Case Law[2022] ZASCA 56South Africa
Commissioner, South African Revenue Service v Sasol Chevron Holdings Limited (1044/2020) [2022] ZASCA 56; 85 SATC 216 (22 April 2022)
Headnotes
Summary: Administrative law – Promotion of Administrative Justice Act 3 of 2000 (PAJA) – application for review of administrative action – delay in instituting application – s 7(1) of PAJA – no agreement between the parties under s 9(1) for extension of period prescribed in terms of s 7(1) – nor application to court under s 9(2) for extension of the prescribed 180 day period.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Supreme Court of Appeal
South Africa: Supreme Court of Appeal
You are here:
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2022
>>
[2022] ZASCA 56
|
Noteup
|
LawCite
sino index
## Commissioner, South African Revenue Service v Sasol Chevron Holdings Limited (1044/2020) [2022] ZASCA 56; 85 SATC 216 (22 April 2022)
Commissioner, South African Revenue Service v Sasol Chevron Holdings Limited (1044/2020) [2022] ZASCA 56; 85 SATC 216 (22 April 2022)
Download original files
PDF format
RTF format
Links to summary
PDF format
RTF format
make_database: source=/home/saflii//raw/ZASCA/Data/2022_56.html
sino date 22 April 2022
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
### JUDGMENT
JUDGMENT
Not Reportable
Case
no:
1044/2020
In
the matter between:
COMMISSIONER
FOR THE SOUTH
AFRICAN
REVENUE SERVICE
APPELLANT
and
SASOL
CHEVRON HOLDINGS LIMITED
RESPONDENT
Neutral citation:
Commissioner, South African Revenue
Service v Sasol Chevron Holdings Limited
(Case
no
1044/2020
)
[2022] ZASCA 56
(22 April 2022)
Coram:
PETSE DP and
ZONDI,
MOCUMIE and HUGHES JJA and MEYER AJA
Heard:
09 March 2022
Delivered:
This judgment was handed down
electronically by circulation to the parties' legal representatives
by email, publication on the Supreme
Court of Appeal website and
release to SAFLII. The date and time for hand-down is deemed to be
09H45 on 22 April 2022.
Summary:
Administrative law – Promotion of
Administrative Justice Act 3 of 2000 (PAJA) – application for
review of administrative action
– delay in instituting application
– s 7(1) of PAJA – no agreement between the parties under s 9(1)
for extension of period
prescribed in terms of s 7(1) – nor
application to court under s 9(2) for extension of the prescribed 180
day period.
###
### ORDER
ORDER
On
appeal from:
Gauteng Division
of the High Court,
Pretoria
(A J
Louw
AJ
, sitting as court of first
instance):
1 The
appeal is upheld with costs, including the costs of two counsel.
2
The order of the court below is set aside and in its place is
substituted
the following order:
'The application is dismissed with costs, including the
costs of two counsel where so employed.'
###
### JUDGMENT
JUDGMENT
Petse DP
(Zondi, Mocumie and Hughes JJA and
Meyer AJA
concurring
)
:
Introduction
[1]
This is an appeal by the Commissioner for the South African Revenue
Service (the Commissioner)
against a decision of the Gauteng Division
of the High Court, Pretoria (the high court) in favour of Sasol
Chevron Holdings Limited
(Sasol Chevron), the respondent in this
appeal, delivered on 20 December 2019. In terms of its decision, the
high court (per A J
Louw AJ) reviewed and set aside the
Commissioner's decision of 6 December 2017, namely that Sasol Chevron
was not entitled to a refund
of the Value Added Tax levied on the
supply of the goods sold to Sasol Chevron as envisaged in
s 11(2)
(a)
(ii)
(bb)
of the Value Added Tax Act
[1]
(the VAT Act) read with regulation 6, Part One of the Export
Regulations.
[2]
In addition, the high court remitted the dispute between the
protagonists to the Commissioner for reconsideration. Costs followed
the event.
Factual background
[2]
The background facts are briefly as follows. Sasol Chevron is an
incorporated joint venture company registered
in accordance with the
laws of Bermuda. In 2014, Sasol Chevron purchased certain movable
goods
[3]
from Sasol Catalyst, a division of Sasol Chemical Industries (Pty)
Ltd for exportation from South Africa to Nigeria. In line with
the
applicable statutory and regulatory framework,
[4]
the goods were supplied to Sasol Chevron on what is known as an
'ex-works' and 'flash title' basis.
[5]
Consequently, the goods were delivered by Sasol Catalyst to a
warehouse at the Durban Harbour, from where they were sold to Sasol
Chevron and then immediately on-sold to Escravos Gas-to-Liquids
Project (EGTL) for export to Nigeria. The goods were specially
manufactured
for EGTL and could not be used in any other application.
[3]
Regulation 15(1) of the Export Regulations requires that goods sold
for exportation must be exported within
90 days of the date of sale.
The relevant tax invoices for the sale of the goods concerned were
dated 20 August 2014, 22 September
2014 and 22 October 2014.
Sasol Catalyst, the seller of the goods, elected as the vendor
[6]
to supply the goods to Sasol Chevron and levy tax at the zero rate in
terms of s 11(1)
[7]
of the VAT Act.
[4]
For reasons not germane for present purposes, Sasol Chevron did not
export the movable goods within 90
days of the date of the tax
invoice as required by regulation 15(1). The goods were ultimately
exported on 24 April 2015. Accordingly,
Sasol Catalyst was, by
operation of regulation 8(2)
[8]
of the regulations, required to levy value added tax at the standard
rate on the supply of the goods to Sasol Chevron as prescribed
in
terms of s 7(1)
[9]
of the VAT Act.
[5]
Cognisant of the fact that value added tax would be payable in
respect of the goods, Sasol Catalyst then
addressed a letter to the
South African Revenue Service (SARS) on 30 January 2015 in which it
sought from SARS that the latter should
issue a ruling in accordance
with s 11(1)
(a)
(ii)
[10]
of the VAT Act read with regulation 15(1) extending the prescribed 90
day period within which the goods sold to Sasol Chevron were
required
to be exported to ECTL in respect of the tax invoices issued by the
former during August, September, October, November and
December 2014.
[6] In support of its
application, Sasol Catalyst stated:
'The delay in the exportation of the goods is as a result of
various factors, including the delay in obtaining the required tax
import
clearance certificates from the Nigerian authorities;
industrial action in Nigeria during November and December, delays in
finalising
contracts between the Nigerian entity and the freight
forwarders.'
