Case Law[2024] ZAGPJHC 1048South Africa
Joint Venture Comprising Gorogang Plant Razz Civils and Others v Infiniti Insurance Limited (02252/2023) [2024] ZAGPJHC 1048 (15 October 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
15 October 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 1048
|
Noteup
|
LawCite
sino index
## Joint Venture Comprising Gorogang Plant Razz Civils and Others v Infiniti Insurance Limited (02252/2023) [2024] ZAGPJHC 1048 (15 October 2024)
Joint Venture Comprising Gorogang Plant Razz Civils and Others v Infiniti Insurance Limited (02252/2023) [2024] ZAGPJHC 1048 (15 October 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_1048.html
sino date 15 October 2024
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
Case
number: 02252/20234
[1]
REPORTABLE: NO
[2]
OF INTEREST TO OTHER JUDGES: NO
[3]
REVISED: NO
15
October 2024
In
the matter between:
THE
JOINT VENTURE COMPRISING GOROGANG PLANT
RAZZ
CIVILS
First
Applicant
H
L MATLALA PROPERTIES t/a GOROGANG PLANT
HIRE
(PTY) LTD
(Registration
Number: 2004/067203/23)
Second
Applicant
RAZZ
CIVILS AND PLANT HIRE
(Registration
Number: 2016/145104/07)
Third
Applicant
and
INFINITI
INSURANCE LIMITED
(Registration
Number: 2005/029823/06)
First
Respondent
THE
EASTERN CAPE DEPARTMENT OF TRANSPORT
Second
Respondent
JUDGMENT
PULLINGER
AJ
INTRODUCTION
[1]
The second respondent ("
the Department
") applies for
the reconsideration of an interim order granted by Mia AJ on
19 September 2023. The interim order
was granted on an
urgent basis in the Department’s absence. The first respondent
(“
Infiniti
”) abides.
[2]
Mia AJ ordered
"2. Pending
the determination of Part B of this application, that:-
2.1 the first respondent
is interdicted and restrained from making payment to the second
respondent pursuant to the purported demand
made upon the guarantee
issued by the first respondent with reference PS GUA RZZ01,
a copy of which is annexure JV3 to
the founding affidavit (the
guarantee), made by the second respondent in terms of the letter
dated 11 September 2023,
and which appears at annexure JV23
to the founding affidavit in the application (the demand); and
2.2 the second respondent
is interdicted and restrained from making demand, or purporting to
make demand, upon the guarantee, either
in respect to any issue
arising out of and/or in connection with the purported termination of
the contract concluded between the
first applicant and the second
respondent and/or at all."
[3]
This application was set down on the Urgent Court Roll for
26 March 2024, ostensibly in accordance with Rule 6(12)(c).
[4]
The Department contends that reconsideration applications are
"inherently urgent" and ought properly to be heard
before
the Urgent Court, notwithstanding the lapse of some six months
between the time Mia AJ granted the above order and
the date of
the launch of this application.
[5]
Mr Hodge, who appeared for the applicants presented a forceful
and well reasoned argument, the gist of which,
was that because
the Department brought the application in terms of Rule 6(12)(c),
it did not axiomatically and automatically
warrant the enrolment and
hearing of the matter before the Urgent Court. The point was made,
especially in the context of what
must be seen as an extraordinary
delay in the launch of the Department's reconsideration application.
[6]
Although I am inclined to agree with Mr Hodge, I am not inclined
to strike this matter from the roll and prefer to
address the merits
of the matter as all the papers are before me, I have heard full
argument in relation to both the procedural
aspects and the merits
and therefore there is no good reason to burden another Court in the
circumstances. This should not however,
be construed as any sort of
judicial sanction of the Department’s conduct. I deal more
fully therewith below.
# THE FACTS
THE FACTS
[7]
In April 2022, and pursuant to a tender, the Department appointed the
first applicant to upgrade certain roads in the
Eastern Cape
Province. The performance of the works by the first applicant was to
be undertaken in terms of a written agreement
(“
the
Agreement
”) which was in terms of The General Conditions of
Contract for Civil Engineering Works, Third Edition, 2015.
[8]
In terms of the Agreement the applicants were required to deliver a
performance guarantee to the Department's agent. In
terms of clause
6.2.1 of the Agreement, the applicants were required to deliver “…
the
type of security for the due performance of the Contract, as selected
in the Contract Data
”. Clause 25 of the Contract Data
stipulates that “
[t]he security to be provided by the
Contractor
[a reference to the applicants]
shall be a Fixed
Performance Guarantee of 10% of the Contract Sum
”.
[9]
A guarantee issued by Infiniti in favour of the Department was duly
delivered by the applicants (“
the Guarantee
”). The
Guarantee is in the form of the
pro forma
as required by the
Department.
[10]
Pursuant to the delivery of the Guarantee, the applicants proceeded
with the works in terms of the Agreement.
[11]
Subsequent thereto a dispute arose between the applicants and the
Department. The dispute concerns delays in reaching
milestones, the
causes thereof and payment for work done by the applicants. This
culminated in the Department cancelling the Agreement.
The applicants
contend that the Department was not entitled to cancel the Agreement
and contend that cancellation was a repudiation
of the Agreement.
[12]
This dispute is the subject of a pending adjudication before the
South African Institute of Civil Engineering.
[13]
On 11 September 2023 the Department made written demand on
Infiniti calling upon it to make payment under the
Guarantee.
