Case Law[2024] ZAGPJHC 754South Africa
Khanyisela Mineral Traders (Pty) Ltd v EJ Resources (Pty) Ltd (2024/069252) [2024] ZAGPJHC 754 (12 August 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 754
|
Noteup
|
LawCite
sino index
## Khanyisela Mineral Traders (Pty) Ltd v EJ Resources (Pty) Ltd (2024/069252) [2024] ZAGPJHC 754 (12 August 2024)
Khanyisela Mineral Traders (Pty) Ltd v EJ Resources (Pty) Ltd (2024/069252) [2024] ZAGPJHC 754 (12 August 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_754.html
sino date 12 August 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO: 2024-069252
1.
REPORTABLE:
NO
2.
OF INTEREST
TO OTHER JUDGES: NO
3.
REVISED:
YES
In the matter between:
KHANYISELA
MINERAL TRADERS (PTY) LTD
Applicant
and
EJ
RESOURCES (PTY) LTD
Respondent
Delivered
12
August 2024 – This judgment was handed down electronically
by circulation to the parties' representatives via email,
by being
uploaded to CaseLines and by release to SAFLII.
JUDGMENT
Bester
AJ:
[1]
The applicant urgently applies for an interdict restraining the
respondent from disposing coal mined on portion 5, Farm
Mooifontein
35 IT, Registration Division IS, Mpumalanga (the mine) to any party
other than the applicant, pending the final determination
of a
dispute between the parties in respect thereof. The applicant
proposes to institute an action within 30 days.
[2]
On 22 March 2024 the applicant and the respondent entered into a
written agreement. In terms thereof, the applicant agreed
to assist
the respondent to establish the mine by making advance payments for
RB1, RB2 and RB3 grade coal from the mine (the coal),
to be delivered
once the mine has been established. In return, the respondent granted
the applicant the exclusive right of first
refusal to purchase all
coal.
[3]
The applicant made advance payments and the respondent established
the mine. A dispute arose between the parties as to
whether the
respondent validly terminated the agreement on 5 June 2024. The
applicant seeks to secure the continued availability
of the coal
whilst the dispute is being resolved at trial. At the hearing I ruled
that the matter is sufficiently urgent to be
heard forthwith.
# Factual Matrix
Factual Matrix
[4]
In terms of the contract, the applicant agreed to assist the
respondent by making early payments, stipulated as an aggregate
total
amount of R10 million or any portion thereof, for the establishment
of the mine. In return, the respondent irrevocably granted
the
applicant the right of first refusal to purchase the coal on the
terms set out in the agreement, which would terminate once
the
applicant has purchased “
any and all ... coal produced from
the Mine”
.
[5]
The parties agreed on a purchase price, per ton, for each of the
three grades of coal stipulated in the agreement. Clause
4.3 provides
that the applicant shall pay invoices submitted by the respondent or
third-party contractors for goods and services
required by the
respondent to establish the mine. In terms of clause 4.4, the parties
agreed that once the mine has been established,
the purchase price of
coal supplied shall be offset against the early payments.
[6]
In terms of clause 4.6, the applicant had the “
sole and
unaffected discretion”
, but not the obligation, to exercise
its right of first refusal. It was however obliged to purchase a
minimum of 15 000 tons
of coal per month; whilst the respondent
was obliged to produce a minimum of 20 000 tons of coal per month.
[7]
In terms of clause 5.2, the respondent had to establish the mine
within four weeks of the commencement date. The applicant
had the
“
sole and unfettered discretion”
to cease making
early payments, “
should it anticipate that the mine shall
not be established within the period referred to ... and/or there has
been wasteful expenditure
in the establishment of the Mine”
.
[8]
It is common cause that the applicant made early payments in terms of
the agreement totalling R6 688 581,50.
It is not clear from
the papers when the mine was established, and the exact date is in
dispute between the parties. However, they
agree that by early June
2024 the mine was operational.