[7] And elaborating on this, it
asserted in its founding affidavit, in support of the relief sought
in the
high court, that:
'The delay in exporting the goods from South Africa was mainly due
to a delay in obtaining the required import clearance certificates
from the Nigerian authorities which in turn caused delays in
finalizing contracts between EGTL and the freight forwarders as well
as industrial action being experienced in Nigeria during November and
December 2015.'
Sasol Chevron amplified this in its replying affidavit
and stated that:
'The industrial action referred to in the applicant's founding
affidavit paragraph 19, and which was a contributing cause in the
delay
of the exportation of the goods, was experienced during
November and December 2014, and not 2015 as stated therein.'
[8] In the interim, and
presumably in anticipation that its request for an extension would be
acceded to,
Sasol Catalyst issued new and revised tax invoices in
substitution of those previously issued in August, September,
October, November
and December 2014 thereby substituting the initial
zero rated tax invoices with new tax invoices in which value
added tax was
levied at the standard rate of 14% that was operational
at the time. Sasol Chevron, in turn, duly paid the value added tax
levied
by Sasol Catalyst in respect of the latter's replacement tax
invoices.
[9] On 6 July 2015, Sasol
Catalyst applied to SARS for the extension of the period within which
to submit
an application to the Vat Refund Authority (VRA) for a
refund of the value added tax paid in respect of Sasol Catalyst's
revised
tax invoices. In a comprehensive letter of 7 November 2016 to
Sasol Catalyst's attorneys, SARS responded to Sasol Catalyst's
request
and declined the application for an extension of the 90 day
period for the exportation of the goods sold in terms of the tax
invoices
issued in August, September and October 2014. However, SARS
acceded to Sasol Catalyst's request in relation to the tax invoices
issued
in November and December 2014.
[10] Undaunted by this setback, Sasol
Catalyst made further representations to SARS to 'reconsider the
application by
Sasol Chevron to submit the application for a refund
of the South African VAT paid by Sasol Chevron on the goods sold by
Sasol Catalyst'.
However, in a letter dated 6 December 2017, SARS was
not prepared to budge and reiterated its unwavering stance that Sasol
Chevron
was not entitled to a refund of the value added tax levied on
the supply of the movable goods sold to Sasol Chevron. SARS' response
seemingly failed to convince the non-fatigable Sasol Catalyst that
SARS too was unrelenting. Further correspondence was exchanged
between the parties, culminating in a letter dated 26 March 2018 from
SARS to Sasol Chevron in which SARS reaffirmed its previous
stance,
consistent with what it had earlier communicated to Sasol Catalyst's
attorneys in its letter of 7 November 2016.
Before the high court
[11]
Some five months later, on 21 September 2018, and with a stalemate
having arisen, Sasol Chevron instituted a review
application under
PAJA seeking, inter alia, an order to review and set aside SARS'
decision of 6 December 2017.
[11]
[12] It is common cause between the parties
that the review application papers were served on SARS on 25
September 2018.
Thus, SARS asserted that by then the 180 day period
provided for in s 7(1) of PAJA, reckoned either from 7 November
2016 or
6 December 2017, had long expired. Accordingly, in argument
before the high court, SARS contended that absent an application for
an order that the 180 day period be extended in terms of s 9(2) of
PAJA, the review application fell to be dismissed on that ground
alone without consideration of the merits of the review application
itself. I pause here to observe that it is common cause between
the
parties that Sasol Chevron did not bring any application for the
extension of the 180 day period in terms of s 9(2) of PAJA.
[13] In the event, the high court dismissed
the preliminary objection raised by SARS and thereafter proceeded to
determine
the substantive merits of the review. The high court then
upheld the application and, in the result, granted an order in the
terms
foreshadowed in paragraph 1 above. The present appeal, with the
leave of the high court, is directed against that order.
[14] Insofar as the issue of delay is
concerned, the high court, in essence, held that as the Commissioner
provided his
reasons for his decision of 6 December 2017 only on 26
March 2018, this meant that the 180 day period commenced to run from
27 March
2018. And, having regard to the fact that the 'review
application was issued on 21 September 2018 . . . [on] the 179
th
day after the reasons were provided on the 26
th
March
2018', it followed that 'the review application was timeously
instituted within the prescribed 180 day period' as required
in s
7(1) of PAJA. With this procedural obstacle now out of the way, the
high court then – as stated above – proceeded to consider
the
merits of the review application. The high court's conclusion on the
issue of delay raises the question whether the high court
was right
to reach such a conclusion. Therefore, it is necessary to first
determine this antecedent question, for if it is answered
against
Sasol Chevron, that result would be determinative of the outcome of
this appeal, thus rendering it unnecessary to enter into
the
substantive merits of the review application.
Statutory framework
[15] Section 7(1) of PAJA provides as
follows:
'Any proceedings for judicial review in terms of section 6(1) must be
instituted without unreasonable delay and not later than 180
days
after the date–
(a)
subject to subsection (2)
(c)
,
on which any proceedings instituted in terms of internal remedies as
contemplated in subsection 2
(a)
have been concluded; or
(b)
where no such remedies exist, on which the person
concerned was informed of the administrative action, became aware of
the action
and the reasons for it or might reasonably have been
expected to have become aware of the action and the reasons.'
Self-evidently, with a view to ameliorate the position
of a litigant hit by the time limitation provision in s 7(1), s 9(1)
of
PAJA provides that the 180 day period may, either by agreement
between the parties or absent such agreement, by a court on
application,
be extended for a fixed period. And a court may grant an
extension of the 180 day period referred to in s 7(1) if, in terms of
s
9(2) of PAJA, the interests of justice so require.
[16]
What the interests of justice will demand in any given situation will
largely depend on the facts of each case. In
Camps
Bay Ratepayers and Residents Association and Another v Harrison and
Another
,
[12]
this court put it thus:
'[A]nd the question whether the interests of justice require the
grant of such extension depends
on the facts and circumstances of each case: the party seeking it
must furnish a full and reasonable explanation for the delay which
covers the entire duration thereof and relevant factors include the
nature of the relief sought, the extent and cause of the delay,
its
effect on the administration of justice and other litigants, the
importance of the issue to be raised in the intended proceedings
and
the prospects of success.' (Footnote omitted.)
