Case Law[2023] ZALCC 28South Africa
Basfour 3327 (Pty) Ltd v Thwala and Others (Leave to Appeal) (LCC160/2017B) [2023] ZALCC 28 (11 September 2023)
Land Claims Court of South Africa
11 September 2023
Headnotes
IN RANDBURG
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Land Claims Court
South Africa: Land Claims Court
You are here:
SAFLII
>>
Databases
>>
South Africa: Land Claims Court
>>
2023
>>
[2023] ZALCC 28
|
Noteup
|
LawCite
sino index
## Basfour 3327 (Pty) Ltd v Thwala and Others (Leave to Appeal) (LCC160/2017B) [2023] ZALCC 28 (11 September 2023)
Basfour 3327 (Pty) Ltd v Thwala and Others (Leave to Appeal) (LCC160/2017B) [2023] ZALCC 28 (11 September 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZALCC/Data/2023_28.html
sino date 11 September 2023
IN THE LAND OF SOUTH
AFRICA
HELD IN RANDBURG
CASE NO: LCC160/2017B
(1)
REPORTABLE: YES
/NO
(2)
OF INTEREST TO OTHER JUDGES: YES
/NO
(3)
REVISED: YES/
NO
DATE:11/09/2023
SIGNATURE:
In the matter between:
BASFOUR
3327 (PTY) LTD
Applicant
/ Respondent
and
ROBERT
THWALA
First Respondent
LUCY THWALA
Second Respondent
MINEWHLE
MAHLANGU
Third Respondent
FEZEKA THOMO
Fourth Respondent
SOUTH AFRICAN POLICE
SERVICES,
Fifth Respondent
VOLKSTRUST
DEPARTMENT OF
AGRICULTURE, RURAL
Sixth Respondent
DEVELOPMENT AND LAND
REFORM
JUDGMENT ON
APPLICATION FOR LEAVE TO APPEAL
FLATELA J:
Introduction
[1]
On 30
th
June 2023, I delivered a judgment dismissing the Applicant’s
application to have the construction of an unauthorized structure
or
dwelling by the Respondents be declared unlawful. The application
also sought that the Respondents be ordered to demolish the
unlawfully constructed structure within 10 (ten) days from date of
judgment. Furthermore, the respondents were to be ordered to
remove
all building materials for purposes of constructing the unlawful
structure within 2 (two) weeks from date of judgment and
in failure
of the Respondents removing the building materials, then the Sheriff
of the district be authorized to demolish the unlawfully
constructed
structure or dwelling and to also remove all building materials of
the dwelling on the Applicant’s farm. The
Applicant’s
last prayer was that the Respondents be held to be in contempt of
Judge Ncube’s order under case number
LCC160/2017 and dated 5
October 2022.
Background context
[2]
The genesis of this application is
comprehensively captured in the main judgment I delivered on 30
th
June 2023 under case number 160/2017B. I do not intend to be as
comprehensive here seeing that this is a judgment on mere leave
to
appeal. However, a brief background context will suffice. On the 9
th
of June 2017 the Applicant approached this Court on an urgent basis
seeking an order declaring a structure that the respondents
were building on the Applicant's property without his consent
unlawful.
The Applicant also sought a prohibitory interdict against
the Respondents from constructing a new structure without the express
written permission of the Applicant or the person in charge. The
litigation dragged on for five years with several orders being
granted for the Applicant against the Respondents, or in attempt to
have the subject issue of the litigation be resolved by the
parties
on their own amicably. Meaningful engagement failed between the
parties and the Respondents continued to erect and build
the
structure without the Applicant’s consent. The matter finally
became settled by Judge Ncube on 5 October 2022 wherein
he gave
orders in favour of the Applicant ,wo are worth mentioning. The first
was that the structure was declared unlawful, and
the Respondents had
to demolish the same within 10 (ten) days from the service of the
order to them. The second was that the Respondent
were prohibited and
restrained from building entirely new dwellings or structures on the
farm U[…] […] his without
the Applicant’s or
person in charge express written permission.
[3]
On 13 April 2023, the Applicant noticed
that a substantial amount of
building
materials, such as river sand and building blocks, were delivered to
the Respondents’ homestead. Upon inspection
of the homestead,
the Applicant found that the Respondents had started constructing an
entirely new dwelling structure on the farm,
with brick and mortar,
without his consent.
On 17 April 2023,
the Applicant instituted contempt of court proceedings on an urgent
basis under case number
160/2017B
for
inter alia,
a
declarator that the Respondents are in contempt of paragraph 2 of
Judge Ncube's judgment. I granted an interim order interdicting
the
Respondents from continuing with the building of the structure till
such time the matter is decided.
