Case Law[2022] ZAGPJHC 409South Africa
Dlamini INC. v Transnet SOC Ltd and Others (16593/19; 23785/19) [2022] ZAGPJHC 409 (2 June 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
2 June 2022
Headnotes
liable for performance in terms of its contractual obligations.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 409
|
Noteup
|
LawCite
sino index
## Dlamini INC. v Transnet SOC Ltd and Others (16593/19; 23785/19) [2022] ZAGPJHC 409 (2 June 2022)
Dlamini INC. v Transnet SOC Ltd and Others (16593/19; 23785/19) [2022] ZAGPJHC 409 (2 June 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_409.html
sino date 2 June 2022
FLYNOTES:
DOCUMENTS
– RULE 53 AND PAJA
Tender
– Subcontracting – Subcontractor excluded after award
of tender – Alleging B-BBEE fronting –
Transnet and
private body refusing request for documents – Rule 53 and
Promotion of Administrative Justice Act 3 of 2000
–
Refusal unlawful and prejudicial.
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NO: 16593/19
Reportable:
No
Of
interest to other judges: No
02
June 2022
In
the matter between:
DLAMINI
INC.
Applicant
and
TRANSNET
SOC LTD
First
Respondent
ERNST
& YOUNG ADVISORY SERVICES (PTY) LTD
Second
Respondent
and
CASE
NO: 23785/19
In
the matter between:
DLAMINI
INC.
Applicant
and
ERNST
& YOUNG ADVISORY SERVICES (PTY) LTD
First
Respondent
TRANSNET
SOC
LTD
Second
Respondent
COVINGTON
& BURLING (PTY) LTD
Third Respondent
MINISTER
OF TRADE, INDUSTRY AND COMPETITION
Fourth
Respondent
Judgment
Vally
J
[1]
There are two applications before me brought by a single applicant,
Dlamini
Inc. (Dlamini). Two respondents, Ernst & Young Advisory
Services (Pty) Ltd (EY) and Transnet SOC Ltd (Transnet) are the same
in both cases. Together with Dlamini they are the main protagonists
in both matters. The first application is case number 16593/19.
The
second application is case number 23785/19. Two other respondents are
cited in the second application. They are Covington and
Burling (Pty)
Ltd (Covington) and the Minister of Trade, Industry and Competition
(Minister). Covington played no part in that
litigation, whilst the
Minister attended to one of the issues therein. The parties referred
to the two cases as Dlamini 1 and Dlamini
2 respectively. For ease of
reference I will adopt the same nomenclature.
DLAMINI
1
Factual
matrix
[2]
On 1 June 2017 Transnet issued a Request For Proposal (RFP) for ‘The
appointment of transaction advisors to create an agile and integrated
process in response to potential business ventures for a
period of
four months.’ Parties interested in being appointed as the
‘transaction advisors’ were invited to bid
for the
appointment. One of the clauses in the RFP deals with the issue
of Broad Based Black Economic Empowerment (B-BBEE)
and socio economic
obligations that a successful bidder is required to comply with. The
clause in relevant parts reads:
‘
B-BBEE Joint
Venture or Consortiums
Respondents [Bidders] who
would wish to respond to the RFP as a Joint Venture (JV) or
consortium with B-BBEE entities, must state
their intention to do so
in their RFP submission. Such Respondents must also submit a signed
JV or consortium agreement between
the parties clearly stating the
percentage [%] split of business and associated responsibilities of
each party. If such a JV or
consortium agreement is unavailable, the
partners must submit confirmation in writing of their intention to
enter into a JV or
consortium agreement should they be awarded
business by Transnet through this RFP process. This written
confirmation must clearly
indicate the percentage [%] split of
business and the responsibilities of each party. In such cases, award
of business will only
take place once a signed copy of a JV or
consortium agreement is submitted to Transnet.
Subcontracting
Respondents are required
to submit proof of the subcontracting arrangement between themselves
and the subcontractor. Proof of the
subcontracting arrangement may
include a subcontracting agreement.
If contemplating
subcontracting, please note that a Respondent will not be awarded
points for B-BBEE if it is indicated in its Proposal
that such
Respondent intends subcontracting more than 25% [twenty-five percent]
of the value of the contract to an entity/entities
that do not
qualify for at least the same points that the Respondent qualifies
for, unless the intended subcontractor is an EME
with the capability
to execute the contract.
…
The successful Respondent
awarded the contract may only enter into a subcontracting arrangement
with Transnet’s prior approval.
The contract will be
concluded between the successful Respondent and Transnet, therefore,
the successful Respondent and not the
sub-contractor will be held
liable for performance in terms of its contractual obligations.
A person awarded a
contract may not subcontract more than 25% [twenty-five percent] of
the value of the contract to any other enterprise
that does not have
an equal or higher B-BBEE status level than the person concerned,
unless the contract is subcontracted to an
EME that has the
capability and ability to execute the subcontract.
In terms of
Section 8
of
this RFP [the B-BBEE Preference Point Claim Form] Respondents are
required to indicate the percentage of the contract that will
be
sub-contracted as well as the B-BBEE status of the subcontractor/s.’
[3]
EY placed a bid on 15 June 2017. Its bid indicated that Dlamini would
be one of the service providers. It said the following in this
regard:
‘
EY has
supplemented their team with Dlamini, a South African law firm to
advise on the legal and regulatory aspect of the transaction,
as well
as with I-manage, a 100% black-female advisory firm to contribute its
procurement and human resources expertise while upscaling
its skills
in investment process and best practices.’
[4]
Dlamini’s involvement in the project reigned prominently in the
bid documents. There were numerous references to its expertise. The
curriculum vitae of the founder and director of Dlamini (Ms
Nthabiseng Dlamini) and a subcontractor agreement between EY and
Dlamini were included in the bid documents. The subcontractor
agreement was signed on the same day as the bid was submitted. This
agreement indicated that EY and Dlamini:
‘…
shall
submit the Bid as a Team
…
shall
collectively produce the Bid in the manner set out herein. The Bid
will include at a minimum all of Parties mandatory terms
and
conditions of business.
…
…
hereby agree
that upon the successful bidding by the Team and the subsequent
awarding of Services to be rendered to the Client,
the Parties shall
enter into a Consortium Agreement. Such Consortium Agreement shall
regulate the Services and deliverables (including
where appropriate,
support for each other) to be delivered by each Party.’
[5]
Dlamini was to perform 30% of the work if the bid was successful.
[6]
On 18 January 2018 Transnet informed EY that its bid was successful.
On
16 January 2018, EY and Dlamini concluded a Letter of Intent
(LOI). The LOI would remain in place until a Master agreement was
concluded, or until 120 days from the date of signing had passed,
whichever was the earlier date. On 23 January 2018 Transnet convened
a meeting with EY. Dlamini and another of EY’s subcontractors
(I-Manage) were present at the invitation of EY. There all
the
parties discussed, amongst others, the practicalities of the
implementation of the contract. At this meeting:
‘
[i]t became
apparent to all present, including Dlamini, that EY had a different
interpretation of the scope of services required
when compared with
Transnet’s interpretation. For example, Transnet appeared to be
seeking deliverables with a much greater
level of detail than EY had
assumed in its bid submission. Further, Transnet appeared to no
longer want a PSP focus nor was it
interested in an analysis of the 6
projects listed in clause 2.1(a) of the Scope of Work contained in
the RFP.’
[7]
The meeting concluded with Transnet requesting EY to draft a work
plan.
This was drafted and sent to Transnet on 25 January 2018. In
terms of the work plan Dlamini was allocated the task to:
‘
lead the item on
the work plan labelled ‘
develop proposed changes to
applicable Regulatory and Legal Framework.
’’ (italics
in original)
[8]
In other words, despite the differences of opinion between EY and
Transnet
regarding the interpretation of the scope of work (and
whether there was a need to undertake ‘an analysis of the 6
projects
listed in clause 2.1(a)’), EY still appreciated that
there was a role for Dlamini in the performance of the contract.
[9]
Transnet and EY met again on 28 January 2018 in order to attend to
their
different interpretations of the scope of work. Dlamini was not
included in this meeting. Their different interpretations became
even
clearer during the discourse that took place. According to EY the
differences focused on clause 2.1(b) of the Scope of Work
described
in the RFP:
‘
EY was of the view
that the RFP required it to offer an
analysis
of current
business case development practices and criteria without being
required
to
actually develop
the business case
practices and criteria for Transnet. Transnet indicated that it did
not want an analysis but needed EY to develop
the business case
practices and criteria. Transnet indicated that it wanted an “end
to end process” (rather than a
mere “framework”)
which it could “go live with.”’ (Underlining in
original)
[10]
EY made it known that based on its interpretation it had put in place
an ‘Infrastructure
Team’ to perform its obligations in
terms of the contract. This was indicated to Transnet at the meeting.
In response:
‘
Transnet indicated
that even if the Infrastructure Team could not offer what it needed
then surely there was another team in the
so-called “innovation”
space that could assist.’
[11]
At this point both Transnet and EY were fully aware that not only
were their respective
interpretations of the scope of work different,
but also that EY had not catered for the implementation of the
contract as per
the understanding of Transnet. They were also aware
that Dlamini was to perform a substantial part of the work. Instead
of accepting
the incapacity of EY’s team to perform the
contract as per Transnet’s interpretation and reconsidering the
awarding
of the contract to EY, Transnet asked EY to find another
team to perform the work it sought. An email in response was sent to
Transnet
on 29 January 2018, wherein the following was recorded:
‘…
Further
to our meeting … and subsequent discussions internally at EY,
it is clear that our interpretation of the scope/ key
deliverables
set out in the RFP… seems to be significantly different from
what your expectations are.
…
the differences
between the respective interpretations as follows: Transnet had “much
more granular” view on the “level
of detail required”,
for example Transnet “indicated we need to produce all required
approval templates … we
had viewed the deliverables at more of
a framework/guidelines level”; “we had not allowed for
any “live”
testing of the developed governance and
controls process … and considered this out of scope”;
“the emphasis
and effort to be spent on case studies and
international best practice seems to now be less important”;
“the RFP was
issued through the PSP Panel … as such we
had assembled expertise in these areas … these skills seem
largely irrelevant
now”.
Unfortunately given the
above concerns, it is unlikely that we will be able to meet your
expectations on the scope of work/key deliverables
in the relatively
short time available. As such, unless we can somehow reach a landing
on the scope issues, we think it is in the
best interest of both
Transnet and EY, that EY withdraws from the project.’
[12]
Transnet was unambiguously informed that EY was unable to perform the
services required
by the RFP, since EY’s interpretation of its
bid did not cater for what Transnet was looking for. In fact, it says
that Transnet
was looking for ‘deliverables with a much greater
level of detail that [it] had assumed in its bid submission.’
[13]
EY made it patently clear to Transnet that, based on its
understanding of its bid, it had
‘assembled’ a particular
team to undertake the project. That team was not able to undertake
the work Transnet believed
it sought in terms of the RFP. EY was
willing to accept that the different interpretations were
irreconcilable and understood that
as a result Transnet may have to
reconsider the award, which, if it did, was not a problem for EY as
EY was willing to withdraw
from the project.
[14]
Transnet, however, did not see it this way. It responded on the same
day, saying that it
was awaiting ‘a revised work plan’
from EY, and until that was received it would ‘be premature for
EY to consider
withdrawing from the project at this stage.’ It
went further to say that its own interpretation of the scope of work
was
‘not cast in stone.’ Interestingly, Transnet also
recorded that the commencement date for the project was 22 January
2018, which had already passed.
