begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 632
|
Noteup
|
LawCite
sino index
## Avbob Mutual Assurance Society v Mkhonza and Others (11408/2022)
[2024] ZAGPPHC 632 (27 June 2024)
Avbob Mutual Assurance Society v Mkhonza and Others (11408/2022)
[2024] ZAGPPHC 632 (27 June 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_632.html
sino date 27 June 2024
FLYNOTES:
PROPERTY – Agreement of sale –
Warranty
–
Purchase
of property for use as funeral parlour – Property not zoned
for such use – Breach of warranty clause
not breach of
material condition of contract of purchase and sale –
Warranty clause severable from agreement of purchase
and sale –
Plaintiff not entitled to remedy of rescission (actio
redhibitoria) – Since seller in breach of warranty
clause on
zoning, remedy is one of damages – Purchaser failed to
quantify and prove any damages it suffered –
Claim
dismissed.
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
Case Number: 11408/2022
(1)
REPORTABLE: NO
(2)
OF INTEREST TO OTHER JUDGES: NO
(3)
REVISED: NO
DATE:
SIGNATURE:
In the matter between:
AVBOB MUTUAL ASSURANCE
SOCIETY
Plaintiff
and
WILLIE
JONAS
MKHONZA
1
st
Defendant
QUEEN
ELIZABETH
MKHONZA
2
nd
Defendant
THE
REGISTRAR OF DEEDS, PRETORIA
3
rd
Defendant
Delivered:
This judgment was prepared and
authored by the Judge whose name is reflected and is handed down
electronically by circulation to
the parties/their legal
representatives by e-mail and by uploading it to the electronic file
of this matter on Caselines. The date
for hand-down is deemed to be
10: 00 am on 27 June 2024.
Summary: Breach of a
warranty clause is not a breach of a material condition of a contract
of purchase and sale. Warranty clause
is severable from the agreement
of the purchase and sale of the immovable property. The plaintiff is
not entitled to the remedy
of rescission (
actio redhibitoria
)
of the agreement of the purchase and sale. The first defendant is in
breach of the warranty clause relating to the zoning of the
premises
and the remedy available to the plaintiff is one of claiming for
damages. The plaintiff has failed to quantify and prove
any damages
it suffered. Held: (1) The plaintiff’s claim is dismissed.
Held: (2) The plaintiff is ordered to pay the costs
of the defendants
on a party and party scale to be taxed or settled at scale B.
JUDGMENT
MOSHOANA,
J
Introduction
[1]
These are action proceedings instituted by Avbob
Mutual Assurance Society (Avbob). The action is instituted against
Willie Jonas
Mkhonza and his wife Queen Elizabeth Mkhonza (hereafter
collectively referred to as the “Mkhonzas”). In this
action,
Avbob claims an amount of three million rands, being in
respect of the purchase price paid to acquire the immovable property
(
restitutio in intergrum
)
and in respect of the alleged suffered consequential damages against
the Mkhonzas.
[2]
Additionally, Avbob sought an order directing the
registrar of deeds to cancel the transfer and registration of the
immovable property
in the name of Avbob and return it to the name of
the Mkhonzas. The registrar did not defend the action.
[3]
The order against the registrar is dependent upon
an order of rescission of the purchase and sale agreement (
actio
redhibitoria
). An order refusing a
rescission denotes a refusal to reverse the transfer process
(
restitutio in intergrum
).
At the conclusion of the trial, during closing argument, the claim
for consequential damages was abandoned due to lack of evidence
in
support of any damages claim.
[4]
The instituted action is duly defended by the
Mkhonzas. The Mkhonzas led no evidence in defence of the action. The
genesis of this
action is the alleged breach of two clauses (namely
19.3 and 19.4) included in the agreement for the purchase and sale of
an immovable
property. In both the clauses, a warranty was given by
the Mkhonzas that (a) there were plans in place which were approved
by the
local authority and (b) that the immovable property was
properly zoned for the business of conducting a funeral parlour and
mortuary.
[5]
Despite the breach of the warranties having been
discovered, that there are no approved plans in place and that the
property was
not zoned for a funeral parlour business, the immovable
property was transferred from the names of the Mkhonzas to Avbob. At
the
time when this action was instituted, Avbob was the registered
owner of the immovable property and has been for a considerable
while.
Background facts and
evidence
[6]
Avbob is a registered mutual assurance society.
