters that should
rather be dealt with
in terms of the processes which have been established by the Act.
However, and with reference to the decision
in Standard Credit,
[21]
he expressed the view en passant that insofar as judges and
magistrates may not have the power to refuse to hear such matters,
they should use their judicial discretion in respect of costs to
discourage any inappropriate resort to the courts in relation
to
cases that should more appropriately have been taken to the Community
Scheme Ombud Service.
[37] These remarks must
be seen in the context of the facts in Coral Island, where somewhat
unusually, it was the body corporate
which proceeded to Court, not
the owner of a unit in the sectional title scheme concerned. It
sought an order declaring that the
owner had made certain
unauthorised plumbing alterations to piping from a geyser which had
been installed in her garage, and was
utilizing the garage for a
purpose other than that for which it was designated in terms of the
sectional plan, and should consequently
be directed to replace the
piping with the same kind of piping as that which had been used
throughout the scheme. Shortly before
the matter was to be heard the
respondent made an offer of settlement, which was accepted, in which
she conceded that the applicant
was entitled to the relief which was
sought, save for costs. In this regard she maintained that costs
should not be awarded against
her because the body corporate should
have sought to resolve the dispute in terms of the procedures
provided for in the CSOS Act
and not by way of an application to
court. The Court agreed that it had been inappropriate for the matter
to have been brought
before it rather than before the Community
Schemes Ombud but in the light of the settlement which had been
arrived at it granted
the relief sought, and ordered that each party
should bear their own costs.
[38] In the
circumstances, the issue of whether or not the Court was entitled, as
a matter of law, to decline to hear the matter
was not one which
pertinently arose for decision and the comments which were made in
this regard were obiter, and the reference
to the decision in
Standard Credit should be seen in that light.” (Internal
references otherwise omitted)
10.
In
Coral
Island
, Binns Ward J commented as
follows regarding the purpose of the CSOS.
“
[8]
The disputes that lay at the heart of the current litigation, namely
the appearance and utility of plumbing appurtenances and
the
permitted usage of designated areas, are of the sort that commonly
arise in the context of the shared ownership and close neighbour
interaction that are inherently part and parcel of membership of the
body corporate of any sectional title scheme. They are essentially
of
a domestic character and involve issues that fall to be determined
with reference not only to statutory law and rules and regulations,
but also the common law principles of private nuisance or neighbour
law; in the context of which, as one judge sagely observed,
‘[t]he
homely phrases “give and take” and “live and let
live” are much nearer the truth than the
Latin maxim
sic
utere tuo ut alienum non laedas’
.
[9] It was no doubt
because of their common occurrence, the desirability that they be
determined as informally and cheaply as possible,
and the fact that
the cost of litigating such disputes in the courts is beyond the
reach of the vast majority of individual owners
of sectional title
units that the Ombud Act was enacted as part of the tranche of
sectional title-related reform measures adopted
by the legislature
nearly a decade ago. The Ombud Act provided for the establishment of
a service to provide for a dispute resolution
mechanism in community
schemes. All community schemes are required to raise a levy on their
members to contribute to the funding
requirements of the Ombud
Service. The Act’s provisions allow for the adjudication of
disputes such as those that presented
in the current litigation by a
suitably qualified adjudicator who will deal with the matter on an
inquisitorial basis and, save
in especially indicated circumstances,
without the involvement of legal representation on behalf of any of
the parties. The Ombud
Act also provides for the adjudicator to refer
disputes for conciliation in suitable cases. Conciliation is
undertaken by appropriately
trained and qualified conciliators
employed by the Community Schemes Ombud Service. The adjudicators’
determinations are
amenable to being made orders of court by means of
an inexpensive administrative process, and are subject to appeal to
the High
Court.” (Internal references omitted)
11.
In the circumstances, and while this issue
did not fall for determination, the decision by the Trust to seek
interim relief before
this court to effectively freeze the situation
regarding access to the roof while a speedy extra-curial process was
pursued, cannot
be faulted. It is to be likened to a party bound
contractually to go to arbitration to resolve a dispute, approaching
the High
Court for an interim interdict pending resolution of such
dispute.
12.
