Case Law[2023] ZAGPJHC 1165South Africa
Masehla v N.G and Another (2019/40372) [2023] ZAGPJHC 1165 (16 October 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
16 October 2023
Headnotes
Summary
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1165
|
Noteup
|
LawCite
sino index
## Masehla v N.G and Another (2019/40372) [2023] ZAGPJHC 1165 (16 October 2023)
Masehla v N.G and Another (2019/40372) [2023] ZAGPJHC 1165 (16 October 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1165.html
sino date 16 October 2023
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
IN THE HIGH COURT OF
SOUTH AFRICA,
GAUTENG DIVISION,
JOHANNESBURG
CASE NO: 2019/40372
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
In the matter between:
MASEHLA, TEBOGO
MATHIBENG
Applicant
And
G, N
First
Respondent
G, S-S
Second
Respondent
In re
G, N
First
Plaintiff
G, S-S
Second
Plaintiff
And
MASEHLA, TEBOGO
MATHIBENG
First
Defendant
MATHIBENG, ADAM
CHINAME
Second
Defendant
MOODLEY, RHONA
Third
Defendant
JUDGMENT
MOORCROFT AJ:
Summary
Rule 27(1) of uniform
rules – good cause – bona fides – reasonable
explanation and bona fide defence
Bar –application
for removal of bar – no reasonable explanation for three-year
delay
Order
[1] In this matter
I make the following order:
1.
The
application is dismissed;
2.
The
applicant is ordered to pay the costs of the application.
[2] The reasons for
the order follow below.
Introduction
[3]
For
the sake of convenience I refer to the parties as they are referred
to in the action. The applicant in this application is the
first
defendant in the action and is referred to as such.
The contract of sale
[4]
The
plaintiffs (as purchasers) and the first and second defendants (as
sellers) entered into a contract of sale of immovable property
in
December 2016. The sellers were going through a divorce at the time
and were liquidating their assets as part of the process.
[5]
The
contract of sale was subject to a voetstoots (“as is”)
clause. A number of specific defects were listed in clause
18 of the
contract and the sellers undertook to remedy these listed defects.
An addendum to the
contract was signed in October 2016. In terms of the addendum the
defendants as sellers would no longer be responsible
for the listed
defects and the purchase price was reduced.
The plaintiffs took
occupation of the property on 1 January 2017.
[6]
The
plaintiffs allege that they never received an electrical compliance
certificate as they were entitled to in terms of clause
14 of the
contract and in January 2017 they learned that there were no approved
building plans in respect of the improvements on
the property.
Approved building plans is a prerequisite for the erection of
structures on land and the failure to have plans approved
when
building may amount to a continuous offence.
They
also became aware of a number of latent defects after moving
into the house, and aver that the sellers knew of these
defects but
failed to point these out to the plaintiffs as they were obliged to
do.
The bar
[7]
The
plaintiffs caused a summons to be served on the defendants on 20
November and 2 December 2019. The first defendant entered appearance
to defend the action on 6 December of that year. A plea was not
forthcoming and a notice of bar was served on 9 March 2020. Receipt
of the notice of bar is not in dispute.
[8]
The
plaintiff’s particulars of claim were amended in 2021 but the
amendment did not elicit a response from the first defendant.
The application to
remove the bar
[9]
The
first defendant now seeks to remove the bar three years later. In
January 2023 the first defendant requested the plaintiffs
to agree to
the removal of the bar and the request was refused. The present
application followed on 6 February 2023 and the answering
affidavit
was filed on 25 March 2023.
The answering affidavit
was filed out of time and condonation is being sought by the
plaintiffs for the late filing. The answering
affidavit was filed
some 33 days after receipt of the application and in terms of the
notice of motion the plaintiffs were granted
ten days to give notice
of an intention to oppose the application and fifteen days to file
their answering affidavits. They were
late by some eight days.
The
plaintiff explain that the second plaintiff was working in the United
Kingdom and a new attorney had taken over the matter at
their
attorneys’ offices. There is no reason why condemnation should
not be granted as no prejudice was shown. The short
delay in filing
the answering affidavit is insignificant in the context of the long
period that has elapsed since the notice of
bar was given.
[10]
The
plaintiff’s application for default judgement was removed from
the roll on 19 April 2022 because of non-compliance with
requirements
for enrolment, but only after a notice of set down had been served on
the first defendant. It evoked no response.
The matter was then
enrolled for 12 September 2022 on which occasion the first defendant
appeared in person. The matter was postponed.
[11]
Four
months later the first defendant
’s attorney came on
record and the application was launched.
Rule 27(1)
[12]
Rule
27(1)
[1]
provides
that in the absence of agreement between the parties the court may on
good cause shown make an order extending or abridging
any time for
doing any act or taking any step in connection with proceedings of
any nature whatsoever. The rule therefore provides
the machinery for
the removal of a bar upon good cause shown.
Good cause comprises two
elements, a
bona fide
defence and a reasonable explanation for
the delay. The purpose of the rule is not to come to the aid of a
reckless litigant or
one who acts with an intentional disregard for
the rules of court; the purpose is rather to accommodate the
bona
fide
litigant.