[17]
In
Mulaudzi v Old
Mutual Life Assurance Company (South Africa) Limited
,
[13]
this court said that in applications for condonation (extension of
time in the context of s 9(2) of PAJA), the substantive merits
of the
principal case may be relevant. The court proceeded to say that in
circumstances where the merits are considered to be relevant,
they
are not necessarily decisive. In
Opposition
to Urban Tolling Alliance and others v The South African National
Roads Agency Limited and Others
[14]
this court stated that absent an extension, 'the court has no
authority to entertain the review application.' However, this
statement
was qualified in
South
African National Roads Agency Limited v City of Cape Town,
[15]
in which Navsa JA said that this dictum 'cannot be read to signal a
clinical excision of the merits of the impugned decision, which
must
be a critical factor when a court embarks on a consideration of all
the circumstances of a case in order to determine whether
the
interests of justice dictates that the delay should be condoned.'
[16]
[18] However, it is necessary to emphasise
that in this case, as already indicated above, Sasol Chevron did not
bring
any application for the extension of the 180 day period as
contemplated in s 9(2) of PAJA. Accordingly, the fate of this appeal
hinges
entirely on the question whether or not Sasol Chevron's review
application was instituted within the 180 day period prescribed in
s
7(1) of PAJA. If not, that will be the end of the matter, and the
appeal would fall to be dismissed without further ado.
[19]
In
OUTA
,
[17]
this court held that:
'. . . after the 180 day period the issue of unreasonableness is
pre-determined by the legislature; it is unreasonable per se. It
follows that the court is only empowered to entertain the review
application if the interest of justice dictates an extension in
terms
of s 9. Absent such extension the court has no authority to entertain
the review application at all. Whether or not the decision
is
unlawful no longer matters. The decision has been "validated"
by the delay.'
[20]
The rationale for what has come to be known as the delay rule under
s 7(1) of PAJA, whose roots are embedded
in common law, was
reiterated by Brand JA in
Associated
Institutions Pension Fund and Others v Van Zyl and Others
[18]
as follows:
'Since PAJA only came into operation on 30
November 2000 the limitation of 180 days in s 7(1) does not apply to
these proceedings.
The validity of the defence of unreasonable delay
must therefore be considered with reference to common law principles.
It is a longstanding
rule that courts have the power, as part of
their inherent jurisdiction to regulate their own proceedings, to
refuse a review application
if the aggrieved party had been guilty of
unreasonable delay in initiating the proceedings. The effect is that,
in a sense, delay
would "validate" the invalid
administrative action (see eg
Oudekraal
Estates (Pty) Ltd v City of Cape Town and others
[2004] 3 All SA 1
(SCA) 10b-d, para 27). The
raison
d'etre
of the rule is said to be
twofold. First, the failure to bring a review within a reasonable
time may cause prejudice to the respondent.
Second, there is a public
interest element in the finality of administrative decisions and the
exercise of administrative functions
(see eg
Wolgroeiers
Afslaers (Edms) Bpk v Munisipaliteit van Kaapstad
1978 (1) SA 13
(A) 41).
The scope and content of the rule has been the
subject of investigation in two decisions of this court. They are the
Wolgroeiers
case and
Setsokosane Busdiens (Edms) Bpk
v Voorsitter, Nasionale Vervoerkommissie en 'n Ander
1986 (2) SA 57
(A). As appears from these two cases and the numerous
decisions in which they have been followed, application of the rule
requires
consideration of two questions:
(a) Was there an unreasonable delay?
(b) If so, should the delay in all the circumstances be condoned?
(See
Wolgroeiers
39C-D.)
The reasonableness or unreasonableness of a delay
is entirely dependent on the facts and circumstances of any
particular case (see
eg
Setsokosane
86G). The investigation into the reasonableness of the delay has
nothing to do with the court's discretion. It is an investigation
into the facts of the matter in order to determine whether, in all
the circumstances of that case, the delay was reasonable. Though
this
question does imply a value judgment it is not to be equated with the
judicial discretion involved in the next question, if
it arises,
namely, whether a delay which has been found to be unreasonable,
should be condoned (See
Setsokosane
86E-F).'
[21]
In
Gqwetha v
Transkei Development Corporation Ltd and Others
,
[19]
Nugent JA elaborated on this theme and said the following regarding
the delay rule:
'Underlying that latter aspect of the rationale is the inherent
potential for prejudice, both to the efficient functioning of the
public body, and to those who rely upon its decisions, if the
validity of its decisions remains uncertain. It is for that reason
in
particular that proof of actual prejudice to the respondent is not a
precondition for refusing to entertain review proceedings
by reason
of undue delay, although the extent to which prejudice has been shown
is a relevant consideration that might even be decisive
where the
delay has been relatively slight . . .'
[22]
What an application for an extension of the 180 day period in terms
of s 9 contemplates – just like any other
application for
condonation for that matter – is that the applicant must, in
general, proffer a reasonable and satisfactory explanation
for the
delay. This entails that the explanation proffered must not be bereft
of particularity and candour and that a full explanation
must be
proffered not only for the nature and extent of the delay,
[20]
but also for the entire period covered by the delay. And the
explanation proffered for the delay must also be reasonable. It is as
well to bear in mind that in considering whether the court should
come to the aid of the applicant, the substantive merits of the
review application will also be a critical factor in determining
whether the interests of justice dictate that the delay should be
condoned.
[21]
But in the present matter, there is no application such as is
contemplated in s 9(2) of PAJA. Thus, these considerations do not
arise
in this case.
[23]
Where no application for the extension of the 180 day period in terms
of s 9(2) has been made – as in this instance
– a court has no
authority to enter into the substantive merits of a review
application brought outside the 180 day period prescribed
in s 7(1).
In
Mostert NO v
Registrar of Pension Funds and Others
[22]
it was stated that:
'Section 7(1) of PAJA provides that proceedings for judicial review
must be instituted without unreasonable delay and not later than
180
days after the dates specified in subsections (a) and (b). In
Opposition to Urban Tolling Alliance Brand JA said (para 26):
"At common law application of the undue delay rule required a
two stage enquiry. First, whether there was an unreasonable delay
and, second, if so, whether the delay should in all the circumstances
be condoned . . . Up to a point, I think, s 7(1) of PAJA requires
the
same two stage approach. The difference lies, as I see it, in the
legislature's determination of a delay exceeding 180 days as
per se
unreasonable. Before the effluxion of 180 days, the first enquiry in
applying s 7(1) is still whether the delay (if any) was
unreasonable.
