Case Law[2025] UGSC 15Uganda
SBI International Holdings AG (U) Ltd v COF International Company Ltd (Civil Appeal 14 of 2020) [2025] UGSC 15 (3 April 2025)
Supreme Court of Uganda
Judgment
THE REPUBLIC OF UGANDA
IN THE SUPREME COURT OF UGANDA AT KAMPALA
CIVIL APPEAL NO. 014 OF 2018
SBI INTERNATIONAL HOLDINGS AG (U) LTD:::::::::APPELLANT
VERSUS
COF INTERNATIONAL COMPANY LTD: : : : : : : : : : : : : : :RESPONDENT
(Appeal from the decision of the Court of Appeal (Kasule, Kakuru and Obura, IJA) in Civil
Appeal No. 194 of2014 dated 2id May, 2018)
CORAM: HON. LADYIUSTICE PERCY NIGHTTUHAISE, JSC
HON. MR. JUSTICE MIKE CHIBITA, JSC
HON. LADYJUSTICE ELIZABETH MUSOKE, JSC
HON. MR. JUSTICE STEPHEN MUSOTA, JSC
HON. MR. JUSTICE CHRISTOPHER MADRAMA IZAMA, JSC
JUDGMENT OF ELIZABETH MUSOKE, JSC
This appeal is from the decision of the Court of Appeal (Kasule, Kakuru, and
Obura, JJA) in CivilAppeal No. 194 of 2014 dated 23'd May,2018.
Background
The respondent sued the appellant In the High Court claiming fraud and
breach of contract, and sought special, general and punitive damages,
interest and costs. The appellant denied the respondent's claims and prayed
for dismissal of the suit. The appellant also counter-claimed for breach of
contract by the respondent and sought general damages and costs.
The facts of the case are briefly that by an agreement dated 4th April, 2006,
the appellant contracted the respondent to construct lined drains in grouted
stone pitching for a section of road sltuated in Bwera, Kasese District, at a
price of Ug. Shs. 18,000/= per sq. metre of road constructed, and payable
according to terms set out in the agreement. The agreement also stipulated
that the appellant would supply diesel at a price of Ug. Shs. 1850/= per litre
and cement at a prlce of Ug. Shs. 19,400/= per bag for use by the
1,
respondent in the project. The respondent claimed, in lts suit, that it was
underpaid by the appellant yet it executed the relevant works in accordance
with the relevant contract and sought for special damages representing the
difference between the amount rightly due to it and the underpaid amount.
The respondent also claimed that the appellant charged higher prices for the
cement and diesel supplied than the rate agreed upon in the parties'
contract.
The appellant denied the respondent's claim and averred that the respondent
was paid what was due to lt under the agreement as per approved
certificates showing the work done and amount payable. The appellant also
claimed that the charging of higher prices for diesel and cement was justified
by market fluctuations in the prices for the same. The appellant also counter-
claimed for breach of contract arising from the respondent's failure to
complete the construction works within the agreed timeframes, which clalm
was denied by the respondent.
The High Court allowed the respondent's claim and found that the appellant
had underpaid it to the tune of Ug. Shs. 208,186,L201= which sum was
awarded as special damages. The High Court also awarded general damages
of Ug. Shs. 40,000,000/= and punitive damages of Ug. Shs. 30,000,000/=,
interest on the comblned award of damages at 10% per annum from the
date of judgment
till payment in full, and costs. The appellant's counter-
claim was also dismissed with costs.
The appellant appealed to the Court of Appeal but was unsuccessful, hence
this further appeal to this Court. The grounds of appeal are as follows:
"(1) The Learned Justices of the Court of Appeal erred in law and fact
when they failed to reappraise themselves of the evidence on
record and make independent findings which resulted into
dismissing the Appellant's Appeal.
(2) The Learned Justices of the Court of Appeal erred in law and fact
when they upheld the decision of the Trial Court awarding the
Respondent Special damages of Ug. Shs. 208,186,120 without
specific proof.
2
(3) The Learned Justices of the Court of Appeal erred in taw and fact
when they found that the Appellant was in breach of the contract
executed with the Respondent,
(4) The Learned Justices of the Court of Appeal erred in law and fact
when they found that the Respondent is entitled to Generai
damages of Ug. Shs.40,000,000/= and punitive damages of Ug,
Shs. 30,000,000/=.
(5) The Learned Justices of the Court of Appeal erred in law and fact
when they held that the Respondent was not estopped from
making fudher claims against the Appellant after it had received
payment in full and final settlement of all its claims and undertook
not to make any further claims against the Appellant.
(6) The Learned Justices of the Court of Appeal erred in Iaw and fact
when they found that the Respondent is entitled to interest on the
decretal sums at 10olo per annum from the date of judgment."
The appellant prayed this Court for orders that:
'i) The appeal be ailowed.
ii) The decision of the Court of Appeal be set aside.
iii) The appellant be granted the costs ofthe appeal and in the Courts
below."
The respondent opposed the appeal.
Representation
At the hearing, Mr. Isaac Walukagga and Mr. Raymond Ndyagambaki, both
learned counsel, jointly
appeared for the Appellant. Mr. Caleb Alaka learned
counsel, appeared for the respondent.
Appellant's submissions
Counsel for the appellant argued the grounds of appeal in the followlng
order; grounds 1, 2 and 3 jointly, followed respectively by each of grounds
5, 4 and 6, independently.