[13]
A
satisfactory explanation must be given with sufficient particularity.
This does not mean that an applicant for condonation must
prove its
claim or rebut a plaintiff’s claim as it would at trial.
It
must also be established that the granting of the order will not
prejudice the other parties in a way that cannot be compensated
by a
suitable cost order.
[2]
[14]
The
first defendant blames the failure to timeously defend the action on
the fact that she was not able to procure the services
of a legal
representative to assist her and she only managed to do so in
December 2022. There is however no explanation as to why
she was
unable to obtain the services of an attorney during the period March
2020 to December 2022, a period of 21 months.
[15]
In
the founding affidavit the first defendants deals with the reasons
for the delay as follows in paragraph 42 of the founding affidavit:
“
The
plaintiffs’ combined summons were served on me on 02 December
2019. Thereafter, I served the notice of intention to defend
on time
on 06 December 2019. On 12 September 2022, the plaintiffs applied for
default judgement against me, and I went to appear
in court
personally to defend the application, as I was then not legally
represented. On this day I informed the honourable court
that I was a
lay person and that I was in the process of procuring attorneys that
would assist me in responding to the combined
sermons that were
served on me.
”
[16]
The
first defendant waited another four months to brief attorneys and it
was only in December 2022 that the attorneys contacted
the
plaintiffs’ attorneys. She at all times knew of the importance
of proper legal advice and already in 2019 before the
litigation
commenced she confirmed in correspondence that she was being advised
by an attorney.
[17]
Justice
delayed is justice denied. In the absence of a reasonable explanation
for the long delay the application must be dismissed.
[18]
In
respect of the
bona fide
defence the first defendant relies on the
voetstoots close in the sale agreement and to a list of defects. The
plaintiffs deny that
the list of defects formed part of the agreement
and state that it was only furnished in April 2017, some seven months
after the
agreement were signed in September 2016. The plaintiffs
aver that the first defendant was aware of the latent defects and
could
not rely on the voetstoots clause.
It is the case for the
first defendant that list of defects was in existence when the
contract was signed and that it formed part
of the written contract;
it follows that the contents were known to the first defendant at the
time when the contract was entered
into, and this is confirmed the
signatures of the first and second defendants appearing on the
document.
The document was however
not signed by the plaintiffs who did sign the contract itself. The
document is not referred to in the body
of the contract. It is a
free-standing document.
Prescription
[19]
The
first defendant also relies on prescription. The summons were served
three years and two months after the contract was entered
into and
the three-year prescription period in
section 11(d)
of the
Prescription Act, 68 of 1969
is applicable. Prescription only begins
to run when the “
creditor
becomes aware of the existence of the debt”
[3]
and
the plaintiffs explained that the defects only became visible after
they had taken occupation on 1 January 2017.
Conclusion
[20] I conclude
that the first defendant failed to show good cause for removal of the
bar. I therefore make the order as set
out in paragraph 1 above.
J MOORCROFT
ACTING JUDGE OF THE
HIGH COURT OF SOUTH AFRICA
GAUTENG DIVISION
JOHANNESBURG
Electronically
submitted
Delivered: This judgement
was prepared and authored by the Acting Judge whose name is reflected
and is handed down electronically
by circulation to the Parties /
their legal representatives by email and by uploading it to the
electronic file of this matter
on CaseLines. The date of the judgment
is deemed to be
16 OCTOBER 2023
.
COUNSEL
FOR THE APPLICANT:
T
QHALI
INSTRUCTED
BY:
NYAPOTSE
INC
COUNSEL
FOR THE RESPONDENTS:
N
TERBLANCHE
INSTRUCTED
BY:
COETZEE
ATTORNEYS
DATE
OF HEARING:
3
OCTOBER 2023
DATE
OF JUDGMENT:
16
OCTOBER 2023
[1]
See the discussion by Van Lo
ggerenberg
Erasmus:
Superior Court Practice
RS 17, 2021, D1-321 to D1-328B.
[2]
IL & B Marcow Caterers (Pty) Ltd v
Greatermans SA Ltd and Another; Aroma Inn (Pty) Ltd v Hypermarkets
(Pty) Ltd and Another
1981 (4) SA 108
(C)
112H to 113A.
[3]
Section 12(2)
of the
Prescription Act.
sino noindex
make_database footer start
Similar Cases
Masehla v Ganca and Another (2019-40372) [2024] ZAGPJHC 167 (22 February 2024)
[2024] ZAGPJHC 167High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Masebebalo v Matenji (53948/21) [2025] ZAGPJHC 271 (13 March 2025)
[2025] ZAGPJHC 271High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Maseule and Others v Grove and Others (2024/135845) [2024] ZAGPJHC 1299 (18 December 2024)
[2024] ZAGPJHC 1299High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Maseko v S (SS107/2019) [2022] ZAGPJHC 886 (25 October 2022)
[2022] ZAGPJHC 886High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Maseko v Passenger Rail Agency of South Africa (01242/2016) [2023] ZAGPJHC 477 (15 May 2023)
[2023] ZAGPJHC 477High Court of South Africa (Gauteng Division, Johannesburg)99% similar