Case Law[2023] ZAGPPHC 1892South Africa
Avgold Limited and Another v Minister of Water and Sanitation and Others (039650 /2023) [2023] ZAGPPHC 1892 (27 October 2023)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 1892
|
Noteup
|
LawCite
sino index
## Avgold Limited and Another v Minister of Water and Sanitation and Others (039650 /2023) [2023] ZAGPPHC 1892 (27 October 2023)
Avgold Limited and Another v Minister of Water and Sanitation and Others (039650 /2023) [2023] ZAGPPHC 1892 (27 October 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_1892.html
sino date 27 October 2023
HIGH
COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
CASE
NO:039650 /2023
(1)
REPORTABLE: YES/NO
(2)
OF INTEREST TO
OTHERS JUDGES: YES/NO
(3)
REVISED
DATE:
8/11/2023
SIGNATURE
In
the matter between:
AVGOLD
LIMITED
First
Applicant
HARMONY
GOLD MINING COMPANY LIMITED
Second
Applicant
and
MINISTER
OF WATER AND SANITATION
First Respondent
DIRECTOR-GENERAL
DEPARTMENT
OF
WATER AND SANITATION
Second
Respondent
PROVINCIAL
HEAD, FREE STATE
Third
Respondent
DEPARTMENT
OF WATER AND SANITATION
DIRECTOR:
COMPLIANCE AND ENFORCEMENT
Fourth
Respondent
FOR
THE FREE STATE
DEPARTMENT
OF WATER AND SANITATION
JUDGEMENT
RAULINGA,
J
This
matter has been heard in open court and is otherwise disposed of in
terms of the Directives of the Judge President of this
Division. The
judgment is accordingly published and distributed electronically.
Introduction
[1]
This is an application brought by the applicants on an
urgent basis for an interim
interdict.
Background
[2]
The applicants submit that the application is urgent since it meets
the
requirements set out in Rule 6(5)(b) as further communicated in
the leading case of
Luna Meubel Vervaardigers v Makin
1977
(4) SA 135
(W),
and other relevant cases.
[3]
The respondents oppose the application and contend that the matter is
not urgent, and the urgency is self-created.
[4]
The respondents contended further that the applicants failed to meet
the requirements
necessary for granting of the interim
interdict.
[5]
In September 2022, the Department of Water and Sanitation (DWS), Free
State Provincial Office received a complaint that the applicants
(Harmony); Target Operations situated near the town of Allanridge
was
discharging water into the Voelpan Dam. Following receipt of the
complaints, an officer of DWS, contacted Harmony to enquire
if they
are aware of the discharge. Harmony acknowledged the discharge into
the Voelpan and presented a mitigation plan to DWS
including measures
to be implemented to stop the discharge.
[6]
On 20
th
October 2022, a site inspection was conducted with
Harmony officials, and it was observed that there was an overflow
from Harmony
into the Voelpan. This resulted in DWS issuing a Notice
of Intention to issue a Directive (pre-directive) dated 14 November
2022
to Harmony for the unauthorised discharge into Voelpan and its
possible pollution to the dam. Consequently, Harmony submitted a
representation. According to the representation submitted in response
to the Notice issued to Harmony in November 2022, they acknowledged
water having been discharged into the Voelpan from 2019 without
informing DWS or without authorisation which is a contravention
of
the National Water Act, 36 of 1998 (NWA)
[7]
This resulted in the issuance of the Directive dated 30 March 2023.
Following
receipt of the Directive, Harmony submitted a request to
DWS for extension of the deadline to comply with the Directive. DWS
rejected
the request citing the unlawful discharge into Voelpan and
flooding in which the rising water levels has caused and continues to
cause the Allanridge /Nyakallong communities and the R30 road.
[8]
Avgold owns and operates the Target Operations (“Target
Mine”)
a technologically advanced deep-level mine in the Free State,
approximately 270m Sout-West of Johannesburg.
