Case Law[2026] ZAGPJHC 9South Africa
Bombela Operatin CO (Pty) Ltd v Nedbank Limited and Others (249754/2025) [2026] ZAGPJHC 9 (2 January 2026)
High Court of South Africa (Gauteng Division, Johannesburg)
2 January 2026
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2026
>>
[2026] ZAGPJHC 9
|
Noteup
|
LawCite
sino index
## Bombela Operatin CO (Pty) Ltd v Nedbank Limited and Others (249754/2025) [2026] ZAGPJHC 9 (2 January 2026)
Bombela Operatin CO (Pty) Ltd v Nedbank Limited and Others (249754/2025) [2026] ZAGPJHC 9 (2 January 2026)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2026_9.html
sino date 2 January 2026
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
Case
No 249754/2025
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
2
JANUARY 2026
In
the matter between:
BOMBELA
OPERATIN CO PTY
LTD
Applicant
And
NEDBANK
LIMITED
1
ST
Respondent
BOMBELA
CONCESSION COMPANY (LTD) LTD
2
nd
Respondent
THE
MEC FOR THE GAUTENG PROVINCIAL
3
rd
Respondent
GOVERNMENT,
THE REBPUBLICNOF SOUTH AFRICA
Acting
through the DEPARTMENT OF PUBLIC
TRANSPORT,
ROADS AND WORKS
JUDGMENT
MAHOMED
J
THE
BACKGROUND
[1]
The first and third respondents in this matter abide by the court’s
decision.
[2]
The parties before me are responsible for the management and
operation of the Gautrain, a rapid rail service, which services
Johannesburg and surrounds including the international airport.
They concluded a contract in terms of which the 2
nd
respondent, known as the concessionaire, may issue a notice of
operator default on the applicant/ operator in the event of a clearly
identified default and to allow the operator 30 days to address the
default. The applicant is the operator; it is the sole
operator
for this critical service. A precondition to this relationship
is that the applicant is to secure a performance
guarantee.
[3]
The first respondent, (Nedbank) issued such guarantee in favour of
the second respondent, the concessionaire in the amount
of
R205 934 250.39, to secure certain of the applicant’s
performance related obligations in terms of the operating
contract.
Nedbank would be obliged to pay over those monies to the
concessionaire if the concessionaire is able to demonstrate
that it
qualifies for its entitlement. There are two contracts that are
in focus in the matter, the operator performance
contract and the
bond guarantee contract.
[4]
A default notice was served on 19 November 2025 after the second
respondent placed the applicant on terms to rectify the
default, the
applicant failed to do so in the time permitted, therefore the second
respondent called up payment of the guarantee.
The second
respondent has been awaiting a handing over report, as the operator
contract will end in March 2026 and the contract
will again be put
out to tender.
[5]
Stanlianou SC appeared for the applicant and submitted the applicant
seeks to interdict Nedbank from paying out the monies
on three
grounds, viz it claims the bond is not a standard bond but a
conditional bond, furthermore, the preconditions to payment
had not
been met and therefore Nedbank is not obliged to pay the monies over
and finally, that the second respondent acts
fraudulently in
that on the facts, it could not have believed that all of the
conditions for payment had been met, notwithstanding
it called up the
bond. Counsel contended that on a reading of the clauses in the
operating bond it is clear the bond is not
a standard bond such as a
letter of credit, he contended it is a conditional bond which
requires Nedbank to make reasonable inquiries
to determine if the
second respondent/ concessionaire is entitled to payment.
[6]
He relied on s 4.2.1 and 4.2.2 of the bond, he submitted Nedbank
failed to do so and must be interdicted from paying out
the monies to
the second respondent. Counsel submitted that the default has
been addressed, the report which the second respondent
/concessionaire required is due only on 6 January 2026, having regard
to the date of the notice, the report has been delivered
to the 2
nd
respondent. The second respondent has downloaded the
information.
[7]
Cassim SC for the second respondent/concessionaire, submitted that
the bond is unconditional, and referred the court to
clause 4 of the
bond document, Clause 4 provides:
“
4.
PAYMENT
4.1
The guarantor irrevocably and unconditionally agrees,
subject
to the terms of
this performance bond; ….
4.1.1
.
4.1.2
…
4.1.3
…
to
forthwith make payment of the amount specified in any demand to the
account specified in clause 4.6 within 5 (five) business
days of the
date of receipt of any demand.
4.2
Notwithstanding anything to the contrary contained in this
performance bond, the concessionaire and
the Operator agree
that
the Guarantor, in evaluating
or making any payment pursuant to
any demand made under this performance bond, shall.
4.2.1 not
be entitled or obliged to make any enquiry in relation to, inter
alia:-
…
4.2.2
be
obliged to make reasonable enquiry
only in relation to whether or
not the
demand is made in terms of the performance bond
.”