[9]
On 5 June 2024 the respondent’s attorneys addressed a letter to
the applicant, in which it was claimed that the
applicant was in
breach of the agreement in that it had failed to pay:
a) invoices in
respect of fuel over the period 15 April 2024 to 21 May 2024;
b) the costs of an
excavator of R56 000,00, in respect of which an invoice was
forwarded to it on 3 May 2024; and
c) several other
items, despite invoices having been forwarded to it.
[10]
The letter alleged that the applicant’s breach was an event of
default as described in clause 7.1 of the agreement,
and,
consequently, the respondent elected to cancel the agreement with
immediate effect, in terms of clause 8.1.
[11]
The letter also tendered payment of the full amount of the early
payments by the delivery of coal to that value, as calculated
at the
purchase price described in clause 4.1 of the agreement, to the
applicant.
[12]
On 10 June 2024, the applicant placed an order for 8 823.9862 tons of
RB2 coal, which, at the pricing in the agreement,
came to
R6 688 581,54, with no reference to the 5 June letter.
[13]
On 11 June 2024, the applicant’s attorneys responded that it
was in the process of obtaining instructions in respect
of the letter
of 5 June. They recorded that the mine is operational and that the
applicant has furnished the respondent with a
purchase order for coal
at a price as envisaged in the agreement, which order was being
fulfilled at the time of writing the letter.
[14]
The order was fulfilled, and the coal was collected on 12 June 2024.
[15]
On 19 June 2024 the applicant’s attorneys addressed a further
letter to the respondent’s attorneys, responding
in more detail
to the letter of 5 June. The respondent’s cancellation of
the contract was rejected. The letter recorded
that the agreement
does not obligate the applicant to make payment of all invoices
submitted to it and entitled it to cease making
payment should the
mine not be established within the envisaged period, or if there has
been wasted expenditure. The letter does
not, however, tie these
rights to any specific invoice referred to by the respondent.
[16]
The letter further claimed that the respondent had failed to place
the applicant in
mora
, and thus it could not cancel the
agreement. The applicant considered the attempt to cancel as a
repudiation of the agreement,
which it rejected, and it demanded
specific performance. As a result, written confirmation was sought
that the respondent would
continue to supply coal in terms of the
agreement.
[17]
On the same day (19 June 2024), the applicant delivered a purchase
order for 6,000 tons of RB2 coal. The following day
an email response
was received from Mr Hill, the respondent’s Chief Executive
Officer. He confirmed that the order would
be filled as requested
(thus at the contracted price) but stated that further orders would
not be filled. He advanced two reasons.
He claimed that the
respondent’s weighbridges were inaccurate and lamented that the
applicant failed to inform the respondent
that it had previously
delivered an extra two tons. He also claimed that the pricing (as
stipulated in the contract) could not
be honoured and stipulated
substantially higher prices for future orders. The email does not
make any reference to the contract,
or the 5 June letter.
# The challenge to
jurisdiction
The challenge to
jurisdiction
[18]
At the hearing, the respondent objected to this Court’s
jurisdiction to hear the matter. The answering papers did
not raise
the issue of jurisdiction at all. Ms Butler, appearing for the
respondent, explained that the challenge to jurisdiction
flows from
the applicant’s replying affidavit. The argument goes as
follows. From the founding papers, the respondent understood
the
applicant to seek specific performance. Because the contract was
concluded within this Court’s jurisdiction, the respondent
did
not object to this Court's jurisdiction. However, in reply, the
applicant expressly stated that it is seeking an interim interdict,
and not specific performance. This caused the challenge to
jurisdiction, because the subject matter of the interdict, the coal,
is situated outside this Court’s jurisdiction.
[19]
At the time
I ruled that the Court had jurisdiction to entertain the matter and
argument proceeded. Generally, a court will not
have jurisdiction to
grant an interdict where the performance thereof will take place
outside of the Court’s jurisdiction
and the respondent is a
peregrinus
to that
court.
[1]
However, in this
instance, the respondent, in my view, submitted to this Court’s
jurisdiction. It was clear from the notice
of motion and the founding
affidavit that the applicant sought an interdict restraining the
respondent from dealing with the coal
at the mine. In reply, it
merely reiterated that position, in the light of the respondent's
argument that the applicant seeks specific
performance and therefore
has to make out a case for final relief.
