Case Law[2025] ZAGPJHC 955South Africa
Mulebeke and Others v Cest La Vie Construction and Others (2025/145152) [2025] ZAGPJHC 955 (30 September 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
30 September 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 955
|
Noteup
|
LawCite
sino index
## Mulebeke and Others v Cest La Vie Construction and Others (2025/145152) [2025] ZAGPJHC 955 (30 September 2025)
Mulebeke and Others v Cest La Vie Construction and Others (2025/145152) [2025] ZAGPJHC 955 (30 September 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_955.html
sino date 30 September 2025
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED. NO
DATE
22 September 2025
CASE
NO:
2025-145152
In the matter between:
JAMES
ALVIN WILLY MULEBEKE
First
Applicant
JOYCE
NANSEMBE MULEBEKE
Second
Applicant
BHEKAYIPHI
BENEDICT NZUZO MAPHUMULO
Third
Applicant
ADELADE
NOTHANDO MAPHUMULO
Fourth
Applicant
and
CEST
LA VIE CONSTRUCTION (PTY) LTD
First
Respondent
MICHAEL
GRAHAM KING
Second
Respondent
COMPLEX
MANAGEMENT OF DERBY VILLAS
ESTATE
(HOMEOWNERS ASSOCIATION)
Third
Respondent
CHRISTOPHER
RICARDO
Fourth
Respondent
SCHEPTER
SECURITY COMPANY
Fifth
Respondent
JUDGMENT
This judgment is
handed down electronically by circulation to the parties’ legal
representatives by email and by being uploaded
to CaseLines. The date
for hand down is deemed to be 22 September 2025.
MAHON
AJ:
# Introduction
Introduction
[1]
This is an urgent application in which the applicants, who are the
registered owners of two stands in the Derby Villas Estate,
Johannesburg, seek relief arising from building agreements concluded
with the first respondent, Cest La Vie Construction (Pty)
Ltd. They
ask the court to confirm that those agreements have been validly
cancelled and to grant interdictory relief securing
their and their
nominated contractors’ free and undisturbed access to the
properties so that building work may proceed under
their own
management.
[2]
The respondents oppose the application. They contend that the
building agreements remain in force, that the applicants
did not
comply with the contractual provisions requiring a prior notice to
remedy breach before cancellation, and that the applicants
have not
shown any unlawful denial of personal access to their properties,
only that entry by unauthorised contractors has been
regulated.
[3]
During the hearing the court raised, and counsel addressed, a further
question: whether the statements on which the applicants
rely as
misrepresentations are, on a proper characterisation, promises of
future performance rather than statements of existing
fact. That
question matters because a promise that something will be done
engages the law of contract and breach, whereas a misrepresentation
concerns a false statement about an existing state of affairs and can
support rescission without prior notice to remedy breach.
[4]
The application accordingly turns on three broad issues: whether the
applicants’ purported cancellations of their
building
agreements were legally effective; whether, in the light of the
nature of the statements relied on, the alleged misrepresentations
entitled them to bypass the contractual notice requirement; and
whether the facts justify the final interdictory relief sought
to
compel access to the properties.
#
# Background Facts
Background Facts
[5]
The applicants are the registered owners of two stands in the Derby
Villas Estate, Johannesburg. The first and second
applicants own erf
2971, and the third and fourth applicants own erf 2996. Each pair
concluded a written building agreement with
the first respondent,
Cest La Vie Construction (Pty) Ltd, represented by its sole director,
the second respondent. The agreements
obliged the first respondent to
construct homes on the stands for agreed prices and within specified
periods.
[6]
For the first and second applicants, the history is protracted. They
initially signed a building agreement in April 2020,
which was
superseded by a second agreement dated 7 August 2023. Their stand was
registered in April 2024. They complain that construction
progress
was slow and beset by problems, including a collapse of part of a
wall and concerns over the first respondent’s
registration with
the National Home Builders Registration Council (NHBRC). Although
payments were made and dates for the houses
to be complete were
repeatedly promised, the works remained far from complete by
mid-2025.
[7]
The third and fourth applicants concluded their building agreement on
7 May 2024. Their site was likewise registered with
the deeds office
later in 2024. They too experienced lengthy delays and raised
concerns about the first respondent’s NHBRC
compliance. Despite
additional payments for agreed variations, construction scarcely
advanced beyond the foundations and was nowhere
near complete.