When the Trust approached the urgent court,
it went further and included a second cause for complaint against the
body corporate
in its notice of motion in which it sought a temporary
interdict pending a referral of a separate dispute to the CSOS. That
dispute
related to building renovations which were being conducted in
an apartment directly below that of the Trust. These renovations,
said Mr. Motlhabane, were excessively noisy and in breach of the body
corporate’s so-called “contractor policy”,
which
restricted the time when such work might be done in the scheme. The
Trust complained that the body corporate was remiss in
failing to
enforce its own policy by restricting the times when the building
works might take place, but the body corporate contended
that it was
not bound by the policy to do so. In the result, the Trust indicated
that this dispute, too, would be referred to the
CSOS and asked for
an interdict
pendent lite
in that regard too.
PROCEEDINGS IN THE
COURT A QUO
13.
The Trust lodged the application on 15
November 2019 for a hearing on 9 December 2019 in which, in addition
to the customary prayers
for urgency and costs, it asked for the
following relief.
“
2.
That the First to Seventh Respondents, in their capacities as
trustees of The Adderley Body Corporate (“the Body Corporate”)
be:
2.1 Interdicted from
permitting any contractors from working on or generally accessing the
roof of section number 353 in The Adderley
Sectional Title scheme
(scheme number 212/2003) (“the Property”).
2.2 Ordered to ensure
that the building works being conducted in the section immediately
below the Property comply with the contractor
policy of the Body
Corporate and in particular that noisy building work be carried out
between 08h30 and 13h00 and between 15h00
and 17h00 on weekdays.”
3. That the interdict and
order in paragraph 2 above operate as an interim interdict pending
the determination of the proceedings
described in paragraph 4 below.
4. That the Applicants
shall institute proceedings in terms of the Community Schemes Ombud
Services Act 9 of 2011 (“CSOS”)
in which the Applicants
will seek relief relating to the issues on 2.1 and 2.2 above will
(sic) within 15 days of the granting
of this order failing which the
interim interdict an order will automatically lapse.”
14.
The body corporate filed its answering
affidavit on 2 December 2019 and the Trust replied thereto on 6
December 2019. On the designated
day the matter was postponed by
agreement between the parties and was eventually heard by Golden AJ
on 10 March 2020. In the interim,
the parties’ engaged with
each other in an endeavour to resolve their disputes but were
evidently unable to settle. And,
during that interregnum, certain
further affidavits were filed to address issues which had become
contentious as the parties had
engaged with each other.
15.
On 8 May 2020 Golden AJ handed down
judgment, dismissing the application with costs. In her judgment the
learned Acting Judge found
that the Trust had established
“
at
least a
prima facie
right not to have their property damaged by the respondents, or
contractors appointed by the respondents in order to conduct
maintenance
and/or repair work to the building.”
However, Her Ladyship
found that the Trust had failed to establish the remainder of the
requirements for an interim interdict.
16.
In that regard, the Court
a
quo
found, firstly, that the Trust did
not establish that it would suffer irreparable harm if the
contractor’s workers were permitted
to walk on the roof over
the extension. The Court
a quo
was
satisfied that any damage that occurred in the circumstances (minimal
as it might be) was readily capable of being recovered
in an action
for damages. This, of course, points to the availability of an
alternative remedy – a further consideration
for the refusal of
an interim interdict. Furthermore, as the Court
a
quo
pointed out, the Trust was entitled
to make use of the CSOS procedure to recover any amounts found to be
due to it by the body
corporate.
17.
Then, said the Court
a
quo
, the balance of convenience
favoured the body corporate which was required to effect regular
maintenance and repairs to the exterior
of The Adderley. On this
score, said the learned Acting Judge, the evidence placed before the
court (including the supplementary
affidavits filed after the parties
were unable to settle), established sufficiently for the purposes of
interim relief that the
method of access employed by Skysite for its
workers was the safest and most practical. As a consequence, the
Court
a quo
held
that there was no alternative for its workers but to make use of the
roof over the extension to do the necessary maintenance
and repairs.
18.
Turning to the noise complaint, Golden AJ
found that the Trust had demonstrated that it enjoyed a
prima
facie
right to demand of the body
corporate that it comply with the terms of its “Contractors’
Policy” and limit the
building work to the times specified
therein. But, said the Court
a quo
,
the evidence established that by the time the application was finally
heard in March 2020, the noise had effectively abated. In
the result,
the Court
a quo
found that the nuisance issue was moot at that stage.
19.