But after the 180 day period the issue of unreasonableness is
pre-determined by the legislature; it is unreasonable
per se. It
follows that the court is only empowered to entertain the review
application if the interest of justice dictates an extension
in terms
of s 9. Absent such extension the court has no authority to entertain
the review application at all." '
[24] As already indicated above in this case
Sasol Chevron adopted the stance that the review application was
instituted
within 180 days after the dates stipulated in paragraphs
(a)
and
(b)
of s 7(1). It, therefore, elected to argue
the case on the footing that an application for an extension of the
180 day period was
wholly unnecessary.
Counsel's submissions
[25] The diametrically opposing contentions
advanced by counsel on behalf of the parties in this court may
broadly be
summarised as follows. On behalf of SARS, it was submitted
in the heads of argument that the Commissioner declined the
application
made by Sasol Chevron in response to the latter's
application made in July 2015 on 7 November 2016. Accordingly, so the
argument
went, SARS' response – communicated to Sasol Chevron in
writing on 7 November 2016 – constituted its written decision
supported
with reasons underpinning such decision. Before us, and to
meet the counter-argument advanced on behalf of Sasol Chevron –
counsel
for the Commissioner accepted for purposes of the appeal that
SARS' decision was taken on 6 December 2017. Indeed, this is the very
decision that Sasol Chevron sought to have reviewed and set aside in
its notice of motion.
[26] Counsel for the Commissioner went on to
highlight that as the application for review was instituted only on
21 September
2018 – some 22 months after the decision was taken and
reasons therefor provided – the fact that even on Sasol Chevron's
own
account, the decision was taken on 6 December 2017 meant that the
high court was not empowered to enter into the substantive merits
of
the review application. Instead, so the argument went, the high court
should have dismissed the application simply on the basis
that it was
instituted outside the 180 day period without an application for the
extension of that period as required in terms of
s 9(2).
[27] Whilst accepting the submissions
advanced on behalf of the Commissioner as to the factual backdrop
against which
this appeal should be considered, counsel for Sasol
Chevron embraced the reasoning that prevailed in the high court. In
essence,
the high court held that although SARS took its decision on
6 December 2017, it provided its reasons in support of that decision
only on 26 March 2018. Therefore, as the review application was
instituted on 21 September 2018 (and served on 25 September 2018),
this meant that it was still within the 180 day period prescribed by
s 7(1). Hence, it concluded that it was not necessary to apply
for an
extension of time under s 9(2).
[28]
However, the counter-argument advanced by counsel for Sasol Chevron
and the reasoning of the high court on this score
must be tested with
reference to the following fundamental considerations. First, as was
submitted on behalf of the Commissioner,
SARS' letter of 26 March
2018 was no more than a recapitulation of the position that SARS had
consistently adopted since 2016. The
letter itself makes explicit
reference to the earlier decision – termed the ruling – made on 6
December 2017, as are virtually
all the subsequent letters from SARS
to Sasol Chevron. SARS' letter of 6 December 2017, in turn, makes
reference to the ruling made
on 7 November 2016 in which the
background facts are comprehensively set out, Sasol Chevron's request
summarised, the relevant statutory
framework set out and, finally,
the decision (ruling) –
supported
with comprehensive reasons – is articulated.
[29]
In contending that the impugned decision was not taken on 26 March
2018, counsel for the Commissioner called into
his aid the decision
of this court in
Aurecon South Africa
(Pty) Ltd v City of Cape Town
,
[23]
in which Maya ADP said the
following:
'The decision challenged by the City and the reasons therefor were
its own and were always within its knowledge. Section 7(1)
unambiguously
refers to the date on which the reasons for
administrative action became known or ought reasonably to have become
known to the party
seeking its judicial review. The plain wording of
these provisions simply does not support the meaning ascribed to them
by the court
a quo, ie that the application must be launched within
180 days after the party seeking review became aware that the
administrative
action in issue was tainted by irregularity. That
interpretation would automatically entitle every aggrieved applicant
to an unqualified
right to institute judicial review only upon
gaining knowledge that a decision (and its underlying reasons), of
which he or she had
been aware all along, was tainted by
irregularity, whenever that might be. This result is untenable as it
disregards the potential
prejudice to the respondent (the appellant
here) and the public interest in the finality of administrative
decisions and the exercise
of administrative functions. Contrary to
the court a quo's finding in this regard, the City far exceeded the
time frames stipulated
in s 7(1) and did not launch the review
proceedings within a reasonable time. In that case, it clearly needed
an extension as envisaged
in s 9(1)
(b)
without which the court
a quo was otherwise precluded from entertaining the review
application.'
[30]
Aurecon
was cited with approval by the Constitutional Court in
City
of Cape Town v Aurecon South Africa (Pty) Ltd
,
[24]
in which the following was stated:
'On a textual level, the City's contention confuses two discrete
concepts:
reasons and irregularities
. Section 7(1) of PAJA
does not provide that an application must be brought within 180 days
after the City became aware that the administrative
action was
tainted by irregularity. On the contrary, it provides that the clock
starts to run with reference to the date on which
the reasons for the
administrative action became known (or ought reasonably to have
become known) to an applicant.'
Thus, s 7(1) explicitly provides that the proverbial
clock begins to tick from the date on which the reasons for the
administrative
action became known (or ought reasonably to have
become known) to the applicant, in this instance, Sasol Chevron.
[31] There is, to my mind, considerable
force in the contentions advanced on behalf of the Commissioner. On
this score,
it is instructive to keep at the forefront of one's mind
that the fact that the parties continued to exchange further
correspondence
beyond 6 December 2017 cannot detract from the truism
that SARS' impugned decision was taken on 6 December 2017. What is
more, is
that this is the very decision that Sasol Chevron sought to
have reviewed and set aside. And yet no attempt was made by Sasol
Chevron
in its founding papers to explain any correlation between the
decision of 6 December 2017 and SARS' letter of 26 March 2018 to
support
its belated contention that in instituting its review
application on 21 September 2018, it was still within the time frame
prescribed
by s 7(1) of PAJA.