[14]
The applicants contend, in relation to the demand, that
"92. On
13 September 2023, and in reliance upon its (bad and
ineffectual) termination of the contract, the
Employer addressed a
demand under the Guarantee to Infiniti, a copy of which is annexure
"JV23" hereto (as aforesaid,
"the demand").
93. The Employer recorded
therein that:-
…
94. The demand is
non compliant in a number of respects:-
94.1 first, the
demand falsely and knowingly, misrepresents that:-
94.1.1 the
Contractor has defaulted on the contract. For the reasons set out
above, the Contractor had not defaulted on the
Contract, either as
alleged by the Employer and/or at all;
94.1.2 the
Employer terminated the Contract in terms of Clause 9.2.1.3.3.
For reasons set out above, this, too, is,
to the Employer's
knowledge, false. Neither the Employer's Agent's correspondence nor
the Employer's correspondence references
this clause;
94.1.3 the letters
of 7 and 21 June 2023 are relied upon yet neither of these
are annexed, if they exist;
94.2 second, the
demand of 13 February 2023 was not delivered to Infiniti's
physical address, as required by Clause 2.3
of the Guarantee;
94.3 third, the
demand is not accompanied by the notice of termination (had it been
it would have been abundantly clear that
what is recorded in the
demand was false), as required by Clause 2.3.3 of the Guarantee
(if it were it would be plain that
the demand is bad);
94.4 fourth, the
Employer does not expressly state that the Contract has been
terminated due to the Contractor's default;
94.5 fifth, the
Employer has demanded payment despite not having returned the
original Guarantee to Infiniti, as required
by Clause 2.7 of the
Guarantee; and
94.6 finally, the
demand is for an amount in excess of the Guaranteed Sum and
Infiniti's maximum liability, thereby invalidating
the demand.
95. On this basis
alone the demand is fatally defective and cannot, or ought not to, be
given effect to."
[15] The applicants
conclude
“
100. The
demand is thus fraudulent and unconscionable, falls to be declared as
such and payment pursuant thereto falls to
be interdicted.”
[16]
The applicants contend that the Guarantee is a conditional guarantee.
Their case is that
"105. …
the Guarantee is not a demand guarantee but, rather, a conditional
one and payment thereunder is conditional
upon a valid termination of
the contract for the Contractor's default. This is because, the link
created in the Guarantee itself,
being the statements to be made and,
more particularly, that the notice of termination must be supplied
with the demand (thereby
opening a demand to be assailed on the basis
of either the statements being incorrect or there being deficiencies
in the termination),
renders payment thereunder dependent upon facts
and jurisdictional requirements that arise under the contract. Put
differently,
the Guarantor (in this case Infiniti's) obligation is
not '
wholly independent of the underlying contract
' as would
be the case in respect of a demand guarantee but, rather, is
dependent upon the facts of a valid termination and the
Contractor
being in default being substantiated in the demand.
106. The Employer's
entitlement to benefit thereunder is predicated upon, and
inextricably linked to, the validity of the
termination
and
the Contractor having been in breach of the contract sufficient as to
permit the Employer to terminate.
107. As intimated
above, this is so because Clause 2.3.1 of the Guarantee requires
two statements, namely that the contract
has been terminated
(implicit in which is that the termination must have been valid and
unimpeachable) and it was terminated to
[sic] the Contractor's
default (implicit in which is that the Contractor must, factually
have been in default).
108.
Self evidently, the statements, in being made, are being made to
derive a benefit under the Guarantee. Accordingly,
in so making the
statements the Employer must ensure not only that they are correct
but, also, any relevant information in respect
thereof must be placed
before the Guarantor, Infiniti. It is for this reason that
Clause 2.3.3 requires that the notice of
termination accompanies
the written demand."
[17]
The Department takes issue with the applicants' contentions
concerning the demand on the Guarantee, their conclusion
of fraud and
their interpretation of the Guarantee.
[18]
The Department contends that the Guarantee is a demand guarantee and
as such it is independent of the underlying agreement
and the
Department is entitled to insist on performance from Infiniti under
the Guarantee. The Department contends that there is
no privity of
contract between the applicants and Infiniti insofar as the Guarantee
is concerned. Thus, it is contended, the applicants
lack
locus
standi
to have sought the interim order granted by Mia AJ.
[19]
The applicants have a further string to their bow. They contend for a
development of the common law to require that an
employer, such as
the Department, in making a demand on a guarantee "…
must
ensure not only that they are correct but, also, any relevant
information in respect thereof must be placed before the Guarantor
Infiniti.
" They contend that the development of the common
law in this regard is consonant with the development of the law in
other
jurisdictions and is particularly apposite to conditional
bonds. The applicants propose that a less stringent standard can
justifiably
be adopted for determining whether a call on a guarantee
can, or should, be restrained.
[20]
The applicants rely on the
boni mores
of society demanding
that where parties are drawing on a guarantee, to the detriment of
other parties, "…
their dealings must be in the utmost
good faith and ought not to be permitted [sic] that conduct which is
unconscionable …
". The detriment is stated as being,
inter alia
, financial prejudice as payment under the Guarantee
by Infiniti will “trigger” Infiniti to make a claim
against the
applicants in terms of the security they provided to
Infiniti (being a special counter-indemnity given by the applicants
to Infiniti,
a deposit and pledge and a deed of suretyship and
indemnity given by certain companies and individuals to Infiniti).
