Case Law[2024] ZAGPJHC 1076South Africa
Rand Mutual Assurance Company v Charles (A5045/2022) [2024] ZAGPJHC 1076 (22 October 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
22 October 2024
Headnotes
Gore’s appeal and dismissed RMA’s cross appeal. The material terms of the order were:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 1076
|
Noteup
|
LawCite
sino index
## Rand Mutual Assurance Company v Charles (A5045/2022) [2024] ZAGPJHC 1076 (22 October 2024)
Rand Mutual Assurance Company v Charles (A5045/2022) [2024] ZAGPJHC 1076 (22 October 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_1076.html
sino date 22 October 2024
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG LOCAL
DIVISION, JOHANNESBURG
CASE NO: A5045/2022
(1)
REPORTABLE: YES/NO
(2)
OF INTEREST TO OTHER JUDGES: YES/NO
(3) REVISED: YES/NO
22/10/2024
In the matter between:
# RAND MUTUAL ASSURANCE
COMPANY LIMITED
RAND MUTUAL ASSURANCE
COMPANY LIMITED
# Applicant
Applicant
and
# GORE VINCENT CHARLES
GORE VINCENT CHARLES
# Respondent
Respondent
In
re:
# GORE VINCENT CHARLES
GORE VINCENT CHARLES
# Appellant
Appellant
and
RAND
MUTUAL ASSURANCE COMPANY LIMITED
Respondent
JUDGMENT ON LEAVE TO
APPEAL
# Manoim J (Maier-Frawley J
and Allen AJ concurring):
Manoim J (Maier-Frawley J
and Allen AJ concurring):
Introduction
[1]
This is an application for leave to appeal a
decision a full court has made in this matter.
[2]
The matter had come to the full court as an appeal
from a decision of a tribunal constituted in terms of the
Compensation for Occupational
Injuries and Diseases Act 130 of 1993
(“COIDA”), COIDA Act.
Briefly
put, the employee, Vincent Charles Gore, had appealed to the Tribunal
against a decision made by the respondent, Rand Mutual
Assurance
Limited (“RMA”), reducing his compensation.
[3]
The reason why RMA is the respondent is that it is
the entity licensed in terms of section 30 of COIDA to assess and
make claims
in respect of compensation. It was thus the licensed
entity relevant to the claim made by Gore whose accident occurred in
July
1996.
[4]
RMA made three assessments in relation to Gore.
The first, what we have termed the “original award”, was
made in August
1997. Years later, at the instance of Gore, RMA
reviewed the original award and made a new award which we have
referred to as the
‘revised award’. The revised award
increased the compensation to Gore from that in the original award.
But Gore again
approached RMA because he queried the computation of
the revised award. But instead of doing so, RMA concluded that the
revised
award was based on erroneous information and decided not only
to refuse him increased compensation but
overturned
the revised award with one providing for much lower
compensation.
This
has
been
referred
to
as
the
“
reduced
award”
(or “deprivation decision”) and was
made in December 2014.
[5]
Gore then decided to object to this award. In
terms of COIDA an ‘affected person’ may object to an
award made by the
Director-General, or in this case, the relevant
mutual association, the RMA. The objection is then heard by a
tribunal constituted
in terms of COIDA. There is no dispute between
the parties that this is the correct process to be followed. What is
in dispute
is whether Gore, as the affected person, brought his
objection timeously. This point was raised by RMA before the tribunal
which
dismissed it. Nevertheless, the tribunal also dismissed Gore’s
objection on the merits. He then appealed in terms of COIDA
to the
full court. RMA then cross-appealed the tribunal’s decision to
dismiss its argument that the objection was lodged
out of time.
[6]
The full court upheld Gore’s appeal and
dismissed RMA’s cross appeal. The material terms of the order
were:
a.
The order of the tribunal dismissing the
appellant's objection to the respondent's rejection of his claim for
compensation is set
aside and is replaced with the following order:
"The respondent's revised award, evidenced by its letter of 30
April 2013,
is reinstated with retrospective effect.
b.
The
cross-appeal
is
dismissed
with
costs,
including
the
costs
of
two
counsel.
