Case Law[2025] ZAGPPHC 280South Africa
Clinix Health Group (Pty) Ltd v Peirre Badenhorst Engineers Inc and Another (2023-085773) [2025] ZAGPPHC 280 (14 March 2025)
High Court of South Africa (Gauteng Division, Pretoria)
14 March 2025
Headnotes
of invoices submitted to date to CHG.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2025
>>
[2025] ZAGPPHC 280
|
Noteup
|
LawCite
sino index
## Clinix Health Group (Pty) Ltd v Peirre Badenhorst Engineers Inc and Another (2023-085773) [2025] ZAGPPHC 280 (14 March 2025)
Clinix Health Group (Pty) Ltd v Peirre Badenhorst Engineers Inc and Another (2023-085773) [2025] ZAGPPHC 280 (14 March 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2025_280.html
sino date 14 March 2025
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
REPUBLIC
OF SOUTH AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
CASE NO: 2023-085773
1.
REPORTABLE:
YES
/ NO
2.
OF INTEREST TO OTHER JUDGES:
YES
/NO
3.
REVISED:
YES
/ NO
DATE:
14 March 2025
SIGNATURE
OF JUDGE:
In the matter between:
CLINIX HEALTH GROUP
(PTY) LTD
Applicant
and
PEIRRE
BADENHORST ENGINEERS INC
1
st
Respondent
TOM
MCDONALD N.O
2
nd
Respondent
JUDGMENT
MEADEN AJ
On
08 NOVEMBER 2024 upon hearing counsel for the parties and considering
the papers, I handed down the following Order:
[1]
“
The application is dimissed with costs at scale C.”
The
above Order was handed down, taking consideration of the
undermentioned:
[1]
This is an
application entailing the review and setting aside of an arbitration
award made by the 2
nd
respondent in his capacity as arbitrator on 19 July 2023. This
arbitration award is annexed as “Annexure FA01” to the
Applicant’s Founding Affidavit.
[1]
[2]
In this review application, the applicant contends that the 2
nd
respondent misconducted himself in re his duties as arbitrator, in
the process exceeding his powers and committing a gross procedural
irregularity. This is alleged in circumstances where the 2
nd
respondent, according to the applicant, decided the dispute arising
between the applicant and the 1
st
respondent (“the
parties”) and on the basis of a case that was not pleaded,
presented, nor argued before the 2
nd
respondent.
[3]
In these circumstances, the applicant seeks to have the above
arbitration award set aside in terms of section 33(1) of the
Arbitration
Act 42 of 1965 (‘the
Arbitration Act&rdquo
;). The
salient portion of
section 33(1)
references:
“
33.
Setting aside of award
(1) Where-
(a) any member of an
arbitration tribunal has misconducted himself in relation to his
duties as arbitrator or
umpire; or
(b) an arbitration
tribunal has committed any gross irregularity in the conduct of the
arbitration proceedings
or has exceeded its
powers; or
(c) …
the court may, on the
application of any party to the reference after due notice to the
other party or parties, make an order setting
the award aside.”
[4]
Presented with the above High Court
application, the 2
nd
respondent did not take issue with nor oppose this application,
preferring to abide the outcome of this application including the
above order handed down.
[5]
In contextualizing the factual
circumstances of this matter:
5.1
The applicant and 1
st
respondent entered into PROCSA Client/Consultant Professional
Services Agreements for:
5.1.1
CIVIL
ENGINEER
[2]
(Edition 4.0 October
2017), (applicable work – full civil engineering services for
the new hospital and external works for
Clinix Health Group on Erf
1[...], P[...] G[...] Ext 12); and
5.1.2
STRUCTURAL
ENGINEER
[3]
(Edition
4.0 October 2017), (applicable work – full structural
engineering works for the new hospital and external works for
Clinix
Health Group on Erf 1[...], P[...] G[...] Ext 12).
5.2
The effective dates of the above
professional service agreements were 05 March 2018 vis-à-vis
the proposed Dr Nthato Motlana
Memorial Hospital – Protea Glen
- Site identification and address: Erf 1[...], P[...] G[...] Ext 12
(“the project”).
5.3
Per the above PROCSA professional service
agreements, the contracting parties on the above project were:
5.3.1
Client
– Clinix Health Group (CHG) (applicant)
[4]
;
5.3.2
Consultant – Pierre Badenhorst
Engineers Inc (1
st
respondent).
