Case Law[2024] ZAGPJHC 704South Africa
NV Properties (Pty) Limited v Myburgh N.O and Another (10409/2022) [2024] ZAGPJHC 704 (22 July 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
22 July 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 704
|
Noteup
|
LawCite
sino index
## NV Properties (Pty) Limited v Myburgh N.O and Another (10409/2022) [2024] ZAGPJHC 704 (22 July 2024)
NV Properties (Pty) Limited v Myburgh N.O and Another (10409/2022) [2024] ZAGPJHC 704 (22 July 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_704.html
sino date 22 July 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA,
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO: 10409/2022
1.
REPORTABLE: NO
2.
OF INTEREST TO OTHER JUDGES: NO
3.
REVISED: YES
22
July 2024
In
the matter between:
N
V PROPERTIES (PTY) LIMITED
Applicant
and
GARY
STEPHEN MYBURGH N.O
First Respondent
RADON
PROJECTS (PTY) LIMITED
Second Respondent
Judgment
Mdalana-Mayisela
J
Introduction
[1]
This is an application to review and set aside the arbitration award
made by the first respondent and published on 2 February
2022 (“final
arbitration award”) in his capacity as the arbitrator in
arbitration proceedings between the applicant
(employer and defendant
in the arbitration proceedings) and second respondent (contractor and
claimant in the arbitration proceedings).
The ground of the review is
that the first respondent committed a gross irregularity in the
conduct of the arbitration proceedings
and/or exceeded his powers as
contemplated in section 33(1)(b) of the Arbitration Act, No. 42 of
1965 (“the
Arbitration Act&rdquo
;).
[2]
The applicant also seeks the order replacing the first respondent as
the arbitrator in the arbitration proceedings with another
arbitrator
to be appointed in accordance with the method specified in clause
41.7.4 of the construction contract which is the subject
of the
arbitration proceedings; and the order correcting the arbitration
award.
[3]
The second respondent is opposing the review application and has
filed a counter - application in terms of Rule 6(7) of the
Uniform
Rules of Court seeking the order that the Court in terms of
section
31(2)
of the
Arbitration Act corrects
the clerical mistake or patent
error in the calculation of VAT in paragraph 44(a) of the final
arbitration award; and the
order making the final arbitration
award an order of court in terms of
section 31(1)
of the
Arbitration
Act.
[4]
The applicant is opposing the counter - application and has raised a
plea of
lis alibi pendens
on the ground that on 21 February
2022 the second respondent instituted an application to make a final
arbitration award an order
of court in the East London Circuit Local
Division of the High Court and the aforesaid application is still
pending.
[5]
The applicant has also brought a conditional interlocutory
application for an order granting the applicant a one-day extension
in terms of
section 38
of the arbitration Act, of the six-week period
which it had under
section 33(2)
of the
Arbitration Act within
which
to make the review application, being an extension from 16 March 2022
to 17 March 2022. The aforesaid order is sought only
in the event of
the Court finding that publication by the first respondent of the
final arbitration award to the parties in the
arbitration proceedings
which is the subject matter of the review application took place on 2
February 2022 and not on a subsequent
date; and that the applicant
made the review application on 17 March 2022 and not on 16 March
2022.
[6]
At the commencement of the proceedings I was advised by the parties
that they have reached an agreement that the publication
of the final
arbitration award was made on 2 February 2022, and the applicant
brought the review application on 17 March 2022.
It follows that the
conditional interlocutory application for a one-day extension of time
should be granted by agreement between
the parties. The parties also
agreed that the applicant be ordered to pay the costs of the
conditional interlocutory application,
including the costs of two
counsel on a party and party scale. They requested that the terms of
their agreement be included in
the main judgment.
Background
[7]
The background facts are common cause between the parties.
