Case Law[2024] ZAGPJHC 555South Africa
Siemans (Pty) Limited v Eskom Holdings SOC Limited and Others (026621/2024) [2024] ZAGPJHC 555 (7 June 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 555
|
Noteup
|
LawCite
sino index
## Siemans (Pty) Limited v Eskom Holdings SOC Limited and Others (026621/2024) [2024] ZAGPJHC 555 (7 June 2024)
Siemans (Pty) Limited v Eskom Holdings SOC Limited and Others (026621/2024) [2024] ZAGPJHC 555 (7 June 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_555.html
sino date 7 June 2024
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
CASE
NO: 026621-2024
(1)
REPORTABLE: YES
(2)
OF INTEREST TO OTHER JUDGES: YES
(3)
REVISED
DATE:
07 JUNE 2024
SIGNATURE
In
the matter between:
SIEMENS
(PTY) LIMITED
Applicant
and
EKSOM
HOLDINGS SOC
First Respondent
Limited
GE DIGITAL SOUTH
AFRICA
(PTY)
LIMITED
Second Respondent
HITACHI ENERGY SOUTH
AFRICA
(PTY)
LTD
Third Respondent
Delivered:
This judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically by circulation
to the
Parties / their legal representatives by email and by uploading it to
the electronic file of this matter on Case Lines.
The date of the
judgment is deemed to be 07 June 2024
JUDGMENT
UNTERHALTER J
Introduction
[1]
The applicant, Siemens (Pty) Ltd
(‘Siemens’), brings under review a tender, issued by the
first respondent, Eskom Holdings
SOC Ltd (‘Eskom’). The
tender sought bids for the construction of a new Transmission Power
System Control and Monitoring
System (TPSCM) for Eskom. The tender
was divided into two parts: Part A was for the provision and
maintenance of a software system;
and Part B for the provision and
maintenance of front and rear projection systems. Bidders were
invited to submit bids for Part
A or Part B, or both. The second
respondent, GE Digital South Africa (Pty) Ltd (‘GE’),
submitted a bid for Part A;
Siemens did so for Part A and Part B; as
did a third bidder, the third respondent, Hitachi Energy South Africa
(Pty) Ltd (‘Hitachi’).
[2]
On 8 January 2024, Eskom published its
decision. It awarded Part A of the tender to GE. It made no award in
respect of Part B. Siemens
was informed that its bid was
unsuccessful. Eskom entered into a contract with GE, following the
award of the tender. Siemens challenges,
by way of judicial review,
the decision of Eskom to award the tender to GE. Siemens seeks to set
aside the award of the tender
to GE, and the contract concluded by
Eskom and GE pursuant to the award.
[3]
Siemens brought its application in two
parts. In part A, it sought to interdict Eskom from concluding a
contract with GE, following
the award, and executing any contract
that may already have been concluded, pending the determination of
its review. Siemens agreed
to forego its part A relief, in
consideration of an expedited timetable under which the record would
be produced, and further affidavits
exchanged. This the parties have
done with commendable expedition, permitting the review to be heard.
[4]
Though Siemens raised a number of grounds
of review in its papers, counsel for Siemens made it plain, in his
heads of argument and
during oral argument, that the grounds of
review relied upon were three-fold. The principal ground of review is
as follows. The
tender provided for a tender validity period. The
tender validity period expired on 31 October 2023. It was not
lawfully extended.
The tender thus came to an end. The tender could
not thereafter be awarded. The award of the tender outside the tender
validity
period to GE was unlawful, as was the contract that Eskom
concluded with GE. I shall refer to this challenge as the validity
challenge.
[5]
Siemens does not abandon two further
grounds of review, though it presses them with less centrality.
First, Siemens avers
that Eskom permitted GE to enjoy advantages over
other bidders. GE was the incumbent provider of the existing system
and thereby
secured knowledge and access that placed GE in an
advantageous position to the detriment of the two other bidders. This
was neither
fair, equitable, transparent or competitive, and so
rendered the process unlawful. I shall refer to this challenge as the
incumbency
challenge. Second, Siemens complains that its bid was
rejected as non-compliant with the tender requirements on the basis
that
its bid lacked supporting documents. This, Siemens contends, was
not so. It made comprehensive responses to the clarification request
of Eskom, and thus no basis existed for the rejection of its bid. I
shall refer to this challenge as the disqualification challenge.