5.4
The
appointed Principal Agent cited in the above agreements was VSB
Quantity Surveryors CC (VSB). This entity was also cited as
a
consultant, being the appointed Quantity Surveyor to the above
project.
[5]
5.5
These agreements also cited
additional consultants, which over and above the aforesaid applicant
and 1
st
respondent, constituted the Planning and Design Coordinaton
Team employed by the applicant and which was further supplemented
from time to time with additional consultants where needed and as
effect was given and progress made on the rollout of the project
and
applicable works.
5.6
In
actually giving effect to the above project and over the period 06
March 2018 – 29 October 2019; a series of minuted Planning
and
Design Coordination Meetings involving the participation of the
Client, Principal Agent, Architect and various professional
consultants (including that of the 1
st
respondent) took place. These Planning and Design Coordination
minutes were incorporated in the court bundle
[6]
,
and were compiled by the above Principal Agent – VSB.
5.7
In essence, the above Planning and Design
Coordination meetings contended with issues arising on a daily/weekly
basis in giving
effect to the rollout of the project and related
works. These Planning and Design minutes contextualized the
circumstances at hand
and being contended with by the applicant in
conjunction with the principal agent and consultants in re the
project. Further reference
will be made to applicable minutes of the
Planning and Design Coordination Meetings in the unfolding
circumstances of the matter
contended with below.
[6]
The PROCSA style agreements concluded as
between the applicant and 1
st
respondent comprised the undermentioned stages:
6.1
Stage
1: Inception;
[7]
6.2
Stage
2: Concept and Viability;
[8]
6.3
Stage
3: Design Development;
[9]
6.4
Stage
4: Documentation and Procurement;
[10]
6.5
Stage
5: Construction;
[11]
and
6.6
Stage
6: Close Out
[12]
.
[7]
At the Planning and Coordination Design
meeting held on 21 May 2019 (meeting no. 21) it was specifically
minuted by the principal
agent that:
“
3.2
APPOINTMENTS
3.2.1
PROCSA documents to be revised. CHG will meet with each consultant
individually. Consultant
services to
terminate after stage 4.”
[13]
[8]
This
was reiterated in the ensuing Planning Meeting no. 22 held on 20
August 2019 and again at item 3.2.1 of these minutes.
[14]
[9]
Then in Planning Meeting no. 23 held on 29
October 2019 and per the minutes contained therein, under “CLIENT
MATTERS”
the following was recorded:
“
2.3
CHG will pay outstanding invoices submitted to date from PIC
funding. Invoice details do not have to change – changes
with
regards to VAT numbers, etc will only be implemented after first
payments are done.
2.4 VSB to send
updated summary of invoices submitted to date to CHG.
2.5
Fees for work done by all consultants to date to be updated –
VSB will contact each team member to finalize.”
[15]
[10]
The above directions emanating from the
applicant as minuted in the above Planning & Design Coordination
Meeting No. 21 –
23, were circulated by the principal agent in
the space of six months with the various consultants and in the
course of the aforesaid
Planning and Design Coordination meetings.
These directions entailed a material and substantial deviation from
that set out per
the above defined stages of the PROCSA agreements
and with the applicant terminating works and services of the various
consultants
(including the 1
st
respondent) upon the completion of stage 4 of the PROCSA agreements.
[11]
This
was further summarized in the arbitrator’s award
[16]
and where the arbitrator recorded inter alia; that the above minutes
revealed:
11.1
The applicant’s commitment to pay its
professional consultants up to the termination of stage 4;
11.2
the principal agent being directed to
update the total fees due to the various professional consultants,
and
11.3
the professional consultants to invoice the
applicant hereon and the applicant then to pay such invoices out of
PIC funding.
[12]
This came about in circumstances where upon
regard being had to the various construction tenders being received
and considering
the lowest bid tabled by Tri-Star Construction; this
tenderer proposed the conclusion of an Engineering Procument and
Construction
(EPC) style contract and which then found favour with
the applicant and would supersede the previously concluded PROCSA
style agreements.