Around 2018, Avbob developed an interest to purchase a funeral
parlour business
which was a going concern and was operated by the
Mkhonzas. Negotiations for the contemplated sale of business
commenced in earnest
with the Mkhonzas. Those negotiations only
culminated in a conclusion of a written agreement of the purchase and
sale in respect
of the immovable property to wit, Portion 4 of Erf
2[...] S[...] Township, Registration Division J.R. Province of
Gauteng, measuring
approximately 1867 SQM (“the property”).
The contemplated purchase of the business as a going concern fell by
the way
side.
[7]
On or about 14 June 2019, the property was
registered and transferred into the name of Avbob under the deed of
transfer number T[...].
After the said transfer, Avbob took
occupation but was unable to conduct a business of a funeral parlour
and mortuary due to the
fact that the property was not properly zoned
for that.
[8]
On or about 20 December 2021, Avbob directed a
written notice to the Mkhonzas advising them of the contended breach
of the warranties
and required of them to remedy the breach within 10
days of that notice. The notice also advised them that should the
breach not
be remedied, the purchase and sale agreement shall be
cancelled. I interpose to remark, how does a party remedy the breach
of a
warranty? Once the promised warranty does not materialize, water
runs quietly under the breach unless a new promise is made.
[9]
The breach was not remedied as demanded (in my
view irremediable) and on 22 February 2022, Avbob issued a notice
seeking to cancel
the purchase and sale agreement. Following the
effected cancellation, which in my view was meaningless at the time
it was effected,
on 24 February 2022, Avbob caused a combined summons
to be issued against the Mkhonzas and the registrar. As indicated
above the
action was duly defended by the Mkhonzas.
[10]
For the purposes of context, the provisions of
clause 19 alleged to be, in parts, offended by the Mkhonzas was
introduced into the
agreement of the purchase and sale by Avbob given
its previous melancholic experience of leasing a property in the same
township
of Soshanguve which was not suitably zoned.
[11]
Prior to the conclusion of the purchase and sale
agreement, a due diligence exercise was performed by Avbob. The
employee who performed
the due diligence exercise assumed that since
the Mkhonzas were already operating a funeral parlour business, there
were proper
plans in place and that the property was suitably zoned.
[12]
The allegedly offended clause 19 was drafted by
Avbob and it labelled it “other or special conditions”.
The pertinent
portions read thus:
“
This
offer to purchase is subject to the suspensive conditions that:
19.3
The Seller warrants that all alterations and
improvements to the Property have been approved by the Local
Authority and that all
plans which are required have been submitted
to and approved by such Local Authority. Copies of the approved plans
to be provided
to the purchaser.
19.4
The seller hereby warrants that the property is
zoned for business with specific approval from the local authority to
use the premises
for a funeral parlour with a mortuary, failing which
this offer to purchase shall be cancelled and be of no further force
or effect.
This clause is for the benefit of the Purchaser who may
unilaterally waive at any time prior to the fulfilment of the
condition.”
[13]
In this Court, Avbob contended that its case is
predicated on the breach of the above warranties as opposed to the
non fulfilment
of any suspensive conditions. Upfront, a stance was
adopted by Avbob that clause 19 does not amount to suspensive
conditions. Ironically,
this it did despite it, as the author, having
labelled it as such.
[14]
In support of its case, Avbob presented evidence
of four witnesses, namely Mr Peter John Dacomb; Ms Thando Mlangeni;
Mr Ettiene
Burger; and Mr Ernest Mokoena. Given the fact that this
matter revolves around an interpretation of the offended clauses, it
is
unnecessary to regurgitate the testimony of all those witnesses in
this judgment.
[15]
Interpretation is a matter of law as opposed to
fact. I do however hasten to mention that performance of the terms of
an agreement
is a matter of fact. A brief summation of the testimony
of each witness shall, in the present circumstances, suffice.
[16]
Mr Dacomb is a Professional Planner (Town and
Regional Planning). He was mandated by Avbob to investigate whether
there are approved
plans in place for the property and whether the
property was zoned for a funeral parlour business. His investigations
revealed
that although the property was zoned for other business
uses, it was not zoned for funeral parlour business use.
[17]
The investigation also revealed that no plans
approved by the City of Tshwane were in place. The plans or sketches,
as he termed
them, that he perused bore stamps and signatures of
Garankuwa Hospital and some other government department. Those stamps
and signatures
were affixed and appended around 1985/6.
[18]
Having made those discoveries, he concluded that
the sketches provided by the Mkhonzas were not, in his opinion,
approved building
plans and do not comply with the applicable
regulations. He further concluded that the property being zoned for
“Business
2” is not permitted to be used for the purposes
of a funeral undertaker or a mortuary.
