begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 633
|
Noteup
|
LawCite
sino index
## Grid Electronics v Quandomanzi Investments (Pty) Limited t/a SM Structures (2021/21032)
[2024] ZAGPJHC 633 (12 July 2024)
Grid Electronics v Quandomanzi Investments (Pty) Limited t/a SM Structures (2021/21032)
[2024] ZAGPJHC 633 (12 July 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_633.html
sino date 12 July 2024
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT
OF SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
1.
NOT
REPORTABLE
2.
NOT
OF
INTEREST TO OTHER JUDGES
CASE
NO
:
2021-21032
DATE
:
12
th
JULY 2024
In the matter between:
GRID
ELECTRONICS (PTY) LIMITED
Plaintiff
and
QUANDOMANZI
INVESTMENTS (PTY) LIMITED t/a
SM
STRUCTURES
Defendant
Coram:
Adams J
Heard
:
22, 23 and 24 January 2024
Delivered:
12 July 2024 – This judgment was handed down electronically
by circulation to the parties' representatives by email, by being
uploaded to
CaseLines
and by release to SAFLII. The date and
time for hand-down is deemed to be 11:30 on 12 July 2024.
Summary:
Contract – material supplied and services rendered in terms
of written agreement – breach of contract – defendant
failing to deliver all of the material and failing to complete a
portion of the works – general and special contractual damages
claimed by plaintiff arising from such breach of contract –
defendant disputes amounts claimed and plaintiff’s entitlement
to special damages – calculation of general damages –
plaintiff bears the onus to prove the amount needed to place
him in
the same position he would have been in if the defendant had
performed in terms of the contract – therefore, the reasonable
costs of remedying the defendant’s defective performance –
special damages – plaintiff required to plead and
prove –
that the loss, which does not generally flow from a breach of the
agreement in question – therefore,
unless the plaintiff proves
that the parties actually or presumptively contemplated that a loss
of that kind would probably ensue
on such a breach, such damages are
too remote and not recoverable –
Judgment
granted in plaintiff’s favour for general damages only.
ORDER
(1)
Judgment is
granted against the defendant in favour of the plaintiff for: -
(a)
Payment of the
sum of R103 618.45;
(b)
Payment of
interest on the amount of R103 618.45 at the applicable legal
interest rate of 7% per annum from date of service
of the summons,
being 7 May 2021, to date of final payment; and
(c)
Costs of suit
on the appropriate Magistrates Court scale.
JUDGMENT
Adams J:
[1].
The plaintiff, Grid Electronics (Pty)
Limited (‘Grid Electronics’), is a distributor and a
supplier of automotive sound
and accessories. The defendant,
Quandomanzi Investments (Pty) Limited (‘SM Structures’),
trades as SM Structures
and, as its trade name suggests, is a
manufacturer, producer and a supplier of building structures such as
steel warehouse structures.
On 29 October 2019 Grid Electronics
concluded an agreement with SM Structures for the supply and the
erection on Erf 8[…],
Blue Hills Agricultural Holdings
(‘plaintiff’s property’), of a portal frame steel
structure with the following
dimensions:
15
meters wide by 60 meters long by 6 meters high at column height, with
a roof pitch of 10 degrees and with no internal Columns.
The contract
price agreed upon was the sum of R435 500, inclusive of value
added tax (‘VAT’) and the contract
expressly provided
that the sheeting to be used for the roof was to be
0.5mm
IBR Chromadek
,
which is a special type of high-quality roof sheeting.
[2].
The further express
terms and conditions of the contract between the parties, as well as
the detailed specifications relating to
the structure, were all
incorporated into the written part of the agreement – the quote
dated 28 October 2019, which was
accepted by Grid Electronics on 29
October 2019. As regards the delivery time, the agreement
specifically provided that ‘[t]he
structure will be delivered
within 2 weeks from order and receipt of the first payment required
as detailed below’. Payment
of the contract was to be effected
as ‘progressive payments’ as follows: (a) 30% payment
with order; (b) 60% of quoted
value on arrival of structures on site;
and (c) 5% of quoted value on completion of the frame. The balance,
5% of quoted value,
was payable on completion of erection.