This will
affect the applicants’ cashflow crippling their
short-term ability to trade and “inevitably” leading to
the demise
of their businesses and a consequent loss of employment
for their employees.
[21]
The applicants contend that
"116. The
exception would, or should, accommodate demands:-
116.1 for excessive
sums;
116.2 based on
contractual facts, circumstances and/or breaches that the beneficiary
of the call itself is responsible for;
116.3 tainted by
unclean hands, mounted on the back of selective and incomplete
disclosures;
116.4 made for
ulterior motive;
116.5 based on a
position which is inconsistent with the stance that the beneficiary
took prior to calling on the performance
bond."
[22]
In the context of this matter, the applicants contend that the
Department's conduct was unconscionable and tainted by
unclean hands
arising from incomplete disclosures, breaches of the GCC Agreement
for which the Department was responsible and in
particular the
circumstances in which the Agreement was terminated.
#
# THE GUARANTEE
THE GUARANTEE
[23]
In
Zanbuild
,
[1]
the Supreme Court of Appeal identified the two forms of guarantee
familiar to our law. The first being a “conditional guarantee”
and the second being a “demand guarantee”. The difference
between the two was explained thus
“…
a
claimant under a conditional bond is required at least to allege
and — depending on the terms of the bond — sometimes
also
to establish liability on the part of the contractor for the same
amount. An 'on demand' bond, also referred to as a 'call
bond', on
the other hand, requires no allegation of liability on the part of
the contractor under the construction contracts. All
that is required
for payment is a demand by the claimant, stated to be on the basis of
the event specified in the bond.”
[24]
Accordingly, it is necessary to begin by establishing the nature of
the Guarantee.
[25]
The material portion of Guarantee in this case provides
“
1.
Fixed
Performance Guarantee
1.1 Where a Fixed
Performance Guarantee has been selected, the Guarantor's liability
shall be limited to the amount of the Guaranteed
Sum.
1.2 The Guarantor's
period of liability shall be from and including the date on which the
Performance Guarantee is signed, up to
and including the Expiry Date,
or the date of issue by the Employer's Agent of the Certificate of
Completion of the Works, or the
date of payment in full of the
Guaranteed Sum, whichever occurs first.
1.3 The Employer's Agent
and/or the Employer shall advise the Guarantor in writing of the date
on which the Certificate of Completion
of the Works has been issued.
2.
Conditions Applicable to Variable and Fixed Performance Guarantees
2.1 The Guarantor hereby
acknowledges that:
2.1.1 Any
reference in this Performance Guarantee to the Contract is made for
the purpose of convenience and shall not be
construed as any
intention whatsoever to create an accessory obligation or any
intention whatsoever to create a suretyship.
2.1.2 Its
obligation under this Performance Guarantee is restricted to the
payment of money.
2.2 Subject to the
Guarantor's maximum liability referred to in 1.1, the Guarantor
hereby undertakes to pay the Employer the sum
certified upon receipt
of the documents identified in 2.2.1 to 2.2.3:
2.2.1 A copy of a
first written demand issued by the Employer to the Contractor stating
that payment of a sum certified by
the Employer's Agent in an Interim
or Final Payment Certificate has not been made in terms of the
Contract and failing such payment
within seven (7) calendar days, the
Employer intends to call upon the Guarantor to make payment in terms
of 2.2.2;
2.2.2 A first
written demand issued by the Employer to the Guarantor at the
Guarantor's physical address with a copy to the
Contractor stating
that a period of seven (7) days has elapsed since the first written
demand in terms of 2.2,1 and the sum certified
has still not been
paid:
2.2.3 A copy of
the aforesaid payment certificate which entitles the Employer to
receive payment in terms of the Contract
of the sum certified in 2.2.
2.3 Subject to the
Guarantor's maximum liability referred to in 1.1 the Guarantor
undertakes to pay the Employer the Guaranteed
Sum or the full
outstanding balance upon receipt of a first written demand from the
Employer to the Guarantor at the Guarantor's
physical address calling
up this Performance Guarantee, such demand stating that;
2.3.1 the Contract
has been terminated due to the Contractor's default and that this
Performance Guarantee is called up in
terms of 2.3; or
2.3.2 a
provisional or final sequestration or liquidation court order has
been granted against the Contractor and that the
Performance
Guarantee is called up in terms of 2.3; and
2.3.3 the
aforesaid written demand is accompanied by a copy of the notice of
termination and/or the provincial/final sequestration
and/or the
provisional liquidation court order.
2.4 It is recorded that
the aggregate amount of payments required to be made by the Guarantor
in terms of 2.2 and 2.3 shall not
exceed the Guarantor's maximum
liability in terms of 1.1.
2.5 Where the Guarantor
has made payment in terms of 2.3, the Employer shall upon the date of
issue of the Final Payment Certificate
submit an expense account to
the Guarantor showing how all monies received in terms of the
Performance Guarantee have been expended
and shall refund to the
Guarantor any resulting surplus. All monies refunded to the Guarantor
in terms of this Performance Guarantee
shall bear interest at the
prime overdraft rate of the Employer's bank compounded monthly and
calculated from the date payment
was made by the Guarantor to the
Employer until the date of refund.
2.6. Payment by the
Guarantor in terms of 2.2 or 2.3 shall be made within seven (7)
calendar days upon receipt of the first written
demand to the
Guarantor.
2.7. Payment by the
Guarantor in terms of 2.3 will only be made against the return of the
original Performance Guarantee by the
Employer.
