Case Law[2025] ZALCC 20South Africa
Moletele Community and Others v Certain Farms in the Maruleng Region as listed in Annexure 'NR1' (LCC206/2010) [2025] ZALCC 20 (7 May 2025)
Headnotes
PDF format RTF format
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Land Claims Court
South Africa: Land Claims Court
You are here:
SAFLII
>>
Databases
>>
South Africa: Land Claims Court
>>
2025
>>
[2025] ZALCC 20
|
Noteup
|
LawCite
sino index
## Moletele Community and Others v Certain Farms in the Maruleng Region as listed in Annexure 'NR1' (LCC206/2010) [2025] ZALCC 20 (7 May 2025)
Moletele Community and Others v Certain Farms in the Maruleng Region as listed in Annexure 'NR1' (LCC206/2010) [2025] ZALCC 20 (7 May 2025)
Download original files
PDF format
RTF format
Links to summary
PDF format
RTF format
make_database: source=/home/saflii//raw/ZALCC/Data/2025_20.html
sino date 7 May 2025
IN
THE LAND CLAIMS COURT OF SOUTH AFRICA
HELD
AT RANDBURG
CASE
NO: LCC206/2010
(1)
REPORTABLE: YES
(2)
OF INTEREST TO OTHER JUDGES: YES
(3)
REVISED. YES
DATE:
7 May 2025
SIGNATURE:
In
the matter between:
THE
MOLETELE COMMUNITY
First
Claimant
HEIR
PRINCE-MAEKANE TRIBAL COMMUNITY
Second
Claimant
KGOSI
LACKSON ABUTHI CHILOANE
on
behalf of
MOLETELE TRIBE
Third
Claimant
MOLETELE-BLYDEPOORT
COMMUNITY
Fourth
Claimant
Concerning
CERTAIN
FARMS IN THE MARULENG REGION
AS
LISTED IN ANNEXURE “NR1”
JUDGMENT
CONDONATION
APPLICATION AND COUNTER-APPLICATION
SPILG,
J
INTRODUCTION
1.
In October 2010 the Regional Land Claims
Commissioner (“
RLCC”
)
referred the land claim of the first to fourth claimants to this
court. It is filed under case no LCC 206/2010. These claims are
generally referred to as the Moletele Land Claim and the persons who
brought the claim as the
main claimants
.
In this judgment the court will refer to them either as the Moletele
or the main claimants.
2.
By agreement with the Moletele, represented
by its legal team, its claims were split into two separate
components.
The
one component concerns land identified in the referral report as
white owned land and includes some land acquired by Telkom
and Eskom,
either by way of expropriation or direct purchase from white
farmers.
[1]
3.
The
balance of the Moletele claims, forming the other component, comprise
land which was purchased in terms of the Native Trust
and Land Act 18
of 1936. This land had been incorporated into the so-called Lebowa
and Gazankulu homelands which, as the referral
report mentions “
is
now substantially occupied by persons of African descent” (“the
Trust lands”)”.
The
referral report makes plain that, because there are significant
factual and legal differences, the Trust lands do not form part
of
the referral but will be dealt with at a later stage by way of a
separate referral under s 14 “
if
necessary
”
.
[2]
4.
Accordingly only the land to which the
Gazette Notices referred, and which were identified in annexures NR1A
and NR1B of the Referral
Report forms the subject matter of the
referral to this court under the provisions of s14(1) of the
Restitution of Land Rights
Act 22 of 1994 (“
the
Act”
) and to which the present
case number in relation to that referral was allocated (i.e. LCC
206/2010).
5.
In
other words, the only land which is presently subject to this court’s
jurisdiction is that identified in the aforesaid
referral and a
referral, by reason of the provisions of s11(1) through to s12
[3]
, can only deal with land
that has been specifically Gazetted in accordance with the Act and in
the manner set out in the Commission’s
Rules (see below).
This
is highly relevant when considering the events which have resulted in
the applications before the court; the one by the main
claimants for
condonation for their failure to comply with court directions and
orders of 16 May and 12 August 2024 and the other
being a
counter-application by the Commission on Restitution of Land Rights
(“
the Commission
”) declaring that the referral
under case number LCC206/2010 shall be confined to the farms that
were identified in the attachment
to the Referral Report as annexures
NR1A and NR1B, these being all the farms that were Gazetted other
than the Trust land farms.
6.
The Trust land farms related to a not
inconsiderable area of land owned by the State which was settled and
has already been restored
to the Moletele. The relevance of this will
become apparent later.
7.
The claim then became bogged down with a
large number of disputes between the main claimants and a large
number of individual and
corporate landowners. The disputes range
from challenging the competency of the claim to non-restorability in
respect of specific
property. The defendants to the claim have also
relied on a referral report of Prof. Delius which has been challenged
in generalised
terms by the main claimants.
8.
In the latter part of 2015 a number of
other claimants delivered their statement of claim. Their claim had
been referred to this
court some years earlier under case no LCC
20/2012. It is generally identified as the Mnisi Land Claims. These
claims cover a portion
of the land in respect of which the main
claimants seek restitution. The group bringing the Mnisi Land Claims
are referred to as
the
competing
claimants.
9.
The effective consolidation of these two
sets of land claims added a further series of major disputes to an
already burgeoning list
of issues requiring court adjudication.
.As
a result the case became bogged down with not only substantive issues
but also a large number of procedural and technical issues.
Numerous
pre-trial conferences have been held both prior to and since 2015.
Indeed Gildenhuys J was brought in to assist in finalising
the
gazetting of the claims so that the referral could proceed.
10.
In order to bring the matter to trial, the
parties were directed to prepare a litigation plan. This was done by
7 February 2020
. I do not recall when I took over the matter from
Sardiwalla J, but it is evident that I have presided over pre-trial
conferences
since the litigation plan was presented.
11.
At the conference of 28 February 2020 the
following of relevance is noted in the approved minutes;
·
the adoption
of
the minutes of the litigation planning meeting held on 21 November
2019;
·
the main claimant had failed to furnish the
Commissioner with information regarding financial statements despite
previously undertaking
to do so, including at the meeting on 16
September 2019. This related to issues concerning the continued
funding of the Moletele’s
legal fees by the Commission. Mr.
Notshe, on behalf of the main claimants, stated that they
refused to provide any information.
In the result the court made an
order requiring them to provide audited financial statements, failing
which provisional financial
statements and certain supporting
documents, of the Moletele Community Property Association (“
the
Moletele CPA”)
up to January
2020;
·
many of the landowner defendants
sought a separation of hearings. Generally this was based on the
sheer magnitude of the areas involved
and what were contended to be
quite different and unrelated geographical areas as well as the
“waiting time” involved
while testimony unrelated to
their land was being presented. One of the aspects sought to be
separated was whether claims had been
properly lodged.
·
In responding to the question of a separate
hearing, Mr. Notshe said that the Moletele had a serious issue with
the question of
whether claims had been properly lodged in respect of
some of the farms. His view as recorded in the minute was that;
“…
the
decision made by the Regional Land Claims Commissioner to Gazette the
claims still stands, unless it is taken on review.”
This
will be contrasted later with the position the Moletele now wish to
take.
·
Mr. Dodson for the Commission placed on
record the case of a judgment of Carelse J (at that time)
(
Emantanjeni Community
[2019] ZALCC 31)
where the judge precluded legal representatives from
recovering fees in terms of section 29(4) because they had pursued
unwarranted
litigation. Mr. Dodson stated that this judgment would be
applied in the event that unwarranted litigation was pursued by any
party
whose legal costs were funded under that section. At that time
both claimants were being so funded.
·
The
issue of the Minister filing a plea was raised, Mr. Dodson contending
that Mr. Notshe had agreed not to persist with that at
a pre-trial
held on 16 September 2019.
[4]
When
Mr. Notshe disputed that he had abandoned the request for a plea from
the Minister, he was referred to para 29 of the pretrial
minute where
Sardiwalla J had adjourned the matter for 30 minutes to allow the
parties to discuss
inter alia
the issue of the Minister's
plea. The court also raised the concern that it appeared that on
three occasions statements were made
by the main claimants’
counsel at previous pretrial conferences which the claimant community
failed to comply with;
·
The main claimants
had
previously obtained a report from
Prof.
Delius. It
subsequently expressed
reservations with the report and had been requested to identify what
aspects of the report were in issue.
·
The stated position of the Commission at
the conference was that the dispute over funding should not delay the
progress of the litigation.
As will appear later, the contention was
that the Moletele could well afford engaging an expert and would be
reimbursed if it was
entitled to continued funding.
12.
The court subsequently heard the parties on
the separation issue, the necessity of the Minister pleading and the
continued funding
of the main claimant’s legal costs by the
Commission. On 3 July 2020 the court ordered a separation, but
only in respect
of Telkom and directed that it was unnecessary for
the Minister to file a plea.
13.
Also on 3 July 2020 the court issued the
following ruling and directions which are relevant to the present
application and counter
application.
“
7.
The Main Claimants are required to state in writing by 31 August 2020
which cadastral units that have been Gazetted
fall within “the area between Klaserie river and Olifants river
and Blyd river encashment area and all the areas bordering
the
Drakensberg mountain escarpment”
8.
Each of the claimants is required to state in writing by 31 August
2020
which of the cadastral units that have been Gazetted
a.
are not subject to any claim;
b.
are no longer being claimed
c.
are accepted as non-restorable;
9.
Each of the witness statements of each of the claimants must contain
a clear
and concise statement, in chronological order where
applicable, of the following;
……
.
“
(emphasis
added)
14.
Among the
issues to be dealt with in the witness statements referred to in para
9 of the 3 July ruling and directions were:
“
2.
In respect of each element the witness statement shall identify the
specific claimed property to which
the material fact relates,
such
property or fact being identified by reference to
;
a.
the cadastral information registered at the relevant Deed Registry
office
;
b.
the portions of the claimed farm to which the witness’
statement relates,
according to the cadastral portions
as they
existed at the time of dispossession and also their present
descriptions; the specific paragraph in the report of Professor
Delius;
…
..
