Case Law[2025] ZAGPJHC 83South Africa
Idwala Industrial Holdings Limited v Amserve Equipment (Pty) Limited (8475/2017) [2025] ZAGPJHC 83 (31 January 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
31 January 2025
Headnotes
Summary: Contractual claims and counterclaims arising from the conclusion, execution and termination of an Initial Manufacturing Agreement between Plaintiff and Defendant for the pelletization by the Defendant of the Plaintiff’s raw materials of limestone and gypsum for sale and use in agriculture - Contractual interpretation of the written agreement - Whether a party is entitled to contractual restitution of advance payments without having received product from the other party in respect of which advance payments were made in circumstances where the contract was terminated by effluxion of time on a date agreed by the parties.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 83
|
Noteup
|
LawCite
sino index
## Idwala Industrial Holdings Limited v Amserve Equipment (Pty) Limited (8475/2017) [2025] ZAGPJHC 83 (31 January 2025)
Idwala Industrial Holdings Limited v Amserve Equipment (Pty) Limited (8475/2017) [2025] ZAGPJHC 83 (31 January 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_83.html
sino date 31 January 2025
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA,
GAUTENG DIVISION,
JOHANNESBURG
CASE NO:
8475/2017
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED.
DATE: 31.01.2025
SIGNATURE
In the matter between:
IDWALA
INDUSTRIAL HOLDINGS LIMITED
Plaintiff
and
AMSERVE
EQUIPMENT (PTY) LIMITED
Defendant
Summary: Contractual
claims and counterclaims arising from the conclusion, execution and
termination of an Initial Manufacturing
Agreement between Plaintiff
and Defendant for the pelletization by the Defendant of the
Plaintiff’s raw materials of limestone
and gypsum for sale and
use in agriculture - Contractual interpretation of the written
agreement - Whether a party is entitled
to contractual restitution of
advance payments without having received product from the other party
in respect of which advance
payments were made in circumstances where
the contract was terminated by effluxion of time on a date agreed by
the parties.
Held: On a proper
interpretation of clause 4.1.1, the parties intended that the
Defendant had undertaken to have a production capacity
of 5000MT per
month by 1 February 2016. Having failed to comply with this
undertaking, the Plaintiff was not obliged to comply
with its
undertaking in clause 4.1.2 of the agreement and did not order 60
000MT of pelletized product on a take or pay basis at
a rate of
5000MT per month and clause 4.1.3 of the agreement did not apply. In
the circumstances, the Plaintiff had not breached
any take or pay
undertaking and the Defendant’s counterclaims are dismissed.
Held: The Plaintiff
was entitled to claim contractual restitution of advance payments it
had made to the Defendant for which it
had not received the
concomitant pelletized product by the date of the termination of
agreement by effluxion of time on 31 January
2017, but only in
respect of advance payments made post the date of the conclusion of
the agreement on 1 December 2015.
The Plaintiff’s
claim alternative claim 1 and claim 3 were granted with mora interest
from date of demand.
The Plaintiff’s
claim 2 was absolved from the instance.
The Defendant was
ordered to pay the Plaintiff’s costs of action and the costs of
defending the Defendant’s counterclaims
on scale C of Rule 67A
read with Rule 69 of the High Court Rules.
JUDGMENT
KAIRINOS
AJ:
1.
This matter arises from a commercial
dispute between the Plaintiff and Defendant pursuant to the
conclusion, partial execution and
eventual termination of a written
agreement concluded between them, called the “Initial
Manufacturing Agreement” (the
“IMA”), which was
concluded on 1 December 2015.
2.
The IMA provided for the manufacture
by the Defendant for the Plaintiff of Pelletized Product (“the
product”) from raw
material (limestone and gypsum) (“the
raw material”) supplied by the Plaintiff at an agreed fee. The
product to be
manufactured under the IMA was a solid pellet-like
product known as ‘prills’ which is used in the
agricultural sector
to provide a controlled slow release of nutrition
to plants. The prills are sown by farmers onto their lands and when
it becomes
wet – either from rainwater or irrigation - it
dissolves and releases nutrients into the ground. The benefit and
advantage
of this over sowing powder limestone products onto the
lands, is that due the solid form and weight of the prill, it not
blown
away by winds before water is introduced.
3.
The IMA was either cancelled by the
Defendant in January 2017 or it expired by the effluxion of time
(despite the Plaintiff purporting
to cancel the agreement in February
2017 based on an alleged repudiation thereof by the Defendant in
purporting to cancel it in
January 2017).
4.
Both parties seek to hold the other
liable for breaches of the IMA.
5.
The Plaintiff instituted three
claims:
5.1
Claim 1 – payment of the sum
of R1 604 150, alternatively R1 334 254, being repayment of
advance payments made by the
Plaintiff to the Defendant for the
pelletizing of the raw materials, in respect of which product was not
delivered by the Defendant.
5.2.
Claim 2 - payment of the sum of R945
181, being the value of raw material supplied by the Plaintiff, which
was used by the Defendant,
but which resulted in 1 279 MT of
oversized pellets which were incapable of being reworked or resold
and rendered waste.
5.3.
Claim 3 - payment of the sum of R83
488, being the amount outstanding in respect of bags supplied by the
Plaintiff to the Defendant
for which the Defendant undertook to pay,
but failed to do so.
6.
The Defendant defended the
Plaintiff’s action and in turn instituted a counterclaim for
payment of the sum of R17 885
400 based upon the following
alternative causes of action:
6.1.
specific performance of the
Defendant's "take or pay" rights under the IMA;
6.2.
alternatively, contractual damages
suffered by the Defendant as a result of the Plaintiff's breach of
the IMA.
7.
The following issues are common
cause between the parties on the pleadings or became common cause
during the course of the trial:
7.1.
Prior to the conclusion of the IMA
and 23 July 2015, the parties concluded an agreement (“the
prior agreement”) for
the pelletization of 24 000 MT of
limestone raw material by the Defendant for the Plaintiff, which
agreement was recorded in writing
and which resulted in the placement
of an order by the Plaintiff on the Defendant for 24 000 MT of
pelletized limestone product
(gypsum was not part of the prior
agreement).
7.2.
On 1 December 2015, the parties
entered into the IMA on the written terms thereof.
7.3.
On 1 February 2016, the Defendant
did not have production capacity of at least 5000 MT per month.
7.4.
The Defendant’s new plant was
only commissioned during May 2016 and began production from 1 June
2016.
7.5.
The Plaintiff made advance payments
to the Defendant in the sum of R1 604 150 for product which was
not delivered to it by
the Defendant made up as follows:
7.5.1.
571 tons of limestone granules;
7.5.2.
961 tons of gypsum granules.
7.6.
The Defendant did not produce 60 000
MT of product during the twelve-month production period of the IMA,
being 1 February 2016 until
31 January 2017.
7.7.
The Defendant produced product in
smaller quantities than 5000 MT per month.
7.8.
The Plaintiff delivered some raw
materials to the Defendant from time to time.
7.9.
There were bags unaccounted for by
the Defendant upon a reconciliation of the number of bags allegedly
supplied on behalf of the
Plaintiff to the Defendant, which resulted
in an oral agreement between the parties that the Defendant would
compensate the Plaintiff
for the cost of the missing bags in the
total sum of R125 232,59 by way of three monthly payments of R41
744,20.
7.10.
The Plaintiff recovered one payment
of R41 774,20 by way of set-off.
8.
The list of issues in dispute on the
pleadings was extensive but ultimately crystallized into the
following main issues in dispute
(although each had a number of
potential sub-issues):
8.1.
Whether the Plaintiff had correctly
pleaded and/or proved a case entitling it to repayment of the advance
payments and what the
correct cause of action for such repayment
would be if the IMA had expired by effluxion of time;
8.2.
The factual correctness of the
calculations on annexure "POC2" of advance payments made in
respect of limestone and gypsum
respectively for which no finished
product was received from the Defendant under the IMA.
8.3.
Whether the Plaintiff supplied
sufficient raw materials for the manufacture of the product related
to the advance payments by the
Plaintiff.
8.4.
Whether a portion of the advance
payments were made in respect of the prior agreement and whether such
advance payments were claimable
as contractual restitution pursuant
to the cancellation or termination of the IMA.
8.5.
Whether on a proper interpretation
of clause 4.1.1 of the IMA, the Defendant had undertaken to have a
production capacity of at
least 5000MT of product per month by 1
February 2016, or whether it by 1 February 2016 merely had to have
taken the necessary steps
to have a production capacity of at least
5000 MT of product per month (even if it did not have such production
capacity available
by 1 February 2016);
8.6.
In the event that the Plaintiff had
undertaken to order 60 000MT of product per annum on a take or pay
basis at the rate of 5000MT
per month during the production period as
per clause 4.1.2 and the Defendant had failed to produce material at
the rate of 5000
MT per month, whether the Defendant was entitled to
“catch-up” its production in the amount of a total of 60
000MT
per annum prior to the termination of the IMA on 31 January
2017;
8.7.
Whether the Defendant was entitled
to enforce its "take or pay" rights upon termination of the
IMA.
8.8.
Whether the Defendant's claim for
payment, alternatively damages, amounts to R17 885 400.00.