[15]
Transnet and EY met the next day, 30 January 2018. Dlamini was not
present. They were not
able to reconcile their different
interpretations of the scope of work. However, that afternoon EY
delivered a second draft of
the work plan to Transnet and shared it
with Dlamini. Dlamini responded the same day suggesting minor
changes. The next day, 31
January 2018, EY updated Dlamini on the
outcome of the meeting with Transnet. EY informed Dlamini that there
was no need for any
further meeting for at least a week. Then,
according to the deponent to EY’s answering affidavit:
‘
Around this time
[after 31 January] it finally became clear to EY that the different
interpretations of the Scope of Work meant
that the Infrastructure
Team within EY was not best placed to deliver services that Transnet
required. At this point it became
clear that Transnet was seeking
predominantly business advice rather than infrastructure advice.’
[16]
We know that EY learnt at the meeting of 23 January 2018 – see
[5] above –
that its own interpretation of the scope of work
was very different from that of Transnet. By ‘around’ 31
January 2018
EY came to realise that Transnet was not willing to
accept that EY’s interpretation of the scope of work should be
implemented.
It insisted that its own interpretation of the scope of
work be implemented. This, despite the fact that EY informed Transnet
that
the team it had assembled to perform the work was incapable of
performing the work Transnet sought.
[17]
Thus far, EY was clear in its mind that it was its Infrastructure
Team and not its Advisory
Team that responded to the RFP, and that
its Infrastructure Team was to subcontract 30% of the work to
Dlamini. The work plan it
furnished to Transnet was designed on the
basis of this understanding.
[18]
Nevertheless, around a week later – after 31 January 2018 - EY
decided to convene
an internal meeting between its Infrastructure
Team and its Advisory Team. At the conclusion of this meeting EY
decided that its
Advisory Team should replace its Infrastructure Team
and perform the work as per Transnet’s interpretation of the
scope.
This was necessary because of Transnet’s insistence that
EY replace the Infrastructure Team since it was not ‘seeking
infrastructure advice but business advice’.
[19]
On 5 February 2018 EY informed Dlamini that it was engaging with
Transnet and that it would
revert to Dlamini in a ‘few days’
time regarding the official kick off plan and the dates relating to
the implementation
of the project.
[20]
On 6 February 2018 EY’s Advisory Team met with Transnet.
Dlamini was not invited
to the meeting. After the meeting the
Advisory Team, on the instruction of Transnet, prepared its own work
plan. This took place
on 8 February 2018 and was presented to
Transnet that same day. This work plan was radically different from
the one prepared by
EY’s Infrastructure Team on 25 January 2018
(which had input from Dlamini) and which was presented to, and
rejected by, Transnet.
A month later, on 6 March 2018 - bear in mind
the project was to commence on 22 January 2018 – see [13] above
– Transnet
accepted the work plan of the Advisory Team. This
work plan removed all legal work from the services that EY’s
Infrastructure
Team intended to deliver and on which its bid was
based.
[21]
There was a lull for over a month, and on 14 March 2018 Dlamini
sought an update from EY.
The response Dlamini received, per email,
was:
‘
Sorry for the
delayed reply.
Unfortunately based on our various discussions with
Transnet, it has emerged that there are a number of changes in the
scope interpretation
of this engagement since we originally responded
to the RFP
back in June 2017. For example the PSP focus, and PSP
case studies has reduced radically with for example more emphasis on
bringing
innovative products to implementation etc.. This has led to
a complete change in the make-up of the EY team best able to meet the
client needs – i.e. myself and Kebu have been replaced by
another EY team from a consulting background with a better matching
experience to client needs.
Given
the change of scope interpretation, regrettably there is no longer
need for specialist legal input so as such unfortunately
there is no
longer a role for Dlamini
. My apologies that this has occurred
but could not foresee [sic] this at time of tendering.’
(Underlining added)
[22]
Dlamini, wrote to EY on 27 July 2018 – four months and one week
after receiving the
letter – requesting that EY repeat the
contents of the email on a letterhead of EY. EY did not respond to
the request. On
23 August 2018 Dlamini sent another email to EY, this
time expressing its disappointment about being abandoned by EY. The
email
reads:
‘
Please note that
we have been requesting clarification and official written
communication from you since January this year, as to
why after we
tendered with EY and was awarded the … [the contract] with EY,
but we are no longer your partners in the Project.
After attending the kick
off meeting with Transnet and commenting on the proposed work
program, there was no indication that our
services were no longer
required. If you claim, as you do below, that our services were no
longer required was this communication
from Transnet? If so, can you
please provide us with such communication before close of business
today, failing that we will have
no option but to approach client
directly.
The tendency to
partner with companies for work and not share the work when it is
awarded after a fair and open tender, is tantamount
to fronting and
Dlamini Attorneys do not engage in such practices.
Now, if the
Scope of work changes radically as you state below we then assume
that the scope changed significantly for Treasury
Regulations be
applicable, and
in such circumstances if we receive a letter from
Transnet confirming compliance with same then we shall put this
matter to rest
’ (Underlining added, otherwise quote is
verbatim)
[23]
Dlamini asked that EY respond to the email on the same day. EY did
not do so. Importantly,
Dlamini asked that EY provide them with
written confirmation from Transnet that the scope had changed and
that there was compliance
with Treasury Regulations. It told EY that
if such confirmation was provided it would regard the matter as
closed. Not having received
a response by 27 August 2018, Dlamini
penned another email to EY requesting that it be given ‘written
confirmation of the
change of scope and confirmation that our
services were no longer necessary.’ On 27 August 2018 EY
responded per formal
letter explaining the position in full. It
stated:
‘
We refer to the
email exchange between [Dlamini] and [EY] dated 14 March 2018 in
which [EY] advised of the change of interpretation
of scope in the
above mentioned engagement. … [in that communication, EY
informed Dlamini] that there are a number of changes
in the scope
interpretation of this engagement since EY and Dlamini Attorneys
(“Dlamini”) had originally responded
to the RFP back in
June 2017. Given the change of scope interpretation, regrettably
there is no longer need for specialist legal
input so as such
unfortunately there is no longer a role for Dlamini.’
[24]
EY went on to say that it was unable to secure a letter from Transnet
to confirm its view
that there was a ‘change in the scope
interpretation’ since the contract was awarded. On this
response, Dlamini,
on 30 August 2018, decided to write to Transnet
informing it that it had been excluded from benefitting from the
contract awarded
to the consortium headed by EY. In the same letter
it asked Transnet to furnish it with certain information. The
relevant portion
of the letter reads:
‘
6.
Taking into account the feedback we received from EY in March and
August 2018, we kindly request
a letter from Transnet to confirm
that:
6.1.
the scope of the services have been changed by Transnet. If so, then
please provide us with communication
from Transnet to EY to that
effect;
6.2
as a result of the change in scope, the services to be provided by
Dlamini in terms of the
Partnership’s [Dlamini claimed that the
relationship between it and EY was one of a partnership] response to
the Transnet
RFP are no longer required. If so, then please provide
us with communication from Transnet to EY to that effect;
6.3
the supplier development plan provided, and undertaken, by the
Partnership … has
been complied with. If so, then please
provide us with a copy of the approved supplier development plan; and
6.4
the services contemplated in the Transnet RFP have been rendered by
EY, and whether the
services rendered by EY in terms of the Transnet
RFP have been paid.’
[25]
Transnet interpreted the contents of the letter to be a recordal of a
complaint and responded
in the following terms:
‘
1. Your letter of
complaint dated 30 August refers.
2. We wish to record that
at issue here is the interpretation of scope of work as opposed to
change of scope that is being alleged
by Dlamini Attorneys.
3. As you would know, the
two concepts are completely different from each other and a change of
scope would require mutual Agreement
between EY and Transnet, and
depending on the nature and extent of the change, a change of scope
may, in certain circumstances,
result in the award of the tender
being cancelled and RFP re-issued.
4. This was not the case
in this instance and we can confirm that EY is correct in saying
their initial interpretation of scope
was not completely aligned to
Transnet’s requirements.
5. Upon clarification and
alignment in interpretation of scope between Transnet and EY, EY
decided that another EY team, i.e. their
strategy team, was best
suited to deliver the project.
6.
Upon Transnet
agreeing,
the project was handed over to the EY strategy team and
delivered according to the scope that Transnet had defined in the
RFP,
LOI and MSA.
7. This is also confirmed
by EY in the various correspondence between EY and Dlamini Attorneys,
which correspondence appears to
be the source of your complaint.
8. In the correspondence
EY clearly stipulates that the issue at hand is around scope
interpretation by EY – not a change
in scope by either EY or
Transnet.
9. With regards to your
question on whether or not EY has complied fully with its SD
requirements, we wish to confirm that EY has
fully complied with its
SD obligations.
10. We trust that this
fully answers your questions.’
[26]
Dlamini was dissatisfied with aspects of the response received from
Transnet and on 21
November 2018 sought clarity as well as further
information from Transnet. Transnet interpreted this request as a
case of it being
drawn into a conflict between EY and Dlamini. It
attended to Dlamini’s request in the following terms:
‘
1. We refer to the
above matter and your e-mail dated 21 November 2018.
2. From the onset, we
must point out that we find it worrying that Transnet is being placed
on terms by [Dlamini] to provide certain
answers and information
relating to subcontracting arrangements between [Dlamini] and EY
3. For the record,
Transnet was not involved in the formation or discussions in relation
to the formation of the Consortium between
[Dlamini] and EY, but
Transnet evaluated a tender on the basis of a joint proposal
submitted by the Consortium.
4. Upon the award of the
tender, a contract was concluded between Transnet and the Consortium
in terms of which certain deliverables
were agreed upon, and which
deliverables were achieved by the Consortium and payment made by
Transnet.
5. In this regard, to the
extent that there may be a dispute between the Parties to the
Consortium in relation to how the contract
was performed, Transnet
had taken a considered decision that such matters must be resolved by
the Parties through the dispute resolution
process (if any) in terms
of the Consortium agreement.
6. In the circumstance,
we regret to inform you that we are not in a position to assist you
further in this matter and advise that
all issues in relation to the
performance of the above tender/Agreement by the Consortium be taken
up with EY.’
[27]
It is clear from the above that Transnet was:
a.
of the view that it was not its duty to ensure that the obligations
of the Consortium were performed
by the party identified in response
to the RFP as the one that would perform the specific obligation.
b.
unwilling to assist Dlamini by providing it with the information as
to what work was done by EY
and how much was paid for it.
[28]
Nevertheless, Dlamini wrote on 16 January 2019 to Transnet reminding
it that the tender
was awarded on the basis that it, Dlamini, was a
party to the Consortium, and that despite this being the case, it was
denied the
opportunity to perform the legal work that the Consortium
undertook to be performed by Dlamini. Therefore, it asked Transnet to
provide it with:
‘
3.1
The BEC/BAC Scoring sheets and Adjudication Reports;
3.2 The
Report finalised by EY, including information on deliverables
achieved;
3.3 The
alleged Proof of Payment made to the “Consortium”.’
[29]
Transnet refused to furnish these documents. Dlamini sought
them later by bringing
its application in terms of the provisions of
the Promotion of Administrative Justice Act 3 of 2000 (PAJA), and by
utilising rule
53 of the Uniform Rules of Court. It asked both
Transnet and EY to furnish these documents (the record). Both
Transnet and EY refused
to do so.
The
refusal to furnish the record
[30]
Transnet filed a formal response to the rule 53 notice, wherein it
said:
‘
KINDLY TAKE NOTE
that [Transnet] does not have a record in terms of which a decision
was taken to exclude [Dlamini].’
[31]
EY did not file a formal response to the notice. It dealt with the
issue in a letter its
attorneys sent to Dlamini and in its answering
affidavit. It gave two reasons for its refusal: (i) it did not take
any decision
to exclude Dlamini from participating in the tender and,
(ii) it was a private body, whose actions are not susceptible to
judicial
review, thus relieving it of any legal obligation to furnish
a record. The letter its attorneys wrote states:
‘…
2. In
regard to the
alleged decision
taken by [EY] we are instructed
to record that [EY] did not
“decide”
to exclude
Dlamini from the execution of the Tender. Instead, the need for
Dlamini’s services fell away as a result of the
proper
interpretation of the scope of work.