[6]
I consider first the validity challenge.
The validity challenge
[7]
Eskom’s invitation to submits a
proposal for the TPSCM is set out in the Request for Proposal (RFP).
The RFP provides for
a tender validity period. It is framed as
follows;
‘
The
tender validity period is
twelve (12)
weeks
from the Tender closing date and
time.
NB:
While
a
twelve (12) week
Tender
validity period has been provided from the tender closing date, the
evaluation and adjudication process may take up to six
(6) months.
Should the evaluation extend beyond the twelve (12) weeks,
Tenderers
will be requested to extend their
validity beyond the twelve (12) weeks.’ (emphasis appears in
the original text).
[8]
The RFP must be read together with Eskom’s
Standard Conditions of Tender. Clause 2.13 reads as follows:
‘
Hold
the tender(s) valid for acceptance by Eskom at any time within the
period after the deadline for tender submission. Extend
the validity
period for a specified additional period if Eskom requests the
tenderer to do so. A tenderer agreeing to the request
will not be
required or permitted to modify a tender. If contracts have not been
concluded and the tender validity period has not
been extended (as
prescribed in the Eskom PSCM 32-1034) and lapses; then the tenders
are deemed to be invalid and the procurement
process cannot continue.
A new procurement process will have to be initiated.’
I shall refer to this
provision as the ‘drop-dead provision’.
[9]
The drop-dead provision references Eskom
PSCM 32-1034. That is a reference to Eskom Procurement and Supply
Chain Management Procedure.
(PSCM). Clause 14.7.8.1 of the PSCM, in
relevant part, contains the following:
‘
Tenders
are required to remain valid until such time that the relevant DAA
awards tenders, but within the validity of the timeframe
stipulated
in the enquiry or any extensions.
Procurement Practitioners
are required to extend the validity of all tenderers until the final
contract has been concluded.
…
..
The extension of a tender validity period means that the tenderer
maintains its original pricing and all other terms and conditions
as
tendered.
…
..If
a tenderer cannot maintain the original tender (including prices)
during the tender validity extension period of the tender.
Then the
tender may not be considered for further evaluation, and the supplier
therefore cannot be awarded a contract. Extension
of the validity
period is not an invitation to the tenderer to amend the tendered
price, scope and/ or the delivery period. NB:
Tenders cannot be
extended after tender validity had expired. Tender validity can ONLY
be extended while the tender is still valid.’
(emphasis appears in the
original text) I shall refer to these provisions as the ‘extension
provisions’.
[10]
The facts as to the extension of the
validity period are not in dispute. The tender closing date was
extended on a number of occasions.
Eskom sought successive extensions
of the tender validity period from Siemens, GE and Hitachi. The
tenderers granted extensions
until 31 October 2023. Siemens further
extended the validity period to 31 January 2024; and GE did so to 24
December 2023. However,
Hitachi did not grant an unconditional
extension for a period after 31 October 2023. It was only willing to
do so under a proviso
that acceptance by Eskom of Part B of its
tender was contingent on acceptance of Part A. This conditionality
was unacceptable to
Eskom. And it is common ground that Hitachi did
not consent to the extension of the validity period beyond 31 October
2023.
[11]
The central question that arises is this:
what is the consequence of the fact that Hitachi did not agree to
extend the validity
period beyond 31 October 2023? The parties
offered different answers to this question. Siemens submits that the
valid extension
of the period beyond 31 October 2023 required all the
bidders to consent to such extension. Hitachi did not do so. The
tender validity
period thus expired on 31 October 2023; the tender
came to an end on that date; the tender could not be awarded; and
consequently,
the award of the tender to GE on 21 December 2023 took
place after the validity period had expired, and it was thus awarded
unlawfully.
For like reasons, so too was the contract concluded
between Eskom and GE unlawful.
[12]
Eskom takes a different position. The
effect of Hitachi’s decision not to extend the tender validity
period was that its bid
was no longer open for acceptance by Eskom
beyond 31 October 2023. Siemens and GE agreed to extend the period.
Their bids remained
open for acceptance within these periods. Eskom
award the tender to GE on 21 December 2023, within the period of
extension granted
by GE. That Hitachi did not extend the tender
validity period did not preclude Eskom from awarding the tender to
those tenderers
that had granted extensions, provided the award took
place within the periods of extension granted. To hold otherwise,
Eskom submitted,
would allow a bidder to collapse the tender process,
and that is not a business-like interpretation to place on the
tender.