8.9.
The fate of the prior agreement upon
the conclusion of the IMA on 1 December i.e. whether the prior
agreement of July 2015 was repudiated
by the Defendant or whether the
IMA superseded the earlier agreement or whether the separate
agreement ceased to exist on the conclusion
of the IMA.
8.10.
Whether the quantities of product to
be purchased on a take or pay basis would be subject to pro-rating if
the Defendant was only
able to have a production capacity of at least
5000 MT of product per month from some time after 1 February 2016.
8.11.
Whether the Plaintiff proved its
case in respect of the quantum of the non-specification product by
the Defendant as per annexure
"POC3" of the Plaintiff's
Particulars of Claim; the value of the lost and wasted product and
raw material in terms of
the Plaintiff’s second claim and
whether the Plaintiff had or was compelled to comply with the
prescribed procedure for rejection
of non-complying products set out
in the IMA.
8.12.
Whether the Plaintiff breached the
IMA by failing to supply the Defendant with sufficient raw materials.
9.
It is immediately apparent from the
list of disputed issues that many are in fact interrelated. However,
it is also immediately
apparent from the pleadings and the issues in
dispute that the determination of the issues is largely predicated on
a proper interpretation
of the material terms of the IMA.
10.
Ultimately and as it transpired, the
main issue in the matter became whether clause 4.1.1. on its proper
interpretation, meant that
the Defendant had to take the necessary
steps to establish a production capacity of at least 5000 MT of
product by 1 February 2016,
i.e. whether the Defendant had to have
such production capacity by 1 February 2016 as contended by the
Plaintiff; or whether the
Defendant merely had to have taken the
necessary steps by 1 February 2016 to establish the said production
capacity, i.e. whether
the mere taking of the necessary steps by 1
February 2016 was sufficient to have fulfilled its undertaking in
clause 4.1.1, even
if the production capacity had not
de
facto
been established by 1 February
2016, as contended by the Defendant. The proper interpretation of
clause 4.1.1 therefore became
determinative of most of the remaining
issues in the matter.
11.
The evidence of the following
witnesses was led during the trial:
11.1.
For the Plaintiff:
11.1.1.
Mr Bertus Wessels ("Wessels"),
the Plaintiff's business development manager at the relevant time;
11.1.2.
Mr Jaco Vorster, the Plaintiff’s
Chief Financial Officer and during the relevant period, the
Plaintiff’s Head of Acquisitions
and Integration;
11.1.3.
Mr Robert Behrens, who at the
relevant time was employed with the Plaintiff as a financial
accountant;
11.1.4.
Mr Robert Ziemerink, who was
employed during the relevant period by the Plaintiff as a despatch
field supervisor.
11.2.
For the Defendant:
11.2.1.
Mr Andrew Wilmot, the managing
director of the Defendant;
11.2.2.
Mr Louis Klue, the Defendant’s
operational manager,
11.3.
Mr Troy Colin Momberg, the
Defendant’s expert.
12.
The evidence led by the respective
parties related largely to the contextual background of the IMA and
the circumstances which led
to the dispute between the parties. Much
of the evidence related to the Defendant’s counterclaim and its
quantification.
13.
It is therefore to the proper
interpretation of clause 4.1 that I now turn since this was the
burning issue upon which most if not
all the disputed issues are to
be determined.
14.
In relation to the proper
interpretation of the agreement, it is accepted law that the proper
interpretation of an agreement must
take place in its context as set
out in the leading case of
Natal Joint
Municipal Pension Fund v Endumeni Municipality
2012 (4) SA 593
(SCA) at paras [18] and [25] – [26], where the
Supreme Court of Appeal held as follows in this regard:
“
[18]
Over the last century there have been significant developments in the
law relating to the interpretation of documents, both
in this country
and in others that follow similar rules to our own. It is unnecessary
to add unduly to the burden of annotations
by trawling through the
case law on the construction of documents in order to trace those
developments. The relevant authorities
are collected and summarised
in Bastian Financial Services (Pty) Ltd v General Hendrik Schoeman
Primary School. The present state
of the law can be expressed as
follows: Interpretation is the process of attributing meaning to the
words used in a document, be
it legislation, some other statutory
instrument, or contract, having regard to the context provided by
reading the particular provision
or provisions in the light of the
document as a whole and the circumstances attendant upon its coming
into existence. Whatever
the nature of the document, consideration
must be given to the language used in the light of the ordinary rules
of grammar and
syntax; the context in which the provision appears;
the apparent purpose to which it is directed and the material known
to those
responsible for its production. Where more than one meaning
is possible each possibility must be weighed in the light of all
these
factors. The process is objective, not subjective. A sensible
meaning is to be preferred to one that leads to insensible or
unbusinesslike
results or undermines the apparent purpose of the
document. Judges must be alert to, and guard against, the temptation
to substitute
what they regard as reasonable, sensible or
businesslike for the words actually used. To do so in regard to a
statute or statutory
instrument is to cross the divide between
interpretation and legislation; in a contractual context it is to
make a contract for
the parties other than the one they in fact made.
The 'inevitable point of departure is the language of the provision
itself',
read in context and having regard to the purpose of the
provision and the background to the preparation and production of the
document.
.
. .
[25]
Which of the interpretational factors I have mentioned will
predominate in any given situation varies. Sometimes the language
of
the provision, when read in its particular context, seems clear and
admits of little if any ambiguity. Courts say in such cases
that they
adhere to the ordinary grammatical meaning of the words used.
However, that too is a misnomer. It is a product of a time
when
language was viewed differently and regarded as likely to have a
fixed and definite meaning; a view that the experience of
lawyers
down the years, as well as the study of linguistics, has shown to be
mistaken. Most words can bear several different meanings
or shades of
meaning and to try to ascertain their meaning in the abstract,
divorced from the broad context of their use, is an
unhelpful
exercise. The expression can mean no more than that, when the
provision is read in context, that is the appropriate meaning
to give
to the language used. At the other extreme, where the context makes
it plain that adhering to the meaning suggested by
apparently plain
language would lead to glaring absurdity, the court will ascribe a
meaning to the language that avoids the absurdity.
This is said to
involve a departure from the plain meaning of the words used. More
accurately it is either a restriction or extension
of the language
used by the adoption of a narrow or broad meaning of the words, the
selection of a less immediately apparent meaning
or sometimes the
correction of an apparent error in the language in order to avoid the
identified absurdity.
[26]
In between these two extremes, in most cases the court is faced with
two or more possible meanings that are to a greater or
lesser degree
available on the language used. Here it is usually said that the
language is ambiguous, although the only ambiguity
lies in selecting
the proper meaning (on which views may legitimately differ). In
resolving the problem, the apparent purpose of
the provision and the
context in which it occurs will be important guides to the correct
interpretation. An interpretation will
not be given that leads to
impractical, unbusinesslike or oppressive consequences or that will
stultify the broader operation of
the legislation or contract under
consideration.
”
15.
The Constitutional Court has cited with
approval the aforementioned principles in
Airports
Company South Africa v Big Five Duty Free (Pty) Ltd and Others
2019
(5) SA 1
(CC) where this Court held as follows at paragraphs [29] and
[30]:
“
[29]
There is no dispute about the principles of interpretation. The
correct approach to the interpretation of documents was summarised
by
the Supreme Court of Appeal in Endumeni Municipality
'Interpretation
is the process of attributing meaning to the words used in a
document, be it legislation, some other statutory instrument,
or
contract, having regard to the context provided by reading the
particular provision or provisions in the light of the document
as a
whole and the circumstances attendant upon its coming into existence.
Whatever the nature of the document, consideration must
be given to
the language used in the light of the ordinary rules of grammar and
syntax; the context in which the provision appears;
the apparent
purpose to which it is directed and the material known to those
responsible for its production. Where more than one
meaning is
possible each possibility must be weighed in the light of all these
factors. The process is objective, not subjective.
A sensible meaning
is to be preferred to one that leads to insensible or unbusinesslike
results or undermines the apparent purpose
of the document. Judges
must be alert to, and guard against, the temptation to substitute
what they regard as reasonable, sensible
or businesslike for the
words actually used. To do so in regard to a statute or statutory
instrument is to cross the divide between
interpretation and
legislation; in a contractual context it is to make a contract for
the parties other than the one they in fact
made. The ''inevitable
point of departure is the language of the provision itself'', read in
context and having regard to the purpose
of the provision and the
background to the preparation and production of the document.' [27]
[Footnotes omitted.]
[30]
I begin then with the 'inevitable starting point', the language of
the settlement agreement itself.
”
16.