3. In
addition to the above, and in response to the request for the record
of the
alleged decision
, we are instructed to record that [EY]
actions are not capable of being judicial reviewed; nor has our
client exercised any public
powers that render its actions capable of
being judicial reviewed.
4. In
the circumstances, our client will not produce a record of the
alleged decision
.’ (Underlining added, otherwise quote
is verbatim)
[32]
In the founding affidavit, Dlamini said:
# ‘G.
Record and reasons
‘
G.
Record and reasons
70. In terms
of Rule 53(1)(b) of the Uniform Rules of Court, Transnet and EY are
required to dispatch to the Registrar
of this Honourable Court the
record of their decision to exclude the applicant both from the
execution of the project and from
the economic benefits thereof,
together with such reasons as Transnet and EY are by law required to
give or desire to make.
71. The
record must
include
,
71.1
EY’s complete response to the request for proposal
in terms of
the RFP which it
in fact
submitted to Transnet;
.
71.2
EY’s section 8: B-BBEE Preference Points Claim
Form in respect
of the RFP which it in fact submitted to Transnet;
71.3
Transnet’s BEC and BAC scoring sheets and adjudication
reports;
71.4
The joint venture and/or consortium and/or subcontract
agreement/s
actually
submitted by EY to Transnet in respect of the RFP;
71.5
EY’s complete working plan in its
final
form;
71.6
EY’s report that was finalised including information
on
deliverables achieved particularly in respect of proposals for
changes to applicable Regulatory and Legal frameworks to streamline
the required governance process;
71.7
Proof of payment by Transnet to EY for execution of
the RFP;
72. The
reasons that Transnet and/or EY are required by law to give must
include
:
72.1
What was the initial interpretation of the scope;
72.2
What was the later interpretation;
72.3
How do the two interpretations differ;
72.4
Why does the one interpretation entail exclusion of
legal elements
and the other not;
72.5
Who came up with the idea that closer attention should
be paid to the
interpretation of scope;
72.6
When did EY first realise that their interpretation
was not in line
with Transnet’s needs;
72.7
When did Transnet convey to EY that their interpretation
was not in
line with Transnet’s needs;
72.8
Why was the applicant, whose role was to be directly
affected by the
change of interpretation, not consulted.
73 The
applicant reserves its right to amend the relief sought and
supplement its papers upon receipt of the record
of the decision and
the reasons therefor.’
[33]
The list of questions posed by Dlamini are expressive of the rights
conferred upon it as
well as the legal duty imposed by rule 53 on
Transnet and EY. They, however, do not constitute an exhaustive list
of what the rule
53 record should contain.
[34]
Transnet denied that PAJA applied and that the provisions of rule 53
have any bearing on
the matter. It does not say however that this is
the reason it refused to furnish the record. Instead it filed a
formal response
to the rule 53 notice simply stating that it ‘does
not have a record in terms of which a decision was taken to exclude
Dlamini’.
[35]
EY on the other hand made two claims: (i) it did not take any
decision to exclude Dlamini
from executing the tender and, (ii) it
did not understand itself to be bound by the call for the record as
rule 53 was inappropriately
utilised by Dlamini.
[36]
The first claim is strange. By its own version, EY was the party that
had interpreted the
scope of work initially and based its bid on its
interpretation of the scope. Upon securing the contract it met
with Transnet
and at this very first meeting it realised that its
initial interpretation was erroneous. Apart from its various
discussions with
Transnet which took place between 23 January –
31 January 2018, it had internal discussions where it considered what
to do
given that it was its Infrastructure Team rather than its
Advisory Team that bid for, and was prepared to undertake, the
project.
The conclusion of that discussion was that the Advisory Team
would take over. Once that conclusion was reached, the intended role
for Dlamini fell away. EY must have realised that it was now
undertaking work that was very different from the one it bid for.
And
so, the decision to hand over the contract to the Advisory Team was a
decision to hold on to the contract. Included therein
was a decision
to exclude Dlamini from engaging in the contract. It may well have
been a single decision but it consisted of two
parts: (i) allow the
Advisory Team to perform work that it did not bid for and (ii)
exclude Dlamini from any further engagement
in the work. By taking
this decision, EY lost sight of the fact that
ab initio
it had
always catered for Dlamini’s inclusion in the project. In these
circumstances, for EY to claim that no decision was
taken to exclude
Dlamini is, I hold, not consistent with the facts. It is
important to bear in mind that Dlamini was
seeking a copy of the
record of EY’s meeting with Transnet, the record of its
internal deliberations as well as those reflecting
the internal
deliberations of Transnet. It was legally entitled to all of these
records from both Transnet and from EY.
[37]
As for the
second claim, this is simply incorrect in law. The decision not to
continue with the services of Dlamini may well have
constituted
administrative action as envisaged in PAJA, or it may have been an
exercise of public power.
[1]
Even if it is neither, the decision to exclude Dlamini may be
reviewable in terms of the common law.
[2]
Absent reference to the records it is not possible to reach any
sensible conclusion on whether the reviewable grounds set out in
PAJA
or the common law have been established.
[3]
Mr Maenetje for EY submitted that as it was certainly not an exercise
of public power, it was no more than a refusal by one private
party
to conclude a contract with another private party. He drew attention
to a
dictum
by myself in
Moropa
[4]
where I held that two decisions taken by a private pension fund to
terminate contracts with another private party did not constitute
an
exercise of public power. There is however a difference between that
case and the present one. This case involves a decision
taken by
Transnet to continue with the services of EY - which commenced with
the awarding of a contract following a bidding process
and therefore
may have been an exercise of public power – which decision
impacted on the decision of EY to exclude Dlamini
from the execution
of the contract. It is not possible to conclude with absolute
certainty that the latter decision – that
of EY - was not
an exercise of public power, especially since the first decision –
that of Transnet - may well
have been an exercise of public
power. The two decisions by EY’s own version are inextricably
linked. Therefore, to draw
that conclusion one would have to have
regard to the record.
[38]
Crucially, it is the court having regard to all the facts, including
those revealed by
the record, that will have to make a decision as to
whether PAJA or the common law grounds of review were correctly
relied upon
by Dlamini, and whether it appropriately utilised rule
53. It is legally incorrect for a party – especially one who is
required
by law to avail the record – such as Transnet or EY,
to of its own accord make that decision. No party should usurp the
role
of a court. The correct approach would have been for them to
provide the record without detracting therefrom, or waiving their
rights thereto, and to raise the point that the record is irrelevant
as there is no case in public law for them to answer. That,
at the
very least, is the duty of Transnet, which is an organ of state. It
is also the duty of EY whose conduct was central to
the entire
procurement process. It was involved
ab initio
– by
tendering – until the contract terms were fully implemented and
finalised. And once it became embroiled in litigation
involving the
lawfulness of the contract – from tendering to performance of
the contract – it had to abide the call
made in terms of rule
53 to make available whatever part of the record it possessed. This
is its duty as a law-abiding corporate
citizen. It is required to
assist the court.
[39]
Dlamini had the option to seek an order compelling EY and Transnet to
supply the record.
It would, of course, be an interlocutory
application. Doing so, however, would result in the matter on the
merits being delayed
until the interlocutory application was
finalised. The cost of this – in time and money –
constituted an insurmountable
obstacle for Dlamini. Thus it elected
not to pursue the application. For a small firm of attorneys with
limited resources the election
is reasonable.
[40]
More important is the problem that is posed by the failure of
Transnet and EY to furnish
the record, for it has made it difficult
for Dlamini to accept that its subsequent exclusion was neither
mala-fide
nor capricious, but was a consequence of an innocent
mistake particularly on the part of EY.
[41]
Dlamini expended time and money by participating in the tender and by
attending the first
meeting that took place between Transnet and EY
once the contract was awarded. It had every reason to feel aggrieved
by abruptly
being denied the opportunity to benefit from the
contract. It was told that there was a change in the interpretation
of the scope
by EY. The message it received raised suspicion that it
was used to secure the contract and then abandoned once that
objective
was achieved. Nevertheless, it asked for a confirmation
from Transnet that the scope of the contract had changed and, if so,
whether
there was compliance with Treasury Regulations. Dlamini said
further that upon receipt of such confirmation it would, without
more,
accept the decision that there was no role for it in the
implementation of the contract and would let the matter rest. But
Transnet
responded by saying that there was no change in the scope,
and that it had no role to play in the change of the interpretation
of the contract. Transnet was informed of this difference in the
interpretation by EY and that Dlamini would not be involved anymore.
The record of discussions to this effect are what Dlamini required to
be part of the rule 53 record. It also sought the record
of the
deliberations that led to EY winning the bid. These would reveal to
what extent Dlamini’s status and its intended
involvement in
the contract affected the outcome of the bid. And following
therefrom, it would reveal to what extent its subsequent
exclusion
would constitute a breach of the terms of the tender, and whether it
constituted a violation of the terms or spirit of
the B-BBEE Act.
[42]
The fact that the record may subsequently be found to be irrelevant
is no ground for disentitling
Dlamini of the legal right conferred by
rule 53. It cannot be gainsaid that, had Dlamini been given the
record, (i) its case
in public law may have been established, and/or
(ii) unlawful conduct on the part of Transnet (and possibly even EY)
may have been
exposed, or (iii) it may have come to the conclusion
that it was legitimately excluded from participating in the execution
of the
work that was ultimately performed.
[43]
Thus, the refusal by Transnet and EY to furnish those records is, I
hold, unlawful and
regrettable. It was also prejudicial to Dlamini.
[44]
Simultaneously, Dlamini has a right not to compel them to comply with
the provisions of
rule 53: the provision of rule 53 calling for the
record is there for its benefit. In this case, having elected to
waive the benefit
Dlamini has to accept, which it does, that the
matter can only be determined on the papers before court.
Dlamini’s
case
[45]
On 10 May 2019, Dlamini launched the application in Dlamini 1 wherein
it sought three distinct
forms of relief: (i) a declarator to the
effect that excluding Dlamini from ‘executing’ the
contract awarded to the
Consortium amounted to a fronting practice as
envisaged in the B-BBEE Act; (ii) a declarator to the effect that the
decision of
EY and/or Transnet to exclude it from ‘executing’
the contract is unconstitutional; and, (iii) an order requiring EY
and/or Transnet to jointly and severally pay Dlamini 30% of all
revenue derived from the execution of the contract.
[46]
Dlamini
invokes rights conferred by the Bill of Rights (BoR) chapter of the
Constitution, particularly s 9(2) of the Constitution.
It also sought
succour in s 195 of the Constitution. Transnet as an organ of state
is bound by the BoR.
[5]
Transnet
is also bound by s 195 of the Constitution, specifically ss
195(1)(a), (d), (g) and (i).
[6]
The rational underpinning its case is that its exclusion from the
contract violates the human dignity of the black women professionals
associated with it. It effectively transforms the black women
professionals into ‘mere fodder for the advancement of the
commercial interests of EY’: their conduct constituted an act
of fronting as envisaged in the B-BBEE Act. In essence, Dlamini
contends that its constitutional rights, particularly those set out
in s 9(2) of the Constitution, have been trampled on by Transnet
and
EY ‘with impunity’. This occurred once EY, either
unilaterally or with the collaboration of Transnet, decided to
terminate the participation of Dlamini in the contract. Its right to
participate in a state tender was thwarted by the exclusion;
the
means utilised to come to the decision to exclude it were
non-transparent and therefore in breach of s 195(1)(g) of the
Constitution.
[47]
In its papers Dlamini relied on the provisions of PAJA, and in the
alternative on the principle
of legality, to secure the relief. At
the hearing it asked that the court invoke its power to grant ‘just
and equitable’
relief if its case in public law fails.
