Case Law[2025] ZAGPJHC 754South Africa
Umzinyathi District Municipality v Fusion Guarantees (Pty) Ltd (23247/2019) [2025] ZAGPJHC 754 (22 May 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
22 May 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 754
|
Noteup
|
LawCite
sino index
## Umzinyathi District Municipality v Fusion Guarantees (Pty) Ltd (23247/2019) [2025] ZAGPJHC 754 (22 May 2025)
Umzinyathi District Municipality v Fusion Guarantees (Pty) Ltd (23247/2019) [2025] ZAGPJHC 754 (22 May 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_754.html
sino date 22 May 2025
IN THE HIGH COURT OF SOUTH AFRICA
GAUTENG LOCAL DIVISION,
JOHANNESBURG
CASE
NO
: 23247/2019
DATE
:
22-05-2025
(1) REPORTABLE: NO.
(2) OF INTEREST TO OTHER JUDGES:
NO.
(3) REVISED.
DATE
:22 MAY 2025
In the matter between
UMZINYATHI DISTRICT
MUNICIPALITY
Plaintiff
and
FUSION GUARANTEES (PTY)
LTD
Defendant
JUDGMENT
DE
SOUZA-SPAGNOLETTI, AJ
:
1.This matter centres around a
Performance Guarantee issued by the defendant in favour of the
plaintiff, as found on CaseLines at
section 1 page 15. It is noted
that the Guarantee as issued by the defendant, cites the plaintiff as
the employer and Soundrite
Construction and Plant Hire as the
contractor. The works described in the Guarantee, are stated to be
works under contract T2015-03
with the description of the works
describing construction of a raw water steel pipeline from the
Gaywood area to the Greyton Water
Works. The dispute itself hinges
around the defendant’s liability or otherwise under the
Performance Guarantee with material
questions to be answered as to
whether the plaintiff has complied with what is necessary to call up
payment on the Guarantee.
2.Although, and while not specifically
pleaded, there is alleged non-compliance of the plaintiff with
paragraph 4 of the Guarantee
which has been raised in the defendant’s
heads of argument in addition to the alleged non-compliance with
paragraph 5 of
the Guarantee. Plaintiff contends that it has complied
with all that is required under the Guarantee while defendant
contends that
it is not liable. The parties at commencement of the
trial agreed that there are various issues that are not in dispute
and which
are set out in paragraph 3 of the 2023 practice note found
at CaseLines, section 6, item 2. There is also a further practice
note
found in section 11 of CaseLines. The Court was advised that the
parties had scrapped this particular practice notice at commencement
of the trial.
3.Liability under these performance
guarantees is no stranger to this Court with courts having come
across them repeatedly and there
is definitely, ample authority in
relation thereto. Both parties did a good job of articulating the
important principles relevant
to this matter, this both in the heads
of argument and in the list of authorities that were provided. The
Court is appreciative
of these efforts.
4.While not all strictly relevant to
these proceedings, the Court was given the opportunity to peruse all
the case law that was
placed before it. The Court was also afforded
the opportunity of perusing the very recent Supreme Court of Appeal
judgment of
Set Square Developments (Pty)
Limited V Power
Guarantees and Vahva Construction
which was handed down recently
on the 20
th
of May 2025. It is in consideration of all of
the above that this judgment is delivered.
5.The Court will start by dealing with
the issues which were found not to be in dispute and as stated
previously, most of which
was set out in the practice note of 2023
and in paragraph 3. The Court will read these into the judgment as
follows. Paragraph
3 of the practice note states that:
3. The issues
not in dispute are the following,
3.1 The citation of the
parties;
3.2 The total value of the
contract awarded by the plaintiff to the Soundrite Construction and
Plant Hire, being R43 556 513.60;
3.3 That an allowance for
the contingency of 10 percent amounting to R4 356 651.36,
an escalation of eight
percent amounting to R3 485 312.09 to be
added to the total value of the contract referred to above at the
discretion of the
plaintiff;
3.4 That annexure B to the
plaintiff’s summons is indeed a copy of the Performance
Guarantee with Guarantee number
FUS501583JHB, issued by the defendant
to Soundrite Construction and Plant Hire pursuant to the conclusion
of the agreement between
the plaintiff and Soundrite.