[13]
GE
advances a distinctive submission. Eskom’s technical evaluation
report dated 11 September 2023 sets out that Hitachi’s
bid had
failed, in respect of Part A, to meet what is described in the RFP as
‘technical gatekeepers’. These gatekeepers
specify
certain requirements that must be met. If they are not, then the RFP
provides as follows; ‘Failure by the Tenderer
to meet the above
technical gatekeepers will lead to disqualification and their bids
will not be evaluated further’.
GE contends that
Hitachi’s bid for Part A was judged non-responsive and was
disqualified. Accordingly, by the time that the
extension was sought
from Hitachi for a period beyond 31 October 2023, Hitachi’s bid
for Part A was ineligible for acceptance,
and Hitachi’s failure
to agree an extension of the validity period was of no consequence in
respect of Part A. While Hitachi’s
bid for Part B remained
eligible for consideration and further evaluation, as at 31 October
2023, Hitachi’s failure to extend
beyond that date made no
difference because Eskom made no award in respect of Part B, as it
was entitled to do. GE places reliance
upon
Aurecon
[1]
which
found that a request for the extension of the validity period in a
tender need not be made to bidders found to be ineligible.
[14]
My analysis must commence with the terms of
the tender itself. These terms were determined by Eskom and accepted
by the bidders.
They must be interpreted according to the
well-established triad of text, context and purpose. I have set out
above the relevant
provisions of the tender that bear upon the
validity challenge. These provisions make plain a number of matters.
[15]
First, as appears from clause 2.13 of the
RFP, the tender validity period is to permit Eskom to undertake the
process of evaluation
and adjudication. Its extension is to complete
this process. The period is specified and precise. Beyond the twelve
weeks from
the closing date and time, tenderers will be requested to
extend the period. A request connotes choice: tenderers may
decide
whether to grant the request or decline to do so. Their
decision has entailments for the tenderers. The drop-dead provision
requires
that, if a tenderer agrees to the request for extension,
then it may not modify its tender. The extension provision spells
this
out. The extension of the tender validity period means that the
tenderer maintains its original pricing and other terms and
conditions,
as tendered. This plainly has important commercial
consequences. If input costs are rising, then agreement to an
extension is detrimental
to the tenderers and advantageous to Eskom.
And hence, tenderers may choose whether to extend. They are certainly
not required
to do so.
[16]
Second,
there can be no extension of the tender validity period after the
period has expired. Extension can only take place before
the
expiration of the tender validity period. This accords with
authoritative case law.
[2]
The
drop-dead provision is clear: if the tender validity has not been
extended, as prescribed in the extension provision, the tenders
lapse; they are deemed invalid, the procurement process cannot
continue, and a new tender has to be initiated.
[17]
Third, the validity period of the tender is
important for a further reason specified in the introductory sentence
of the drop-dead
provision. During the validity period, the tenders
are held valid for acceptance by Eskom. Within the period, Eskom is
at liberty
to accept the tenders. Outside of the period, the process
ends, and the tenders are no longer held open for acceptance.
[18]
While it is clear then that a tenderer has
an election to make if Eskom requests an extension of the tender
validity period, the
central question to be answered in this case is
this: if a tenderer does not extend, does that simply end its bid or
does it end
the tender process? Eskom contends for the first
consequence, and Siemens for the second.
[19]
The drop-dead provision requires that the
extension of tender validity takes places as prescribed in the
extension provision. The
extension provision is not formulated with
precision. The RFP states that tenderers will be requested to extend.
How that occurs
is set out in the extension provision. Eskom’s
procurement practitioner must seek permission from a senior manager
to seek
an extension. This is so because frequent extensions may be
detrimental to the efficiency of the evaluation process, as the
extension
provision observes. If the required permission is given,
then the procurement practitioner requests an extension from the
tenderers.
[20]
The following sentence that forms part of the extension provision
bears repetition: ‘Procurement Practitioners are required
to
extend the validity of all tenderers until the final contract has
been concluded’. This provision requires some interpretative
dexterity because the procurement practitioner cannot require
extension but can only request it. However, as best I can understand
this provision, the procurement practitioner must (‘is
required’) to seek from all the tenderers the extension of the
validity period. Such a request may be declined, and if it is, what
then? There are two interpretative pointers of some value.
