Case Law[2024] ZAGPPHC 273South Africa
Chapman Fund Manager (Pty) Ltd v Minister of Public Works and Another (25558/2021) [2024] ZAGPPHC 273 (26 March 2024)
Headnotes
it would render the action irrelevant and it stood to be dismissed.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 273
|
Noteup
|
LawCite
sino index
## Chapman Fund Manager (Pty) Ltd v Minister of Public Works and Another (25558/2021) [2024] ZAGPPHC 273 (26 March 2024)
Chapman Fund Manager (Pty) Ltd v Minister of Public Works and Another (25558/2021) [2024] ZAGPPHC 273 (26 March 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_273.html
sino date 26 March 2024
SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
CASE NO.: 25558/2021
(1) REPORTABLE: YES/NO
(2) OF INTEREST TO OTHER
JUDGES: YES/NO
(3) REVISED.
26/03/2024
In the matter between:
CHAPMAN FUND MANAGER
(PTY) LTD
Plaintiff
and
MINISTER OF PUBLIC
WORKS
First defendant
DIRECTOR-GENERAL OF
PUBLIC WORKS
Second defendant
JUDGMENT
van
der Westhuizen, J
[1]
The plaintiff issued summons against the defendants for payment of
monies due and
owing under a contract between the parties. The said
contract followed upon the grant of a tender to the plaintiff. The
defendants
defended the action.
[2]
The contract entered into upon the successful award of the tender
provided for an
extension of that contract for a further period on
the same terms and conditions of the initial contract. It was
contemplated in
the relevant clause that the option of extending the
contract was for the defendants’ prerogative. It was common
cause that
the contract was extended for a further period, but for
the defendants’ plea that such extension was unlawful. The
non-payment
of invoices flowed from the extended contract.
[3]
The essence of the contract was for the supply of services and
equipment to property
occupied by the first defendant for energy
saving in respect of electricity used by the first defendant and for
which it was liable
to pay. The sole financial burden of rendering
the service, management thereof and installation of energy saving
devices fell upon
the plaintiff. In return, the first defendant would
pay 50% of the savings achieved through the plaintiff’s
interventions,
to the plaintiff. Where there were no savings, no
payment befell the plaintiff.
[4]
The case was allocated to me for case management and eventually a
trial date was set
for the period 4 March 2024 to 22 March 2024.
[5]
When the matter was called on 4 March 2024, the plaintiff commenced
leading oral evidence
in respect of invoices submitted to the
defendants that were allegedly not paid by the defendants. The
evidence of the witness,
a Mr Johan Gouws, was not completed on 4
March 2024 and continued on the following day. On the third day,
although the first witness’
evidence was yet to be completed,
the plaintiff indicated that it would interrupt the evidence in chief
of the first witness and
would lead the evidence of a second witness
instead. Apparently, the second witness, a Mr M Dlamini, was an
erstwhile employee
of the defendants and his availability was
limited. Counsel for the defendants did not object to the procedure
suggested by the
plaintiff.
[6]
The evidence of the second witness would relate to the alleged
extension of the contract
entered into following on the award of the
tender to the plaintiff. During the cross-examination of Mr Dlamini,
the defendants
raised the issue of alleged illegality of the extended
contract. On behalf of the defendants it was argued that at all times
the
issue of alleged illegality of the extension of the contract was
in issue as it was pled in the defendants’ plea. The plea
in
respect of the alleged illegality of the extension of the contract
referred to alleged non-compliance with section 217 of the
Constitution. No special plea in that regard was filed. Nor was it
raised as a point to be considered in a stated case. There simply
was
no compliance with the provisions relating to the raising of a
constitutional point. Should the plea of illegality be upheld,
it
would render the action irrelevant and it stood to be dismissed.