EY’s
and Transnet’s response
[48]
On the merits, EY’s case is that it submitted a bid in response
to the RFP, in which
it said that Dlamini would perform that part of
the RFP dealing with legal services. In its understanding, should the
bid be successful,
it would conclude a sub-contract agreement with
Dlamini for Dlamini to provide legal services and be accordingly
compensated. As
‘[t]he legal and regulatory framework that was
originally envisaged in the bid submission was no longer required by
Transnet’
it decided not to include Dlamini in the project. The
decision was a consequence of circumstances outside of its control.
[49]
Transnet, on the other hand, denies that it changed the scope of the
work or that it had
any hand in the removal of Dlamini. After placing
on record that the scope had not changed, that it had remained the
same from
the moment the RFP was issued until the implementation of
the contract was finalised, it went on to say:
‘
What did in fact
transpire is that, in one of the project meetings, it became clear to
EY that it, did not fully understand the
requirements of the project
and as a result, EY needed to rework and adjust its project team.’
[50]
It is clear from this that the position of Transnet and EY are not
ad
idem.
Transnet lays all blame for the exclusion of Dlamini at the
feet of EY. This is a position it adopted throughout its engagement
with Dlamini. When Dlamini sought its intervention it said that the
dispute regarding Dlamini’s exclusion was a matter that
fell
exclusively within the purview of the relationship between Dlamini
and EY. Whether this is correct or not we cannot say, as
we are
denied access to the records. Similarly with EY’s version,
which, as I show below, indirectly lays the blame at the
feet of
Transnet.
[51]
Both Transnet and EY ask that Dlamini be non-suited for delaying the
launching of its application.
Unreasonable
Delay
[52]
Undoubtedly Dlamini could have launched its application a few months
earlier than it did.
From the moment it was informed of the decision
it took some time to exactly formulate its concerns or grievances,
for example,
it took four months to seek clarity on the decision. But
at the same time, Transnet and EY did not always respond timeously to
Dlamini.
[53]
Dlamini’s delay in any event was not of such magnitude as to
justify it being denied
access to court. Such a decision would not
serve the interests of justice. This is particularly so in the light
of the findings
I make hereunder regarding the nature of Dlamini’s
complaint and the role of Transnet and EY both pre and during the
litigation.
Further, it is only part of the relief sought by Dlamini
that attracts a time-bar – the part that is brought in terms of
PAJA and on the grounds of legality. The part that concerns an
allegation of fronting is not confronted with the same restriction.
It will have to be decided- even if it is found that Dlamini
unreasonably delayed the launching of its application. Accordingly,
I
decline the invitation by Transnet and EY to non-suit Dlamini.
Conclusions
on the merits of Dlamini’s case
[54]
The facts do not support the contention that Dlamini, by its
exclusion, was unfairly discriminated
against in contravention of s
9(2) of the Constitution. Nothing before me shows that Dlamini was
excluded because its members were
all black women. The mere fact that
it was excluded and that all its members are black women are in
themselves insufficient to
allow for the conclusion that the
exclusion was because of its racial and gender profile. Dlamini was
excluded because Transnet
chose to get EY to perform work that was
very different from the work EY had bid for. By so doing it cannot be
said the Transnet
and EY acted in direct contravention of s 9(2) of
the Constitution. It is one thing to find that the decision to get EY
to do that
work, and the subsequent decision of EY that there was no
longer a role for Dlamini in the work it secured with Transnet were
nontransparent
and possibly even unlawful. But it is a completely
different thing to find that those decisions were discriminatory. The
facts
simply do not allow for such a finding. A finding to that
effect would constitute a leap in logic.
[55]
As for the
possible breaches of ss 195 and 217 of the Constitution are concerned
these do not constitute a cause of action.
[7]
[56]
Accordingly, Dlamini’s case has to fail on the merits.
Conclusion
on the claim of fronting
[57]
The B-BBEE Act defines ‘Fronting’ as:
‘
a transaction,
arrangement or other act or conduct that directly or indirectly
undermines or frustrates the achievement of the objectives
of this
Act or the implementation of any of the provisions of this Act,
including but not limited to practices in connection with
a B-BBEE
initiative –
a)
in terms of which black persons who
are appointed to an enterprise
are discouraged or inhibited from substantially participating in the
core activities of that enterprise;
b)
in terms of which the economic benefits
received as a result of the
broad-based black economic empowerment status of an enterprise do not
flow to black people in the ratio
specified in the relevant legal
documentation;
c)
involving the conclusion of a legal
relationship with a black person
for the purpose of that enterprise achieving a certain level of
broad-based black economic empowerment
compliance without granting
that black person the economic benefits that would reasonably be
expected to be associated with the
status or position held by that
black person; or
d)
involving the conclusion of an agreement
with another enterprise in
order to achieve or enhance broad-based black economic empowerment
status in circumstances in which-
(i)
there are significant limitations, whether implicit or explicit,
on
the identity of suppliers, service providers, clients or customers;
(ii)
the maintenance of business operations is reasonably considered
to be
improbable, having regard to the resources available;
(iii)
the terms and conditions were not negotiated at arm’s length
and
on a fair and reasonable basis.’
[58]
Both EY and Dlamini hold a level 1 B-BBEE status. Dlamini was
included in the bid not because
of its B-BBEE status but because of
its legal expertise. The work that was performed by EY was
accordingly performed by an entity
that possessed the B-BBEE status
required in the bid documents. As the work was undertaken by an
entity enjoying a level 1 B-BBEE
status it cannot be said that it or
Transnet ‘directly or indirectly undermine[d] or frustrate[d]
the achievement of the
objectives of [the B-BBEE] Act’ or the
implementation of any of the provisions of’ the B-BBEE Act.
Dlamini’s
exclusion from the contract may have been wrongful
but it did not frustrate or undermine the B-BBEE Act.
[59]
Further, the facts show that EY genuinely intended to get Dlamini to
perform some of the
work that it bid for. EY did not use Dlamini’s
name to secure the contract and then dispense with Dlamini once it
secured
the contract. The work that EY performed is not the same that
it bid for. Whether it should have performed this work or not is one
matter, but whether it fronted by performing this work is another. On
the former issue, I have already said that by performing
the work
Transnet and EY may have breached certain statutory prescripts as
well as the procurement policies of Transnet. As for
the latter
issue, EY did not secure this work on the strength of its intention
to sub-contract part of it to Dlamini. As soon as
Transnet got EY to
perform work which involved ‘a greater level of detail than EY
had assumed in its bid submission’
and which excluded ‘a
PSP focus’ as well as ‘an analysis of the 6 projects
listed in clause 2.1(a) of the Scope
of Work contained in the RFP’,
it knew, or ought to have known, that Dlamini’s involvement was
not a pre-requisite
for granting the contract to EY. Hence, it was
not misled into awarding the contract to EY on the basis of an
understanding that
Dlamini was to perform some of the work. In other
words, Dlamini was not used as a front to mislead Transnet into
giving the contract
to EY.
[60]
Accordingly, I find that the allegation that Transnet and EY are
guilty of fronting as
defined in the B-BBEE Act is without merit.
Despite
the conclusion on the merits, was Transnet and EY’s conduct
unlawful?
[61]
Whether
they have infringed the
Public Finance Management Act 1 of 1999
or
any other applicable statute would at this stage remain an open
question. Reference to the record, of course, would settle the
question. That said, the facts as curated by EY
[8]
,
but not disputed by Transnet, clearly indicate that EY bid to
provide a particular set of services (which included those
to be
provided by Dlamini), was willing to withdraw from the project
altogether when it realised that it was mistaken as to what
Transnet
actually sought, but then allowed itself to be persuaded by Transnet
to provide services for which it did not bid.
So radically
different was its interpretation that it had to replace its entire
team. Transnet ‘no longer want[ed] a PSP
focus nor was it
interested in an analysis of the 6 projects listed in clause 2.1(a)
of the Scope of Work contained in the RFP’,
or to put it
differently, ‘[t]he legal and regulatory framework that was
originally envisaged in the bid submission was no
longer required by
Transnet’. Transnet is silent on this allegation. It says that
EY initially misunderstood the scope of
work spelt out in the RFP.
But if that was so then on its own version – which is also EY’s
version – the EY bid
was not suited for the project. According
to EY, it brought this fact to Transnet’s attention when it
offered to withdraw
from the project, but Transnet urged it to find
another team to undertake the work that Transnet wanted performed.
The problem
for both of them is that EY did not bid to perform that
work. The work was suitable for its Advisory Team and not its
Infrastructure
Team. Instead, it got EY to undertake a task that EY
did not bid for, or which its bidding team was ill-equipped to
perform. This
may very well have been unlawful. Put differently,
Transnet may well have been legally obliged to withdraw the award
and, if there
were other bids, re-examine the bids or cancel the
process as a whole and start again. EY, too, may have been legally
obliged not
to be party to Transnet’s decision to not withdraw
the award. In other words, EY may have acted unlawfully by performing
work it did not bid for. In short, Transnet and even EY may
have violated the procurement policies and principles of Transnet,
and they both may have acted contrary to the
Public Finance
Management Act. But
, it is not possible to come to a definitive
conclusion as to whether one or both of them acted unlawfully without
recourse to the
record. It must be remembered that they are
responsible for the absence of the record. That said, it would, I
believe, be
in the public interest that the matter be further
investigated by Transnet and/or EY or by the Public Protector.
[9]
Despite
the conclusion on the merits, should a claim in private law be
considered
[62]
Dlamini specifically eschewed any reliance on the law of contract. It
relied exclusively
on the principles enshrined in public law for its
remedy. It stated that it came to court to vindicate public law
rights and not
enforce a private contract. However, the question of
whether it may have had a case in law of contract on the grounds that
the
conduct of EY contravened public policy and should therefore not
be countenanced by the court was briefly raised at the hearing.
Mr
Ngalwana submitted that if this court were to come to the conclusion
that Dlamini has, on the undisputed facts, made out a case
in
contract then this court, in the exercise of its powers to issue a
just and equitable remedy, should award it all or at least
some of
the relief it asked for, especially the relief in the form of
monetary compensation. The case in contract would be based
on a
contravention of public policy in enforcing or failing to enforce its
agreement with Dlamini. Mr Ngalwana drew attention to
a
dictum
of Froneman J in
Maphango
which reads,
‘
Courts deciding
constitutional matters may, and in some circumstances are obliged to,
make any order that is just and equitable.
These powers are not
confined by the pleadings.’
[10]
[63]
This
dictum
, according to the submission, allows this court to
fashion an appropriate remedy by making an order that is just and
equitable
regardless of whether a party sought such a remedy in its
pleadings or not. In
Maphango
, a landlord of a residential
property attempted to evict tenants in terms of the tenants’
unwillingness to consent to an
increase in the monthly rental. Upon
their failure to agree to a new term in the lease, the landlord,
relying on another term in
the lease agreement, terminated the
leases. Hence, the eviction claim. The tenants challenged the
landlord’s claim to eviction
on a number of grounds, but what
they did not do is rely on a provision in the Rental Housing Act, 50
of 1999 (Rental Act), which
related to unfair practices by landlords
and tenants. Having all the facts before it the Constitutional Court,
per majority, found
that the said provision bore relevance to their
dispute, despite neither party having relied on it. Its reasoning was
expressed
by Cameron J as follows:
‘
As I see it, the
question before us is not whether the Act prohibited the landlord
from terminating the tenants’ leases in
order to secure higher
rents, but whether the termination was capable of constituting an
unfair practice. Whether it was an unfair
practice, and what a just
and fair ruling would be if it was an unfair practice, lies within
the Tribunal’s [a tribunal established
by the Rental Act] power
to decide. If the termination is capable of constituting an unfair
practice, I must consider what order
this court should make.
In my view, neither the
landlord nor the tenant fully appreciated the force of the Act’s
provisions in litigating their dispute.
But it would be wrong for
this Court to take a narrow view of the matter that ignores the
importance and impact of the statute.
That would imply that this
court could allow litigants to ignore legislation that applies to an
agreement between them. Rule of
law considerations militate against
this.’