[19]
Ms Mlangeni is an employee of the City of Tshwane
in the health department. As a functional head she deals with
certification and
compliance with regulations. She confirmed that the
funeral parlour business conducted by the Mkhonzas had a certificate
of competency
that was issued by her department. However, she
testified that such certification did not exempt them from complying
with the other
requirements like zoning and submission of building
plans for approval.
[20]
Mr Burger is an employee of Avbob employed as an
investment specialist. He was involved in the process leading to the
acquisition
of the property. He was instrumental in the generation
and inclusion of clause 19 into the agreement of the purchase and
sale.
He testified that Avbob was unhappy with the transferring
attorney for not having ensured that the provisions of clause 19 were
met before transfer of the property was effected.
[21]
He testified that, in his view, the warranties had
to be satisfied before transfer could take place. He confirmed that
Avbob did
not waive compliance with the warranties. He further
confirmed that Avbob attempted to regularise the zoning issue but he
was unaware
as to why did the regularisation not materialize. He also
confirmed that clause 19 was introduced late into the agreement and
was
drafted by the legal department of Avbob.
[22]
Mr Mokoena is an employee of Avbob employed as a
provincial manager. He was intimately involved in the negotiations
that led to
the purchase of the property. Although he did not see any
certificates, he assumed that the property was suitably zoned since
the
premises of the Mkhonzas were already operating as a funeral
parlour. He confirmed that he received the plans exhibited in C1 and
C2 respectively as well as the certificates of compliance from the
Mkhonzas.
[23]
The Mkhonzas closed their case without calling any
witness.
Analysis
[24]
It is, in my view, obsolete for the purposes of
this judgment to engage in an elaborate interpretative exercise given
the clear
language employed in clause 19. Although, clause 19 is
labelled as “suspensive conditions”, in truth it contains
separable
and severable warranties made by the Mkhonzas. In contract
parlance, a suspensive condition is a
one
which prevents an obligation
from arising
unless and until a specific future event, certain or uncertain,
occurs.
The fact that the drafter of clause
19 chose to label it a suspensive condition does not make it one. The
warranties given by the
Mkhonzas did not amount to conditions which
will prevent an obligation from arising. A warranty is distinct from
a condition in
a contract.
[25]
Typically, a contract is formed where one party
makes an offer and the other accepts that offer. On the available
evidence, Avbob
made an offer to purchase immovable property and that
offer was accepted by the Mkhonzas. Thus, a contract for the sale of
the
immovable property was consummated.
[26]
The supposed suspensive conditions are attached to
an offer to purchase as opposed to any obligations arising from the
purchase
and sale agreement. Ordinarily, a proper offer is incapable
of being cancelled. An offer is either accepted or withdrawn before
acceptance. Once an offer is withdrawn there can be no contract
consummated. Similarly, once an offer is accepted a contract shall
be
consummated.
[27]
In my view, clause 19 constitutes a separate and
severable warranty agreement and not a true suspensive condition.
Accordingly,
this Court agrees with a submission by Avbob’s
counsel to that effect. If they were suspensive conditions, the fact
that
the conditions were not met would entail that an agreement of
the purchase and sale did not come into existence. Such is absurd
in
view of the fact that transfer happened and Avbob belatedly sought to
cancel a consummated agreement.
[28]
A sale
agreement is consummated if (a)
emptor
et venditor
(buyer
and seller capable of entering into an agreement of sale); (b) the
merx
or
res
vendita
(the
thing or things which form the subject matter of the agreement of
sale)
[1]
; (c) the
pretium
(the
price in money or which is readily ascertainable in terms of
money)
[2]
; and (d)
consensus
ad idem
(the
mutual consent of the contracting parties) are all present.
[29]
The warranties are not the essential to the
formation of a valid purchase and sale agreement. On the other hand,
a warranty is merely
a contractual statement of fact by one party to
another, asserting that a specific state of affairs is true. It is an
innominate
term that does not go to the root of the contract and as
it shall later be demonstrated, it entitles the innocent party to
damages
claim if it is breached.
[30]
In
casu
,
there can be no doubt that the Mkhonzas stated as a true fact that
there are approved plans and that the property is zoned for
a funeral
parlour use. It had turned out that the statement of zoning status is
untrue. With regard to the statement of the approved
plans, the
clause refers to a “Local Authority” as the body to
approve those plans. No evidence was led that during
the negotiations
or so soon thereafter there were on-going alterations and or
improvements to the property.