[7]
RMA now seeks leave to appeal both the full
courts’ decision to uphold the appeal and to dismiss its
cross-appeal. Gore opposes
leave being granted in respect of both.
#
# Is leave to appeal
required from a full court?
Is leave to appeal
required from a full court?
[8]
The first issue the full court had to decide is
whether it was necessary to get leave to appeal a full court decision
from the full
court. Such leave is not required when the full court
has determined an appeal from a single judge in the High Court. In
such an
instance, the party seeking to appeal does not seek leave
from the full court but must instead, by way of special leave,
petition
the Supreme Court of Appeal. (“SCA”) This is in
terms of section 16(1)(b) of the Superior Courts Act 10 of 2013,
(“the
‘Act’”). However, the Act is silent on
whether the full court is required to hear an application for leave
to
appeal, when the original appeal came to it from a statutory
tribunal, as it did in the present case, or whether such leave is
also by way of petition to the SCA.
[9]
The situation was clarified recently, in
National
Credit Regulator v Lewis Stores (Pty) Ltd and Another
2020
(3) SA 390
SCA, where Wallis JA held that section 16(1)(b) of the
Act, does not apply to appeals to the full court from statutory
tribunals.
Hence in such an instance, he held, leave of the full
court is required.
[10]
Although that decision dealt with a different
statutory tribunal, it was common cause that this court is bound by
this decision
and hence it is competent for RMA to approach this full
court for leave to appeal.
# Basis of the appeal
Basis of the appeal
[11]
Although the notice of appeal is lengthy –
sixteen pages - Mr Hulley, who appeared for RMA, succinctly reduced
the issues
to three points. Two relate to the upholding of the appeal
and the third relates to the dismissal of the cross-appeal. Since the
cross-appeal point, if successful, would dispose of the matter, I
deal with it first.
# Cross- appeal
Cross- appeal
[12]
In terms of the cross-appeal, RMA contended that
the objection that served before the tribunal was lodged out of time.
RMA argues
that the objection should have been lodged within 180 days
of the decision by RMA to reduce Gore’s compensation. Since the
decision objected to was made on 12 December 2014, the objection
should have been lodged by 8 June 2015, but it was only lodged
on 29
September 2017.
[13]
It is common cause that the objection was not
lodged within 180 days. This point was argued by RMA before the
tribunal, but it nevertheless
granted condonation for the late
filing. On appeal to the full court, this court upheld the tribunal’s
decision on this point,
and dismissed the cross-appeal.
[14]
Two issues are raised in the leave to appeal on
this aspect. First RMA argues that the 180-day period is mandatory
and cannot be
condoned. Second, that even if there is a power to
condone, on the facts, no condonation should have been granted.
[15]
The relevant provision in COIDA is section 91(1),
which states:
“
Any
person affected by a decision of the Director-General or a trade
union or employer's organization of which that person was a
member
at the relevant
time
may,
within
180
days
after
such decision,
lodge
an
objection
against
that
decision
with
the
commissioner in the prescribed manner.”
[16]
RMA argues that the “
may
”
in this section only applies to the right to lodge
an objection. It argues that it is drafted in this way because a
person with
a right to object is not obliged to object. Hence the use
of the permissive ‘may’. However, RMA argues, the 180-day
period is peremptory. On its reading of the section, it must be
interpreted as follows: an affected person may object, but if they
do, they must do so in 180 days.
[17]
Of course, the section has not been drafted in
this way. RMA’s response has been to argue against the contrary
interpretation
- that if there was a power to condone the late filing
of the objection - the legislature would have catered for this
specifically,
but it has not done so. Absent such a clear indication,
so the argument goes, the period of 180 days is peremptory and cannot
be
condoned.
[18]
The
full court in its main decision has dealt with this issue and
explained why this section must be interpreted to allow a discretion
to a court to condone a late filing. This interpretation is one
consistent with protecting an objector’s right of access
to the
court. But even, if at best for RMA, there is some ambiguity, as the
Constitutional Court held in
Pickfords,
where
there are two possible interpretations of a statute, both of which
limit the right of access to the courts, one “…
must
consider which of these two interpretations would better promote the
spirit, purport and objects of the Bill of Rights and
constitute a
lesser infringement on the right in s 34 of the Constitution.”