However, in
Tshwane
City of v Blair Atholl Homeowners Association
2019 (3) SA 398
(SCA), the Supreme Court of Appeal held that
negotiations are nevertheless inadmissible as evidence in the
contextual setting and
held as follows at paragraphs [76] and [77]:
“
[76]
Insofar as the admissibility of evidence in relation to negotiations
is concerned, this court has recently, in Van Aardt v
Galway
2012 (2)
SA 312
(SCA), para 9, with reference to Van Wyk NO v Rottcher's Saw
Mills (Pty) Ltd
1948 (1) SA 983
(A) at 991, reaffirmed that evidence
of the intention of the parties of their prior negotiations is
inadmissible. In Delmas
Milling Co Ltd v Du Plessis
1955 (3) SA
447
(A) at 454 the court excluded, as a general rule, reference to
'actual' negotiations and 'similar statements'. It is true that at
455A – C there is a suggestion that 'conceivably', in
contractual cases where, after regard is had to surrounding
circumstances,
the ambiguity in a written text persisted, one could
have regard to what passed between the parties. It must be understood
that
this statement followed on what was understood to be admissible
in relation to testamentary documents. It is also true that in
Coopers & Lybrand and Others v Bryant
[1995] ZASCA 64
;
1995 (3) SA 761
(A) ([1995]
2 All SA 635
;
[1995] ZASCA 64)
at 768D – E, the passage from
Delmas at 455A – C is Navsa ADP and Mothle AJA (Swain JA,
Dambuza JA and Mokgohloa AJA
concurring) cited as support for the
view that evidence of negotiations could, in the face of enduring
ambiguity, be admitted.
[77]
In our view, Van Aardt and Van Wyk should be followed. It would be in
line with the parol evidence rule which we imported and
have
maintained and it is consonant with the modern approach to
interpretation of contracts in English law, the development of
which
mirrors developments in our law. Allowing evidence in relation to
negotiations will see further extensive evidence being
led and will
have the effect of minimising the words the parties have chosen to
employ. Endumeni rightly emphasises the significance
of the words the
parties have chosen to record their agreement, though not above
context. Permitting evidence of negotiations will
lead to further
uncertainty. The words, as an objective measure, are elevated above
the partisan positions of parties in negotiations
and litigation.
”
17.
The Supreme Court of Appeal in
Capitec
Bank Holdings Limited v Coral Lagoon Investments 194 (Pty) Ltd
2022
(1) SA 100
(SCA), held as follows at paragraphs [51]:
“
51]
Most contracts, and particularly commercial contracts, are
constructed with a design in mind, and their architects
choose words
and concepts to give effect to that design. For this reason,
interpretation begins with the text and its structure.
They have a
gravitational pull that is important. The proposition that context is
everything is not a licence to contend for meanings
unmoored in the
text and its structure. Rather, context and purpose may be used to
elucidate the text.”
18.
The subsequent conduct of the parties and
how they implemented the contract, is also important in determining
their intention as
part of the factual context. In this regard, it
was held as follows in
Unica Iron and
Steel (Pty) Ltd and Another v Mirchandani
2016
(2) SA 307
(SCA) at para [21]:
“
All
that needs to be added is that it can be accepted that the way in
which the parties to a contract carried out their agreement
may be
considered as part of the contextual setting to ascertain the meaning
of a disputed term — see eg Rane Investments
Trust v
Commissioner, South African Revenue Service
2003 (6) SA 332
(SCA)
(2003 (8) JTLR 216
;
65 SATC 333
;
[2003] 3 All SA 39)
para 27. As is
stated in Christie & Bradfield Christie's The Law of Contract in
South Africa 6 ed (2011) at 117, relying upon
Breed v Van den Berg
and Others
1932 AD 283
at 292 – 293, this is because the
parties' subsequent conduct 'may be probative of their common
intention at the time they
made the contract'.
”
19.
Interpretation
is accordingly a so-called ‘unitary endeavour’.
[1]
Moreover the interpretation of a contract is a matter for the court,
not witnesses.
[2]
20.
Before dealing with the salient
terms of the IMA and the proper construction thereof, it is therefore
necessary to place the IMA
in its proper context. Fortunately, the
parties were largely
ad idem
as to how the IMA arose, its contextual background and its purpose.
21.
The factual background to the
dispute (including the context in which the IMA was concluded), is
that during or about March 2015
the Plaintiff and another firm,
Advanced Agri, decided to jointly introduce an ultra-fine limestone
product into the agricultural
fertiliser market in South Africa with
the Plaintiff being responsible for its production and Advanced Agri
being responsible for
sales thereof. Advanced Agri introduced the
Plaintiff to the Defendant as the possible manufacturer of the
product. By “manufacture”
is mean the pelletization of
the powder raw materials into pellets or “prills”.
22.
The relationship between the
Plaintiff and the Defendant commenced with a presentation made by
Klue on behalf of the Defendant on
8 May 2015. At that time the
Defendant had as single production plant with a capacity of
approximately 1 500 tons of granulated
product per month. The
Defendant agreed to upgrade the old plant to a capacity of 2 000 MT
per month and following a test
order placed by the Plaintiff on 22
May 2015, the Plaintiff placed an order for 24 000 MT of pelletized
limestone on 23 July 2015,
to be produced at volumes of 2 000 MT per
month for 12 months starting in August 2015. An agreement was reached
that should the
Defendant not be able to produce 2000 MT within a
specific month, the shortfall would be made up in the following
month. This was
the prior agreement referred to above. There is a
dispute whether this prior agreement ceased to exist or was
subsequently replaced
by the IMA and this issue also turns on the
proper interpretation of the IMA. Production on the 24 000-ton order
started on or
about 6 August 2015.
23.
The Plaintiff then required
additional and more reliable production of product and negotiations
took place between the Plaintiff
and the Defendant during October and
November 2015 for an order of 5 000 MT per month of products (being
limestone and gypsum)
for an initial period of 12 months from 1
February 2016 to 31 January 2017, to be manufactured by a new modular
pelletization plant
(sometimes referred to during the trial as “a
granulation plant”) to be built and commissioned by the
Defendant.
24.
On 1 December 2015, the parties
concluded the IMA. During January 2016, the Defendant obtained
finance from Standard Bank for the
construction of the new plant and
during the period December 2015 to May 2016, the new plant was built,
commissioned and production
started on 1 June 2016. This despite the
IMA providing for the “production period” to be a
twelve-month period from
the date on which the new plant was
commissioned or 1 February 2016, whichever date was the earlier.
25.
During October 2016, a dispute arose
between the Plaintiff and the Defendant as the latter was of the view
that there was not a
sufficient volume of raw materials being
supplied by the Plaintiff to the Defendant for it to achieve 5000 MT
per month.
26.
On 28 November 2016, the Defendant
again complained of shortfalls in limestone deliveries by the
Plaintiff (it being common cause
that the Defendant would supply the
gypsum raw material and not the Plaintiff), contending that the
arrears amounted to more than
18 000 MT over the preceding six months
and by 3 650 MT in November 2016 alone. The Defendant asserted
that, in addition
to the 50 000 MT of limestone granulation agreed to
in the IMA, there was also the additional prior order for 24 000 tons
of limestone
granules of July 2015. It was contended by the
Defendant that the continued raw material delivery shortfalls were
having
a devastating effect on the Defendant's daily production and
cost recoveries. The Defendant contended that it required sufficient
buffer stocks of raw material (i.e. 1000 MT) to be able to run the
plant continuously since continuous stop-start would affect
the
variable costs of the plant since it required huge loads of
electricity to fire up the furnace if it had cooled down.
27.
On 30 November 2016, Mr Behrens, on
behalf of the Plaintiff, indicated to the Defendant that the original
order number for the 24
000 MT was completed and that the Defendant
should use another order number from that date.
28.
On 13 December 2016, the Defendant
again complained of the Plaintiff's inability to deliver limestone
raw material. It is at this
juncture important to record that all the
Defendant’s complaints to the Plaintiff about insufficient raw
materials being
supplied related to buffer stock that was required to
run the plant efficiently to reduce the variable costs and not
specifically
to an agreed 5000 MT per month. It was only during the
latter part of 2016 that the Defendant began to refer to 5000 MT per
month
and the take or pay referred to in the IMA.
29.
On 20 December 2016, the Plaintiff
proposed an addendum to the IMA with effect from 1 December 2016,
which provided for the parties
to agree that any production amounts
and/or Pelletized Product required to be manufactured by the
Defendant and/or purchased by
the Plaintiff in terms of the IMA would
be terminated and be replaced in their entirety by a required
production of 10 000 MT of
Pelletized Product in terms of the
addendum. The addendum was not accepted by the Defendant.
30.
On 18 January 2017, the Defendant
purported to cancel the IMA. The IMA would in any event have lapsed
by effluxion of time, on 31
January 2017.
31.
On 14 February 2017, the Plaintiff
informed the Defendant that it regarded the Defendant’
purported cancellation of the IMA
as a repudiation of the agreement,
which repudiation the Plaintiff accepted, and it made demand for
payment by the Defendant.
32.
Having regard to all the evidence in
the trial, the purpose of the IMA, in general terms, was to establish
a contractual relationship
between the Plaintiff and the Defendant in
terms of which the Defendant would use it production plant to
pelletize the raw material
supplied to it by the Plaintiff at an
agreed price. The “purpose” is of course different to the
“how”.
The details of the “how” are to be
found in the terms of the IMA.
33.
Having placed the IMA in its proper
context, one must then turn to the “inevitable starting point”
being the language
of the IMA itself. I refer below to the
uncontentious clauses of the IMA because the contentious clause must
be interpreted in
the context of the remaining clauses of the IMA so
as to ascertain what the parties probably intended.