3.5 The plaintiff has
presented an original of the aforesaid Performance Guarantee at the
defendant’s attorney’s
offices for inspection;
3.6 That Annexure E1 to the
plaintiff’s summons is indeed a copy of the first written
demand by the plaintiff to the
defendant for payment in terms of
paragraph 5 of the aforesaid Performance Guarantee dated 6 June 2015.
3.7 That no payment or
undertaking to pay was made by the defendant to the plaintiff in
terms of the aforesaid Performance
Guarantee.
3.8 That the defendant’s
liability in terms of the Performance Guarantee is autonomous from
the underlying contract,
and that the defendant’s obligation to
make payment is to be construed strictly in terms of the Performance
Guarantee.
6.In addition to these issues which
were not in dispute, the parties agreed on further common cause facts
or issues which were not
in dispute and which were added.
7.Firstly, there was no admission by
the defendant that the plaintiff cancelled the contract with
Soundrite and concluded a new
contract with the joint venture.
8.Secondly, it was admitted by the
defendant that the first letter of demand, being Annexure E1 to
plaintiff particulars of claim
was in fact delivered to the
defendants.
9.Lastly, that there was a certificate
of completion issued to the joint venture, found at Annexure Plea1 to
defendant’s plea.
Plaintiff did not dispute that the
certificate of completion is what it purports to be.
10.Plaintiff closed its case without
leading any evidence, relying instead on the various admitted or
common cause facts, and the
balance of documentation. The plaintiff
contended that it was entitled to judgment on this basis.
11.The defendant, subsequent to
initially noting its intention to apply for absolution from the
instance, changed its mind and instead
also closed its case without
leading any evidence when the hearing resumed on the 22
nd
of May 2025.
12.The issues in dispute, on listening
to the parties and on perusal of the heads of argument and all the
papers in the matter,
crystalise somewhat and there were issues of
law which were required to be determined.
13.The Court will start by noting
there to be two distinct trigger events to payment becoming due and
payable under the Guarantee.
The first is set out in paragraph 4 of
the Guarantee, and the second is set out in paragraph 5. It is
patently clear to this Court
that these two paragraphs operate
independently of each other and in the case before this Court, it is
very clear that the events
triggering liability of the defendant as
claimed by the plaintiff are based on those set out in paragraph 5 of
the Guarantee.
14.Nowhere in the Guarantee is it
stated, nor is it implied that these two paragraphs are connected in
any way or that the requirements
set out in the one paragraph are
dependent upon compliance with that set out in the other.
In this regard the defendant’s
contention that the plaintiff failed to comply with paragraph 4 of
the guarantee, does not
figure in the Court’s judgment. The
plaintiff was simply not obligated to comply with paragraph 4 in the
face of compliance
with paragraph 5. Paragraph 5 cannot be considered
to be “additional compliance” necessary over and above
that which
is set out in paragraph 4. Compliance with paragraph 5 of
itself triggers liability under the Guarantee. It should also be
noted
that non-compliance with paragraph 4 as a defence is not
specifically pleaded.
15.The final payment certificate and
the issues raised in relation thereto, again do not find application
here. It pertains to a
contract which in no way falls within the
ambit or operation of the particular Guarantee which forms the basis
of the dispute before
Court. The Guarantee before Court, and this
will be stated more than once in this judgment, is autonomous and
exists completely
independently.
16.It is noted, and I think I noted it
before, that the parties provided constructive and helpful authority
in this matter all of
which has been considered in the formulation of
this judgment.
17.The Court is going to start with
the first issue, relating to whether the plaintiff is obliged to
prove a cancellation of the
contract with Soundrite. The Court would
like to read the requirements of paragraph 5 of the Performance
Guarantee into the record,
and these state the following:
“
Subject to
the guarantor’s maximum liability referred to in 1, the
Guarantor undertakes to pay the employer the guaranteed
sum of the
full outstanding balance upon receipt of a first written demand from
the employer to the Guarantor at the Guarantor’s
physical
address calling up this Performance Guarantee, such demands stating
that:
5.1 The Contract has been
terminated due to the Contractor’s default and that this
Performance Guarantee is called
up in terms of 5;or
5.2 A provisional or final
sequestration or liquidation order has been granted against the
Contractor and that the Performance
Guarantee is called up in terms
of 5; and
5.3 The aforesaid written
demand is accompanied by a copy of the notice of determination and or
the provisional final
sequestration order, and/or the provisional
liquidation order.”