[7]
In view of the fact that adjudicating upon that plea of illegality
only after all
evidence was heard, would severally impact on the
waste of court resources, court time and have a severe impact upon
costs unnecessarily
incurred should the plea of illegality eventually
be upheld. After a debate on that point, the parties agreed that in
terms of
the provisions of Rule 33(4) of the Uniform Rules of Court a
separation should be ordered on the limited issue of alleged
illegality.
I so ruled.
[8]
After the conclusion of the cross-examination and re-examination of
Mr Dlamini, the
matter stood down to enable the defendants to consult
with their possible witness in reply to the evidence of Mr Dlamini.
The defendants
called a Mr M Rakau and a Mr M Legotlo, both employed
by the defendants. After the leading of their evidence, the parties
requested
time to prepare and file heads of argument on the limited
separated issue of alleged illegality and to present oral argument in
addition. It was so ruled. Oral argument, in addition to the heads of
argument, was received on Thursday, 14 March 2024. The parties
accepted that insufficient reserved court time was available after a
ruling on the limited separated issue of alleged illegality
for the
action to be completed. I indicated that I would attempt to deliver
judgment on the limited separated issue during the
last week of the
reserved dates for the action. Accordingly, judgment on the limited
separated issue was reserved.
[9]
This is the judgment on the limited separated issue.
[10]
The plaintiff bore the onus of proving an extended contract, whilst
the defendants bore the onus
on the alleged non-compliance with the
provisions of section 217 of the Constitution in respect of the
alleged issue of illegality.
[11]
The evidence of Mr Dlamini sought to prove the plaintiff’s case
that a valid extension
of the contract entered into following on the
successful award of the tender to the plaintiff existed. The
plaintiff submitted
that it had discharged its onus of proving a
contract on that evidence. That led the defendants to prove
non-compliance with the
provisions of section 217 of the
Constitution,
i.e.
the issue of illegality.
[12]
The defendants initially admitted that there was a lawful extension
of the contract. However,
in an amended plea it denied that such
extension was unlawful and further did not comply with the provisions
of section 217 of
the Constitution. The non-compliance related to the
alleged breach of the requirement in subsection 217(1) of the
Constitution,
namely, “
contacts for goods or services, it
must do so in accordance with a system which is fair, equitable,
transparent, competitive and
cost-effective.”
[13]
Section 217 of the Constitution provides as follows:
“
(1)
When an organ of state in the national, provincial or local sphere of
government, or any other
institution identified national legislation,
contacts for goods or services, it must do so in accordance with a
system which
is fair, equitable, transparent, competitive and
cost-effective.
(2)
Subsection (1) does not prevent the organs of state or institutions
referred to in that
subsection from implementing a procurement policy
providing for –
(a)
Categories of preference in
the allocation of contracts: and
(b)
The protection or advancement of
persons or categories of persons, disadvantaged by unfair
discrimination.
(3)
National legislation must prescribe a framework within which the
policy referred to in subsection
(2) must be implemented.”
[14]
The framework referred to in subsection (3) of section 217 of the
Constitution was regulated
in terms of
inter alia
the Public
Finance Management Act, 1999 (the PFMA). It prescribed the calling
for tenders in certain circumstances as provided
for in the Schedules
and Regulations under the PMFA. That is common cause.
[15]
The defendants contended that for purposes of this enquiry, it
necessitates a determination whether
there has been a breach in
respect of the requirement “
in accordance with a system
which is fair, equitable, transparent, competitive and
cost-effective”
as stated in subsection 217(1) of the
Constitution. No reliance was placed in particular on the provisions
of the PFMA, but for
an oblique reference to a schedule to the PFMA.
The main defence remained a reliance on section 217 of the
Constitution. An oblique
reliance by the defendants was placed on
Regulation 16A 6.1 of the treasury Regulations with reference to
certain threshold values
in Practice note 8 of the National Treasury.
[16]
The defendants raised three reasons why there was no compliance with
the aforementioned requirement
of subsection 217(1) of the
Constitution, namely:
1.
It was unfair to service providers who
could have been interested in rendering the services and/or goods
rendered by the plaintiff;
2.