[8]
By early July 2025 both sets of applicants had lost confidence in the
first respondent’s performance. Acting through
their attorneys,
they each addressed letters purporting to cancel their building
agreements. The letters alleged persistent breaches,
including
failure to have the houses complete within the agreed periods,
failure to remedy defective work, and misstatements about
NHBRC
registration. No prior notice to remedy breach was given in terms of
clause 15.3 of the agreements, which requires written
notice
identifying the default and affording 21 days to remedy it.
[9]
The first respondent, through its director, disputed the validity of
the cancellations and insisted that the agreements
remained in force.
It warned that owners who attempted to engage alternative contractors
without its consent would be prevented
from doing so and might face
interdict proceedings. Security guards employed by the fifth
respondent were instructed to deny access
to contractors not
authorised by the first respondent. The applicants allege that this
instruction extended to them personally,
though the respondents
maintain that owners were never barred, only their contractors.
[10]
The applicants contend that they have suffered continuing harm in the
form of delayed ability to have their homes complete
and ready for
occupation, financial losses on bonds and rental, and personal
hardship to their families. They therefore seek confirmation
of the
cancellations and interdictory relief to ensure that they and their
contractors may access the properties without interference.
[11]
The respondents deny that any valid cancellation has occurred. They
emphasise that the agreements contain a clear notice-to-remedy
clause, that NHBRC registration was in place, and that the complaints
of misrepresentation are not borne out. They further dispute
that the
applicants have been unlawfully excluded from their own properties.
#
# Submissions and Exchanges
at the Hearing
Submissions and Exchanges
at the Hearing
[12]
The matter was argued as an urgent application. At the outset, the
respondents challenged the appropriateness of entertaining
the
application urgently, relying primarily on alleged defects in service
and the absence of an explanation in the founding papers
for
non-compliance with Rule 6(12)(b). It was pointed out that the fourth
respondent initially received only a WhatsApp copy of
the notice of
motion and only later obtained the founding papers by way of a
Dropbox link. Counsel argued that this fell short
of the requirement
that an applicant seeking urgent relief must set out fully the
reasons for any failure to effect proper service,
and that the court
ought to strike the matter from the roll or, at the least, reserve
the question of costs to reflect the irregularities.
[13]
The court engaged extensively on the issue of urgency. It was
observed that, assuming the correctness of the applicants’
version for this purpose, the deprivation of access to their own
properties amounted to an ongoing harm that justified urgent
intervention. The court noted that all parties who wished to
participate had in fact received the papers and were represented, and
questioned whether any real prejudice had been caused by the alleged
procedural defects. Counsel for the respondents accepted that
their
clients were able to file answering papers and argue the merits, but
maintained that the lack of formal service should not
be overlooked,
cautioning that a precedent might be set which would undermine the
discipline required by Rule 6(12)(b).
[14]
In my view, this concern should not carry weight in the present
matter. All respondents who wished to be heard were fully
apprised of
the application in time to instruct attorneys and file detailed
answering papers. The substance of the rule, namely
to ensure that
respondents are informed and able to participate, was therefore met.
This was not a case where non-compliance undermined
the purpose of
service or caused real prejudice. It was instead one where the
practical realities of urgent motion practice justified
condonation
for what were, in context, formal defects in an application where
ongoing harm can only be arrested through an urgent
hearing.
[15]
Argument then turned to the merits. The respondents’ principal
submission was that the building agreements remain
of full force and
effect because clause 15.3 of each contract stipulates that, before
cancellation for breach, the innocent party
must give written notice
identifying the default and allowing 21 days to remedy it. No such
notice was given. On this basis, it
was argued, the purported
cancellations of July and August 2025 were ineffectual and incapable
of founding the declaratory or interdictory
relief sought.
[16]
The applicants accepted that no clause 15.3 notice was given but
sought to justify their course on the footing that they
were induced
to contract by misrepresentations, particularly about the first
respondent’s NHBRC registration and ability
to have the houses
complete within agreed timeframes. They contended that these
misrepresentations vitiated the agreements and
excused the
requirement of a prior notice to remedy breach.
[17]
During argument the court raised the question whether the statements
relied upon as misrepresentations were, on a proper
characterisation,
promises of future performance rather than statements of existing
fact. Counsel were invited to address whether
such promises, if not
fulfilled, would amount to contractual breaches requiring notice to
remedy, rather than actionable misrepresentations
permitting
cancellation without an obligation to provide for notice under clause
15.3. The applicants submitted that the respondents’
statements
about NHBRC registration and completion dates were presented as
present compliance and therefore fell within the concept
of
misrepresentation. The respondents maintained that, even if some
statements proved inaccurate, they were no more than undertakings
as
to what would be done in the future.