[9]
Mining operations use both mechanised and conventional
stopping
techniques. The gold mineralisation currently exploited is contained
in a succession of Elsburg and Dreyerskuil quartz
conglomerate reefs.
Theses reefs are mined to depth of approximately 2,300 meters below
surface. Ore mined is milled and processed
at the Target plant, with
gold recovered on site by means of gold cyanide leaching. The target
mine is situated adjacent to the
Allan Ridge town and a water
resource known as “Voelpan”, nearby Nyakallong in the
Free State Province.
[10]
Following the closure of the Lorraine mine in August 1998, the
Lorraine
1 and 2 shafts were transferred to the Target Mine as target
1 and 2 shafts. As a result, although the Target Mines are only 21
years old, the infrastructure and operations have been in existence
much longer.
[11]
When the Lorraine shafts were transferred to Target Mine, Avgold was
granted an exemption in terms of section 21(a) and (b) of the Water
Act, 1956 to dispose of the purified or treated water, including
water recovered from any effluent into Voelpan.
[12]
Water use by Target Mine
Under the exemption
Avgold was authorised to discharge a maximum of 140MI/month of excess
mine water into Voelpan for evaporation.
Based on an average 30-day
month, this amounted to an average discharge of 4.6MI/day. The
motivation for granting the exemption
indicated that investigations
revealed that “the water discharged into Voelpan will not
negatively affect any groundwater
users, nor would an expected rising
of the water level affect the area surrounding the pan.”
[13] The
groundwater discharged is not a dirty by-product of mining processing
but is groundwater that is pumped out
of the mine shafts to prevent
flooding.
[14]
This exemption was recognised as an existing lawful water use when
the
National Water Act (the
NWA) came into effect and was registered
with the DWS. Avgold was permitted to continue with the existing
lawful water use in accordance
with the terms and conditions of the
exemptions until October 2004.
[15]
At the time that the exemption expired, Avgold elected not to apply
for a water use license
under NWA as it was no longer discharging
water into Voelpan as the Target Mine, at that time, was experiencing
a negative water
balance.
[16]
The negative water balance continued until approximately 2016 when
the water balance at
the Target Mine began to be water positive. At
this time, the Target Mine was able to store excess water at the
Million Gallon
Dam, with occasional, low (8MI/month) discharge into
the Voelpan.
[17]
However, since September 2021, the volume of water depositing into
the Target Mine increased
significantly due to Avgold’s mining
activities intercepting underground water and a significant increase
in rainfall, approximately
923mm, in the region compared against the
regional average of 587mm for the period November to March each year
which percolated
into Target Mines underground mining operations.
[18]
As a result, the water discharged into Voelpan doubled during the
rainy season to over
80MI per month from November 2021 to May 2022.
For the period November 2022- March 2023 the average water discharged
to the Voelpan
was 46.5MI per month. This despite the higher rainfall
during that period.
[19]
During September 2022, the DWS indicated that it received a compliant
regarding discharge
of water into Voelpan.
Was the issuing of the Directive by
the DWS an unreasonable administrative action.
[20]
On or about 17 November 2022, Avgold received from the Provincial
Head,
a Notice of Intention to issue a Directive in terms of
sections
19(3)
and
53
(1) of the NWA (the Notice).
[21]
The Notice afford Avgold an opportunity to respond to and to provide
reasons why a Directive should not be issued requiring Avgold to
cease all water uses within 14 days of the issue of the Directive.
The details of the complaint were not specified in the Notice.
[22]
The only substantive conclusion of the site inspection was that there
is no authorisation for the discharge taking place.
[23]
On the 7
th
December 2022, Avgold responded to the Notice.
The response acknowledged that there were certain water uses which
were being conducted
without a water use licence, being the discharge
of groundwater into Voelpan. The response included details of
measures taken to
date to reduce the groundwater discharge and
measures that were to be implemented in the immediate future to bring
about the cession
of ground water discharge into the Voelpan.