4.
In relation to the
properties published in the Gazette
but which either were not
mentioned in the claim form to which the witness’s statement
relates or were not verified in the
referral report;
a.
The material facts on which a claim in respect of such property is
persisted with;
b.
The material facts to support a claim to the property in question
(emphasis
added)
15.
It will be evident from these extracts of the ruling and directions
of 3 July 2020 that the main claimants were required by
31 August
2020 to have dealt in their witness statements with all the land that
had been gazetted even if it had been omitted from
the referral
and to limit the issues in respect of the land gazetted in respect of
both the main claimants and the competing
claimants by identifying if
any of the land gazetted is either not subject to any claim, is no
longer being claimed and equally
importantly is accepted as
non-restorable. The latter is important as any land which is accepted
as not restorable releases the
landowner from the litigation and from
the restrictions imposed by s11(7) over the land, the issues being
solely between the claimants
and the Minister.
16.
It will also be evident from the 3 July rulings and directions that
once complied with, the case would be well on the way to
trial
readiness. Even the aerial photographs had been obtained while
outstanding expert reports would still have to be provided
and
meetings between the experts arranged.
17.
The court then heard the application to review the refusal of
the Commissioner to continue funding the litigation costs
of the main
claimants. Of relevance is that the main claimants had also sought a
stay of the entire proceedings until the final
outcome of their
review through appeals, which, if permitted, would have delayed the
finalisation of the pre-hearing further.
18.
On 1 February 2021 the court dismissed the review application and
made the following order:
“
1.
The application brought by the first
claimant, being the Moletele Community, to stay the proceedings under
the above case numbers
pending the outcome of its review application
is dismissed.
2.
The application to review the decision of the Land Claims
Commissioner of 9 July
2020 withdrawing the arranging of legal
representation for the first claimant at the expense of the
Commission on Restitution of
Land Rights under
section 29
(4) of the
Restitution of Land Rights Act 222 of 1994
is dismissed.
3.
The first claimant is to pay the opposed party and party costs of the
Land Claims
Commissioner and the Steyn Group of landowners, and in
the case of the Land Claims Commissioner such costs shall include the
costs
of two counsel.
19.
A number of oversight pretrial conferences were held to deal
with issues raised by the parties regarding extending times and the
inadequacy of responses. However on 30 September 2023 the main
claimant’s attorneys filed
a”
Notice
of a Land Surveyors Report
” which
the main group of landowners contended (subsequently in a practice
note in April 2024) enlarges the Moletele claim
by almost 50%. The
main claimant’s attorneys had also requested confirmation
from the Commission that ”
all the
owners of properties falling within the boundaries of the land claim
have been given formal notice of the claim”.
20.
The pretrial conferences of 16 May and 12 August 2024 dealt with the
issues raised by the main claimants’ notice of September
2023
initially by way of directions and, when not complied with, by way of
the order given on 12 August.
21.
Mr Notshe for the main claimants accepts that they had not
complied with the direction of 16 May but contends that the
order of
12 August was complied with. The Commission challenges that the order
of 12 August has been complied with and opposes
the application for
condonation as to both the adequacy of the explanation for the
failure to comply with the direction and the
merits of their case for
not being obliged to respond to the directions (of 16 May) or the
order (of 12 August) in a manner other
than that contained in their
Notice of 12 September 2024.
22.
The terms of the directions and order which the main claimants were
to comply with and their response by way of the Notice of
12
September will now be set out.
THE
COURT DIRECTIONS AND ORDER AND THE MOLETELE NOTICE
23.
The directions of 16 May 2024 were that:
By
30 May 2024 the main claimants will indicate
whether they wish to add additional land to their claim, and should
they wish to do
so all such additional land will be identified in the
process.
T
he
main claimants were to identify all such additional pieces of land in
an application or process they intended to take by 30 June
2024
Unless
there are special circumstances no additional land may be included or
sought to be included after 30 June 2024.
24.
The order made at the pretrial conference on 12 August provided
that:
“
B
y
Friday, 13 September 2024, the main claimant will identify if there
are any additional pieces of land claimed to those that have
been
gazetted.
A
failure to do so will preclude the main claimant from contending that
there is any other additional piece of land that ought to
be claimed,
and that if they do so they will have to bring a substantive
application, including an application for condonation.”
25.
On 12 September the main claimants sent the
following notice;
“…
be
pleased to take notice that the main claimants in the above mentioned
matter are unable to comply with the directives given by
Judge Spilg
on 16 May 2024 and 12 August 2024 because the aforesaid directives
are invalid for the following reasons:
1.
The aforesaid directives were issued at a case management meeting
presided over
by Judge Spilg.
2.
Judge Spilg gave directives to the effect that the main claimants
should give
notice to indicate whether they intend to extend their
claim to include areas covered by the land surveyors report. In the
event
that the aforesaid claimants wished to extend their claim
they should institute an application to that effect.
3.
The Judge further directed that in the event that the aforesaid
claimants do
not institute such an application they will be prevented
from leading their expert evidence of the land surveyor.
4.
The directives given by Judge Spilg go to the substance of the
dispute between
the parties,
5.
The powers of a Judge presiding over a case management meeting are
limited to
procedural issues in the case. They do not extend to
substantive issues. The substantive issues are dealt with in the form
of pleadings
so that an order of court can be granted or refused.
6.
In the circumstances the directions issued by Judge Spilg are ultra
vires his
powers as a Judge presiding in a case management
meeting.
7.
Accordingly Judge Spilg issued the directives ultra virus his powers,
and the
directives are invalid.”
26.
At this stage it is
necessary
to point out that the notice does not comply with any of the
operative parts of the respective directions and order which,
as will
be demonstrated, followed an undertaking by Mr. Madlanga in the
presence of his attorney (via remote hearings);
23.1.
firstly on 16 May, that the main claimant would identify
whether it wished to add additional
land to its claim by 30 May 2024; and
23.2.
subsequently on 12 August, that the main claimant would identify by
13 September
2024 any additional pieces of land claimed to those that
have been gazetted
27.
It is also necessary to point out that the
notice in its terms seeks to attack the validity of the directions
and orders but does
not constitute an application to declare them or
any part of them invalid.
This
raises the issue of whether it is competent to ignore a court order
on grounds of invalidity absent a successful application
to
declare it invalid. This court understood it to be a trite
proposition that a court order must first be set aside if a
party
believes that it is ultra vires, for otherwise it undermines
court processes and is no different than taking the law
into one’s
own hands
[5]
.
28.
In
putting the
notice in context, the court again refers to the sections of the Act,
and now their counterparts in the Land Court Act
6
of 2023
, as well as the court rules in
relation to the holding of conferences.
APPLICATIONS
BEFORE THE COURT
Main
Claimants’ Condonation Application
29.
On 17 January 2025 the main claimants
brought an application seeking condonation. This related only to
their noncompliance with
the 16 May directions, claiming that they
had complied with the 12 August order.
30.
In their application the main claimants
aver that at the conference held on 16 May 2024 they were directed to
indicate by 31 May
2024 whether they persisted to claim land as
indicated in the boundary lines marked on their land surveyor’s
map and that,
if so, they should institute application proceedings to
that effect by 30 June 2024.
31.
In
their founding affidavit the main claimants also referred to the
subsequent conference of 12 August. They said that at this meeting,
it was explained that non-compliance with the directive of 16 May was
because their legal representatives were unable to
take
instructions since they had not received the minutes of the earlier
meeting. They add that the land claimed “
was
described in the historical names and not the current description of
the properties”
[6]
.
32.
The main claimants also averred that at the
16 May case management meeting they had adopted the position that any
party who wished
to raise an objection to the admission of their land
surveyor report, which they intended using at the trial (to
determine
the extent of the land claimed) should do so in the form of
a notice and that the issue would be dealt with by the trial court.
33.
While
this may have been the position initially taken by the main
claimants, certainly after Mr. Dodson on behalf of the Commission
had
indicated at the 16 May meeting why it believed that such a course
was impermissible and that there were cost risks if persisted
with
[7]
, Mr. Madlanga on behalf
of the main claimants (and as stated earlier, with his attorney
on-line) when asked to respond to
Mr. Dodson said:
“
Thank
you, Judge. Judge, what I should say is that I am in your lordship's
hand on this one now. After having heard advocate Dodson
submissions,
I am in your Lordship's hands. Thank you.
The
court then responded:
“
No,
no. Advocate Dodson is saying that your client must either say that
they are not pursuing these additional claims, or they are.
So, by
when do you want to respond to that? Advocate Dodson and Advocate van
der Merwe have referred to case law which they
say indicates
that it is not permissible.
So I
would like to give you an opportunity and your client an opportunity,
to consider whether or not these are going to be retracted
or not,
and if not, to provide a time by when you will bring an application
to have them introduced
, clearly
identified, but that is going to be the last opportunity so that
everything needs to be sorted out one way or another.
Either there is
an acceptance of the position as contended for by the other parties,
and if not, then an application needs to be
made to introduce these
claims before a court, or whatever the process is, but we need
timelines….
…
So,
you can identify, and if on consideration of case law … that
it is not possible, well, then that ends that. But if you
believe
that … these should be pursued, then they have got to be
pursued by a particular time after that.”
Mr.
Madlanga replied:
“
Can
I then request … that the date for the indication, whether
this is pursued or not, be 30 May.”
34.
The court was amenable to the request and
added, that if the alleged extended area was being pursued, the main
claimants were to
indicate the steps they needed to take to introduce
them into the claim; whether they needed to direct the Commissioner
to Gazette
such land or whether it is to be done by way of an
application for direct access or by way of any other appropriate
application
or process to enable any additional pieces of land to
form part of the referral and that this was to be done by 30 June.
Mr.
Madlanga said that he was happy with that date.