34.
In terms of uncontentious clauses of
the IMA, the Plaintiff's main obligations were the following:
34.1.
To
place all orders and instructions on the Defendant in terms of the
IMA.
[3]
34.2.
To
ensure that it delivers the raw material as advised by the Defendant
from time to time.
[4]
34.3.
To
supply gypsum within a specification agreed between the parties from
time to time.
[5]
34.4.
To
pay the Defendant at the rate of R570 per MT of product produced with
limestone and R600 per MT of product produced with gypsum.
[6]
34.5.
To
make such payment, for the initial 3 000 MT of product, in respect of
each 1 000 MT to be produced, prior to production and on
receipt of a
valid tax invoice from the Defendant.
[7]
34.6.
To make payment thereafter on
completion of each 15 days of production of product and on receipt of
a valid tax invoice from the
Defendant.
35.
The Defendant's main obligations
under the IMA were:
35.1.
To
take receipt of the raw materials and to warehouse same under
suitable conditions, as advised by the Plaintiff, to ensure the
integrity and longevity of the raw materials.
[8]
35.2.
To
manufacture the required mass of the product within the required
timeframe, as specified and ordered by the Plaintiff from time
to
time. Upon manufacture, the ownership of the product, on making
full payment to the Defendant, would immediately vest
in the
Plaintiff.
[9]
35.3.
The
Defendant would not be held responsible for "production
shrinkage" which the parties agreed, in the case of limestone,
would not be more than 3% but may, in the case of gypsum, be as high
as 30%.
[10]
35.4.
To produce product to the
specification as set out in annexure "B" to the IMA.
35.5.
To
bag the product as required for immediate transportation or for
storage, to warehouse the product under suitable conditions,
as
advised by the Plaintiff and to ensure the integrity and longevity of
the product until such time that the necessary logistical
arrangements for uplifting the product were confirmed by the
Plaintiff.
[11]
35.6.
To
keep stock of all raw materials, product and bags supplied under the
terms of the IMA, as advised by the Plaintiff.
[12]
35.7.
To
undertake a monthly stocktake, with representatives of the Plaintiff,
to ensure that all raw materials and product was accounted
for.
[13]
35.8.
To
comply with all applicable safety, health and environmental laws and
regulations.
[14]
35.9.
To
comply with the agreed quality requirements with regard to the
specification and other related qualities.
[15]
35.10.
The
Defendant would not release any product for shipment that did not
conform to the specification, without the prior written approval
of
the Plaintiff.
[16]
35.11.
The
Plaintiff could advise of any non-complying product by providing
notice of rejection to the Defendant within ten days following
receipt by the Plaintiff of any shipment of such product.
[17]
35.12.
In
addition to any other rights or remedies available to the other
parties under the IMA, the Defendant would replace rejected product
as soon as practicable at no additional charge to the Plaintiff, and
the Defendant would reimburse the Plaintiff for any raw materials
or
other product used to manufacture any such non-complying product.
[18]
35.13.
Notwithstanding
anything to the contrary, the Plaintiff would be solely responsible
for all costs and expenses incurred in connection
with and
non-complying product to the extent any raw material resulted in such
product being non-compliant, and would reimburse
the Defendant for
its costs and expenses incurred in connection with the manufacture of
such non-complying product.
[19]
35.14.
All
non-complying product and product rejected pursuant to the IMA would
be removed and either re-processed or disposed of by the
Defendant in
accordance with all applicable laws.
[20]
36.
As alluded to in clause 4.1 and the
proviso to clause 4.1.2, as quoted below, the initial manufacturing
arrangement in terms of
the IMA was part of a long-term plan of the
Plaintiff to set up its own production plant. This is common cause
and further borne
out by:
36.1.
The
obligation of the Defendant to provide additional support services to
the Plaintiff, subject to a further written agreement,
to:
[21]
36.1.1.
assist the Plaintiff in
commissioning a new production plant in South Africa and/or Africa;
36.1.2.
advise the Plaintiff with regard to
the optimal binders to use in production;
36.1.3.
train the Plaintiff's operational
staff;
36.1.4.
advise the Plaintiff in
commercialising any pelletizing ventures.
36.2.
The terms of clause 4.2 which read
as follows:
"
At least 90 days
prior to Idwala commissioning its production plant and/or the expiry
of the Production Period, the Parties undertake
to enter into good
faith negotiations regarding the continuation of the Project.
In terms of negotiations, the Parties shall
negotiate, inter alia,
the product to be pelletized, price and the duration.
"
36.3.
In terms of clause 8, the IMA would
be effective from the signature date and would remain in effect until
the expiry of the Production
Period or, if applicable, the expiry of
the period agreed in terms of clause 4.2, whichever was the later
date.
37.
The
"Production
Period meant a period of twelve months, which would commence on the
earlier of (i) the date when the Defendant
had
commissioned the necessary plant to manufacture at least 5 000
MT of product per month or (ii) 1 February 2016, as set
out in
further detail in clause 4.1.1."
[22]
38.
Clause 7 of the IMA granted
exclusivity to the Plaintiff:
"
Amserve agrees
that it shall exclusively supply and not compete with Idwala in the
sale of any micro-fine, ultra-fine and/or micronized
calcitic or
dolomitic limestone product or similar produced with the Raw
Materials, for the duration of this Agreement and subject
to Idwala
exercising the option in clause 9.4, for twenty-four months after the
termination or expiry of the Agreement.
"
39.
Clause 15.1 of the IMA contained a
restraint / non-solicitation provision:
“
Amserve
agrees that during the term of this Agreement and for twelve months
after its termination, Aserve shall not, directly or
indirectly,
solicit or attempt to solicit any micro-fine granule business (which
uses the Raw Materials to make products of similar
application to the
Pelletized Product) from any of Idwala’s customers, prospective
customers, or vendors, whether such parties
are directly or
indirectly engaged with Idwala.
”
40.
In terms of clause 9.3, the
termination of the IMA, for whatever reason, would not affect the
rights of any of the parties which
may have accrued as at the date of
termination and would further not affect any rights which
specifically or by their nature survived
the termination of the IMA.
41.
In terms of clause 9.4, if the IMA
was terminated for any reason whatsoever, then upon termination:
41.1.
The Plaintiff would retake
possession of all or the raw materials then in the possession of the
Defendant.
41.2.
The Plaintiff would take possession
of all paid for product then in the possession of the Defendant.
42.
The Defendant would grant the
Plaintiff an option to purchase all of the Defendant's production
facility and plant used in the manufacture
of the product (whether
commissioned at the signature date or later) at a price calculated in
accordance with clause 9.4.3.3 of
the IMA.
43.
The contentious clause of the IMA
and on which the whole matter turns, is clause 4.1, which reads as
follows:
"
4.1
In respect [of] the arrangements set out in clause 3 and in order to
advance the Project,
the Parties agree that until such time that
Idwala has the necessary production plant:
4.1.1
Amserve undertakes to take all necessary steps (which shall include
expanding its production plant) to produce at least 5000 MT of
Pelletized Product per month by 1 February 2016, which shall be
determined by the availability of Limestone and gypsum and the market
requirements; and
4.1.2.
provided Amserve satisfies the undertaking in clause 4.1.1 by 1
February
2016, Idwala undertakes to purchase at least 60 000 MT of
Pelletized Product per annum on a "take or pay" basis, with
a minimum of 5 000 MT per month, for the Production Period which
shall comprise of at least:
4.1.2.1
50 000 MT of Pelletized Product produced using Limestone per annum;
and
4.1.2.2
10 000 MT of Pelletized Product produced using gypsum;
provided
that such amounts shall be pro-rated in the year that Idwala's
production plant is commissioned, if such date occurs after
the
expiry of the Production Period.
4.1.3
For the sake of clarity, should Amserve fail to produce a minimum
of
5 000 MT of Pelletized Product per month from 1 February 2016, Idwala
shall only be obliged to take the annual volumes as produced
to 31
January 2017. Any shortfall in the volume shall not be carried over
to the next year.
"
44.
Taking into account the IMA as a
whole and the relevant factual contextual background in which it was
concluded, the parties clearly
intended that the Defendant would be
able to pelletize 60 000 MT raw material, divided between 50 000 MT
of limestone product and
10 000 MT of gypsum for the Plaintiff,
initially for the production period as defined in clause 2.1.11, and
then possibly for a
further agreed period, until the Plaintiff had
either erected and commissioned its own pelletization plant at some
point in the
future or had purchased the Defendant’s new
pelletization plant. For this purpose, the Defendant agreed to build
a new pelletization
plant capable of producing at least 5000 MT per
month.
45.
As set out above, the production
period is defined as a period of twelve months which would commence
on the earlier of (i) the date
when the Defendant had commissioned
the necessary plant to manufacture at least 5000 MT of Pelletized
Product per month or (ii)
1 February 2016 as set out in further
detail in clause 4.1.1. It is common cause that the new plant was not
commissioned by 1 February
2016 and therefore the production period
of twelve months commenced on 1 February 2016 to 31 January 2017.
What is important in
this definition of the production period is that
it was agreed that the “necessary plant” is one which
could manufacture
at least 5000 MT of product per month. The need was
clearly for a new plant which could manufacture at least this volume
of product.
