Case Law[2025] ZAGPJHC 1172South Africa
Afrirent (Pty) Ltd v Rand West City Local Municipality and Another (A2024/053317) [2025] ZAGPJHC 1172 (17 November 2025)
High Court of South Africa (Gauteng Division, Johannesburg)
17 November 2025
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 1172
|
Noteup
|
LawCite
sino index
## Afrirent (Pty) Ltd v Rand West City Local Municipality and Another (A2024/053317) [2025] ZAGPJHC 1172 (17 November 2025)
Afrirent (Pty) Ltd v Rand West City Local Municipality and Another (A2024/053317) [2025] ZAGPJHC 1172 (17 November 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_1172.html
sino date 17 November 2025
###### IN THE HIGH COURT OF
SOUTH AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO: A2024-053317
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
In
the matter between:
AFRIRENT
(Pty) LTD
APPELLANT
and
RAND
WEST CITY LOCAL MUNICIPALITY
FIRST RESPONDENT
FLEET
HORIZON SOLUTIONS (Pty) LTD
SECOND RESPONDENT
THE
ORDER
(1)
The appeal succeeds.
(2)
The order of the court below is set aside and replaced with one
reading:
“
1.
The award of
the tender by Rand West to Fleet is declared to be unconstitutional
and unlawful. It is reviewed and set aside.
2. The service level
agreement between Rand West and Fleet is set aside from inception.
3. Rand West and Fleet
are jointly and severally to pay the costs of Afrirent. These include
those of senior counsel.”
(3) Rand West may,
at a time of its choosing, if it so wishes, call for tenders afresh,
relating to subject matter, length
of contract and other details as
specified by Rand West.
(4) Rand West may
contract with any suitable supplier or suppliers, on an emergency but
fair and transparent basis, for the
supply of vehicles necessary to
keep the municipality functioning, pending the conclusion of a fresh
tender process.
(5) Rand West and
Fleet are jointly and severally to pay Afrirent’s costs of the
appeal. These include those of senior
counsel. Scale C applies.
(6). Regarding all
applications relating to condonation and lapsing of the appeal which
the parties abandoned at the beginning of
the hearing, each side is
to carry its own costs.
JUDGMENT
The Court (Coram:
Sutherland DJP, Wright J and Carrim AJ):
Introduction
1.
The first respondent, a municipality (Rand West) called for tenders.
It wished to hire a fleet of vehicles and have them maintained.
Among
others, the appellant (Afrirent) and the second respondent,
Fleet Horizon (Fleet), tendered.
2.
Afrirent’s bid was for R153 million. Fleet’s bid was for
R244 million.
3.
Fleet’s tender was accepted and a three-year service level
agreement was concluded between Rand West and Fleet. That was
in May
2023. The agreement expires in May 2026, some seven months from the
date of this judgment.
4.
Afrirent, unhappy at not being awarded the tender launched an
application seeking to review the decision to award the tender to
Fleet. Afrirent sought an order too, that the tender be awarded to
it. Afrirent later abandoned the latter relief.
5.
Afrirent’s review application was dismissed. Also dismissed was
an application for leave to appeal. Afrirent now appeals
with the
leave of the Supreme Court of Appeal.
6.
At its heart, Afrirent’s case has three points.
The provision of a
SARS statement issue
7.
First, it says that it was wrongly excluded by Rand West for not
having provided a SARS statement when called upon by Rand West
to do
so. In short, Afrirent, Fleet and at least one other bidder had all
included SARS clearance certificates with their bids.
Arising out of
queries by SARS to Rand West, raised by SARS after close of bids that
suggested that Afrirent’s tax affairs
were not in order, Rand
West became concerned that Afrirent’s bid might need to be
excluded for want of compliance with regulatory
requirements relating
to its tax affairs. Rand West then required from the bidders their
SARS statements, not just clearance certificates.
These statements
were immediately provided by Fleet and by the other bidder. Afrirent
did not provide with a SARS statement.
8.
A clearance certificate is in effect a bland statement that the
taxpayer is in good standing, that its tax is up to date or that
the
taxpayer has made arrangements, satisfactory to SARS at least on an
interim basis, to pay outstanding tax. A statement, on
the other hand
is a setting out of the state of the account between SARS and the
taxpayer.
9.