During
November 2017 the applicant and second respondent concluded a written
construction contract (“the contract”)
comprising of a
standard form JBCC Series 2000 (4
th
Edition, code 2101, March 2014) Principal Building Agreement (“the
PBA”) plus the following Annexures thereto: Annexure
A (the
agreed revisions/qualifications to the tender), Annexure B (the
provisional Bill of Quantities), Annexure C (the contract
award
document), Annexure D (the revised preliminary program documents),
Annexure E (the site possession certificate), and Annexure
F (the
waiver of the contractor’s lien document). The contract was for
the construction of a two (level) storey Convention
Centre, including
an Exhibition Hall, on the rear portion of erf 39719 in East London
and was signed by the second respondent on
6 November 2007 in East
London and was countersigned by the applicant on 22 November 2007 in
East London.
[8] The original
contractually agreed date for the practical completion of the works
to be carried out by the second respondent
in terms of the contract
was 17 October 2008. Possession of the site was given to the second
respondent on 6 November 2007 whereafter
it commenced with the works.
During the construction period the second respondent was granted
various revisions of the date for
practical completion from 17
October 2008 to 9 March 2009. On 14 December 2009 a certificate of
practical completion of the works
was issued.
[9] Clause 40 of the PBA
provides for a 2-phase disagreement/dispute process. Any disagreement
between the applicant or its agents,
on the one hand, and the second
respondent, on the other, arising out of or concerning the PBA is
processed as a “
disagreement
” in terms of clauses
40.1 to 40.3 thereof. If a disagreement becomes an (unresolved)
“
dispute
” as contemplated in clause 40.3 thereof,
it is thereafter processed as a “
dispute
” in terms
of clauses 40.4 to 40.7 thereof.
[10] After practical
completion of the works had been certified, the second respondent
referred 20 disputes contemplated in clause
40.4.3 of the PBA to
arbitration which, in terms of clause 40.5 thereof, had to be dealt
with in terms of the JBCC dispute resolution
procedures in clause
41.7 of the PBA. In terms of clause 41.7.4, the parties had agreed
that the arbitrator to be appointed for
the purposes of dispute
resolution under clause 40.4.3 thereof would be a mutually agreed
arbitrator appointed by the Association
of Arbitrators who was suited
to the nature of the dispute. The first respondent was mutually
appointed by the parties as the arbitrator
in terms of these
provisions on 14 November 2010. The matter before the first
respondent concerned several claims for extensions
of time for
practical completion and additional remuneration arising out of the
contract.
[11] During the course of
the arbitration the parties reached an agreement on claims 8, 17 and
41 which was made an interim award
by the arbitrator on 15 August
2014. By that stage, the second respondent had withdrawn claims 1, 5,
9, 10, 11, 12, 15, 16, 18,
19, 25 and 29, and the arbitrator was
required to determine the merits of claims 2, 4 and 27 (treated as
one claim), 24, 35 and
39 and quantum thereof. On 7 September 2015
and during a further hearing of the arbitration, the second
respondent abandoned/withdrew
claim 2, which at that stage reduced
the number of claims for merits determination to four.
[12] The evidence was led
and concluded on the merits of the four remaining claims at a hearing
from 15 to 26 February 2016. The
first respondent made the award on
the merits on 6 March 2017, wherein the second respondent was granted
an overall revision of
the date of practical completion from 9 March
2009 to 7 August 2009, plus a further 4 working days revision to 13
August 2009 in
respect of claim 39. All penalties imposed upon at the
time and including such revised date were reversed. The applicant was
directed
to cause an account to be drawn in accordance with the
merits award and to submit same to the second respondent for
consideration.
The second respondent was directed to respond to such
account.
[13] What remained was
the determination of the financial entitlements that accrued to the
second respondent as a consequence of
the revision of practical
completion date. The second stage of arbitration commenced to
determine the financial consequences of
the revisions of the date for
practical completion agreed to and granted during the first stage of
the arbitration, being from
9 March 2009 to 13 August 2009. The
applicant duly delivered an account as directed by the first
respondent, albeit in the nature
and form of submissions. In that
account the applicant also asserted that it would be inappropriate
for the first respondent to
make an award for payment of money and
that he should instead direct that certain entries be made in the
next interim payment certificate.