35.
The
court then summed up that the main claimants were to identify all
such additional pieces of land in such application or process
as it
intended to take by 30 June, failing which, unless special
circumstances existed, no additional land may be included or sought
to be included after that date. The court adding “
everyone
needs clarity and we need a cutoff.”
[8]
36.
The main claimants contend that, what they
refer to as the case management meeting of 12 August, the court was
informed that the
surveyor report did not extend the extent of the
claim lodged by it and that the report on the description of the
claim was based
on “
the historical
names of the land and not the registered names.
”
37.
The founding affidavit in the condonation
application then purports to records that the court directed the main
claimants to indicate
by 13 September 2024 “
whether
or not there were any additional pieces of land added to the claimed
land
.”
This
is incorrect. The transcript reads as follows in relation to
the direction and order made at the case management meeting
of 12
August :
“
That
by Friday, 13 September, the main claimant will identify if there are
any additional pieces of land claimed to those that have
been
gazetted. A failure to do so, and I am making that as an
order. A failure to do so will preclude the main claimant
from
contending that there is any other additional piece of land that
ought to be claimed. And that if they do so, they will
have to
bring a substantive application, including an application for
condonation.”
Immediately
after this was read out, the transcript records the following
exchange between the court and the main claimants’
counsel:
“
COURT
:
Mr Madlanga, have you got that?
MR
MADLANGA
: Yes, Judge, I
got it. Thank you.
COURT
:
Right, no waiting for minutes. This is my order. It has
now been given. It is a direction and an order.
Okay.
So, now we have covered that.
The
court then moved onto other items on the agenda.
38.
It is evident from the exchanges on 12
August that the court wished to ensure that the main claimants’
legal representatives
acknowledged that the terms of the
direction and order had been noted.
39.
It is equally clear that the court was not
concerned with how the claim form described the land, which may lead
to an obfuscation
of the issues then before the court, but whether
the main claimants were contending for any land in addition to that
described
in the Gazette notice.
The
point being; however land is described in a claim form, it is the
responsibility of the RLCC
[9]
,
to identify the claimed land by reference to each of its
cadastre recordings (i.e. the title deed description at the relevant
Deeds Registry) and the identity of its registered owner in each case
so that the Gazette notice required under s 11(1) of
the
Restitution of Land Rights Act 22 of 1994 (“
the
Act”)
can
be published.
40.
This is expressly provided for in
Commission Rule 13(1) which requires that the s
11(1) notice sets out,
amongst others, the title deed
description , its extent, the title deed number, the name of the
current registered owner
and any other detail that would help
interested parties in the identification and location of the property
that forms the subject
matter of the claim.
Section
11(6) also requires the RLCC to give written notice to every
landowner, and any other party who may have an interest in
the claim,
of the publication of the notice and refer that person to the
restrictions on disposal, development (including rezoning)
or
encumbering the land, and those affecting the
status quo
,
including the continued occupation by a land claimant or the
improvements on the land.
41.
The scheme of the Act in so far as it
concerns the extent of this court’s jurisdiction in restitution
claims is straight forward.
Firstly,
the court exercises jurisdiction only in respect of land claims which
were lodged no later than 31 December 1998, subject
to the provisions
of the Restitution of Land Rights Amendment Act 15 of 2014 (“
the
Amendment Act”
) should it be reenacted (which extends that
date to 30 June 2019).
Secondly,
in relation to referrals by the Commission under s 14 of the
Act, which is the process by which the present
claims are
before the court, the court enjoys jurisdiction to determine
restitution matters in respect of land which has been identified
in a
Gazette notice published under s 11(1) . The RLCC has the power to
withdraw or amend the s 11 (1) Gazette notice by including
or
deleting land provided it was described in the claim form lodged
before the December 1998 cut-off date (again subject to the
30 June
2019 provisions of Amendment Act if it is reenacted).
42.
This
can only be lawfully effected under the Act through s 11A and
provided its provisions are complied with. This includes
giving any
affected party an opportunity to be make representations
[10]
.
In the case of additional land being gazetted , the RLCC may do so
without giving notice if there was an obvious error in the
original
s11(1) notice or in every other case by giving notice and calling on
affected parties to make representation before publishing
a notice to
include additional land in a gazette notice.
43.
All these steps by the RLCC to give notice
under s 11(1) or to subsequently include additional land under
s11A is without
prejudice to any competing claimant or landowner’s
rights to challenge the claim on any competent ground, including that
the land claim never included the land which was gazetted.
44.
Makhuva-Mathebula Community v Regional
Land Claims Commissioner, Limpopo and Another
[2019]
ZASCA 157
is directly in point on the question of the land
description contained in the claim form. In that case the RLCC had,
during its
investigations, queried an anomaly between the land
identified in the claim form and the contents of an attached map. On
receiving
the reply, the RLCC was satisfied that the claimant had
intended to claim only the land identified in the form itself. The
Supreme
Court of Appeal held that the claimant was bound by its
description of the land as set out in its claim form and the answers
given
by it to the RLCC during the latter’s investigation of
the claim; it could not add to the land that had been so identified
and
then
gazetted.
In
the present case the main claimants do not dispute that there
was a process of investigation which preceded the gazetting.
In their
condonation application Mr Chiloane, who is a member of the land
claims sub-committee of the Moletele CPA, which authorised
bringing
the application by resolution of the CPA, said that;
“
the
land claim was described in the historical names and not by their
current description of properties”
[11]
45.
In its answering affidavit the RLCC, Mr
Maphutha, stated that
the claim forms
comprised a number of documents. These were provided to the court.
They comprised annexes RR1 to RR4 of the Referral
Report.
The
RLCC
submitted that the;
“
farms
were claimed with express reference to particular farm names as
reflected in the cadastre. This then formed the basis upon
which
farms were published in the Gazette notices. A generous approach
favouring the applicant and competing claimants was adopted,
so that
the Commission erred on the side of inclusion of farms where the name
of a farm in a claim form was unclear. I am therefore
confident that
all land which may be subject to the claims has already been included
in the Government Gazette notices. Farms not
included in the Gazette
notices do not therefore fall within the claim.
This
statement is found in para 17 of the answering affidavit.
46.
Furthermore, the RLCC referred to the
process of gazetting and referring the claim to court. After the
initial referral, which was
bad and withdrawn due to challenges by
landowners, a process was adopted which extended over a period of
years where all the parties
were represented by attorneys and counsel
and they all sat down and agreed exactly which farms would be
published in the Gazette.
The gazetting itself was done in phases.
47.
It was also averred that this process
was conducted on the basis of complete transparency and co-operation
between the parties “
including the
applicant
(i.e. the present main
claimants)
, which was legally
represented by attorneys and counsel throughout”
48.
Three relevant Gazette notices were
published identifying the land subject to the claim. They were the
Gazette notices of 1 August
2008, 28 January 2010 and 24 December
2010.
This
is dealt with in paras 16 to 19 of the answering affidavit
49.
In its answering affidavit the RLCC also
referred to an analysis done of the farms identified in the
Moletele surveyor’s
report. The most important aspect is that
there are a large number of new farms which have not been
gazetted at all and therefore
could not form part of any referral to
this court. This is set out clearly in paras 18,19 and 22 of the
answering affidavit with
the analysis set out in annexure LHM11.
50.
Another aspect pointed out by the RLCC
is that the parties, including the main claimants, through their
legal representatives at
the meetings mentioned earlier, had
agreed not to include all the farms that are identified in the
Gazette notices and that
these would form the subject matter of a
later referral. An explanation for this has been provided earlier in
the judgment. In
short, the referral before the court concerns farms
which essentially constitute white owned land and exclude farms which
were
designated for occupation under the then Trust and Land Act.
This is set out in para 21 of the answering affidavit.
51.
It also bears mentioning that during
the pretrial conference of 16 May, which is relevant to the
issues now before me, Mr.
Dodson expressly referred the main
claimants to what he contended were a number of problems facing
them if they sought to
extend the claim.
Among
the difficulties mentioned was that none of the Gazette notices
included the farms which appear in the Moletele surveyor’s
report and that there are judgments which prevent the main claimants
from doing so. The other was that the main claimants were
impermissibly going behind agreements that were reached at binding
pretrial conferences; reference being made to the process where
over
a period of years the legal representatives of the parties had agreed
on exactly which farms would be included in the Gazette
notices after
the original referral was withdrawn.
52.
The court has set out in some detail the
relevant paragraphs in the answering affidavit where the issue
regarding the identification
of the land in the claim forms was set
out and the circumstances surrounding the identification of the land
and the extent of the
present referral, with the RLCC concluding that
if any piece of land now appearing in the Moletele surveyor’s
report was
not contained in any Gazette then it could not be
the subject matter of a referral and therefore could not be subject
to the jurisdiction
of this court.
53.
These
material allegations contained in paras 16 to 22 of the
answering affidavit, and for which adequate chapter and verse
was
provided to enable the main claimant to respond, were all dealt
with in six lines by the main claimants. Their reply
reads as
follows
[12]
:
“
11.2
AD PARAGRAPHS 16 TO 22 THEREOF
I
do not wish to deal with the allegations made in these paragraphs
until the issue of the regularity of the counter application
has been
dealt with. I however state that the allegations made in these
paragraphs are denied. The claimed land was described in
general and
historic terms. This is an issue that can only be resolved through
oral evidence.”
.
54.
In addition the claim forms have been
produced to court. It is evident from them that land was described by
reference to the farm
names and in most cases their cadastral
reference. Para 1 of each claim form required the main claimants to
identify if the
land claimed was rural or urban and if rural (as
confirmed by them it was) para 1.1 required them to insert “
If
it is rural land, the portion(s), name(s) and number(s) of the farm
and district”.
The
main claimants replied in the claim form of 3 July 1995 by
identifying farms by name and generally added a number (e.g.
Buffelshoek
216 or Camdebon).