It was not competitive because other
service providers did not submit bids or quotes for services that
would be rendered consequent
to the extended agreement; and
3.
It was otherwise not transparent and not
cost effective as it was not in terms of a public tender and that the
payments were made
based upon the equipment of which ownership of
that equipment befell the first defendant after the initial 7 year
period.
[17]
The plaintiff contended that the provisions of section 217 of the
Constitution, in respect of
the matter
in casu,
do not apply
for the following:
(a)
The tender called for the supply of
services for energy savings to the first defendant in respect
of electricity used by the
first defendant and for which it was
liable to pay;
(b)
After the award of the tender to the
plaintiff, a contract was prepared between the parties. It contained
provisions for the supply
of energy saving services and the relevant
equipment to achieve such energy savings;
(c)
That contract was for an initial period of
7 years, subject to an extension for a further period, at the behest
of the first defendant,
which the plaintiff could accept or not. The
contract would endure for the 7 year period commencing in May 2003
and end in May
2010;
(d)
In terms of clause 2 of the contract, the
plaintiff requested the first defendant whether it intended to extend
the contract for
a further period and in that event, a proposal was
put before the defendants;
(e)
The defendants subsequently considered the
plaintiff’s proposal and in turn submitted a report to the Bid
Committee of the
first defendant. In that report, a proposal was
included to extend the contract for a period of 10 years on the same
terms and
conditions as the existing contract;
(f)
A letter was addressed by the defendants to
the plaintiff that clearly stated the first defendant’s
intention to extend the
contract on the same terms and conditions as
the existing contract. The plaintiff accepted that proposal in
writing. No “new”
contract was signed between the
parties. The existing contract was extended and continued after the
initial 7 years for a period
of 10 years that ended in 2020;
(g)
The extension of the contract did not
constitute a variation, modification, waiver or consent to depart
from the position of the
contract as contemplated in clause 28
thereof.
[18]
Clause 2 of the contract that followed on the award of the tender,
reads as follows:
“
This
Agreement shall terminate 7 years after signing this Contract. The
Department of Public Works reserves the right to extend
the Contract
period after mutual agreement with the Contractor. The Contractor may
choose to waiver
(sic)
such
an offer by the Department.”
[19]
It was common cause that the contract that followed on the lawfully
granted award of the open
tender to the plaintiff endured from 20 May
2003 to 20 May 2010. It was common cause that during 2008 the parties
agreed to extend
the contract for a further period of 10 years that
would endure from 20 May 2010 to 20 May 2020. The only issue being
that the
defendants alleged that the procedure to extend the contract
fell short of the requirements stipulated in subsection 217(1) of the
Constitution, and hence was unlawful.
[20]
The evidence of Mr Dlamini was not tarnished during
cross-examination. He withstood the attack
on his evidence. It is to
be noted that nothing was put to Mr Dlamini in respect of what the
defendants’ witnesses would
testify. The defendants’ case
was simply not put to Mr Dlamini. His evidence was undisputed. His
evidence can be summarised
as follows:
(1)
At the relevant time during 2008 he was the
Regional Manager: Gauteng North Regional office of the first
defendant;
(2)
During that period, the plaintiff, through
a director of it, addressed a letter to Mr Dlamini enquiring whether
the first defendant
intended to extend the contract as provided for
in clause 2 thereof. A proposal was included should the first
defendant elect to
extend the contract. The proposal referred to a 10
year period of extension;
(3)
The said letter comprehensively dealt with
the projected summary of benefits after the 7 years with continued
investment of capital
expenditure by the plaintiff;
(4)
The regional Bid Committee, chaired by Mr
Dlamini, received a memorandum drawn by Mr Shabane from the property
payments section.
