Case Law[2024] ZALCC 31South Africa
Sibeko and Others v A Re Shomeng Project Proprietary Limited and Others (LCC02/2024) [2024] ZALCC 31 (13 September 2024)
Land Claims Court of South Africa
13 September 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Land Claims Court
South Africa: Land Claims Court
You are here:
SAFLII
>>
Databases
>>
South Africa: Land Claims Court
>>
2024
>>
[2024] ZALCC 31
|
Noteup
|
LawCite
sino index
## Sibeko and Others v A Re Shomeng Project Proprietary Limited and Others (LCC02/2024) [2024] ZALCC 31 (13 September 2024)
Sibeko and Others v A Re Shomeng Project Proprietary Limited and Others (LCC02/2024) [2024] ZALCC 31 (13 September 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZALCC/Data/2024_31.html
sino date 13 September 2024
IN
THE LAND COURT OF SOUTH AFRICA
RANDBURG
CASE
NO: LCC 02/2024
Before:
Honourable Ncube J
Head
on: 04 June 2024
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED. NO
In
the matter between:
LETTA
SIBEKO
CHRISTINA
SOKO
MEISI
EMILINAH NKOSI
AARON
TATSHI SOKO
ELIZABETH
MINAH NKOSI
1
st
Applicant
2
nd
Applicant
3
rd
Applicant
4
th
Applicant
5
th
Applicant
SIPHO
MAHLANGU
PHAKAMANI
JOHANNES MAHLANGU
and
A
RE SHOMENG HOLDINGS PROPRIETARY LIMITED
A
RE SHOMENG PROJECT PROPRIETARY LIMITED
JOSEPH
MASIKWAMENG
6
th
Applicant
7
th
Applicant
1
st
Respondent
2
nd
Respondent
3
rd
Respondent
Heard
:
04 June 2024
Delivered:
This judgement was handed down electronically by circulation to
the parties’ legal representatives via e-mail. The
date and
time for hand-down is
13 September 2024
JUDGMENT
Ncube
J
Introduction
[1]
This is the application in which the applicants seek the relief
declaring the respondents to be in contempt of a court order
of my
sister Cowen J dated 29 February 2024. The application was
brought on urgent basis and it is opposed by the respondents.
The
respondents have filed a counter application seeking relief ordering
a relocation of the applicants to the houses constructed
for them by
the respondents at a different site. The applicants resist the
relocation to the houses built for them as they perceive
such houses
as not being suitable alternative accommodation compared to the
houses they are being relocated from. The affected
land is Portion 35
of the farm Kromkrans 208 IS, Mpumalanga Province.
[2]
The applicants contend that there was no compliance with Cowen J’s
order for various Reasons. To name but a few, the applicants
contend
that there was no meaningful engagement before the relocation process
was undertaken. The second applicant (‘’SOKO’’)
was unlawfully relocated as Cowen J’s order did not permit her
removal on the date she was removed from her house to the
temporary
structure. They contend further that the living conditions at the new
sites are not commensurate with the living conditions
at their
previous sites in that the applicants were previously living in a
village set up but they are being relocated to a township
set up
where no provision is made for their livestock. The size of the yard
is smaller than the size of their previous yards, consequently,
they
are unable to practise their cultural activities like iqhude and
ingoma. Those who were moved to new structures have returned
to their
previous homesteads leaving the new houses unoccupied.
Parties
[3]
The applicants are representatives of seven (7) families which are
resident on Portion 35- of the farm Kromkrans 208 IS in (‘’the
farm’’) in the Mpumalanga Province. All applicants can be
described as occupiers on the farm. The first respondent
own a coal
mine known as Motshaotshile Colliery which operates on the farm in
question. The first respondent conducts open cast
coal mining
activities on the farm pursuant to a mining right granted by the
Minister of Mineral Resources and energy. The third
respondent is the
CEO of the first respondent.