[31]
The clause does not specifically refer to the City
of Tshwane. The agreement provides no special definition to the
phrase local
authority. By grammatical definition, a local authority
means an administrative body in local government. The plans submitted
by
the Mkhonzas entered into evidence as C1 and C2 respectively bear
stamps from amongst others, the chief civil engineer of control
inspector of works. This stamp was affixed on 18 June 1985. A
signature was also appended assumedly by the civil engineer.
[32]
This Court must take judicial notice of the fact
that in June 1985, the City of Tshwane was not in existence.
Accordingly, it cannot
be correct to assume that the alterations or
improvements effected in 1985 required the approval of the City of
Tshwane or its
predecessor in law.
[33]
There was no cogent evidence led that Soshanguve,
being the area where the property is situated, fell under the
authority of the
City of Tshwane or its predecessor in law in 1985.
Mr Dacomb was himself uncertain as to under which local authority
Soshanguve
fell.
[34]
Clause
19 was drafted in 2019. It may be assumed that Avbob when inserting
the undefined phrase local authority in the clause, it
had in mind
the City of Tshwane. However, as a matter of fact there were no
alterations or improvements that were taking place
in 2019.
Therefore, on application of the
contra
proferentem
rule,
the relevant clause must be interpreted against Avbob.
[3]
The legal department of Avbob had all the opportunity to make the
language employed clearer. The stamp affixed by the chief civil
engineer of the control inspector of works is preceded by the words
“approved by”.
[35]
Therefore, there can be no doubt that
ex
facie
the plans duly submitted, there
was an approval. The approval is from a local authority or an
authority in charge of Soshanguve
identified as control inspector of
works. With such evidence, it cannot be correct that the Mkhonzas
breached the warranty by providing
an untrue statement. There were
plans in place which were approved by the relevant authorities in
1985. Accordingly, this Court
concludes that the warranty in respect
of the plans was not breached.
[36]
With regard to the zoning warranty, the Mkhonzas
specifically warranted that the property is zoned for business with
specific approval
from the local authority to use the premises for a
funeral parlour with a mortuary. The certificate that was unearthed
by Mr Dacomb
zoned the property differently. Therefore, the fact that
the property was zoned for use as a funeral parlour is not true.
[37]
The Mkhonzas advisedly chose not to testify. All
the versions put during cross- examination which suggested that
documents may have
been burned and obliterated when “
Munitoria
”
burned down amount to no evidence to rebut the
uncontested version of Mr Dacomb. There is no evidence to remotely
suggest that the
perspicuous misrepresentation was innocent.
[38]
It may well have been so that the Mkhonzas
innocently believed, owing to the fact that they operated a funeral
parlour business
without any hindrance, that the premises are
appropriately zoned. Having not testified such a conclusion is
incapable of being
made in favour of the Mkhonzas. Accordingly, the
conclusion this Court reaches is that the warranty was indeed
breached by the
Mkhonzas.
[39]
What then is the effect of such a breach? Avbob
contends that the breach entitles it to a rescission of the agreement
of the purchase
and sale. I disagree. Although clause 19 was inserted
in the same document embodying the agreement of the purchase and
sale, it
is, in my view, severable from the purchase and sale
agreement. The warranties are clearly separate and independent from
the purchase
and sale agreement. Their late inclusion into the
drafted agreement bears testimony to their discrete nature and
purpose. It must
have not dawned on the drafters of clause 19 that
the stage of offer and acceptance had long passed.
[40]
In
both
Middleton
v Carr
[4]
and
Nash
v Golden Dumps (Pty) Ltd
[5]
,
the Supreme Court of Appeal, particularly in
Nash
held
that a sale of the future office unit created reciprocal rights and
obligations which were entirely unrelated and separate
from the
option to purchase additional office space, which on its own, also
initiated a different independent set of rights and
obligations. It
followed that, although the sale of future office unit and the option
to purchase additional office space were
incorporated in the same
document, two separate and independent contracts were concluded.
[6]
In
Carr
it
was concluded that an undertaking by a husband to pay his estranged
wife a substantial sum of money was severable from a collusive
agreement for divorce.
[41]
Similarly, this Court takes a view that the
warranties and the purchase and sale agreement although embodied in
the same document
are unrelated and separate. The warranty seeks to
regulate and insulate, as it were, the offer to purchase. Whilst the
purchase
and sale seeks to embody the already orally agreed terms of
the sale of an immovable property. The requirement to conclude a
written
and signed agreement is not an
essentialia
of the agreement but a legal
requirement of the Alienation of Land Act.