Despite a reminder by Rand West that Afrirent provide its SARS
statement, Afrirent did not. This compounded Rand West’s
concerns about the ability of Afrirent, particularly from a cash flow
point of view, if not from a technical regulatory point of
view, to
deliver on a three-year contract if Afrirent was successful.
10.
In our view, Rand West was reasonably concerned about compliance and
about the ability on the part of Afrirent to deliver fully
over a
three-year period. Rand West was accordingly justified to exclude
Afrirent on both these grounds.
11.
It does not follow from this that Afrirent lost standing to launch
its review. Afrirent, in the event of a repeat of the tender
process
would be entitled to bid and to have its bid considered. It therefore
has sufficient direct legal interest in its review
application.
The three years
audited accounts requirement
12.
The second point is that Fleet’s bid should have been excluded
for failure by Fleet to submit three years’ audited
financial
statements with its bid. It is common cause that Fleet did not
do so; it submitted two years’ audited accounts
and one year
unaudited.
13.
Under paragraph 21.1(d) of Rand West’s Supply Chain Policy,
where an envisaged contract is to be for more than R10 million,
as is
the contract now in question, a bidder who is is “
required
by law
” to have its financial statements audited, must
submit three years of such accounts.
14.
In Fleet’s answering papers it makes out the case that it is
not “
required by law”
to have its financial
statements audited as it is a private limited company, it holds no
assets in a fiduciary capacity, does not
compile its statements
internally but retains an external entity to compile them and it is
thus not required to have its financial
statements audited in the
public interest. These allegations are confirmed in an affidavit by
an external accountant. These being
motion proceedings, Fleet’s
allegations must be accepted, leading to the conclusion that the
failure by Fleet to provide
the three years’ of audited
accounts was not an irregularity.
The Condition imposed
on the acceptance of Fleet’s Tender
15.
The third point relates to the service level agreement concluded
between Rand West and Fleet. Despite Afrirent’s bid being
some
R90 million lower than that of Fleet, Fleet was awarded the tender.
Rand West, understandably alert to this significant difference,
included in its letter to Fleet when awarding the tender the clause
“
The appointment is subject to a negotiation of decreasing
an original amount of R244 820 693,77 to an affordable
amount
for Three (3) years inclusive of VAT and contingencies
.”
16.
There are two aspects to weigh. First, the case advanced by
Rand West and Fleet was that all this condition required was
a
negotiation. This is untenable. Were that to be all that was
contemplated then Fleet could simply hold out for the price
stipulated
and on the grounds that the condition was met, compel an
agreement. The meaning to be attributed to the condition has to mean
what
it plainly states, i.e., there had to be a price reduction in
respect of the work specified in the tender. What did happen, as
dealt with hereafter, was a re-jig of the services to be rendered
which albeit affecting the overall cost to the municipality, in
a
degree not properly revealed, did not fulfil the condition. In our
view, the condition failed and the subsequent service level
agreement
fails too. The review succeeds on this ground alone.
17.
Second, despite an allegation that no negotiations occurred, Rand
West says that there were negotiations, and as a result, it would
order vehicles from Fleet “
on a needs basis. The price will
depend on the needs of Rand West and the availability of funds. Rand
West has reduced the number
of vehicles needed.”
This
averment by Rand West must be accepted on the
Plascon Evans
Rule.
18.
Nevertheless, the award of the tender was irregular. Awarding a
tender to a bidder with a price so much higher than that of a
competing bidder is startling. Rand West was clearly alive to the
suspicion that naturally arises from that fact. That is why it
tried
to soften the impression of the award by the condition about
negotiation to reduce the price to an ‘affordable’
amount. Plainly, the reference to “
an affordable amount”
is an admission by Rand West that it could not afford to pay the R244
million.
19.
The result of the award, with its vague condition, is that it leaves
the award completely open ended. Neither the price nor what
is to be
delivered by Fleet is determined or even determinable. Only agreement
can fasten the loose strings. It is hardly surprising
that
negotiations did not lead to a definite agreement, as appears to be
the case. It is plain that the award is tainted.
20.
Fleet had no motive to negotiate very much, seeing that it had an
award and that negotiation would lead only to a reduction of
the
price or an increase in what Fleet had to deliver, or both. In these
circumstances, the negotiation as alluded to in the award
would be
more apparent than real. A comparison of prices has meaning only if
what the bidders have to deliver is the same. What
Rand West did is
to render meaningless the critical price comparison.