[18]
A further aspect that emerged from the contractual framework is that,
for as long as the building agreements remain extant,
the applicants
are contractually precluded from introducing their own contractors to
perform the works or to gain site access for
that purpose. Clause 3.1
expressly appoints the first respondent as the builder and provides
that it will supply all material and
labour required for the works.
[19]
Read with clause 15.3, which makes notice to remedy breach a
condition precedent to cancellation, these provisions mean
that the
builder not only has the duty to construct the dwellings but also the
right to regulate and control access to the site
in order to perform
and to assume the associated risks. Allowing outside contractors on
site before a valid cancellation would
undermine the builder’s
responsibility for NHBRC compliance, warranties and insurance, and
would defeat the carefully defined
cancellation procedure.
[20]
Other
issues received more limited attention. The respondents disputed that
the applicants themselves had ever been refused access
to their
properties, contending that security personnel merely enforced
restrictions on the entry of unauthorised contractors.
The
applicants, in reply, insisted that they and their contractors had in
fact been excluded and that their proprietary rights
were infringed.
The court noted that these competing versions raised factual disputes
which might engage the
Plascon-Evans
rule
[1]
if final interdictory relief were sought.
#
# Cancellation and
Misrepresentation
Cancellation and
Misrepresentation
[21]
The decisive question is whether the applicants were entitled to
cancel their building agreements without giving the
contractual
21-day notice contemplated by clause 15.3 of the agreements.
[22]
Clause 15.3 stipulates that the employer may cancel the agreement
only if the builder defaults in one of three defined
ways:
[22.1] without
reasonable cause wholly suspends the works before completion,
[22.2] without
reasonable cause refuses to proceed with the works with reasonable
diligence, or
[22.3] without
reasonable cause fails to comply timeously with local authority
conditions, and even then only if the default
continues for 21 days
after written notice specifying the default.
[23]
This wording makes it clear that clause 15.3 is not a general
cancellation clause for every conceivable breach. It is
directed at
defined defaults relating to the progress and legality of the works.
If the employer relies on some other breach that
does not fit these
categories, cancellation might be governed by the common law rather
than by clause 15.3. The first question
is therefore whether the
breaches on which the applicants relied fall within one or more of
the defined categories.
[24]
The applicants’ notices of cancellation and founding papers
emphasise persistent and lengthy delays in construction,
periods when
work ceased altogether, failure to have the houses complete within
the agreed or promised timeframes, defective work
including a
collapsed wall, and misstatements about NHBRC registration and
ability to perform.
[25]
Each of these complaints concerns either suspension of the works or a
failure to proceed with reasonable diligence. They
therefore fall
squarely within the defaults enumerated in clause 15.3. There is no
pleaded breach of a different character that
could sustain a
common-law right to cancel independently of clause 15.3.
[26]
It follows that the operation of clause 15.3 is engaged and that the
21-day notice to remedy default was a condition
precedent to
cancellation. It is common cause that no such notice was given.
Unless the applicants can establish that their case
falls within a
different ground for rescission not subject to clause 15.3, the
absence of the required notice is fatal.
[27]
The applicants sought to avoid the operation of clause 15.3 by
characterising certain statements by the first respondent
as
misrepresentations. They contended that they were induced to
contract, and later to persist with the agreements, by statements
that the first respondent would be duly registered with the National
Home Builders Registration Council (NHBRC), that construction
would
be complete within specified timeframes, and that adequate resources
and contractors were in place to achieve those outcomes.
[28]
The legal distinction between a misrepresentation and a contractual
promise is critical. A misrepresentation is a false
statement of an
existing fact, made before or at the time of contracting, which
induces a party to contract and, if proved, may
justify rescission
without the need to comply with contractual notice provisions. A
contractual promise, by contrast, is an undertaking
to bring about a
state of affairs in the future. Non-performance of such an
undertaking does not constitute a misrepresentation;
it is a breach
of contract, which must be addressed through the contract’s own
remedial mechanisms.
[29]
Counsel were invited to identify any specific statement that was, at
the time it was made, false as to an existing fact.
None emerged. The
undertakings relied upon - that the houses would be complete within
six months, that project plans would be met,
or that NHBRC
registration would be secured - are, on their face, commitments about
what would be done, not assertions of an existing
state of affairs.
Even on the applicants’ version, these are promises of future
performance and therefore part of the contractual
bargain, not
extraneous representations.
[30]
At worst, there were delays in progressing individual NHBRC
enrolments or inspections. That may constitute non-performance
of a
contractual undertaking to comply with statutory requirements, but it
is not a misrepresentation of an existing fact at the
time the
contracts were concluded.