[3].
In terms of and
pursuant to the agreement, Grid Electronics paid to SM Structures
the following amounts on the following dates:
(a) the first payment
of R115 800 on 27 September 2019, which date in fact preceded
the date of the final conclusion of the
agreement; (b) the second
payment of R276 150 on 31 October 2019; and (c) the third
payment of R21 775 on 29 June
2020. A balance of R21 775
therefore remained outstanding on the contract price, which would
have been payable on completion
of the installation and erection of
the whole structure.
[4].
Grid Electronics
alleges that SM Structures breached the agreement in that it failed
to complete the installation of the roof on
the structure, in
addition to it failing to deliver a sufficient number of 0.5mm IBR
Chromadek
galvanised roof sheeting to complete the installation of the roof of
the structure. In my view, there does not appear to be much
dispute
about the aforegoing, I will revert to this aspect of the matter
shortly.
[5].
In this defended
action, Grid Electronics claims contractual damages arising from the
alleged breach of contract by SM Structures.
An amount of R147 756.60
is claimed by Grid Electronics as representing the fair and
reasonable costs of purchasing the shortfall
of the galvanized roof
sheeting and the cost of completing the erection of the roof –
general / direct damages. A further
sum of R428 506.08 is
claimed in respect of additional rental payable by Grid Electronics
to its erstwhile Landlord (from
whom it was renting business premises
at the time) after the date on which it had expected to take
occupation of the new premises
housed in the aforesaid portal frame
steel structure – that is for the period 1 December 2020 to 31
March 2021. The latter
amount represents alleged ‘special’
or ‘consequential’ damages.
[6].
The claim of Grid Electronics is resisted
by SM Structures on the basis that the agreement in question, on
which the cause of action
is based, was in fact concluded by SM
Structures with a Mr Mather (the sole shareholder and sole director
of Grid Electronics)
and not with Grid Electronics, as alleged by it
in its particulars of claim. The case on behalf of SM Structures is
therefore that
it concluded the agreement with Mr Mather in his
personal capacity and not on behalf of Grid Electronics. This is in
fact the main
defence by SM Structures as regards the liability
issue. Secondly, SM Structures denies that it breached the agreement.
This denial
by SM Structures is however somewhat equivocal especially
if regard is had to the undisputed facts in the matter. Lastly, SM
Structures
denies that Grid Electronic suffered the contractual
damages and the amount thereof as alleged by it.
[7].
At the commencement of the trial before me
on 22 January 2024, SM Structures, through its attorney, Mr
Meintjies, made the
formal concession that it
supplied
and fitted only 88 of the actual 176
Chromadek
sheeting provided for in the agreement, thus admitting to a shortfall
and a short supply of 88 roof sheeting. The concession was
incorporated into a formal ‘with prejudice’ tender by SM
Structures to pay to Grid Electronics R75 458.50 in full
and
final settlement of the latter’s claim, conditional upon Grid
Electronics proving that it (the company) was the party
to the
agreement and therefore has the necessary
locus
standi in iudicio
to claim the contractual damages from SM Structures. I interpret this
‘with prejudice’ tender as an admission by SM
Structures
that there was a breach of the contract and that damages arose from
such breach. This was in fact confirmed by Mr Meintjies
in his
written heads of argument.
[8].
This then means that
the issues to be adjudicated by me in this action are the following:
(a) Whether the contract was concluded
between SM Structures and Grid
Electronics and whether the latter’s sole director, Mr Mather,
acted personally or on its
behalf when he signed the written
agreement; and (b) a calculation of the amount of the contractual
damages suffered by Grid Electronics
as a result of the breach of
contract by SM structures. As regards the calculation of the
contractual damages, the main issue to
be considered by me relates to
whether or not Grid Electronics is also entitled to special /
consequential damages relating to
the additional rental it had to
fork out as a result of the installation of the portal steel
structure not being completed on time.
[9].