An application for leave to appeal was
dismissed by Golden AJ on 14 September 2020. (No doubt some of the
overall delays in the
matter were attributable to the hard lockdown
enforced at the end of March 2020 in response to the COVID-19
pandemic). The Trust
is before this Court with the leave of the
Supreme Court of Appeal (“SCA”), same having been granted
on 22 February
2021.
THE ISSUES ON APPEAL
20.
Notwithstanding that this matter concerned
the refusal of a temporary interdict, the order of the SCA is
unrestricted in respect
the ambit of the appeal granted. Counsel for
the Trust, Mr. van Reenen, accepted that the noise complaint was moot
and did not
fall for determination on appeal. However, he argued that
the costs order granted against the Trust in the Court
a
quo,
should be reversed on appeal
because the application (and the cause for complaint) in that regard
was well-founded at the time it
was lodged in November 2019.
21.
In relation to the roof issue, Mr. van
Reenen argued that the Court
a quo
was
wrong in finding that the Trust had established a
prima
facie
right to the relief sought.
Rather, said counsel, the Court
a quo
should have found that the Trust had
established a clear right to demand the avoidance of damage to its
property and that in such
circumstances it did not have to establish
the criterion of irreparable harm.
22.
In the result, this Court was requested by
counsel to uphold the appeal, set aside the order of the Court
a
quo
and grant an interim interdict in
relation to the roof issue in the same terms sought before the Court
a quo
pending a referral of the dispute for adjudication under CSOS. It
bears mention that the exact nature of that dispute has never
been
fully articulated. But, whatever the formulation of the dispute might
ultimately encompass, it follows that, in asking this
Court to make
the order which it is averred should have been made by the Court
a
quo
, the Trust has not yet lodged its
request for arbitration with the CSOS: if it had done so, counsel
would not have formulated the
order on the basis that it would
automatically lapse if the proceedings had not been lodged within 15
days of the order to be made
on appeal.
23.
Given that more than two years had expired
since the lodging of the original application, and having regard to
the formulation of
the order sought on appeal, this Court enquired
from counsel during the virtual hearing of the appeal on 19 January
2022 whether
they were prepared to inform the Court of the status of
any referral by the Trust to the CSOS for dispute resolution, and if
so,
what the status was. After a brief adjournment to take
instructions and discuss this request, counsel reverted and had no
hesitation
in jointly informing the Court that it was common cause
that, as of the middle of January 2022, the position which obtained
before
the Court
a quo
still
prevailed.
24.
The position then is that the Trust, having
tolerated Skysite’s workers traipsing over the roof covering
the extension for
the past two years and more and, no doubt having
had to endure similar cracks in the ceiling to those that it
complained about
in late 2019, requests this Court now to interdict
the body corporate from allowing such workers to continue with
essential maintenance
and repair work for an undetermined period of
time while the Trust looks to resolving the issue in an application
yet to be instituted
before the CSOS.
25.
In categorizing the time period as
“undetermined”, I am mindful of the fact that, as pointed
out by Binns Ward J in
Coral Island
,
a party which is unsuccessful in an application under the CSOS has an
automatic right of appeal to the High Court on a point of
law in
terms of s57 of the CSOS, and may request that the operation of the
order appealed against is suspended “to secure
the
effectiveness of the appeal”.
IS AN INTERIM
INTERDICT IN RESPECT OF THE ROOF ISSUE WARRANTED AT THIS STAGE?
26.
The
requirements for the granting of an interim interdict
pendent
lite
are
by now trite.
[22]
The following
dictum
by
Corbett J in
LF
Boshoff
[23]
provides a useful summary of the requisite approach.
“
Briefly
these requisites are that the applicant for temporary relief must
show –
(a) that the right which
is the subject matter of the main action and which he seeks to
protect by means of interim relief is clear
or, if it is not clear,
is
prima facie
established, though open to some doubt;
(b) that, if the right is
only
prima facie
established, there is a well-grounded
apprehension of irreparable harm to the applicant if the interim
relief is not granted and
he ultimately succeeds in establishing his
right;
(c) that the balance of
convenience favours the granting of the of interim relief; and
(d) that the applicant
has no other remedy.”
That
approach follows the earlier cases such as
Setlogelo
[24]
and has been endorsed more recently in cases such as
Hix
Networking
[25]
.
27.
These
criteria are, however, all subject to the court’s overriding
discretion. In his seminal work
[26]
,
CB Prest notes the following.