3
Grounds 1, 2 and 3
The key point made by counsel in the submissions on grounds 1, 2 and 3 is
that the Court of Appeal, in several respects, failed to properly reappraise
the evidence as required by law, and as a result it arrived at the wrong
decision of upholding the judgment of
the trial Court.
In the first respect, counsel submitted that the evidence adduced at the trial
showed that the appellant duly paid the respondent for the work done, in
accordance with the pafties'agreement. Counsel pointed out that the parties
agreed that the respondent would be paid Ug. Shs, 18,000/- per sq. metre
of stone-pitching work done. Further, that according to Exhibit D2, a report
showing the work done by the respondent, the actual stone-pitching work
done measured 6,544.67 sq. metres, which, in light of the parties'agreement
entitled the respondent to payment of Ug. Shs. 117,804,0601-. Counsel
pointed out that the appellant paid the respondent for 7272 sq. metres of
stone-pitching work at an amount of Ug.Shs. L30,907,3401= which indlcated
an over payment. In those circumstances, according to counsel, the
respondent was not entitled to any further payment. Counsel faulted the
Court of Appeal for failing to properly reappraise the evidence leading it to
erroneously upholding the decislon of the trial Court yet the learned trial
Judge ignored the above-highlighted evidence while arriving at his decislon.
In the second respect, counsel submitted that the Court of Appeal failed to
reappraise the evidence in regard to the respondent's claims that the
appellant had refused to pay for certain extra works it carried out, namely
works pinpointed in certificates tendered in evidence as Exhibits P1 (b) (i)
-
(vi). According to counsel, the trial Court ordered a re-measurement of
the amount of work done by the respondent, with the results from this
exercise captured in Exhibit D2 showing that the respondent did less work
done was paid for.
Thirdly, counsel submitted that the Court of Appeal failed to reappraise the
evidence showing that the respondent did not, in its pleadlngs, set out the
basis for computation of the amount claimed for the extra works. He
submitted that the claims for extra works for items llke cast concrete to
4
foundation base, demobilization expenses and accumulated incorrect
quantities were not pleaded and neither did the respondent adduce evidence
to prove the same.
In addition, counsel submitted that the parties' binding agreement did not
provide for payment for extra works, and thus in allowing the respondent's
claims, the lower Courts contravened the principle that parties are bound by
their agreements and cannot be allowed to depart therefrom. For this
proposition, counsel relied on Access Financia! Seruices PLC Ltd vs.
Rutiba, High Court Civil Suit No. 61 of 2OO7 (unreported), where the
Court refused to allow a party to succeed on a case that departed from her
pleadings.
Counsel concluded his submissions on grounds 1, 2 and 3 by submitting that
the award of special damages of Ug. Shs. 208,t86,1201- by the trial Court
that was upheld by the Court of Appeal was erroneous as the respondent
neither specifically pleaded nor proved the said damages. Fufther that, the
decision awarding special damages was against the weight of the evidence
on record. Counsel submltted that ground l, 2 and3 ought to succeed.
Ground 5
In support of ground 5, counsel submitted that prior to the respondent
instituting the suit in the trial Court, the pafties had executed Exhibit D3 in
which the respondent undertook not to make further claims against the
appellant, in connection with the stone-pitching project. In counsel's view,
the undertaking estopped the respondent from making the claims which
formed the basis of the special damages awarded to it. Counsel relied on
Stanbic Bank Uganda Ltd vs. Uganda Crocs Ltd, Supreme Court Civil
Appeal No. O4 of 2004 (unreported) for the principles on estoppel.
Counsel contended that the lower Courts refused to consider the evidence
of the undeftaking which resulted in their erroneous decisions to award
damages to the respondent. Counsel submitted that ground 5 should also
succeed.
5
Ground 4
Counsel submitted that the Court of Appeal failed to reappraise the relevant
evidence and consequently reached an erroneous decision to uphold the trlal
Court's respective awards to the respondent of Ug. Shs. 40,000,000/= and
Ug. Shs. 30,000,000/- as general and punitive damages, respectively.
Counsel submitted that the evidence did not support the trial Court's findings
of two instances of breach of contract that formed the basis of the award of
damages, namely; 1) failure to pay the respondent for certain works; and 2)
unlawful variation of fuel and cement prlces. In relatlon to the failure to pay
for certaln works, counsel contended that Exhibit D2, a report tendered in
evidence showed that the respondent was not only duly paid but was
overpaid for some of the work done. With regard to the variation of fuel and
cement prices, counsel submitted that the respondent was supplied fuel and
cement at prices which it accepted. Therefore, according to counsel there
was no loss suffered by the respondent to justify the damages awarded to
it.
Fufthermore, counsel submitted that the award of general damages of Ug.
Shs. 40,000,000/= was excessive and served more than just compensating
the respondent since it had already been awarded U9. Shs. 208,186,7201-
as special damages,
Further still, and in relation to the award of punitive damages, counsel
submitted that the Court of Appeal erred in upholding the trial Couft's award
of punitive damages yet the principles for awarding that class of damages,
as set out in Omunyokol Akol Johnson vs. Attorney General, Supreme
Court Civil Appeal No 6 of 2O12 (unreported) were not satisfied in thls
case. In Omunyokol Akol Johnson (supra), it was held that punitive
damages may be awarded only in the following cases:
'1) Where the government servants had been guilty of oppressive,
arbitrary or unconstitutional action.