[20]
The
respondent did not challenge the Court’s jurisdiction before
litis
contestatio
and was deemed to have submitted to the Court’s
jurisdiction.
[2]
The Court’s
lack of jurisdiction was raised from the bar during argument. The
change in stance does not have a factual basis.
Ultimately,
jurisdiction is a matter of effectiveness,
[3]
and I see no reason not to hold the respondent to its initial
election.
# Has a right been
establishedprima facie?
Has a right been
established
prima facie
?
[21]
The
applicant seeks an interim interdict pending the outcome of the
proposed action. It is well settled that such an applicant must
establish (a) a
prima
facie
right even if it is open to some doubt; (b) a reasonable apprehension
of irreparable and imminent harm to the right if an interdict
is not
granted; (c) that the balance of convenience favours the granting of
the interdict; and (d) that the applicant has no other
legal
remedy.
[4]
[22]
The applicant asserts a
prima facie
right to purchase all the
coal from the mine in terms of the written agreement between the
parties.
[23]
To decide
whether an applicant has established a
prima
facie
right the Court considers whether, on the facts set out by the
applicant together with the facts set out by the respondent which
the
applicant cannot dispute, the applicant could obtain final relief at
the trial, having regard to the inherent probabilities.
If serious
doubt is thrown on the applicant’s case, it cannot succeed with
temporary relief.
[5]
[24]
The applicant would have a right to performance in terms of the
agreement unless the respondent is correct when it asserts
that the
agreement was terminated.
[25]
The respondent asserts that the applicant breached the agreement in
that it did not timeously pay the items identified
in the 5 June
letter. The applicant does not dispute that it did not pay these
invoices. Its Chief Operations Officer, Mr Argyle,
baldly asserts in
the founding affidavit that “
the applicant has paid all
invoices received by it from the respondent and / or third-party
contractors as envisaged in clause 4.3”
, suggesting that
some invoices may not have been received and that others fall outside
of the ambit of the clause, without explaining
why.
[26]
In reply,
the applicant expressly denied that all the invoices were received,
without providing any details. It also attempted to
explain why the
invoices were not payable. It is well established that a party
must make out its case in its founding papers.
[6]
The applicant had to show its
prima
facie
right
in its founding papers and it was not entitled to leave its
explanations for not paying the invoices for reply. In any event,
these explanations provide little in detail. The applicant has not
shown that a trial court will probably find in its favour on
this
point.
[27]
The applicant’s contention that the agreement was not properly
cancelled, if it is assumed that the applicant was
in breach, seems
to be on stronger footing.
[28]
The contract contains a cancellation clause that, on the face
thereof, may be relied upon by the applicant, but not the
respondent.
Clause 7 of the agreement stipulates that an event of default will
include a breach of ‘any provision of this
Agreement’.
Clause 8 stipulates that, on the occurrence of an event of default,
the applicant may cancel the agreement, amongst
several options.
However, the cancellation clause is silent as to cancellation by the
respondent. It thus seems that the respondent’s
reliance on
clauses 7 and 8 will probably not withstand scrutiny at trial.
[29]
In the
absence of a cancellation clause the test of whether the innocent
party is entitled to cancel the contract because of malperformance
by
the other, entails a value judgment by the court.
[7]
It requires balancing the competing interests of the parties with the
ultimate criterion of treating both parties fairly in the
circumstances. The court will bear in mind that cancellation is the
more radical remedy, compared with specific performance or
a damages
claim. Simply put, the question must be answered whether the breach
is so serious that it is fair to allow the innocent
party to cancel
the contract.
[30]
Clause 4.3
requires the applicant to make payment of invoices submitted to it,
but the contract does not expressly stipulate when
that performance
is due. Mr Shepstone, appearing for the applicant, submitted that
where the contract does not fix a time for the
performance, and where
there is no legal prescript as to the due date, a demand is necessary
to place the debtor in
mora.
I agree. As Wessels JA explained in
Breytenbach
[8]
:
“
[n]ot having
placed appellant in mora the respondent was not entitled to sue for
cancellation of the contract merely because in
his opinion transfer
was not effected within a reasonable time”.