The second respondent also
responded by way of submissions. It asserted that it was entitled to
an award sounding in money. The
parties were unable to reach
agreement on the form of the award and the first respondent was
requested to make a determination
in respect of the outstanding
issues. Correspondence thereafter ensued between the parties, of
which I do not intend to refer to
it in this judgment, save for the
relevant correspondence which will be referred to under hereunder.
[14] On 2 February 2022
the first respondent published his final award, in which he ordered
the second respondent: (i) to pay an
amount of “
R6 442
59.34
” plus VAT at the standard rate of 15%; and (ii) to
pay the second respondent interest at the rate prescribed in terms of
the Prescribed Rate of Interest Act reckoned from 28 February 2018 to
date of payment.
Issues
[15] It is common cause
between the parties that in terms of the provisions of the
construction contract, and as a consequence of
the aforesaid revision
of the date for practical completion from 9 March 2009 213 August
2009, financial entitlements totaling
R6 442 593.39 accrued
to the second respondent, which amount represents the total of the
following three amounts: (i)
‘Preliminaries’ in the
amount of R2 793 326.58 excluding VAT; (ii) reversal of
‘Penalties’ in
the amount of R1 774 509,91
excluding VAT; and (iii) default interest in the amount of
R1 874 760.90 including
VAT.
[16] The issue in dispute
in this review application relates to the form of the final award the
first respondent made in relation
to the aforesaid financial
entitlements. The second respondent submitted that it was entitled to
an award sounding in money for
payment of the aforesaid amount
together with interest thereon to date of payment.
[17] The applicant
submitted that the appropriate method by which the first respondent
should have given effect to the financial
consequences of the
revisions of the date for practical completion agreed to and awarded
was to give an effective award to ensure
that such financial
consequences were processed by way of interim and/or final payment
certificates issued in terms of the payment
provisions of the
contract. It submitted that the first respondent in making the award
sounding in money for payment of the financial
entitlement accrued to
the second respondent committed a gross irregularity in the conduct
of the arbitration proceedings and/or
exceeded his powers as
contemplated in
ss 33(1)(b)
of the
Arbitration Act.
[18] Furthermore, the
applicant submitted during the arbitration proceedings, that it had
already given effect to the financial
consequences of the first
respondent’s award dated 6 March 2017 and that it had done so
in interim payment certificates 35,
47 and 48 and their accompanying
recovery statements.
Did the first
respondent commit any gross irregularity and/or exceed his powers
[19]
The applicant has brought the review application on the ground that
the first respondent committed a gross irregularity in
the conduct of
the arbitration proceedings and/or exceeded his powers. The applicant
bears the onus of persuading the Court to
review and set aside the
final arbitration award. S
ection 33(1) of the
Arbitration Act sets
out the grounds for review as follows:
(i)
where any member of the arbitration tribunal has
misconducted himself in relation to his or her duties as arbitrator
or umpire;
(ii) where an arbitration
tribunal has committed any gross irregularity in the conduct of the
arbitration proceedings or has exceeded
its powers; and
(iii) where an award has
been improperly obtained.