In that memorandum Mr Shabane recommended that
approval be granted to extend the energy saving contract for a
further period of
10 years. That memorandum was signed by Mr Shabane
and the Director: Property Management. That memorandum was signed on
4 April
2008;
(5)
The Regional Bid Committee, of which Mr
Dlamini was the chair, met on 9 April 2008. The recommendation of the
extension of the contract
was included on the agenda for that
meeting,. After deliberations on that issue, the Bid Committee
unanimously agreed to extend
the contract for a period of 10 years.
The Bid Committee comprised a wide representation by all relevant
regional sub-departments
of the first defendant;
(6)
At that meeting, it was further noted that
the plaintiff’s systems be used as blue print for roll out to
other provinces;
(7)
The first defendant confirmed the extension
of the contract to the plaintiff in writing on 11 April 2008;
(8)
On 17 April 2008, the plaintiff accepted
the first defendant’s extension offer in writing.
[21]
None of the foregoing evidence was disputed in cross-examination,
other than that the Bid Committee
was obliged to follow an open
tender process. Mr Dlamini’s response was simple: there was no
need to follow an open tender
process as the contract in clause 2
thereof provided for an extension at the behest of the first
defendant, and furthermore that
the extension would continue on the
same terms and conditions of the contract that was in place at the
time. No new terms or conditions
were agreed upon.
[22]
As recorded earlier, the defendants called two witness to counter the
evidence of Mr Dlamini
and to support the plea of illegality. The
first witness called by the defendants was Mr Rakau, the first
defendant’s head
of legal services at the time. His evidence
related to an investigation into the extension of the contract and
alleged “irregularities”
thereto. However, his evidence
was vague, lacked particularity and was not completed. The defendants
abandoned his evidence without
any cross-examination of that witness.
That evidence, in view of the abandonment by the defendants, stands
to be struck. No evidentiary
value can be attributed thereto.
[23]
The second witness called on behalf of the defendants was a Mr
Legotlo. That witness simply handed
in, as Exhibit A, a spreadsheet
purporting to show all payments made in terms of the contract for the
initial 7 years and all payments
made in terms of the extended
contract. The plaintiff denied the content of the spreadsheet. It was
apparently obtained from the
first defendant’s departmental
computer system. In presenting that evidence, there was no compliance
with the provisions
of
section 15(3)
of the
Electronic Communications
and Transactions Act, 25 of 2002
. No basis was laid for the admission
of that evidence. Furthermore, Mr Legotlo admitted that he did not
collate the figures on
the spreadsheet himself. No application was
made on behalf of the defendants for the admission thereof in terms
of the provisions
of the
Law of Evidence Amendment Act, 45 of 1988
.
That disposed of any compliance with, or applicability, of the
provisions of the
Law of Evidence Amendment Act. The
relevance of
Exhibit A in respect of the separated issue of legality was not
indicated, nor argued on behalf of the defendants.
It took the
separated issue no further.
[24]
From the foregoing, it follows that the defendants placed no evidence
before the court in support
of its contention of the breach of the
provisions of section 217(1) of the Constitution.
[25]
The plaintiff relied upon the dicta in paragraph [25] of
MEC for
Health, Gauteng v 3P Consulting (Pty) Ltd
2012(2) SA 542 SCA in
support of its contention that compliance with the provisions of
section 217(1) of the Constitution was not
relevant, nor required. In
particular, the plaintiff submitted that the call for open tenders in
respect of the services to be
rendered as contained in the extended
contract was not required in the present instance.
[26]
In
3P
,
supra,
the Supreme Court of Appeal held in
paragraph [25]:
“
It
is clear that the renewal of the services agreement did not give rise
to a new service agreement; it simply extended the duration
of the
services agreement for a period of 3 years. Properly interpreted,
clause 2.3 of the agreement provides for a renewal for
a period of
two years on the same terms as before subject only to such amendments
as may be negotiated and agreed between the parties.
… As
there was no new service agreement, there was no new procurement of
goods or services and it was therefore in my view
not necessary to
follow a competitive public bidding process in this regard.”