2.8. The Employer shall
have the absolute right to arrange his affairs with the Contractor in
any manner which the Employer may
consider fit and the Guarantor
shall not have the right to claim his release from this Performance
Guarantee on account of arty
conduct alleged to be prejudicial to the
Guarantor.”
[26]
The
principles of interpretation of documents are uncontroversial. A
Court undertakes a unitary, purposive and objective exercise
by
giving the words used their ordinary grammatical meaning, in their
correct contextual setting, and construed consistently with
the
Constitution
[2]
together with
admissible background circumstances.
[3]
[27]
The Department relies upon clause 2.3 of the Guarantee. This clause
imposes a contractual obligation on Infinity to pay
the Department,
subject to its maximum liability, the sum certified on the first
written demand which must be accompanied by certain
documents as
stipulated in the relevant sub-clauses. This is an independent
obligation between the Department and Infiniti, discrete
from the
GCC.
[28]
This is not
unlike the guarantees held to be a demand guarantee by the Supreme
Court of Appeal in
Kentz
[4]
citing
its earlier decision
Landmark
[5]
where the relevant clause provided
“
'3. The
Guarantor hereby acknowledges that:
3.1 Any
reference in this Guarantee to the Agreement is made for the purpose
of convenience and shall not be construed
as any intention whatsoever
to create an accessory obligation or any intention whatsoever to
create a suretyship.
3.2 Its
obligation under this Guarantee is restricted to the payment of
money.
3.3 Reference
to a practical completion certificate or to a final completion
certificate shall mean such certificate
as issued by the Principal
Agent.'”
[6]
[29]
In each of the
Landmark
and
Kentz
authorities, the
guarantees were held to be demand guarantees.
[30]
Landmark
was distinguished by the Supreme Court of Appeal in
Zanbuild
where it considered a guarantee framed as follows:
"[18]
…
'. . . whereas it is
stipulated in the [construction] contract that the contractor [ie
Zanbuild] shall provide the employer [ie
the department] with a bank
guarantee of 10% of the contract value . . . as security for the
compliance of the contractors performance
of obligations in
accordance with the contract,
and whereas the bank [ie
Absa] is willing to agree to guarantee an amount . . . which is equal
to 10% of the contract value under
certain conditions stipulated
hereafter . . . .
Now therefore we the
undersigned . . . in our capacities as [employees of] the bank do
hereby guarantee and bind the bank as guarantor
for the due and
faithful performance by the contractor of all its obligations in
terms of the said contract subject to the following
conditions . . .
With each payment under
this guarantee the bank’s obligation shall be reduced
pro
rata
.
Each claim by the
employer must be made in writing accompanied by a signed statement
that the contractor has failed to fulfil his
obligations in terms of
the contract and shall be sent to the bank’s domicilium address
as indicated below . . .
The bank reserves the
right to withdraw the guarantee after the employer has given 30
(thirty) days written notice of its intention
to do so, provided the
employer shall have the right to recover from the bank the amount
owing and due to the employer by the contractor
on the date the
notice period expires.'."
[31]
The Court held that this guarantee was not an "on demand"
guarantee but gives rise to a liability akin to a
suretyship. It
said:
"The first indicator
in that direction is the assertion at the outset that the guarantee
‘
provide
security for the compliance of the contractor’s performance of
obligations in accordance with the contract
’.
And in the body of the document the bank guarantees ‘
the
due and faithful performance by the contractor
’.
This accords with language associated with suretyships."
[7]
[32]
Zanbuild
was discussed further in
KNS
[8]
where the Supreme Court of Appeal considered a guarantee framed as
follows:
"[2] …
‘
1. . .
Mutual & Federal Insurance Company Limited (Reg. No:
1970/00619/06) (hereinafter referred to as “the Guarantor”)
do hereby hold at your disposal the amount of R3 423 850.49 (Three
million, four hundred and twenty three thousand, eight hundred
and
fifty rand and forty nine cents) for the due fulfilment by Aqua
Transport & Plant Hire (Pty) Ltd (Reg No. 2003/007768
(hereinafter referred to as “the sub-contractor”) of its
obligations to KNS Construction (Pty) Ltd Reg. No: 2004/013912/07
thereafter referred to as “KNS” [Construction] in terms
of the above stated contract between the Sub-Contractor and
KNS
[Construction].
2. The Guarantor
hereby renounces the benefits of the exceptions
non numeratae
pecuniae
, non-causa debiti, excussion and division, the meaning
and effect whereof we declare ourselves to be fully conversant.
3. The Guarantor
undertakes to pay KNS the said amount of R3 423 850.49 (Three
million, four hundred and twenty three thousand,
eight hundred and
fifty rand and forty nine cents) or such portion as may be demanded
on receipt of a written demand from KNS [Construction]
which demand
may be made by KNS [Construction] if, (in your opinion and at your
sole discretion), the said Contractor fails and/or
neglects to
commence the work as prescribed in the contract or if he fails and/or
neglects to proceed therewith or if, for any
reason, he fails and/or
neglects to complete the services in accordance with the conditions
of contract, or if he fails or neglects
to refund to KNS
[Construction] any amount found to be due and payable to KNS
[Construction], or if his estate is sequestrated
or if he surrenders
his estate in terms of the Insolvency Law in force within the
Republic of South Africa’."
[9]
[33]
The Court went on to find that:
"The language used
is similar to that in
Zanbuild
.