18.It is clear that paragraph 5.2 in
relation to this Guarantee does not find application in the matter
before Court. The Court
again emphasises the principle of autonomy in
that it is important in the context of these Guarantees, with the
case law being
amply clear and with both parties making reference
thereto.
19.The Guarantee operates
independently from any underlying contracts. To suggest that the
contract was not cancelled as alleged
by the defendant, is to the
Court’s mind, by necessity to claim fraud on the part of the
plaintiff. The plaintiff has, in
compliance with paragraph 5 of the
Guarantee, confirmed cancellation of the contract on the basis of
default of the contractor.
Further, a certificate of completion which
is to be found on CaseLines at section 9, item 32 would to the mind
of this Court, make
it abundantly clear that the contract was indeed
cancelled as the work in question, which is described similarly in
this certificate,
was performed by a different contractor, namely
Cerimele-Mantombana joint venture. The certificate refers to a
different contract
number, that being T2017-11. The reasonable,
rational conclusion that the Court can reach, bearing in mind the
fact that the different
contract referred to therein describes the
same work as that described under contact T2015-03 for which the
Performance Guarantee
was issued - the only conclusion the Court can
reach in this regard is that the certificate of completion relates to
another contract
and in relation to work performed by another
contractor. This is supportive of the contention by the plaintiff
that the contract
was indeed cancelled. This is now stated for the
sake of completeness, that the Court again must reinforce the
recognition of the
autonomy of the Guarantee itself, and the
Guarantee itself does not require proof of cancellation.
20.To the Court’s mind, the
defendant’s scope to dispute the cancellation would be limited
to a claim of fraud on the
part of the plaintiff, fraud which is most
certainly not pleaded and at the request of clarification by this
Court, the defendant
confirmed is not claimed. The Court cannot take
the inquiry any further in relation to this.
21.Moving on to the next issue in need
of address or in need of finding, is whether the defendant was
released from liability when
the completion certificate was issued or
whether this can result in defendant escaping liability on this
Performance Guarantee.
Defendant contends that the Completion
Certificate issued to another contractor, confirming completion of
work performed under
a different contract, releases it from
liability. The Court has already noted that the Completion
Certificate pertains to a contract
number T2017-11, a different
contract to that which the Performance Guarantee in question pertains
to. In this regard, it is somewhat
mischievous of the defendant to
then suggest that the one can have a bearing on the other. The Court
simply cannot accept this
to be the case.
22.If one was to follow this trail of
thought through to its conclusion, it would mean that any employer
constrained to cancel a
contract due to the default of a contractor,
and who then subsequently employs an alternative contractor to
complete the uncompleted
work, would be precluded from claiming on a
Performance Guarantee based on the defaulting contractor. The Court
can find no logic
in this train of thought. It flies in the face of
the very purpose of a Performance Guarantee and what it seeks to
achieve. In
any situation where a contractor defaults and the slack
is then picked up by another contactor at a later stage, the employer
would
then be unable to call up performance or should I say call up
payment on a Performance Guarantee. The Court cannot accept such
notion and finds that the Completion Certificate as uploaded to
CaseLines has no bearing on the defendant’s liability under
this Guarantee in question.
23.In relation to the issue of the
Performance Guarantee being returned to the defendants, the Court
finds that there is sufficient
compliance on the part of the
plaintiff to satisfy what is required in order for it to call up
payment on the Guarantee. In this
regard the Plaintiff did two
things. Firstly, it tendered return of the Guarantee and secondly, it
returned the Guarantee to the
defendant’s offices for
inspection or the defendants attorneys for inspection. While tender
of return of the Guarantee may
not satisfy the requirements under
paragraph 5, presentation by the plaintiff of the Guarantee at the
offices of the defendant
or defendants attorneys most certainly
constituted a return. The defendant was already placed in possession
of a copy of the document,
and it was returned to its offices albeit
for inspection. The Court on considering the papers in the matter,
the heads of argument
by the parties, and the arguments presented,
finds that such return satisfies what is required under paragraph 9
of the Guarantee,
and what is required for payment under the
Guarantee.