[27]
The defendants challenged that judgment on a number of grounds:
(a)
In terms of clause 2 of the original
agreement, the period of the original agreement shall terminate after
7 years,
i.e.
that the contract would terminate after a specific period;
The defendants obtusely
ignore the rest of that clause 2 where it is specifically recorded
that the first defendant had the right
to extend that contract for a
further period on mutual agreement and which the plaintiff had the
right to decline. There is no
merit in that submission.
(b)
The defendants further submitted that if
the contract was indeed extended, it amounted to a contract for the
procurement of the
supply of goods and services, thus falling within
the ambit of section 217 of the Constitution.
There is equally no merit
in that submission. Firstly, it was common cause that no new contract
was concluded. The duration of the
contract following on the lawfully
awarded tender to the plaintiff, was merely extended on the same
terms as the contract. The
defendants’ attempt to aver that the
inclusion of “additional buildings” is of no consequence.
The contract in
fact anticipated such addition.
(c)
It was further the defendants’
contention that the extended contract concerned the procurement of
goods or services in excess
of R 500 000, and thus constituted a
contravention of Practice Note 8 issued in terms of the PFMA. That
note required a competitive
bidding process to be followed in such
event.
Similarly, there is no
merit in that submission. The contract explicitly provided that the
plaintiff would bear the financial burden
in setting up the capital
required to supply and install the energy saving devices and the
management thereof. The project would
be undertaken at no cost to the
first defendant. It would only benefit from the savings achieved by
the installation and management
of the energy savings devices. The
parties would share equally in such savings. In terms, the first
defendant would only enjoy
the benefit of the energy savings
achieved, and where there was no savings, it paid nothing.
Furthermore, at the end of the contract,
the ownership in the energy
saving devices would accrue to the first defendant at no cost to it.
Clearly a win-win situation for
the first defendant. Accordingly,
there was no transgression of the provisions of Practice Note 8.
(d)
On behalf of the defendants it was
submitted that whenever an organ of state contracts for goods or
services, that organ of state
was obliged to adhere to the provisions
of section 217 of the Constitution. In this regard, reliance was
placed upon a host of
authorities:
1.
Firstly,
reliance was placed upon the dicta in
Airports
Company South Africa SOC LTD v Imperial Group Ltd et al.
[1]
That matter concerned a request for bids in respect of an open tender
and in particular of the terms of that bid request, unlike
the
present matter where there was an extension of the duration of a
contract granted on a lawful award of a tender. It finds no
application
in
casu
.
2.
Further
reliance was placed upon
Eastern
Cape Development Agency et v Agribee Beef Fund (Pty) Ltd et al.
[2]
That judgment concerned the conclusion of a tripartite agreement
entered into between two organs of state and a private party.
The
issue to be adjudicated was whether the agreement concluded was one
for the procurement of goods or services. No procurement
procedure as
intended for in section 217 of the Constitution was followed. The
parties merely entered into the tripartite agreement.
That matter is
clearly distinguishable from the present instance.
None of the
aforementioned cases dealt with, nor considered the
3P
matter.
That authority remains applicable and in point in this matter.
(e)
There is no merit in the defendants’
contention that, following and open tender bid request, another party
may have tendered
for a split of the savings on a formula of, e.g.
70/30 in the first defendant’s favour. That submission was
extremely speculative
and no supporting submissions were made, or
supporting facts were presented therefor were placed before the
court. It is of no
moment that for a speculative reason, the first
defendant was obliged to follow a prescribed procurement procedure.
It could well
be speculated that another party may have sought a
higher percentage in its favour.
(f)
It was further submitted on behalf of the
defendants that the extension of the contract varied the terms of the
contract in a material
way by extending the initial period of 7 years
to 10 years. There is no merit in that submission. Clause 2 of the
contract clearly
made provision for the extension of the contract at
the behest of the first defendant on mutual agreement between the
parties and
did not qualify any period of extension. The period of
extension would follow on mutual agreement between the parties.