[4]
The matter served before me on 17 April 2023 on an urgent
basis. In the Applicant’s main application as per his Notice of
Motion, he sought the following orders:
Prayer
2:
That it be declared that the construction of the unauthorized
dwelling or structure by the Respondents on a portion of the farm
Uitkyk 121 HS…, as depicted on annexures “A” and
“B” hereto, unlawful.
Prayer 5:
That the
Respondents are ordered to demolish the unlawfully constructed
building on the farm within 10 (ten) days from date of this
order
being granted.
Prayer 6:
That the
Respondents [be] ordered to remove all building material for purposes
of constructing the unlawful building on the farm
within 2 (two)
weeks after the date of this order.
Prayer 7:
That the
Sheriff [of the district be] authorized to demolish the unlawfully
constructed building and to remove all building material
on the farm
in the event the Respondents fail to comply with paragraphs 4 and 5
above.
Prayer 8:
a
declaratory order declaring that the Respondents are in contempt of
[Judge Ncube’s order dated 5 October 2022].
[5]
I characterized the application as a contempt of
court application and held that if I find that the Respondents are
not guilty for the crime of being in civil contempt of court, the
Applicant’s prayers as put above but excluding prayer 8,
fall
away. I held that the Applicant’s prayer 2, 5, 6, and 7 were
contingent on I find for the Applicant in terms of prayer
8.
Therefore, I approached these prayers as consequential relief to
prayer 8. However, in the judgment I also held that even if
I were to
treat prayer 2 as independent relief sought from the alleged
contemptuous conduct of the Respondents, this Court would
be
nonsuited to grant the application because of the interest of
justice, this I elaborated in the last paragraph 66 of the main
judgment.
The Applicant’s
arguments
[6]
The Applicant now contends that to treat have treated his
application as a contempt of court application was an incorrect
understanding
of the application in that the application was not a
mere contempt of court application, but rather an application to have
the
new structure being constructed by the Respondents declared
unlawful. The consequential relief therefrom, subject to the Court’s
exercise of its discretion, was prayers 5, 6, 7. These prayers, so
the Applicant contends, were independent from prayer 8 and should
have been dealt as such. Prayer 8 was but one of the orders sought by
the Applicant but not the mainstay of his application. Therefore,
so
the Applicant contends, my finding that these prayers were contingent
on a positive finding in favour of the Applicant in terms
of prayer
8, that is, finding the Respondents in contempt of Judge Ncube’s
order of 5 October 2022, was incorrect. Instead,
prayers 5, 6 and 7
were consequential relief piggybacked on prayer 2 of Ncube J’s
order. The Applicant contends that I should
have determined prayewrs
independently from prayer 8, where upon had I done so, then a
decision on the consequential relief, i.e.,
a demolition order of the
structure (prayers 5, 6 and 7) would have followed. The Applicant
contends that this Court did not even
reach this stage of deciding on
the consequential relief because it understood the Application to be
a contempt of court application
rather than an application to have
the new structure then being constructed by the Respondents be
declared unlawful.
[7]
The Applicant does not seek to appeal
against my finding that the Respondents are not in contempt of Judge
Ncube’s order.
They concede to the correctness of that
decision. Reason for doing so is that they also concede that the
Respondents could not
have been in found to be in contempt of court
as the element of willful intent and mala fides to disobey the
Court’s dignity,
authority, and repute, was absent.
Establishing the absence of mala fides on part of the Respondent was
that the Respondents relied
on Judge Ncube’s obiter on
paragraph 31 (below) for the construction of the new structure. The
obiter on paragraph 31 says,
‘
‘
[31]
In casu, the existing mud structures are clearly old and have cracks
on the walls. The corrugated is iron roof pressed down
with rocks on
top. Occupation of those structures is clearly not in harmony with
the Respondents’ right to human dignity.
Had the Respondents
demolished the mud structures, levelled the same site, and rebuilt
the same, strong, and durable structure
using concrete or cement
blocks, they would have brought their structure within the meaning of
improvements which render the structure
habitable and concomitant
with their right to human dignity. This they could do even without
the consent of the Applicant or Mr
Hatting, if after a meaningful
engagement the Applicant, or Mr Hatting unreasonably withheld
consent. The Respondents, on the contrary,
are building a totally new
structure without the consent of the owner or person in charge. That
is not allowed. It is therefore
up to the Respondents what they
intend doing, from now moving forward. What is clear is that the
Respondents urgently need proper
dwellings, the occupation of which
will be in keeping with their right to human dignity.’