2) Where the defendant's conduct had been calculated by him to
make a profit for himself which may exceed the compensation
payable to the plaintiff.
6
3) Where such an award was sanctioned by statute."
Counsel thus contended that the circumstances of this case did not justify
an award of punitive damages.
Counsel submitted that the respondent adduced no evidence justifuing
the
award of general damages and thus the Court of Appeal erred in upholding
the trial Court's award of general damages.
Counsel submitted that ground 4 of the appeal also ought to succeed.
Ground 6
Counsel for the respondent argued the grounds in the same manner as his
colleagues for the appellant.
Grounds L,2and3
Counsel for the respondent submitted that the lower Courts properly
considered the pleadings and adequately evaluated the evidence on breach
of contract before finding in favour of the respondent. The High Court
considered thatthe appellant had breached the contract with the respondent
by: 1) unilaterally increasing the price of cement and fuel over the prices
agreed upon in the contract; and 2) retaining some of the money owing to
the respondent yet the contract did not provide for retention. The Court of
Appeal after re-evaluating the evidence found that the appellant had
breached the contract by; 1) failing to pay the respondent for additional
works it had done in accordance with a work plan authorized by their
1
Counsel submitted that the Court of Appeal erred in upholding the trial
Court's award of interest of l0o/o on the decretal sums awarded to the
respondent because in his view: 1) the respondent was not kept out of any
money to justify
awarding interest; and 2) the rate of interest was manifestly
excessive and a fair rate should have been 6010. Counsel submitted that Couft
finds that ground 6 ought to succeed.
Respondent's submissions
contrac! and 2) unilaterally increasing the price of cement and diesel to the
detriment of the respondent.
With regard to the appellant's submission that the respondent was duly paid
for all the work done as set out in Exhibit D2, a repoft of work done by the
respondent, counsel submltted that the Court of Appeal declined to rely on
Exhibit D2 because its author was just
a student pursuing and not an
engineer and was therefore not competent to give evidence on the work
done by the respondent.
In relation to the submission that the Court of Appeal erred in upholding the
trial Court's award of Ug. Shs. 208,186,123 to the respondent as special
damages, counsel submitted that the said award was justified given that the
respondent specifically pleaded and strictly proved its claim for special
damages. According to counsel, the respondent led evidence to prove the
respective heads for which special damages were claimed.
Counsel concluded by submitting that grounds l, 2 and 3 ought to fail.
Ground 5
Counsel concluded by submitting that ground 5 should also fail.
Grounds 4 and 6
With respect to grounds 4 and 6, counsel submitted that the Court of Appeal
applied the correct principles as set out in Bholm vs. Car and General
Ltd, Supreme Court Civil Appeal No. 12 of 2OO2 (unreported), in
upholding the trial Court's award of Ug, Shs. 40,000,0007= 1o the respondent
as general damages. In the Bholm case (supra), it was held that:
8
Counsel submitted that ground 5 should not be entertained as it is raising a
new point that the appellant did not raise before the Court of Appeal.
Furthermore, counsel submitted that Exhibit D3 applied only to the breach
relating to retention money and not the entire claim against the appellant as
submitted by counsel for the appellant,
"An appellate Court will not reverse a judgment, or part of a judgment
of a Court below on a question of damages unless the appellate court is
satisfied that the judge acted on a wrong principle or that the amount
awarded was so extremely large or so very small as to make it an entirely
erroneous estimate of the damage."
According to counsel, as the Court of Appeal found no reason to interfere
with the award of general damages, it rightly upheld the same.
On the award of punltive damages, counsel submitted that the Court of
Appeal correctly applied that the principle set out in Omunyokol Akol
Johnson vs. Attorney General, Supreme Court Civil Appeal No. 6 of
2012 (unreported) that punitive damages may be awarded, "...where
the defendant's conduct had been calculated by him to make a
profit for himself which may exceed the compensation payable to
the plaintiff." Counsel contended that the respondent was a victim of
conduct by which the respondent sought to make a profit and accordlng
punitive damages were appropriate. He prayed that grounds 4 and 6 also be
disallowed.
Ground 6
On ground 6, counsel submitted that interest of 100/o was fair and there was
no compelling reason for the Court of Appeal to interfere. He urged this Court
to disallow ground 6.
Consideration of the Appeal
I have carefully studied the record, and considered the submissions of the
respective counsel, as well as the law and authorities cited. I have also
considered other applicable authoritles that were not cited.
This is a second appeal from a decision of the Court of Appeal that affirmed
a decision rendered by the High Court in exercise of its originaljurisdiction.
I shall begin by setting out the main principles governing the exercise of this
Court's
jurisdiction in second appeals. Rule 3O (1) of the Judicature
(Supreme Court Rules) Directions, SI 13-10 provides that:
9
"30. Power to reappraise evidence
(1) Where the Court of Appeal has reverced, affirmed or varied a
decision of the High Court acting in its original jurisdiction,
the
court may decide matters of law or mixed law and fact, but shall
not have discretion to take additaonal evidence."
It is now well-established from the case law that, on second appeals, this
Court will consider the points of law presented for determination, but will not
ordinarily reappraise the evidence unless exceptional circumstances justiflT
its doing so. In Goustar Enterprises Ltd vs. John Kokas Oumo,
Supreme Court Civil Appeal No. O8 of 2OO3 (unreported), this Court
held that:
"...as a second appellate court, except in the clearest of cases, we are
not required to re-evaluate the evidence like a first appellate Court.