The first
is textual. The procurement provision contains the following
sentence: ‘If a tenderer cannot maintain the original
tender
(including prices)
during the tender
validity extension period
then the
tenderer may not be considered for further evaluation, and the
supplier therefore cannot be awarded a contract’ (my
emphasis).
A tenderer is required to maintain the terms of their offer during an
extension period. But if they cannot do so, then
they fall out of
consideration. This regulates what is to happen to a particular
tender during the validity extension period. That
is to say, during a
period when the tender process enjoys validity, a tenderer that
cannot maintain its tender will suffer exclusion.
No equivalent
provision is to be found that specifies a similar outcome when a
tenderer is requested to give an extension and declines
to do so.
Nowhere does the extension provision state that a tenderer who does
not extend is eliminated as a tenderer, but the process
continues on
the basis of the extensions granted by other tenderers. If that was
the consequence, it is reasonable to suppose that
this would have
been stated, given what is expressly provided for in the case of a
tenderer that cannot maintain its original tender
in a tender
extension period.
[21]
The second consideration rests upon the
purpose of requesting all the tenderers to extend, and, by so doing,
maintain their tenders.
Given that one of the constitutional
requirements of a tender system is that it must be competitive and
cost effective, the request
to all tenderers to extend is to maintain
the competitive rivalry of the tender process. It is the contestation
of rival bids that
secures procurement outcomes that serve the public
good. The request to all seeks to secure the competitive rivalry upon
which
the integrity of the tender depends. If, as in this case, a
tenderer does not give its consent, two types of harm may result. If
the ongoing validity of the merger depends on the consent of all
tenderers, a veto power vests in each tenderer. And each tenderer
may
then collapse the process, perhaps well advanced, and require that a
new tender process commences. This is wasteful.
[22]
But there is a second risk of harm. Assume
that two of three tenderers decline the requested extension, leaving
Eskom with but one
tenderer that remains in contention. The
continuation of the tender process under these conditions could be
uncompetitive and might
privilege the least competitive bidder. That
is a risk not readily countenanced, given what the constitution
requires of a tender
process. And it is very difficult, when setting
the terms of a tender, to know in advance who will give extensions,
at what point
in the process, and with what consequence for the
competitiveness of the tender. For this reason, securing the consent
of all tenderers
to an extension is the more compelling rule of
general application to secure the competitiveness of a tender. I do
not thereby
suggest that it is an invariable rule. A tender could
create a regime under which not all tenderers must grant extensions,
subject
to some careful assessment of the resulting competitiveness
of the tender. But, as here, absent such a provision, the residual
rule that enjoys interpretative primacy is the one that is
constitutionally indicated, that is, to keep all tenderers in the
process
or end the process.
[23]
The text of the relevant provisions of the
tender does not state that a tenderer that does not grant an
extension is simply eliminated
as a bidder. The text does so provide
if, during the tender validity period, a tenderer cannot maintain its
tender. If Eskom had
wanted to specify that the consequence of
declining a request to extend is self-elimination, it could, and
likely would, have formulated
the tender in these terms. This textual
consideration is consistent with a purposive perspective. The point
of securing the extensions
of bidders is to maintain their bids so as
to permit Eskom to complete its evaluation with the full competitive
benefit of the
submitted tenders. Such a regime is also fair to the
tenderers. There is commercial risk that attaches to maintaining a
tender
over time. That is why the RFP is specific about the
anticipated time for evaluation, and its extension. It would not
necessarily
be advantageous to Eskom to allow for a situation where
the most competitive bidders drop out because they can’t
maintain
their bids, while less competitive bidders remain. And it is
also fair to tenderers that their bids are evaluated on the merits
of
the bids submitted, rather than on the basis of the tenderers that
have the greatest staying power. For these reasons, I consider
the
interpretation proposed by Eskom to be insufficiently availing, and I
reject it.
[24]
I turn to consider GE’s
interpretation of the tender. That interpretation, to recall its
central elements, holds that Hitachi’s
tender was no longer
eligible for consideration in respect of Part A, at the time the
extension was sought from it in October 2023,
because it had failed
technical gatekeeper evaluation. The RFP stipulated that such failure
led to disqualification. The extension
of tender validity in respect
of Part A cannot depend upon the agreement of a tenderer already
disqualified from further consideration
as to Part A. The extension
was given by Siemens and GE. And as to Part B (where Hitachi remained
a bidder), Part B was not awarded,
and so the fact that Hitachi did
not extend the tender is of no relevance.