[13]
With
this, the various consultants were then to be paid by the applicant
on all updated invoices submitted and again per the above
minutes of
29 October 2019. The various consultants’ fees invoiced for
works to the conclusion of stage 4 were to be updated
by the
principal agent and in consultation with the consultants. Here, the
applicant mandated the principal agent to establish
and determine the
updated fees of the consultants arising vis-à-vis their
respective PROCSA agreements. This culminated
in the principal agent,
just short of a year later, providing the applicant with a “DR
NMM HOSPITAL: PROFESSIONAL FEE SUMMARY”
[17]
dated 08 September 2020.
[14]
In these circumstances, the 1
st
respondent then based its claim on the above updated “DR NMM
HOSPITAL: PROFESSIONAL FEE SUMMARY” compiled by the principal
agent and which arrived at the undermentioned total:
14.1
Structural engineering R 2 213
888.79 (excl. vat);
14.2
Civil engineering
R 1 539 049.73
(excl. vat);
14.3
Subtotal (excl. vat)
R
3 852 938.52
(excl. vat);
14.4
Vat
R 577 940.78
14.5
Total
R 4 430 879.30
(vat incl.)
[15]
The 1st respondent then compiled and
presented to the applicant, tax invoice 3074 in the sum of R 4
430 879.30 (vat incl.)
and in so doing, accepted the principal
agent’s above professional fee summary relating to the 1st
respondent. The principal
agent in proceeding as above, abided the
directions of the applicant and as minuted in the above Planning and
Design Coordination
meetings and which culminated in the production,
inter alia, of the aforesaid professional fee summary and ensuing
invoice from
the 1
st
respondent.
[16]
It is further noteworthy here that the
principal agent was also the applicant’s appointed quantity
surveyor on the project
and enjoyed comprehensive insights on the
scope and extent of the works and costings attributed thereto.
[17]
It
is useful here to contextualize the role of the principal agent. In
Aveng
Grinaker v MEC Department of Human Settlements
[18]
it
was confirmed that the principal agent represents the client/employer
in the capacity of a key independent professional role
player. The
principal agent’s role contributes to the strengths or
weaknesses of the entire building project and the principal
agent
manages the services of all consultants during the project
implementation, ensuring that the best interests of the
client/employer
are served. The principal agent here issues
instructions on behalf of and binds the client/employer. The
authority of the principal
agent in confirming payment obligations
due by the client/employer in favour of independent professional
consultants and further
in authorizing payment and binding the
client/employer hereto is not in dispute.
[18]
Per
the definition of principal agent in the above PROCSA agreements
[19]
,
a principal agent is described as the entity named in the schedule,
appointed and authorized by the client as agent to manage
and
administer the contracts. In compiling and presenting the above DR
NMM HOSPITAL: PROFESSIONAL FEE SUMMARY, the principal agent
abided
the directions of the applicant in updating the professional fee
summary and then binding the applicant hereto. This was
confirmed by
the 2
nd
respondent in his above arbitration award and I concur with this
conclusion of the 2
nd
respondent.
[20]
[19]
In being presented with the 1
st
respondent’s above invoice and taking account of interim
payments already made in aggregate of R 3 429 923.57 in favour of
the
1
st
respondent for services rendered, the applicant in turn refused to
effect payment of the balance then outstanding (per the professional
fee summary presented by the principal agent and quantity surveyor
and invoiced on by the 1
st
respondent to the applicant) or to compromise hereon and effect
payment in favour of the 1
st
respondent.
[20]
Instead, the applicant sought to sideline
its principal agent and quantity surveyor and proceeded in engaging
with third parties,
including Glenro Commercial & Construction
Consultants (Pty) Ltd and of which there is no record of prior
involvement in the
above project and in attempting to assess the
scope and extent of the works of the 1
st
respondent.
[21]
This then culminated in a dispute arising
between the applicant and 1
st
respondent and in these circumstances, the 1
st
respondent on 25 October 2021 engaged with the Association of
Arbitrators (Southern Africa) (‘the Association”)
regarding
the appointment of an arbitrator to contend with:
“
Dispute
in terms of PROCSA Agreement clause 13.0, 13.1., 13.3. Non-payment of
invoices. Clinix disputes amount to be paid, not paying
invoices in
full, not disputing the invoice to clause 13.3. Also not in agreement
with the fee structure as set out in contract.”
[22]
Ultimately, this dispute became the subject
of arbitration proceedings convened before the 2nd respondent –
Tom McDonald N.O
and who was then presented and contended with the
above factual matrix.
