Case Law[2024] ZAGPJHC 774South Africa
Zethu Consulting Services (Pty) Ltd v Ekurhuleni Metropolitan Municipality and Others (46470/2021) [2024] ZAGPJHC 774 (6 August 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
6 August 2024
Headnotes
in a recently decided case, Transnet SOC Ltd[3] the case law suggest that the merits of the review must be dealt with before dealing with the issue of delay. Sutherland DJP usefully
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 774
|
Noteup
|
LawCite
sino index
## Zethu Consulting Services (Pty) Ltd v Ekurhuleni Metropolitan Municipality and Others (46470/2021) [2024] ZAGPJHC 774 (6 August 2024)
Zethu Consulting Services (Pty) Ltd v Ekurhuleni Metropolitan Municipality and Others (46470/2021) [2024] ZAGPJHC 774 (6 August 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_774.html
sino date 6 August 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NO:
46470/2021
1. REPORTABLE: NO
2. OF INTEREST TO OTHER
JUDGES: NO
3. REVISED: NO
06/08/2024
In
the matter between:
ZETHU
CONSULTING SERVICES (PTY) LTD
Applicant
and
EKURHULENI
METROPOLITAN MUNICIPALITY
First
Respondent
DR
IMOGEN MASHAZI
N.O
Second
Respondent
CHIDI
MANYANE
N.O
Third
Respondent
MABELA
JONATHAN
N.O.
Fourth
Respondent
ADV
MOEKETSI MOTSAPI
N.O
Fifth
Respondent
JUDGMENT
MANOIM J:
Introduction
[1]
This matter involves a payment dispute for services rendered by the
applicant, Zethu Consulting Services Pty Ltd (“Zethu”),
to the first respondent, the Ekurhuleni Metropolitan Municipality
(“the Municipality”).
[1]
In the main application Zethu claims payment of several outstanding
invoices which amount to R 16 891 186.85 for services
it
performed on three projects for the Municipality.
[2]
But in a counter application, the Municipality seeks to review
Zethu’s appointment to perform these projects and to reclaim
an
amount of R 23 383 775.43 already paid to it.
Background
[2]
In July 2016, the Municipality issued a tender for consultants to
render consulting services to the Municipality’s
Real Estate
Department. The successful tenderer would be appointed to the
Departments Technical Resource Team (“TRT”).
The bid
specified that the consultant should comprise a multi-disciplinary
team who would be utilised on an “…
as and when
required basis
.”
[3]
Zethu is a consulting company comprising a number of professionals in
a range of disciplines pertaining to the built environment.
It
submitted a bid in August 2016 and was successful because it was
appointed to the TRT in November 2016. This appointment is
not the
subject of the review challenge by the Municipality. What is being
challenged are its subsequent appointments to the three
projects.
[4]
The first project Zethu performed for which it charged a fee was what
is known as the asset verification project. The
Municipality owns a
large number of properties and needed to verify its ownership of
these properties. Zethu claims to have performed
this service and to
have verified a large number of properties. The work was performed
over a period commencing July 2017 until
April 2019.
[5]
Zethu invoiced the Municipality regularly over this period. The
Municipality paid Zethu a total of R18 821 207.93 for
the project.
This amount was paid in respect of five invoices rendered between
February and November 2018. In the counter-claim
the Municipality
seeks repayment of this amount.
[6]
But Zethu also billed the Municipality again for services rendered on
this project in April 2019. This invoice, the sixth,
was for R
2 383 161.10 and remains unpaid. In the main application
Zethu seeks payment of this amount. The Municipality
opposes this
claim.
[7]
In September 2018 Zethu was appointed to plan, organise, and carry
out what is referred to as a Public Private Partnership
(“PPP”)
Investor Summit. This is the second challenged project. The investor
summit was to be an event for one thousand
delegates and was to take
place at the end of the year. The summit never took place. Zethu
claims it does not know why the summit
was cancelled but nevertheless
at the time of the cancellation it had performed a substantial part
of the work or as it describes
it, ‘
the front-end work
.’
Zethu billed the Municipality for R7.1 million for these services.
The Municipality has previously paid R4 562 567,50
for this
work. Zethu now seeks payment of the balance - an amount of R
2 453 367.68. The Municipality opposes the claim
and claims
repayment of the amount paid i.e., R4 562 567.50.