[25]
The factual premise of GE’s
submission is that Hitachi had failed to meet the technical
gatekeeper evaluation in respect of
its Part A bid, and that the RFP
then stipulated that Hitachi was disqualified as to Part A. The
record contains Eskom’s
technical evaluation report (‘TER’)
dated 11 September 2023, compiled some five months after Eskom’s
technical
gatekeeper evaluation report (‘TGE’),
authorised on 17 April 2023. The TER in its executive summary
references the
evaluation of the tenders, as to both Part A and Part
B, and in a table ‘summarizes the responses that were evaluated
after
the
conclusion of the technical gatekeeper evaluation’ (my
emphasis). The TER reports the results of these technical
evaluations.
It is clear from the TER that the evaluation undertaken
after the technical gatekeeper evaluation, reported upon in the TGE,
did
not include any further evaluation of Hitachi’s tender in
respect of Part A. The TER is an evaluation of GE’s and
Siemens’
bids in respect of Part A, and Hitachi’s and
Siemens’ bids in respect of Part B. Eskom, as the TER states,
considered
Hitachi’s bid for Part A to be non-responsive, as a
result of the gatekeeper evaluation, and therefore warranted no
further
evaluation, as the RFP stipulated.
[26]
It does not appear that this evaluation of Hitachi’s bid as to
Part A was conveyed by Eskom to Hitachi. Rather, Eskom
on 24 October
2023 e-mailed Mr Kaye of Hitachi and requested Hitachi to extend
tender validity for its tender, both as to Part
A and Part B. Mr
Kaye’s response was to make any extension contingent upon the
linkage of Part A and Part B. He wrote: ‘we
would not be able
to participate in further negotiations on Part B alone.’
Plainly then, Hitachi still considered itself
to be a tenderer for
Part A. Eskom’s affidavits do not suggest otherwise.
[27]
The results of Eskom’s evaluation had
plainly concluded that Hitachi did not meet the technical gatekeeper
requirements for
Part A. The RFP stipulates the consequence of such
failure: disqualification. The RFP was accepted by the tenderers as
the basis
upon which their bids would be determined. And therefore,
once Hitachi had failed the technical gatekeeper evaluation for Part
A of its bid, as an objective matter, the RFP determined that its bid
for Part A was disqualified. That Hitachi did not know this
to be the
case on 24 October 2023 does not alter that determination. That an
Eskom official sought an extension from Hitachi in
respect of Part A
also does not change what the RFP regulated. In other words, that an
Eskom official and Hitachi thought that
Hitachi remained a tenderer
in respect of Part A, did not make it so. The RFP determined the
status of Hitachi’s bid for
Part A.
[28]
Once that is so, in October 2023, Hitachi
was no longer a tenderer as to Part A, it was disqualified by
operation of the RFP. If
it was not a tenderer for Part A, as I find,
then there was no duty upon Eskom to request Hitachi to extend the
tender validity
period in respect of its bid for Part A. The RFP
requires that Eskom seeks extensions from tenderers. The only
tenderers for Part
A in October 2023 were GE and Siemens. They gave
the requested extensions. Hitachi remained a tenderer for Part B. It
did not extend
the tender validity period as a Part B tenderer. On
the reasoning set out above, that ended the tender’s validity
in respect
of Part B. But that is of no consequence because Eskom
made no award of Part B. I should add, parenthetically, that I am
doubtful
that
Aurecon
entrenches
a principle of general application to all tenders. But I am spared
having to decide that question.
[29]
It follows that the validity challenge must
fail.
The incumbency
challenge and the disqualification challenge
[30]
Siemens complains that its bid was rejected
for non-compliance or partial non-compliance, when Siemens responded
to Eskom’s
clarification request in a comprehensive fashion,
with relevant references. Eskom however sets out a detailed account
of its evaluation
of Siemens’ tender. It instances a lack of
supporting references or motivation that was required. The TER also
provides an
evaluation of Siemens’ tender for Part A and Part
B. The tender was found not to meet the overall technical scoring
threshold
for Part A and Part B. The scoring allocated to Siemens’
bid was not simply a function of its incompleteness, but its low
scores on other criteria. I cannot find, on the evidence, that
Eskom’s evaluation was not undertaken by recourse to relevant
criteria, objectively applied. The disqualification challenge
therefore cannot succeed.