[1]
Whilst
in
Pickfords
the
Court was dealing with a provision in the Competition Act that
limited the time period in which a complaint for anticompetitive
conduct could be lodged, the principle enunciated is of general
application. The court there distinguished between absolute
substantive
time bars and procedural time bars, preferring the latter
as it was more constitutionally compliant than the former. (Having
decided
that the provision could be interpreted as a procedural time
bar, the court went on to consider condonation.)
[19]
Applying that principle to the current matter, the
interpretation least limiting of access to the courts is the one
adopted in the
main decision. For this reason, the reading offered,
that the section affords a power to condone, is not a decision that
another
court would decide otherwise.
[20]
As far
as the facts on condonation are concerned, I do not consider that
another court would overturn the finding of the full court
on this
point. There is no dispute that for the purposes of section 91(1),
the reference to a decision by the director-general
can be understood
to be the decision made by RMA. The decision in this case that was
the subject of the objection was what we have
termed the reduced
award. Within one month of being notified of this award, Gore wrote a
letter to the chairperson of the RMA asking
for it to be
reconsidered.
[2]
Granted,
this letter probably did not comply with the formalities of
COIDA,
and
hence
was
arguably
not
in
the
prescribed
manner.
But
as
a
factor
in
considering
condonation,
it
is
relevant
to
show
that
Gore
acted
timeously
and diligently to vindicate his right to appeal.
[21]
Thereafter, in response to this letter, the
process was diverted at the suggestion of RMA, to a possible
arbitration, in January
2015. For reasons that are common cause the
arbitration process was never concluded, and Gore then, whilst the
arbitration process
was pending, filed his notice of objection with
the tribunal. This notice was only filed on 29 September 2017. Yet in
response,
RMA, in a letter to Gore’s representative’,
dated 3 October 2017, still urged that the arbitration process be
continued.
Various delays plagued this process until in late 2019,
the arbitrator concluded that he lacked jurisdiction to determine the
dispute.
[22]
RMA correctly concedes that this time period –
the interregnum caused by the arbitration diversion - should not be
taken into
account in assessing the time period. But it says Gore is
still unreasonably late, even subtracting this period from the time
that
had elapsed. However, this ignores the following facts: his
attempt to commence the process earlier (within one month of being
notified of the deprivation decision); that the period of delay was
not unreasonable once the arbitration diversion period is subtracted,
and that his prospects of success were strong. Gore after all was
appealing a deprivation decision that had taken away benefits
that
the RMA had agreed to give him two years earlier. It was not simply a
decision not to increase his benefit – its real
sting was to
remove a previous benefit. All this is relevant to condonation. I do
not consider that another court would decide
otherwise.The court
erred in finding that the appeal to it had been brought in terms of
section 91(5)(a)(iii) of COIDA
[23]
The full court found that the appeal had been
brought in terms of two sections of COIDA, being subsections 91(5)
(i) and (iii).
These state:
“
Any
person affected by a decision referred to in subsection (3)(a), may
appeal to any provincial or local division of the Supreme
Court
having jurisdiction against a decision regarding—
(i)
The interpretation of this Act or any other
law;
(ii)
…
(iii)
the question whether the amount of any
compensation awarded is so excessive or so inadequate that the award
thereof could reasonably
have been made
;
[24]
RMA
seeks to make two points here. First that the notice of appeal to
this full court did not refer to sub-section 91(5)(a) (iii)
, which
was the sub-section the full court relied on to order the relief. The
argument was that the appeal was confined to 91(5)(i)
which meant the
full court did not have the power to substitute. It argues that the
matter should have been referred back to the
tribunal. However, the
notice of appeal refers to section 91(5)(a) – i.e. the entire
section. The fact that it did not in
a piecemeal fashion itemise the
relief sought by citing each sub-section is an argument based on pure
formalism.
[3]
There
could have been no confusion as to what was being sought. RMA was
well aware of this and came prepared to meet this argument.