However, we stated in the case of Kifamunte Henry vs. Uganda Cr,
Appeal No. 10 of 1997 that where the Court of Appeal has failed to do so
or has applied wrong principles as in that case, we must correct any
errors committed."
In the Goustar Enterprises Ltd case (supra), the Court gave examples
of exceptional circumstances justin/ing reappraisal of evidence to include:
I shall bear the above principles in mind as I consider the grounds of appeal.
I shall consider the grounds in the following manner: first, grounds l, 2 and
3 jolntly, followed by grounds 4 and 6 jointly, and lastly, ground 5
independently.
Grounds 1,2 and 3
The main point made in counsel for the appellant's submissions on grounds
I, 2 and 3 is that the Court of Appeal's decision to uphold the trial Court's
award of Ug. Shs. 208,186,1231= as special damages to the respondent was
10
"...where it is apparent that the evidence on record has not been
subjected to adequate scrutiny by the trial Judge or the first appellate
Court, as the case may be, the appellate Court has an obligation to do
so."
unjustified because of two main reasons: 1) the appellant did not owe the
respondent any money, and instead the evldence showed that the appellant
paid more than was due to the respondent under the parties'contract; 2)
the respondent did not prove lts claim for unpaid works which constituted
part of the special damages awarded by the learned trial Judge.
The Court of Appeal did not address the above-highlighted points despite
the appellant having raised them before it, which, in my view, amounted to
failure by the Court of Appeal to exercise its duty to reappraise the evidence
and make its own conclusions. I shall, therefore, proceed to re-evaluate the
evidence so as to address these points.
The respondent averred at paras 5 to 9 of lts 2nd amended plaint, as follows:
5 The plaintiff shall aver and prove that the amounts of works
executed on behalf of the defendant and as per the contract
formulae ol 2.32 m2 under all the 6 interim certificates i.e No.
llL9i 2l2O; 3l2L; 4122i 5123 & 5/24 totals to 11,223.59 m2 and
other works equiyalent to Ugx. 324,936,8001=.
The plaintiff was only paid for total works under Cert. No. 1 & 3
measuring 3799.25 m2 exclusive of diesel and cement sold worth
Ugx. 28,468,064/- together with the advanced Ugx. 4,000,000/=
totaling to Ugx. 32,468,0641= which constitutes just only 9.7.45o/o
ofthe plaintiff's executed works under the project,
The plaintiff shall aver and prove that, for all the works it
executed, the defendant was fully paid 100o/o of 11,234.91 m2at
LOL,TLO per m2 worth Ugx. L,L42,7O2,696/= and the defendant
ought to have been pleased enough to pay the plaintiff what was
due to her, which she did not.
The plaintiff shall further aver and prove that later discovery
disclosed precisely quantities in para 7 a bove, the defendant's IPC.
No. 19-26, it was discovered that RAFU had certified and 100o/o
fully paid works invoiced by the defendant in the categories of
1232.18 m2for Cert No.1; 1620.51 m2for Cert No.2; 2001.71 m2
for Cert No.3; 805.90 m2 for Cert No.4; 1414,61 m2 for Cert No.s;
2212.69 m2for Cert. No, 6; 1571.32m21or Cert. No. 25 and 375.A4
11
6
8
7.
m2 for Cert. No. 26 respectively, which altogether total to
LL,234.9 I m
2
at U gx. LOl,7 LO | =
tota I i ng to U gx. L,142,7 O2,9 69 | =
whereas the plaintiff only receaved Ugx. 32,468,064/= frqm 16.
defendant.
The plaintiff shall aver and prove that the defendant calculated to
negative deficits and never attempted to pay off amounts invoiced
and due under Certs, No. 2,4, 5 and 6, save for Ce*s. No, 1 and 3
which were incorrectly calculated and paid creating a wrong
impression that the defendant owes the plaintiff nothing."
The appellant disputed the above clalms and contended at para 5 of its
written statement of defence that:
"The defendant shall further aver that its dealings with the Road Agency
Formation Unit have no bearing on the plaintiff's claim and/or works in
light of the sub-contract aforementioned."
I noted that prior to institution of the respondent's suit, the appellant had
computed that the respondent carried out 7272.63 m2 of stone-pitching
works (See: Interim Certificate No. 6). But as set out earlier, the
respondent's case was that it carried out stone-pitching work measuring
tL,234.91 m2. The question that immediately arises is whether or not the
respondent proved that it carried out stone pitching work covering 11,234.9t
m2.
PW1 Okot Olum Charles, the respondent's Managing Director testified in
support of the respondent's case. He stated that the respondent did more
work than was recorded by the appellant in the interim payment certificates
Nos. 2 to 6. The amount of work actually done by the respondent and the
amount for which the appellant paid are summarised in the table below:
Interim
Certificate
No.
Work actually
done (A) (m2)
Work certified by the
Appellant (BXm')
Difference (A-B)
(m')
No. 1 t420.8 1420.8 Nil
No.2 2277,67 7777.72 933.89
12
9
No.3 2683.85 2378.45 305.4
No.4 2326 868 1458
No.5 672.3 600 72.3
No.6 808.54 727.63 80.91
TOTAL 8,707.45 7277.63 t428.82
I further noted that PW1 also testified, at page 90 of the record, that in total,
the amount of work done by the respondent that remained unpaid measured
BB83,B1 m2. At the price of Ug, Shs. 18,000 per sq. metre, this represented
Ug, Shs. 159,908,580/-. However, as indicated in the above table, the
correct computation of the amount of work done as per PW1's evidence was
8,701.45 m2 translatlng to Ug. Shs. 156,626,1001-.