[8]
On 25 November 2028 Zethu was appointed to the third challenged
project, referred to as the Germiston Valuation and Scenario
Analysis
project. This project involved six sites in Germiston. The project
was to achieve three things for the Municipality. To
confirm the
ownership of buildings, to perform a valuation of them, and to
perform an options analysis. Zethu invoiced the Municipality
R 11
million for the work it says it did on the project. Although
initially invoicing in two separate invoices for this amount,
Zethu
was told by Ms Jonathan, an official in the Real Estate Department of
the Municipality, to divide the total invoiced amount
into six
invoices - one for each of the six sites.
[9]
It is common cause that all the invoices for which Zethu claims
payment in the main application remain unpaid. However,
the
Municipality denies that Zethu was validly appointed to perform these
projects. This is the basis for the counter-claim in
which it seeks
to review the award of the contracts and consequently seeks repayment
of the amounts it has already paid to Zethu
in respect of them. The
total amount re-claimed in the counter-claim is R23 383 775.43, made
up as follows:
a.
R18
821 207.93 paid to Zethu in respect of the Physical Asset
Verification project; and
b.
R4,562
567.50 paid to Zethu in respect of the PPP Investor Conference.
Issues
to be decided
[10]
Given the counter-claim, the first issue to be decided is the
Municipality’s review. Zethu has vigorously contended
that the
review has been brought too late. Intuitively it would make sense to
consider the issue of lateness first. But as Sutherland
DJP has held
in a recently decided case,
Transnet
SOC Ltd
[3]
the
case law suggest that the merits of the review must be dealt with
before dealing with the issue of delay. Sutherland DJP usefully
identifies five features that emerge from these cases, which are:
17.1 it is improper to
deal with delay before giving attention to the merits of the review,
17.2 where invalidity
is indeed detected, it must be declared to be so,
17.3 the merits are
relevant to what to choose to do about an undue delay when that is
found to exist,
17.4 whether or not to
overlook undue delay is a flexible evaluation which is driven by
several factors,
17.5 undue delay is
bound up in the just and equitable remedy which may be that no
consequent relief is granted; i.e., the
review might succeed but
the contracts are not set aside.
[11]
I will follow this approach and consider the merits of the review
before I consider the delay.
Review
merits
[12]
The deponent to the Municipality’s affidavit is Davey Frank,
the Head of its Legal Service Division. Frank does
not have personal
knowledge of the facts in this case but to the extent that is
necessary, supporting affidavits have been filed
by a Mr Thando Miti
and a Ms Mabelo Jonathan, who at the relevant time were variously the
divisional heads and heads of department
of the Municipalities’
Real Estate Development Department, which was the Department
responsible for authorising the contracts
that the Municipality now
seeks to set aside. Jonathan is the fourth respondent in this matter.
Miti is no longer employed by the
Municipality.
Review
[13]
The Municipality alleges that the appointments are reviewable on
several grounds.
[14]
The first ground of review concerns the validity of the appointment.
The Municipality whilst conceding that Zethu was
validly appointed to
serve on the TRT panel, denies that this extended to its appointment
in respect of the three projects.
[15]
It is common cause that Zethu, along with two other firms, was
appointed subsequent to a bidding process under a contract
referred
to as PS-RE39-216. The contract sets out the terms of the services
for which the successful tenderers were appointed.
[16]
The Municipality wanted a multi-disciplinary team to assist it with
procurement related activities. But it argues that
none of the
projects fell within this scope.
[17]
I agree. On a strict construction of the tender document the
Municipality is correct. The services rendered are not contemplated
in the document and hence on that ground alone the appointment to
perform the three projects was not properly authorised and was
irregular.
[18]
The next question is whether there is any justification for giving
the contract a more expansive meaning so as to contemplate
one or
more of the projects. But it must be borne in mind that this is a
contract given by an organ of state following a public
tender. If the
Municipality can freely adopt an expansive reading of the contract,
it has two dangers.
[19]
The first is that if the tender made it clear that these other
services were contemplated, other firms might well have
tendered.
Tender terms must be transparent so that competitors know they can
compete for it. If others can compete for a tender,
then it is
possible that lower prices can be achieved. This obligation to draft
contracts in clear terms is what is required by
the Constitution.