The aforesaid issues
are to be decided against the factual backdrop of the matter, the
facts being by and large common cause as
set out in the paragraphs
which follow, and which facts are gleaned from the evidence led
during the trial on behalf of both parties,
as well as from the
documentary evidence introduced via the medium of these witnesses. In
that regard, there were two witnesses
called on behalf of Grid
Electronics, namely its sole shareholder and director, Mr Courtenay
Robert Dilbey Mather (‘Mr
Mather’), and an expert, Mr
Dennis Edward White (‘Mr White’), whereas SM
Structures called its sole director,
Mr Stephen John Maycock
(‘Mr Maycock’), as its only witness.
[10].
I now proceed to deal
firstly with the issue as to whether the contract was indeed
concluded between Grid Electronics, as against
Mr Mather personally,
and SM Structures. I intend making short thrift of this aspect of the
matter for the simple reason that,
according to Mr Mather and his
uncontested and undisputed
viva
voce
evidence, his intention throughout was to enter into the agreement
not in his personal capacity but for and on behalf of Grid
Electronics. The fact that the quote dated 28 October 2019, which
formed the basis of the agreement between the parties, was addressed
to him and apparently accepted by him, is neither here nor there. The
simple fact of the matter is that his evidence was that when
he
signed the quote and concluded the agreement, he acted in his
capacity as the sole director of Grid Electronics. As I have already
indicated, that evidence is unchallenged and undisputed and cannot be
challenged on sound grounds.
[11].
Moreover, as
confirmed by Mr Mather during his evidence, the invoices were made
out and addressed to Grid Electronics, which also
paid by electronic
funds transfer, the amounts due and payable in terms of the
agreement. The structure was erected and installed
on land owned by
and registered in the name of Grid Electronics, which intended to use
the structure as its new business premises.
All of the aforegoing
proves, in my view, conclusively that the agreement was indeed
between Grid Electronics and SM Structures.
I have no doubt that that
is exactly how the parties understood the agreement as well.
[12].
I therefore conclude
that there is no merit in the defence raised by SM Structures
relating to the supposed lack of
locus
standi
on
the part of Grid Electronics. That would also then take care of any
dispute relating to the breach of contract by SM Structures.
This is
so becuase, during his
viva
voce
evidence, Mr Maycock admitted that his company, SM Structures, had
breached the agreement during or about October 2019 when it
short
delivered by 88 the
Chromadek
sheets. SM Structures, by their ‘with prejudice’ tender,
has also conceded that Grid Electronics suffered general or
direct
damages amounting in total to R75 458.50 in respect of the short
supply of 88 chromadek sheets.
[13].
The only remaining
dispute between the parties as regards general damages is the amount
of such damages. It was submitted on behalf
of SM Structures
that such damages amount to R75 458.50, as per their formal
tender, whereas it was submitted on behalf
of Grid Electronics that,
after certain recalculations, the actual amount of its damages is the
sum of R122 012.60.
[14].
It is therefore
necessary for me to have regard to the respective calculations on
behalf of the parties and to quantify the actual
damages suffered by
Grid Electronics. In that regard, it was only Grid Electronics which
called an expert witness to give an indication
of the reasonable
costs of the supply and installation of the 88 short-supplied
Chromadek
sheets.
[15].
The starting point
for Grid Electronics’ calculation of their general damages is a
quotation by a third-party supplier of
Chromadek
roof sheeting, namely Icon Doors, Maintenance & Electrical CC
(‘Icon’), for a total amount of R136 344 (inclusive
of VAT), as well as a final tax invoice from Icon dated 25 November
2020, confirming that Grid Electronics paid to the said company
R136 344 for the following material supplied and services
rendered by them: (a) Supply and install ‘82 x 8.1m dove
grey sheets’; (b) Supply and install ‘30m of flashings’;
(c) Waterproof 30m of wall; and (c) Fit centre
knock on factory
sheeting. The amount quoted and invoiced in respect of the material
supplied was the total sum of R102 960
(exclusive of VAT) and
for the labour was R15 600 (excluding VAT).
[16].