[20]
In
Rabinowitz
v Levy and Others
[1]
the Supreme Court of Appeal in relation to the interpretation of the
provisions of
section 33(1)
stated:
“
[14]
The provisions of section 33 of the Act are exhaustive of the grounds
of review of awards in consensual arbitrations. [16]
An aggrieved
party wishing to successfully review an arbitration award must bring
his or her case squarely within the four corners
of the relevant
provisions of s33 of the Act. The primary principle is that material
errors in an award, that is, errors which
lead to a party being
unsuccessful, are not reviewable, otherwise the distinction between
appeals and reviews would be eroded[17]
and s 33 of the Act
impermissibly becomes a right to appeal arbitration decisions[18]
[15] The ‘gross
irregularity’ required by s 33(1)(b) must relate to the conduct
of the proceedings, and not the result
or outcome of the
proceedings.[19] Thus, if an arbitrator is guilty of conducting an
arbitration in some form of high-handed or
arbitrary manner, or
dishonestly, he or she would be guilty of a gross irregularity. But a
bona fide mistake in respect of the
merits, no matter how gross, will
not suffice.[20] it is furthermore not every irregularity in the
conduct of the proceedings that
will afford grounds for review: the
irregularity must have been of such a serious nature that it resulted
in the aggrieved party
not having his case fully and fairly
determined.[21]
[16] In Lufuno
Mphaphuli and Associates v Andrews[22] the Constitutional Court held:
‘
At
Roman-Dutch law, it was always accepted that a submission to
arbitration was subject to an implied condition that the arbitrator
should proceed fairly or, as it is sometimes described, according to
law and justice. The recognition of such an implied condition
fits
snugly with modern constitutional values. In interpreting an
arbitration agreement, it should ordinarily be accepted that
when
parties submit to arbitration, they submit to a process they intend
should be fair.’
O’Regan ADCJ
cautioned that:
‘
It
seems to me that the values of our Constitution will not necessarily
best be served by interpreting s 33(1) in a manner that
enhances the
power of courts to set aside private arbitration awards … In
my view, and in the light of the reasoning in
the previous
paragraphs, the Constitution would require a court to construe these
grounds reasonably strictly in relation to private
arbitration ….
Courts should be respectful of the intentions of the parties in
relation to procedure. In so doing, they
should bear in mind the
purposes of private arbitration which include the fast and
cost-effective resolution of disputes. If courts
are too quick to
find fault with the manner in which an arbitration has been
conducted, and too willing to conclude that the faulty
procedure is
unfair or constitutes a gross irregularity within the meaning of s
33(1), the goals of private arbitration may well
be defeated.’[25]”
[21]
In
Telcordia
Technologies Inc v Telkom SA Ltd
[2]
the Supreme Court of Appeal held”
“
[52]
The term ‘exceeding its powers’ requires little by way of
elucidation and this statement by Lord Steyn says it
all:
‘
But
the issue was whether the tribunal “exceeded its powers”
within the meaning of s 68(2)(b) [of the English Act].
This required
the courts below to address the question whether the tribunal
purported to exercise a power which it did not have
or whether it
erroneously exercised a power that it did have. If it is merely a
case of erroneous exercise of power vesting in
the tribunal no excess
of power under s 68(2)(b) is involved. Once the matter is approached
correctly, it is clear that at the
highest in the present case, on
the currency point, there was no more than
erroneous
exercise of power available under s 48(4). The jurisdictional
challenge must therefore fail.”
[22] The applicant stated
that the first respondent committed a gross irregularity and/or
exceeded his powers by making a final
arbitration award for the
payment of the amount sounding in money which was incompetent as it
was inconsistent with his ruling
of 21 August 2015 (“2015
ruling”) and confirmed on 25 November 2017, and also by making
an award sounding in money
which the Practical Agent could not have
made and which was not permissible under the provisions of the PBA.
[23] The second
respondent contended that the 2015 ruling was not a ruling and it was
not binding as it had the words “
any order which I may make
”
thus describing something in the future. It has also contended that
if the Court finds that it is a ruling, then the applicant
must fail
on the basis that by unconditionally participating in the final leg
of the arbitration (in 2020 – 2022) which culminated
in the
final arbitration award, it forfeited the right to challenge the
final arbitration award on the basis of gross irregularity
or
exceeding of powers. Even if it is entitled to bring a review
application despite entrusting the first respondent with the
decision, it must fail for not proving any of its grounds of review
on either gross irregularity or exceeding of powers.