[23]
In the course and scope of the conduct of
these arbitration proceedings, the applicant engaged independent
experts - Messrs Zimba
and Wickham and the 1
st
respondent in turn engaged Mr. Von Geusau. In so doing, further
disputes arose as between these experts.
[24]
The
2
nd
respondent concluded that Wickham, Zimba and Geusau all provided
somewhat different evaluations of the percentage works undertaken
and
completed by the 1
st
respondent.
[21]
In
understanding and appreciating the above factual matrix; the 2
nd
respondent inter alia had regard to the principal agent’s
minutes no. 21 – 23 and ensuing professional fee summary
and
related documentation. The principal agent was intimately involved in
the project and had the 2
nd
respondent not so done, then he may have placed himself at risk of
being accused of being remiss.
[25]
According
to the applicant, the 1
st
respondent required to prove how much work was completed by it and
with that, the associated entitlements to fair value for services
rendered in relation to such work.
[22]
Per the applicant, the 2
nd
respondent required to determine how much of the work had been
completed by the 1
st
respondent and consequently, what was the fair value payable by the
applicant to the 1
st
respondent for the services rendered in accordance with the PROSCA
agreements.
[26]
In this context, the applicant attempted
and for purposes of this review application to limit the ambit of the
inquiry of the 2
nd
respondent to that of considering the evidence of the various experts
for purposes of determining the percentages of works completed
by the
1
st
respondent in the various stages of the services referenced in the
civil and structural engineering PROCSA agreements. This is
then
entrenched by the applicant and in it averring that the 2
nd
respondent exceeded his power qua arbitrator, misconducted himself in
relation to his duties and committed a gross irregularity
by:
26.1
“
Determining
that the Parties amended the Agreements as set out in the minutes of
the Planning and Design Coordination Meetings No
21, No 22 and No 23
(hereinafter referred to as the “Amended Agreement Issue”)
notwithstanding that this element did
not form part of either Party’s
pleaded case, with neither party leading evidence or providing
argument in relation to the
amendment to the Agreements, as found by
the 2
nd
respondent
[23]
;
26.2
determining
that VSB was in a better position to determine the value of the
services as rendered by the 1
st
respondent when this was not the case before the 2
nd
respondent and;
[24]
26.3
breaching
the provisions of Article 18 of the rules which provide: ‘Subject
to these Rules, the arbitral tribunal may conduct
the arbitration in
such manner as it considers appropriate, provided that the parties
are treated with equality and that at an
appropriate stage of the
proceedings each party is given reasonable opportunity in presenting
its case. The arbitral tribunal,
in exercising its discretion shall
conduct the proceedings so as to avoid unnecessary delay and expense
and to provide a fair and
efficient process for resolving the
parties’ dispute’
”
[25]
.
[27]
The
aforesaid stands to be reconciled against the actual dispute declared
by the 1
st
respondent and referred to ad paragraph 21
[26]
above. Clearly in this regard, the dispute was not limited and as
framed and set out in paragraph 26 above.
[28]
In
this context, the 1
st
respondent contended that part of the documents received in evidence
during the arbitration were the various minutes of the Planning
and
Design Coordination Meetings (incorporating minutes No. 21 –
23) and which minutes were attached to the 1
st
respondent’s statement of case. Flowing herefrom was the
production of the principal agent’s professional fee summary
of
8 September 2020
[27]
and which
the 1
st
respondent accepted and relied on in presenting its tax invoice of 9
October 2020
[28]
to the
applicant. There is no commercial and legal basis upon which the
applicant can inhibit the 2
nd
respondent having regard to the above factual matrix in the course of
the arbitration at hand.
[29]
The arbitrator, in giving consideration to
the above factual circumstances, would have realized that consequent
upon Planning and
Design Coordination Meetings No. 21 – 23; the
above PROCSA agreements were inter alia; to be summarily terminated
upon the
completion of stage 4, thus resulting in a variation of the
contracting parties’ rights and obligations under the PROCSA
agreements and including the consultants performing up to completion
of stage 4 of the works and with that then being remunerated
therefor.