The expert, Mr White,
who was called as a witness by Grid Electronics, confirmed the
reasonableness of the amounts quoted in respect
of the material
supplied and the services rendered. He did however concede that the
amount relating to the supply and the installation
of the ‘flashings’
is a duplication in that, according to a delivery note signed off by
Grid Electronics during October
2019, the required number of
flashings had in fact been delivered to their premises. The charges
relating to the supply and installation
of the flashings, as well as
the charges relating to the waterproofing of the wall, ought to be
deducted from the actual amount
paid on the invoice. The
waterproofing clearly was not part of the initial quote by SM
Structures and therefore did not form part
of the services to be
rendered by them. During his cross-examination, Mr White confirmed
that the reasonable amount to be deducted
from the total claimed to
provide for these two items is R17 000 (excluding VAT),
representing R15 000 for the material
to be supplied and R2000
for the rendering of the service in relation thereto. This amounts to
R19 550 (inclusive of VAT),
leaving a balance due of R116 794
in respect of the 82 sheets supplied by Icon
.
[17].
To this total should be added a further
amount to provide for the additional six sheets required to complete
the roof. In that regard,
it will be recalled that the shortfall
amounted in total to 88 (half) of the total 176 sheets quoted for
initially by SM Structures.
In support of the claim relating to the
aforesaid, Grid Electronics relies on a further invoice from another
third-party supplier,
namely Freestock Steel Traders, dated 1
February 2021, for a total amount of R11 412.60 (inclusive of
VAT) for the supply
and delivery of eight 8.1m dove grey IBR 0.5mm
sheets, which total also includes the delivery charges. Mr White
confirmed the reasonableness
of these amounts, which, according to
him, were in fact a very good price if regard is had to the fact
that, at the time, there
was a shortage of
Chromadek
sheeting and that the prices were rising almost on a daily basis. He
described the R11 412.60 paid for the eight sheets as
a ‘top
price’. This then means that a reasonable price for six of the
sheets would have amounted to R8 599.45,
which should be added
to the R116 794 for the 80 sheets as per the calculation above,
giving a grand total of R125 393.45.
[18].
This, in my view, is
the correct calculation of the reasonable cost of remedying the
defective performance of SM Structures, which
translates into the
quantum of the general contractual damages suffered by Grid
Electronics as a result of the admitted breach
of the contract by SM
Structures. Lastly, from this total of R125 393.45, should be
deducted the balance outstanding on the
contract price, which had not
been paid by Grid Electronics, that being R21 775, leaving a
grand total of
R103 618.45
.
[19].
The reasoning behind
this deduction is simply that contractual damages is calculated on
the basis that a plaintiff should be placed
in the position he would
have been in had the breach not occurred. That would be accomplished
by supposing that Grid Electronics
would have paid the whole amount
of the contract price. A defendant would then be liable for the costs
of remedying the defective
performance on the assumption that the
full amount of the contract price had been paid.
In
casu
,
R21 775 had not been paid by Grid Electronics, hence the
deduction.
[20].
Mr Meintjies, the
attorney who appeared on behalf of SM Structures, submitted that the
calculation of the general damages should
be done on a basis
different from that on which Grid Electronics did it. He proposed
that the figures reflected on the invoice
from Freestock Steel
Traders – R9 687.60 (inclusive of VAT) for eight sheets,
therefore R1 210.95 for one sheet
– should be used as a
starting point and a basis for the calculation of the loss. He also
then introduces the square meterage
to be covered and on that basis
submits that the amount of the damages is R86 346, from which is
to be deducted R10 887
= R75 459.
[21].
I do not accept these
calculations nor the basis on which they were done, as they are not
supported by the evidence. Importantly,
Mr Mather confirmed during
his evidence, and this was not disputed, that the invoices from Icon
and Freestock Steel Traders were
in fact paid by Grid Electronics. Mr
White, the expert witness, testified that the prices were on the up
at the relevant time and
this trend was influenced by the fact that
it was becoming more and more difficult to source
Chromadek
roof sheeting. I am therefore inclined to accept the figures of Grid
Electronics as representing the reasonable prices and costs
relating
to the supply of the short supplied sheets and the charges relating
to its installation. The alternative postulation by
SM Structures
is not fact based and, in my view, is an artificial approach which
does not accord with the realities in the
matter.