[8]
Counsel contended that his client has a clear right, it is entitled
to payment on demand, and Nedbank is obliged to pay
over the
guaranteed amount of R205 934 250.30. It was
submitted that clause 4 of the bond is clear in its language
and the
wording expressly “disables” Nedbank from making any
inquires other than those set out in clause 2.2 of the
bond.
There is no duty on Nedbank to inquire further once it has noted a
dispute notice, a certification from AFSA of non-referral,
and that
the time permitted to resolve the dispute has expired, the dispute
remains unresolved, therefore the second respondent
is entitled to
demand payment.
[9]
Mr Cassim referred the court to the judgment in the Group Five case,
where Van der Linde J, stated that “the underlying
dispute is
required to be resolved in the manner provided for in the contract
between the parties. The court furthermore
stated that the
determination of the dispute in the underlying contract may
lead to a result that is wholly different from
that of the
unconditional bond,” however the bond is open to be called up,
it is independent of the underlying contract.
Mr Cassim argued
that the applicant conflates the operations contract with the
performance guarantee.
[10]
It was submitted that the applicant on its version was unable to
provide the information sought, he contended that on
the facts in
this matter the 5 days allowed to remedy the default was reasonable,
his client has requested the information since
September 2025, the
applicant has known of the default and done nothing to remedy the
default. The applicant’s allegations
of fraud were
rejected, and it was contended that only the clearest of cases must
exist for the applicant to succeed with this
allegation. The second
respondent relied on the decision in the Eskom matter, where the
court stated that the call demand is independent
of the underlying
contract. Mr Cassim proferred that his client would not have
been wise to accept a guarantee for a relationship
of this nature
with the applicant, linked to the operator’s performance
contract.
[11]
Counsel for the applicant argues that this is a conditional bond and
it incorporates the underlying contract. He
referred the court
to clause 4.2.2 of the performance guarantee and submitted that the
provision in the clause requires Nedbank
to make inquiries as to
whether the preconditions to payment had been met. In comparison to
the language in clause 2.2 of the same
document, which requires
Nedbank to conduct a tick box exercise. In terms of clause
4.2.2 Nedbank was to “evaluate
and make reasonable enquiry”
before payment is made.
[12]
Clause 4.2.2 provides:
“
be obliged to
make reasonable enquiry only in relation to whether or not the demand
is made in terms of the performance bond.”
The
judgments of our courts have confirmed the approach is to consider
the nature of the contract. It was contended that this duty
to
enquire establishes that the bond is a conditional one.
[13]
Stanlianou SC argued that one must also have regard to what Nedbank
must do as provided for in clause 2.2.2 of the performance
bond
guarantee, inter alia, that the operator has been provided with the
notice of default, for a remedy of the default, that it
has been
remedied within the prescribed remedy period in the operating
contract. Stanlianou argued if not much more
was expected
of Nedbank, clause 4.2 would be meaningless. He submitted
that on a proper interpretation of the terms
Nedbank is required to
satisfy itself that the concessionaire has met the basic
preconditions and is entitled to payment on the
guarantee.
Counsel contended that the period for remedy is 30 days as provided
for in the operator contract and it was not
disputed it expires only
on 6 January 2025. Counsel proffered that the applicant has
delivered the report and therefore purged
the default, the
concessionaire has downloaded the information.
[14]
Mr Cassim reiterate that the bond guarantee makes no reference to the
30 days to resolve the dispute or the 20 days to
file a remediation
plan. He submitted that the 5 days permitted to resolve the
dispute was reasonable if one had regard for
the request for the
information having been sought as far back as October 2025.
[15]
He argued that the applicant on its own version in correspondence
dated 17 December 2025 stated that the dispute remains
unresolved.
Mr Cassim rejected the applicants claim that the second respondent
knew it had not met the certifications to
call the bond yet called on
Nedbank for payment. He submitted the allegations of
fraud lack a basis and stand to be
rejected.
URGENCY
[16]
Cassim SC argued that the urgency is self-created that the applicant
knew on 19 November 2025 of the default, it
could have brought
this application much earlier. He further argued that the applicant’s
case is that it had 30 days as per
contract, however the respondent
affords him 5 days (arbitrarily), the applicant could on that very
basis have approached this
court much earlier, he contended the
matter is not urgent. Counsel furthermore argued that the applicants
have an alternate remedy
and can obtain substantial redress at a
hearing in due course, approaching the urgent court is an abuse of
process. The operator
performance contract provides for related
disputes to be taken to arbitration.
[17]
Stanlianu contended his client provided the documents ahead of due
date and it would have been premature for it to have
launched a
urgent application any earlier, moreover nothing was said on an
intention to call on the bond. The
urgency arose as
Nedbank was obliged to pay within 5 days and has no grounds to do
so. He submitted the matter is urgent
and the applicant has
made out a case for interim relief. This interdict is pending
the outcome at arbitration.