[11]
[64]
The court did not make any factual findings outside of the averments
made in the papers,
nor did it pronounce on an issue of the public
policy that is engaged by those facts. It looked to the applicable
law, which the
parties failed to recognise, and applied that law to
their dispute. In other words, the factual findings were first made,
the applicable
law was identified and only thereafter was the order
made. The order made was really one of postponing the appeal and
allowing
the tenants to lodge their complaint with the tribunal. The
court made no findings, nor issued any order on the merits of the
dispute.
[65]
Another
case relied upon by Mr Ngalwana is
KZN
Joint Liaison Committee
.
[12]
In that case the applicant, a committee representing an association
of independent schools in KwaZulu-Natal (committee), sought
an order
compelling the first respondent, the MEC, to pay certain monies. Its
claim was founded in a subsidy the MEC promised to
the schools
represented by the committee. The subsidy was recorded in a notice
sent to these schools. In time, and for economic
reasons beyond the
control of the MEC, he was unable to abide by the promise in full;
unexpected budgetary constraints meant that
he was only able to pay
the schools a portion of the subsidy. The committee approached the
court to enforce the promise in full.
It prayed for an order
compelling the MEC to pay the schools all of the subsidy promised.
Its cause of action was a simple one:
the promise constituted a
binding obligation on the MEC and an enforceable right in its
members’ hands. Its entire case was
pivoted on this claim. It
did not rely on, but actually renounced, any remedies available to it
in public law. After losing in
the High Court and the Supreme Court
of Appeal it approached the Constitutional Court. The MEC argued that
the committee misconstrued
its case by relying on the private law of
contract. Its case should have been brought in public law.
[66]
Cameron J
writing for a majority of six judges
[13]
– one of whom Froneman J wrote a separate concurring judgment,
which I deal with below – found that the committee had
failed
to establish that the promise resulted in the formation of a binding
contract between its members and the MEC. However,
says Cameron J, by
issuing the notice the MEC was acting in terms of the government’s
‘
duty under the
Constitution in fulfilling the right to a basic education of learners
at schools that benefit from the subsidy. And
once government
promises a subsidy, the negative rights of those learners – the
right not
to have their right to a basic education impaired – is
implicated.’
[14]
And
so,
‘
[48] Even the
[notice] may not have given rise to an enforceable agreement between
[the committee’s members] and the MEC,
it constituted a
publicly promulgated promise to pay. And, once the due date for
payment of a portion of the subsidy had passed,
this created a legal
obligation unilaterally enforceable at the instance of those who were
intended to benefit from its promise.
This is by no means new to our
law. Before the Constitution, the Appellate Division found ‘nothing
peculiar’ in the
notion that the state can unilaterally make a
promise to pay that becomes enforceable at the instance- of those
intended to benefit
from it. In fact, the Court found it ‘strange
to think that the government’s undertaking in terms of [a]
notice can
be made enforceable only once it has been accepted and
converted into a contract.’’
[15]
[67]
Froneman J, applying the basic principle of our law that a promise,
if seriously made,
is legally enforceable, came to the conclusion
that the facts of the case were such that the committee had
established that the
promise resulted in the MEC voluntarily
committing himself to the obligation. While agreeing with Cameron J
that the matter could
be decided on public law principles, the
learned judge went further to say that the same outcome should be
arrived at by applying
the ordinary law of contract:
‘
I arrive at the
same result even if one goes the route of contract.’
[16]
[68]
On the question of whether the case should be decided on public law
principles or in terms
of the principles enunciated in the law of
contract, Froneman J held that either of the two approaches would be
suitable. The reasoning
is based on a trite principle articulated as
follows:
‘
[79] How important
is the legal label one attaches to a set of facts upon which a party
relies for a remedy under the law? Not decisively
so, I would
suggest, in a matter where the facts are not essentially disputed and
no material prejudice to any party flows from
whatever label is
assigned to them by the formality of the law. This is that kind of
case, but the opposing parties urged us to
attach different labels to
the facts upon which relief was sought, and determine the outcome
according to the label. The invitation
should be resisted –
substance should count, not form.’
[17]
[69]
Cameron J came to the conclusion that in terms of public law if the
state makes a promise
it becomes binding, once it is made. Froneman J
does not quibble with this, but goes further and says on the facts a
binding contract
had arisen after the promise was made. Fundamentally
though, the learned judges reached their conclusions by relying on
the facts
that were pleaded and agreed. They did not stray from those
facts. This is manifest in Froneman J’s reference to the trite
principle that the label used to describe a cause of action is really
irrelevant. It is the facts that are before court that are
most
relevant in determining whether relief ought to be granted to a party
or not. To be precise:
‘
[93] There is thus
nothing in principle that hinders one from enquiring whether the
facts before us may attract the label of being
a contract under our
law. In that enquiry it will be useful to examine whether there is
anything that prevents constructing this
matter as one falling under
the law of contract from both perspectives, the law of contract on
the one hand and administrative
law on the other.’
[18]
[70]
Dlamini’s name reigned prominently in the bid. It was indicated
therein that it would
be performing some of the work should EY secure
the contract. It is also undisputed that there was an agreement
between EY and
Dlamini that upon the awarding of the contract, EY and
Dlamini were to conclude a subcontracting agreement: this is a
classic case
of the parties having a legally binding agreement to
conclude another agreement in due course and once a suspensive
condition –
such as the success of the bid - materialises. The
subcontracting agreement was not concluded because EY decided that it
could
no longer accommodate a role for Dlamini in the work it
undertook. Whether this constituted a failure on the part of EY to
relate
in good faith towards Dlamini is a matter that would have had
to be pleaded and proven. In other words, whether EY’s conduct
exposed it to a claim in contract law is an issue that could only be
resolved when the court is invested with the full facts.
[71]
At the same time, a court cannot, under the pretext of utilising its
powers to make a just
and equitable order, make an order
independently of making factual findings upon which a cause of action
can be identified. Orders
follow therefrom: a court is not empowered
to issue ‘just and equitable’ orders from thin air. It
too is bound by the
rule of law. Put simply, if a cause of action is
absent then the power to grant appropriate relief is non-existent.
[72]
In the present case, I cannot find that EY infringed the public
policy by breaching its
agreement to conclude the subcontracting
agreement with Dlamini. The facts presented in the papers do not
constitute sufficient
material to justify such a finding.
Accordingly, any relief that would have followed such a finding
cannot be granted.
Costs
[73]
Transnet and EY have succeeded in resisting Dlamini’s claim.
But they may not have
done so had they complied with their legal
duties to furnish the full record of what transpired during the
assessment of the bids,
the full record of their joint interactions
after the first meeting of 23 January 2018, and the full record of
their respective
internal discussions after that meeting. Their
failure to comply with their legal duty is a matter of concern and
should not go
unpunished. Had Dlamini been granted access to these
records it may well have elected not to pursue this application. It
was forced
to do so because Transnet and EY were not forthcoming from
the moment it sought clarity, which lack of co-operation continued
unabated
until the case was finalised. Accordingly, I am of the view
that Dlamini should be awarded its costs and that both Transnet and
EY should jointly be liable for these costs. Dlamini asked for
punitive costs. Given (i) Transnet’s and EY’s conduct
in
refusing to furnish the record is unlawful, (ii) the refusal
prejudiced the case of Dlamini and (iii) it frustrated, if not
defeated, the course of justice, I believe a punitive costs order
would be appropriate.
DLAMINI
2
Factual
matrix
[74]
The case in Dlamini 2 as I demonstrate below is (i) fundamentally
different from that in
Dlamini 1 and (ii) turns exclusively on facts
that are in the main common cause. Those facts are revealed in
exchanges of sometimes
lengthy emails between Dlamini, EY and
Covington, Dlamini and EY and Dlamini and Transnet. Given their
central importance to the
determination of the issues in dispute it
is necessary to quote at length from these emails.
[75]
On 14 September 2017 Transnet issued an RFP for the provision of
advisory services to prepare
and conclude a joint development
partnership for the development and operation of natural gas networks
for a period of 36 months.
It was a requirement of the RFP that
whoever seeks to bid for the contract must meet ‘pre-qualification
criteria’
5.1
B-BBEE Joint Ventures or Consortiums
Respondents who would
wish to respond to this RFP as a Joint Venture [JV] or consortium of
B-BBEE entities, must state their intention
to do so in their RFP
submission. Such Respondents must also submit a signed JV or
consortium agreement between the parties clearly
stating the
percentage [%] split of business and the associated responsibilities
of each party. If such a JV or consortium agreement
is unavailable,
the partners must submit confirmation in writing of their intention
to enter into a JV or consortium agreement
should they be awarded
business by Transnet through this RFP process. This written
confirmation must clearly indicate the percentage
[%] split of
business and the responsibilities of each party. In such cases, award
of business will only take place once a signed
copy of a JV or
consortium agreement is submitted to Transnet.
5.2
Subcontracting
As prescribed in terms of
the Preferential Procurement Policy Framework Act (PPPFA), Act 5 of
2000, Preferential Procurement Regulations
2017, it is a
prequalification criteria to participate in this RFP that Respondents
subcontract a minimum of 20% [Twenty percent]
of the total value of
the contract to one or more of the following designated groups:
Ø
QSEs and/or EME’s which are at
least 51% owned by black people and/or black woman owned.
A bid that fails to meet
this pre-qualifying criterion will be regarded as an unacceptable
bid.‘
[76]
On 13 October 2017 the third respondent (Covington) approached
Dlamini on the suggestion
of EY requesting that the two of them
collaborate for purposes of securing the contract. Eventually,
they both teamed up
with EY in a consortium. On 31 October 2017 the
consortium submitted its bid. On 13 July 2018 Dlamini received
confirmation that
the consortium had been awarded the tender. Dlamini
was one of the EME’s that EY was to use as a sub-contractor,
and Covington
was listed as the lead legal advisor. On 19 July
2018 the consortium had its first meeting post the award. On 25
July
2018 EY sent Dlamini a proposed master subcontracting agreement
(MSA). During August and September 2018 Dlamini,
Covington
and EY met a few times to discuss various drafts of the
MSA. On 15 August 2018 Dlamini attended a legal work-stream kick-off
meeting
with Covington. On 22 August 2018 Dlamini sent EY
comments on the proposed First Draft MSA. Thereafter EY and Dlamini
continued
to exchange drafts, with each commenting on the draft
before returning it to the other. In the meantime, Dlamini and
Covington
commenced working on the project.
[77]
In September 2018 the relationship between Covington and Dlamini
began to sour. It commenced
on 20 September 2018 with Dlamini sending
a first draft of the Regulatory Report to Covington. Covington was
not happy with the
draft. It wrote to Dlamini on 25 September 2018
expressing its displeasure. It wrote:
‘
I
t
appears that your lawyers either did not understand the mandate or
did not apply themselves to the task at hand, as large parts
of the
draft Regulatory Report are irrelevant (and unnecessary). Where the
discussion was relevant, in many instances the discussion
does not
incorporate critical analysis of the issues discussed, and
consequently the discussion delivers no or little value to
the
client. The draft also unnecessarily deals with upstream and
downstream elements of the Project when the Project is a "midstream"
storage, regas and pipeline project. There are no upstream and no
downstream elements to the Project. The due diligence should
be
focused exclusively on the midstream. This will cut down on the
excessive amount of repetition in the memorandum.’
[78]
Included in its correspondence was a detailed response to Dlamini’s
draft. Dlamini
took offence at the response. It relayed it sentiments
the next day:
‘
We
understand the mandate and have applied ourselves to the instruction
at hand.
The
fact we are comprehensive in our due diligence is not an indication
of lack of understanding of what is required. We are not
in agreement
with some aspects of your reports and we are not quick to label you
or jump to conclusion on your capability or lack
thereof to deliver
the mandate. I find it strange that at this point you think we do not
understand the mandate when we presented
our approach to your firm
and provided you with the presentation on and to date had no comments
from your firm. I don't know if
this is how treat your partners on
joint mandates but your approach on resolving this is tasteless and
totally flawed.’ (Quote
is verbatim)
[79]
Covington wrote back the same day, stating that its response to the
draft was intended
to serve as ‘constructive criticism’.