In
another claim form also dated 3 July 1995, para 1.1 was answered by
referring to an attachment marked annexure B. The attachment
referred
to some 32 farms listed by name and divided into farms occupied by
other tribes and farms occupied by whites.
In
the subsequent claim form of 8 November 1995, the main
claimants identified farms by name and number (e.g. Eden-Fleur de
Lys.194, Moriah.83KU) and then ended with “
Epsom-189,
all (14) farms, others for negotiation
”.
Finally
in a claim form dated 22 July 1998 an additional farm was identified
being Blyderivierpoort 595 (possibly 545) KT.
55.
To these must be added two sets of
correspondence which are included in the claims forms set .
The
first is from Mrs D Gilfillan on behalf of Legal Resources Centre
(then representing the main claimants), to the Chairperson
of
the Advisory Committee on Land Allocation dated 30 July 1992. It
states the following:
“
The
land involved in the claim comprises the following farms:”
The
list consists of 25 farms which appear to be included in the
subsequent claim forms. In the Legal Resources Centre letter, the
farms are identified and save on three occasions the identity of the
registered owners are included. Attached to the letter is
an historic
background which identifies 29 farms by name. It appears that these
were cross-referenced into the body of the main
letter.
The
other is a letter from the Moletele Local Government Authority to the
Minister of Land Affairs dated 9 September 1994.
It
commences in general terms by stating:
“
The
areas affected the area between Klaserie river and Olifants river and
Blyd river encatchment area and all the areas bordering
the
Drakensberg mountain escarpment.
It
then states:
“
The
following are the names of farms which previously belonged to us
and
please the fact that there might be name changes to these farms need
be mentioned
.”
(emphasis
added)
Then
follows a list of 30 farms, all of which appear to have been included
in the subsequent claim forms. In any event, the
main claimants do
not dispute the averments contained in the answering affidavit that
the land as identified in the correspondence
and claim forms have
been duly gazetted pursuant to a process of agreement with the main
claimants and their legal representatives
and that this had taken
place over a number of years.
56.
The replying affidavit was delivered on 7
February 2025 and the matter heard on 14 February.
The
allegations made in the answering affidavit are self-evidently
germane to whether or not a case has been made out for condonation.
57.
It is trite that a condonation application
must traverse the failure to comply with the court order timeously,
including the
failure to comply with an undertaking given to
the court to provide the necessary responses on time, and also must
deal with the
merits of its defence, which in this case is its
challenge the orders made; namely that the directions and orders of
16 May and
12 August 2024 are
ultra
vires
the courts powers as set out in
the main claimants’ notice of 12 September 2024.
58.
It is also trite that whatever a party’s
view of the competency of a procedure, it must plead over.
59.
The
main claimants have sought to provide the court with an explanation
for their failure to comply with the court direction
of 16 May,
claims to have complied with that part of the court order of 12
August which required it to identify by 13 September
2024 any
additional pieces of land claimed to those that were gazetted,
and have offered no defence to the merits as to why
they are not
bound either by the directions or the orders of 16 May and 12 August
save to contend that these are
ultra
vires
the court’s powers.
[13]
60.
As
already stated, it is trite that a party in application proceedings
must plead over. It is also trite that a failure to engage
in the
merits amounts to an acceptance of the allegations of the other party
where final relief is sought (
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984
(3) SA 623
(A) at 634 to 635
[14]
)
and that a bald denial is inadequate, save in cases where the
information is not within that person’s knowledge or in the
other circumstances set out in
Room
Hire Co.
(Pty)
Ltd v Jeppe Street Mansions (Pty) Ltd
,
1949 (3) SA 1155
(T), which is a case that does not involve the
seeking of final relief..
61.
The reason is obvious as to why the court
required to know, before the matter could be ripe for trial, if there
was any land which
the main claimant intends to claim in addition to
that already gazetted.
62.
In terms of the Act the court can only
exercise jurisdiction in respect of land which has been gazetted.
If
any substantive rights are affected by allowing a matter to proceed
to trial before such land has been gazetted and notice given,
it is
those of every person who has an interest in the land in question and
who has not prior to the trial been given adequate
notice
[15]
.
And
a failure to give notice by way of application to court for
direct access or otherwise in good time
before
the trial date
will result in a postponement of the trial to the prejudice of the
other parties in relation to costs. It is necessary
to point out that
costs will be substantial if the trial is postponed after the
first day.
63.
Firstly,
the parties have estimated that the trial will run for three to six
months. There are some nine teams of lawyers
[16]
which often include senior and junior counsel. Accordingly the trial
sessions will have to run for several weeks at a time and
accommodate
the diaries of a large contingent of legal representatives and court
personnel, paid experts have to be available and
paid as do counsel
and their attorneys, transport and accommodation must be provided for
most if not all.
Moreover
court resources will be wasted and unnecessary costs incurred, in
particular if the case is to commence in the area of
the claim where
the communities reside. This includes the Hoedspruit, Blyde River and
Thornybush areas. Those costs, as pointed
out by Mr. Dodson at the 16
May 2024 pretrial will be sought from the main claimants. This risk
in fact precipitated the main claimants
to agree to provide the
information by 30 May.
64.
In
addition there is the further delay which an application at the
commencement of the trial would occasion in a matter that should
have
long since been trial ready.
[17]
In
this regard the court cannot ignore the complaint formally lodged by
the competing claimants, the Mnisi Community represented
by Mr.
Maluleke, who already at the 16 May 2024 conference expressed
opposition to any issue which could delay the matter coming
to trial.
He indicated that their witnesses were old and some had already died
and that whereas the main claimants had already
received large and
valuable tracts of land, the competing claimants had yet to have any
land claim determined despite the years
that have intervened since
their claim was gazetted.
The
court also cannot simply ignore the complaints of the various legal
teams who between them represent over 500 landowners. They
say that
after all these years since the matter was gazette and then referred
to court they are entitled to have finality without
unnecessarily
incurring costs.
65.
The only way in which the matter can
properly proceed if a claimant wishes to add land not gazetted after
a s 14 referral
appears to be by way of direct access. That is
a process which, if the land is only identified for the first time on
the first
day of trial, will result in a postponement to enable due
process to be initiated under the direct access to court provisions
which
are contained in Chapter IIIA of the Act.
And
the first days of trial are likely to involve the inspection in loco
which the parties anticipated would stretch over a period
of more
than two weeks. This would mean that all the legal teams with all
their experts would have to be in attendance and would
have been
required to set aside the full period, the fees for which would
presumably have been negotiated upfront. The claimants’
members
[18]
involved in the
trial and at the inspection as well as individual defendants would
also have to attend court.
66.
In short; the matter can therefore never be
ripe for hearing if there is still land which is sought to be claimed
in these proceedings
and which has not been gazetted.
This
court can therefore not permit the matter to be set down for trial if
that is the case. However, due to the lengthy delays
in this matter,
the court also can no longer delay setting the matter down for
trial if a party fails to comply with its
own undertakings, or
court’s own directions and orders.
67.
In this case, the first direction affecting
the land which is subject to the present referral was given
almost five years
ago at the pretrial conference held in July 2020
(the court dealt earlier with relevant aspects of that conference).
It is also
difficult to appreciate how the witness statements
required in terms of the directions and rulings given at that
conference can
fulfil their intended purpose unless they deal with
only gazetted land before the case can be trial ready.
68.
All this must be known to the main
claimants’ legal team who practice in this court. If the land
was always subject to the
claim as contended for, then either it is
included in the Gazette notices that have already been published or
the main claimants
would have been expected to raise the issue of
outstanding land either during the cursory investigative phase which
preceded the
s 11(1) gazetting or during the s 11A or s 12
investigation phases prior to re-publication of the Gazette Notices.
Furthermore
the main claimants would have had the opportunity to do
so during the case management process conducted by Gildenhuys J, if
not
during the discussions between the parties and the Commission
themselves.
If
land was sought to be introduced at the pre-gazetting stage then the
RLCC would be entitled to gazette it as land falling in
the claim
provided the s 11(1) threshold was met, or if the RLCC had considered
the claim to an area of land to be frivolous or
vexatious then he or
she would have dismissed the claim (see s 11(3)), or if the criteria
of 11(1) were not met then the
RLCC would not gazette it and
would advise the claimant accordingly.
69.
An
attempt to approach a court on the first day of trial (which it is
now clear the main claimants intended to do at least after
12 August
after submitting at the one of 16 May to the position taken by the
Commission, the competing claimants and the landowners
[19]
)
to include land which was not previously Gazetted as part of the
claim therefore by-passes all the checks and balances that the
Act
has put in place to ensure that land claims are only referred to
court after a proper investigation phase, placing it in the
hands of
the RLCC to decide whether the required threshold has been met before
a court is seized with the matter and allowing for
an investigation
by the Commission before that occurs. This too would be known to the
main claimants’ legal representatives
during the years when the
land to be gazetted and the referral itself was ironed out during
meetings with them and with their agreement.
70.
On
the basis of the uncontested statements by the RLCC in the answering
affidavits, supported by similar statements at the pretrial
conference of 16 May 2024 which went unchallenged
[20]
,
the land identified in the claim was gazetted and this was pursuant
to a process of investigation and agreement by the parties,
including
the main claimants who were at all relevant times represented by
their legal team.
REQUIREMENTS
FOR CONDONATION AND EFFECT OF NON-COMPLIANCE WITH AN ORDER OR
DIRECTION
71.
In
eThekwini
Municipality v Ingonyama Trust
2013 (5)
BCLR 497
(CC) at para 28 the Constitutional Court repeated the two
requirements which must be satisfied for the grant of condonation. It
said that: “
Two factors assumed
importance in determining condonation applications: The explanation
furnished for the delay and the prospects
of success.
”.
The court also explained that where the failure is over a period of
time an explanation is required to cover the entire
period of
default.
72.