Clause 1 states that it is issued for the ‘due fulfilment’
by Aqua of its obligations to KNS Construction in terms
of the
sub-contract. Clause 3 of the guarantee states that the
guarantee amount is payable ‘. . . on receipt of a written
demand from KNS [Construction], which demand may be made by KNS
[Construction] if (in your opinion and at your sole discretion)
the
said Contractor [Aqua] fails and/or neglects to commence the work as
prescribed in the contract or if he fails and/or neglects
to proceed
therewith or if, for any reason, he fails and/or neglects to complete
the services in accordance with the conditions
of contract. . ."
[10]
[34]
The Court concluded:
"… The
inescapable conclusion is therefore that the guarantee is akin to
suretyship (like that in
Zanbuild
),
and thus a conditional guarantee and not a call or demand guarantee.
Therefore the court
a
quo
erred in holding that the guarantee is a demand and not a conditional
guarantee."
[11]
[35]
There is no language in the Guarantee indicating that Infiniti’s
obligations thereunder are not sperate and that
the primary
obligations are owed to the Department. Clause 2.3 of the Guarantee
is clear in its terms and the applicants do not
contend otherwise.
[36]
The
applicants’ case of the Guarantee being conditional is
predicated on a link (or, as the applicants suggest, an implied
term)
between the requirement in the Guarantee stating that “
the
Contract has been terminated due to the Contractor's default
”
and the facts underlying this statement. The applicants’
argument is substantially the same argument advanced and
rejected in
Kentz
.
[12]
Similarly, the assertion that an employer in the position of the
Department is required to “
prove
”
cancellation, by “
substantiating
it” and placing “…any relevant evidence in respect
thereof before the Guarantor
”
has been rejected in
Dormell
.
[13]
As stated in
Dormell
:
“…
the cases
to which I have referred above make abundantly clear, the appellant
did not have to prove that it was entitled to cancel
the building
contract with the second respondent, as a precondition to
enforcement of the guarantee given to it by the first
respondent. Nor
does it have to do so now.”
[37]
I, in turn, and as I am bound to do, reject the applicants’
argument too.
FRAUDULENT
DEMAND
[38]
It is not a
new controversy that a contractor, in the position of the applicants,
disputes an employer's right to cancel the construction
contract that
gave rise to the guarantee. It is also asserted that the call on the
guarantee is, in those circumstances, fraudulent
and thus approaches
a court for interdictory relief in those circumstances. The learned
author of
The
Law of Letters of Credit and Bank Guarantees
[14]
,
with
reference to
Sztejn
[15]
,
suggests that injunctive relief is available to stop payment by the
guarantor. This goes to the Department’s
locus
standi
point. By virtue of the view I have taken in this case, this point
does not need to be decided.
[39]
It is long
established that a court will only reach a conclusion on paper that a
fraud has been committed in the clearest of cases.
[16]
[40]
The issue herein is whether the dispute between the applicants and
the Department surrounding the latter's right to cancel
the
Agreement, and the circumstances surrounding that dispute, disentitle
the Department to make demand on Infiniti in terms of
the Guarantee
and whether having done so, it is fraudulent as contemplated in the
authorities.
[41]
In effect, the applicants seek a judicial pronouncement on whether
the Department was entitled to terminate the Agreement.
[42]
I have
difficulties with the proposition that the demand "misrepresents"
certain facts (the misrepresentation being the
high watermark of
the applicants' case on fraud) and with what it seeks this Court to
do. This falls short of the bar set
in
Loomcraft
[17]
which
holds that a factually incorrect contention is insufficient to found
fraud. Knowledge that a factual contention is incorrect
and bad faith
in advancing that contention are required.
[18]
[43]
As pointed
out by Cloete JA in
Dormell
,
[19]
the "dispute" between the applicants and the Department is
res
inter alios acta
as far as the applicants are concerned.
[20]
Further, and notwithstanding any adjudication in relation to that
dispute, it is not bad faith for the Department to insist upon
payment from Infiniti while the dispute is pending before an
adjudicator.
[21]
[44]
This is not
a situation where the Department has called on the Guarantee with
knowledge that it is not entitled to the payment.
[22]
When viewed from the Department's perspective, there is a dispute
surrounding cancellation. The applicants' case is that the Department
was not entitled to cancel for various reasons and thus it cannot be
said that it was in default. The Department's contrary contention
is
that irrespective of any dispute raised by the applicants, the
applicants failed to achieve the milestones required in terms
of the
Agreement.
[45]
I am not
entitled to determine the parties' rights and obligations flowing
from the Agreement.
[23]
Consequently, I find that the applicants have not discharged the onus
of establishing the fraud exception.
[46]
In any event, and even if the, I am uncertain whether this court
enjoys jurisdiction over the Department. Be that as
it may, this is
an issue for the court seized with Part B of this application to
determine.
# VALID DEMAND ON THE
GUARANTEE
VALID DEMAND ON THE
GUARANTEE
[47]
I have found above, that the Guarantee is unconditional and an
on-demand Guarantee. The consequence of these findings
is that
Infiniti is obliged to pay the Department in terms of the Guarantee,
subject only to the demand satisfying its requirements.
[48]
The applicants' contention in this regard is that the demand is
fatally defective. The grounds upon which it relies for
this
conclusion are quoted above.
[49]
Before addressing these grounds, it is necessary to establish some
principles.