Indeed,
express reference was made to both sub-sections at the outset of the
argument presented by Mr Pearce (representing Mr Gore)
at the hearing
of the appeal.
[25]
Once
it is clear that the full court could act in terms of subsection
91(5)(a)(iii) the question then is whether it was correct
to
substitute its decision for that of the Tribunal. This is explained
in the judgment. There was little point in sending the matter
back to
the tribunal. The full court relied on an amount set out in a letter
from Gore’s employer Goldfields to RMA, not
its own
calculations.
[4]
Moreover, RMA
had itself applied the same amount to arrive at what we termed the
revised award. It then implemented the revised
award for some time,
until it made the deprivation decision that led to it adopting the
reduced award. It is now twelve years since
the revised award was
made, and twenty eight years since Gore’s accident. The letter
relied on was submitted at the time
by Goldfields, who were by then
the new owner of the mine. It is wholly unlikely that if the matter
was referred back any new evidence
could be produced by Goldfields.
Moreover, after waiting for 12 years only to go through a further
round of hearings would be substantial
injustice to Gore. Given this
background the full courts’ decision to substitute, was
entirely appropriate and accords with
the principles for substitution
set out by the Constitutional Court in
Trencon
[5]
# Incorrect interpretation
of section 51 of COIDA
Incorrect interpretation
of section 51 of COIDA
[26]
This third argument goes to heart of the appeal.
Gore’s compensation was based on him being permanently
disabled. The relevant
section which deals with this is section 51 of
COIDA. RMA seeks to found its leave to appeal on the basis that the
full court erred
in its interpretation of section 51, and
alternatively, erred as a matter of fact in relying on a figure
provided by Goldfields
which was itself based on an error of fact.
[27]
Section 51 of COIDA deals with compensation for
permanent disablement for persons who are either an employee in
training (51(1)(a))
or were under 26 at the time of the accident
(51(1)(b).
[28]
Each of these two subsections then provides for a
further option based on whether the person had a further five years’
experience.
Put differently, section 51 provides for four paths to
compensation. Since because of the accident, the employee never
follows
these paths, compensation is derived by considering the
position of someone who is a proxy for the employee if he/she had
followed
one of the four paths. The argument advanced by RMA is that
these paths are to be understood as distinctive. It argues that
contrary
to this approach the full court’s
decision
has
read
the
one
sub-section
conjunctively
and
not disjunctively. But the full court has not done
so.
[29]
The court appreciated the distinction between the
four paths to compensation and discusses them at length. As noted in
the decision:
“
For
purposes of determining the appellant's compensation within the
context of the mining engineering profession, the earnings of
the
following four different proxies ought to have been considered by the
respondent when reviewing the revised award, for purposes
of arriving
at the reduced award, and the most favourable outcome applied.”
[30]
There is thus no interpretive difference between
what the full court found is the correct interpretation of the
section and what
RMA contends. As Mr Pearce for Gore pointed out,
this argument on the law is moot.
[31]
The next argument advanced by RMA was that
regardless of its interpretation the full court had erred in its
choice of proxy. RMA
argues for two possible errors. The first error
is what I call the ‘qualification error’. The proxy
chosen, it argues,
was on the facts a person more qualified than
someone who is recently qualified. The second error is that even if
that was not
the case, the proxy chosen was someone who was both
recently qualified and with five years more experience in that
position. Since
this resulted from an elision of two distinct paths
in section 51(2)(a) (you had to be either, not both) I will refer to
this as
the elision error.
[32]
I briefly reprise the key facts on this before I
discuss the criticism further.
[33]
At the time of the accident Gore was a 25-year-old
engineer. He had still to complete a professional exam, but had he
done so and
thus become a recently qualified person, he would have
been classified as a sectional engineer. RMA accepts that he would
have
been a sectional engineer.
[34]
Granted there was some debate in the hearings over
whether he would have qualified to be a resident engineer, a more
senior position
and hence one better remunerated than that of a
sectional engineer. But the full court did not find that he would
have become a
resident engineer. Nevertheless, the notice of appeal
says this is what the full court did, but there is no basis for this
assertion.