46.
In clause 4.1.1, the Defendant
undertook to take all necessary steps (including expanding its
current production plant) to produce
“at least” 5000 MT
of product per month by 1 February 2016. However, it is further
stated that this volume would be
determined by the availability of
limestone and gypsum and the market requirements.
47.
The Defendant contends that taking
into account the contextual evidence that the new plant could not be
finally commissioned by
1 February 2016, because the Defendant was
still finalising the acquisition of the necessary finance from
Standard Bank and some
major components with long lead manufacture
times had not yet been ordered and the subsequent conduct of the
parties, clause 4.1.1
must be interpreted as meaning that the
Defendant did not have to establish a production capacity of 5000 MT
per month by 1 February
2016, but rather that it merely had to have
taken the necessary steps to do so by 1 February 2016. The Defendant
contends that
as long as it had taken all the necessary steps (such
as ordering the components, contracting with the necessary
contractors etc.),
it had complied with its undertaking in clause
4.1.1 and therefore the Plaintiff had undertaken to order at least 60
000MT of product
per annum on a take or pay basis, at a rate of at
least 5000MT per month for the duration of the production period –
being
1 February 2016 to 31 January 2017.
48.
Furthermore, the Defendant contends
that no businessman in their right mind would commit to the expense
of a new plant and to sign
finance agreements with a bank where the
company had to repay more than a million rand per month, without the
“guarantee”
of the take or pay arrangement for 60 000MT
per annum, otherwise, says the Defendant, it would be at the mercy of
the Plaintiff
who would not have any obligation to place any orders
at all. This says the Defendant is reinforced by the fact that the
IMA had
an exclusivity clause therein in terms of which the Defendant
could not use the plant for any other customer other than the
Plaintiff.
49.
The Defendant contends therefore
that the only commercially sensible interpretation of clause 4.1.1
and what it was undertaking
therein, was not to having a production
capacity of 5000 MT per month by 1 February 2016 but rather merely
having taken the necessary
steps by 1 February 2016 to acquire such
production capacity.
50.
There are however a number of
problems with the Defendant’s contentions in this regard. The
Defendant’s interpretation
of clause 4.1.1 militates against
the definition of “production period”, which the parties
agreed would be from the
date the plant was commissioned or 1
February 2016, whichever was the earlier. This means the parties
clearly contemplated the
production period commencing by no later
than 1 February 2016. There would be no point in agreeing to such a
production period
even if the plant was unable to produce the
required 5000MT per month by 1 February 2016.
51.
Furthermore, it was also clear from
the evidence that both the parties believed that the sales of the
product would be high and
the Plaintiff’s research had
predicted they would need approximately 5000MT per month during the
production period. This
means that the Defendant’s Mr Wilmot,
whilst possibly realising that the Defendant may not be able to
comply with clause
4.1.1 by having a production capacity of 5000MT by
1 February 2016, was not overly concerned since he was of the view
that the
Defendant had in any event landed a massive customer with
huge orders and the Defendant would be making sufficient revenue to
repay
the bank loan, irrespective of whether the Plaintiff had agreed
to the take or pay commitment.
52.
Furthermore, it is not clear that
the Defendant would be unable to commission the plant by 1 February
2016 and it also not clear
that the Plaintiff was aware that the
plant could not be commissioned by that date. This is important since
the proper interpretation
to be accorded to a term is what the
parties’ common intention probably was and not only what one
party may have been aware
of, but rather what both were definitely
aware of. There is also evidence which shows that even Mr Wilmot may
have harboured the
hope that the plant could have the necessary
production capacity by 1 February 2016, since on 1 December he wrote
to Standard Bank
and indicated that he expected the plant to be
finally commissioned by end of January 2016. Counsel for the
Defendant contended
that this letter merely served to put pressure on
Standard Bank to finalise the loan (which by 1 December 2015) had not
yet been
finalised. However, if that was so it would mean that Mr
Wilmot was making a material and intentional misrepresentation to
Standard
Bank. In my view the more plausible explanation is that Mr
Wilmot genuinely and
bona fide
believed that it was indeed possible to have the plant commissioned
by end of January 2016, as stated in his letter. If that is
so, it
means that the Defendant when the IMA was signed, was of the belief
that the plant could possibly have a production capacity
of 5000MT
per month by 1 February 2016 and the Defendant took the chance of
signing the IMA and trying to comply with clause 4.1.1
by
commissioning the new plant by 1 February 2016 and even if it could
not do so, it was worth the risk since it anticipated large
orders
from the Plaintiff irrespective of the Plaintiff had committed to the
take or pay order in clause 4.1.2.
53.
Lastly, the Defendant made much of
the subsequent conduct of Mr Vorster, contending that he wrote a
letter to the Defendant on 30
November 2016, in which he indicated
the Plaintiff was unable to fulfil its contractual obligations to the
Defendant. The Defendant
contends that the only contractual
obligations that Mr Vorster could have been referring to was the take
or pay obligation for
60 000 MT of product per annum as envisaged in
clause 4.1.2. The Defendant contends that this subsequent conduct
when taken into
account as part of the contextual evidence supports
its interpretation of clause 4.1.1 and that therefore it had complied
with
taking the necessary steps by 1 February 2016 to establish a
plant with a capacity of at least 5000 MT per month and therefore the
Plaintiff had undertaken the take or pay order envisaged in clause
4.1.2. However, a perusal of that letter does not reveal whether
Mr
Vorster was referring specifically to an obligation in terms of an
enforceable take or pay order or to the Plaintiff’s
obligations
generally in terms of the IMA. After all, irrespective of a take or
pay order, the Plaintiff nevertheless had an obligation
to use the
Defendant exclusively to pelletize its raw materials. What the letter
appears to be telling the Defendant is that the
Plaintiff was unable
to deliver raw material because of a problem at its quarries and not
specifically that it was unable to comply
with an obligation to
deliver sufficient raw material to enable the Defendant to produce at
least 5000 MT of product per month.
In as much as this letter is not
clear, it does not assist the Defendant’s interpretation of
clause 4.1.1.
54.
The Plaintiff in turn contends that
taking into account the contextual evidence that the Plaintiff needed
to build up reserves of
product stock in anticipation of the planting
season (which was from approximately November 2016 to February or
2017), the need
to arrange logistics and transport of the raw
material and the product and storage thereof, that the production
period would commence
by latest 1 February 2016 and the remaining
clauses of the IMA (most importantly clauses 4.1.2 and 4.1.3), clause
4.1.1 must be
interpreted as meaning that the Plaintiff would only
commit to the take or pay order in clause 4.1.2, whereby it was
committing
to paying for at least 60 000 MT of product (at a rate of
at least 5000 MT per month) irrespective of whether it took such
product
or not, if the Defendant had in fact established a production
capacity of 5000 MT per month by the beginning of the production
period
in casu
being 1 February 2016. This was so that the Defendant could in fact
produce 5000MT per month, for which volume the logistics was
manageable and which would allow it to build up a reserve of product
stock to facilitate the planting season when demand was anticipated
to be high and the stock had to be readily available in the
Plaintiff’s warehouses for shipping to farmers as and when
necessary.
55.
Taking the aforesaid contextual
evidence into account, the proper interpretation of clauses 4.1.1 is
that the parties agreed that
the Defendant would take all necessary
(note – the wording is “necessary” and not
“reasonable”) steps
to be able to pelletize at least 5000
MT of product by 1 February 2016. Whilst this clause does
specifically not refer to the building
of a plant in order to do so,
if this clause is read in conjunction with the definition of
“Production Period” in clause
2.1.11, it is clear that
the parties intended that a plant be constructed and commissioned
capable of a production capacity of
at least 5000 MT per month by 1
February 2016. But the requirement in clause 4.1.1 (read with the
definition of “Production
Period”) envisages that the
Defendant had to ensure that it had the capacity to pelletize at
least 5000 MT of product per
month from 1 February 2016, since that
is when the production period would commence.
56.
In my view, there would be no point
in agreeing to a production period commencing on 1 February 2016, if
the production plant did
not have to be ready to produce at least
5000MT by 1 February 2016 and an interpretation that the production
plant would not have
to be commissioned and able to produce 5000MT
per month by 1 February 2016 is not a commercially sensible
interpretation in the
circumstances of the agreement and having
regard to its purpose.
57.
What is more difficult to determine
is what was meant by the words “which shall be determined by
availability of limestone
and gypsum and market requirements”.
Both parties were
ad idem
that this can only mean that the requirement that the plant can
produce at least 5000MT per month means that the actual requirements
every month may be more and would be determined by limestone and
gypsum available to do so and/or if the market required more than
5000 MT per month. Ultimately, the Defendant must by 1 February 2016
and thereafter have had in place the capacity to produce at
least
5000 MT per month, Clause 4.1.1 does not refer to actual production
by 1 February 2016 but rather to the capacity to do so.
The actual
production thereafter would be determined by the availability of
limestone and gypsum and the market requirements.
58.