[24] The starting point
in determining whether the first respondent committed a gross
irregularity and/or exceeded his powers is
to interpret the 2015
letter to determine whether it is a decision and it is binding.
Clause 40.4.4 of the PBA provides that ‘
the arbitrator’s
decision shall be binding on the parties who shall give effect to it
without delay
.’
[25]
In
Frankel
Max Pollak Vinderine Inc v Menell Jack Hyman Rosenberg & Co Inc
and Others
[3]
the Appellate Division held:
“
The
general approach to the interpretation of a judgment or order of
Court was stated in Firestone South Africa (Pty) Ltd v Genticuro
AG
1977 (4) SA 298
(A) as follows (at 304D-H): ‘The basic
principle applicable to construing documents also apply to the
construction of a court’s
judgment or order: the court’s
intention is to be ascertained primarily from the language of the
judgment or order as construed
according to the usual, well - known
rules ….Thus, as in the case of a document, the judgment or
order and the court's reasons
for giving it must be read as a
whole in order to ascertain its
intention. If, on such a reading, the meaning of the judgment or
order is clear and unambiguous,
no extrinsic fact or evidence is
admissible to contradict, vary, qualify, or supplement it. Indeed, it
was common cause that in
such a case not even the court that gave the
judgment or order can be asked to state what its subjective intention
was in giving
it…. Of course, different considerations apply
when, not the construction, but the correction of a judgment or order
is
sought by way of an appeal against it or otherwise - see infra.
But if any uncertainty in meaning does emerge, the extrinsic
circumstances
surrounding or leading up to the court's granting the
judgment or order may be investigated and regarded in order to
clarify it;
for example, if the meaning of a judgment or order
granted on an appeal is uncertain, the judgment or order of the court
a quo
and its reasons therefore, can be
used to elucidate it. If, despite that,
the uncertainty still persists, other relevant extrinsic facts of
evidence are admissible
to resolve it. (Per Trollip JA.) (See also
Administrator, Cape, and another v Ntshwa-qela and Others
1990 (1) SA
705
(A) at 715F – 716C; Weber – Stephen Products Co v
Alrite Engineering (Pty) Ltd and Others
[1992] ZASCA 2
;
1992 (2) SA 489
(A) at
494E-H.) The correction of a judgment is dealt with more fully by
Trollip JA in the Firestone case at 306F – 307E.
It is to this
passage that the notation ‘see infra’ refers. (See also
Friedman v Mandes
1976 (4) SA 734
(W) at 736C – F; S v Wells
1990 (1) SA 816
(A) at 819J – 820G.) I am of the view that in
general the same principles apply to the interpretation of an
arbitrator’s
award, particularly where, as in this case, the
award has been made an order of Court (,cf Friedman v Mendes (supra)”
[26] The 2015 ruling
reads as follows:
“…
..
Subject:
Radon Properties, RULING: Financial consequences.
Importance: High
Good morning
gentlemen,
I
have again reviewed the competing submissions which I have received
regarding the claimant’s financial entitlement/s arising
out of
the extension
which has so far been
granted. I have also reviewed the pleadings and the relevant
authorities.
As the position
currently stands it seems to me that there is consensus save in
relation to the form which the award should take.
The claimant seeks an
award in a fixed amount of money whereas the defendant contends that
I ought to make an award which is more
in the nature of a declarator.
Having
reviewed the authorities and, as I say, the pleadings, the view which
I have reached is that it would not be proper for me
to make an award
which could be construed is creating a debt outside of the ambit of
the contract. That is to say, I am in agreement
that any order which
I may make would essentially be in the nature of directives as to how
matters had to be dealt with in the final
account and related documentation as opposed to a “free
standing” award which
could be enforced outside of the
contractual framework. As I have previously pointed out, authority
for this approach is to be
found in several decisions, in particular
see the Shelagatha case and also Oua Oua Ree………
v Martin Harris
& Sons OFS
2000 (3) SA 353.