Section 217 of the Constitution requires organs of state when
contracting for services to do so in a manner that
is “…
fair, equitable transparent, competitive and cost effective”
.
The second, and is evident in this case, is that if the terms of a
contract can be interpreted more expansively than the literal
terms
of the text suggests, officials can expand upon the remit of a
favoured firm, to include services that the firm was
not appointed to
perform, to the detriment of the ratepayers of the municipality
because the services were not subject to a competitive
tender and
hence the possibility of lower prices or superior services.
[20]
The second ground of review is that the Municipality alleges that
there was non-compliance with the Local Government
Municipal Finance
Management Act 56 of 2003 (MFMA). In terms of section 15 of the MFMA:
“
15.
A
municipality may, except where otherwise provided in this Act, incur
expenditure only—
(a) in terms of an
approved budget; and
(b) within the limits
of the amounts appropriated for the different votes in an approved
budget
.
[21]
What constitutes a vote is also a defined term:
‘‘
vote’’
means—
(a) one of the main
segments into which a budget of a municipality is divided for the
appropriation of money for the different departments
or functional
areas of the municipality; and
(b) which specifies
the total amount that is appropriated for the purposes of the
department or functional area concerned.
[22]
This statutory requirement is premised on the constitutional
injunction in terms of section 215 of the Constitution which
requires
municipal budgetary processes to “…
promote
transparency, accountability and the effective management of the
economy, debt and the public sector.”
[23]
It is the Municipality’s case that the none of the projects had
been budgeted for and hence the expenditure was
not made in terms of
an approved budget and were in contravention of section 15 of the
MFMA.
[24]
Zethu has not been able to satisfactorily refute these contentions
despite its denial. A belated attempt by counsel to
argue that a
broad approval of funding made in terms of the budget constituted
compliance with section 15 as it constituted a vote
was not
convincing. It is clear that the definition of what constitutes a
vote requires more detail than this. To interpret it
otherwise would
provide a loophole for a Municipality to escape proper scrutiny of
its expenditure.
[25]
The third ground of review relates to the absence of what is termed a
‘gap analysis.’ The Municipality employs
a large staff
with different skill sets in its various departments. This means it
can provide a wide range of services which it
might require from its
own staff complement. If it wants to appoint outside parties to
perform services, it must justify why they
cannot be performed
in-house. This is what is meant by a gap analysis, and it must be
done before those services are outsourced.
But no gap analysis was
performed in respect of any of the projects. The Municipality
suggests that the finance department could
have performed the asset
verification services whilst its Communications Department could have
organised the PPP conference.
[26]
Whether or not this is so I cannot decide definitively but there was
no gap analysis and since this is a necessary requirement
its absence
too renders the appointments irregular.
[27]
The fourth ground of review is that the Municipality has adopted a
Standard Operating Procedure (“SOP”) for
the approval of
projects. This procedure according to Frank is known to those
participating in tenders and would have been known
to Zethu. In terms
of this SOP there are eight steps to be followed for the approval of
a project and if any of them is not followed
the project is not
valid. Again, in the case of all three projects the SOP was not
followed.
[28]
There are thus four independent grounds on which the appointment of
Zethu to perform the services has been effectively
challenged. Zethu
has argued that these have amounted to internal procedures. It could
not have known there was non-compliance.
This is an argument premised
on estoppel. But the courts have rejected this type of argument in
procurement cases involving an
organ of state. Thus, in
City of
Tshwane
the SCA stated:
“
It is settled
law that a state of affairs prohibited by law in the public interest
cannot be perpetuated by reliance upon the doctrine
of estoppel for
to do so would be to compel the defendant to do something that the
statute does not allow it to do. In effect therefore
it would be
compelled to commit an illegality.”
[4]
[29]
It is a matter of dispute in this matter whether Zethu was misled by
insiders in the Municipality’s Real Estate
Department (“RED”)
that all formalities to authorise or regularise the projects had been
observed. Again, in
City of Tshwane
the SCA says this does not
alter the fact that the contracts were unlawful. As the court put it:
“
The fact that
the plaintiff was misled into believing that the defendant's
employees were authorised to vary an agreement that had
earlier been
lawfully concluded with it, can hardly operate to deprive the
defendant of that power which had been bestowed upon
it by the
legislature. To do so would be to deprive the ultra vires doctrine of
any meaningful effect.'