The addition of those words in
clause 4.1.1 reinforces the interpretation that the Defendant had to
have commissioned a plant capable
of producing at least 5000MT per
month by 1 February 2016 and not merely have taken the necessary
steps to do. If it merely had
to have taken the necessary steps to do
so, it would not have been necessary to add the words “which
shall be determined
by availability of limestone and gypsum and
market requirements” since there would in any event not
necessarily be any production
capacity by 1 February 2016 on the
Defendant’s interpretation and therefore no need to qualify the
necessary production capacity
by the inclusion of those words in
clause 4.1.1.
59.
It is noteworthy that those words
were included in clause 4.1.1. and not in clause 4.1.2 which refers
to the take or pay and where
such words would have made more sense
once a production capacity had been established. This also reinforces
the interpretation
of clause 4.1.1. that the Defendant had undertaken
to establish a production capacity by 1 February 2016 and not merely
the taking
of the necessary steps by 1 February 2016 to do so.
60.
Clause 4.1.2 then provides that
“provided” the Defendant had satisfied the undertaking in
clause 4.1.1 by 1 February
2016 (as explained above), the Plaintiff
undertook to purchase at least 60 000 MT of Pelletized Product per
annum on a “take
or pay” basis, with a minimum of 5000 MT
per month, for the production period, which would comprise of at
least 50 000 MT
of limestone pelletized product and 10 000 MT of
gypsum pelletized product. This clause is material to the Defendant’s
counterclaim
because its entire counterclaim is predicated on the
Plaintiff having committed to an order of 60 000MT per annum on a
take or
pay basis.
61.
The Defendant contends that clause
4.1.2 means that the Plaintiff was obliged to take 5000 MT of product
(which include limestone
or gypsum or both making up 5000 MT per
month) and pay for it, failing which the Plaintiff would in any event
have to pay for the
equivalent of 5000 MT of product. This calls into
question two issues: firstly, whether that obligation arose at all if
the Defendant
failed to comply with its undertaking in clause 4.1.1
and secondly, what was meant by “take or pay” and how it
was
to be applied practically, particularly since it did not specify
whether the payment for 5000 MT of product would be for limestone
or
gypsum or in what proportion of whether it would be pro-rata the
amount of 50 000 limestone product per annum and 10 000 gypsum
product per annum, for the purpose of calculating the monthly payment
amount. This itself calls into question whether the “take”
option was for 50 0000 MT of limestone per annum divided by 12 months
and 10 000 MT of gypsum product per annum divided by 12 months
i.e.
whether the Plaintiff obliged to take or pay for 4166 MT of limestone
product per month and 833 MT of gypsum product per month.
Fortunately, on the proper interpretation of clause 4.1.1 and since
the take or pay undertaking did not come into effect as explained
below, it is not necessary to determine the correct interpretation of
the take or pay clause.
62.
However, it is necessary to
determine whether the take or pay came into effect and bound the
Plaintiff at all. In order to determine
this, it is necessary to
interpret the words “provided Amserve satisfies the undertaking
in clause 4.1.1 by 1 February 2016,
Idwala undertakes to purchase …”.
The Defendant was constrained to concede (correctly so) that it would
have had to
comply with its undertaking in clause 4.1.1 (as properly
interpreted) before the Plaintiff was obliged to commit to the
undertaking
in clause 4.1.2 to place such order on a take or pay
basis. This is clear from the words “provided Amserve satisfies
the
undertaking in clause 4.1.1 by 1 February 2016, Idwala undertakes
to purchase …” (my emphasis) and there can be no
other
commercially sensible meaning to this word “provided” in
this clause.
63.
As set out above, the Plaintiff
contends that clause 4.1.1 imposes an absolute obligation upon the
Defendant to have its production
plant ready to produce at least 5
000 MT of product per month by 1 February 2016, failing which the
Plaintiff is permanently relieved
of the obligation in terms of
clause 4.1.2 to purchase at least 60 000 MT of product per annum on a
take or pay basis, with a minimum
of 5 000 MT per month. In
other words, if the deadline of 1 February 2016 is missed, it becomes
discretionary for the Plaintiff
to place orders for the production of
product on the Defendant and the Plaintiff is not bound by the take
or pay basis.
64.
But for the conditional undertaking
in clause 4.1.2, the IMA was merely an agreement in terms of which
the Defendant would pelletize
the tonnages of raw material supplied
to it by the Plaintiff from time to time, without any obligation on
the Plaintiff to order
any minimum tonnage per month or per annum.
The only obligation on the Plaintiff to order a specific minimum
tonnage of product
per annum with an agreed minimum, is found in
clause 4.1.2 – but that undertaking which gives rise to the
obligation to do
so is itself subject to the proviso that the
Defendant had complied with its own undertaking in clause 4.1.1.
65.
The Defendant contends, correctly,
that clause 4.1.1 does not constitute a guarantee or warranty that
the plant would have 5000
MT per month capacity by 1 February 2016.
However, what this contention ignores is that the failure to do so
had consequences in
respect of whether the Plaintiff was obliged to
comply with its own undertaking in clause 4.1.2.
66.
The Defendant is also correct in its
contention that it is clearly envisaged in the definition of
"Production Period"
that the necessary plant to manufacture
at least 5 000 MT of Pelletized Product per month may only be
commissioned at a date later
than 1 February 2016. But similarly,
whilst it is so that the pelletization plant could indeed be
commissioned on a date later
that 1 February 2016, this too had
consequences as set out above. The main consequence would be that the
Plaintiff was relieved
of the obligation to take or pay for 60 000 MT
of product per annum, with a minimum of 5000 MT per month.
67.
The Defendant further contention in
this regard is that clause 4.1.3 clearly caters for the situation
where the Defendant fails
to produce a minimum of 5 000 MT of product
per month from 1 February 2016. In such a case, the Plaintiff is only
obliged to take
so much of the annual volumes (60 000 MT) as produced
up to 31 January 2017 and any shortfall in the annual volume is not
be carried
over to the following year. The Defendant contends
further that this implies by necessity that any shortfall in the
monthly
volume produced may be carried over to the following months
subject to the 31 January 2017 cut-off i.e. that it can make up the
low production.
68.
On a proper interpretation of clause
4.1.3, it was not intended to apply in the absence of an obligation
by the Plaintiff in terms
of clause 4.1.2. In other words, should the
Defendant comply with its obligation in clause 4.1.1, and clause
4.1.2 did not become
operative then clause clause 4.1.3 also did not
become operative. Clause 4.1.3 merely made it clear that if the
Plaintiff had committed
to the take or pay in clause 4.1.2, the
Plaintiff was however not entitled to take or pay what the Defendant
has not produced and
was only obliged to take (and pay) the volumes
actually produced by the Defendant every month up to 31 January 2017.
69.
Clause 4.1.3 then also made it clear
that any shortfall in the volume (i.e. 60 000 MT) could not be
carried over into the next year
(the word “year” in the
last sentence of clause 4.1.3 can only sensibly be interpreted as
referring to the next “production
period” i.e. if a
further agreement is concluded for another production period).
70.
But ultimately, clause 4.1.3 was
only applicable if the Plaintiff had the obligation to take or pay 60
000 MT per annum, with a
minimum of 5000 MT per month and this in
turn only became enforceable if the Defendant has a production
capacity of at least 5000
MT per month by 1 February 2016. It is
common cause that it did not, since it is common cause that the new
production plant was
only commissioned in June 2016 – some five
months after 1 February 2016. This means that it is not necessary to
determine
whether on a proper interpretation of clause 4.1.3, the
Defendant had a right to catch-up production by the end of the
production
period on 31 January 2017, in the event that it could not
produce 5000MT per month during the production period since this
alleged
right would only have been relevant if the Plaintiff had
undertaken the take or pay order in terms of clause 4.1.2 –
which
it did not.
71.
Ultimately the Defendant’s
interpretation of clause 4.1.1 and its reliance on subsequent conduct
of the parties, is “unmoored
in the text and its structure”
and particularly if one has regard to the text in the context of
clauses 4.1.2 and 4.1.3.
72.
Having found that the Plaintiff did
not have an obligation to purchase at least 60 000 MT per annum, with
a minimum of 5000 MT per
month, on a take or pay basis, there appears
no reason to determine what exactly is meant by the concept take or
pay. Neverthless,
it seems that “take or pay” in the
context of the IMA simply means that if the Defendant was making its
production
capacity exclusively available to the Plaintiff for 60 000
MT per annum, with a minimum of 5000 MT per month, the Plaintiff was
then obliged to take supply sufficient material to produce at least
5000 MT of granulated product per month and the Plaintiff had
to then
take delivery of (and pay) for such product and furthermore would be
liable to make payment of the equivalent of 5000 MT
of product, even
if it had not delivered sufficient raw material to the Defendant. In
other words, the Plaintiff would pay the
Defendant the equivalent of
5000 MT of product per month essentially for reserving the
Defendant’s production capacity for
that month. The Plaintiff
then either delivered sufficient raw material and took it or it did
not deliver sufficient raw material
and paid the equivalent for 5000
MT as if the Defendant had in fact produced it.
73.