[49.1]
In
Hospitality
Hotel Development
[24]
the Supreme Court of Appeal left the question of "whether strict
compliance" is necessary for a proper demand on a performance
guarantee.
[25]
It held that
the point did not arise because there had not been compliance, let
alone strict compliance, with the express terms
of the guarantee
which required a particular document to accompany the demand. Because
the relevant document did not accompany
the demand, it was held that
the demand did not comply with the terms of the guarantee.
[49.2]
In
Schoeman
[26]
the Supreme Court of Appeal considered the distinction between
mandatory and directory provisions of a demand in the context of
the
address at which the demand was to be made. In that case, the
appellants contended that the demand was bad because it was made
at
an address other than that stipulated in the guarantee. With
reference to English authority, the Supreme Court of Appeal held
that
efficacy of the presentation is the guiding principle. It held the
demand to be effective.
[49.3] Accordingly,
a proper demand on an on-demand guarantee requires an effective
demand that, on the face of it, satisfies
its requirements for
validity.
[50]
Turning now to the Department’s demand on the Guarantee.
[51]
The demand is couched as follows:
“
Infiniti Insurance
Limited has provided the Performance Guarantee No. PS GUA RZZ 01
to Gorogang Plant/ Razz Civils
JV for the above contract - see
attached copy of Performance Guarantee.
The Contractor, Gorogang
Plant/ Razz Civils JV has defaulted on the Contract and the
Performance Guarantee is now being called up.
In terms of Clause
9.2.1.3.3 of the GCC 2015 (Third Edition), the Employer has
terminated the above contract - see attached letters
dated 07 &
21 June 2022.
You are hereby given
Notice in terms of Clause 2.3.1 and 2.3.3 of the Performance
Guarantee, that the Department of Transport, Eastern
Cape as the
Employer is now calling up the payment of the Guaranteed Sum, of R
44,442,702.75 (Forty Four Million Four Hundred and
Forty Two Thousand
Seven Hundred and Two Rand Seventy Five Cents).
Payment is to be made
within 7 days of receipt of this Notice, in terms of Clause 2.6 of
the Performance Guarantee, into the following
bank account number :
…
Could you please indicate
as to the details as to where the original Guarantee Documents can be
delivered.
If you have any questions
regarding the above, please do not hesitate to contact Mr Clive
Boshoff atc[…]."
[52]
Ex facie
the demand, the notice of termination contemplated in clause 2.3.1.
of the Guarantee is attached thereto. The applicants dispute
this,
specifically, they deny that there are letters dated 7 and 21 June
2022. In answer, the Department states that the “
termination
letter was attached to the demand
”
and “
the
correct letter of termination is annexed to the demand
.”
The applicants appear to accept that is the position in the replying
affidavit. To the extent that there is a dispute on
this issue, the
balance of probabilities is against the applicants.
[27]
[53]
I am not
satisfied that the demand was bad. Infiniti received the demand and
it was accompanied by the termination. The demand states
that the
Agreement was terminated on account of the applicants’ default.
The requirement in clause 2.7 to return the original
Guarantee is not
a requirement for a valid demand. The clause pertains to when payment
will be made.
[28]
In the same
way, the overstatement of the amount claimed in the demand does not
defeat it. In terms of clause 2.3 of the Guarantee,
Infiniti’s
liability is limited to “Guaranteed Sum”. In these
circumstances, the “amended” demand
is of no moment.
DEVELOPMENT
OF THE COMMON LAW
[54]
In
Sasfin
[29]
the Appellate Division considered whether a
parate
executie
clause was contrary to public policy and the decision therein holds
that contractual provisions are contrary to public policy when
that
is their clear effect. In
Juglal
[30]
the Supreme Court of Appeal, having considered
Sasfin
,
held that if a contractual provision is capable of implementation in
a manner that is against public policy, but the tenor of
the
provisions are neutral, then the offending tendency is absent. In
such an event, the creditor who implements the contract in
a manner
which is unconscionable, illegal or immoral will find that a court
refuses to give effect to this conduct but the contract
itself will
stand.
[31]
[55]
It is correct that, as a general proposition, demand guarantees may
be the subject of abuse in the sense of a fraudulent
demand. That is
the very reason that the fraud exception to a guarantor's liability
exists.
[56]
In
Gutteridge and Megrah's Law of Bankers' Commercial Credits
,
the authors, citing numerous English decisions, submit that:
"… it is now
established that the bank is under no obligation to pay the seller
where the seller fraudulently presents
documents that contain
material misrepresentations of fact that to the sellers' knowledge
are untrue. The corollary of this
is that where the fraudulent
conduct of the seller is obvious or clear to the bank, the bank is
not entitled to reimbursement from
the buyer if he pays it. In
this respect there is an amplified limitation on the bank's mandate
to pay under the letter of
credit and it is no discretion to pay
where it knows of the fraud”.
[32]
[57]
This is not
a controversial proposition. It is based on the New York
Supreme Court case of
Sztejn
[33]
,
which was approved by the English Court of Appeal in
Edward
Owen Engineering Limited
[34]
which, in turn, was approved and followed by the Appellate
Division
[35]
and of the
Supreme Court of Appeal in,
inter
alia
,
Coface
.
[36]
[58]
When due regard is had to the purpose of demand guarantees which have
been set out with precision and clarity by,
inter alia
, the
Supreme Court of Appeal in the numerous decisions cited in this
judgment, I can find no basis for the development of the common
law
along the lines suggested by the applicants.