To this I would add
that the claim in the pleadings is not for a lump sum by rather for
reversal of penalties, additional time related
costs, additional
escalation and the like.
The claimant is hereby
requested to prepare a draft award following the principles outlined
above and to submit same to the defendant
for consideration.
If the parties are
able to reach agreement, then I will make a partial award by
agreement. Alternatively, to the extent that the
parties may not be
able to agree the terms of the order I will then decide whatever
issues remain and make a further partial award.
……
..”
[27] The intention of the
first respondent is to be ascertained primarily from the language of
the document. The heading of the
document is “
RULING:
Financial consequences
”. At the beginning he refers to the
competing submissions made by the parties on the form of the award to
be made in relation
to financial entitlement/s. Then he stated that
he has reached a view that it would not be proper for him to make an
award which
could be construed as creating a debt outside of the
ambit of the contract. That is to say, he is in agreement that any
order which
he may make would essentially be in the nature of
directives as to how matters are to be dealt with in the final
account and related
documentation. He gave reasons supported by
authorities for his view. He concluded by directing the second
respondent to prepare
a draft award following the principles outlined
in the ruling and to submit same to the defendant for consideration.
[28] The meaning of the
abovementioned document is clear and unambiguous, and it requires no
extrinsic evidence for its interpretation.
From its language, it is
clear that the view that the first respondent has reached is not
prima facie and it is not a guideline.
In my view the first
respondent has made a decision in relation to the form which the
award should take. The words “any order
which I may make”
relates to the award to be made in future in relation to financial
entitlement/s and not the form of the
award. It is clear from the
language of the abovementioned document that the first respondent
intended it to be a ruling and accordingly
it remains binding on the
parties.
[29] The first respondent
has confirmed his decision on the form of the award in the letter to
the parties dated 25 November 2017,
wherein he stated:
“…
.
In a letter received from the claimant representatives dated 18
October 2017 I was requested to issue an interim award on the
“crisp
issue” of whether I consider myself to have the jurisdiction to
make a “final award sounding in money”.
I do not believe that
the question posed can properly form the subject matter of an interim
award; However, I do believe that it
would facilitate
the final
resolution
(my emphasis) of this matter if I were to indicate
what I consider the extent of my jurisdiction to be – with
specific reference
to the issue in question. That then is the purpose
of this letter.
Having again reviewed
the competing submissions and having researched the authorities I
have to advise that I do not consider that
I have the jurisdiction to
make an award sounding in money which would be capable of being
enforced independently of the payment
in accounting mechanisms
provided for in the contract. While I do not think it necessary to
adumbrate at length given the nature
of this communication I believe
it appropriate to record that the suggestion that claims for payment
arising in the course of a
contract of this kind can arise
independently of the payment regime or not be susceptible to
discharge by way of latter certificates
runs directly contrary to
established jurisprudence, including decisions of the Supreme Court
of Appeal - by way of example
the decision in the Shelagetha
case.
……
..
So that there should be no misunderstanding, I do consider my
jurisdiction and powers to extend to directing the defendant to
include certain amounts in subsequent interim certificates and/or a
final account and/or payment certificate - this even though
I do not
have jurisdiction to consider the validity of any entries which may
appear in those documents which do not form the subject
of any of the
disputes which form the subject of this reference.
I trust this will
assist the parties in reaching a final settlement…..”
[30]
Having made a finding that the 2015 letter is a ruling and binding on
the parties, I now turn to the question whether the applicant
has
proved that the first respondent committed a gross irregularity in
the conduct of the arbitration proceedings. The applicant
contended
that the first respondent committed a gross irregularity in making an
award for payment of the amount sounding in money
contrary to his
2015 ruling and November 2017 view. The applicant has not tendered
any evidence showing that the first respondent
committed a gross
irregularity in the conduct of the arbitration proceedings. Its
complaint does not relate to the method of arbitration
proceedings
but to the result thereof. Such complaint cannot support a review
application on the ground of gross irregularity in
the conduct of the
proceedings.