[30]
Presented with the above dispute, the 2
nd
respondent adopted a logical and practical approach in reviewing and
being appreciative of the above factual matrix and in the
process
realizing that the PROCSA agreements were being prematurely
terminated upon completion of stage 4 and with that followed
the
compilation and production of the principal agent’s updated
professional fee summary. This very fee summary had in turn
been
relied upon by the 1
st
respondent in invoicing the applicant as above. This then included
the 2
nd
respondent taking consideration of the existence and participation of
the principal agent that was also the project’s appointed
quantity surveyor. The principal agent was indeed in the best
position to compile the updated fee summary and was directed so to
do
by the applicant and bound the applicant accordingly in so doing.
[31]
The circumstances as framed in Planning and
Design Coordination meetings No. 21 – 23 above brought about a
change of direction
in the project, including in re the envisaged
termination of the PROCSA agreements and upon the various consultants
achieving completion
of stage 4.
[32]
Further given the existence of a principal
agent, in understanding the scope, extent and circumstances of the
rollout of the PROCSA
agreements; it was prudent for the 2
nd
respondent to take cognizance of, inter alia, the Planning and Design
Coordination meeting minutes and specifically meetings No.
21 –
23 and with that the principal agent’s updated fee summary. The
principal agent here enjoyed a hands on and current
insight on the
scope and extent of the works of the various consultants and
including that of the 1
st
respondent and further had been instructed by the applicant to value
and update the various professional consultants’ accounts
as at
the completion of stage 4 of the PROCSA agreements. The principal
agent did this, thus culminating in its production of its
revised
professional fee summary of 08 September 2020 and which was then
relied upon by the 1
st
respondent and in its ensuing production of its tax invoice 3074
dated 9 October 2020, duly addressed to the applicant.
[33]
It is indeed doubtful here and certainly no
insights have been provided by any of the litigants regarding Glenro
Commercial &
Construction (Pty) Ltd together with any of the
independent experts introduced by the applicant and 1
st
respondent enjoying any superior knowledge and insights compared with
that of the principal agent/project quantity surveyor. Further,
had
the 2
nd
respondent not given consideration to the insights of the appointed
principal agent/quantity surveyor on the project as above,
then
undoubtedly; there would have been room to criticize the 2
nd
respondent for being remiss and actually negligent in not so doing.
[34]
Much is made here by the applicant of the
2
nd
respondent committing a gross irregularity in concluding that
consequent on Planning and Design Coordination Meetings No 21- 23
as
above, an amendment of the PROCSA agreement occurred. There is no
substance to these allegations on the part of the applicant.
The 2
nd
respondent certainly could not ignore the above summarized factual
matrix in establishing the scope and extent of the works undertaken
by the 1
st
respondent for stages 1 – 4 and then in attributing value
thereto. Further, I can see no impediment in the 2
nd
respondent placing reliance on the advices and conclusions of the
principal agent/project quantity surveyor.
[35]
What is indeed noteworthy here, is that the
applicant in opposing the 1
st
respondent’s claim, did not reference formally taking issue
with the underlying principal agent’s professional fee
summary
of 08 September 2020 that was duly accepted by the 1
st
respondent and which in turn was premised on the insights of the
project’s quantity surveyor. I am not aware of any impediment
arising in the applicant so doing. Had there been a genuine issue
here, then and in giving effect to the criteria of the above
PROCSA
agreements, the applicant should have placed in contest the above
professional fee summary presented by the principal agent
and
quantity surveyor and raised issue with these very entities. There is
no substantive reference in this application to this
ever occurring.
In the absence of such disputes, refusing to pay on the principal
agent’s above requested updated professional
fee summary, aside
from being disingenuous; left the applicant financially accountable
in favour of the 1
st
respondent and as confirmed in the 2
nd
respondent’s above award. This review application in its own
right is very narrow and contrived, disregarding the reality
of the
above factual matrix and serves only to aggrevate the already tenuous
position of the applicant vis-à-vis the 1
st
respondent.
[36]
Accordingly, I conclude that the applicant
has not made out a case regarding the 2
nd
respondent misconducting himself in relation to his duties as
arbitrator and in the process exceeding his powers and committing
a
gross procedural irregularity in the conduct of the above arbitration
proceedings culminating in the 2
nd
respondent’s award of 19 July 2023. This award remains of full
effect and may at the 1
st
respondent’s instance and request be made an order of court.
[37]
In the circumstances I conclude that there
are no valid and sustainable grounds upon which to review and set
aside the arbitration
award as published by the 2
nd
respondent on 19 July 2023.