PW1 stated in cross-examination that the appellant prepared fraudulent
ceftificates wherein it indicated less work than had actually been done by
the respondent. In a passage at page 134 of the record, PWl stated as
follows:
"Walukaga: Do you confirm that such ceftificates covered the works you
had done?
PW1: No, they didn't cover the works we had done, they were
fraudulently reduced to smaller quantities that we did. Certificates
passes were issued by the client's representatives handed it over to the
defendant, the defendant on receipt of those certified work hid them
under their confidential custody."
PW1 therefore gave oral evidence of the existence of other invoices prepared
by the project client that set out the correct amount of work done by the
respondent/ and that the correct amount was more than was certified and
paid for by the appellant. However, it will be noted that the invoices prepared
by the project client were not tendered in evidence and this made it difficult
to verify PW1's oral evidence,
13
I further noted another dimension of PWl's evidence which was that the
respondent carried out extra works but was not allowed to make an invoice
for the same. PW1 testified that the respondent did demolition and repitching
works on dralns on the road leading to Katwe Army Barracks at a cost of Ug.
Shs. 8,108,480/= and Ug. Shs. 5,497,0001- respectively, but was not paid
for this work by the appellant.
Therefore, according to my analysis of PW1's evidence, the total amount of
money, without deducting the cost of the cement and diesel supplied by the
appellant, that remained unpaid to the respondent (for invoiced and un-
invoiced work) was Ug. Shs. 170,231,5801-. However, regarding the
respondent's claim for unpaid work, the learned trial Judge found that:
"In this case, the Plaintiff led evidence to prove special damages as
pleaded in his plaint and I allow the same at Ug. Shs. 2O8,L86,L2O|=
(Uganda Shillings Two Hundred Eight Million One Hundred Eighty-Six
Thousand One Hundred Twenty Shillings Only."
The learned trial Judge made no attempt In hls judgment to analyze the
evidence that led him into concluding that the respondent had proved the
quantum of special damages that it was awarded. He only made the
summary findings set out above. I have therefore reappraised the evidence
in order to establish whether the respondent proved his case for unpaid
works, and if so whether the amount of money he was entitled to was to the
tune awarded by the lower courts or less.
I earlier referred to the respondent's pleadings with respect to its claim for
special damages and to the key evidence of PW1 in support of the
respondent's claim for special damages, which PW1 stated comprised of
unpaid invoiced and un-invoiced work. It is worth reiterating that special
damages are such damages as the law will not presume to be the
consequences ofthe defendant's act. Such damages depend in part, at least,
on the special circumstances of the case and must therefore always be
explicitly claimed in the pleadings and, at trial, must be proved by evidence
proving both that the loss was incurred and that it was the direct result of
the defendant's conduct. See: Musoke v Depafted Asians' Propefi
Custodian Board and another [199O-1994]
1 EA 419 quoting from
1,4
Odger's Principles of Pleading and Practice (21 ed.). Further, in
relation to pleading and proof of special damages, this Couft held in the case
of Mutekanga v Equator Growers (U) Ltd
[1995-1998]
2 EA 219 as
follows:
"Again, it is trite law that special damages and loss of profit must be
specifically pleaded, as it was done in the instant case. They must also
be proved exactly, that is to say, on the balance of probabilities.
This rule applies where a suit proceeds inter partes or ex parte. It follows
that even where as in the instant case, the defendant neither enters
appearance nor files a defence, the plaintiff bears the burden to prove
his case to the required standard. The burden and standard of proof does
not become any less.
As the learned author stated in MC Gregor on Damages (4 ed) at 1028,
the evidence in special damages must show the same particularity as is
necessary from its pleading. It should therefore, normatly consist of
evidence of particular losses such as the loss of specific customers or
specific contracts.
However, with proof as with pleadings, the Courts are realistic and
accept that the particularity must be tailored to the facts.
In one of the leading cases on pleading and proof of damages, namely,
Ratcliffe v Evans
[1892]
2
QB
524, Bowden lJ, said this at 532-533:
"The character of the acts themselves which produce the damage, and
the circumstances under which these acts are done must regulate the
degree of certainty and particularity with which the damage ought to be
proved, As such, certainty must be insisted on in proof of damage as is
reasonable, having regard to the circumstances and the nature of the
acts themselves by which the damage is done, To insist upon less would
be to relax old and intelligible principles. To insist upon mone would be
the vainest pandatory,"
In the present case, the evidence in support of the amount of money claimed
by the respondent as special damages emerged only in the oral evidence of
PW1. I have reviewed PWl's evidence and, for the reasons that will follow,
I am not satisfied that that evidence assisted the respondent to prove its
claim for special damages to a satisfactory standard.
15
16
First, the oral evidence of PW1 was difficult to verify. In Armagas Ltd v
Mundogas SA (The Ocean Frost)
[1985]
1 LIoyd's Rep 1 (per Lord
Justice GofF) lt was held that:
"Speaking from my own experience, I have found it essential in cases of
fraud, when considering the credibility of witnesses, always to test their
veracity by reference to the objective facts proved independently of
their testimony, in pafticular by reference to the documents in the case,
and also to pay particular regard to their motives and to the overall
probabilities. It is frequently very difficult to tell whether a witness is
telling the truth or not; and where there is a conflict of evidence such as
there was in the present case, reference to the objective facts and
documents, to the witnesses' motives, and to the overall probabilities,
can be of vely great assistance to a Judge in ascertaining the truth."