Factual
Background
[4]
This matter commenced in January 2024 when the respondents applied on
urgent basis to the Land Court, initially for the
removal of
the occupiers to the temporary accommodation in the mobile homes
provided for them on the farm. Thereafter, the occupiers
were to be
moved to permanent new accommodation which was being built by the
respondent 600 metres away from the occupiers’
current
homesteads. Following negotiations and consultations, the occupiers
agreed to relocate to new permanent homes. Although
the
occupiers agreed to relocate to new permanent homes, they resisted a
temporary relocation to temporary structures. They perceived
the
temporary relocation to be destructive to their lives and not having
been raised in their negotiations and they claimed the
temporary
accommodation was not suitable for their needs. On the other hand,
blasting activities had come to a halt as it could
not continue in
the presence of the occupiers. Ultimately Cowen J granted a
relocation order, relocating some of the respondents
to temporary
mobile homes subject to applicants in that case complying with
certain conditions.
Court
Order
[5]
Cowen J’s order serves as the basis upon which the contempt
application is premised.
It
is therefore important to quote that order in its entirety. The order
provides:
“
29.1
Mr Phakamani Johannes Mahlangu is substituted as the seventh
respondent in the application.
“
29.1
The First and Fourth respondents and persons claiming rights of
residence through them is ordered by 16h00 on the 23 February
2024,
to vacate their existing homes on Portion 35 of the farm Kromkrans
208 IS (‘’Portion 35’’’)
and relocate
to the temporary housing made available for them by the applicants on
Portion 35.
29.3
The applicants must ensure that the temporary housing provided to the
first
and
the fourth respondents includes sleeping, kitchen, lounge /dining
room and sanitation facilities commensurate with each family’s
requirement. Water and electricity must be supplied as follows:
29.3.1.
Generator power will be supplied at the applicants’ costs until
the applicants have installed Solar electricity or
have provided an
Eskom connection. Once the Eskom connection is supplied the relevant
occupiers will be responsible for their own
electricity costs.
29.3.2.
Water will be supplied in a jojo tank, and the applicants will ensure
the tank remains adequately filled to address the
mobile homes’
occupiers’ reasonable needs.
29.3.3
The first and seventh respondents’ livestock will continue to
graze Portion 35 at all relevant times.
29.4
The applicants must forthwith facilitate an ongoing process of
engagement with the first and the fourth respondents either
directly
or through their legal representatives, to communicate the temporary
relocation plan and decision to facilitate the relocation
process to
ensure that the temporary accommodation is commensurate with
respondents’ reasonable needs having regards to their
existing
living arrangements.
29.5
The applicants must provide such assistance with transport and labour
as is
required to move the furniture’s and belongings of the
families in a safe, orderly and dignified manner.
29.6
The applicants must construct at the first and fourth respondent’s
permanent house on Portion 35 in accordance with the
plans signed off
by the first and fourth respondent’s, FA4 to the applicants’
founding affidavit and take such steps
as are reasonably necessary to
follow the programme F5 to the founding affidavit (attached). The
first and fourth respondents must
relocate to the permanent houses
once constructed, on no less than 14 days’ notice and the
provisions of the paragraph 29.5
apply.
29.7
The applicant will endeavour to expedite the construction of the
second, third, fifth, sixth and seventh respondents’
permanent
houses to avoid them having first to relocate to the temporary mobile
homes. Save where otherwise agreed these permanent
houses must be
constructed following the plans signed off by the first to sixth
respondents’ FA4 to the applicants’
founding affidavit
and in accordance with the seventh respondent’s existing plans.
29.8
The applicants shall, within ten court days of the date of this order
deliver a report to court and the respondents detailing
the proper
sequence in which the applicants will construct the second, fifth,
sixth and seventh respondents’ permanent houses,
the
anticipated time frames within which construction will take place and
advising. of the order in which and likely time frames
in which any
of these respondents’ families may need to relocate to
temporary housing on Portion 35 to ensure mining activities
are not
unduely interrupted. The report must include details of the intended
ongoing process of engagement and assistance in accordance
with
paragraph 29.4 and 29.5.