[31]
Where
immediate performance is contemplated, no demand is necessary.
[9]
The trial court will thus have to determine whether performance was
due forthwith upon the presentation of the invoices, negating
the
need for a demand. The respondent contends that the invoices were due
‘on a weekly basis’, but the contract does
not contain
such a provision, and it is not necessarily clear what is meant by
the phrase.
[32]
Prima facie
, it seems that payment was not to be immediately
made and an unmet demand should have preceded notice of cancellation.
It thus
seems probable that the issue would be decided in the
applicant’s favour at trial.
[33]
The respondent, in the alternative, contends that the applicant
tacitly accepted the separation terms offered by the
respondent in
the 5 June letter, by placing an order for a volume of coal with a
purchase price equal to the early payments made
by the applicant. The
applicant denies this, pointing out that the purchase order itself
stipulates that the purchase price is
to be set off against the early
payments in accordance with the agreement, thus contradicting the
alleged tacit agreement that
the order constitutes acceptance of the
separation terms. I agree that the order on the face of it seeks
enforcement of the contract
and not its agreed termination. The order
was followed by a letter on 11 June 2024 insisting on specific
performance of the agreement,
further speaking against the suggested
novation.
[34]
The
agreement contains a term stipulating that any variation, novation or
cancellation of the agreement must be in writing and signed
by the
parties. The respondent seeks to avoid the obvious consequences of
the non-variation clause, often referred to as a
Shifren
clause
[10]
, by reasoning that
such a clause does not exclude the existence of tacit terms of the
agreement, and by extension thus does not
apply to the tacit novation
thereof. Unsurprisingly, Ms Butler was unable to refer me to any
authority in support of such an extension
of the principle. The
respondent’s proposed approach would have the result that a
non-variation clause can be avoided tacitly
but not orally, an
outcome that in my view is unlikely to find favour with the trial
court.
[35]
I therefore conclude that the applicant has established a
prima
facie
right to insist on performance in terms of the agreement
and that no serious doubt has been cast thereon.
# Is there a reasonable
apprehension of irreparable harm?
Is there a reasonable
apprehension of irreparable harm?
[36]
The applicant advances four reasons why it reasonably anticipates
suffering irreparable harm if the order is not granted.
It argues
that it will be deprived of its contractual right to exclusively
purchase the coal. Although the proposition is sound,
it does not
consider the whole picture. The same agreement also creates other
contractual rights, including to claim damages. The
harm is therefor
in my view not irreparable.
[37]
The applicant further alleges that its business model and financial
projections are based on the exclusive right to purchase
the coal.
However, the applicant does not explain how this statement translates
into an actual apprehension of irreparable harm.
[38]
The applicant also explains that it needs to fulfil existing client
orders, for which it requires the coal. It argues
that, if the
respondent does not supply it with the coal, the applicant will
either lose the orders (and possibly future orders)
or have to buy in
the coal from other sources. The respondent counters that there is
ample alternative supply available to fill
the orders, which
assertion is not challenged by the applicant.
[39]
The respondent asserts that the contract prices were substantially
below the market prices – it calls the prices
“predatory”
in its answering affidavit. In reply, the applicant denies the market
prices stated by the respondent,
and asserts that coal prices have
decreased since the signing of the agreement. Unhelpfully, neither
party offered any proof for
their contentions. Because no evidence
was presented as to the current coal prices, it is not clear to me
that the price to be
paid to third-party suppliers will be higher
than the prices agreed between the parties.
[40]
Lastly, the applicant contends that quantification of damages would
be “
extremely difficult, if not impossible, to calculate
accurately
”. Why this is so, remains unexplained. The
respondent argues that the price difference between the contract
price and the
price asked by third parties would be the obvious
measure of damages, and easily calculable. I agree, with the rider
that there
may be additional costs involved that may form part of the
loss. I do not see why these items would raise insurmountable
hurdles.
Thus, any price and cost differential can be claimed as
damages.
[41]
The relief sought by the applicant is in the form of prohibiting the
respondent from disposing of the coal, unless it
is to the applicant.