It further made clear that it was ‘the lead law firm’ on
the project:
‘
I
am sorry that you have chosen to take offence to this, rather than to
look at what is actually requested in our scope of work
and to try to
take constructive criticism for what it is. I am not sure exactly
what approach you would have us take — your
deliverable was
late in getting to us, we had very little time to review, and we sent
our initial comments to you alone and asked
for a private
conversation about the way forward.
While
it is clear that significant effort has gone into your part of the
draft report and the primary legislative acts have been
identified,
we were brought into this project (you will recall that Deon and I
approached you about joining us) because of our
extensive experience
on LNG and gas pipeline projects and regulation, and I can tell you
with certainty that the legal and regulatory
review as it currently
stands needs significant work. I am afraid that on this particular
project we are the lead law firm and
need to put our name behind the
entire legal workstream, so we are going to have to be happy with the
work product.’
[80]
On the same day Dlamini responded:
‘
It
is incorrect to create the impression that our report was
unreasonably late. Both parties agreed to exchange reports on the
17
th
of September. When we realised we could not meet the deadline, we had
the courtesy to call your office to request an extension
and Kgabo
from your office informed us that you were also experiencing the same
challenges. We then agreed to provide our report
on the 19
th
and then you still had not
provided us with your draft report. On the 20
th
you still had not provided us with
your report when we sent ours by midday. We only received your report
on the evening of the 20
th
.
We need to put to rest the notion that our report was late, your
report was late as well.
Please
do not patronise us regarding our efforts and capabilities. We have
reviewed your work and can say the same thing regarding
your work
which I have sensitised Deon on. Your report has missed the point in
that you are attempting to pre-empting option and
comment on
“options” before the technical and finance work streams
have provided their options analysis report. The
inception report
clearly sets out when this legal input is required from the legal
work stream. So the report we have received
from your firm needs
significant work to comply with the requirements of the phase 1
deliverables. For instance there is a section
in your report where
the interpretation of section 56 of the National Ports Act is
incorrect.
As
much as you are capable we are more than capable to do the work on
our own. You were sent to us by EY to partner with us based
on the
work we had done on this project previously, the Solar PV IPP we
undertook with EY and generally similar projects we have
undertaken
in the energy space on our own. We were never consulted on you
leading
us. Our discussions with you was always on collaboration on this
project. To this you find yourself as a lead and want to
abuse your
position, we refuse to be abused and lead in this fashion. We are
more than capable to undertake this mandate on our
own.
If
you want to lead this stream we expect you to do so with integrity.’
(Quote is verbatim)
[81]
Covington responded that evening:
‘
I'm
not sure why you are taking this attitude, but it is not helpful. I
am going to respond to your specific statements below, but
after this
I really refuse to engage in a further email exchange. If you have an
issue you want to discuss, I am happy to get on
the phone.
Our
report was ready over two weeks ago, but we explicitly agreed with
you in our meeting at our offices on 13 September that we
would not
send it to you until we'd seen your report, since your report covered
the critical legislation and was the larger report.
That is why it
was not sent to you, which you seem to have forgotten. You did indeed
kindly inform us that you would be late in
delivering the draft, but
that does not derogate from the fact that it was delivered later to
us than agreed, which gave us less
time for review and interaction
with you. That is why I mentioned this, nothing more.
We
will check on the point you mentioned in our report; please send us
your comments and we can discuss. We are happy to receive
constructive comments on any of our drafting, particularly in areas
such as the Port Act where you have more experience. That is
why we
are cross-checking each other’s work. That is why we provided
you with the NDA for your comment. That being said,
I do not agree
that stating options cannot be a part of legal analysis per se,
particularly where we have relevant experience from
prior
regas/pipeline projects on what the most likely structures will look
like. We will look forward to your comments.
Finally
I want to be very clear that EY did not "send us to you";
we didn't tell EY we were even talking to you until
after we had
finished interviewing candidate firms and finalised our selection. As
we are the lead law firm on the project EY considers
Dlamini to be
our subcontractor and was not involved in the process of selecting a
local law firm. Deon and I knew who you were
already and we decided
to include Dlamini in the firms we spoke with.
We
were brought into this project by EY because we have extensive
international experience on LNG and gas pipeline projects. We
also
have over 15 years of experience working with EY on large-scale
African energy and infrastructure projects, and they know
that we can
do the job (and that they can get along with us). Your firm does not
have our level of experience on this specific
type of project, but
has other skills and experience that we do not have. Ergo, I think we
are a good team. If you choose to view
those facts as being
patronising, then that is your interpretation, but I do not see why
you think this has to be some sort of
competition.
I
have checked with Kgabo and she inadvertently inserted the Covington
logo in the draft sent to you; as I mentioned it was not
in the draft
I approved for distribution. My apologies again, our inhouse forms
all include the logo and our associates are trained
from Day 1 to
insert it in our drafts. She is aware of the issue and any joint work
product will not have logos etc. in them going
forward.
If
you want to continue this conversation, let me know a time and number
I can reach you.’ (Quote is verbatim)
[82]
The exchange of this correspondence must be read together with the
comments on the draft
prepared by Dlamini. These comments reflect a
significantly different approach and understanding of the project,
the applicable
law and the role played by each of them. The exchange
resulted in so much acrimony between the two that their working
relationship
deteriorated to the point where it compromised the
quality of the service provided to Transnet.
[83]
On 2 October 2018 Dlamini approached Transnet. It sent the draft
Regulatory Report to Transnet
and informed Transnet that once it has
commented thereupon, a final Report will be drafted and presented to
EY. Transnet,
it seems, did not respond to Dlamini, nor did it
comment on the draft Report.
[84]
On 8 October 2018 Dlamini wrote to Transnet requesting a meeting with
Transnet to address:
(i) its (Dlamini’s) subcontracting
arrangement with EY and Covington; (ii) the agreed work allocation
between Covington and
itself; (iii) its request that Transnet
intervene where it and Covington have diverging views on the legal
matters; and, (iii)
the relationship between itself and Covington,
which it characterised as an ‘abusive’ one. It also
recorded that it
would want to address its concerns that EY was not
able to attend to its issues objectively.
[85]
Transnet hosted a meeting between itself, Dlamini, Covington and EY
on 15 October 2018.
Transnet made it clear at that meeting that
whatever subcontracting arrangements Dlamini, Covington and EY
entered into was a matter
for themselves. Dlamini said that it would
be subcontracting directly with EY as per the bid document of the
consortium. Transnet
informed the meeting that Covington would have
the final say on any legal issues where it and Dlamini disagreed, and
lastly that
it would only intervene in any dispute between Covington
and Dlamini if Covington conducted itself in a manner that would be
unprofessional
or unethical.
[86]
On 17 October 2018 Transnet sought Covington’s views on the
draft Regulatory Report
sent to it by Dlamini on 2 October 2018. It
also informed Dlamini that in future Dlamini should not send any
reports directly to
it, unless that report was signed-off by
Covington.
[87]
On 18 October 2018 Transnet wrote, per email, to EY stating that it
is guided by, and relies
upon, the vertical structure outlined in the
EY bid response in which Covington was identified as Lead Advisor
with Dlamini being
subcontracted by, and providing support to,
Covington. Transnet does not want to be involved in the disputes
between Covington
and Dlamini. It said:
‘…
as both
Dlamini and Covington are contracted to EY and not Transnet, we
propose the EY attend to meet both Parties and outline what
their
respective responsibilities are in line with the Bid Response.
Further we do not think that it is appropriate for your
sub-contractors
to be sending us the type of emails [those sent by
Dlamini referred to above] and if there are issues in relation to
this project,
EY and its subcontractors should have proper channels
on how to address such matters without involving Transnet.’
(Quote
is verbatim)
[88]
Aggrieved by Transnet’s response, Dlamini informed Transnet
that it ‘felt oppressed’.
[89]
On 29 October 2018, a fourth draft of the MSA was circulated but no
agreement reached,
and soon after EY produced a new draft (the fifth
draft) and sent it to Dlamini.
[90]
The disagreement between Dlamini and Covington did not abate post the
15 October 2018 meeting
hosted by Transnet and the email penned by
Transnet on 18 October 2018. The disagreement manifested itself in
the work that was
completed by Dlamini and Covington. Dlamini would
issue a report, provide an opinion or comment on the possible legal
consequences
of any actions or steps that Transnet may adopt, and
Covington would make changes to these, which Dlamini was not able to
agree
to.
[91]
Further negotiations on the MSA continued during November 2018. The
negotiations were tough
and challenging for both Dlamini and EY. A
key obstacle to concluding the MSA was the strained relationship
between Covington and
Dlamini. Central to this strained relationship
was one individual from each side – Ms Dlamini the lead partner
of Dlamini
and Mr Govender from Covington. Both of them were central
to each party’s contribution to the project. There was some
mention
during these discussions that one or both of the two
individuals should step aside for the sake of the project as a whole.
This
suggestion aside, the parties remained in deadlock.
[92]
Dlamini wrote to Transnet on 7 November 2018 stating:
‘
We write this
e-mail fearing that you may respond in a way that willand further
embarrass us and erode whatever small role and participation
we still
have in this project. However, since the last time you wrote the two
e-mails below, we have continued to work with Covington
as you have
directed at our meeting of 15 October 2018 (i.e. Covington
having
the last word on any disagreement we may have on legal principles)
but the fact that Covington has the last word on deliverables
where
we have agreed Dlamini Attorneys will take the lead hampers the
quality of every deliverable to the extent that it is almost
impossible for us to have an opinion or say on any work produced by
the legal work stream. We now have to prepare a presentation
on the
two deliverables under your consideration and we
do
not agree with certain conclusions reached in the deliverables which
were circulated to you, in particular on the second deliverable.
We
are now faced with a dilemma of having to present on work product
that we are not 100% in agreement with on fundamental legal
principles.
We draw your attention to
the fact that the failure to schedule regular legal work stream
meetings is impacting on our ability to
meaningfully participate in
this project since we have to be content with whatever Covington's
last word is on deliverables where
we have agreed Dlamini Attorneys
will take the lead. We were hoping that the legal work stream meeting
would allow for fair discussions
on legal issues and to the extent
that we are not in agreement with Covington, you as Client
representative can fairly rule on
legal issues which we are not in
agreement. To continue working under what we have complained about
before and after your directive
of 18 October 2018 makes it
impossible to have meaningful participation in this project. We are
now left with a watching brief
mandate in this project and three
years is a very long time to hold on to a watching brief.
Kindly confirm your
availability for the legal work stream meeting in the hope that we
can reach agreement on some of these fundamental
legal principles.’
(Quote is verbatim)
[93]
Transnet responded to Dlamini on 13 November 2018. It
reiterated what it had said
on 18 October 2018: that it was EY which
had responded to the bid, and that Covington was the lead legal
advisor, and that it should
not be drawn into any dispute between the
subcontracting partners of EY, or even between EY and any of its
subcontracting partners.
It advised Dlamini not to correspond with it
on any of these issues, but to rather raise them with EY.
[94]
In the meantime, the discussions regarding the MSA continued. By this
stage the sixth draft
was in circulation. Dlamini responded thereto
on 15 November 2018 indicating that it was not satisfied with certain
aspects and
suggested some changes. On 21 November 2018 Dlamini wrote
to EY complaining about being undermined and disrespected. It wrote:
‘
As
you may be aware, we previously raised our concerns around the
hostility we have encountered at the hands of our colleagues,
Covington. Since the submission of the legal team's first report we
have been overruled by Covington on a number of matters, but
more
importantly on legal matters where Dlamini Attorneys and Covington
have diverging views. On such occasion, we approached Sipho
Risiba of
Transnet Legal requesting his intervention and ruling on such legal
matters, but instead of confirming the resolutions
reached at our
meetings, he issued the directive that Covington (as lead of the
legal team) has the last word on all legal matters,
as well as the
directive on the 18th of October (attached for ease of reference)
which contradicts the collaborative arrangements
between the two law
firms.