[31]
The applicants also referred to alleged coercive demands for
additional payments. Even accepting those allegations at
face value,
they do not transform the builder’s promises into actionable
misrepresentations. At most, they raise issues of
performance and
breach that remain subject to clause 15.3.
[32]
The result is that no independent ground for rescission based on
misrepresentation has been established. All the breaches
on which the
applicants rely either fall within clause 15.3 or are not established
on the facts. The 21-day notice to remedy default
was therefore a
necessary condition to a valid cancellation, and the applicants’
failure to give such notice is fatal to
their case. Their purported
cancellations of July and August 2025 were invalid, and the building
agreements remain in force.
#
# Consequences for the
Interdictory and Access Relief
Consequences for the
Interdictory and Access Relief
[33]
The principal relief sought by the applicants, apart from
confirmation of cancellation, is a final interdict to secure
their
and their contractors’ free and undisturbed access to the
properties for purposes of carrying out their own work.
[34]
That relief cannot be granted. The finding that the building
agreements have not been validly cancelled means that those
agreements remain of full force and effect. While they remain extant,
the first respondent continues to hold the exclusive contractual
mandate to construct the dwellings and to regulate access to the
sites for that purpose.
[35]
Clause 3.1 expressly records that the builder “will supply all
material and labour required for the works”.
Read with clause
15.3, which provides the sole mechanism for termination, this confers
on the builder not merely the duty to build
but the correlative right
to control the building site and to prevent the introduction of
outside contractors whose presence could
compromise safety, NHBRC
compliance, warranties, insurance cover, and the integrity of the
works. The applicants cannot, while
the agreements endure,
unilaterally appoint their own contractors or insist on their access
for purposes of carrying out their
own work without breaching the
agreements.
[36]
The factual dispute about whether the applicants themselves have been
barred from entering their properties does not
assist them. On the
respondents’ version, which must be preferred where there is a
genuine dispute of fact on final motion,
the applicants have never
been refused personal access. What has been regulated is the entry of
third-party contractors not appointed
by the first respondent.
Indeed, the respondents have expressly undertaken not to deprive the
applicants themselves of access to
their properties. Even if there
had been occasional interruptions or misunderstandings, those do not
translate into a clear right
to compel access for outside contractors
when the contract itself forbids such access.
[37]
Final interdictory relief requires proof of a clear right, an injury
actually committed or reasonably apprehended, and
the absence of an
adequate alternative remedy. Because the applicants’ agreements
remain binding and give the first respondent
exclusive rights over
the construction works and associated access, the applicants cannot
demonstrate the clear right that is the
first and essential element.
The remaining requirements therefore need not be considered in
detail.
[38]
Accordingly, the prayer for an interdict to secure unrestricted
access for purposes of carrying out their own work must
also fail.
The contractual arrangements that they themselves concluded, and that
have not been validly terminated, preclude such
relief.
[39]
As to costs, I do not consider there to be
any compelling reasons why the ordinary rule should not apply,
namely, that costs should
follow the result. As for the scale of
costs, I am of the view that Scale B is appropriate.
[40]
In the circumstances, the following order
is made:
1.
The application is dismissed with costs on
scale B.
D MAHON
Acting Judge of the High
Court
Johannesburg
Date of
hearing:
4 September 2025
Date of
judgment:
22 September 2025
APPEARANCES
:
For the
Applicant:
Adv J Brenkman
Instructed
by:
Wilkins Attorneys
For the First to Third
Respondents: Adv A
Bishop
Instructed by:
Ricardo & Partners Inc
No appearance for the
Fourth and Fifth Respondents
[1]
See
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984 (3) SA 623
(A)
sino noindex
make_database footer start
Similar Cases
Muleya v Minister of Police and Another (32440/18) [2023] ZAGPJHC 1466 (18 December 2023)
[2023] ZAGPJHC 1466High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Mthembu v Mlamba and Others (17373/2019) [2025] ZAGPJHC 269 (7 March 2025)
[2025] ZAGPJHC 269High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Masebebalo v Matenji (53948/21) [2025] ZAGPJHC 271 (13 March 2025)
[2025] ZAGPJHC 271High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Makhubela v Road Accident Fund (2011/30124) [2025] ZAGPJHC 18 (16 January 2025)
[2025] ZAGPJHC 18High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Mthembu v Woolworths (Pty) Limited and Another (44235/2019) [2024] ZAGPJHC 914 (29 July 2024)
[2024] ZAGPJHC 914High Court of South Africa (Gauteng Division, Johannesburg)99% similar