[31]
Siemens complains further that GE had
access to and knowledge of Eskom’s existing system, and hence
GE enjoyed the advantages
of an incumbent, not available to other
bidders. So too, it is alleged that Eskom assisted GE to rectify the
shortcomings of its
bid, and this too was unfair, inequitable,
lacking in transparency, and detrimental to the competitiveness of
the tender.
[32]
Eskom denies that it afforded GE any
advantage over other bidders. GE’s engagements with Eskom in
respect of the existing
system were limited. Eskom sets out the basis
upon which all bidders were given the same information, and bidders
were not given
access to Eskom’s generation information system.
Eskom in its answering affidavit sets out the exposure GE had
to this
system. On this version, I cannot find that GE enjoyed
asymmetric access to information so as to skew the tender and give GE
a
material advantage. Nor is there sufficient evidence to warrant the
conclusion that Eskom sought to assist GE to the detriment of
other
bidders. The assessment of the tenders is evidence before me. On that
assessment, it appears that the bids succeeded or failed
on their
merits. And there is no showing that GE’s incumbency had any
systemic causal impact upon the content of the tenders
or their
ultimate assessment. For these reasons the incumbency challenge also
cannot succeed.
Conclusion
[33]
I find, for the reasons given, that the
grounds of review relied upon by Siemens cannot prevail. I do not
consider that there is
warrant to impose a punitive costs order.
Siemens advanced certain grounds of review that it did not ultimately
pursue. They were
not recklessly raised. Litigants should not be
dissuaded from determining that certain grounds of review have been
answered or
ultimately hold less promise than initially expected.
In the result the
following order is made:
The application is
dismissed with costs, which costs include the costs of the
application for interim relief, on Scale C, inclusive
of the costs of
two counsel.
UNTERHALTER J
JUDGE OF THE HIGH
COURT OF SOUTH
AFRICA, GAUTENG
DIVISION,
JOHANNESBURG
APPEARANCES
COUNSEL FOR THE
APPLICANT:
ADVOCATE L HOLLANDER
INSTRUCTED BY:
BOWMAN GILFILLAN
COUNSEL FOR THE 1
ST
RESPONDENT: ADVOCATE B
MAKOLA SC WITH ADVOCATE B MANENTSA
INSTRUCTED BY:
MAMATELA ATTORNEYS
COUNSEL FOR THE 2
ND
RESPONDENT: ADVOCATE MJ ENGELBRECHT SC WITH ADVOCATE N SIBOZA
INSTRUCTED BY: ENS
DATE OF
HEARING:
31 MAY 2024
DATE OF
JUDGMENT:
07
JUNE 2024
[1]
Aurecon
South Africa (Pty) Ltd v Cape Town City
2026
(2) SA 199
(SCA) at [23]
[2]
Ekurhuleni
Metro Municipality v Takubiza Trading & Projects CC & Others
2023
(1) SA 44
(SCA) paras [6] – [15] and there referenced.
sino noindex
make_database footer start
Similar Cases
Siyathemba Project Management and Development (Pty) Ltd v Weinberg (22984/202) [2024] ZAGPJHC 837 (5 August 2024)
[2024] ZAGPJHC 837High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyamanga v Balcony Shisa and Chill (18284/2022) [2025] ZAGPJHC 67 (27 January 2025)
[2025] ZAGPJHC 67High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corporation Proprietary Limited and Another v Redpath Africa Limited (55896/2021) [2024] ZAGPJHC 475 (8 May 2024)
[2024] ZAGPJHC 475High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corpoation (Pty) Ltd and Others v Redpath Mining South Africa (Pty) Ltd and Others (Application for Leave to Appeal) (57639/2021) [2024] ZAGPJHC 933 (19 September 2024)
[2024] ZAGPJHC 933High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corporation (Pty) Ltd and Others v Redpath Mining (South Africa) (Pty) Ltd and Another (9234/2022) [2024] ZAGPJHC 680 (22 July 2024)
[2024] ZAGPJHC 680High Court of South Africa (Gauteng Division, Johannesburg)99% similar