[28]
Much was made on behalf of the defendants that the energy saving
devices were to become the property
of the first defendant in terms
of clause 4.3 thereof. That submission ignores the precise wording of
that clause which clearly
states on the termination of that contract.
The contract was not terminated, but extended for a further period.
Only after that
extended period elapsed, would the contract
terminate.
[29]
In view of all the foregoing, the extension of the contract for a
further period did not fall
foul of the provisions of section 217 of
the Constitution. In the particular circumstances the provisions of
that section simply
did not apply.
[3]
[30]
The plaintiff contended that in view thereof that the extended
contract had run its full course,
no possible purpose could be served
setting same aside. In that regard, the court has a discretion to
decline to set aside a contract
due to inconsistency with section 217
of the Constitution.
[4]
[31]
It follows that the defendants have not discharged the onus upon them
in respect of separated
issue of illegality. That issue stands to be
decided in favour of the plaintiff.
[32]
In view thereof that insufficient time remained in respect of the
period for which this action
was enrolled, and further in view
thereof that the evidence in respect of the plaintiff’s claim
for payment has yet to be
completed, the action stands to be
postponed.
I grant the following
order:
1.
It is declared that, on or about 11 April
2008, the parties lawfully, by agreement, extended the contract,
following on the lawful
award of Public Tender number P[...] to the
plaintiff, on the same terms and conditions for an additional period
of 10 years which
period was calculated from 20 May 2010 to 20 May
2020;
2.
The defendants are ordered to pay the costs
of the trial from Wednesday 6 March 2024 to Thursday 14 May 2024,
which costs shall
include the costs consequent upon the employment of
two counsel;
3.
The matter is postponed to a date to be
arranged with the Deputy Judge President in consultation with the
trial judge;
4.
The balance of the costs is reserved.
C J VAN DER WESTHUIZEN
JUDGE OF THE HIGH COURT
On
behalf of Applicant:
Adv
P Ellis SC
Adv
A Ellis
Instructed
by:
Weavind
& Weavind Attorneys
On
behalf of Respondent:
Adv
M Mojapelo SC
Adv
V Mabuza
Instructed
by:
State
Attorney, Pretoria
Dates
of Hearing:
04
- 14 March 2024
Judgment
Delivered:
26
March 2024
[1]
2020(4)
SA17 (SCA)
[2]
[2022] JOL 51939 (SCA)
[3]
See
3P,
supra
[4]
Chairperson,
Standing Tender Committee et al v JFE Sapela Electronics (Pty) Ltd
2008(2) SA 638 (SCA)
sino noindex
make_database footer start
Similar Cases
Alto Management CC v Wingtip Crossing Shopping Centre (Pty) Ltd (Leave to Appeal) (59545/2018) [2024] ZAGPPHC 1113 (29 October 2024)
[2024] ZAGPPHC 1113High Court of South Africa (Gauteng Division, Pretoria)97% similar
Barak Fund SPC Limited obo Barak Structured Trade Finance Segregated Portfolio v Business Venture Investments and Others (Leave to Appeal) (36125/2022) [2024] ZAGPPHC 1348 (20 December 2024)
[2024] ZAGPPHC 1348High Court of South Africa (Gauteng Division, Pretoria)97% similar
Alto Management CC v Wingtip Crossing Shopping Centre (Pty) Ltd (59545/2018) [2024] ZAGPPHC 808 (12 August 2024)
[2024] ZAGPPHC 808High Court of South Africa (Gauteng Division, Pretoria)97% similar
W Capital Finance (Pty) Ltd and Another v GP Venter Attorneys Inc and Another (79444/2019) [2024] ZAGPPHC 223 (11 March 2024)
[2024] ZAGPPHC 223High Court of South Africa (Gauteng Division, Pretoria)97% similar
MM Chartered Accountants Inc. v Ntokazi Consulting (Pty) Ltd (2021/54556) [2024] ZAGPPHC 251 (11 March 2024)
[2024] ZAGPPHC 251High Court of South Africa (Gauteng Division, Pretoria)97% similar