[59]
The effect of the applicants' contentions is to turn demand
guarantees into conditional guarantees and impose a higher
threshold
on a party seeking to enforce their security.
[60]
To do so would defeat the entire purpose of demand guarantees in
circumstances where our law already recognises and provides
safeguards against the abuses contended for by the applicants.
[61]
There is nothing
contra bonis mores
in the Guarantee,
specifically, or generally.
REQUIREMENTS
FOR INTERDICTORY RELIEF
[62]
The
requirements for interdictory relief are long established. The
applicants were required to establish
a
prima facie
right even if it is open to some doubt; a reasonable
apprehension of irreparable and imminent harm to the right if an
interdict
is not granted; the balance of convenience must favour
the grant of the interdict; and the absence of a suitable
alternative
remedy.
[37]
[63]
The applicants’
prima facie
right is predicated on it
having not breached the Agreement and the proposition that the
Department’s demand on the Guarantee
“…
is
inextricably linked to whether or not [they were] in breach
”.
[64]
So it is contended, “…
the applicants have a clear
right to have the [Department] restrained from benefitting under a
demand that is not only procedurally
defective but, also,
unsubstantiated by the underlying jurisdictional prerequisites and
tainted on the bases traversed in this
affidavit, more particularly
fraud and unconscionability.
”
[65]
In the alternative, the applicants content for a
prima facie
right on the basis that they enjoy a “right” to prevent
the department from benefitting under the Guarantee on the
aforementioned grounds and to seek that Infiniti be restrained from
making payment pending Part B.
[66]
I have found above, that the applicants’ construction of the
Guarantee is unsustainable and that the onus in respect
of fraud has
not been passed. In these circumstances, they do not enjoy a right,
whether
prima facie
or at all, to the interim interdict that
was sought.
[67]
In the
absence of a right, an application for interdictory relief must
fail.
[38]
[68]
The position is not saved by the applicants’ intention to seek
the extension of the common law. As I have indicated,
there is no
basis upon which the court’s duty to develop the common law is
triggered.
[69]
It follows that, in the absence of a right, no harm can follow.
URGENCY
AND COSTS
[70]
It is, however, necessary to examine the Department's conduct in
bringing this application before Court as this impacts
upon the
costs.
[71]
An
application for reconsideration is not urgent for the purposes of
Rule 6(12) simply because an order was granted in the
Urgent
Court.
[39]
This means, that in
the absence of demonstrable prejudice in the time between when an
application may be heard before an Urgent
Court and in the ordinary
course, a party seeking a reconsideration must set out the prejudice
that will ensue. The Department
did not do so. The vague allegations
that it is under pressure to complete the works in the Agreement,
without any further explanation,
do not pass the threshold. The
threshold is the same whether in an application for reconsideration
or when approaching the Court
under Rule 6(12)(a). In both
instances, the parties seeking relief must set out in clear terms
facts duly supported that will
pass the threshold of "absence of
substantive relief" if the matter is not heard before the Urgent
Court.
[72]
The Department did not do so.
[73]
To compound matters the Department delayed considerably in bringing
this application. There is simply no explanation
for a delay of
several months between when Mia AJ granted her order and when
this application was brought before the court.
This difficulty is
further compounded by the fact that when this application was set
down, it was not ripe for hearing.
[74]
Save for the need for finality, this application should not have been
heard before the Urgent Court.
[75]
The ordinary rule in respect of costs is that a successful party is
entitled thereto. In this case, however and given
the Department's
conduct, I decline to grant any costs order in its favour.
# CONCLUSION
CONCLUSION
[76]
I have found, above, that the Guarantee is a demand guarantee. I have
also found that the dispute concerning the termination
of the
Guarantee is not one that I can adjudicate upon. I have also found
that the demand on the Guarantee is good and that there
is no basis
for the extension of the common law. As a result, the applicants are
not entitled to the interdictory relief they sought
before Mia AJ.
[77]
In all of these circumstances, the interim order granted by Mia AJ
falls to be set aside. I intend to do so.
[78]
In the circumstances, I make the following order
The
Order granted by Mia AJ on 19 September 2023 is set aside.
A
W PULLINGER
ACTING
JUDGE OF THE HIGH COURT
GAUTENG
DIVISION, JOHANNESBURG
This
judgment was handed down electronically by circulation to the
parties’ and/or parties’ representatives by email
and by
being uploaded to CaseLines. The date and time for hand-down is
deemed to be
10h00
on
15 October 2024
.