[5]
[30]
I thus conclude that the Municipality has raised cogent grounds for
reviewing the validity of the award of the projects.
I now go on to
consider the issue of undue delay.
Undue
delay
[31]
Zethu argued the review should not be considered because the
Municipality had only brought the review by way of a counter-claim
and then only many years after it had been appointed to perform the
contracts. The Municipality seeks condonation for the late
filing of
its review.
[32]
To decide whether there has been undue delay one must first determine
when the clock starts running. Zethu has relied
on the awarding or
completion of the projects to determine when the clock starts. Set
against this timeline the delay is lengthy.
Thus, based on this
clock, the Physical asset verification project was reviewed after a
delay of 4 years eight months, the Germiston
Project 3 years and 4
months and the PPP Investor summit 3 year and 5 months.
[6]
[33]
But Frank sets the clock to run from a much later date. His reasoning
is premised on the fact that insiders had prevented
the Municipality
from finding out about the services. It was only when the ‘outsiders’
had been made aware of the irregularities
that they were able to act.
As he put it in his affidavit requesting condonation for the late
review:
“
I am advised
and submit that the period for which the clock begins to run for the
purposes of calculating whether there was an undue
delay, starts at
the moment a litigant becomes aware of the facts giving rise to the
grounds of review or the moment a litigant
reasonably ought to have
been aware of such facts.”
[34]
And he goes to say that the Municipality only became aware of the
facts that gave rise to the review when it received
the application
on 30 September 2021. It then acted immediately as he explains:
“
Not long after
receipt thereof, the Municipality instructed its attorneys and, with
their assistance, began to investigate the Applicant's
claims and the
circumstances that led to the Applicant's appointment to the three
projects that did not fall within the type of
works contemplated for
the TRT consultants and in respect of which there was no budget
allocation. Extensive and several consultations
were conducted with
officials that were directly involved in the alleged transactions,
some of whom have left the employment with
the Municipality, as well
as some of the officials who reported to them. In that process, it
became apparent that several documents
would be required from the
Applicant which are not provided in its founding papers, but
expressly mentioned and/or alluded to therein.
A rule 35(12) and (14)
notice was accordingly issued calling upon the Applicant to provide
certain documents listed in the notice.”
[35]
This leads him to justify when the clock should be deemed to have
started running:
“
Therefore, the
point in time that must be used to determine whether there was undue
delay in instituting the review is sometime
during January 2022, when
a clearer picture of the fundamental irregularities associated with
the alleged transactions emerged
and became apparent to the
Municipality. With all that information obtained, the answering
affidavit could be prepared and finalised,
and a copy thereof was
served on the Applicant's attorneys on 11 February 2022. In the
circumstances, it cannot be said that there
was a delay in
instituting the counter-application, let alone an inordinate delay.”
[36]
Neither party disputes the time calculations made by the other. What
they dispute is the principle – when is it
justifiable to start
the clock? As Theron JA put it in
Buffalo City:
“…
the
proverbial clock starts running from the date that the applicant
became aware or reasonably ought to have become aware of the
action
taken
.”
[7]
[37]
I accept that this is a case where knowledge of the irregularity was
concealed by insiders in the Municipality until
the present
application was brought. Only then did the claims for payment become
evident to those I term ‘outsiders’
i.e. persons without
any involvement in the appointments or management of Zethu, and who
are charged by their obligations to the
Municipality, to ensure that
its processes are complied with. The time from when they acquired
this knowledge – was just
over four months.
[38]
In terms of
Buffalo
City,
the explanation for the delay must cover the entire period of the
delay.
[8]
But given that an
investigation had to take place, before legal advisors could be
briefed, including the need to get documents,
I accept that this
satisfactorily explains the four-month delay.
[39]
Moreover, also as Keightley J held in
SABC
following the
Buffalo
City
approach noted: “
Even
if the delay is unreasonable the court retains a discretion to
overlook it.”
[9]
[40]
While in this case I do not consider the delay unreasonable, if I am
wrong on this, the importance of exercising a discretion
to overlook
the delay is that the Municipality is taking steps to prevent the
unlawful use of tenders that bypass its procedures.
As Francis J held
in
Swifambo
:
“
In my view
state institutions should not be discouraged from ferreting out and
prosecuting corruption because of delay, particularly
not where there
has been obfuscation and interference by individuals within the
institution.”