Although a court appears to be
entitled to end the enquiry and refuse condonation when the
explanation for the failure to
comply is unacceptable, in
Minister
of Land Affairs and Agriculture and Others v D & F Wevell Trust
and Others
2008 (2) SA 184
(SCA) at
para 41 Cloete JA on behalf of the court, after finding the
explanation for the failure to comply with the time limit
unsatisfactory said that “
In all
the circumstances, a demonstrably good case on the merits would be
required before condonation could be considered
.”
73.
Under s 25(5) of the Land Court Act 6 of
2023, which came into effect on 5 April 2024, the court at a
conference may issue such
orders and directions as to the procedure
to be followed before and during the trial as it deems appropriate.
In terms of
Rule 30 which deals with conferences the
presiding judge at a conference may make any interlocutory
order or give any
direction which the court may make or give under
any provision of the rules and may investigate any non-compliance
with the rules
or with any
order or
direction previously given in the matter and give such orders or
directions in relation thereto as may be just, including
an order for
costs or a postponement of any hearing. In addition, if any party is
present at a conference where an interlocutory
order or direction is
applied for informally, no further notice of the application needs to
be given to that party, unless the
court directs otherwise.
74.
The types of orders or directions which a
court can give under the rules in relation to non-compliance with an
order or direction
is to
inter alia
strike out the claim, defence or response of the defaulting party,
whereupon that party will no longer be entitled to exercise
the
rights to deliver or file documents, participate in or be represented
at the hearing, apply for leave to appeal or participate
in any
appeal against any order of the court unless the court orders
otherwise. This is provided for in rule 32(7) read with subrule
(5)
and rule 26(2) which deal with the right to participate in a case.
Accordingly
the Rukes themselves, as do all rules of Court provide that a party
may be deprived of a right to proceed if in default
of the rules
themselves, or of an order (or as with the Land Court a direction) of
the court.
THE
DIRECTIONS OF 16 MAY and ORDER OF 12 AUGUST 2024
75.
The main claimants have only dealt with the
failure to comply with the direction issued at the pretrial
conference of 16 May which
required
them to
identify all such additional pieces of land by 30 May and pursue such
application or process as they intended to take in
that regard by 30
June, failing which, unless special circumstances existed, no
additional land may be included or sought to be
included after that
date.
76.
It is common cause that the main claimants
did not identify all such additional pieces of land either by 30 May,
30 June or at all.
This notwithstanding being given a further
opportunity on 12 August to expressly identify by 30 September
if there are any
additional pieces of land claimed to those that have
been gazetted, and despite the conversion of the direction into
a clear
order of court which, also on 12 August, the claimant’s
counsel acknowledged had been noted by him, this being all done with
the main claimants’ attorney in attendance.
77.
In addition the time limit to provide the
information was not imposed on the main claimants- and this was not
the first time the
main claimants were asked to make it clear whether
they intended to add land which had not been gazetted to the claim.
78.
The history of the court’s direct
involvement in the identification of the land in issue arose in April
2024 when attorneys
for one of the main groups of landowners, CHM
Steyn, compiled a practice note (which was in effect their addendum
to a practice
note prepared by Mr Dodson on behalf of the
Commission).
I
take the note up from after Gildenhuys J had been brought in to case
manage the matter by giving guidance after a court order
had been
brought by the landowners in about 2005.
“
One
of the important issues which was addressed at the early pretrial
conferences was to establish the extent of the claim. ….
The
matter was thoroughly debated and considered, and the parties came to
a clear and binding agreement as to what extent the claim
would be,
and to what extent it will be limited with reference to the area
claimed.
For
the last circa 16 years everyone involved in the Maruleng land claim
honoured the agreement referred to above.
On
29 September 2023, out of the blue, Ngoepe attorneys on behalf of the
Moletele’s filed a” Notice of a Land Surveyors
Report”
containing a map which enlarges the Moletele claim by almost 50%. ….
Mr.
Ngoepe further requests confirmation from the Commission that”
all the owners of properties falling within the(new?) Boundaries
of
the land claim have been given formal notice of the claim”
it
is our submission that the claim cannot be extended now- and it is
obvious that the new judge should clarify the situation as
a matter
of urgency.”
79.
By this stage the matter had been handed
over due to my imminent retirement. In view of these developments I
was amenable to continuing
running pretrial conferences due to my
knowledge of the matter.
80.
At the pretrial of 16 May, Mr. Du
Plessis, who is counsel for one of the main groups of landowners,
raised the issue of whether
the main claimants were extending their
claim beyond that identified in the Gazette and the Referral Report.
Mr. Dodson contended
for the Commissioner that any attempt at this
late stage to incorporate a huge swathe of new land must be stopped
on at least three
bases. He claimed that although he had only dealt
with a portion of the main claimants’ land survey report, a
large number
of new farms had been introduced.
81.
Among the grounds raised by Mr. Dodson is
that it was unfair to expand the claim, particularly in relation to
the competing claimants
who are sitting waiting patiently to have
their claims adjudicated and have not obtained any land in the way
that the main claimants
have. He said it was unfair too to the
landowners who have been waiting for 20 odd years to get the matter
resolved. It was also
unfair to the Commission who have spent hours
basically in the middle trying to make the claim manageable.
Mr
Dodson
then set out the grounds mentioned
earlier which included the
Makuwa-Matebula
judgment of the Supreme Court of Appeal. He also contended that the
farms which had been gazetted and to which the referral related
did
not include all the farms identified in the survey report sought to
be introduced by the main claimants and then referred to
the
impermissibility of breaching agreements reached at pretrial
conferences which were binding.
This
was supported by Mr. Maluleke for the competing claimants. Mr. van
der Merwe, for other land claimants, also took the point
that by
reason of section 14(6) of the Act the court’s jurisdiction is
effectively precluded unless the Commission has referred
the matter
to it. He also expressed concern that the additional land now
identified may already have been the subject of other
restitution
claims and could therefore also impacted by s 35(1).
82.
Earlier I mentioned the exchange where Mr.
Dotson referred to the cost risk which the main claimants faced in
bringing any proceedings
to introduce additional ungazetted land
later.
83.
In view of the position taken opposing any
attempt to introduce additional land to the claims, the court engaged
Mr. Madlanga as
follows:
“ …
I
would like to give you an opportunity and your client and
opportunity, to consider whether or not these are going to be
retracted
…, and if not, to provide a time by when you bring
an application to have them introduced, clearly identified, but that
is going to be the last opportunity so that everything needs to be
sorted out one way or another. Either there is an acceptance
of the
position contended for by the other parties, and if not, then an
application needs to be made to introduce these claims
before a
court, or whatever the process is, but we need timelines.
Mr.
MADLANGA; “Just to be clear … is the question that we
should come up with a date as to when the claimants will
indicate
whether they are proceeding with the claim as allegedly extended, or
they are taking out the impugned extension, And then
the application,
if the claimants decide to proceed with it, it is another date?
When
the court agreed, Mr. Madlanga then requested that the date
when the main claimants would indicate whether they were
pursuing an
extended claim could be 30 May.
84.
After both Mr. Dodson and Mr. du Plessis
address the court, it added that should the land claimed extend to
include land not previously
gazetted and not subject to the Referral
Report then the main claimants would be obliged to bring an
application or appropriate
process to enable these additional pieces
of land to form part of the referral and that this was to be done by
30 June.
85.
The court then added that unless there were
special circumstances, no additional land may be included or sought
to be included after
30 June. This was to ensure clarity and the need
for a cutoff.
86.
The
court is unable to accept that the main claimants were unaware of the
obligation they had expressly undertaken through their
legal team to
provide the information by 30 May or bring some form of proceedings
by 30 June, despite the extent of exchanges
on the subject
during the 16 May conference, despite the presence of both counsel
and the attorney there representing the main
claimants, and more
particularly the active engagement by counsel who was responsible for
requesting that the main claimants be
allowed to indicate by 30 May
whether or not they intend pursuing any additional land. The court is
also unable to accept that
despite notes being taken, as asserted was
done
[21]
, they failed to
comply.
87.
In correspondence the main claimants
attorney belatedly called on the court to provide the minute of the
16 May conference. The
court confirmed that it was not responsible
for drafting the minutes and never previously undertook that
responsibility. This is
due to resources and time constraints.
However
the notes which the legal representatives of the main claimants said
they had taken would have confirmed that Mr. van der
Merwe had
undertaken responsibility for drafting the minutes. If the main
claimants had any difficulty in trying to recall
what they had
undertaken to do by 30 May, then they only had to ask Mr. van der
Merwe or, for that matter, any other counsel or
attorney who had
attended. It is evident that the main claimants did not take either
the pretrial process seriously or, at
least since the 12 August
conference, had decided to ignore the direction.
88.
Whether the main claimants, through their
representatives had not taken the 16 May pretrial and its directions
seriously or were
deliberately disrupting the process through
non-compliance was a concern which required attention at the
subsequent conference
called on 12 August.
89.
At the 12 August conference Mr.
Madlanga offered the following explanation for failing to provide the
information by 30 May,
let alone bring appropriate proceedings by 30
June.
Judge,
on that point, on that issue, we could not take proper instructions
because we also needed to first get to the minutes of
the previous
meeting of the previous pretrial conference.
COURT:
Why? Don't you make notes during the course of a pretrial?
MR
MADLANGA: We do.
COURT:
I do. So, you knew what had to be done.
MR
MADLANGA: We do, Judge. But our view is that we should
get to the minutes so that we are sure that we properly convey
what
transpired in the meeting without just giving us, giving clients what
we captured, which may not be.
90.
But the issue of noncompliance in relation
to providing the necessary information or bringing appropriate
proceedings does
not end on 30 May.
The
extract provided earlier of the 12 August conference reflects that
the court now insisted that the main claimants make
their
position clear as to whether or not they sought to include land which
had not previously been Gazette. It also expressly
asked Mr. Madlanga
to confirm that he understood what was required. The court also made
it clear that this was no longer a direction
but an order.
91.