[24]
On 5 April 2023 Avgold received the Directive dated 30 March 2023
issued
by the Director General, Department of Water and Sanitation
(“DWS”)
, advising that Avgold’s response to
the Notice was “deemed unsatisfactory”. This Directive
requires Avgold to:
[24.1]
Stop the abovementioned water use within fourteen (14)
working days from the date of the receipt
of the
Directive.
[24.2]
Appoint a suitably qualified environmental consultant to
compile a rehabilitation plan for the affected areas within
thirty
(30) working days upon receipt of the Directive. The rehabilitation
plan must entail amongst others; the nature and extent
of the impact
of the water use activity had or may have on the water resources and
measures that will be implemented to remediate
or mitigate the
impacts with clear timeframes and descriptions of how and when each
remedial/ mitigation action will be implemented.
[24.3] The
rehabilitation plan must further indicate the cost estimate of the
entire rehabilitation
process, and
[24.4] Implement
all the recommendations contained in the rehabilitation plan and
rehabilitate the areas affected by
the water use activities within
thirty (30) working days of the Departmental Recommendation of the
Rehabilitation Plan.
[25]
On the 19 April 2023, the first applicant addressed a letter to the
DWS. The letter requested
that the Department consider amending
paragraph 1 of section II of the Directive to take effect from 1 July
2023. This was to afford
Avgold sufficient opportunity to complete
the communicated measures contained in the response to the
pre-Directive and in the letter
of 19 April 2023, which measures were
necessary to achieve zero discharge.
[26]
The letter to DWS and its attendant request were based on the
understanding
that if Avgold were to stop discharging ground water,
there would be catastrophic consequences, including the flooding and
potential
permanent closure of the mine.
[27]
On 24 April 2023, the third respondent directed a letter to the first
applicant refusing to extend the Directive until 30 June 2023.
[28]
As a consequence of the DWS refusing to countenance the applicant’s
proposal for an extension, an appeal has been launched against the
decision to issue the Directive in the form that it was.
[29]
I agree with the applicant’s submissions that, the procedure
followed
by both the second and third respondents in issuing the
Directive was procedurally unfair as it failed to indicate the
underlying
reason for which it sought to issue the Directive, namely
the increasing water level in the Voelpan and the impact on houses
adjacent
to Voelpan. As a result, the first applicant was not
afforded a reasonable opportunity to make representations to the
second respondent
which would and should have influenced the third
respondent’s decision to issue the Directive.
[30]
First applicant only became aware that the “real” reason
for the issuing of the Directive was that the rising water levels of
the Voelpan were impacting on some houses along the pan that
had been
flooded. This information was only made available to the applicant
after it sought in a letter addressed to the DWS on
the 19 April 2023
for an extension of the timelines provided in the Directive.
[31]
Importantly, it must be noted that measures were already undertaken
to
move the affected households to alternative accommodation while
the process for permanent relocation had already been substantially
advanced. As such Avgold was not afforded a fair and proper
opportunity to address the DWS as the decision maker on the true
facts
surrounding this issue and concern.
[32]
In effect, the affected houses either have already been relocated or
will soon be relocated from the one area likely to be impacted by any
rising water levels of the Voelpan. Furthermore, the measures
undertaken by the first applicant which will be completed by 30 June
2023, will ensure that no further discharge will occur and
therefore
there will be no rising in water levels of the Voelpan.
[33]
The principle of procedural fairness as inherent in the Bill of
Rights
was discussed by Chaskalson P, in KYALAMI Ridge – see in
this regard
Minister of Public Works v Kyalami Ridge Environmental
Association
2001 7 BCLR 652
CCC par 101
.
‘
Observants of the
rules of procedural fairness that an administrative functionary has
an open mind and a complete picture of the
facts and circumstances
within which the administrative action is taken. In that way the
functionary is likely to apply his or
her mind to the matter in fair
and regular manner- LAWSA Procedural Fairness para 16.’