[10]
[41]
I find that the delay in bringing the review has been justified, and
further as to the merits of the review, I find that
although the
appointment of Zethu to the TRT panel was valid, the appointments to
the three projects were not. But this does not
decide the matter
definitively. It is still necessary to consider in terms of section
172 of the Constitution a just and equitable
remedy.
Just
and equitable
[42]
In
Allpay
the Constitutional Court stated:
“
Once a finding
of invalidity . . . is made, the affected decision or conduct must be
declared unlawful and a just and equitable
order must be made”
[11]
[43]
The court went on to state:
“
Any contract
that flows from the constitutional and statutory procurement
framework is concluded not on the state entity's behalf,
but on the
public's behalf. The interests of those most closely associated with
the benefits of that contract must be given due
weight.”
[12]
[44]
The Municipality was of the view that there was no basis for
considering just and equitable relief in respect of any
of the
projects that favoured it making any payment to Zethu, and hence all
amounts paid to Zethu should be repaid, whilst the
Municipality was
entitled to an order that it was not required to pay any of the
outstanding invoices. Zethu took the opposite
view.
[45]
I consider the best approach to evaluating a just and equitable order
is to consider each project separately. Whilst
they were all subject
to invalidity on the same considerations, the facts show that each
had distinctive features that are relevant
to a just and equitable
consideration.
[46]
Nevertheless, I have had regard in doing this evaluation to the
following issues: the proximity of the service provided
to the terms
of the original tender for which Zethu was validly retained: the
extent to which the ongoing work was queried by officials
of the
Municipality in communications with Zethu; whether the service, where
it was performed, was of value to the Municipality;
any indications
of impropriety in the actions of Zethu.
Germiston
Project
[47]
On Zethu’s version this project was initiated at great haste.
The ‘invitation to perform work’
(IPW) was issued
on 10 October 2018, and it indicated that the fees were estimated as
R 53 269 500 excluding VAT. Miti
was responsible for its
issue. Zethu was then appointed on 25 November 2018 by way of a “…
full verbal brief
” given “
on site
”.
The first deliverable was to be done by 27 November i.e., two days
after the verbal brief. The next deliverable was a draft
inception
report to be delivered on 6 December 2018 which Zethu claims it did.
Ms Jonathan was apparently satisfied with this at
the time.
[48]
Matters came unstuck thereafter. The narrative of the interactions
between Zethu’s project manager, a Mr Ndlovu,
and Ms Jonathan,
are strange even on Zethu’s narrative. The upshot is that after
querying the invoice and then asking it
to be divided into six
invoices – one for each site- the invoices were never paid.
Zethu’s last word on this is that
it had to attend a meeting in
April with the Head of Real Estate, Mr Manyane. Nothing is said about
what happened at this meeting
or thereafter
[49]
Although Zethu filed a supplementary answering affidavit it does not
deal with any of the anomalies except to say that
the Germiston
project was an extension of an existing IPW. The verbal appointment,
by which is meant an oral as opposed to written
IPW, is now described
as having taken place at a site meeting for conducting the next phase
of an existing IPW.
[50]
But according to the Municipality, when Zethu’s sole director,
Ms Honeli-Mdhluli, was challenged in a meeting with
its officials,
including Jonathan, on whether she had been authorised to perform the
contract because no IPW had been issued, she
became angry and implied
she had outside pollical authority to perform the services.
[51]
According to one official, Ms Naicker, it was suggested by the
Municipality to Holeni-Mdhluli that the impasse could
be resolved by
mediation. But instead of accepting the suggestion Honeli-Mdhluli
became “
rude and unruly
” and, according to
Naicker:
“
Holeni
was not accepting this suggestion Ms. Holeni said she was just
representing Zethu and that the directors of the company were
from
Luthuli House. Ms. Jonathan then stopped the dialogue and requested
Ms, Nandi Khumalo, Mr. Siphiwe Ndlela and myself to leave
the
meeting. We three (3) then excused ourselves and left the meeting,
From that point, I am unaware as to how and whether the
meeting was
resolved.”
[52]
The same facts are also confirmed in an affidavit made by Khumalo.
Honeli-Mdhluli has denied saying this. However, she does not
put up her own version of what happened at the meeting.