[8]
In the Applicant’s Appeal heads of
argument, the Applicant now contends that in open Court, counsel for
the Applicant did
not seriously press the issue of the Respondent’s
contempt because,
‘
In
view of the explanation by the respondents that they acted on advice
of their attorney and on their interpretation of paragraphs
[10] and
[31] of the judgment by the Honourable Ncube J, although that
interpretation was clearly incorrect, it was improbable
that a Court
would find under those circumstances that the respondents acted in
wilful contempt of the order of Ncube J by constructing
a further
building without the consent of or engaging the applicant. The
applicant had to satisfy the Court that they have acted
wilfully and
in contempt of the order. Although incorrect, their explanation
excluded a positive finding of wilfulness. Counsel
however
extensively argued the main relief with reliance on Daniels v
Scribante
2017 (4) SA 341
(CC).’
[9]
During the hearing, I expressly asked
counsel for the applicant whether prayers 2, 5, 6 and 7 are premised
on paragraph 2 of Judge
Ncube’s order. The answer was in the
affirmative. Therefore, it stands to reason that if these prayers are
piggybacked on
paragraph 2 of Judge Ncube’s order and read with
the applicant’s papers that had seriously pressed the issue of
contempt,
the cause of action arising is that the Respondents are in
contempt of the Court’s order. However, I do give it to the
Applicant
that indeed his counsel had left it to my discretion as to
whether I find the Respondents in contempt in view of their defence
that they had relied upon the advice of their attorneys and on
paragraph 31 of Judge Ncube’s order. Therefore, the Applicant
may very well be correct in submitting that to have characterized the
issue in the application as contempt did not reflect the
understanding that I had considered prayer 2 and the consequential
relief flowing therefrom independently from the contempt issue.
However, what I cannot let stand in the Applicant’s Notice for
leave to appeal is the submission that I did not consider
at
all
his submissions to having the
structure be declared unlawful.
The Applicant’s
specific grounds for leave to appeal
[10]
In addition to submitting that I had erred
in treating the application as a contempt of court application, the
Applicant submits
that I overlooked its second primary relief being
the prayer for confirmation of the Rule
nisi
calling for the Applicants demolish the
structure on the property and to remove all building materials within
2 (two) weeks days
of the judgment, in failure of which, the Sheriff
of the district be authorized to demolish the unlawfully erected
structure. There
is no such prayer in the rule Rule
nisi
I granted. The Rule
nisi
in the Applicant’s first application called upon the
Respondents to show cause why a declaratory order declaring the
structure
being constructed by the Respondents should not be declared
unlawful. Furthermore, it was prohibitory and operating with
immediate
in interdicting the Respondents from further construction
of the structure without the Applicant’s express written
permission.
The relief for an order of demolishment of the structure
was independent of the Rule
nisi
and
in the Applicant’s own version, it was consequential relief
premised on the declarator order sought.
[11]
Paragraph 11 of the Applicant’s
replying affidavit and quoted in part in paragraph 53 of my judgment
has the statement,
“
had
[the Respondents] engaged me or requested to consent to improve their
present dwelling, which they had not done, I could not
have lawfully
refused them such permission. I do not know whether they have
improved their existing traditional structures in which
they reside,
as they should have done in view of the observations of the Court
that those structures were
uninhabitable”.
[12]
From this statement I inferred that the
impression given by the Applicant is that that the problem here is
two-fold. Firstly, that
the Respondents are erecting a whole new
structure as improvements, but said structure not being the dwelling
that they inhabited,
uninhabitable as it was; and secondly, that had
the case been the latter, that is that they were improving the
dwelling that
they inhabited, then there is an implication (from the
Applicant’s statement) that the Respondents could have done
this without
his consent.
[13]
The Applicant now submits I incorrectly
inferred that there is an implication that Respondents could have
erected a new mortar and
brick dwelling without his consent. Nowhere
in my judgment do I make infer such an implication. It was the
Applicant’s exact
case that the Respondents could not have
lawfully erected a new structure with new mortar and brick
without his express written
permission. However, had they improved
their existing dwellings as they should have done (and those being
the Applicant’s
words) without building a new structure (and
here the Applicant went on to say that it is easy to improve
traditional mud dwellings)
then this they could have done without his
consent. The inference that I did make from this statement is
actually in paragraph
54 where I state that ‘
the
Applicant contends that the improvements could have been done without
building a new structure. He goes on to say
that improving the traditional mud dwellings is relatively easy to
make them habitable.