[32] During argument, there was some debate
about whether the word 'institute' in s 7(1) of PAJA ought to be
construed
to mean that the court process initiating legal proceedings
– in this instance the review application – in a court must not
only
be issued by the court concerned but must also actually be
served on the respondent. Counsel for the Commissioner embraced this
proposition
and contended that this is the sense in which the word
'institute' should be understood. I did not understand counsel for
Sasol Chevron
to contest this proposition. Rather, he was content to
argue that on the facts of this matter, and having regard to the fact
that
it was common cause that the review application was served on
SARS on 25 September 2018 – that is, on the 179
th
day of
the 180 day period – the requirements of s 7(1) were satisfied. In
the circumstances, argued counsel, no application in
terms of s 9(2)
of PAJA was necessary.
[33]
On the facts, counsel's argument cannot be sustained. Taking as one's
logical point of departure, the requirement
in s 7(1) that 'any
proceedings for judicial review . . . must be instituted without
unreasonable delay and not later than 180 days'
after either of the
dates referred to in paragraphs
(a)
and
(b)
of s 7(1), it must ineluctably follow that the word 'institute'
when considered contextually and purposively,
[25]
as it must be, means to commence the review proceedings by issuing
the process and effecting service thereof on the decision-maker
whose
administrative action is impugned.
[34]
Thus, any argument to the contrary would be untenable. This can be
tested with reference to the following considerations.
If it were
otherwise, one may rhetorically ask, what would be the virtue in
issuing the review application and thereafter remain
supine for
months on end without effecting service of the application on the
respondent? Could that be said to meet the requirements
of s 7(1)
of PAJA, which decree that 'any proceedings for judicial review in
terms of s 6(1) must be instituted without reasonable
delay and not
later than 180 days' of the occurrence of either of the events
referred to in paragraphs
(a)
and
(b)
thereof. And, more fundamentally, would a mere issuing of the review
application that is not followed by immediate service thereof
on the
respondent without unreasonable delay not undermine the legitimate
purpose that the delay rule is designed to serve? To my
mind, the
answer must ineluctably be Yes. To contend otherwise would, as
indicated above, undermine the
raison
d'être
of the
delay rule as aptly articulated by Millar JA in
Wolgroeiers
Afslaers (Edms) Bpk v Munisipaliteit van Kaapstad
.
[26]
And, as already observed above
,
the underlying rationale for the rule lies in the 'inherent potential
for prejudice, both to the efficient functioning of the public
body
and to those who rely upon its decision, if the validity of its
decisions remains uncertain.'
[27]
[35] There can be no doubt that s 7(1) is a
time limitation provision. Thus, its object and purpose would not be
served
if the decision-maker is not made aware, by service of the
process impugning the decision, that his or her or its decision is
being
challenged and, whilst at the same time, the beneficiaries of
the decision arrange their affairs on the acceptance that the
decision
concerned is beyond question because they are completely
oblivious to the pending challenge.
[36]
In
ABM Motors v
Minister of Minerals and Energy and Others
,
[28]
Ploos van Amstel J had occasion to consider whether an application
which has been issued but not served on the respondent can be
taken
to have been made. After making reference to various decisions of our
courts,
[29]
the upshot of which is that not only must the application be issued
by the Registrar but must also be served on the affected parties,
the
learned Judge concluded as follows:
'I
do not consider that this approach [issue and service of the process]
will place an undue burden on applicants for judicial review
in terms
of PAJA.'
[30]
[37]
Before leaving this topic, I consider that it will be useful to make
reference to certain dicta of our courts that
bear repeating. The
first of these is the oft-quoted passage from the judgment of Wallis
JA in
Endumeni
.
[31]
The learned Judge of Appeal had occasion to explain the import of
what he had said some eight years earlier in
Endumeni
in
Commissioner for
the South African Revenue Service v United Manganese of Kalahari
(Pty) Ltd
[32]
and stated:
'It is an objective unitary process where consideration must be given
to the language used in the light of the ordinary rules of
grammar
and syntax; the context in which the provision appears; the apparent
purpose to which it is directed and the material known
to those
responsible for its production. . .'
[38] The learned Judge then went on to say:
'The difference in the genesis of statutes and contracts provides a
different context for their interpretation. Statutes undoubtedly
have
a context that may be highly relevant to their interpretation. In the
first instance there is the injunction in s 39(2) of the
Constitution
that statutes should be interpreted in accordance with the spirit,
purport and objects of the Bill of Rights. Second,
there is the
context provided by the entire enactment. . . Fourth, the legislative
history may provide useful background in resolving
interpretational
uncertainty. Finally, the general factual background to the statute,
such as the nature of its concerns, the social
purpose to which it is
directed and, in the case of statutes dealing with specific areas of
public life or the economy, the nature
of the areas to which the
statute relates, provides the context for the legislation.'
[39]
There is also the judgment of Rumpff JA in
Republikeinse
Publikasies (Edms) Bpk v Afrikaanse Pers Publikasies (Edms) Bpk
[33]
where
it was said that the purpose of a summons or notice of motion is to
implicate or involve a respondent into a lawsuit. Thus,
it goes
without saying that one can only implicate or involve a respondent or
defendant in a lawsuit by bringing the summons or notice
of motion to
his or her notice by effecting service of the process.
[34]
[40]
Finally, I must also refer to
Finishing
Touch 163 (Pty) Ltd v BHP Billiton Energy Coal South Africa Ltd and
Others
[35]
in which this court interpreted the word 'initiate' used in a court
order granting an interim interdict pending certain review
proceedings
to be initiated by no later than a certain date, to mean
not only the filing of the review application papers with the
registrar
and the issue thereof, but crucially also service thereof.
In reaching that conclusion this court inter alia relied on
Mame
Enterprises (Pty) Ltd v Publications Control Board
[36]
wherein Nicholas J held that it was manifest from uniform rule 6 and
from the contents of Form 2(a) that the giving of notice to
the
respondent in a case in which relief is claimed is an essential first
step in an application on notice of motion; and on
Tladi
v Guardian National Insurance Co Ltd
.
[37]
In
Tladi
,
Botha J held that an application that was required to have been made
within a period of 90 days as contemplated in s 14(3) of the
Motor
Vehicle Accidents Act 48 of 1986, could not be considered to have
been made if it had merely been issued but not served.
[41] Although I have derived much assistance
from reading the cases referred to in
ABM Motors
, I do not
propose to analyse and discuss all of them in detail in this
judgment, for to do so would render this judgment unduly prolix.
Suffice it to say that all of them underscore the obvious point in a
case such as the present that an application for review in terms
of s
6(1) of PAJA must be issued and served on the affected parties in
order to satisfy the prescripts of s 7(1) of PAJA.