At the meeting of 12 August the exchanges
regarding the notification about any additional land was as follows
“
MR
MADLANGA
:… to say that
our preliminary view, without
having taken proper instructions, as I have just mentioned, is that
the report is not extending the
claim at all
.
Therefore, in fact, the expert who prepared the
report for the main claimants prepared it based on the description,
on the property
description that was given to him by the claimants.
It must be borne in mind that the claimants gave the historical
property
description and boundaries in some or most of the instances
in which they gave the property description of the claimed land,
which
may have caused the problems or the confusion that the claim is
being extended. Otherwise …[intervenes]
COURT
:
Okay.
So we are hopeful
that the land that has been gazetted is the full extent of land.
Is that what we are hoping will be the
result of a further discussion
with the community, but you cannot bind yourself to it
?
MR
MADLANGA
: As I say, Judge,
our view is that the land
claimed as gazetted is the same land as reflected in the report
.
The only confusion that may be
there may be as a result of the historical description which has been
given to the expert for him
to prepare the report. And our
submission is that whoever or whichever party that is opposed to the
report as it stands,
may just raise an objection to the admission of
the report as evidence insofar as those impugned parts of the report
are concerned
.
COURT:
No, no, it cannot work that way because we need, I need, the Court
needs to have absolute clarity before we go further
as to whether the
land gazetted is the land that is being claimed in these proceedings
.
(emphasis
added)
92.
The court then asked the other parties
whether they would be agreeable to
the
main claimants being given until 13 September to report back on
whether or not there is any additional piece of land to those
that
have been gazetted.
Mr
Maluleke voiced his objection as follows:
:
You should have started with me because this delay affects my
clients heavy and because each and every time we come here, there is
the delay which is caused by the main claimant, and they have got the
chunk of the properties transferred to them. I have
nothing.
And it is very worrying that they get postponement after
postponement, and it is not warranted
The
court then agreed to note Mr. Maluleke’s concern should there
be any further delays on the part of
the main claimants.
93.
In all the circumstances the main claimants
must have understood that it was now to take the court's order
seriously and that they
had exhausted the patience of at least the
competing claimant.
94.
Instead of complying with the order
informing the court whether they wished to include land that had not
been gazetted, the Moletele
gave notice that they would not comply
with the court order because of their view that it was
ultra
vires
the courts powers.
95.
It is not possible for any reasonable
litigant represented by a capable legal team to believe, having
regard to the relevant circumstances,
that the operative part of the
order which required the main claimants to in effect comply with the
undertaking that had been given
by their counsel as far back as 16
May could be ignored or that the court had not, as far back as 16 May
assisted the main claimants,
if they were entitled to add the land to
do so formally despite the objections of the other parties and the
Commissioner that it
was
per se
incompetent to do so.
96.
In short, the main claimants were given
every opportunity and opening to inform the parties and the court in
good time if they were
claiming in the referral, which was to be set
down for trial dates, any land which had not been gazetted and then
to bring
appropriate proceedings in good time.
97.
The main claimants have given excuses for
their failure, which are unacceptable. The answer is simply
that the main claimant
have since at least 12 August refused to
supply the information and still refuse to do so. And they offer no
explanation for their
continued refusal. They, through their legal
team, would also know that the trial cannot proceed if they
intend to include
land not yet gazetted and that delaying a trial
once set down for hearing would be at significant cost and delay to
all the other
parties.
98.
The
court concludes that the failure to provide the basic information
requested (and earlier I highlighted in bold counsel’s
statements at the 12 August conference), and then to contend
that the court acted
ultra
vires
in calling for the information when their counsel had undertaken to
provide it (let alone bring the necessary proceedings by dates
suitable to them), can only be explained as deliberately frustrating
the court’s functioning and disrupting the expeditious
bringing
of the claims to finality in the least costly and most effective way
as required by the Act and now by s 25 of the Land
Court Act .
[22]
99.
It is now apparent that the main claimants
consciously chose after further reflection to revert to their initial
position prior
to the Commissioner’s counsel indicating the
costs risks of pursuing what was contended by him and other parties
at
the 12 May pretrial to be impermissible under the Act.
100.
These
findings therefore make it incumbent on the
main
claimants to show, in the words of Cloete JA “
a
demonstrably good case on the merits … before condonation
could be considered
.
”
[23]
101.
The only defence raised is that the
direction of 16 May and the order of 12 August were
ultra
vires
.
102.
It is clear that the court has the power in
terms of the Act, and now the Land Court Act, and also the court
Rules to direct and
order a party to provide information or bring
appropriate proceedings in order to expedite and bring to trial
readiness a matter
in the least costly manner. The parties were heard
on the matter of providing the information which is the subject of
the 16 May
and 12 August directions and order, and the court
exercised its discretion which a litigant cannot unilaterally choose
to ignore,
let alone second guess.
More
so where there are other claimants and over 500 landowners who have
waited already twenty or so years for finality and at the
eleventh
hour are to be confronted, as a clear stratagem for whatever reason,
by the main claimants with the reality of further
delay and
unnecessary costs which the court, in the exercise of its judicial
discretion, is entitled avoid being incurred.
103.
In regard to the sanction if there is
non-compliance; simply put the court must be able to make effective
orders. It is no use continually
requiring a party to comply unless
there is an effective sanction. It is a sanction which only took
effect because the claimant
refused to take certain necessary steps,
which in this case it had agreed to at two conferences which were
held three months apart
from each other.
104.
The
sanctioning part of the directions and order were not final in
effect. Both provided that the main claimants could still show
cause
for non-compliance and of the merits of introducing any additional
land to that already gazetted. It was their election,
and in their
own hands, as to whether the sanction would be imposed. They only had
to comply with their undertaking to avoid such
consequences-
consequences which the court Rules permit.
[24]
This
appears from the general rules of court which preclude a party from
pursuing a claim or raising a defence if it fails to comply
with
court rules, orders or directions. The provisions of rule 32(7)
read with subrule (5) and rule 26(2), which have already
been dealt
with, are to this effect. The direction of 16 May and the court
order of 12 August fall within the application
of these rules and
their purpose.
105.
It is clear also that the parties had
agreed to separate the referrals. There is nothing to preclude the
main claimants from pursuing
any other claims for land which has not
been gazetted; just not in the present proceedings under the
Referral Report to which
it relates, and which must now be brought to
trial readiness and have trial dates allocated.
106.
Accordingly there were no grounds for
contending that the court directions and order were ultra vires and
the defences raised for
not complying with the operative part and the
subject matter of the directions and of the order of 16 May and 12
August fail.
107.
The condonation application is therefore
refused.
COUNTER-APPLICATION
108.
The
counter-application is brought by the Commission for an order
declaring
that the referral and the case number LCC 206/2010 shall be confined
to the farms listed in annexures NR1A and NR1B to
the notice of
referral.
[25]
109.
The main claimants object to the
counterclaim on the grounds that it is incompetent. It is not.
Save
by reason of common law exceptions, a respondent is always entitled
to bring a counterapplication, particularly if it concerns
the same
subject matter and evidence or point of law which requires
traversing. The rules of this court, which refer back to the
Uniform
Rules of Court where there is a lacuna say as much. The only
exception that comes to mind is in relation to spoliation
orders
where the requirement that no one may take the law into their own
hands overrides all other considerations.
110.
No such exception arises here, nor has Mr
Notshe been able to refer me to one. I therefore find that the
opposition to the counter-application
has no merit.
111.
Secondly, the main claimants were obliged
to plead over. A litigant is not entitled to take the risk that its
objection is sound
or that its objection must first be heard before
it is obliged to plead over. This is well established, for otherwise
it may feed
into the hands of those who seek delay when they have no
defence to the merits.
112.
In the main proceedings for condonation the
main claimants could produce no argument or case law to support a
submission that this
court has jurisdiction to hear a restitution
claim in respect of land which has not been gazetted. However the
claim form may have
been worded, the point remains that this court is
seized with a matter which must be brought to trial in respect of
only a claim
to land which has been gazetted.
And
there is no application or other procedure brought before this court
to bring any other piece of land within the jurisdiction
of the court
other than the land identified in the Gazettes, despite the main
claimants being given ample opportunity to
do so, whether
during the case management meetings held all those years ago before
Gildenhuys J or even up to a year ago.
113.
The main claimants have been well aware for
a number of years that the competing claimants are entitled to bring
their claim before
the court, and they can only do so within the same
referral which is presently before it and to which the main claimants
are also
a party. The main claimants are also aware that all
landowners are entitled to finality and that, but for them holding up
the proceedings
now for almost a year since 16 May 2024, this case
could have been trial ready.
114.
Any attempt by the Moletele to bring an
application or other proceedings that will introduce other pieces of
land not yet gazetted
into the present referral will result in
unwarranted and extended delay. They were given enough opportunity to
regularise their
position but instead took a decision not to and wait
until the trial actually commences.
115.
It
is also apparent from submissions made by other parties that,
including land not previously identified by agreement between the
parties ( which included the main claimants properly represented) to
be the subject matter of the present referral, can lead to
interminable delay and incur unnecessary costs.
[26]
116.
It
is clear from this court’s findings that the main claimants
intend to bring the issue forward only at the eleventh hour,
having
been given ample opportunity to do so, despite being appraised of the
other parties’ positions
[27]
.
117.
In all the circumstances the court must cut
the gordian knot. And this brings me to those parts of the directions
and the order
which may still be considered extant to the extent that
they still afford the main claimants an opportunity to approach a
court
to include ungazetted land if
special
circumstances are shown or a substantive application is brought which
includes an application for condonation (the latter
being contained
in the order of 12 August in respect of which the main claimants did
not seek condonation, claiming that they did
not have to).
118.
It is therefore clear that this court’s
directions and the order of 12 August 2024 have not achieved the
objective of the
Land Court Act, the Act itself and the court rules.
Only the order sought by the Commission its counter-application will.