Furthermore,
we are continuously and deliberately excluded from pivotal
correspondence with members on this project such as the
stakeholder
engagement team, the technical team and yesterday Sipho, which issue
we have raised with Covington on a weekly basis
but to no avail (we
attach correspondence to this effect).
Although
we have been forced to abide by Sipho's directives and acknowledge
Covington's role as lead of the legal team, Covington's
conduct and
Sipho's directives continuously erode the collaborative arrangements
in place. This has resulted in Covington reaching
certain legal
conclusions which we do not agree with and such conclusions relate to
matters that have a fundamental impact on the
project as a whole.’
(Quote is verbatim)
[95]
A seventh
draft was sent by EY to Dlamini on 29 November 2018.
[19]
On the same day EY wrote to Transnet seeking consent to replace
Dlamini as a subcontractor. Its letter reads:
‘
EY
was awarded the tender for the Project and would act as prime
contractor to Transnet and the other parties would act as
subcontractors
to EY. EY subsequently went about putting in place
subcontractor agreements with the various subcontractors involved in
the Project,
including Dlamini. The vast majority of the
subcontractor agreements are in place and the remaining subcontractor
agreements being
finalised. This is, unfortunately not the case with
the subcontract with Dlamini. Despite EY's best efforts Dlamini are
proving
to be quite challenging in negotiating the subcontractor
agreement. As you are aware they have approached Transnet, in
contradiction
of Transnet's wishes with complaints about Covingtons
and Burling ("Covingtons") and EY. EY requested Dlamini to
engage
with EY only in relation to subcontracting matters, which
Dlamini has not done. Covington are international experts in the
field
of oil and gas transactions and working together with Dlamini
have reported a sub-standard of work from Dlamini as well as
"bullying"
tactics used by Dlamini, this has resulted in
Covington "walking on eggshells" around Dlamini in order to
accommodate
demands from them. This is wasting time and effort which
we can ill afford. As the Project is set to take place over a period
of
three years, EY as the prime contractor, has a duty towards
Transnet that all our subcontractors work well together in a
collegial
and professional fashion. This assists EY in ensuring a
high level of quality in the work we present to Transnet and the
current
situation may detract from that intent, which we are not
prepared to accept. EY has just received a marked-up draft (one of
many)
from Dlamini. We are attempting to meet them in the middle but
it is becoming increasingly apparent that Dlamini are not willing
to
compromise on their position. This makes it near impossible to
contract with them and even if such contracting is possible,
we are
concerned about the longevity and efficacy of the relationship due to
their behavior throughout this process, especially
their behavior
towards Transnet - our end Client.
Consequently,
we wish to inform Transnet that we may be forced to replace Dlamini
with another empowered law firm who matches Transnet's
criteria,
should you have any objection to this step we request you to provide
your urgent response to this letter, if we receive
no reply from you
by 3 November 2018 we will assume you are in agreement. Apologies to
burden you once more with matters relating
to sub-contractors.’
(Quote is verbatim)
[96]
The next day, 30 November 2018, EY received a response from two
employees of Transnet saying
that they would not object ‘provided
that the law firm’ which replaces Dlamini has ‘the same
B-BBEE’ credentials
as Dlamini. The response was confirmed by
two more senior employees of Transnet. On 4 December 2018
Dlamini rejected the
seventh draft.
[97]
An eighth draft was sent to Dlamini on 10 December 2018. On 11
December 2018 EY informed
Dlamini that if it did not accept this
particular draft it would remove Dlamini from the project. Dlamini
responded that it would
accept the fifth draft and that its main
partner, Ms Dlamini, would step aside and the person from Covington
who was actively involved
in the project - Mr Govender - should
also be asked to withdraw from the process so that the two firms
could co-operate more
effectively. On 12 December 2018 EY informed
Dlamini that the eighth draft was the only one on the table, and
similarly the withdrawal
of Mr Govender was not negotiable. Dlamini
refused to accept the draft indicating that it was being coerced by
EY to accept terms
that were not acceptable to itself. It refused to
sign the draft and EY refused to change it. On 14 December 2018
Dlamini was removed
from the project.
[98]
On 15 January 2019 EY confirmed that it had removed Dlamini from the
project, but gave
Dlamini an opportunity to reconsider its position
on accepting the eighth draft without any amendments from Dlamini.
The email
in this regard reads:
‘
Further
to my mail on 14 December 2018 please note that we have not accepted
any of your counter-proposals and we confirm that your
mandate has
been withdrawn in accordance with my email of 11 December 2018, due
to your non-acceptance of our terms.
Nonetheless,
in the event you wish to work with us again on the project, we look
forward to receiving a signed copy of the agreement
(attached) by
close of business tomorrow 16 January 2019 along with an email
confirming agreement to the terms of my email of 11
December 2019,
falling which we will deem our offer to be finally rejected.’
[99]
Dlamini refused to accept this draft. It replied to EY placing
certain facts on record:
‘
We
refer to our e-mail of 12 December 2018 from Ayanda, our e-mail below
and your e-mail of yesterday which does not address the
concerns
raised below.
As
you are aware, we have deliverables due end of March in terms of the
project timelines and we note that we have not been copied
on any
communication since 13 December 2018. Please confirm If you have
unilaterally removed Dlamini Attorneys from the project
making it
impossible for us to perform.
Further,
please confirm, as per your e-mail from yesterday, you intend to
remove us from the project if we refuse to sign under
duress your
version of a master subcontractor agreement which contains provisions
that the parties had not reached consensus on,
namely:
1.
to accept the insertion of clause 15
(Independence), which relates to the professional independence
requirements EY must comply
with in relation to its audit clients.
This provision requires Dlamini Attorneys to assist EY with complying
with these requirements
by not only disclosing to EY that its
directorships or shareholdings of 5% or more in any entity on an
on-going basis; but should
EY determine in its sole discretion that
there are professional independence concerns, then Dlamini Attorneys
agrees to resign
from a
position,
decline an offer, relinquish its shares in such entity. Notable the
provisions of clause 15 apply to any director, officer
or trustee of
Dlamini Attorneys and/or Dlamini Attorneys' directors, trustees,
executive officers, shareholders holding 5% or more,
subsidiaries,
associated entities or parent company. EY is not contracted with
Dlamini as its auditors, so we do not understand
why we must agree to
such a provision. Furthermore, this clause didn't appear in any of
the previous iterations of the master subcontractor
agreement. If it
was of such importance why is it only being incorporated so late in
the negotiation. The rationale provided by
EY on 29 November 2018 for
this provision’s sudden insertion as a regulatory requirement
in terms of section 90 of the Companies
Act, does not align with the
requirements set out in section 90 of the Companies Act. Section 90
of the Companies Act merely sets
out the requirements to appoint an
auditor. The obligations here are quite onerous and unreasonable in
the circumstances;
2.
to accept the insertion of Schedule 5
(Framework for Legal Teams' Collaboration) which contain provisions
that are unjustifiably
onerous, unreasonable and oppressive. Dlamini
Attorneys agreed working arrangements with Covington before and after
the award of
the Project. To disregard such collaborative
arrangements and attempt to contract for and on behalf of parties
with such oppressive
terms is
unreasonable.
It is not clear to us why such terms and conditions with the level of
detail would be required on a mandate where
each work-stream has a
client approved fixed budget (irrespective of Individual charge out
rates) and payment is based on reaching
client approved milestones
and deliverables are necessary. It is clear that this schedule has
been drafted taking into account
comments from Covington and
Transnet, but none of ours.
We
note that EY expects Dlamini Attorneys to accept the abovementioned
terms by close of business today to secure our continued
participation on this project. However, we find it disappointing that
EY expects us to sign an agreement under duress and in total
disregard of our request for a meeting with EY, the concerns raised
through the project and those raised on our e-mail dated 12
December
2018. In light of the above, should EY insist on removing Dlamini
Attorneys from this mandate, please could you provide
us with
official confirmation of our removal from this project.’ (Quote
is verbatim)
[100]
On 17 January 2019 EY sent Dlamini written confirmation of its
decision to remove Dlamini from the project.
Dlamini was replaced by
another firm, Shandu Attorneys (Shandu), which enjoys the same B-BBEE
status as Dlamini. Transnet was informed
in advance of Shandu being
appointed as the replacement for Dlamini. It had no difficulty with
the decision and endorsed it.
The
relief sought
[101]
Dlamini asks this court to: (i) declare its removal from the project
by EY acting unilaterally and/or in
concert with Transnet to be
‘unlawful as it is not founded on any law, contract or other
prescript.’; (ii) declare
that the removal of Dlamini is not
rationally related to Dlamini’s obligations in terms of the
tender; (iii) declare that
the removal of Dlamini is unconstitutional
and unlawful because it undermines the objectives of the B-BBEE Act;
(iv) declare that
the failure of Transnet to intervene and prevent
Dlamini’s removal to be unconstitutional as it abdicated its
responsibility
to ensure compliance with the B-BBEE Act; (v) review
and set aside EY’s decision to remove Dlamini from the project;
(vi)
review and set aside Transnet’s ‘failure to
intervene and stop’ Dlamini’s removal from the project;
and,
(vii) order EY to pay Dlamini an amount of R10 777 612,02
(Ten million Seven Hundred Seventy-Seven Thousand Six Hundred and
Twelve Rand and two cents).
[102]
Dlamini also claims that both EY and Transnet, by removing it
from the project, have made themselves
guilty of committing the
offence of fronting as set out in the B-BBEE Act.
[103]
As with Dlamini 1, Dlamini’s case in Dlamini 2 is founded in
public law. It asks this court to find
that its exclusion and/or
removal from enjoying the benefits of the contracts to be unlawful
and unconstitutional; violates the
human dignity of black women
professionals associated with it, and effectively transforms the
black women professionals into being
‘mere fodder for the
advancement of the commercial interests of EY.’ It is also
unconstitutional for undermining the
achievement of the objectives of
the B-BBEE Act.
[104]
As with Dlamini 1 Dlamini relied on the provisions of PAJA in its
quest to review and set aside the decision
of Transnet to remove it
from the contract, or to fail to intervene with EY in order to
prevent the removal. Again, the application
was brought in terms of
rule 53. In Dlamini 2 though Transnet and EY furnished an incomplete
record.
[105]
Dlamini had expertise in natural gas contracts. It claims that it is
for that reason it was included in
the bid, and absent its inclusion,
EY would not have succeeded in its bid.
EY’s
case
[106]
EY claims that it had a Level 1 B-BBEE status at the time it bid for
the contract. It further denied that
it secured the contract on the
strength of Dlamini’s name or involvement in the bid. Thus, the
indication in the bid documents
that Dlamini would be performing some
of the legal work did neither strengthen nor weaken the chances of
the bid succeeding. Covington
was always the main subcontractor for
legal work. However, it concedes that by including Dlamini it was
able to satisfy the pre-qualification
requirement that 20% of the
contract should be sub-contracted to exempted micro-enterprises
(EMEs) or qualifying small-business
enterprises (QSEs) that are more
than 51% black-owned. EY’s intention was to award 12% of the
sub-contracted share of the
contract to Dlamini. The contract
involved providing a complex set of services – part of which
was legal advisory services
- which EY could not provide on its own.
At the same time, it was the party that bid for the contract and that
concluded a contract
with Transnet. It had to engage various service
providers, and had to co-ordinate the work done by each of the
service providers
in order to fulfil its obligations in terms of the
contract. The legal advisory services could not be provided by one
firm only.
However, it had agreed to grant Covington lead legal
advisor status and this was revealed to all the parties, including
Dlamini.
Covington, according to EY, ‘is one of the most
experienced and knowledgeable group of lawyers in the gas market
globally.’