“
In
every case of an application for an interdict
pendent
lite
the court has a discretion whether
or not to grant the application. It exercises this discretion upon
consideration of all the
circumstances and particularly upon a
consideration of the probabilities of success of the applicant in the
action. It considers
the nature of the injury which the respondent,
on the one hand, will suffer if the application is granted and he
should ultimately
turn out to be right, and that which the applicant,
on the other hand, might sustain if the application is refused and
he
should ultimately turn out to be right. For though there may be no
balance of probability that the applicant will succeed in the
action,
it may be proper to grant an interdict where the balance of
convenience is strongly in favour of doing so, just as it may
be
proper to refuse the application where the probabilities favour the
applicant, if the balance of convenience is against the
grant of
interim relief.
The exercise of the
court’s discretion usually resolves itself into a nice
consideration of the prospects of success and the
balance of
convenience - the stronger the prospects of success, the less the
need for such balance to favour the applicant; the
weaker the
prospects of success, the greater the need for the balance of
convenience to favour him.
It follows that even
where an applicant establishes the necessary requisites for the grant
of an interdict, there may well be factors
and circumstances present
which will cause the court to find against him and to refuse the
grant of the interdict.” (Internal
references omitted)
28.
It seems to me that Mr. van Reenen is
correct: the Trust has a clear right that its property (and more
particularly, the ceiling
of the extension) is not damaged when an
aspirant abseil specialist trudges over the roof of the unit before
plunging over the
edge of the building in pursuance of a day’s
work. That being so, considerations (c) and (d) in
LF
Boshoff
come into play, subject to the
Court’s residual discretion. Further, in giving consideration
to the exercise suggested by
Prest
- weighing up the prospects of success in the envisaged litigation
against the balance of convenience - it must be emphasized that
neither the Court
a quo
nor this Court has been presented with any facts in order to make
that assessment.
OTHER REMEDIES
29.
Consideration (d) in
LF
Boshoff
can be disposed of without
more. While it cannot ask the CSOS for interim relief
pendent
lite,
the Trust manifestly has other
remedies available to it to address any further damage which might
occur to the roof. In this regard,
it seems to me on the available
evidence that it is not every passage of workers over the roof of the
extension that results in
cracking of the ceiling. Perhaps some
trudge less resolutely than others? Be that as it may, whatever the
frequency and extent
of the cracking, the Trust has inexpensive
remedies in the Small Claims Court and before the CSOS, and a
relatively inexpensive
remedy before the Magistrates’ Court
whose jurisdiction presently stands at R200 000 in respect of
damages’ claims.
BALANCE OF CONVENIENCE
30.
As already alluded to, the Court
a
quo
carefully evaluated the expert
evidence presented on affidavit and came to the conclusion that the
balance of convenience lay with
the body corporate, hence the refusal
of the interim interdict. I cannot fault Golden AJ’s reasoning
in that regard.
31.
In considering the balance of convenience,
it is important, in my considered view, to have regard to the
function of the body corporate
which the Trust seeks to restrict
while it goes about litigating with it under the auspices of the
CSOS. That function is an important
one and is executed in respect of
all the unit owners in The Adderley. It includes attending to the
maintenance and repair of the
exterior of the building, cleaning
windows, repairing the roof and gutters and so on.
32.
The body corporate’s stance is that
there is no other way for Skysite’s workers to discharge their
functions than in
the way they have hitherto done. In the second set
of affidavits filed before the hearing in March 2020, the Trust put
up an affidavit
and an expert report by another company that provides
a similar service to Skysite. It was thereby suggested by the Trust
that
there were other available places for the fixing of anchor
points to which workers’ ropes could be attached.
33.
The body corporate countered this by
stating (through an affidavit from Skysite) that the alternative
anchor points suggested by
the Trust were not safe as they were to be
located in parts of the building where the walls were old and the
cement and bricks
crumbling. Possibly this proposal will form the
backbone of the Trust’s case before the CSOS where it may seek
to force the
body corporate to utilize other anchor points, thereby
avoiding the necessity for the passage of workers over its roof. I
say possibly,
because this Court still does not know what the
envisaged CSOS process will embrace, notwithstanding the lapse of
more than two
years in which the alternate dispute resolution process
might have been commenced by the Trust.
34.