ORDER
Accordingly.
I made the undermentioned order:
[1] “
The
application is dimissed with costs at scale C.”
MEADEN
JR
ACTING
JUDGE OF THE HIGH COURT
This
Judgment was handed down electronically by circulation to the
parties’ and or parties’ representatives by email
and by
being uploaded to CaseLines. The date and time for the hand down is
deemed to be 13h00
on this 14
th
day of March 2025.
Appearances
For Applicant:
Adv. A Glendinning
Instructed by:
Neil Du Toit Inc.
For 1
st
Respondent:
Adv. TJ Jooste
Instructed by:
VFV Attorneys
Date
of Hearing:
08
November 2024
Date
of Judgment:
14
March 2025
[1]
FA
01-46 – 01-85.
[2]
Annexure
FA02/01-86 – 01-115.
[3]
Annexure
FA03/01-116 – 01-144.
[4]
Annexure
FA02/01-98 – 01-99.
[5]
Annexure
FA02/01-99 – 01-100; FA03/01-129 – 1-01-130.
[6]
04-1100
– 04-1248.
[7]
Applicant’s
FA, 01-12 at para 23.1.
[8]
Applicant’s
FA, 01-12 at para 23.2.
[9]
Applicant’s
FA, 01-12 – 01-13 at para 23.3.
[10]
Applicant’s
FA, 01-13 at para 23.4.
[11]
Applicant’s
FA, 01-13 – 01-14 at para 23.5.
[12]
Applicant’s
FA, 01-14 at para 23.6.
[13]
Minutes of Planning and Design Coordination Meeting 21-
04-1266.
[14]
Minutes of Planning and Design Coordination Meeting 22- 04-1273.
[15]
Minutes of Planning and Design Coordination Meeting 23 - 04-1280.
[16]
Annexure
FA01/ 01-102 at para 101.
[17]
Annexure
SOC 14 – 04-286.
[18]
(EL459/15) [2018] ZAECELLC 3;
[2018] 3 All SA 466
(ECLD, East
London) (5 June 2018).
[19]
Annexure
FA02/01-90
at 1.1.15 and FA03 – 01-120 at 1.1.15.
[20]
Annexure
FA01/01-102 at para 102.
[21]
Annexure
FAO1/ 01-81 at para 193-194.
[22]
Applicant’s
Replying Affidavit/ 01-270 at para 25.1.
[23]
Applicant’s Heads of Argument/06-38 at para 76.1. .
[24]
Applicant’s Heads of Argument/06-39 at para 76.2.
[25]
Applicant’s Heads of Argument/06-39 at para 76.3.
[26]
“Dispute in terms of PROCSA Agreement clause 13.0, 13.1.,
13.3. Non-payment of invoices. Clinix disputes amount to be paid,
not paying invoices in full, not disputing the invoice to clause
13.3. Also not in agreement with the fee structure as set out
in
contract.”
[27]
Annexure
SOC
14.
[28]
Annexure
SOC
15.
sino noindex
make_database footer start
Similar Cases
Board of Healthcare Funders of Southern Africa NPC v President of the Republic of South Africa and Another (2024/058172 ; 24/111209) [2025] ZAGPPHC 429; 2025 (5) SA 395 (GP) (6 May 2025)
[2025] ZAGPPHC 429High Court of South Africa (Gauteng Division, Pretoria)98% similar
Board of Healthcare Funders NPC v Council for Medical Schemes and Others (Leave to Appeal) (012058/2022) [2025] ZAGPPHC 609 (24 June 2025)
[2025] ZAGPPHC 609High Court of South Africa (Gauteng Division, Pretoria)98% similar
Medical Information Technology South Africa (Pty) Ltd and Another v Public Protector and Others (29760/2020) [2023] ZAGPPHC 50 (31 January 2023)
[2023] ZAGPPHC 50High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Medical Association N.P.C v South African Medical Association Trade Union and Others (13788/22) [2024] ZAGPPHC 580 (27 June 2024)
[2024] ZAGPPHC 580High Court of South Africa (Gauteng Division, Pretoria)98% similar
Medihelp Medical Scheme v De Wet and Others (2022-010668) [2025] ZAGPPHC 1353 (17 December 2025)
[2025] ZAGPPHC 1353High Court of South Africa (Gauteng Division, Pretoria)98% similar