I agree with the above principles. In the present case, there were neither
objective facts independent of PW1's oral testimony nor contemporaneous
documents proving the respondent's claim for special damages. I noted
PW1's evidence that the project client had prepared Invoices that correctly
set out the amount of work done by the respondent, but these were not
adduced in evidence. For these reasons, I would find that the oral evidence
of PWl was insufficient to prove the respondent's case.
Secondly, PW1's pleadings and evidence set out different sums in relation to
the amount of unpaid work done by the respondent; 11,234.91 m2 according
to the pleadings; and 8883.81 m2 plus other un-invoiced work according to
PW1's evldence.
Thirdly, the payment certificates that were prepared by the appellant but
also endorsed by the respondent indicated that it had carrled out works
measuring 7272.63 m2
Fourthly, there was evidence given by DW1 Kasiita A. Mustafa that the trial
Court commissioned a survey to investlgate the amount of work done by the
respondent and the findings were set out In Exhibit D2 which concluded that
the total amount of work done by the respondent was 6544.67 m2 The report
was not seriously challenged in cross examination. However, I noted that
the learned trial Judge in his judgment doubted DW1's expertise and
competence to prepare the report, He stated as follows:
"Although the defendant company employed him as an expert, he was
surely not one as he was merely pursuing a Diploma course in the field
he was employed as an expert. To rely on his evidence or expertise he
does not possess would surely be misleading this Court."
In my view, the contents of Exhibit D2 could not, in the circumstances of this
case, be doubted. The report was produced following a survey that was
ordered by the trlal Court, and was the joint work of representatives of both
the appellant and the respondent, that is DW1 for the appellant and Mr.
Nicholas E. Oder for the respondent. DW1's competence was not challenged
at the trial and thus the learned trial Judge's findings that he was not an
expeft had no basis. I would believe Exhibit D2 as rendering it highly
probable that the amount of work done by the respondent was less than the
appellant actually paid for. This further complicated the prospects of success
of the respondent's case.
The other aspect of the respondent's case was that the appellant unilaterally
inflated the prices of diesel and cement contrary to the paties'contract. The
parties had agreed in their contract that the appellant would supply the
respondent with diesel and cement as required for the stone pitching works
at the price of Ug. Shs. 1850 per litre of diesel and Ug. Shs. 19,4001= per
bag of cement. The interim payment certificates Nos. 2, 3, 4, 5 and 6 all
indicated that the appellant charged a hlgher price than agreed in the
contract of Ug. Shs. 20501- (excess of Ug. Shs. 2001-) for diesel and Ug.
Shs. 19500/= (excess of Ug. Shs. 100/=; for cement. PW1 testified that the
respondent suffered a loss of Ug. Shs. 2,445,9001- arlsing from being
charged more for diesel and cement than it ought to have been charged.
The respondent's reason for charging increased prices for diesel and cement
according to the testimony of DWl was that there had been a fluctuation in
the prices of diesel and cement which necessitated the charging of higher
prices. However, the parties' contract anticipated the charging of a fixed
price for cement and diesel by the appellant and did not give allowance for
charging of a higher price because of price fluctuation. This claim for
17
charging of increased prices for cement and diesel contrary to the parties
contract therefore had merit.
owing to the above analysis, I would accept the submission of counsel for
the appellant that the respondent did not prove its case for unpaid works
against the appellant and was not entitled to the special damages it pleaded.
Grounds 1 and 2 would therefore succeed. Ground 3 would also largely
succeed but would fail to the extent that the appellant acted in breach of
contract by supplying diesel and cement at higher prices than was agreed in
the parties'contract causing the respondent loss to the tune of Ug. Shs.
2,499,000/-.
Grounds 4 and 6
Ground 4 challenges the trial court's respective awards to the respondent of
Ug. Shs. 40,000,000/= as special damages and Ug. Shs. 30,000,000/- as
punitive damages, that were upheld by the Court of Appeal. Ground 6
challenges the award of interest by the trial court. Having earlier found that
the respondent did not prove its case for unpaid works against the appellant,
it would follow that the awards of general and punitive damages and interest
against the appellants must be set aside.
Grounds 4 and 6 would also succeed,
Ground 5
I need not consider ground 5 because, the appellant having succeeded on
grounds I, 2, 3, 4 and 6, is sufficient to dispose of the appeal.
In conclusion, I would allow the appeal and make the following orders:
a) The respective decisions of the Court of Appeal and High Court are set
aside.
b) The respondent's suit in the High Court substantially fails and only
succeeds with respect to the claim that the appellant unlawfully charged
higher prices of diesel and cement than was agreed in the parties,
contract.
18
c) The appellant shall pay the respondent Ug. Shs. 2,499,0001= for loss
suffered due to the charging of higher prices of fuel and diesel.
d) The amount in (c) shall attract interest at Bolo per annum from the date
of filing of the respondent's suit in the trial Court till payment in full.
e) The appellant shall be paid
3/+
of the total costs of this appeal and in the
courts below.
3"4
t
Dated at Kampala this day of ......2025.