21.
Accordingly, there can be no shying away from the need to declare the
award bad in law.
The Remedy
22.
The question is, what to do now? The agreement has run for about two
and a half years and has about six months to run. Apparently,
the
vehicles are necessary to keep Rand West functioning. Some of the
vehicles are used for important tasks like collection of
refuse.
23.
An important consideration is that it would encourage non-compliance
with the strict and necessary procurement laws simply to do
nothing
other than to declare the award irregular. It would allow
municipalities and those who contract with them to think that
the
game was worth the candle. The service level agreement must be set
aside from inception.
24.
That said, the municipality cannot be hamstrung in performing its
necessary tasks, for example collecting refuse.
25.
In our view, the best way out of this impasse is to allow Rand West
to call for tenders afresh. In the interim, Rand West may,
on an
emergency but fair and transparent basis contract with any suitable
party or parties for the supply of necessary vehicles
pending the
outcome of the fresh tender process.
26.
We would not order Rand West to call for specific kinds of tenders
within a specific time. Rand West runs the municipality, not
the
court.
27.
At the commencement of the hearing, counsel for all parties sensibly
agreed that the appeal simply proceed and that the parties
pay their
own costs in certain condonation and lapsing applications.
THE ORDER
(1)
The appeal succeeds.
(2)
The order of the court below is set aside and replaced with one
reading:
“
1.
The award of the tender by Rand West to Fleet is declared to be
unconstitutional and unlawful. It is reviewed and set aside.
2.
The service level agreement between Rand West and Fleet is set aside
from inception.
3.
Rand West and Fleet are jointly and severally to pay the costs of
Afrirent. These include those of senior counsel.
“
(3) Rand West may,
at a time of its choosing, if it so wishes, call for tenders afresh,
relating to subject matter, length
of contract and other details as
specified by Rand West.
(4) Rand West may
contract with any suitable supplier or suppliers, on an emergency but
fair and transparent basis, for the
supply of vehicles necessary to
keep the municipality functioning, pending the conclusion of a fresh
tender process.
(5) Rand West and
Fleet are jointly and severally to pay Afrirent’s costs of the
appeal. These include those of senior
counsel. Scale C applies.
(6). Regarding all
applications relating to condonation and lapsing of the appeal which
issues the parties abandoned at the beginning
of the hearing, each
side is to carry its own costs.
The
Court
HEARD:
12 November 2025
DELIVERED:
17 November 2025
APPEARANCES
:
APPELLANT
Adv PG Cilliers SC
Instructed
by
Albert Hibbert Attorneys
jaco@hibbertlaw.co.za
FIRST
RESPONDENT
Adv V Maleka
SC
Adv M
Salukazana
Instructed
by
Strauss Daly Inc
akhoza@straussdaly.co.za
SECOND
RESPONDENT
Adv AC Botha SC
Adv CJ Bresler
Instructed
by
Bouwer and Olivier Attorneys
mb@law.co.za
sino noindex
make_database footer start
Similar Cases
AfriRent (Pty) Ltd v Rand West City Local Municipality and Another (2023-052811) [2023] ZAGPJHC 1192 (23 October 2023)
[2023] ZAGPJHC 1192High Court of South Africa (Gauteng Division, Johannesburg)100% similar
AfriRent (Pty) Ltd v Rand West City Local Municipality and Another (2023-052811) [2023] ZAGPJHC 1430 (11 December 2023)
[2023] ZAGPJHC 1430High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Africas Best Foods Pty Ltd v CISA Specialita Alimentari S.R.L (2021/26828) [2025] ZAGPJHC 390 (10 March 2025)
[2025] ZAGPJHC 390High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Afriforum v South African Human Rights Commission and Others (14370-2019) [2024] ZAGPJHC 317 (27 March 2024)
[2024] ZAGPJHC 317High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Africas Best Foods (Pty) Ltd v Transpaco Packaging (Pty) Ltd (A3040/2022) [2023] ZAGPJHC 474 (15 May 2023)
[2023] ZAGPJHC 474High Court of South Africa (Gauteng Division, Johannesburg)99% similar