And so, the obvious question that arises is
what to do in the meantime? The answer is self-evident. If the
proposal of the Trust’s
expert is followed, there is a risk
that workers may not operate in a safe working environment. The
consequences might ultimately
be fatal for them and damaging for
other unit owners and members of the public strolling along one of
Cape Town’s more important
streets. The counterpoint is that
while the parties tussle about where the abseiling ropes should be
anchored, the Trust and the
occupants of the unit might have to put
up with occasional cracking of the ceiling of the extension and the
resultant “polyfilla
job” to restore it to its
sought-after pristine condition.
35.
In the circumstances, I similarly conclude
that the balance of convenience overwhelmingly favoured the body
corporate and the application
for an interdict
pendent
lite
was correctly refused. There is
thus no merit in the appeal against that part of the Court
a
quo’s
judgment.
DISCRETION
36.
If I am wrong in my assessment of the
balance of convenience, as the majority of this Court holds, I
consider that it would in any
event be appropriate for this Court, in
considering the appropriate relief to be granted on appeal under
s19(d)
of the
Superior Courts Act, 10 of 2013
, to exercise its
residual discretion and refuse the granting of interim relief. That
discretion, which is now being exercised as
it might have been had
the learned Acting Judge considered it relevant, must, of necessity,
be exercised with due consideration
for all the relevant background
circumstances that obtained before the lower court. In this case that
includes the fact that the
Trust had taken no steps to approach the
CSOS before the judgment had been delivered.
37.
So, for instance, a court of appeal being
asked to reconsider the granting of an interdict
pendent
lite
in circumstances where there had
previously been High Court litigation pending, would want to know the
status of that litigation
before exercising its discretion. A
discretion such as that under consideration can manifestly not be
properly exercised at this
stage in the absence of the knowledge of
all the relevant facts.
38.
My Colleagues for the majority say that
consideration of the current status of the CSOS proceedings
constitutes the inadmissible
receipt of new evidence on appeal. I
disagree. As I have already pointed out, the failure of the Trust to
approach the CSOS was
a fact which existed before the Court
a
quo
and was a fact implicitly existed
before this Court, given that Mr. van Reenen asked that an interim
order be granted that the Trust
be directed to lodge its complaint
within 15 days of this Court’s order, failing which the interim
interdict would lapse.
39.
There is in any event no prejudice
occasioned to either party by consideration of that fact – the
persistent failure to lodge
the complaint with the CSOS. As I have
said, during the virtual hearing of the appeal the parties were
asked, firstly, whether
they wished to disclose to this Court the
current status of the CSOS matter, and if so, what that status was.
Neither party voiced
any objection to this Court receiving that
evidence, which was thus admitted by agreement.
40.
An important consideration in this Court
now exercising that discretion, in my considered view, is therefore
the Trust’s manifest
tardiness in taking the steps before the
CSOS it so urgently contemplated in November 2019. It wanted to stop
the body corporate’s
contractors from walking across the roof
at all costs, while it sought alternative dispute resolution which
was available to it
for speedy and inexpensive resolution, yet it has
done nothing to advance that case.
41.
Given that the parties engaged in
settlement negotiations in January and February 2020, it might be
unfair to hold it against the
Trust that it had not initiated the
CSOS application in the interim. But when it became apparent that
settlement was elusive, the
Trust had every opportunity to commence
the process immediately. It did not need to wait for the Court
a
quo
to rule on the matter. After all,
it then had the breathing-space it ostensibly so urgently needed
several months before, and even
more so, while it sought leave to
appeal both before the Court
a quo
and later the SCA. Yet it did nothing then and has done even less
since.
42.
Mr. Rogers (for the body corporate) argued
that the supine attitude adopted by the Trust suggests a complete
lack of bona fides
on its part and asked for the appeal to be
dismissed on that basis. Counsel may be right but that issue cannot
be determined on
the papers as they stand. However, what the Trust’s
tardiness does demonstrate is that the initial urgency raised in
respect
of the roof issue has undoubtedly dissipated and the downside
which it must now tolerate in enduring occasional cracks to the
ceiling
is not as bad as it suggested. It must now bear the
consequences of its decision (or, more properly, its indecision)
while it pursues
the matter before the CSOS.
43.
At the cost of repetition, I stress that
the Trust is not precluded from asking for the CSOS to hear its
complaint. It is simply
not entitled to an interdict while it does
so. And, if there is further damage to the roof, it will be entitled
to recover its
damages in that regard if the CSOS finds that the body
corporate is liable therefor.
COSTS IN THE COURT
A
QUO
44.