[42]
It therefore follows that Sasol Chevron's review application was
instituted outside the 180 day period prescribed
in s 7(1). Thus, in
the words of Brand JA in
OUTA
'after the 180 day period the issue of unreasonableness is
predetermined by the legislature; it is unreasonable per se.' The
inevitable
consequence of this is that absent an application in terms
of s 9(2) of PAJA, the high court should have dismissed the review
application
for want of compliance with the prescripts of s 7(1) as
it had no power to enter into the substantive merits of the review.
Therefore,
whether or not the impugned decision is unlawful 'no
longer matters.' Rather, it became 'validated' by the unreasonable
delay.
[38]
Consequently the Commissioner's preliminary point ought to have been
upheld.
[43]
The conclusion reached above in relation to s 7(1) of PAJA renders it
unnecessary to determine the interesting questions
of law, namely
whether it is permissible for a vendor as defined in s 1 of the VAT
Act once such a vendor has made an election to
supply goods at a zero
rate in terms of s 11(1)
(a)
(ii)
read with Part Two – Section A of the export regulations to migrate
to Part One of the self-same export regulations in respect
of the
same supply of goods by issuing fresh tax invoices at the standard
rate of value added tax in terms of s 7 of the VAT Act.
I, therefore,
refrain from expressing any opinion on those issues. Indeed, as the
Constitutional Court cautioned in
Albutt
v Centre for the Study of Violence and Reconciliation, and
Others,
[39]
'[s]ound judicial policy requires us to decide only that which is
demanded by the facts of the case and is necessary for its proper
disposal.' Thus, those questions, interesting as they appear to be,
should be left for another day when the opportunity presents
itself
again.
[44] Before making the order, it is
necessary to express our disquiet at one disturbing feature of this
appeal. It is
this: the judgment of the high court was handed down on
20 December 2019. On 3 February 2020, the Commissioner filed an
application
for leave to appeal the high court's judgment. This was
outside the time limits prescribed in terms of rule 49(1)
(b)
of the Uniform Rules by some three days only. The high court rightly
described this slight delay as 'of inconsequential duration';
hence
it readily condoned the delay.
[45] The application for leave to appeal was
heard on 15 May 2020. And the judgment of the high court granting
leave to
appeal to this court was handed down on 26 October 2020
after undergoing a period of gestation of some five months. It is
necessary
to say something about this. An undesirable development
appears to be taking root in some courts where applications for leave
to
appeal are invariably not dealt with and disposed of
expeditiously. This is regrettable as delays in the disposition of
applications
for leave to appeal have a negative impact on the
administration of justice. I mention this not to censure the learned
Judge a quo
but purely to sound a word of caution, namely that if
delays of this nature go unchecked, they have the potential to bring
the administration
of justice into disrepute.
Order
[46] In the result the following order is
made:
1 The
appeal is upheld with costs, including the costs of two counsel.
2
The order of the court below is set aside and in its place is
substituted
the following order:
'The application is dismissed with costs, including the
costs of two counsel where so employed.'
X M PETSE
DEPUTY PRESIDENT
SUPREME COURT OF APPEAL
APPEARANCES
For the appellant:
A R Sholto-Douglas SC (with him T
S Sidaki)
Instructed by:
Ledwaba
Mazwai Attorneys, Pretoria
Matsepes Inc., Bloemfontein
For the respondent:
P A Swanepoel SC
Instructed by:
Cliffe
Dekker Hofmeyer Inc., Pretoria
Honey Inc., Bloemfontein
[1]
Value Added Tax Act 89 of 1991.
[2]
Regulations promulgated under Government Notice
No R316, Government Gazette 37580 of 2 May 2014.
[3]
The goods comprised catalyst of a specific nature and make-up
manufactured for the Gas to Liquid Plant in Nigeria.
[4]
See the Value Added Tax Act 89 of 1991 and Regulations promulgated
under
Government Notice No R.316, Government
Gazette 37580 of 2 May 2014 pursuant to s 74(1) of the Value Added
Tax Act.
[5]
The term 'Flash title' is defined in the export regulations as a
supply of movable goods by a vendor to a qualifying purchaser
contemplated in paragraph
(f)
of the definition of
'qualifying purchaser' and that qualifying purchaser subsequently
supplies the movable goods to another qualifying
purchaser and
ownership of the goods vests in the first mentioned qualifying
purchaser only for a moment before the goods are sold
to such other
qualifying purchaser.
[6]
The Value Added Tax Act defines a vendor as:
'any
person who is or is required to be registered under this Act:
Provided that where the Commissioner has under section 23 or
50A
determined the date from which a person is a vendor that person
shall be deemed to be a vendor from that date.'
[7]
Section 11(1) of the Value Added Tax Act reads,
‘Where, but for this section, a supply of goods would be charged
with tax at the
rate referred to in section 7(1), such supply of
goods shall, subject to compliance with subsection (3) of this
section, be charged
with tax at the rate of zero per cent where–
(a)
the supplier has supplied the goods (being movable goods) in terms
of a sale or instalment credit agreement and–
(i) ...
(ii) the goods have been exported by the recipient and
the supplier has elected to supply the goods at the zero rate
as
contemplated in Part 2 of the regulation referred to in paragraph
(d)
of the definition of “exported” in section 1:
Provided that–
(aa)
where a supplier has supplied the goods to the
recipient in the Republic otherwise than in terms of this
subparagraph, such
supply shall not be charged with tax at the rate
of zero per cent; and
(bb)
where the goods have been removed from the
Republic by the recipient in accordance with the regulation referred
to in paragraph
(d)
of the definition of “exported” in
section 1, such tax shall be refunded to the recipient in accordance
with the provisions
of section 44 (9); or ...’