This formulation of the relief contradicts the applicant’s
concern regarding its irreparable harm that
it will lose the clients.
An interdict in this form will not deal with that problem. There is a
disjunct between the irreparable
harm contended for and the relief
sought.
[42]
I thus conclude that the applicant has failed to show that it has a
reasonable apprehension of irreparable harm.
# Does the balance of
convenience favour the applicant?
Does the balance of
convenience favour the applicant?
[43]
The balance
of convenience, which would be more aptly referred to as the balance
of prejudice, essentially requires the court to
weigh up the position
of the applicant if the interim relief is not granted but it succeeds
in asserting its right at trial, compared
to the position of the
respondent if the interim relief is granted but the applicant
ultimately fails to assert its right at trial.
[11]
[44]
The applicant asserts that its stands to suffer significant financial
loss to its business if the interdict is not granted.
It does not
provide any detail of the anticipated loss, which seems easily
ascertainable. There is nothing on the papers showing
that the
applicant may not be able to recover any loss from the respondent.
[45]
The applicant contends that the respondent will not suffer any undue
hardship because it will “
merely be required to comply with
its existing contractual obligations”
. This, of course, is
the wrong analysis. It considers the question from the perspective of
the applicant being successful in the
trial, instead of its failure.
[46]
In my view, if the interdict is not granted, the applicant could
still buy coal from other suppliers to fill orders placed
upon it. On
the other hand, if the interdict is granted, the respondent’s
business, on all accounts, will come to an immediate
stand still, as
it will be obliged to hoard all coal mined until the trial has been
determined. It will be faced with the dilemma
of operating a mine
without any income to fund its activities.
[47]
The proposed proviso to the order, that the respondent may still sell
the coal to the applicant, does not solve the respondent’s
dilemma. Ms Butler argued that the proviso prejudices the respondent,
as it does not stipulate a price. In the result, she pointed
out, the
applicant can refuse to offer the contract price and force the
respondent to accept lower prices just to survive, to its
prejudice.
[48]
This led Mr Shepstone to propose an amendment to include the proviso
that any sale must be in terms of the agreement.
He did not present a
written amendment at the time, but subsequently, after the hearing,
his attorney sent an amended notice of
motion. The respondent’s
attorney wrote to claim that there was no agreement to amend, and
that the amendment was opposed.
This came as somewhat of a surprise,
given that Ms Butler in argument conceded that the proposed rider
would resolve the complaint
she raised as to the formulation of the
relief, and raised no further objection thereto. Be that as it may, I
considered it unnecessary
to hear further argument, as proposed by
the parties. This is because in my view the different wording will
not affect the outcome
of the matter.
[49]
In the circumstances of the case, if the interdict is granted, the
respondent will be placed on the horns of a dilemma:
if it is to stay
in business, it would be forced to sell to the applicant, or find an
alternative source of funding to stay afloat.
Thus, to decide the
balance of convenience in favour of the applicant on the basis that
the respondent can still sell the coal
to the applicant to avoid
hardship, will allow the applicant to effectively obtain final relief
in the guise of interim relief.
If the respondent sells to the
applicant under the proposed terms of the interdict, it will have
procured the coal at the contract
price, and the respondent, who
elected to sell, will have no recourse for damages if the applicant
fails at trial, as it would
have acted under a court order. In this
fashion the applicant would likely procure all the coal under the
interim order, as the
litigation will probably take longer than the
lifespan of the mine. On the applicant’s case, the mine has a
lifespan of around
12 months.
[50]
The arguments raised by the respondent, that the applicant seeks
final relief, is in my view better approached in this
fashion. The
respondent contended that, as formulated, the interdict is in effect
final, because it will practically force the
respondent to sell the
coal to the applicant in terms of the contract before the conclusion
of the trial. The proposed relief does
not oblige the respondent to
sell the coal to the applicant at the contract price but requires it
to hoard the coal until the final
determination of the dispute. The
relief sought is thus interim in nature. However, when considering
the balance of convenience,
the practical factors, which will
effectively force the respondent to make decisions that will pre-empt
the final determination
of the dispute, tip the scales in the
respondent’s favour.