The full court based its decision on the lower figure in
the Goldfields letter which states clearly that this was the
compensation
for a ‘sectional engineer’. The relevant
sentence in the letter, which is quoted in the full court’s
decision,
and which I quote again makes this clear:
“
The
salary determined for a
sectional
engineer
which
he would have got had he obtained his Certificate of competency (
which he was busy obtaining) would have been R 11 118.65”
(
Emphasis provided)
[35]
In oral argument Mr Hulley did not press the point
that the full court had concluded that Gore would have been a
resident engineer.
Despite this his argument was that the full court
had read the sub-section conjunctively not disjunctively. The court,
he argued,
found that Gore was both recently qualified and with five
years more experience. Since these are two separate paths Gore had to
qualify under one or the other, not both. Put more simply his proxy
could not be someone who is both a sectional engineer (recently
qualified – the first path) and one also with five-years’
experience (the second path). Hence, he argued that there
had been an
error of law and fact, what I referred to earlier as the ‘elision
error’.
[36]
But this is not what Goldfields’ letter
states – it makes no mention of him reaching R 11 118.65 only
after five more
years as a sectional engineer. To get around this
difficulty RMA has tried to argue that Goldfields had based its
decision on the
wrong proxy.
[37]
RMA sought to rely on a payslip in the record for
a Mr Swanepoel, a resident engineer, who it alleged had been used as
the proxy
for Gore’s compensation. But this is not correct on
the facts. Swanepoel’s remuneration only became a factor when
RMA
had requested his payslip at the time it made the later reduced
order. It was not relied on, nor did Gore furnish it, when it made
the earlier revised order – the decision the full court has
given effect to. RMA during argument at the appeal suggested
that
Gore had misled the tribunal by relying on Swanepoel’s
earnings. In the leave to appeal, RMA no longer points the finger
at
Gore for this reliance on Swanepoel, but now argues that it was
Goldfields that was in error, and hence the award of compensation
was
based on its erroneous understanding.
[38]
But RMA has no evidence for this argument. The sum
total of evidence for this is based on a payslip for Swanepoel in
February 1996
which describes him as “resident
engineer”
and
appears
to
show
a
payslip
evidencing
an
amount R12 346.00 as his ‘normal salary’.
Since this figure is close to the R 11 118.65 proxy used by
Goldfields in
its letter, RMA deduces that Swanepoel is the proxy and
because he was a resident engineer as indicated on the payslip, he is
the
wrong proxy.
[39]
But this is not correct on the facts. As Gore’s
counsel points out, the accident took place in July 1996, not
February 1996.
The relevant payslip for comparison from Swanepoel
must then be what he received in July 1996. In July 1996 he by then
received
a ‘normal salary’ of R13 087. But this was not
the figure that the full court has relied on. The court relied on the
lower figure of R 11 118.65. To repeat, this figure is the earning of
a sectional not a resident engineer.
[40]
This leaves as the last issue, regardless of
Swanepoel, whether this figure represents the earnings of a sectional
engineer who
additionally had five years’ experience. The
Goldfields’ letter is the best evidence in the record and makes
no mention
that this was the earnings of a sectional engineer with
five years’ experience.
On the
contrary the language suggests it is the salary of a recently
qualified sectional engineer. RMA did not lead any contrary
evidence
on this point. Its sole witness during the tribunal hearing was
someone from its claims department. But as the full court
noted, he
had no knowledge as to “
how the
revised award had been computed or how the reduced award was
calculated
”
.
[41]
There is no reasonable prospect that another court
would decide differently on the facts before the full court. The law
was correctly
applied to the facts.
# Conclusion
Conclusion
#
[42]
The
three grounds for leave to appeal do not meet the threshold required
for leave to appeal to be granted in terms of the Act.
[6]
The court was not referred to any case law not previously considered
or any new facts from the record. The application falls to
be
dismissed. As far as costs are concerned, even though Gore’s
counsel have disclosed to the court that they have acted
pro
amico
for
him throughout these proceedings, this is no bar to him being awarded
costs. Since both sides relied on two counsel, costs of
both are
appropriate.