[8]
Regulation 8(2) reads:
'The
vendor may only elect to levy tax at the zero rate where–
(a)
the vendor ensures that the movable goods are delivered
(irrespective of the contractual conditions of delivery) to any of
the
harbours or airports listed in the definition of "designated
commercial port" from where the movable goods are to be
exported by the qualifying purchaser. The export of movable goods as
well as the declaration of such goods at ports other than those
ports listed in the definition of "designated commercial port",
may be allowed in exceptional circumstances on application
to and
after approval by the Commissioner;
(b)
the movable goods are exported by means of a pipeline or electrical
transmission line;
(c)
the vendor supplies the goods to a qualifying purchaser on a flash
title basis;
(d)
the vendor supplies the movable goods to a qualifying purchaser and–
(i) the time of supply is regulated by sections 9(1) or 9(3)
(b)
(i)
or (ii) of the Act;
(ii) the movable goods are subject to a process of repair,
improvement, manufacture, assembly or alteration by a vendor other
than the vendor who supplied the goods in the Republic;
(iii) the vendor ensures that the movable goods are delivered to the
premises of the vendor responsible for further processing,
repair,
improvement, manufacture, assembly or alteration for such further
processing, repair, improvement, manufacture, assembly
or
alteration; and
(iv) the vendor responsible for the further processing, repair,
improvement, manufacture, assembly or alteration ensures that the
movable goods are subsequently delivered to any of the harbours or
airports listed in the definition of "designated commercial
port"; or
(e)
the vendor supplies movable goods to a qualifying purchaser or
registered
vendor
and the movable goods are–
(i) situated at the designated harbour or airport;
(ii) delivered to either the port authority, master of the ship, a
container operator, the pilot of an aircraft or are brought
within
the control area of the airport authority; and
(iii) destined to be exported from the Republic.'
[9]
Section 7(1) provides:
'Subject
to the exemptions, exceptions, deductions and adjustments provided
for in this Act, there shall be levied and paid for
the benefit of
the National Revenue Fund a tax, to be known as the value-added tax–
(a)
on the supply by any vendor of goods or services supplied by him on
or after the commencement date in the course or
furtherance of any
enterprise carried on by him;
(b)
on the importation of any goods into the Republic by any person on
or after the commencement date; and
(c)
on the supply of any imported services by any person on or after the
commencement date, calculated at the rate of 15
per cent on the
value of the supply concerned or the importation, as the case may
be.'
[10]
Section 11(1)
(a)
(ii) reads:
'the
goods have been exported by the recipient and the supplier has
elected to supply the goods at the zero rate as contemplated
in Part
2 of the regulation referred to in paragraph
(d)
of the
definition of "exported" in section 1.'
[11]
The relief sought by Sasol Chevron in terms of its notice of motion
was for an order in the following terms:
'
1.
That the decision by the Respondent dated 06 December 2017 to the
effect that the Applicant
". . .
is not entitled to a refund of the VAT levied on the supply of the
goods, as envisaged in section 11(1)(a)(ii)(bb) read
with Regulation
6 of Part I of the Export Regulation"
be reviewed and set aside;
2. That a declaratory order be issued in terms whereof it is
declared that in respect of the movable goods (catalysts) purchased
by the Applicant from Sasol Catalyst, a division of Sasol South
Africa (Pty) Ltd (previously Sasol Chemical Industries (Pty) Ltd)
in
terms of the latter's tax invoices dated 20 August 2014 and 22
September 2014 (referred to in and attached to the Applicant's
founding affidavit), in respect of which goods the Applicant was
responsible for the exporting thereof from the Republic of South
Africa:
2.1 The Applicant qualifies for submission to the Respondent of a
request for extension of the period within which the Applicant
may
submit an application for a refund of the value-added tax paid by
the Applicant as provided for on the aforementioned tax invoices,
in
accordance with the provisions of Regulation 6(6)
(b)
of the
Regulations, issued in terms of section 74(1) read with paragraph
(d)
of the definition of "exported" in section 1(1)
of the Value-Added Tax Act 89 of 1991 (as amended), and that all the
other requirements prescribed in Part 1 of the said regulations were
complied with;
3.
Alternatively
to the relief sought in prayer 2 above,
that:
3.1 The Respondent be ordered to reconsider the Applicant's written
request that an extension be granted to it to submit an application
for a refund to the VAT Refund Administrator in accordance with the
provisions of Regulation 6(6)
(b)
(of the Regulations referred
to in prayer 2 above) (a copy of which earlier written request is
referred to in and attached to the
Applicant's founding affidavit)
on the basis that the Respondent has to consider whether "all
the other requirements prescribed
in this Part" were complied
with, as contemplated in Regulation 6(6)
(b)
in Part 1 of the
Regulations referred to in prayer 2 above
alternatively
that
the Respondent be ordered to reconsider the Applicant's written
request that an extension be granted to it to submit an application
for a refund to the VAT Refund Administrator in accordance with the
provisions of regulation 6(6)
(b)
(of the Regulations referred
to in prayer 2 above);
4. That the Respondent be ordered to pay the costs of this
application only in the event of Respondent opposing any of the
relief
sought herein.'
The remaining two paragraphs sought costs and further or alternative
relief.
[12]
Camps Bay Ratepayers’ and Residents’
Association v Harrison
[2010] ZASCA 3
;
[2010] 2 All SA 519
(SCA) para 54.
[13]
Mulaudzi v Old Mutual Life Assurance Company
(South Africa) Limited
and
Others, National Director of Public Prosecutions and Another v
Mulaudzi
[2017] ZASCA 88
;
[2017] 3 All
SA 520
(SCA);
2017 (6) SA 90
(SCA) para 34.
[14]
Opposition to Urban Tolling Alliance and
Others v The South African National Roads Agency Ltd and Others
[2013] ZASCA 148
;
2013 (4) All SA 639
(SCA) (
OUTA
)
para 26.
[15]
South African National Roads Agency Limited v
City of Cape Town
[2016] ZASCA 122
;
[2016] 4 All SA 332
(SCA);
2017 (1) SA 468
(SCA) para 81.
[16]
See also:
Asla
Construction (Pty) Limited v Buffalo City Metropolitan Municipality
and Another
[2017]
ZASCA 23
;
[2017] 2 All SA 677
(SCA);
2017 (6) SA 360
(SCA) para 12.
[17]
OUTA
para 26.
[18]
Associated Institutions Pension Fund and
Others v Van Zyl and Others
[2004]
ZASCA 78
;
[2004] 4 All SA 133
(SCA) paras 46 - 48.
[19]
Gqwetha v Transkei Development Corporation Ltd
and Others
[2006] 3 All SA 245
;
2006
(2) SA 603
(SCA) para 23 (
Gqwetha
).