As I have said, Golden AJ ordered the Trust
to bear the costs of the body corporate in the postponed urgent
application before her.
The irony of the situation is that, as a
member of the body corporate, the Trust will also be liable for its
pro rata
share of the attorney and client costs incurred by the body corporate
in opposing the Trust’s proceedings. But that is how
it goes in
litigation of this nature, and potential applicants would surely have
been advised of the consequences of taking on
their body corporates.
This makes the case for early resolution of such disputes under the
CSOS all the more pressing.
45.
Be that as it may, Mr. van Reenen argued
that the appeal should be upheld with costs and the order of the
Court
a quo
varied to provide for an interim interdict pending resolution of the
roof issue before the CSOS. That argument cannot succeed in
light of
the findings made above and I am satisfied that the Court
a
quo
correctly dismissed the application
for relief in terms of prayer 2.1 of the notice of motion. The Court
a quo
also
correctly held that the relief sought in prayer 2.2 was moot by the
time the matter was finally determined.
46.
But what of the costs expended by the Trust
in relation to the litigation around the noise issue? Mr. van Reenen
submitted that
the noise issue was substantial and worthy of an
approach to court. I agree. The sixth respondent, who resided in an
adjacent unit
to that being renovated, confirmed in October 2019 that
she regarded the noise as excessive and unduly prolonged. In such
circumstances
the Trust was entitled to call upon the body corporate
to enforce its own policy relating to the employment of outside
contractors
to perform building work at The Adderley. It was not
required, in the circumstances, to take nuisance action at common law
directly
against the owner of the unit from whence the noise
emanated.
47.
When the Trust engaged with the body
corporate in relation to the noise issue it was uncooperative and
ultimately dismissive of
Mr. Motlhabane in relation to the nature and
extent of his complaint. He said that his wife was a student at the
time and that
her studies had regularly been interrupted by the
noise. It goes without saying that the beneficial owner of a unit
such as number
353 is entitled to the reasonable use and enjoyment of
the property. By failing to properly address the Trust’s
reasonable
complaints and enforce its own policy aimed at limiting
the extent of contractors’ interference with the rights of
other
occupants, the body corporate ran the risk of litigation
ensuing.
48.
In
finding that the issue was moot by the time that the matter was
finally heard, Golden AJ did not have regard to the fact that
the
Trust was, at the very least, entitled to approach the court for such
relief in November 2019 and that it incurred costs in
relation to
that aspect of the litigation. No doubt it would have been difficult
to separate out those costs from the costs of
the roof issue (which
certainly enjoyed considerable attention after the matter was
postponed in December 2019) with any degree
of exactitude but a court
considering a costs order has a wide discretion and must do its best
to do justice between the litigants
before it with due regard to all
the circumstances of the matter.
[27]
49.
Having considered the matter carefully, I
am of the view that the Court
a quo
erred in not limiting the body corporate’s entitlement to
recover costs to the roof issue. Employing a robust approach, I
am of
the view that it would have been just and equitable to grant the body
corporate only 60% of its costs in the Court
a
quo.
The order of that court should be
amended accordingly.
COSTS ON APPEAL
50.
The order of the SCA granting the Trust
leave to appeal provided that the costs in that regard before Golden
AJ and in the SCA are
to be costs in the appeal. What then of the
costs of the appeal itself? The Trust has successfully avoided an
order that it should
bear all of the body corporate’s costs in
the Court
a quo
and
to that extent it should be considered to have achieved a measure of
success. On the other hand, the body corporate has successfully
batted off an attack on the finding of that court on the roof issue.
51.
Once again, the calculation of the measure
of the parties’ relative successes cannot readily be achieved
through the use of
a pair of intellectual calipers. The most
equitable outcome in the circumstances seems to me to be an order
that each party to
bear its own costs on appeal.
52.
It now transpires that my Colleagues are
not in agreement with my assessment of the appeal and that this
judgment constitutes a
minority opinion. Had there been consensus in
the matter, I would have proposed the following order:
A.
The appeal succeeds only to the
extent that Paragraph 2 of the order made by Golden AJ on 8 May 2020
is set aside and replaced with
the following –
“
The
applicants, jointly and severally, shall pay 60% (sixty percent) of
the costs incurred by those respondents who constitute The
Adderley
body corporate.
B.
Save as aforesaid, the appeal is dismissed.
C.