[53]
But quite what the point of this project was is obscure. According to
Frank, of the six sites, two were vacant and one
was a covered
parking lot. Yet Zethu employed an array of professionals to work on
the project including, according to Frank, a
project manager,
assistant project manager, and a property valuer, while in respect of
some of the sites, more professionals were
added, such as a civil
engineer, an economist, and a structural engineer.
[54]
Frank also alleges that fees for some of the professionals were
duplicated and others could not be verified. Moreover,
Frank was also
sceptical of the hours of work claimed. As he put it:
“
The amount of
working hours claimed for was excessive and simply humanly
impossible. For instance, the Applicant claimed an average
of 11
man-hours per 7-day week, for three (3) full months straight, for
each of the 8 professional personnel. This meant that the
team would
have worked non-stop, every day, without any breaks. This is
inconceivable and wholly unreasonable
.”
[55]
I consider that there is no justification for the Municipality to
have to pay these fees. There are three reasons for
this: the manner
of appointment was irregular and should have been apparent to Zethu –
this is so even if the alleged invocation
of political influence is
disputed; there is no evidence that the work performed was of any
value to the Municipality; and thirdly
there is evidence that the
invoices reflected both overcharging in the use of professional
services and hours worked.
PPS
conference
[56]
The PPS conference never took place and Zethu, of its own accord,
decided not to continue working on it.
[57]
The Municipality explains why the conference never took place. This
followed media allegations of “some relationship’
between
Zethu, the City Manager, and Executive Mayor. But it was Zethu, not
the Municipality whose decision led to the former’s
withdrawal
from the project, precipitated amongst other reasons by the media
storm. In a letter dated 19 November 2018 Holeni-Mdhluli
wrote to
Jonathan and stated:
“
Our good name
is being dragged into question by unsolicited harassment from media.
This has had a direct impact on my weakening
health and my family to
a point that I personally had to assess if a small company such as
Zethu Consulting Services should risk
all or could even survive the
imminent storm. Furthermore, Zethu Consulting Services has over 30
permanent employees whose well-being
are threatened by ostensible
negative publicity around the summit.”
[58]
Zethu was aware that this project did not fit into the scope of what
it had been retained for. This admission is made
in a supplementary
affidavit by Holeni-Mdhluli where she states of the PPP summit
instruction:”
“
Understanding
that this was not our core function, we turned to our Project
Management Unit (PMU) and accepted this with the view
to project
manage and subcontract the specialist part of it to the service
provider concerned, as is the case with any project.”
[59]
It is thus common cause that this project entailed work that was not
part of the core skill set of Zethu’s professional
staff and
work had to be outsourced to third parties. The fact that Zethu was
sensitive enough to the media controversy to unilaterally
resign the
brief, indicates that it too was aware that the appointment was
irregular. Moreover, the nature of the work was, out
of all the three
projects, the one furthest in nature of services from those for which
it was appointed to the panel. It would
not be just and equitable for
Zethu to claim any fees for these services. Nor should it for the
same reason be entitled to recover
any third-party fees or
disbursements for this project because it must have known it could
not perform the work in-house.
[60]
Finally, I deal with whether it should have to repay the amount of
R4,562 567.50 paid to Zethu in respect of this project.
Given that
this project was far removed from the original tender in terms of
scope, that no value was gained by the Municipality
because the
conference was never held and Zethu resigned the brief, I consider it
is just and equitable that this amount is repaid.
The
Physical Asset Verification project.
[61]
Several of the invoices charged have been paid by the Municipality
for this project. I set out below from the joint practice
note the
amounts and dates of payment.
On 2 February 2018 –
R 2 707 443.00
On 14 May 2018 – R
1 267 005 .60
On 28 September 2018 –
R 4 493 720.45
On 31 October 2018 –
R 5 258 362 .93
On 30 November 2018 - R
5 258 362.93
[62]
A further invoice for this project of R 2 383 161.10 was rendered and
remains unpaid. Zethu claims payment of this invoice
whilst the
Municipality refuses to pay it and claims repayment of the invoices
already paid.
[63]
I deal first with the unpaid invoice. This invoice was submitted for
services rendered between January to March 2019.
But as Frank points
out Zethu, even on its own version, had had been instructed to: ‘
halt
with further verification of the remaining properties" "due
to budgetary constraints" already in May 2018, some
seven (7)
months before January 2019. This factor alone, negates the validity
of the Applicant's first claim.’