[51]
In these circumstances the prejudice to the respondent outweighs the
prejudice to the applicant. The applicant has thus
also failed to
establish that the balance of convenience favours the granting of the
interim relief.
# Is there an alternative
legal remedy?
Is there an alternative
legal remedy?
[52]
Generally
speaking, a court will not grant an interdict where the applicant can
obtain adequate redress by an award of damages.
[12]
There do not seem to be any factors against applying the general
principle. Damages are relatively easy to quantify in this instance,
and the applicant has not shown that a damages claim cannot be met.
[53]
It therefore follows that, in my view, the applicant has not shown
that it cannot obtain redress in the form of a damages
claim.
# The order
The order
[54]
I conclude that the applicant has not made a case for interim
interdictory relief.
[55]
In the result, I make an order in the following terms:
a) The application
is dismissed.
b) The applicant
shall pay the respondent’s costs of the applicant, including
the costs of counsel at scale B.
A
Bester
Acting
Judge of the High Court of South Africa
Gauteng
Division, Johannesburg
Heard
on:
2
July 2024
Judgment
Date:
12
August 2024
Counsel
for the Applicant:
Ross
Shepstone
Instructed
by:
Richmond
Attorneys
Counsel
for the Respondent:
Jeanne-Mari
Butler
Instructed
by:
Brandmuller
Attorneys Inc.
[1]
Leyland
v Chetwynd
(1901)
18 SC 122
;
Ex
parte Goldstein
1916 CPD 483.
[2]
Muller
v Möller
1965
(1) SA 872 (C).
[3]
Foize
Africa (Pty) Ltd v Foize Beheer BV
2013 (3) SA 91 (SCA).
[4]
National
Treasury and Other v Opposition to Urban Tolling Alliance and Others
2012
(6) SA 23
(CC) in [41] to [45], approving of
Setlogelo
v Setlogelo
1914 AD 221
and
Webster
v Mitchell
1948
(1) SA 1186 (W).
[5]
Webster
v Mitchell supra
at 1189, as qualified in
Gool
v Minister of Justice and Another
1955
(2) SA 682
(C) at 688 E – F.
[6]
It
is well established that a party must make out its case in its
founding papers. See for instance
Betlane
v Shelley Court CC
2011 (1) SA 388
(CC) in [29].
[7]
Singh v
McCarthy Retail Limited t/a McIntosh Motors
[2000] ZASCA 129
;
2000
(4) SA 795
(SCA) in [15].
[8]
Breytenbach
v Van Wijk
1923 AD 541
at 549.
[9]
Nel v
Cloete
1972 (2) SA 150
(A) at 169 G, approving of
Mackay
v Naylor
1917 TPD 533
at 537 – 538.
[10]
Referring
to
SA Sentrale Ko-op Graanmaatskappy Bpk v Shifren en Andere
1964 (4) SA 760 (A).
[11]
Eriksen
Motors (Welkom) Ltd v Protea Motors, Warrenton & Another
1973 (3) SA 685
(A) at 691E.
[12]
UDC
Bank Limited v SeaCat Leasing & Finance Co (Pty) Ltd
1979
(4) SA 682
(T) at 695.
sino noindex
make_database footer start
Similar Cases
Khanyi v Minister of Police (16/13227) [2023] ZAGPJHC 434 (8 May 2023)
[2023] ZAGPJHC 434High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Khulekani and Others v S (A43/2024) [2024] ZAGPJHC 539 (6 June 2024)
[2024] ZAGPJHC 539High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Khombamdlelo Building Material CC v South African National Roads Agency (45070/2021) [2024] ZAGPJHC 1028 (11 October 2024)
[2024] ZAGPJHC 1028High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Khanyeza v City of Johannesburg Metropolitan Municipality and Another (2024/079861) [2024] ZAGPJHC 887 (5 September 2024)
[2024] ZAGPJHC 887High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Khambule v Road Accident Fund (2015/30703) [2025] ZAGPJHC 628 (24 June 2025)
[2025] ZAGPJHC 628High Court of South Africa (Gauteng Division, Johannesburg)99% similar