[4]
In the result
this ground of review must fail.
[32] I now deal with the
question whether the first respondent has exceeded his powers in
making an award for payment of amount
sounding in money in the final
arbitration award. The first respondent stated in his 2015 ruling and
November 2017 letter that
he did not have a jurisdiction to make a
“
free standing
” award which could be enforced
outside of the contractual framework and that he considered his
jurisdiction and power to
extend to directing the applicant to
include certain amounts in subsequent interim certificates and/or a
final account and/or payment
certificate.
[33] He added that the
second respondent’s claim in the pleadings is not for a lump
sum but rather for reversal of the penalties,
additional time related
costs, additional escalation and the like. He made the award on the
merits of the remaining claims in accordance
with the aforesaid
ruling.
[34]
The award of payment of a lump sum and an amount sounding in money is
inconsistent with the 2015 ruling which was binding on
the first
respondent, and November 2017 letter. Furthermore, the first
respondent could only award that which was in accordance
with the
terms of reference. He does not have inherent jurisdiction to decide
matters which are not pleaded.
[5]
By making the aforesaid award the first respondent purported to
exercise a power that he did not have. The jurisdictional challenge
must therefore succeed.
[35] The second
respondent has argued that the applicant was supposed to raise its
objection to the first respondent’s jurisdiction
at the outset.
It could not simply proceed to participate in the arbitration
proceedings with a view to raising the jurisdictional
point should
the arbitration turn out unfavourably. This argument is without
merit. The jurisdictional challenge by the applicant
is related to
the result of the arbitration proceedings. There was no ground for
the applicant to raise an objection to the first
respondent’s
jurisdiction before the final arbitration award was made.
Furthermore, it is common cause that the applicant
has always taken a
position during the arbitration proceedings that the first respondent
could only make an award in the form of
a declarator or directive in
relation to the second respondent’s financial entitlement/s.
[36] For the reasons
stated above, I conclude that the first respondent exceeded his
powers in making a final arbitration award
for a payment of a lump
sum and an amount sounding in money in relation to the second
respondent’s financial entitlements.
Accordingly, the final
arbitration award stands to be reviewed and set aside.
[37] In prayer 2 of the
notice of motion the applicant has sought an order replacing the
first respondent as the arbitrator in the
arbitration proceedings
with another arbitrator to be appointed in accordance with the method
specified in clause 41.7.4 of the
contract.
Section 33(4)
of the
Arbitration Act provides
that if the award is set aside the dispute
shall, at the request of either party, be submitted to a new
arbitration tribunal constituted
in the manner directed by the court.
Considering the reasons for reviewing and setting aside the final
arbitration award stated
above, I am inclined to grant prayer 2 of
the notice of motion.
[38] The applicant in
prayer 3 of the notice of motion has sought an order correcting the
final arbitration award. In effect,
the applicant has sought
the substitution order recording that during the course of the
arbitration proceedings, it had already
given effect to the financial
consequences of the first respondent’s award dated 6 March 2017
and that it had done so in
interim payment certificates 35, 47 and 48
and their accompanying recovery statements. The applicant relied on
the aforesaid documents
in its heads of argument and final draft
order filed in the arbitration proceedings.
[39]
I am not inclined to grant the substitution order for the following
reasons. The second respondent objected to the applicant
leading
evidence on the aforesaid interim payment certificates in the
arbitration proceedings on the basis that they are irrelevant,
inadmissible and prejudicial to the second respondent, and as a
result the evidence on the aforesaid documents was not led. The
aforesaid documents were not before the first respondent, and they
could not be considered in making the final arbitration award.
It is
common cause between the parties that the relief sought in prayer 3
was not pleaded in the arbitration proceedings. It is
trite that the
parties are limited to their pleadings and are bound by them.