[64]
Frank goes further to note discrepancies between the description of
the services in the covering letter and what is contained
in the
narrative on the invoice. Frank’s conclusion is to cast doubt
on the genuineness of the invoice. I do not need to
go that far. I
find that given the clear instruction not to proceed with the work
Zethu should not thereafter have charged for
it. Even if it incurred
further costs to third parties it did so in full knowledge that the
matter should not have been continued
with.
[65]
But to return to the paid invoices. Frank has two issues about this
work. First that it was not done procedurally nor
was it contemplated
in the original tender. But he goes on to state that the work on the
project was a duplication of work being
done internally by the
Municipality’s Finance Department. Zethu was told this in an
email of 5 February 2019 from Jonathan.
But she does say two things
that may mitigate the efforts of Zethu until that date. First that:
“…
.
we will compare their studies with our studies thereof.”
[66]
She goes on to state:
“
When comparing
the costs with their studies your study seems to be extremely high in
terms of expenditure That is not an issue though
as you have worked
and therefore your documents reflect the work done to date.”
[67]
She then asks for all the documents to be submitted to the office of
the relevant finance official for verification of
the work done.
[68]
There is also some controversy over the document that purportedly
appointed Zethu to carry out this project. This document
is dated May
2017 and was sent to Zethu. It is signed by both Miti (in two
capacities) and Jonathan). However, in a handwritten
note on the
document, Miti writes: “
Awaiting CIFCO and CM to confirm
approval for the re-allocation of funds for 2016/2017 FY. IPW also
subject to availability of funds
for 2017/2018 and 2018/2019”
[69]
This note should have alerted Zethu, a firm with experience in
dealing with organs of state, that the green light had
not yet been
given for the project and it should have been scrupulous to confirm
that approval had been obtained. There is no documentary
evidence
that it did. However, on a just and equitable basis I take into
account that this internal approval would not necessarily
have been
communicated to it, and it could assume when the first of its
invoices was paid in February 2018, that by then approval
had been
obtained.
[70]
I find that this project, although not validly authorised, differs in
important respects from the other two, in respect
to the work done
for which the Municipality has already paid. First, whilst the nature
of the services performed was not authorised
in terms of the tender
specification, it is not as far removed in terms of the skill sets
required, unlike the PPP conference.
[71]
Second, it is evident from the letter quoted above that Jonathan was
not certain that the work was a duplication of what
was being done by
Finance – she suggests that this still needs to be verified.
Third, it is clear that even if there was
duplication with work done
by Finance (which is not established on the papers), the work was
necessary and was performed. Finally,
the fact that the Finance
Department may have been doing this work was not something known to
Zethu, nor could it have reasonably
been assumed.
[72]
The instruction came from the Real Estate Department which is the
Department responsible for managing the Municipality’s
property
portfolio, a point that Holeni-Mdhluli makes in her supplementary
answering affidavit.
[73]
I therefore conclude that it would be just and equitable for Zethu to
retain the fees for which it has been paid for
this project, but it
is not entitled to be paid for the further invoice.
Conclusion
[74]
In relation to the main application, I find that it is unsuccessful
and falls to be dismissed. The applicant is not entitled
to any
payment in respect of any outstanding invoices in respect of the
three projects. In relation to the counter-application,
I find that
it is only partially successful. The late filing of the application
is condoned. The review of the Zethu’s appointment
to the three
projects has been successful. However, the order for repayment is
confined to the repayment of R4 562 567.50, which
is the claim for
the repayment of the expenditure incurred for the PPP Investor
Conference. The order for the repayment of the
amounts paid in
respect of the Physical Assets Project is dismissed.
Costs
[75]
The Municipality has been successful in opposing the main application
and is entitled to its costs for this, including
the costs of two
counsel. Given the complexity of the matter and detail, required
costs on Scale C as set out in the Uniform Rule
is justified. In
respect of the counter application, the Municipality has only been
partially successful and was unsuccessful in
reclaiming the larger
portion of its claim. On this basis each party can bear its own costs
for the counter-application. The award
of the three contracts is
found unlawful and set aside. However, on just and equitable grounds
Zethu is entitled to retain its
fees for the first five invoices in
respect of the Asset verification project.
ORDER:-
[76] In the result
the following order is made:
1. The main
application is dismissed.