29.9
The applicant shall, upon delivery of the report, conduct a
meaningful engagement with these respondents about the proposed
plan
and their accommodation needs should it be necessary of them to
relocate to the temporary accommodation at any stage.
29.10
The applicants may thereafter approach the Court, on no less than ten
days’ notice, on the same papers duly supplemented,
for an
interim order regulating the relocation of the second, third, fifth,
sixth and seventh respondents, including the notice
period for
vacating their existing homes to either the temporary or, when built,
permanent new housing.
29.11
The first to seventh respondents are ordered to comply with any
direction given to them by the first applicant’s mine
manager
or other authorised official to move to safe place during blasting
operations.
29.12
The sheriff for the district of Carolina is authorised to remove the
first and fourth respondents from their existing homes
on Portion 35
if they have not complied with paragraph 29.2 or 29.6 of the order by
moving to the temporary or permanent housing
made available for them
by the applicants on Portion 35
29.13
The South African Police Service and the sheriff of the high Court
and / or any other entity or person(s) delegate/instructed
by the
South African Police Service and / or the Sheriff of the Court are
authorised to take all such steps as may be necessary
to enforce this
Court Order.
29.14
Service of this order and any process under it may be effected
electronically upon the relevant party’s legal representatives,
who shall thereafter promptly ensure it is delivered to the relevant
respondent, save that this order must be served by the sheriff
or
otherwise physically delivered to the first and fourth respondents by
a representative of the applicants or applicants’
legal
representatives by no later than 10am on 20 February 2024.
29.15
tThe above order operates on an interim basis pending the
determination of Part B of the applicant, in respect of which, the
applicants are directed to deliver any amended notice of motion and
supplementary founding affidavit within one month of the date
of this
order whereafter the ordinary Rules of Court will apply.
29.16
No final relocation order may be granted unless and until the
permanent new homes are constructed and the applicants are authorised
to update their affidavits accordingly and the grant of this order
does not prejudice any rights of any respondent to claim compensation
for which the applicants may be liable arising from the relocation
process.
29.17
Should any dispute arise in respect of the implementation of this
order, the relevant parties must first attempt to resolve
the dispute
by engagement failing which they may approach the Court on such
notice as is reasonable in the circumstances.
29.18
In the event that the relief sought in Part B is not granted, the
second applicant is ordered to ordered to remediate any
damage caused
to any occupier’s existing home situated on Portion 35 due to
the second
applicant’s blasting activities
.’’
Events
after the order of Cowen J
[6]
After Cowen J’s order, the applicants in this case, respondents
in Cowen J’s order, brought the present contempt
of court
application on urgent basis. The contempt application was to be heard
on 25 April 2024. On 25 April 2024, I directed the
parties to have a
meaningful engagement on the completion and sizes of the relocation
houses and the matter was adjourned to a
further date. Relocation to
temporary and permanent houses was not an issue. That much had been
agreed upon between the parties
through the consultation process.
What was placed in issue was the size of the houses and the yards.
[7]
When the first and fourth applicants were to be relocated to
temporary houses, pending their relocation to permanent houses,
chaos
erupted as there was resistance to such relocation. Other members of
the community joined the picketing on the gates of the
mine. People
came up with new demands for employment by the mine, they complained
about the size of new houses, size of yards,
demanding bigger yards
where they could practise their Iqhude and Ingoma dance. Police had
to be called in. Sheriff was called
in to execute the court order.
Twelve people were arrested.