Elizabeth Musoke
Justice of the Supreme Court
19
5 THE REPUBLIC OF UGANDA,
IN THE SUPREME COURT OF UGANDA AT KAMPALA
(CORAM:TUHAISE, CHIBITA, MUSOKE, MUSOTA, MADRAMA, JJSC)
CIVIL APPEAL NO 014 OF 2018
SBI INTERNATIONAL COMPANY LTD} APPELLANT
VERSUS
coF TNTERNATIONAL CoMPANY LTD) RESPONDENT
(Appeat against the decision of the Court of Appeal in Court of Appeal
Civil Appeal No. 194 of 2014 dated 27 May 2018 before
(Kasule, Kakuru
and Obura, JJA)
JUDGMENT OF CHRISTOPHER MADRAMA IZAMA. JSC
I have reviewed the draft judgment prepared
by my learned sister, Musoke,
JSC, which comprehensivel.y outtines the facts, issues, and arguments
presented by counset. I find it unnecessary to rerterate these, as my learned
sister has adequatety addressed them. The crux of the judgment is that the
conclusions of the lower courts regarding the extent of work performed by
the pl.aintiff/respondent in this appeal. are not supported by credibte
evidence, given the evidence reviewed. lndeed, the evidence on record
supports the appetLant's defense, and such an issue is considered a matter
of [aw. The taw is that a conctusion lacking credibte evidentiary support is
tegatty untenabte and witt be set aside.
I wish to emphasize that the factuat dispute concerning the amount of work
compLeted by the respondent, which formed the basis for their ctaim for
damages, necessitates further observation in addition to the Lead
judgment's anatysis of how the court sought to resolve this controversy.
The appeal. record ctearty indicates that PWl testified regarding the court-
commissioned
joint expert measurement of the totaI work compteted by the
ptaintiff, incLuding the ptaintiff's experts' participation.
PWI confirmed that
15
20
25
30
1
10
the court ordered the measurement, and the ptaintiff participated in this
joint effort. The centrat factuaL dispute revolved around whether the work
covered 7,272.63 m' or, as stated in the joint report, 6'51+4 66'l m' PWl
attempted to dispute the joint report by stating that the report was not
according to the court's terms of reference. 0n the other hand, DWl testif ied
that the court directed him to conduct a joint measurement survey with a
quantity surveyor representing the ptaintiff to verify the measurements of
the executed works. DW1 compl.eted the
joint survey, and they determined
the totat measurement of the work done to be 6,544.67 m', of grouted stone
pitching, which was to be muttipl'ied by Uganda shittings 18,000/='
I note that court-ordered inquiries or trials are conducted under the
Judicature Act, Cap 13, 2000 Laws of Uganda, specificatty sections 26 and
27 (prior to the 2023 revision). I wil.t refer to the sections before revision
and at the time of the proceedings. NotabLy, the initiat proceedings involving
a pretriaL conference and order of reference were before a different
judge.
The scheduLing conference notes and the order of reference are not on
record. Each party catted one witness, PW1 and DW1, respectivety. The
examination of these witnesses occurred before yet another judge,
different
from the one who ordered the
joint team measurement. lt can be inferred
from the facts and Law that reference proceedings fatl under sections 26 or
27 of the Judicature Act, which stiputate:
10
15
20
25
30
26. References to referees.
(1) The High court may, in accordance with rutes of court, refer to an official or
special referee for inquiry and report any question arising in any cause or matter,
other than in a criminal proceeding.
(2) The report of an officiaL or special referee may be adopted whoLty or partly by
the High court and if so adopted may be enforced as a judgment or order of the
High Court.
27.frial by referee or arbitrator.
Where in any cause or matter, other than a criminal proceeding-
(a) att the parties interested who are not under disabiLity consent;
2
35
(b) the cause or matter requires any prolonged examination of documents or any
scientific or Lega[ investigation which cannot, in the opinion of the High court,
convenientty be conducted by the High Court through its ordinary officers; or
(c) the question in dispute consists wholly or partly of accounts, the High Court
may, at any time, order the whole cause or matter or any question of fact arising
in it to be tried before a speciaI referee or arbitrator agreed to by the parties or
before an officiaI referee or an officer of the High Court.
A court-ordered inquiry and report on a question arising in a cause or
matter fatts under section 26 of the Judicature Act. A reference for triat fatts
under section 27 and resutts in an arbitral award, which can only be
chaLl.enged on the grounds specified in Order 47, Rul'e 15 of the Civit
Procedure Rutes.
ln this case, there was no arbitral award, but an inquiry resulted in the
submission and admission of a
joint report, Exhibit D2, indicating that the
reference was for inquiry on a matter of fact under section 26 of the
Judicature Act. The report estabLished the extent of the work performed by
the ptaintiff/respondent. The report's findings lead to the inference that the
work measured was aLready paid for, and the respondent's ctaim was for
work al.LegedLy done beyond the scope of the joint report's measurements.