[18]
Addressing
the merits, Cassim SC referred the court to the judgment by Van der
Linde J
[1]
, who stated that a
demand guarantee is “serving as unclouded immediate cash
despite an underlying contract.” He argued
the bond is separate
from the operating contract. Nothing in the bond document
obliges Nedbank to make any inquiries, as
claimed by the applicant,
clause 2 of the bond provides for an unconditional payment by Nedbank
and this was signed by both Nedbank
and the applicant in favour of
the second respondent. Nedbank is only obliged to satisfy itself that
clause 2 has been met.
He argued that the second respondent has
a clear right to the money and the applicant failed to remedy the
default in the time
permitted. Counsel submitted that our
courts have consistently held that the second respondent has only to
demonstrate it
demanded payment. It was submitted that the
applicant’s failure to refer its dispute to AFSA within the
time permitted was
unfortunate when it has known of its dispute since
September 2025.
Judgment
[19]
It was
submitted that the applicant conveniently conflates the provisions of
the bond with that of the operator performance contract.
In
Lombard Insurance Co Ltd, v Landmark Holdings (Pty) Ltd and
Others
[2]
, the court in a
construction dispute stated: “
construction
guarantee is self-contained and distinct. It is not to be
interpreted in conjunction with the construction contract
.”
[20]
I agree with Mr Cassim, and the guarantee is the concessionaire’s
security, the language employed in clause 4.1
is clear on an
unconditional obligation to pay. I am of the view the bond
guarantee is independent of the underlying contract,
that the second
respondent has only to demonstrate that it has made a demand to be
entitled to immediate payment. The applicant
was dilatory and
“missed the boat” when it failed to refer the dispute to
AFSA, upon receipt of the default notice.
The opportunity of a
referral is another “safety feature” inserted to assist
the operator in the face of an unconditional
guarantee, where
immediate payment is guaranteed. I agree with Cassim SC his
client could not have intended to accept a guarantee
which is linked
to a complex operator performance contract. The five days
permitted for remedy, viewed contextually was reasonable,
the
applicant has known that the information was sought over months, it
knew the purpose and significance of the requested information
and
knew that the contracts are to expire within a few months.
[21]
The
applicant’s argument/ reasoning and linking of the two
contracts, appears to denude a “guarantee” of its very
essence and value in commercial contracts. In Loomcraft Fabrics
CC v Nedbank Limited and Another
[3]
,
was stated “
an
interdict restraining a bank from paying in terms of a credit will
accordingly not be granted at the instance of a buyer save
in the
most exceptional circumstances
.”
It is noteworthy that the applicant is a “sole operator”
and the precondition of a guarantee to secure
the concessionaire’s
interest is logical, for as long as the guarantee is given its full
force and effect in commercial transactions.
[22]
Therefore, I am of the view the application must fail.
COSTS
[23]
Costs must follow the cause, and I am satisfied the costs on scale C,
including costs of two counsel is appropriate.
[24]
I make the following order:
1. Part A and B of
the application is dismissed with costs on scale C including the
costs of two counsel.
2. The first
respondent is to pay the second respondent the sum of R205 934 250.39
by 9 January 2026.
Mahomed J
JUDGE OF THE HIGH
COURT
JOHANNESBURG
Date
of Hearing
24 December 2025
Date
of Judgment
2 January 2026
Appearances:
For
Applicant:Stanlianou SC Instructed by Pincent Masons SA Inc
Email:
Jason.smit@pinsentmasons.com
Angela.lawrence@pincentmasons.com
Thethe.mokele@pincentmasons.com
For
Second Respondent: Cassim SC, with him
Advocate
M Desai Instructed by LNP Beyond Legal
Email:
nikita.lalla@lnpbeyondlegal.com
Ricardo.pillay@lnpbeyondlegal.com
Danielle.giannico@lnpbeyondlegal.com
Msizi.zungu@lnpbeyondlegal.com
[1]
Group
5 2008/41068
[2]
2010
(2) SA 86
SCA
[3]
1998
(1) SA 812
(a) headnote
sino noindex
make_database footer start
Similar Cases
Bombela Operating Company (Pty) Ltd v Sadiphiri Transport Services CC (A3104/2021) [2023] ZAGPJHC 463 (12 May 2023)
[2023] ZAGPJHC 463High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Ngubane v S (A41/2020) [2024] ZAGPJHC 1302 (23 December 2024)
[2024] ZAGPJHC 1302High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Isibonelo Property Services (Pty) Ltd v Uchemek World Cargo Link Freight CC t/a The Fish and Chips Company and Another (55408/2021) [2024] ZAGPJHC 660 (18 July 2024)
[2024] ZAGPJHC 660High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Securitization Program (RF) Limited and Others v Maxidor SA (Pty) Ltd and Others (2022/8473) [2024] ZAGPJHC 669 (25 July 2024)
[2024] ZAGPJHC 669High Court of South Africa (Gauteng Division, Johannesburg)98% similar
South African Roadies Association v National Arts Councils of South Africa and Others (2023/076030) [2024] ZAGPJHC 936 (20 September 2024)
[2024] ZAGPJHC 936High Court of South Africa (Gauteng Division, Johannesburg)98% similar