[20]
See, for example
Aurecon South Africa (Pty) Ltd v City of Cape
Town
[2015] ZASCA 209
;
[2016] 1 All SA 313
(SCA);
2016 (2) SA
199
(SCA) para 17. See also:
Van Wyk v Unitas Hospital and
Another
[2007] ZACC 24
;
2008 (2) SA 472
(CC);
2008 (4) BCLR 442
(CC) para 20 and
eThekwini Municipality v Ingonyama Trust
[2013] ZACC 7
;
2013 (5) BCLR 497
(CC);
2014 (3) SA 240
(CC) para 28.
[21]
Asla Construction (Pty) Ltd v Buffalo City
Metropolitan Municipality
[2017] ZASCA
23; 2017 (6) SA 360 (SCA).
[22]
Mostert NO v Registrar of Pension Funds and
Others
[2017] ZASCA 108
;
2018 (2) SA
53
(SCA) para 34.
[23]
Aurecon South Africa (Pty) Ltd v City of Cape Town
[2015]
ZASCA 209
;
[2016] 1 All SA 313
(SCA);
2016 (2) SA 199
(SCA) para 16
(
Aurecon
).
[24]
City of Cape Town v Aurecon South Africa (Pty)
Ltd
[2017] ZACC 5
;
2017 (6) BCLR 730
(CC);
2017 (4) SA 223
(CC) para 41.
[25]
Cool Ideas 1186 CC v Hubbard and Another
[2014] ZACC 16
;
2014 (4) SA 474
(CC);
2014 (8) BCLR 869
(CC) para
28. See also
Dengetenge Holdings (Pty)
Ltd v Southern Sphere Mining and Development Company Ltd and Others
[2013] ZACC 48
;
2014 (3) BCLR 265
(CC)
at paras 84-6 and Department of Land Affairs and Others v
Goedgelegen Tropical Fruits (Pty) Ltd
[2007] ZACC 12
;
2007 (6) SA
199
(CC);
2007 (10) BCLR 1027
(CC) at para 5 for purposive
interpretation. In addition, see
North
East Finance (Pty) Ltd v Standard Bank of South Africa Ltd
[2013] ZASCA 76
;
2013 (5) SA 1
(SCA) at para 24
;
KPMG Chartered Accountants (SA) v Securefin Ltd and Another
[2009] ZASCA 7
;
2009 (4) SA 399
(SCA) at para 39 and
Bhana
v Dőnges NO and Another
1950 (4) SA
653
(A) at 664E-H for proper contextualisation;
Natal
Joint Municipal Pension Fund v Endumeni Municipality
[2012]
ZASCA 13
;
2012 (4) SA 593
(SCA) para 18 (
Endumeni
).
[26]
Wolgroeiers Afslaers (Edms) Bpk v
Munisipaliteit van Kaapstad
[1978] 1
All SA 369
(A);
1978 (1) SA 13
(A) at 375.
[27]
Gqwetha
para
23.
[28]
ABM Motors v Minister of Minerals and Energy
and Others
2018 (5) SA 540
(KZP) paras
13-18 (
ABM Motors
).
[29]
Tladi v Guardian National Insurance Co Ltd
[1992] 1 All SA
168
(T);
1992 (1) SA 76
(T);
Taboo Trading 232 (Pty) Ltd v Pro
Wreck Scrap Metal CC and Others; Joubert v Pro Wreck Scrap Metal CC
2013 (6) SA 141
(KZP);
Finishing Touch 163 (Pty) Ltd v BHP
Billiton Energy Coal South Africa Ltd and Others
[2012] ZASCA
49; 2013 (2) SA 204 (SCA).
[30]
ABM Motors
para 19.
[31]
Footnote 25 above para 18.
[32]
Commissioner for the South African Revenue
Service v United Manganese of Kalahari (Pty) Ltd
[2020]
ZASCA 16
(25 March 2020) para 8.
[33]
Republikeinse Publikasies (Edms) Bpk v
Afrikaanse Pers Publikasies (Edms) Bpk
1972 (1) SA 773
(A) at 780E-F.
[34]
See
Marine Trade
Insturance Co Ltd v Reddlinger
1966
(2) SA 407(A)
at 413 in which the following was stated:
'Although an action is commenced when the summons is issued the
defendant is not involved in litigation until service has been
effected, because it is only at that stage that a formal claim is
made upon him.'
[35]
Finishing Touch 163 (Pty) Ltd v BHP Billiton
Energy Coal South Africa Ltd and Others
[2012] ZASCA 49
;
2013 (2) SA 204
(SCA) paras 14 - 20.
[36]
Mame Enterprises (Pty) Ltd v Publications
Control Board
1974 (4) SA 217
(W) at
220B.
[37]
Tladi v Guardian National Insurance Co Ltd
1992 (1) SA 76
(T) at 80B (
Tladi
).
[38]
See
OUTA
footnote 14 above paragraph 26.
[39]
Albutt v Centre for the Study of Violence and
Reconciliation and Others
[2010] ZACC
4
;
2010 (3) SA 293
(CC);
2010 (2) SACR 101
(CC);
(2010 (5) BCLR 391)
para 82.
sino noindex
make_database footer start
Similar Cases
The Commissioner for the South African Revenue Service v Airports Company for South Africa (785/2021) [2022] ZASCA 132; 2023 (2) SA 506 (SCA); 85 SATC 1 (7 October 2022)
[2022] ZASCA 132Supreme Court of Appeal of South Africa99% similar
Commissioner for the South African Revenue Service v Capitec Bank Limited (94/2021) [2022] ZASCA 97; [2022] 3 All SA 641 (SCA); 2022 (6) SA 76 (SCA); 85 SATC 311 (21 June 2022)
[2022] ZASCA 97Supreme Court of Appeal of South Africa98% similar
The Commissioner for the South African Revenue Service and Others v Dragon Freight (Pty) Ltd and Others (751/21) [2022] ZASCA 84; [2022] 3 All SA 311 (SCA); 85 SATC 289 (7 June 2022)
[2022] ZASCA 84Supreme Court of Appeal of South Africa98% similar
Commissioner for the South African Revenue Service and Another v Richards Bay Coal Terminal (Pty) Ltd (1299/2021) [2023] ZASCA 39; 86 SATC 145 (31 March 2023)
[2023] ZASCA 39Supreme Court of Appeal of South Africa98% similar
Commissioner for the South African Revenue Service v Candice-Jean van der Merwe (211/2021) [2022] ZASCA 106; 85 SATC 10 (30 June 2022)
[2022] ZASCA 106Supreme Court of Appeal of South Africa98% similar