The
reasons to summarise are; the court was unsuccessful in issuing the
directions and making the orders it did in May and August
last year:
The only effective way of bringing this matter to trial expeditiously
and in the least costly manner, after the main
claimants had been
given every opportunity to get their house in order, if they could,
is to accede to the counter-application.
In doing so the court
accedes to the trite proposition stated earlier, that only land which
has been gazetted can be subject to
a court order for restitution. It
will also enable the trial in respect of land which has been gazetted
in respect of both the
main claimants and the competing claimants to
proceed as it now must.
119.
It is necessary to add that the
locus
of the Commission has not been
challenged. I believe that as the body responsible for giving effect
to the Act generally and for
bringing land restitution matters to
finality it has a sufficient interest in opposing the condonation
application.
120.
For reasons which are dealt with under the
costs heading, the court considers that the main claimants have
abused its processes
and have unduly delayed this matter
proceeding to trial to a sufficient degree to warrant granting the
counterapplication
in favour of the Commission, as it will enable the
trial itself to proceed in the most expeditious and least
costly manner
as required by our law.
COSTS
121.
Earlier
in this
judgment the court mentioned that the main claimants themselves took
the position that any decision of the RLCC stood until
taken on
review. A litigant should maintain a consistent principled position.
The main claimants have not.
Mention
was also made earlier that as far back as three July 2020 the main
claimants agreed to prepare statements of witnesses that
would be
provided by 31 August 2020 dealing with all the land claimed. These
statements were due four and a half years ago. Their
surveyor’s
report surfaced almost one and a half years ago, yet they wish
to wait until the first day of trial and
disrupt the proceedings.
This in the face of the statements made by their council at the
conference of 12 August which have been
highlighted.
122.
On 28 July 2021 I was obliged to give a
judgment in respect of the provision of continued funding for
litigation out of State resources
that was insisted upon by the main
claimants by way of an application for review against the
Commissioner and a stay of proceedings
pending the final outcome of
that review.
123.
In that judgment the court mentioned that
the Commissioner had given full reasons for refusing to continue
funding, yet the Moletele
had persisted. The court also indicated
that however they wished to argue the point, the facts were straight
forward: Although
the Moletele had initially required funding some
ten years earlier, since the matter was referred to court in 2010
significant
amounts of commercially exploitable land had been
transferred to them under the Act.
At
the time they sought continued funding for litigation, State land and
significant riparian rights had been transferred to them
which was
yielding an annual revenue stream of over R20 million and enabled
them to have accumulated reserves (in other words undistributed
after
tax profits built over time) of close on R141 million.
124.
This court in its judgment said the
following :
“
Despite
this, they continue to also receive funds earmarked for indigent
communities and individuals. The fund which provides the
finances for
litigation is not a trough; it is taxpayers money intended by
legislation for a remedial purpose. The applicants’
decision
makers should have known better and have no excuse.
They
are members of a community which itself has known hardship and was
rendered indigent through the greed and racial oppression
of others
and itself sought and obtained funding which enabled the members to
secure what they have now.
I
repeat; if anyone should know better it is them.
This
case
(i.e.,
for continued legal funding)
is
therefore also about avarice, taking what is not meant for the
applicants and about violating our constitutional construct of
ubuntu.
[28]
”
125.
In its judgment of July 2021 the
court, when dealing with the application to stay proceedings pending
the final outcome of review
proceedings mentioned (at paras 46
and 47) its concern ;
“…
.
that the applicants have adopted an unnecessarily rigid approach
which may have driven costs up unnecessarily. By way of illustration
the engagement of Telkom appears to have resulted in costs that could
have been readily avoided, as too with the present application
which
has no merit and was ill advised
Equally
important in respect of the application to stay proceedings is that
the competing claimants have had none of their claims
determined
while the landowners have been prejudiced as a result of the
uncertainty of the litigation which has dragged on for
such a lengthy
period. Time is also no one’s ally in litigation save for those
who suffer no adverse consequences.”
That
was said in July 2021
126.
The judgment of July 2021 also dealt with
the courts concern regarding unnecessary litigation. It is apposite
that the factors which
weighed with the court in not making special
orders at that stage be repeated because the main claimants and their
legal representatives
have failed to heed them. I said the following:
“
57.
What I have said, and am about to say, is with a heavy heart. I have
come to know this relatively small
community of legal practitioners
and believe that the working relationship with the Court is a good
one. Nevertheless, I cannot
shirk my responsibilities to litigants
generally and more particularly the individual members of the
applicants’ communities
going forward.
58.
A cost order against the applicants depletes the amount available for
distribution to each
member and, exponentially, the next generation
of a claimant community.
59.
The options available to a court are few.
A
court can hold to account those within the applicants’
communities responsible for this wholly unnecessary litigation while
debarring them from having recourse to the applicants’ funds
whether held via the CPA or otherwise.
A
court can also consider holding one or more of the legal
representatives to account. This would entail a separate enquiry as
to whether the obdurate attitude of the client was the real cause.
And if it was, whether despite their responsibilities as officers
of
the court the lawyers were bound by the instructions, and whether any
one or more of those responsible for persisting with this
irresponsible challenge to the Commissioner’s decision should
be deprived of their costs aside from paying the costs of the
other
litigants de bonis propriis- or whether on circumspection such orders
would stifle vigorous and independent representation.
60.
Each of these considerations are raised in light of a fundamental
concern on the part of
this Court; that the ordinary members of the
applicant communities should not be prejudiced by sanctionable
conduct taken in their
name, but not necessarily with their approval.
127.
The
court concluded that:
[29]
The
Court however has a greater responsibility to the applicants’
individual members and
looking
forward both the decision makers and the legal representatives are
implored not to embark on spurious litigation
.
If the court in the future finds
on the merits that spurious litigation has been embarked on by any
party, then it will enquire
as to who is responsible and determine
whether a party is obliged to pay for the folly of others or whether
the individuals responsible
should do so personally
.
(emphasis added)
128.
The court did its best to inform the legal
representatives of its concerns going forward and said:
“
What
I have said, and am about to say, is with a heavy heart. I have come
to know this relatively small community of legal practitioners
and
believe that the working relationship with the Court is a good one.
Nevertheless, I cannot shirk my responsibilities to litigants
generally and more particularly the individual members of the
applicants’ communities going forward.
129.
The caution set out in that judgment has
not been heeded and the court cannot be expected to turn a blind eye,
notwithstanding the
effect it may have on
our small community,
when a party persists
with spurious litigation, which
to the
knowledge of the main claimants is disruptive and negates the object
and purpose of bringing matters to trial expeditiously
and avoiding
unnecessary costs. This court
cannot shirk
from its responsibilities of acting impartially and without fear,
favour or prejudice.
130.
The failure to comply with the directions
and orders in the present matter, the notice to set them aside and
the condonation application
itself, still without providing the
information required, was spurious.
131.
In the present matter the Commission
applies for costs on the attorney and client scale.
This
is a clear case where it should be granted for reasons that should
appear clear from the judgment.
132.
The question is who should pay these costs.
The
main claimants are well able to pay for failed litigation and should
do so particularly where they continue to delay the matter
from
finalisation and put all the other parties at risk of incurring
unnecessary legal costs.
133.
However
it is not clear whether the community as a whole or the CPA Committee
members are in fact benefitting from these actions.
In part my
concern arises because I already raised concerns about the CPA’s
financial accountability to the Moletele community
in the judgment of
July 2021.
[30]
134.
Accordingly a suitable order is made which
calls on the CPA committee which heads the community, and which
was responsible
for bringing the condonation application by way of
the resolution referred to earlier, to show cause why each of its
committee
members should not be personally liable to pay the costs
de
bonis propriis
as opposed to the
community as a whole. An order is also made for the applicants’
attorney and legal counsel to show cause
why they should not be
deprived of the fees in bringing the application for condonation, the
notice of 12 September and of attending
the conferences of 16 May and
12 June where its deliberations were ignored whether in whole or in
part or why the CPA Committee
members should not personally bear
these costs of their legal representatives
de
bonis propriis
and not the community as
a whole.
ORDER
135.
The following order is therefore
made:
1.
The application for condonation brought on behalf of the claimants
under case
number LCC 206/2010 (hereafter referred to as the “main
claimants”) is dismissed with costs on the attorney and
client scale in favour of the Commission on the Restitution of Land
Rights (“the Commission”) , such costs to include
the
costs of two counsel, the liability for such costs to be determined
at the hearing provided for in paras 3 and 4 below.
2.
The counter-application is granted and the referral under case
number LCC
206/2010 shall be confined to the farms listed in annexure
NR1A and NR1B to the notice of referral, the costs to be on party and
party scale C in favour of the Commission, including the costs of two
counsel, such costs to be borne by the main claimants. This
replaces
the directions and order of 16 May 2024 and 12 August 2024
respectively.
3.
Each member of the Committee of the Moletele Communal Property
Association
(“the CPA Committee”) who passed the
resolution of 16 January 2025 authorising the application for
condonation, such
resolution being annexure A to the application
(“the said resolution”), shall show cause to this court
on Tuesday
17 June 2025 at 10am whether each of them
personally and not the main claimants per se should bear the costs
order as set
out in para 1.
4.
In order to deal with the liability for paying the costs order as set
out in
para 1:
a.
By no later than Friday 16 May the main claimants shall deliver to
the court;
i.
a minute of the meeting and a note of those who attended (if not
contained
in the minute) in terms of which the said resolution
was passed identifying the members of the CPA Committee who
were
present;
ii.
a list of office bearers of the CPA Committee together with their
physical addresses
and emails for purposes of service of this order.
b.
By no later than Friday 23 May the Commission shall serve on those
persons identified
in the documents provided under sub-para (a), and
should no such document be provided, on the persons who are
identified as members
of the CPA Committee in the most current
official returns required under the Communal Property Association Act
28 of 1996.
c.