[6]
Costs of the review
application
[40] The applicant is
substantially successful in the review application and is accordingly
entitled to costs of the review application
on a party and party
scale.
Counter - application
[41] The second
respondent has sought an order, in terms of
s 31(2)
of the
Arbitration Act, correcting
the clerical mistake or patent error in
the final arbitration award to reflect the corrected VAT calculation.
It has also sought
an order for the final arbitration award to be
made an order of the Court in terms of
section 31(1).
[42] Considering the
conclusion I have reached in the review application, the counter -
application has become moot and it stands
to be dismissed. The
applicant has not sought the costs of the counter –
application.
Order
[43] In the premises, the
following order is made:
1.
The
arbitration award made by the first respondent and published on 2
February 2022 in his capacity as the arbitrator in the arbitration
proceedings between the applicant and second respondent is hereby
reviewed and set aside.
2.
The first respondent is replaced with
another arbitrator to be appointed in accordance with the method
specified in clause 41.7.4
of the contract.
3.
The second respondent is ordered to pay the
costs of the review application on a party and party scale.
4.
The counter – application brought by
the second respondent is dismissed.
5.
The conditional interlocutory application
for extension of time in terms of
section 38
of the
Arbitration Act
42 of 1965
is granted.
6.
The applicant is ordered to pay the costs
of the conditional interlocutory application on a party and party
scale.
MMP
Mdalana-Mayisela J
Judge
of the High Court
Gauteng
Division,
Johannesburg
DELIVERED:
This judgment was handed down electronically by circulation to the
parties’ legal representatives by e-mail and
publication on
CaseLines. The date for hand-down is deemed to be on 22 July 2024.
Appearances:
For
the Applicant:
Adv M A Crowe SC
Instructed
by:
Bax Kaplan Russell Inc
For
the Second Respondent: Adv C H J
Badenhorst SC
Adv D J Joubert
Instructed
by:
Klagsbrun Edelstein Bosman Du Plessis Inc
[1]
(1276/2022)[2024]
ZASCA 8 (26 January 2024).
[2]
2007
(3) SA 266 (SCA).
[3]
[1996] ZASCA 21
;
1996
(3) SA 355
(A) at 362E-I.
[4]
Bester v Easigas (Pty) Ltd and Another
1993 (1) SA 30
C at 43B-D.
[5]
Hos+Med
Medical Aid Scheme v Thebe Ya Bophelo Healthcare Marketing &
Consulting (Pty) Ltd and Others
[2007] ZASCA 163
;
2008 (2) SA 608
(SCA) at paras 28 &
30.
[6]
Hanger
v Regal and Another
2015 (3) SA 115
(FS) at para 10-11.
sino noindex
make_database footer start
Similar Cases
NV Properties (Pty) Limited v Myburgh and Another (10409/2022) [2024] ZAGPJHC 1071 (9 October 2024)
[2024] ZAGPJHC 1071High Court of South Africa (Gauteng Division, Johannesburg)100% similar
YG Properties Investments (Pty) Ltd v Ekurhuleni Metropolitan Municipality and Another (Leave to Appeal Application) (2023/059368) [2024] ZAGPJHC 799 (13 August 2024)
[2024] ZAGPJHC 799High Court of South Africa (Gauteng Division, Johannesburg)99% similar
MI Property Holdings (Pty) Ltd and Another v Tshabalala and Others (2021/11293) [2025] ZAGPJHC 993 (17 September 2025)
[2025] ZAGPJHC 993High Court of South Africa (Gauteng Division, Johannesburg)99% similar
N.S.F v R.H.F (2024/060778) [2025] ZAGPJHC 534 (2 June 2025)
[2025] ZAGPJHC 534High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Securitization Program (RF) Limited and Others v Maxidor SA (Pty) Ltd and Others (2022/8473) [2024] ZAGPJHC 669 (25 July 2024)
[2024] ZAGPJHC 669High Court of South Africa (Gauteng Division, Johannesburg)99% similar