However, in what structural engineering ways the
Respondents could have done this to a rundown and dilapidated mud
dwelling is
not said by the Applicant.’
[14]
The Applicant further submits that I
incorrectly held that it drew an arbitrary distinction between
upgrading of a dwelling used
for traditional purposes as opposed from
one that the Respondents are habiting. In this regard, it says I
misconstrued
Daniels v Scribante
and Another
2017 (4) SA 341
(CC)
as
Justice Madlanga held that the constitutional right protected was the
right to human dignity which is infringed if a person must
live in a
dwelling that is uninhabitable or not suitable for human habitation.
This submission was made in the Applicant’s
papers and in
argument before me. I dismissed it on the basis that whether the
Respondents live in the structure being erected
or that they use it
for traditional purposes is neither here nor there and that ‘
it
cannot be left to the Applicant to solely determine what is adequate
and reasonable accommodation measures to be implemented
by the
Respondents for the safety of the roof over their heads’.
The
judgment made it clear that this was to include the traditional mud
structure that the Respondents were using for traditional
purposes.
[15]
The Applicant submits that I held the
Respondents could construct an entirely new structure with building
materials of brick and
mortar without the consent of the Applicant.
To the contrary, I made no such finding.
[16]
To the submission that the Applicant took
issue with the construction of the structure but would not have
objected if the mud houses
were improved without the use of building
brick cement and mortar, I stated in my Judgement that the
Respondents could not have
improved the traditional mud structure in
any other way as the mud structures were delipidated as observed in
the inspection
in loco
.
Furthermore, the Applicant neither suggested the alternative means it
preferred. The Applicant now contends that it had no such
obligation
for the relief sought in paragraphs 2, 5, 6 and 7. That may be
correct but it should be borne in mind that in
order to found for the
relief sought in these prayers, the Applicant’s issue was that
over and above the fact that his consent
was not sought, the
structure was erected with cement brick and mortar.
[17]
The Applicant further submits that by
failing to declare the unauthorized structure unlawful, the Court
exposed the applicant to
an order in terms of section 13(1) of the
Extension of Security Act 62 of 1997 whereby the applicant could be
ordered to compensates
the Respondents upon eviction. This is to be
read against the backdrop of the Applicant’s submission, which
I had dismissed
of having no bearing to the application before me,
that his attorneys have sent a notice of intention to terminate the
right of
residence upon the Respondents. I stand by the dismissal of
this argument.
[18]
Furthermore, the Applicant submits that I
should have held that the construction of the structure without
buildings plans rendered
the structure unlawful. This is a
superficial argument. The basis of wanting to have the structure
rendered unlawful was less the
building plans but more that it had
been built without the Applicant’s consent.
[19]
Lastly, the Applicant submits that I
interpreted Judge Ncube’s obiter in paragraph 31 in
contradiction with
Scribante.
I did not interpret the obiter in any manner save to say that it is
this obiter which the Respondents relied on for the construction
that
exonerated them from the finding of contempt.
The test for Leave to
Appeal
[20]
An application for
leave to appeal is regulated by
s 17(1)
of the
Superior Courts Act 10
of 2013
which provides:
‘
(1)
Leave to appeal may only be given where the judge or judges concerned
are of the opinion that –
(a)
(i) the appeal would have a
reasonable prospect of success; or
(ii) there
is some other compelling reason why the appeal should be heard,
including conflicting judgments on the matter under
consideration;
(b)
the decision sought on appeal does not
fall within the ambit of
section 16(2)
(a)
;
and
(c)
where the decision sought to be appealed
does not dispose of all the issues in the case, the appeal would lead
to a just and prompt
resolution of the real issues between the
parties.’
[21]
Section
17(1)
of the
Superior Courts Act is
to be read holistically with
s17(1)(a)
which further adds that a Court
may
only
grant
leave to appeal where it is satisfied that the Applicant has shown
reasonable prospects of success to suggest that a different
court
would
come to a different outcome. Therefore, if on the merits of the
appeal it cannot be said that reasonable prospects of success exist
to suggest that a different court would come to a different outcome,
the application must fail. The converse is also true, that
if there
should be such grounds that are shown to suggest that another court,
reasonably, would find differently, then the application
must
succeed. Hereto see
The
Mont Chevaux Trust v Tina Goosen & 18 Others
[1]
where Bertelsmann J held as follows:
It
is clear that the threshold for granting leave to appeal against a
judgment of a High Court has been raised in the new act.