2. The applicant is
liable for the respondents’ costs in respect of the main
application, including the cost of two
counsel, on Scale C.
3. In respect of
the counter-application:
a. The late filing
of the counter-application is condoned;
b. The award of the
following three projects to the applicant is reviewed and set aside:
i.The Physical
Asset Verification project
ii.The Germiston
Valuation Project; and
iii.The PPP
Investor Conference.
c. The payments
made in respect of the three projects are declared unlawful and
irregular, but subject to sub-paragraph (e)
below;
d. The applicant is
to repay to the first respondent the amount of
R4
562 567.50
paid to it in respect of the PPP Investor
Conference, within 30 business days of date of this order;
e. It is just and
equitable for the applicant to retain the fees paid to by the first
respondent in respect of the first five
invoices in respect of the
Physical Asset Verification project, as set out in paragraph 61 of
this judgment, in the amount of R18
821 207.93.
f. Each party is
liable for its own costs in respect of the counter-application.
N. MANOIM
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION
JOHNANNESBURG
Date of hearing: 02 May
2024
Date of last submission:
6 May 2024
Date of Judgment: 06
August 2024
Appearances:
Counsel
for the Applicant:
F
Hobden
A
Louw
Instructed
by.
Beder-Friedland
Inc.
Counsel
for the First to Fourth Defendants
PG
Seleka SC
K
Magan
Instructed
by:
Madhlopa
& Thenga Inc.
[1]
The second to fifth respondents are all officials of the first
respondent and were cited in these capacities because of their
interest in the matter.
[2]
As the Municipality has pointed out in its heads of argument, the
amount claimed here is an error, and this error is perpetuated
in
Zethu’s draft order on Case-lines. The invoices relied on by
Zethu add up to R 16 738 810.85, an amount R
152 376
less than the amount claimed. Nevertheless, I do not regard this as
anything more than an arithmetical error by
Zethu.
[3]
Transnet
SOC Ltd and another v CRRC ELoco Supply (Pty) Ltd (formerly CSR
ELoco Supply (Pty) Ltd) and Others
[2022] JOL 25889 (GJ)
[4]
City of
Tshwane Metropolitan Municipality v RPM Bricks Proprietary Ltd
2008
(3) SA 1
(SCA) paragraph 17,
[5]
City of
Tshwane
,
supra, paragraph 18.
[6]
Here Zethu has measured the time from the date of the invitation to
perform the work until the date of the filing of the Municipality’s
counter-application.
[7]
Buffalo
City Metropolitan Municipality v ASLA Construction Pty Ltd
2019(4)
SA 331 at paragraph 49.
[8]
Buffalo City, supra paragraph 52.
[9]
South
African Broadcasting Corporation SOC Ltd and another v Mott
Macdonald SA (Pty) Ltd
[2020] JOL 51538
(GJ) paragraph
61.2
[10]
Passenger
Rail Agency of South Africa v Swifambo Rail Agency (Pty) Ltd
2017 (6) SA 223
(GJ) paragraphs 74- 79.
[11]
Allpay
Consolidated Investment Holdings (Pty) Ltd and others v Chief
Executive Officer, South African Social Security Agency and
others
2014 (4) SA 179
(CC) paragraph 31
[12]
Ibid.
sino noindex
make_database footer start
Similar Cases
Zondi and Others v S (A66/2023) [2023] ZAGPJHC 975 (28 August 2023)
[2023] ZAGPJHC 975High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corporation (Pty) Ltd and Others v Redpath Mining (South Africa) (Pty) Ltd and Another (9234/2022) [2024] ZAGPJHC 680 (22 July 2024)
[2024] ZAGPJHC 680High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corpoation (Pty) Ltd and Others v Redpath Mining South Africa (Pty) Ltd and Others (Application for Leave to Appeal) (57639/2021) [2024] ZAGPJHC 933 (19 September 2024)
[2024] ZAGPJHC 933High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Siyakhula Sonke Empowerment Corporation Proprietary Limited and Another v Redpath Africa Limited (55896/2021) [2024] ZAGPJHC 475 (8 May 2024)
[2024] ZAGPJHC 475High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Lekgetho v S (A152/2022) [2023] ZAGPJHC 922 (16 August 2023)
[2023] ZAGPJHC 922High Court of South Africa (Gauteng Division, Johannesburg)99% similar