By no later than Friday 13 June 2025 each member of the CPA
Committee shall
file an affidavit setting out why they should not be
held personally liable for such costs jointly and severally with
every other
member of the Committee having regard inter alia to any
meetings held with the main claimants whereby they obtained specific
authority
to bring such application in any general or special meeting
and the precise information provided and the minutes of such meeting
or meetings to enable the court to determine the details that were
provided at such meetings to enable an informed decision to
be made
by those in attendance.
d.
In the event that no such affidavits are filed, or no member of the
CPA Committee
appears at the hearing on Tuesday 17 June 2025, the
court will determine liability for the said costs on the papers
presently before
it including those in other applications that have
been determined by this court in matters involving the claimant
community and
which include the review application brought against
the Commissioner by the main claimants relating to the funding of
legal costs.
5.
Each of the legal representatives of the main claimants, being
its attorney
of record and senior and junior counsel involved in the
said condonation application shall show cause to this court on
Friday
25 July 2025 at 10am whether each of them should not be
deprived of their costs in relation to the conferences of 16 May and
12 August 2024 and the application for condonation referred to in
para 1 above as well as the main claimants’ Notice of 12
September 2024, or whether such costs should be borne by the CPA
Committee members personally.
6.
In order to deal with the issue of the legal representatives’
fees as set
out in para 5 above:
a.
By no later than Friday 4 July 2025 each legal representative shall
deliver
written submissions as to why he should not be
deprived of such costs or why the claimant community as opposed to
the CPA Committee
members personally should not bear their costs,
b.
By no later than Friday 18 July 2025 the CPA Committee shall deliver
written
submissions as to why, if its legal representatives are not
to be deprived of costs, each of them personally (and jointly and
severally),
and not the main claimants, should be liable for such
costs;
c.
the main claimant’s attorney shall ensure that this order is
served on
each CPA Committee member by no later than Friday 16 May
2025 and th
e returns of service shall be filed at court by no later than
Wednesday 21 May 2025.
SPILG,
J
DATE
OF JUDGMENT AND ORDER:
5
May 2025
DATE
OF REVISION:
7
May 2025
FOR
THE MOLETELE CLAIMANTS:
Adv.
V S Notshe SC
Adv.
Z Madlanga
Ngoepe
Attorneys
FOR
COMMISSION:
Adv.
A Dodson SC
Adv.
M Manetje
Maluleke
Attorneys
[1]
In July 2020 a comprehensive set of orders, rulings and directions
were given dealing with a number of issues. Para 3 of the
order
concerns Telkom and reads:
“
In
terms of rule 30(9):
a.
Telkom shall state in writing
delivered to all the parties by 27 July 2020 as to whether it
acquired registered title to the Grovedale
property by way of
expropriation or ordinary purchase and sale, and if by expropriation
to identify the applicable legislation;
b.
Irrespective of the response, the
Main Claimants shall state in writing within 15 court days of
receipt of Telkom’s response
to para 2(a) hereof;
i.
whether or not the Grovedale
property is restorable
ii.
whether they admit that the
Grovedale property is approximately 625 sq. metres in size as
alleged by Telkom, failing which they
are to state its approximate
size;
iii.
whether they admit or deny how
Telkom claims to have acquired title to the property, and if they
deny then they are to state the
grounds for such denial;
iv.
separately in respect of each of
the contents of paras 2, 4 and 19 of Telkom’s plea, whether
the allegation contained therein
is admitted or denied.
[2]
See paras 4 and 8 of the Referral
[3]
All references to sections is the Act unless otherwise stated
[4]
Pre-Trial Bundle p24 para 31
[5]
This forms the underlying principle for spoliation orders
[6]
FA p5 para 6
[7]
Prior
to Mr Madlanga responding, both Mr Maluleke for the competing
claimants and Mr van der Merwe for a main body of landowners
supported Mr Dodson’s position regarding the impermissibility
of the then position taken up to then by the Moletele legal
representatives on behalf of their client.
[8]
Transcript
of 16 May 2024 pp 18 to 20
[9]
See
the reference to the RLCC in s 11(1) and to the Commission in s 12
read with rules 3, 5 and 6 of the Rules Regarding Procedure
of the
Commission (GN 703 of 13 May 1995). See also
The
Nyavana Traditional Authority v MEC for Limpopo Department of
Agriculture and another
[2020]
ZALCC 12; [2021] 1 All SA 237 (LCC)
[10]
See
ss 11A(2) and (3)
[11]
See
paras 1, 3 and 6 of the FA in the Condonation Application
[12]
Para
11.2 of the Replying Affidavit
[13]
This
in itself is a
non
sequitur
because
the directions of 16 May also precluded the Moletele from
introducing ungazetted land after 30 June 2024 absent special
circumstances being shown after that
[14]
In
terms of
Plascon-Evans
the evidence on which a court is entitled to base its findings,
where final relief is sought on motion and there is not a referral
to evidence, comprises the averments alleged “
in
the applicant’s affidavits which have been admitted by the
respondent, together with the facts alleged by the respondent”
unless circumstances exist where a denial by the respondent does not
“
raise
a real, genuine or bona fide dispute of fact … and the court
is satisfied as to the inherent credibility of the applicant’s
factual averment …. (or) …. where the allegations or
denials of the respondent are so far-fetched or clearly untenable
that the Court is justified in rejecting them merely on the papers
…
.”.
[15]
This is an aspect of the substantive right to a fair trial under s
34 of the Constitution
[16]
This
excludes the team representing Telkom in the separated matter
[17]
At the pretrial conference of 29 March 2022 the provisional dates
agreed upon by the parties envisaged the filing of expert reports
by
20 June 2022 and that the inspection in loco would be held during
August 2022. Despite more than two and a half years
passing
since then, none of these milestones have been reached.
[18]
That is both the main claimants and the competing claimants
[19]
See the earlier cited extracts from the conference of 16 May where
the risk of cost orders should the Moletele persist with the
position they had taken on the ground that it was impermissible was
put squarely on the table prior to Moletele’s legal
representatives responding as they did. See also para 80 below
[20]
Especially
at para 13
[21]
This
appears from the transcript of the 12 August conference
[22]
These
are the express requirements of s 25(1)(e ) which provides that at a
conference
“
(1)
The Court may at any stage on its own accord or upon
the request in writing of either party direct the parties or their
representatives
to appear before it in chambers for a conference to
consider—
:
(e
) such other matters as may aid
in the disposal of the action in the most expeditious and
least
costly manner.
[23]
See
the
Wevell
Trust
case
supra
[24]
Compare AG v DG [2016] ZAGP JHC 234 ;
2017 (2) SA 409
(GJ) .
There the respondent petitioned the Supreme Court for Appeal
inter
alia
on the grounds that the trial court could not order his
incarceration if he failed to comply with its order to pay the
outstanding
maintenance within the further time afforded. The
petition was refused. In refusing leave to appeal at the earlier
stage I held
that it was the respondent’s election to submit
to the sanction imposed if he failed to pay. He was to “
Pay
with funds that are clearly accessible to him or face imprisonment.
It is his election”.
[25]
Although
the notice of counter-application is signed by the State Attorney on
behalf of both the Commission and the Minister
of Land Reform
(the State Attorney representing both at this stage of the
proceedings), the body of the application
only seeks
orders on behalf of the Commission.
[26]
These
costs are not only those of the several hundred landowners but also
a number of sets of costs which would be borne ultimately
by the
fiscus
.
These costs would include those in respect of the Commission as the
participating party, the competing claimants as it receives
State
funded legal aid, and the Minister of Land Reform and Eskom
as defendants remaining in the main proceedings.
[27]
If
all the land claimed has been gazetted (as was the possibility
mentioned by Mr Madlanga in one of the highlighted extracts
from the
transcript of the 12 August conference) then the legal
representatives of the main claimants would have been obligated
to
say so by now
[28]
S
v Makwanyane and Another
[1995] ZACC 3
;
1995
(3) SA 391
(CC) at para 237 per Madala J;
Barkhuizen
v Napier
[2007] ZACC 5
;
2007 (5) SA 323
(CC) per Ncgobo J (at the time) at paras 51 and 73;
Everfresh
Market
Virginia
(Pty) Ltd v Shoprite Checkers (Pty) Ltd
2012 (1) SA 256
(CC) at para 71 per Moseneke DCJ. See also
Beadica
231 CC and others v Trustees, Oregon Trust and others
2020
(5) SA 247
(CC) at paras 17 and 35 and especially Victor AJA at para
207 to 210 citing
Makwanyane
and
Everfresh
in
relation to the constitutional value of ubuntu permeating the
general body of our law.
[29]
At para 61
[30]
The main claimants had contended that all assets acquired were
illiquid. It required a court order and further delay before the
financials were produced which clearly showed that this was just not
so
sino noindex
make_database footer start
Similar Cases
Moloto Community v Minister of Rural Development and Land Reform and Others (LCC 204/2010) [2022] ZALCC 4 (11 February 2022)
[2022] ZALCC 4Land Claims Court of South Africa98% similar
Michau N.O and Others v Minister of Agriculture, Rural Development and Land Reform and Other (LC117/2012C) [2025] ZALCC 37 (21 July 2025)
[2025] ZALCC 37Land Claims Court of South Africa97% similar
Malangane Community v Minister of Rural Development and Land Refor and Others (LCC 2012/117) [2022] ZALCC 19 (1 September 2022)
[2022] ZALCC 19Land Claims Court of South Africa97% similar
Mpofana Community Land Claimants and Another v Regional Land Claims Commissioner Kwazulu-Natal Province and Others (LCC 164/2021B) [2023] ZALCC 25 (21 July 2023)
[2023] ZALCC 25Land Claims Court of South Africa97% similar
Mpofana Community Land Claimants and Another v Regional Land Claims Commissioner Kwazulu-Natal Province and Others (LCC 164/2021C ; LCC 164/2021) [2023] ZALCC 35 (9 October 2023)
[2023] ZALCC 35Land Claims Court of South Africa97% similar