[34]
There is no reason to discuss the Applicant’s appeal in
terms of
section 148
of the NWA in this judgement, since this has no
bearing on the suspension of the decision made. Without dwelling into
any minute
details, I ‘am also of the view that the decision to
issue the directive is not reasonable in that the impact of complying
with the Directive are not proportional to the impact caused by the
discharging water into the Voelpan as, among others;
[34.1] Complying with the Directive
will result in;
(a)
the Target Mine floods,
(b) risks to the health
and safety of the employees at the mine,
(c)
the sterilisation of minerals which are an important component
of the South African economy,
(d) the ultimate cessation of mining
activities of the Target Mine due to flooding and
(e) the retrenchment of 2225 employees
most of whom reside in the surrounding communities thus significantly
affecting the socio-economic
survival of the community.
Conclusion
[35]
In my view, this matter can be decided only on the reasons discussed
above in this
judgement.
[36]
As the applicants correctly submit, the court may enquire
whether by granting the interdict,
it is not condoning and
perpetuating unlawful conduct on the part of the first applicant. One
important such consideration is that
such an appeal by the
applicants, in terms of
section 148(2)
of NWA indicates that such an
appeal does not suspend the operation of the Directive. A further
consideration is that there is
precedent for the court to suspend the
operation of an order requiring the cessation of unlawful conduct.
This is in order to permit
the conduct to be cured and prevent
serious adverse consequences of the immediate cession of the unlawful
conduct. This approach
was followed in
Mogalakwena
Local Municipality v Provincial executive council Limpopo
& others case no: 35248/14
. See also
Gijima & and Passenger Rail Agency of
South Africa v Siyangena Technologies (pty) ltd others
(487/2021)
[2022] ZASCA 149
[2023] 1 All SA 74
(SCA);
2023 (2) SA 51
(SCA)
(1 November 2022).
[37]
This is the type of order that this court granted in June 2023.
[38]
In my view urgency arose on 24 April 2023 when the
third respondent refused to extend
the Directive until 30 June 2023.
The result of my order is that all requirements of urgency and
interdict have been met by the
applicants.
Order
[39]
Consequently the order that I made on the 26
th
of
June 2023 stands.
[39.1]
The operation of the Directive issued by the second respondent to the
first applicant dated 30 March 2023 is suspended until
and including
30 June 2023 alternatively until the appeal lodged by the applicants
to Water Tribunal under
section 148(1)(a)
and (j) of the
National
Water Act, 36 of 1998
has been finally determined, whichever occurs
first.
[39.2]
The respondents who opposed this application shall pay the costs of
this application jointly and severally, the one paying
the other/s to
be absolved, including the cost of two counsel.
J
RAULINGA
Judge
of the High Court
Gauteng
Division, Pretoria
Date
of Hearing: 10/05/2023
Judgment
delivered
27/10/2023
APPEARANCES:
For the Applicant:
Adv. M Mantrobus SC
Adv. I Nongogo
Attorney for the
Applicant:
White & Case SA
c/o Martin
Attorneys
For the Respondent:
Adv.
Ramatsekisa
Attorney for the
Respondent:
The State Attorney
Pretoria
sino noindex
make_database footer start
Similar Cases
South African Legal Council v Matsi and Another (078312/2023) [2023] ZAGPPHC 1894 (30 August 2023)
[2023] ZAGPPHC 1894High Court of South Africa (Gauteng Division, Pretoria)98% similar
L.G.N and Another v Member of the Executive Committee of Education: Gauteng Province [2023] ZAGPPHC 325; 25873/2020 (22 May 2023)
[2023] ZAGPPHC 325High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Teffo (10991/2021) [2023] ZAGPPHC 1794 (13 October 2023)
[2023] ZAGPPHC 1794High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Masingi (2023/077988) [2023] ZAGPPHC 1158 (13 September 2023)
[2023] ZAGPPHC 1158High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Legal Practice Council v Mokgobi (13023/2020) [2023] ZAGPPHC 22 (20 January 2023)
[2023] ZAGPPHC 22High Court of South Africa (Gauteng Division, Pretoria)98% similar