[42]
Thus, the validity of the purchase and sale
agreement was not dependent on the warranties made by the Mkhonzas.
It was within the
powers of Avbob as the author of clause 19 to make
it related and dependent on the purchase and sale agreement. Instead,
reference
is made to cancellation of an offer to purchase, in the
circumstances where, the stage of offer and acceptance had passed
already.
Ordinarily if an offer is cancelled, which must mean
withdrawn, an agreement does not come into existence.
[43]
It seems to me that the drafters of the clause
contemplated an impossible situation of unscrambling the egg as it
were. This is
so because when the agreement was drafted for
signature, in compliance with the Alienation of Land Act, the stage
of offer and
acceptance had happened as a sequel of the detailed
negotiations process. The warranty clearly brings to the fore
separate and
unrelated rights and obligations.
[44]
Actio
ex empto
is
an
aedilitian
remedy
where a claim for damages with or without a cancelation of sale
occurs where a purchaser can prove that the property had
latent
defect when it was sold and that the seller knowingly concealed the
latent defect or knowingly represented the absence thereof.
On the
other hand,
actio
redhibitoria
–
rescission
- is a remedy only available where the defects either destroys or
impair the usefulness of the thing sold.
[7]
Differently put, the defect must go to the root of the agreement.
[45]
The zoning of the property does not destroy nor
impair the usage of the property. The zoning is a regulatory process
to ensure additional
business use of the property. Avbob had already
commenced a process to ensure that the property is suitably zoned,
however evidence
around that process was for reasons better known to
Avbob inchoate. Had Avbob proceeded with the regulatory process, it
would have
had a claim for damages against the Mkhonzas.
[46]
In
Landbou-Tegniese
Dienste v Scholtz
[8]
it was
found that an action for failure to deliver a fertile bull was an
actio
ex empto
as
opposed to
actio
redhibitoria
.
It would have been
actio
redhibitoria
if
no bull was delivered at all. Similarly, a failure by the Mkhonzas to
deliver a suitably zoned property entitles Avbob to
actio
ex empto
particularly
in an instance where the Mkhonzas warranted the existence of the
relevant zoning.
[47]
Absence of a zoning certificate does not render
the property to be unfit for the purpose an immovable property is
commonly used
for. Avbob did not purchase a funeral parlour business.
It is accepted that a funeral parlour business is not useful to the
purchaser
where the necessary permission to conduct it is absent.
Avbob managed to take occupation of the immovable property.
[48]
This is testimony to the fact that the property
served the purpose which properties are commonly used for, which is
to ensure occupation,
as the saying goes “a roof above the
head”. There was no scintilla of evidence led by Avbob to
suggest any latent defects
on the property (buildings and land).
[49]
Accordingly, this Court concludes that the breach
of the zoning warranty does not entitle Avbob to a rescission of the
purchase
and sale agreement, particularly where Avbob had taken
occupation and a transfer, which has occurred two years before the
purported
cancellation, took place. Avbob is entitled to claim
damages for the breach of the zoning warranty.
[50]
Before I turn my attention to the question of
damages claimable, I must deal with the issue of the cancellation
notice that commenced
in December 2021. At that time, the sale was
already perfected in that the transfer and the risk attendant to the
property had
been passed to Avbob. There was effectively nothing to
cancel. The proverbial horse had bolted already. Clause 19.4 entitled
Avbob
to cancel the offer to purchase and not the purchase and sale
agreement. As discussed above, an offer to purchase is incapable of
being cancelled but only capable of being withdrawn.
[51]
Clause 15 of the purchase and sale agreement
contained a cancellation clause (
lex
commisari
). That right of cancellation
vests on a party only in the event of the breach of the agreement and
most importantly, it avails
to the aggrieved party two options;
namely; (a) to sue for specific performance or; (b) cancel the
agreement. These are known remedies
in contract law that are
available for a breach often known as malperformance. It is trite law
that where the contract is cancelled,
the only residual remedy
available to the aggrieved party is that of claiming and proving
damages against the offending party.
[52]
The
right to cancel does not prescribe in terms of the Prescription Act,
since it is not a debt, but it must be exercised within
a reasonable
time. In
Stewart
v Wrightson Ltd v Thorpe
[9]
it was
held that cancellation is a unilateral juristic act performed by an
innocent party and does not require consent of the guilty
party. To
make that choice to cancel is a subject of reasonableness.