24.The next issue, relating to the
contract value as mentioned in paragraph 40 of the defendants’
heads of argument needs
to be addressed by this Court. The Court
again reinforces that the Performance Guarantee operates
independently of the underlying
contracts. This Court is not placed
to delve into the underlying contract. It is constrained to determine
defendant’s liability
based on the Guarantee, independently.
Again, argument that the Guarantee refers to a different contract or
work cannot be sustained.
The works referred to in the Guarantee
relate to contract T2015-03. It is pertinent to note, and the Court
does note, that the
letter of award found under the pleadings section
001 on CaseLines as item 3, being Annexure A1, similarly states the
contract
number to be T2015-03, and lists the same work as follows,
“
Construction
of a 10 kilometre long 450 by 450 millilitre diameter, raw water
steel pipeline from Gaywood area to Greytown Water
Works.”
25.There can be absolutely no
confusion or doubt that the award and the work contracted is the same
contract for which the Guarantee
was issued. The Court simply cannot
be placed to delve into what may or may not have transpired or agreed
to result in the Guarantee
sum under the Guarantee being different to
that set out on the award.
26.The Court cannot find support for
the defendant’s contention that there is any uncertainty or
ambiguity in this matter.
The Court further cannot find on the basis
of any defences or contentions put forward by the defendant that it
is not liable under
this Guarantee.
27.In relation to costs, the Court
notes the issue for decision in this matter, or the issues for
decision in this matter are not
new, nor are they overwhelming
complicated with these types of performance guarantees having come
before the Court repeatedly.
The Court does not go so far as to
suggest that senior counsel was misplaced. The contentions of the
Court are reflected in the
award made for costs.
28.After careful consideration of the
heads of argument and the arguments put forward by both plaintiff and
defendant, after consideration
of the case law and after perusal of
the documentation that has been made available to this Court, the
Court makes the following
order,
1
The defendant shall pay to the plaintiff
the amount of R5 140 848.61, such payment to be made within 7
days of delivery of
the original Performance Guarantee to the
defendant.
2
Interest is payable on the aforesaid amount
to be calculated at a rate of 10.25 percent per annum
a
tempore morae
to the date of payment.
3
The defendant shall pay the costs of suit
on scale B, save for those relating to the use of senior counsel
which shall be payable
on scale C.
That concludes the judgment of this
Court.
DE SOUZA-SPAGNOLETTI, AJ
JUDGE OF THE HIGH COURT
SIGNATURE
DATE
: 12 JUNE 2025
sino noindex
make_database footer start
Similar Cases
Umvelo Risk Management (Pty) Ltd v Sebogodi and Others (183698/2025) [2025] ZAGPJHC 1214 (21 November 2025)
[2025] ZAGPJHC 1214High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Umzwilili Environmental Solution v Rockwood Fund 1 GP (Pty) Ltd (2025/101302) [2025] ZAGPJHC 704 (21 July 2025)
[2025] ZAGPJHC 704High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Umhlaba Erf 1 Properties CC v Shell Downstream South Africa (Pty) Ltd (03929/2019) [2025] ZAGPJHC 13; [2025] 2 All SA 620 (GJ) (14 January 2025)
[2025] ZAGPJHC 13High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Imithetho Labour Law CC ta Labour Law Distributors v Van Eck and Others (2024/102799) [2024] ZAGPJHC 1252 (2 December 2024)
[2024] ZAGPJHC 1252High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyathemba Project Management and Development (Pty) Ltd v Weinberg (22984/202) [2024] ZAGPJHC 837 (5 August 2024)
[2024] ZAGPJHC 837High Court of South Africa (Gauteng Division, Johannesburg)99% similar