Of course, the clause is silent on
what happens if the Plaintiff delivered sufficient raw material, but
the Defendant did not produce
5000 MT of product. In such a case the
only commercially sensible interpretation would be that the Plaintiff
was not obliged to
make payment for product that the Defendant did
not produce despite being in a position to do so and the take or pay
would not
apply. However, since I have held that clause 4.1.2 and
4.1.3 did not become applicable to the parties, I need not make a
definitive
finding in this regard.
74.
I therefore find that on a proper
interpretation of clause 4.1.1, the Plaintiff was not obliged to
purchase at least 60 000MT per
annum of granulated product, on a take
or pay basis, with a minimum of 5000MT per month. That being so, the
fundamental premise
for the Defendant’s first counterclaim
predicated on the enforceability of the take or pay, must fail.
75.
Based on the aforesaid
interpretation of the IMA, the Plaintiff cannot be said to have
breached the IMA since it was not obliged
to deliver any minimum
amount of raw material to the Defendant. In terms of the IMA and
since clauses 4.1.2 and 4.1.3 were not
applicable or enforceable, the
Plaintiff was only obliged to make payment for the raw material in
fact pelletized and made available
to the Plaintiff by the Defendant.
There is no suggestion that the Plaintiff failed to make payment to
the Defendant for product
pelletized for it by the Defendant –
whether in terms of the initial agreement or the IMA.
76.
Based on the aforesaid finding, it
is not then necessary to deal with the remaining issues raised in
respect of the Defendant’s
counterclaims, such as
inter
alia
whether the Plaintiff had failed
to supply the raw material necessary to produce 5000 MT of granulated
product per month, the reasons
for the stoppages in the production
and the quantification of the Defendant’s counterclaim,
including the issues of its variable
costs, whether the plant had
included a large granulation pan from the outset and many other
ancillary issues and I decline to
do so.
77.
In the circumstances, the
Defendant’s counterclaims are dismissed.
78.
This brings me to the Plaintiff’s
claims for (1) payment of the sum of R1 604 150, alternatively R1 334
254 being repayment
of advance payments made by the Plaintiff to the
Defendant for the pelletizing of limestone and gypsum but in respect
of which
advance payments, product was not delivered by the
Defendant; (2) payment of the sum of R945 181, being the value of raw
material
supplied by the Plaintiff which was used by the Defendant,
but which resulted in 1 279 MT of oversized pellets which were
incapable
of being reworked or resold and rendered wasted and (3)
payment of the sum of R83 488 being the amount outstanding in respect
of
bags supplied by the Plaintiff to the Defendant for which the
Defendant undertook to pay, but failed to do so.
79.
In respect of the first claim,
whether the Plaintiff is entitled to repayment of R1 604 150,
alternatively R1 334 254 (the
Plaintiff's calculations being set
out in annexure "POC2" and "POC2.1" to its
Particulars of Claim), the alternative
amounts claimed are dependent
on whether the prior agreement was replaced and/or subsumed by the
IMA as contended by the Plaintiff,
or whether it remained a separate
agreement to the IMA as contended by the Defendant and therefore
whether certain of the advance
payments were in fulfilment of the IMA
(which took over the prior agreement) or whether they were in
fulfilment of only the prior
agreement separately from the IMA –
in which event the Plaintiff would only be entitled to repayment of
the lesser amount
of R1 334 254.
80.
The Plaintiff of course relies on
clause 19.5 of the IMA which states as follows:
“
[T]his
agreement constitutes the entire Agreement among the Parties with
regards to the subject matter in this Agreement and any
previous
Agreements, understandings and negotiations on that subject matter
cease to have any effect.
”
81.
Whether the initial agreement ceased
to have any effect and was effectively replaced by the IMA is
dependent on whether the “subject
matter” of the
respective agreements is the same. The subject matter of the prior
agreement was the pelletization by the
Defendant of the Plaintiff’s
limestone raw material into prills. The subject matter of the IMA was
similarly the pelletization
by the Defendant of the Plaintiff’s
limestone and gypsum raw material into prills. The subject matter is
therefore exactly
the same (with the addition of gypsum), albeit that
the volumes and sizes of the prills may have differed. Therefore, the
prior
agreement ceased to have effect on the conclusion of the IMA on
1 December 2015 and that is the correct interpretation of clause
19
of the IMA. Any product produced by the Defendant after 1 December
2015 on behalf of the IMA could only have been in terms of
the IMA
and not the prior agreement. The Plaintiff is not therefore entitled
to repayment of any advance payments it made prior
to 1 December 2015
since its claim was exclusively based on the IMA and not any prior
agreements.
82.
What then does one make of the fact
that the Plaintiff kept open the purchase order for 24000MT placed
pursuant to the prior agreement?
It merely means that the remainder
of the purchase order was regulated by the terms of the IMA and
became an order in terms of
the IMA for the remainder of that
purchase order. The evidence was clear that the purchase order number
was maintained only because
it was easier in the system to maintain
that order number rather than create a whole new order for the
balance of the tonnage not
delivered as at 1 December 2016. It was
therefore merely an internal accounting issue.
83.
Lastly in regard to the Plaintiff’s
first claim it is necessary to deal with the Defendant’s
contention that there is
no provision in the IMA for repayment of
advance payments made in respect of which no product was produced and
made available to
the Plaintiff. The Defendant contends that the
Plaintiff is not entitled
per se
to a repayment of advance payments for which it did not receive
product. The Defendant contends that if the Plaintiff's cause of
action is contractual, there is no express term in the IMA providing
for such a repayment and that to the extent that the Plaintiff
relies
on an implied or tacit term, the Plaintiff has failed to plead such a
term and has further failed to lead evidence to satisfy
the so-called
"bystander test" for importing such a term
ex
consensu
.
84.
It
is trite that on the cancellation of a contract due to breach or
anticipatory breach (repudiation), a party has a right to contractual
restitution of that which it has performed by not received the
countervailing performance from the breaching party
[23]
.
At first blush it would seem that the advance payments by the
Plaintiff can be recovered as a contractual restitution claim.
However,
Mr
Strydom
for the Defendant contended that those cases were distinguishable
since in those cases, the right to contractual restitution arose
on
the cancellation of a contract due to breach, whereas in this matter,
the Plaintiff did not rely on a cancellation of the contract
due to a
breach by the Defendant but rather on the termination of the contract
due to effluxion of time. Insofar as I found that
the Defendant’s
purported cancellation of the IMA due to a breach by the Plaintiff
could not be upheld and insofar as the
IMA had terminated by
effluxion of time on 31 January 2017, before the Plaintiff exercised
its election to accept the Defendant’s
repudiation (i.e. its
purported cancellation of the IMA) in February 2017, it would mean
that the IMA terminated by effluxion of
time. In other words, the IMA
terminated by the mutually agreed date of 31 January 2017.
85.
The question is then whether a party
who has made advance payments in expectation of countervailing
performance from the other party,
can claim restitution of its
advance payments on the termination of the agreement by effluxion of
time without relying on a tacit
term to that effect. In
Ace
Motors v Barnard
1958 (2) SA 534
(T) at
537F-G, Dowling J held as follows in this regard:
“
The
authorities quoted by Mr. Pienaar and certain others, seem to me
clearly to establish that on an agreed rescission of a partly
executed contract of sale the seller must refund such of the purchase
price as the purchaser has paid, if it is not otherwise agreed.
In Combrinck v Maritz,
1952 (3) SA 98
(T), the head-note reads: -
'When
a contract of purchase and sale is mutually cancelled and one party
has performed his part of the original contract then,
if he is the
purchaser, he is entitled to recover the price paid.'
”
86.
This finding was upheld by the
Appellate Division in
Van den Berg v
Tenner
1975 (2) SA 268
(A) at 274H,
where it was held as follows (per Botha JA):
“
Een
van daardie gevolge was die terugbetaling aan eiser van die bedrag
van R10 000 wat hy as deel van die koopsom ingevolge die
gekanselleerde ooreenkoms betaal het, want dit is duidelik dat waar
partye na sluiting van 'n ooreenkoms weer ooreenkom om uit
die eerste
ooreenkoms terug te tree, en een of albei van die partye reeds
gedeeltelik onder die eerste ooreenkoms gepresteer het,
daar uit die
tweede ooreenkoms, tensy anders ooreengekom, 'n verpligting ontstaan
tot teruggawe van dit wat reeds gepresteer is.
(Ace
Motors v Barnard,
1958 (2) SA 534
(T)).
”
87.
And at 277F:
“
Myns
insiens was eiser geregtig om die terugbetaling aan hom van die
bedrag van R10 000 te vorder bloot op grond van die kansellasie
van
die ooreenkoms van 12 Junie 1970 en die onmoontlikwording, as gevolg
van die kansellasie van die twee ooreenkomste van 19 November
1970,
van die wyse en tyd waarop terugbetaling van daardie bedrag in die
ooreenkoms van 2 Desember 1970 beding is. Dit was vir
eiser dus nie
nodig om op 'n stilswyende beding te steun nie.
”
(my emphasis)
88.
I therefore find that the Plaintiff
has adequately pleaded a case for the restitution of its advance
payments made under a contract
which expired by effluxion of time.
89.