From the moment the bid was placed, Transnet was
informed of this and it agreed thereto. Having succeeded with the bid
EY concluded
an agreement with Transnet – the EY Transnet
Services Agreement – which regulated the relationship between
EY and Transnet.
The agreement allowed for EY to employ
sub-contractors who may perform any obligation that befalls EY. The
contract between EY
and the subcontractor did not involve Transnet.
While the agreement allowed EY to engage subcontractors, it provided
that the performance
by the sub-contractors would be regarded as
performance by EY. EY, not Transnet, would issue instructions to the
subcontractors.
Any problems with performance by the subcontractor,
such as inadequate or non-performance, would be regarded as
inadequate or non-performance
by EY. And so, Transnet would look to
EY and not the subcontractor for its remedies. In the words of the
contract, the subcontractors
would be treated as ‘employees’
of EY and EY would ‘remain liable for any acts of omissions and
Defaults of the’
subcontractor or the personnel of the
subcontractor. The agreement goes further to say that Transnet
would have no claim
against the subcontractor at all. As a result,
claims EY, it is imperative that EY have the utmost faith and trust
in the subcontractors
it appoints. It is with this in mind that it
attempted to conclude an agreement – the MSA - with Dlamini.
Dlamini would be
providing services to EY and not Transnet. EY, not
Transnet, would have to compensate Dlamini. Dlamini simply refused to
accept
this as the basis of the MSA. Put differently, Dlamini did not
want to be restricted to dealing with EY, it wanted to be free to
deal with Transnet. This, it says, is manifest in the fact that it
wrote directly to Transnet on more than one occasion and complained
about the treatment it received at the hands of EY and particularly
Covington.
[107]
It had replaced Dlamini with Shandu, and as Shandu enjoys the same
B-BBEE credentials as Dlamini any suggestion
that it is guilty of
fronting is without merit. However, should this court find that
its actions fall foul of the fronting
provisions of the B-BBEE Act,
it calls for an order declaring the specific sections of the said Act
which defines fronting and
which criminalises it to be
unconstitutional. The order is only sought if it is found that EY’s
conduct amounts to fronting.
Transnet’s
case
[108]
Transnet’s case is that EY and another entity, Mott McDonald
(Pty) Ltd, submitted a joint bid in response
to its RFP. EY was
identified as the main party. From inception EY informed it that it
would be subcontracting with Covington and
Dlamini to provide the
legal services should it be awarded the contract, but that Covington
would be the lead firm with regard
to providing legal advisory
services. In that sense Covington was distinguished from other
subcontractors. Its QSE and SME credentials
were part of the
consideration in the assessment of the bid. Dlamini was identified as
one of the EME supporting firms that EY
would engage along with other
entities such as Covington, but it did not enjoy the same status as
Covington. The RFP required that
a minimum of 25% of the contract
should be subcontracted to other parties. In the bid EY indicated
that it would subcontract 42%
of the contract. When the
disagreements between Covington and Dlamini surfaced, Dlamini sought
Transnet’s intervention
and when the response it received did
not suit it it turned against Transnet. Transnet understood the
request of Dlamini to be
a call for adjudicative intervention and it
had neither the ‘legal duty’ nor the ‘capacity’
to undertake
this.
[109]
Further, EY was informed on many occasions that the contracts it
concluded with subcontractors were a matter
for itself and the
subcontractors. It, not the subcontractors, was obligated to furnish
the services for which it would be compensated.
This message was
conveyed to Dlamini on more than one occasion. Dlamini’s issue
is solely an issue for Dlamini and EY. When
asked by EY for
authorisation to replace Dlamini with Shandu it duly granted the
request. As the two entities are identical in
terms of their BEE
status the allegation of fronting is ill-founded. Similarly with the
allegation that the objects of the B-BBEE
Act were compromised or
undermined.
No
case in public law
[110]
In contrast to Dlamini 1, in Dlamini 2, (i) there was no allegation
of a change in interpretation of the
scope of work identified in the
RFP and the bid, (ii) there was no change in the work that EY
performed, (iii) there was a substantial
amount of negotiations
between EY and Dlamini regarding the role and function Dlamini would
play in the execution of the contract,
(iv) Dlamini was always aware
as to why it was removed from the execution of the contract, and (v)
the facts as set out in the
correspondence quoted above are the only
ones relevant for the determination of the merits of Dlamini’s
application.
[111]
The problem that Dlamini encountered and which gave rise to this
litigation was a breakdown of the negotiations
concerning the
conclusion of the MSA. The fundamental reason for the breakdown was
the unwillingness of Dlamini to accept a role
subordinate to that of
Covington. There were numerous attempts to address all of its
concerns save for its subordinate role. This
was a red line for it
and for EY. But Dlamini was in no position to dictate to EY what EY -
as the successful bidder and the party
that bore the full risk of
legal action should any of its subcontracting partners fail to
perform any of the obligations EY undertook
vis a vis
Transnet
- should do. It must accept that its refusal to agree to any one of
the eight drafts of the MSA was a major, if not sole,
contributing
factor for its removal. There is no attack on the bidding process, or
on the awarding of the contract to EY.
[112]
There is
therefore no case in public law. This is a case of two private
parties failing to conclude a contract. Here, unlike
in Dlamini 1 the
dictum
in
Moropa
[20]
is apposite. No case in private law has been pleaded, and in any
event a case in private law cannot be founded on these facts.
Failure
to provide a complete record
[113]
I am not unmindful of the fact that in Dlamini 2 both Transnet
and EY failed to file a complete record
in terms of the rule 53
notice. There is however no need for a record in this matter as the
bid and any communication between Transnet
and EY that is relevant
for the determination of the dispute was revealed to Dlamini before
the litigation commenced and during
the litigation. The failure to
file a record certainly did not defeat the course of justice.
Fronting
[114]
Dlamini was replaced by Shandu. Like Dlamini, Shandu is an
exclusively black women partnership of legal
professionals. It enjoys
a Level 1 B-BBEE status. EY was fully transparent with it and with
Transnet as to the problems it faced
and the solution it intended to
apply, which was to replace Dlamini with Shandu. Hence, for this and
for the same reasons set out
in Dlamini 1, there is no basis for the
allegation that by replacing Dlamini with Shandu EY engaged in the
unlawful conduct of
fronting. Dlamini’s claim to this effect
is, to repeat what is said in Dlamini 1, without merit.
Constitutionality
of the B-BBEE Act
[115]
As there has been no ‘fronting’ the conditional
counter-application of EY falls away. Nothing
more need be said about
it, save to record that the Minister who was the only party that
opposed it did not seek any costs.
Conclusion
[116]
For the reasons set out above, the application stands to be
dismissed.
Costs
[117]
Dlamini has failed in its application. The events in Dlamini 1 and in
Dlamini 2 occurred around the same
time. There can be little doubt
that Dlamini was hurting from its experience in Dlamini 1, and this
understandably would have influenced
its decision to embark on the
litigation in Dlamini 2. In the circumstances I hold that it would
serve the interests of justice
if all parties were to bear their own
costs.
[118]
All that remain is for me to thank the legal representatives for
their assistance in this matter.
[119]
Orders
In
case number: 16593/19
1
The application is dismissed.
2
The first and second respondents are to pay the costs of the
application
including the costs of two counsel to be taxed on an
attorney and client scale.
In
case number: 23785/19
1
The application is dismissed.
2
There is no order as to costs.
Vally
J
Dates
of hearing:
14-15 March 2022
Date
of Judgment:
2 June 2022
In
matter number 16593 (Dlamini 1)
For
the applicant: V
Ngalwana SC with F Karachi
Instructed
by: Dlamini
Inc
For
the first respondent: N
Maenetje SC
with Kerry Williams
Instructed
by:
Webber
Wentzel
For the Second
respondent: M
Motsoeneng (Director), V Khathide (PA) and R
Mphosi (Candidate Legal
Practitioner)
From:
Motsoeneng
Bill Attorneys
In
matter number 23785 (Dlamini 2)
For
the applicant: V
Ngalwana SC with F Karachi
Instructed
by: Dlamini
Inc
For
the first respondent: N
Maenetje SC with Kerry
Williams
Instructed
by:
Webber
Wentzel
For the second
respondent: M Motsoeneng
(Director), V Khathide (PA) and R Mphosi (Candidate
Legal
Practitioner)
From:
Motsoeneng
Bill Attorneys
For
the fourth respondent: G
Marcus SC with M Salukazana
Instructed
by:
State
Attorney
[1]
Trustees
for the time being v BAE Estates
2022 (1) SA 424
(SCA) at [18] – [25];
Airports
Company SA v ISO Leisure OR Tambo
2011 (4) SA 642
GSJ at [43] – [62]
[2]
Id at [41] – [50]
[3]
Dlamini did not bring its case in terms of the common law. However,
it is possible that the court may
find
that common law grounds of review may be applicable. Of course, such
a finding could only be made on the proven facts and
without
prejudice to Transnet and EY.
[4]
Moropa
v CINPF
2021 (1) SA 499
(GJ) at [46]
[5]
Subsections 8(1) and 8(2) of the Constitution provides:
‘
(1)
The Bill of Rights applies to all law, and binds the legislature,
the executive, the judiciary and
all organs of state.
(2)
A provision of the Bill of Rights binds a natural or a juristic
person if, and to
the extent that, it is applicable, taking into
account the nature of the right and the nature of any duty imposed
by the right.’
(3)
[6]
These subsections read:
195. Basic values and
principles governing public administration.-
(1)
Public administration must be governed by the democratic values and
principles enshrined
in the Constitution, including the following
principles:
(a)
A high standard of professional ethics must be promoted and
maintained.
…
(d)
Services must be provided impartially, fairly, equitably and without
bias.
…
(g)
Transparency must be fostered by providing the public with timely,
accessible and accurate
information.
…
(i)
Public administration must be broadly representative of the South
African
people, with employment and personnel management practices
based on ability, objectivity, fairness, and the need to redress the
imbalances of the past to achieve broad representation.’
[7]
Britannia
Beach Estate (Pty) Ltd and Others v Saldanha Bay Municipality
2013 (11) BCLR 1217
(CC);
[2013] ZACC 30
at
[16]
– [17]. See
further the cases cited therein
[8]
See [5] – [15] above
[9]
See
s 6
of the
Public
Protector Act 23 of 1994
[10]
Maphango
v Aengus Lifestyle Properties
2012 (3) SA 531
(CC) at [153]
[11]
Id at [47] - [48]
[12]
KZN
Joint Liaison Committee v MEC for Education
2013 (4) SA 262 (CC)
[13]
The minority consisted of four judges
[14]
KZN
Joint Liaison Committee
,
n 4 at [45]
[15]
Id at [48]
[16]
Id at [108]
[17]
Id at [79]
[18]
Id at [93]
[19]
EY claims that this is the eighth draft. Whether it is the seventh
or eighth draft is of no moment for the conclusion I reach
in the
matter.
[20]
See [37] and n4 above
sino noindex
make_database footer start
Similar Cases
Dlamini v The Road Accident Fund (21375/2019) [2022] ZAGPJHC 657; [2022] 4 All SA 360 (GJ) (7 September 2022)
[2022] ZAGPJHC 657High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Dlamini v Van Den Bos N.O.: In re: Van Den Bos v Dlamini and Others (32507/2021) [2022] ZAGPJHC 673 (12 September 2022)
[2022] ZAGPJHC 673High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Dlamini obo Sifundo v Road Accident Fund (2021/24199) [2023] ZAGPJHC 472 (12 May 2023)
[2023] ZAGPJHC 472High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Dlamini and Others v Minister of Police (50725/2021) [2024] ZAGPJHC 953 (26 June 2024)
[2024] ZAGPJHC 953High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Dlamini v Imbokodv Lemabalabala Holdings Limited (2022/051081) [2024] ZAGPJHC 647 (16 July 2024)
[2024] ZAGPJHC 647High Court of South Africa (Gauteng Division, Johannesburg)100% similar