[22].
In sum, the general
contractual damages suffered by Grid Electronics as a result of the
breach of the contract by SM Structures
amounted to R103 618.45.
[23].
That brings me to the
damages claim by Grid Electronics relating to the costs of hiring
alternative premises as a result of the
delay in the completion of
the structure by SM Structures. As indicated
supra
,
Grid Electronics claims an amount relating to the rental paid by them
for the period from 1 December 2020 to 31 March 2021 (a
four-month
period). By the time the trial commenced before me, SM Structures had
agreed that an amount of R428 506.08 represents
the fair and
reasonable rental payable by Grid Electronics during that period. The
only issue remaining in that regard was therefore
whether SM
Structures is legally liable to pay to Grid Electronics such outlay.
[24].
The
claim was pleaded by Grid Electronics as a claim for special /
consequential damages. However, in his written heads of argument
and
during closing argument, Mr Fouché, Counsel for Grid
Electronics, contended that this is in fact also a claim for general
damages. In that regard, I was referred to
Shatz
Investments (Pty) Ltd v Kalovyrnas
[1]
,
in which the Appellate Division held that where, in terms of a lease,
the premises are expressly let for a profit-making business,
loss of
profits may, on breach of the lease by the lessor, be recoverable in
appropriate circumstances. Such damages are ordinarily
regarded, not
as general damages, but as special damages.
A
fortiori
a claim for loss of goodwill on disposal of the business is a claim
for special damages. It is not a loss that generally flows
from a
breach of the lease of business premises. Consequently, so the AD
held, unless the plaintiff proves that the parties actually
or
presumptively contemplated that a loss of that kind would probably
ensue on such a breach, such damages are too remote and not
recoverable.
[25].
Importantly, the
court held at p550 as follows: -
‘
According
to these particulars, plaintiff's claim was not for (a) 'general
damages', but was for (b) 'special damages'. Sometimes
the
corresponding terms 'intrinsic' and 'extrinsic' damages are used (see
Pothier, Obligations, (Evans'
translation
, paras. 161 and 162), and
Whitfield v Phillips and Another
1957 (3) SA 318
(AD) at p. 329D – E). I use the former terms
here as well known, convenient labels to respectively differentiate,
broadly
and without any pretence at precision, between (a) those
damages that flow naturally and generally from the kind of breach of
contract
in question and which the law presumes that the parties
contemplated would result from such a breach, and (b) those damages
that,
although caused by the breach of contract, are ordinarily
regarded in law as being too remote to be recoverable, unless, in the
special circumstances attending the conclusion of the contract, the
parties actually or presumptively contemplated that they would
probably result from its breach (see
Lavery
and Co Ltd v Jungheinrich
1931 AD
156).
’
[26].
The decisive time for
ascertaining the parties' contemplation that such a loss would ensue
on breach of the contract is when they
contract and not when the
contract is breached. Not only must there have been common knowledge
that such a loss would ensue on
breach of the contract, but the
parties must have entered into the contract on the basis of such
knowledge.
[27].
I am of the view
that,
in
casu
, the
claim by Grid Electronics for a refund of the rental paid by them to
their erstwhile Lessor is special damages. To borrow
from
Shatz
Investments
,
‘that is not a loss that generally flows from such a breach’
of the agreement for the supply of material and the rendering
of
services. It is not an intrinsic loss, that being one affecting the
services rendered and material supplied agreement
per
se
, but an
extrinsic one, incidentally affecting the other business affairs of
the Grid Electronics, notably where they operate their
business from.
Its recoverability therefore depends upon the special circumstances
surrounding the conclusion of the agreement
in question to have been
known to SM Structures at the time the contract was concluded.
[28].
The main difficulty
that Grid Electronics have is that its cause of action in that regard
is not supported by the evidence. Importantly,
Mr Mather, when giving
evidence, indicated that during September 2019 he was searching
online for a supplier who could assist them
with the supply and
installation of a portal steel frame structure. He then received a
quote from SM Structures and that appears
to have been the sum total
of the engagement between the parties prior to the acceptance by Grid
Electronics of the final quote
from SM Structures. Moreover, Mr
Mather confirmed that Grid Electronics’ lease with its then
Lessor was to expire during
April 2020, but he confirmed that this
information was not conveyed to SM Structures at the time of the
conclusion of the agreement.