DATE
OF HEARING:
26 March
2024
DATE
OF JUDGMENT:
15 October 2024
APPEARANCES:
COUNSEL
FOR THE APPLICANT:
D S HODGE
ATTORNEY
FOR THE APPLICANT:
TIEFENTHALER ATTORNEYS
COUNSEL
FOR THE SECOND RESPONDENT:
N
MATHE-NDLAZI
ATTORNEY
FOR THE DEFENDANT:
STATE ATTORNEY
[1]
Minister
of Transport and Public Works, Western Cape and Another v Zanbuild
Construction (Pty) Ltd and Another
2011 (5) SA 528
(SCA) at [13] and [14]
[2]
Cool
Ideas 1186 CC v Hubbard and Another
2014
(4) SA 474
(CC) at [28]
[3]
The
City of Tshwane Metropolitan Municipality v Blair Atholl Homeowners
Association
2019 (3) SA 398
(SCA) at [61]
[4]
Guardrisk
Insurance Company Limited v Kentz (Pty) Ltd
[2013] ZASCA 182
(29 November 2013) at [13]
[5]
Lombard
Insurance Co Ltd v Landmark Holdings (Pty) Ltd and Others
2010 (2) SA 86
(SCA) at
[6]
At
[5]
[7]
At [19]
[8]
Mutual
and Federal Insurance Company Limited and Another v KNS Construction
(Pty) Limited and Another
(208/2015)
[2016] ZASCA 87
(31 May 2016)
[9]
At [2]
[10]
At [13]
[11]
At [16]
[12]
At
[9] and [15]
[13]
Dormell
Properties 282 CC v Renasa Insurance Company Limited and Others
NNO
2011 (1) SA 70
(SCA) at [64] approved and followed in
First
Rand Bank Ltd v Brera Investments CC
2013 (5) SA 556
(SCA) at [10];
Coface
South Africa Insurance Company Limited v East London Own Haven t/a
Own Haven Housing Association
2014 (2) SA 382
(SCA) at [16]
[14]
Mugasha,
The
Law of Letters of Credit and Bank Guarantees
at 138
[15]
Sztejn
v J. Henry Schroder Banking Corporation
(1941) 31 N.Y.S.2d at 634
[16]
Kentz
at [18]
[17]
Loomcraft
Fabrics CC v Nedbank and Another
1996 (1) SA 812 (A)
[18]
At
822G to 823 C. See further,
Bombardier
Africa Alliance Consortium v Lombard Insurance Company Ltd and
Another
2021 (1) SA 397
(GP) at [22]
[19]
Dormell
v Renasa
[2010] ZAS CA 137
(1 October 2010)
[20]
ibid
[64]. See further,
Joint
Venture Aveng (Africa) (Pty) Ltd/Strabag International GmbH v South
African National Roads Agency SOC Ltd
2021 (2) SA 137
(SCA) at [28]
[21]
ibid
at [65]
[22]
Kentz
at
[17]
[23]
Kentz
at [22]
[24]
Compass
Insurance Company Ltd v Hospitality Hotel Developments (Pty) Ltd
2012 (2) SA 537 (SCA)
[25]
At [13]
[26]
Schoeman
and Others v Lombard Insurance Company Limited
2019 (5) SA 557 (SCA)
[27]
Webster
v Mitchell
1948 (1) SA 1186
(W) at 1189
[28]
Bombardier
at [23]
[29]
Sasfin
(Pty) Ltd v Beukes
[1989] 1 All SA 347 (A)
[30]
Juglal
NO and Another v Shoprite Checkers (Pty) Ltd t/a OK Franchise
Division
2004 (5) SA 248
(SCA)
[31]
At [12]
[32]
King,
Gutteridge
and
Megrah's Law of Bankers' Commercial Credits
,
8
th
Edition
at
66
[33]
supra
at 631
[34]
Edward
Own Engineering Ltd v Barclays Bank International
Ltd
[1978] QB 159
at 169
[35]
Loomcraft
Fabrics CC v Nedbank Ltd and Another
[1995] ZASCA 127
;
1996
(1) SA 812
(A) at 816 G to 817 A
[36]
Coface
South Africa Insurance Co Ltd v East London Own Haven t/a Own Haven
Housing Association
[2014]
(1) All SA 536
(SCA) at [10], [12] and [21] referring to
Guardrisk
Insurance Company Ltd v Kentz (Pty) Ltd
[2014] (1) All SA 307
(SCA) at [13]
[37]
Setlogelo
v Setlogelo
1914 AD 221
at 227;
Hix
Networking Technologies v System Publishers (Pty) Ltd and Another
[1996] ZASCA 107
;
1997 (1) SA 391
(A) at 398 I to 399 A
[38]
Plettenberg
Bay Entertainment (Pty) Ltd v Minister van Wet en Order en ‘n
Ander
1993 (2) SA 396 (C) at 400G;
Sweets
From Heaven (Pty) Ltd and Another v Ster Kinekor Films (Pty) Ltd and
Another
1999 (1) SA 796
(W) at [11];
Basil
Read (Pty) Ltd v Beta Hotels (Pty) Ltd and Others
2001 (2) SA 760
(C) at 768 C
[39]
Sheriff
Pretoria North-East v Flink and Another
[2005] (3) All SA 492
(T) at 497
sino noindex
make_database footer start
Similar Cases
South Africa Municipal Workers Union v Mahlomoyane and Other (2023/014975) [2024] ZAGPJHC 1175 (12 November 2024)
[2024] ZAGPJHC 1175High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Association of Regional Magistrates of Southern Africa v Independent Commission for Remuneration of Public Office and Others (28644/2024) [2024] ZAGPJHC 1219 (26 November 2024)
[2024] ZAGPJHC 1219High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Association of Regional Magistrates of Southern Africa v Independent Commission for Remuneration of Public Office Bearers and Others (28644/2024) [2024] ZAGPJHC 1235 (26 November 2024)
[2024] ZAGPJHC 1235High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Legal Practice Council v Louw (2023/068293) [2024] ZAGPJHC 1114; [2025] 1 All SA 744 (GJ) (1 November 2024)
[2024] ZAGPJHC 1114High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Known Associates (Pty) Limited v Astron Energy (Pty) Limited (2023/120004) [2024] ZAGPJHC 1020 (11 October 2024)
[2024] ZAGPJHC 1020High Court of South Africa (Gauteng Division, Johannesburg)99% similar