Contempt
of Court
[8]
Contempt of court is the commission of any act or making any
statement that displays disrespect for authority of the court,
of its
officials acting in an official capacity, including wilful
disobeyance or resistance to lawful court order. In
Pheko
and Others v Ekurhuleni City
[1]
Nkabinde
J, expressed herself in the following terms:
“
The
rule of law a fundamental value of the Constitution, requires that
the dignity and authority of the courts be upheld. This is
crucial as
the capacity of the courts to carry out their functions depends upon
it. As the Constitution demands, orders and decisions
issued by a
court bind all persons to whom and organ of state to which they apply
and no person or organ of state may interfere
in any manner with the
functioning of the courts, it follows from this that disobedience
towards court orders or decisions risks
rendering our courts
important and judicial authority a mere mockery. The effectiveness of
court orders or decisions is substantially
determined by the
assurance that they will be enforced.
Elements
of Contempt of Court
[9]
The following are the elements of contempt of Court:
(i)
There must be a court order.
(ii)
The order must have been duly served on or brought to the notice of
the alleged contemnor.
(iii)
There must have been non compliance with the court order
(iv)
The non compliance must have been
wilful
or
mala fide
[10]
In
Casu,
there
is no doubt about the existance of the court order. It is also not in
dispute that the respondents are aware of the court
order. It is only
the last two elements which are in dispute. The onus is on the
applicant to prove the elements of the offence
beyond a reasonable
doubt
[2]
Applicants aver that
the respondents did not provide a report to court within ten days of
the court order as directed by Cowen
J and that the second occupier
was moved without a court order. The respondent argued that the
report was out of time by only three
days and they allege the delay
was caused by the fact that the applicants were not co-operative and
did not want to engage with
the respondents. The respondents have
applied for condonation for late submission, of the report required
by the court.
[11]
The applicants are required to prove that the third respondent is
guilty of
wilful
and
mala fide
refusal
to comply with the court order. This, the applicants have failed to
prove. It is also telling that the founding affidavit
does not define
the third respondent and it fails to show how the third respondent
was complicit in non compliance with the court
order, if any. The
applicant have failed to make out a case of contempt of court against
the three respondents.
Counter Application
[12]
The respondents have filed an application, effectively seeking the
court order forcing the occupiers to relocate to their temporary
and
newly constructed permanent houses. The seventh occupier, Phakamani
Johannes Mahlangu is now late. Consequently, the respondents
abandon
the relief they seek in paragraphs one to four of their Notice of
Motion, in so for as those paragraphs relate to the seventh
occupier.
This part of judgement should not detain me for long. It is just
clear that the respondents have gone, out of their way
and tried to
accommodate the occupiers. The occupiers, on the other hand, keep on
making unreasonable demands.
[13]
Before I completed writing this judgement, I enquired from the
parties’ legal representatives about the progress made
in the
construction of the occupiers’ permanent houses. I was informed
all other houses are now complete and ready for occupation,
except
for two houses for occupier 3, and 7 which will be completed by the
25
th
of November 2024. Photographs of the houses were
forwarded to me. The houses are beautiful with ablution facilities, a
bath and
a shower. Respondents have applied for electricity
connection with Eskom and they have paid for it. The receipt showing
payment
was shown to me. Despite this, there is a generator at the
present moment which provides light to the houses. A borehole is
provided
to pump water for use by the occupiers. Arrangement has been
made for the cattle to graze at Portion 35 of the farm, for those
occupiers who have cattle.
[14]
There is also no reason why I should not condone the respondents’
delayed submission of the report to court. The report
was late by
only three days and the prospect of success on the counter
application is good.
Costs
[15]
It is the practice in this court not to make cost orders unless there
are good reasons to do so. The Supreme Court of Appeal
has confirmed
the said practice
[3]
In my view,
there is no good reason why I should deviate from the general
practice of this court of not making costs orders.
Order
[16]
In the result, I make the following order:-
1.
The
application for contempt of court brought by the occupiers of Portion
35 of the farm Kromkrans 208 IS (“Portion 35”)
is
dismissed.
2.
The failure by
the respondents to submit a report to court within ten (10) days’
of Cowen J’s order is condoned.
3.
The counter
application brought by the Respondents is granted.
4.