ORDER:-
[43]
In the result the following order is made:
a. The application for
leave to appeal is dismissed with costs including the costs of two
counsel.
N. MANOIM
JUDGE OF THE HIGH
COURT,
GAUTENG
DIVISION, JOHANNESBURG
I
agree
A.
MAIER-FRAWLEY
JUDGE
OF THE HIGH COURT,
GAUTENG
DIVISION, JOHANNESBURG
I
agree
J.
ALLEN
ACTING
JUDGE OF THE HIGH COURT,
GAUTENG
DIVISION, JOHANNESBURG
Date
of hearing: 8 October 2024
Judgment
delivered 22 October 2024
This
judgment was handed down electronically by circulation to the
parties’
representatives
via email, by being uploaded to
CaseLines
and by release to
SAFLII.
The
date and time for hand-down is deemed to be 10h00 on 22 October 2024.
APPEARANCES:
Counsel
for Applicant: Adv G. Hulley SC with Adv N. Mayet
Attorneys
for Applicant: Van Velden-Duffy Inc
Counsel
for Respondent: Adv R. Pearce SC with Adv S. Sindikolo
Attorneys
for Respondent: Richard Spoor Inc
[1]
Competition
Commission v Pickfords Removals SA (Pty) Ltd
2021
(3)
SA 1 (CC) at paragraph 47.
[2]
This
letter was dated 11 January 2015. It is not in the record, however
we know about it because of a letter in the record from
RMA, which
confirms the date, and the content of the letter from Gore’s
attorney.
[3]
There
is no place for formalism in the application of law within the
current constitutional dispensation and more so, where the
interests
of justice dictate otherwise. In
City
of Tshwane Metropolitan Municipality v Afriforum and Another
2016
(6) SA 279
(CC), par 18, the Constitutional Court emphasized that
“
The
kind of justice that our constitutional dispensation holds out to
all our people is substantive justice... We cannot emphasise
enough,
that form should never be allowed to triumph over substance
.”
[4]
At this time the
erstwhile employer had been sold to Goldfields which had written the
letter.
[5]
See
Trencon
Construction (Pty) Ltd v Industrial Development Corporation of South
Africa Limited and Another
2015
(5) SA 245
(CC), paragraphs 47 to 55.
[6]
The
Supreme Court of Appeal has on more than one occasion reiterated
that an applicant for leave to appeal ‘must convince
the court
on proper grounds that there is a reasonable prospect or realistic
chance of success on appeal. A mere possibility
of success, an
arguable case or one that is not hopeless, is not enough. There must
be a sound, rational basis to conclude that
there is a reasonable
prospect of success on appeal’. See MEC Health, Eastern Cape v
Mkhitha (1221/2015)
[2016] ZASCA 176
(25 November 2016), paras 16 &
17 (with reference to S v Smith
2012 (1) SACR 567
(SCA), para
7);
Four
Wheel Drive Accessory Distributors CC v Rattan
2019
(3) SA 451
SCA, par 34;
Kruger
v S
2014
(1) SACR 647
(SCA) paras 2 & 3.
sino noindex
make_database footer start
Similar Cases
Rand Mutual Assurance Company Limited v Gore (A5045/2022) [2024] ZAGPJHC 1093 (22 October 2024)
[2024] ZAGPJHC 1093High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Rand Mutual Assurance Ltd v Road Accident Fund (2021/49003) [2025] ZAGPJHC 487 (21 May 2025)
[2025] ZAGPJHC 487High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Rand Water Board and Another v Kariki Pipeline and Water Project (Pty) Ltd (A2023/080029 & 2017/2774) [2024] ZAGPJHC 418 (22 April 2024)
[2024] ZAGPJHC 418High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Rand Leases Property (Pty) Ltd v City of Johannesburg Metropolitan Municipality (2022/23303) [2024] ZAGPJHC 672 (24 July 2024)
[2024] ZAGPJHC 672High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Randfield Education Centre and Another v Life Enrichment Institute NPC and Others (2024/069500) [2024] ZAGPJHC 603 (26 June 2024)
[2024] ZAGPJHC 603High Court of South Africa (Gauteng Division, Johannesburg)99% similar