This issue was probably raised during
2020. The lease was in fact extended for a further period until 31
October 2020. However,
this does not assist Grid Electronics as the
parties ought to have contemplated the loss when the agreement was
concluded and not
afterwards.
[29].
The simple point is
that when Grid Electronics and SM Structures – especially the
latter – concluded the agreement there
must not only have been
common knowledge that such a loss would ensue on breach of the
contract, but the parties must have entered
into the contract on the
basis of such knowledge. In other words, the parties (especially SM
Structures) must have understood that,
in the event of the completion
of the structure being delayed, Grid Electronics would be forced to
continue renting alternative
premises at a costs of about R107 000
per month and that SM Structures would be liable to indemnify Grid
Electronics in respect
of such expenditure, which could amount to a
sum in excess of the actual contract price.
[30].
As I have already
indicated, the evidence does not support such an inference or such a
conclusion. In fact, on the probabilities,
it can safely be concluded
that, had Grid Electronics insisted on concluding the agreement on
that basis, SM Structures would not
have entered into the
arrangement. It would not have made business sense for SM Structures
to enter into such a contractual arrangement.
Moreover, and this is
instructive, Condition of Sale 18 of the agreement between the
parties expressly provides as follows:
‘
No
penalty clauses or a retention of our final balance will be
accepted’.
[31].
In sum, I do not
accept the submissions on behalf of Grid Electronics that the claim
by Grid Electronics to recover their additional
rental payments is a
claim for general / direct damages. In my judgment, those damages are
special / consequential damages. Grid
Electronics has not made out a
case entitling it to such damages. In particular, it has not proven
that there was common knowledge
between the parties that such a loss
would ensue on breach of the contract, nor have they proven that the
parties entered into
the contract on the basis of such knowledge and
understanding.
[32].
For all of these
reasons, I am of the view that the second claim by Grid Electronics
for damages should fail. This means that Grid
Electronics is entitled
only to a judgment in its favour for payment of the general damages
as calculated above.
Costs
[33].
The
general rule in matters of costs is that the successful party should
be given his costs, and this rule should not be departed
from except
where there are good grounds for doing so, such as misconduct on the
part of the successful party or other exceptional
circumstances. See:
Myers
v Abramson
[2]
.
[34].
I can think of no reason why I should
deviate from this general rule
in casu
.
[35].
The quantum of the damages awarded to Grid
Electronics does however fall well within the jurisdiction of the
Magistrates Court.
It would therefore be just and fair that it be
allowed to recover costs only on the appropriate Magistrates Court
scale.
Order
[36].
In the result, the order which I grant is
as follows: -
(1)
Judgment is
granted against the defendant in favour of the plaintiff for: -
(a)
-9Payment of
the sum of R103 618.45;
(b)
Payment of
interest on the amount of R103 618.45 at the applicable legal
interest rate of 7% per annum from date of service
of the summons,
being 7 May 2021, to date of final payment; and
(c)
Costs of suit
on the appropriate Magistrates Court scale.
L R ADAMS
Judge of the High
Court
Gauteng Division,
Johannesburg
HEARD ON:
22
nd
, 23
rd
and 24
th
January 2024
CLOSING ARGUMENT ON:
24
th
January 2024
JUDGMENT DATE:
12
th
July
2024
FOR THE PLAINTIFF:
Advocate Van Rhyn
Fouché
INSTRUCTED BY:
David Bayliss
Attorneys, Blairgowrie, Randburg
FOR
THE DEFENDANT:
Attorney
S J Meintjies
INSTRUCTED
BY:
Retief
& S J Meintjies Incorporated, Weltevreden Park, Roodepoort
[1]
Shatz
Investments (Pty) Ltd v Kalovyrnas
1976 (2) SA 545 (A).
[2]
Myers
v Abramson
,
1951(3) SA 438 (C) at 455
sino noindex
make_database footer start