The
former test whether leave to appeal should be granted was a
reasonable prospect that another Court might come to a different
conclusion. See Van Heerden v Cronwright & Others
1985 (2)
SA 342
(T) at 342H. The use of the word “would” in
the new statutes indicates a measure of certainty that another Court
will differ from the Court whose judgment is sought to be appealed
against.”
[22]
Plasket
AJA, as he then was, in
S
v Smith
[2]
2012
What
the test of reasonable prospects of success postulates is a
dispassionate decision, based on facts and the law that the Court
of
Appeal could reasonably arrive at the conclusion different to that of
the Trial Court. In order to succeed, therefore,
the appellant
must convince this Court on proper grounds that he has prospects of
success on appeal and that those prospects are
not remote but have a
realistic chance of succeeding. More is required to be
established than that there is a mere possibility
of success; that
the case is arguable on appeal or that the case cannot be categorised
as hopeless. There must, in other
words, be a sound, rational
basis for the conclusion that there are prospects of success on
appeal.”
Discussion
[23]
The Applicant’s mainstay submission is that I did not decide on
the consequential relief, let alone
reach that stage, as I
misconstrued the application as a contempt of court application,
whereas it was not. He contends that
the purpose of the
application was to seek a declarator declaring the new
structure being built by the Applicant’s
unlawful; and the
consequential relief flowing therefrom, was a prayer for a demolition
order or in the event that the Respondents
fail to demolish the new
structure, then the Sheriff of the Court be authorized to demolish
the new structure and remove any building
materials on the farm. In
essence, the Applicant contends that I decided his case on a wrong
footing. If had this been or is the
case of the Applicant, then in my
view, the Applicant should have prosecuted the matter as a whole new
case altogether under a
different case number and not piggybacked his
application on the previous prohibitory order of Judge Ncube. That a
prohibitory
order existed and that the Respondents were in breach of
it, whether contemptuously or not, would have been the background
context
of his application. However, this ground of appeal satisfies
section 17(1)(a)(ii)
of the
Superior Courts Act 10 of 2013
in that it
provides for
some other compelling reason why
the appeal should be heard. The Application for leave to Appeal to
the Supreme Court of Appeal
the portions of my judgment dismissing
the Applicant’s prayer 2, 5, 6 and 7 therefore succeeds.
Order
[24]
In the result, I make the following order:
1. The
Applicant’s application for leave to appeal to the Supreme
Court of Appeal, the portion of my judgment
of 30
th
June
2023, dismissing the Applicant’s prayers: 2, 5, 6, and 7,
succeeds.
2. The
costs of this application shall be costs in the appeal.
FLATELA
LULEKA
JUDGE
LAND
CLAIMS COURT
This
Judgment was handed down electronically by circulation to the parties
and/or their representatives by email. The date and time
for the hand
down is deemed to be 10H00 on this 11September 2023
.
Date
of Hearing:
10
August 2023
Date
of Judgment
11
September 2023
Counsel
for Applicant:
H.S.
Havenga SC
Instructed
by
Peet
Grobbelaar Attorneys
Attorneys
for Respondent
T.
Ramollo
Instructed
by:
Legal
Aid South Africa
[1]
The
Mont Chevaux Trust v Tina Goosen & 18 Others
2014 JDR 2335 (LCC) at para 6.
[2]
S
v Smith
2012 (1) SACR 567
, 570 para 7
sino noindex
make_database footer start
Similar Cases
Basfour 3327 (Pty) Ltd v Thwala and Others (LCC 160/2017B) [2023] ZALCC 23 (30 June 2023)
[2023] ZALCC 23Land Claims Court of South Africa99% similar
Basfour 3327 (PTY) Ltd v Thwala and Others (LCC160/2017) [2022] ZALCC 20 (5 October 2022)
[2022] ZALCC 20Land Claims Court of South Africa99% similar
Boplaas 1743 Landgoed (Pty) Ltd v Julies and Others (Leave to Appeal) (LCC151/2022) [2025] ZALCC 7 (6 January 2025)
[2025] ZALCC 7Land Claims Court of South Africa98% similar
Naidoo v Land Claims Commission Kwazulu Natal (Leave to Appeal) (LCC112/2021) [2024] ZALCC 32 (19 September 2024)
[2024] ZALCC 32Land Claims Court of South Africa98% similar
Boplaas 1743 Ladgoed (Pty) Ltd v Julies Others (LCC151/2022) [2024] ZALCC 19 (26 July 2024)
[2024] ZALCC 19Land Claims Court of South Africa98% similar