Each party shall bear its own costs on
appeal, such costs to include the costs contemplated in paragraph 3
of the order of the Supreme
Court of Appeal dated 22 February 2021.
GAMBLE,
J
Coram
: NDTIA J et GAMBLE J et
MANTAME J
Judgment
by
:
NDITA J et B P MANTAME, J
(Majority)
GAMBLE
J (Minority)
FOR
APPELLANTS
: ADV D VAN REENEN
021 422
0787/0844044564
deneysvanreenen@gmail.com
Instructed
by
: Nirenstein Inc
FOR
RESPONDENTS :
ADV J ROGERS
021 423
4606/0731736252
john.rogers@capebar.co.za
Instructed
by
C E Van Geuns & Ass
Date
(s) of Hearing
: 19 January
2022
Judgment
delivered on :
12 MAY 2022
[1]
1914
AD 221
[2]
1948
(1) SA 1186 (W)
[3]
2012
(6) SA 223
(CC) at para 45
[4]
Vol
3 Record page 290 para 15
[5]
Minister
of Law and Order v Committee of the Church Summit
1994 (3) SA 89
(B)
at 98
[6]
1995
(2) SA 813
(W) at 832I – 833B
[7]
2002
(6) SA 96
(O) at 102H - I
[8]
1914 AD 221
At page 227
[9]
Erasmus
Superior Court Practice, Second Edition, Vol 2 (2019) Part D :
Appendices – Interdicts at D6 - 20
[10]
Erasmus
Superior Court Practice, Second Edition, Vol 2 (2021) Part D :
Appendices – Interdicts at D6 - 13
[11]
2017
(1) SA 613
(CC) at 87
[12]
2016
(6) SA 279
(CC) at 302 B - C
[13]
(6220/2019)
[2020] ZAWCHC 92
(4 September 2020)
[14]
1990
(1) SA 375
at 380H-381B
[15]
2014
(4) SA SCA 614 at 620
[16]
2014
(6) SA 123
CC 123
[17]
See
Herbstein
and Van Winsen; The Civil Practice of the High Courts and the
Supreme Court of Appeal,
5
th
ed at page 1239
[18]
1977
(2) SA 778
(T) at 787
[19]
Heathrow
Property Holdings No 33 CC v Manhattan Place Body Corporate and
others
2022 (1) SA 211 (WCC)
[20]
Coral
Island Body Corporate v Hoge
2019 (5) SA 158 (WCC)
[21]
Standard
Credit Corporation Ltd v Bester and others
1987 (1) SA 812
(W)
[22]
See
generally in that regard,
Erasmus,
Superior Court Practice
Vol 2 at D6-1
et
seq.
[23]
LF
Boshoff Investments (Pty) Ltd v Cape Town Municipality
1969 (2) SA 256
(C) at 267A-F
[24]
Setlogelo
v Setlogelo
1914 AD 221
[25]
Hix
Networking Technologies v System Publishers (Pty) Ltd and another
[1996] ZASCA 107
;
1997 (1) SA 391
(A) at 398I - 399B.
[26]
The
Law and Practice of Interdicts
at 79
[27]
Ferreira
v Levin NO and others
[1996] ZACC 27
;
1996 (2) SA 621
(CC) at
[7]
, [8] & [11].
sino noindex
make_database footer start
Similar Cases
Mokoteli and Another v The Body Corporate of Viling Villas Sectional Title Scheme (SS52/2012) and Others (16623/2021) [2022] ZAWCHC 114 (6 June 2022)
[2022] ZAWCHC 114High Court of South Africa (Western Cape Division)99% similar
Motikeng v Regional Magistrate Beaufort West (Ms Moni) and Another (8853/21) [2022] ZAWCHC 263 (15 December 2022)
[2022] ZAWCHC 263High Court of South Africa (Western Cape Division)99% similar
Nkosi and Another v S (A260/2021) [2022] ZAWCHC 50 (19 April 2022)
[2022] ZAWCHC 50High Court of South Africa (Western Cape Division)99% similar
Kotze N.O and Others v UD Boerdery CC (18631/2021) [2024] ZAWCHC 302 (8 October 2024)
[2024] ZAWCHC 302High Court of South Africa (Western Cape Division)99% similar
Makgobo v S (A121/2023) [2023] ZAWCHC 238 (8 September 2023)
[2023] ZAWCHC 238High Court of South Africa (Western Cape Division)99% similar