The 1
st
,
2
nd
4
th
,
5
th
and 6
th
occupiers and all those occupying through them are ordered to vacate
their present homesteads and relocate to their respective
newly
constructed permanent houses on or before
16
September 2024
.
5.
Should the
occupiers mentioned in paragraph 4 above and or those who occupy
through them fail to vacate their present homesteads
on
16
September 2024
,
the Sheriff is hereby authorised to evict them from their present
homestead on
17
September 2024.
6.
The Sheriff is
hereby authorised to seek assistance from the local South African
Police to assist with the eviction of the occupiers
in case of
resistance.
7.
The 3
rd
occupier and all those who occupy through her are ordered to vacate
their present homestead and relocate to the temporary accommodation
provided to her by the respondents on
16
September 2024
and thereafter relocate to her newly constructed permanent house on
27 November
2024
once
that house is completed.
8.
All those who
occupy through the late 7
th
occupier are ordered to vacate their present homestead and to
relocate to the temporary accommodation provided by the respondents
on
16
September 2024
and thereafter relocate to the newly constructed permanent house
provided to the late 7
th
occupier on
27
November
2024
once
that house is completed.
9.
The provisions
of paragraphs 5 and 6 above shall apply to occupiers and other
persons mentioned in paragraphs 7 and 8 above.
10.
The first and
second respondents in the contempt application, shall ensure that the
temporary and permanent houses are provided
with water and
electricity as follows:
10.1:
Generator power will be supplied at the respondents’ cost until
the respondents have provided Eskom Connection. Once
the Eskom
connection is supplied, the relevant occupiers shall be responsible
for their electricity costs.
10.2:
Water will be supplied in Jojo tanks and the first and second
respondents shall ensure that tanks remain adequately filled
to
address the occupiers of both temporary and permanent houses
reasonable needs until the pump in the borehole is in full operation.
11.
All occupiers
who keep livestock are granted leave with the consent of the first
and second respondents to continue grazing their
livestock on Portion
35.
12.
The first and
second respondents are placed on terms to assist the occupiers with
transportation of their goods to their respective
relocation sites at
the first and second respondents’ expense, should the occupiers
ask for such assistance.
13.
No order as to
costs.
M.T
Ncube
JUDGE
OF THE LAND COURT
RANDBURG
Date
of hearing:
04 June 2024
Date
of judgment:
13 September 2024
Appearances
:
For
the Applicant: Adv B. Lukhele
Instructed
by: Ledwaba Mazwai
Attorneys
PRETORIA
For
the Respondent: Adv R. Booysen & S Sibisi
Instructed
by: Webber Wentzel
Rivonia
SANDTON
[1]
2015(5)
SA 600 (CC) Para 1
[2]
Fakie
NO v CCII systems (Pty) Ltd 2006(4) SA 326 (SCA)
[3]
See
Haak
Doutmbly Boerdary CC v Mpela
2007
(5) SA 596
(SCA) para 76.
sino noindex
make_database footer start
Similar Cases
A Re Shomeng Holdings Proprietary Limited and Another v Sibeko and Others (LCC 02/2024) [2024] ZALCC 7 (19 February 2024)
[2024] ZALCC 7Land Claims Court of South Africa99% similar
Smit N.O and Others v Taweni and Others (LanC21R2024) [2025] ZALCC 42 (17 October 2025)
[2025] ZALCC 42Land Claims Court of South Africa98% similar
Mtshali v Bencor Eiendoms (Pty) Ltd and Another (LCC39/2024) [2024] ZALCC 24 (18 July 2024)
[2024] ZALCC 24Land Claims Court of South Africa98% similar
Minister of Department of Rural Development and Land Reform and Others v Selahle and Others (LCC137/2022) [2022] ZALCC 43 (25 November 2022)
[2022] ZALCC 43Land Claims Court of South Africa98% similar
Shah and Others v Minister of Rural Development and Land Reform and Others (LCC93/2014) [2024] ZALCC 41 (6 December 2024)
[2024] ZALCC 41Land Claims Court of South Africa98% similar