The learned triat judge's duty was to either adopt or reject the report. The
judge rejected the report based on doubts about DWI's quatifications. DW1,
Kasiita A. Mustafa, identified himsetf as a road inspector emptoyed by
Nichotas 0duwe ConsuLting Engineers and Ptanners. Under cross-
examination, he stated that he hel.d a higher diptoma in civil' engineering
from Kyambogo University and worked as a measurement technician,
joining the defendant company f rom 2004 to 2008. The triaL judge questioned
DW1's qual.if ications, but there is no credibte basis to assert that a
measurement technician, as DWl was, coutd not perform the
measurements ordered by the court. The measurement was ordered after
the suit was fited. cruciatl.y, the report was
jointty prepared by Mr. Nichol.as
E. Oduwe for the ptaintiff/respondent and DWl for the defendant/appetl.ant.
The quatifications of Mr. NichoLas 0duwe were not even referred to As a
joint report based on a court-ordered factuaI inquiry, there was no
10
15
20
25
30
35
5
and agree with aLt the proposed orde;F.
Dated at KamPata 16"
3ffi or
10
L 2025
op er Madrama lzama
Justice of the SuPreme Court
4
justification for rejecting the measurements contained within it The
damages ctaim hinged on the assertion that the ptarntiff
compteted more
work than measured in the
joint report.
ln conctusion, I concur with the
judgment of my learned sister, Musoke, JSC,
I
THE REPUBLIC OF UGANDA
IN THE SUPREME COURT OF UGANDA AT KAMPALA
(Coram: Tuhaise, Chibita, Musoke, Musota & Madrama,IJSC)
CNIL APPEAL NO.14 OF 2018
SBI INTERNATIONAL HOLDINGS AG (U)
LTD...
......APPELLANT
Versus
COF INTERNATIONAL COMPANY
LTD...
............RESPONDENT
(Atr nppent nrising
front
tlrc
ltdgnrcnt
of tlrc Court of Appenl in Ciuil Alp':!lo
lgis' of ZOI+ befora Kasulc, Knkr,,tt nnrl Oburn, IJA,
dnted 23"t Mny, 20'18.)
proposed.
since all members of the Coram agree with the lead judgement, this
appeal is allowed with the orders as proposed in the lead
judgment.
Judgment
of Percy Night Tuhaise,
fSC
I have had the benefit of reacling in draft the
]udgment
prepared
by *y learned sister Lady
]ustice Elizabeth Musoke, |SC'
I agree
with irer findings and decision. I also agree with the orders she has
Dated at Kampala, this ... 3*..day of
2025.
.,^I,..o^,"'t'q
Percy Night Tuhaise
fustice of
the SuPreme Court
IN THE SUPREME COURT OF UGANDA
AT KAMPALA
(CORAM: TUHAISE, CHIBITA, MUSOKE, MUSOTA, MADRAMA,IISCI
CIVIT APPEAL NO 014 OF 2018
SBI INTERNATIONAL COMPANY LTD APPELLANT
VERSUS
COF INTERNATIONAt COMPANY LTD ::: : : : ::::::r:r:: : r::: RESPONDENT
(Appeal against the decision of the Court of Appeal in Court of Appeal Civil Appeal No, 194 of
2014 dated 23d May 2018 b€fore (Kasule, Kakuru and Obura, JJA)
JUDGMENT OF CHIBITA JSC
I have had the benefit of reading in draft judgment prepared by my
learned sister, Justice Elizabeth Musoke, JSC, and I agree with her
reasoning, analysis and the orders she has proposed.
+
M
J
Dated at Kampala this
)
.day of
A)
202s
on tce ik e ibita
JUSTICE OF THE SUPREME COURT
tt\ 'tf^,5
BAr%
u&
)a;*^">
>_oe=q,
Drr^'t
a{t SC
THE REPUBLIC OF UGANDA
Spe^"
(
THE REPUBLIC OF UGANDA
IN THE SUPREME COURT OF UGANDA AT I(AMPALA
CIVIL APPEAL NO. O14 OF 2O2O
(Aising out of the decision of the Court of Appeal (Kasule, Kakunt and Obura,
JJA) in Ciuil Appeal No. 194 of 2014)
CORAM: TUI{AISE; CHIBITA; MUSOKE; MUSOTA; MAI)RAMA,
JJSC
SBI INTERNATIONAL HOLDINGS AG (U) LTD ::::::::: APPELLANT
VERSUS
COF INTERNATIONAL COMPAtil]I LTD : : : : : : : : : : : : : : : R.ETSPONDENT
JUDGMENT OF STEPHEN MUSOTA, JSC
I have had the benefit of reading in draft the judgment by my sister
Hon. Justice Elizabeth Musoke, JSC.
I agree with her analysis, conclusions and the orders she has
proposed. I have nothing useful to add.
Dated this 3
,4
day of 2025
@o"Tl".-'.''
Stephen Musota
WSTICE OF THI SUPREME COURT
Similar Cases
Sebasif Group Enterprises Limited v DFCU Bank Limited (Civil Appeal No. 28 of 2021) [2026] UGSC 15 (21 April 2026)
[2026] UGSC 15Supreme Court of Uganda84% similar
Stanbic Bank (U) Ltd v Atabya Agencies [2006] UGSC 6 (15 March 2006)
[2006] UGSC 6Supreme Court of Uganda83% similar
Stanbic Bank Ltd v Kiyemba Mutale (Civil Appeal 2 of 2010) [2011] UGSC 32 (6 December 2011)
[2011] UGSC 32Supreme Court of Uganda83% similar
Crane Bank Ltd v Nipun Narottam Bhatia [2015] UGSC 16 (20 August 2015)
[2015] UGSC 16Supreme Court of Uganda81% similar
Bisimillah Trading Ltd v Falcon Estates Ltd [2017] UGSC 46 (24 November 2017)
[2017] UGSC 46Supreme Court of Uganda81% similar