The Defendant however correctly
contends that since the Plaintiff seeks to enforce its rights under
the IMA and not under the prior
24 000 MT order in terms of the prior
agreement, it is clear that it cannot take into account advance
payments made under the previous
agreement and therefore the claim
for the sum of R1 604 105 as set out in annexure “POC2”
to the Plaintiff’s
particulars of claim (which includes
payments prior to the conclusion of the IMA on 1 December 2015),
cannot be granted. On this
basis, the Plaintiff is only entitled to
recover pre-payments made from 1 December 2015, which is the period
governed by the IMA,
the amount of which is R1 334 254, as set out in
annexure "POC2.1" to the Plaintiff’s particulars of
claim.
90.
In
its second claim, the Plaintiff claims the sum of R945 181 being the
value of 1 279 tons of pellets which were allegedly
incapable of
being reworked or resold. This is calculated at a cost of R739
per ton. The evidence of Mr Behrens and
Mr Ziemerink was led in
this regard.
91.
As explained by Mr Klue in his
evidence, there is a difference between oversized pellets (generated
at the start of a production
session) and waste, being the residue in
the granulation pan at the end of a production session.
92.
There was no contractual obligation
placed upon the Defendant in the IMA to rework oversized material.
In any event, the oversized
pellets had to be blended with fresh raw
material in a ratio of 3%-6% of the oversized pellets and 94%-97% of
fresh material.
Furthermore, in terms of clause 3.2.1.4 of the
IMA "production shrinkage" of 3% in the case of limestone
was allowed
and the Defendant was not responsible for this production
shrinkage.
93.
In order to discharge its onus in
respect of proving its second claim, the Plaintiff had to prove:
93.1.
That some granules produced under
the IMA were oversized, in other words, more than the permissible 2mm
– 6mm in size. However,
it was common cause that there was
indeed oversized product as recorded in the monthly stock-sheets;
93.2.
That some of the oversized pellets
were indeed not re-workable. This would have required expert expert
evidence, yet the Plaintiff
relied solely on Mr Ziemerink's
inspection and subjective opinion and he was not qualified as an
expert in this regard;
93.3.
The exact volume of oversized
pellets which was not re-workable, which would also require expert
evidence. Again, the Plaintiff
merely led the evidence of Mr
Ziemerink who conducted a physical inspection and counted the number
of bags which in his subjective
opinion were not re-workable;
93.4.
That the volume of oversized product
which was not re-workable falls outside the production shrinkage
margin of 3% of the total
raw materials supplied. However, 3% of the
total volume of 20 899 tons of raw material supplied by the Plaintiff
in the period
of the IMA amounts to 627 tons. This must be deducted
from the Plaintiff's claim of 1 279 tons;
93.5.
the oversized product did not result
from non-complying raw material. There was no such evidence and
particularly no expert
evidence.
93.6.
the Plaintiff followed the
contractually prescribed rejection procedure in clauses 3.2.3.8 –
3.2.3.10 of the IMA in respect
of non-conforming product. There was
no evidence that such procedures were indeed followed by the
Plaintiff;
93.7.
the Plaintiff had to prove the cost
of the raw material that became wasted. Mr Behrens testified that the
cost price was R739 per
ton and that the proof was in the Plaintiff's
system. No documents were discovered or proved in evidence to
substantiate this cost
price. Bearing in mind that most of the
raw material came from the Plaintiff's own quarry at Port Shepstone
and had to be
transported to Gauteng, the cost is not a readily
apparent figure.
94.
The Plaintiff led insufficient
evidence to prove its claim in this regard and I was not satisfied
that it was proved that the material
was in fact all wasted or what
proportion was wasted and the value of the remaining still usable
material.
95.
In the circumstances, I find that
the Plaintiff did not prove its second claim and this claim must be
absolved from the instance.
96.
In its third claim, the Plaintiff
claims the amount of R83 488 as the amount still owing in terms of an
agreement between the parties
that the Defendant would pay for
missing bags. Payment was to take place in three instalments of
which only the first instalment
was effected. The Defendant has
accepted liability for the of R83 488 but relied on the set-off as
provided for in Rule 22(4) of
the Uniform Rules of Court on the basis
that the Plaintiff’s third claim would be extinguished by the
Defendant's counterclaim.
However, since the Defendant’s
counterclaims are dismissed, there is no viable defence raised to the
Plaintiff’s third
claim and in the circumstances the Plaintiff
is entitled to payment of R83 488.
97.
In respect of costs, there is no
doubt that a large proportion of the trial was devoted to evidence in
relation to the Defendant’s
counterclaim. This counterclaim has
been unsuccessful and there is no reason that the Defendant should
not pay the Plaintiff’s
costs of successfully defending the
counterclaim. The Plaintiff has also been successful in its first and
third claim but has had
absolution granted in respect of its second
claim. On a conspectus of the whole matter, the Plaintiff has been
substantially successful
and should be awarded the cost of the its
action and of its defending of the counterclaim.
98.
In the circumstances, the following
order is made:
98.1.
The Defendant is to make payment to
the Plaintiff of the amount of R1 334 254.00;
98.2.
The Defendant is to make payment to
the Plaintiff of interest
a tempore
morae
on the amount of R1 334 254,
at the legally prescribed interest rate of 10,25% from date of
demand, being 14 February 2017,
to date of final payment in full;
98.3.
The Defendant is to make payment to
the Plaintiff of the amount of R83 488.00; The Defendant is to make
payment to the Plaintiff
of interest
a
tempore morae
on the amount of R83
488.00, at the legally prescribed interest rate of 10,25% from date
of service of summons to date of final
payment in full;
98.4.
The Defendant’s counterclaims
are dismissed;
98.5.
The Defendant is to make payment of
the Plaintiff’s costs of action and the costs of defending the
Defendant’s counterclaims
as taxed or agreed on scale C of Rule
67A read with rule 69 of the High Court Rules.
KAIRINOS AJ
Acting Judge of the
High Court
Gauteng Division,
Johannesburg
For the Plaintiff:
Adv JG Smit
Instructed by:
NLA Inc Attorneys
For the Defendant:
Adv
F Strydom
Instructed by:
Nolte Incorporated
Attorneys
Dates of Hearing: 22 –
26 April 2024; 1 and 2 July 2024 and 13, 14, 16 and 17 January 2025
Judgment date: 31 January
2025
This
judgment is delivered by upload to the digital data base of the court
and by transmission email to the parties on 31 January
2025. The
judgment is deemed to be delivered on 31 January 2025.
[1]
MEC,
Department of Public Works and Others v Ikamva Architects and Others
2022
(6) 275 (ECB) at p
ar
[41]. See also
University
of Johannesburg v Auckland Park Theological Seminary and
Another
2021
(6) SA 1 (CC)
[2]
KPMG
Chartered Accountants (SA) v Securefin Ltd and Another
2009
(4) SA 399
(SCA)
[3]
Clause 3.1.1.1.
[4]
Clause 3.1.1.2. (The term "Raw Material" is
defined as
ultrafine limestone or similar material used to manufacture the
Pelletized Product, which may include gypsum powder").
[5]
Clause 3.1.1.4.
[6]
Clause 3.1.1.3.
[7]
Clause 3.1.1.3.1.
[8]
Clauses
3.2.1.1 and 3.2.1.2.
[9]
Clause
3.2.1.4.
[10]
Clauses
3.2.1.4.
[11]
Clauses
3.2.1.6 and 3.2.1.7.
[12]
Clause
3.2.1.9.
[13]
Clause
3.2.1.10.
[14]
Clause
3.2.2.
[15]
Clause
3.2.3.
[16]
Clause
3.2.3.8.
[17]
Clause
3.2.3.9.
[18]
Clause
3.2.3.10.
[19]
Clause
3.2.3.12.
[20]
Clause
3.2.3.14.
[21]
Clause
3.3.
[22]
Clause
2.1.11 of the IMA
[23]
See
Baker
v Probert
1985 (3) SA 429
(A) at 438I-439C and
Tweedie
and Another v Park Travel Agency (Pty) Ltd t/a Park Tours
1998 (4) SA 802
(W) at 807B-D
sino noindex
make_database footer start
Similar Cases
Ndwammbi N.O and Others v Sematra (Pty) Limited and Others (2020/42224) [2025] ZAGPJHC 939 (25 September 2025)
[2025] ZAGPJHC 939High Court of South Africa (Gauteng Division, Johannesburg)99% similar
WIA Investments SA (Pty) Limited v Robile and Others (2025/012813) [2025] ZAGPJHC 119 (17 February 2025)
[2025] ZAGPJHC 119High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corpoation (Pty) Ltd and Others v Redpath Mining South Africa (Pty) Ltd and Others (Application for Leave to Appeal) (57639/2021) [2024] ZAGPJHC 933 (19 September 2024)
[2024] ZAGPJHC 933High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Imbani Minerals Proprietary Limited v Standard Bank of South Africa Limited and Others (2025/132324) [2025] ZAGPJHC 843 (21 August 2025)
[2025] ZAGPJHC 843High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Gidigidi obo M.B. v Road Accident Fund (22118/2019) [2025] ZAGPJHC 190 (14 February 2025)
[2025] ZAGPJHC 190High Court of South Africa (Gauteng Division, Johannesburg)99% similar