[10]
[53]
A delay in electing a cancellation would lead the
other party to believe that the injured party has elected to condone
the breach.
As far back as June 2019, Avbob got wind that the
warranties are not true, yet it cancelled or gave notice to do so
almost three
years later.
[54]
Cancelling an agreement after passage of such a
considerable period of time is certainly unreasonable and must have
given the Mkhonzas
a believe that their breach was condoned by Avbob.
Steps taken to regularise the zoning is objectively also suggestive
of condonation.
[55]
Condonation
does not amount to a waiver
per
se
but
it is more an acquiescence. Acquiescence as a defence is very much
part of our law since the case of
Dabner
v South African Railways and Harbour.
[11]
[56]
In the circumstances of this case, Avbob has
actually perempted its right to cancel. It cannot approbate and
reprobate at the same
time. It cannot blow hot and cold at the same
time. It had commenced a process of regularising the zoning issue,
which action suggests
a condonation and or peremption on its part.
So, on application of the doctrine of election, having made that
election, it cannot
make a
volte face
and return to the cancellation option.
Accordingly, in my view, Avbob is not entitled to the cancellation of
the purchase and sale
agreement.
[57]
I now
turn to the damages claim. Avbob has prayed for consequential damages
to the tune of three million rands. At the conclusion
of the matter,
during argument, this claim for consequential damages was abandoned
due to lack of evidence in quantification thereof.
As a general rule
the purchaser is entitled to be placed in the same position it would
have been if the contract had been performed.
[12]
[58]
In
casu
,
the Mkhonzas’ warranties may or may not have influenced the
purchase price. In other words, if the warranty was true, the
value
of the property would have been three million rands still, then Avbob
would remain in the same position even if the warranty
was
untrue
[13]
. On the other hand,
if evidence was led that the actual price without the warranty would
have been two million five hundred rands
for instance, then the
amount of five hundred thousand rands would have been the damages
suffered
by
Avbob.
Since
no
evidence
of
any
loss
as
a
direct
consequences
of
the
false warranty was led, Avbob is not entitled to any damages
[14]
.
It did not prove any damages.
[59]
For all the above reasons, I make the following
order:
Order
1.
The claim of Avbob is dismissed
2.
Avbob is ordered to pay the costs of the Mkhonzas
on a scale of party and party to be settled or taxed at scale B.
GN MOSHOANA
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
PRETORIA
APPEARANCES:
For
Plaintiff:
Mr B L
Manentsa
Instructed
by:
Adams
& Adams, Pretoria.
For
Defendants:
Mr E
Janse Van Rensburg
Instructed
by:
S J
Van Den Berg attorneys, Pretoria.
Date
of the hearing:
11,
12, and 14 June 2024
Date
of judgment:
27
June 2024
[1]
See
Kriel
and Another v Le Roux
[2000]
2 All SA 65 (SCA).
[2]
See
Lubbe in 2000
Annual
Survey
pp
213-221.
[3]
See
Kliptown
Clothing Industries (Pty) Ltd v Marine and Trade Insurance Co of SA
Ltd
1961
(1) SA 103
(AD) at 108C and
Fedgen
Insurance Ltd v Leyds
1995
(3) SA 33 (AD)
[4]
1949
2 SA 374 (A).
[5]
1985
3 SA 1 (A).
[6]
See
also
Exdev
(Pty) Ltd v Pekudei Investments (Pty) Ltd
2011
2 SA 282 (SCA).
[7]
See
Dihbley
v Furter
1951
(4) SA 73 (C).
[8]
1971
(3) SA 188 (A).
[9]
[1977]
(1) PH A15 (AD).
[10]
See
Segal
v Mazzur
[1920]
CPD 634
at 644-5.
[11]
1920
AD 583.
See also
SARS
v CCMA and others
(2017)
38 ILJ 97 (CC) at para 26.
[12]
See
Clark
v Durban and Coast SPCA
1959
(4) SA 333 (N).
[13]
See
Caxton
Printing Works (Pty) Ltd v Transvaal Advertising Contractors Ltd
1936
TPD 209.
[14]
See
Holz
v Thurton & Co
1908
TS 158
;
Vivian
v Woodburn
1910
TPD 1285
;
Bower
v Sparks, Young and Farmers’ Meat Industries Ltd
1936
NPD 1
at 13-15.
sino noindex
make_database footer start