Case Law[2025] ZAWCHC 515South Africa
Bennet v Prima Toys and Leisure Trading (Pty) Ltd and Another (4420/2017) [2025] ZAWCHC 515 (7 November 2025)
Headnotes
Summary: Delict – Claim for damages against owner of warehouses and asbestos contractor – Contractor employed to clean warehouse roofs – Plaintiff, employed by contractor, fell through roof when he stepped on a skylight and injured himself – Duty of care and liability of defendants distinguished – Contributory negligence of plaintiff in not wearing fall arrest equipment while on the roof, considered
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2025
>>
[2025] ZAWCHC 515
|
Noteup
|
LawCite
sino index
## Bennet v Prima Toys and Leisure Trading (Pty) Ltd and Another (4420/2017) [2025] ZAWCHC 515 (7 November 2025)
Bennet v Prima Toys and Leisure Trading (Pty) Ltd and Another (4420/2017) [2025] ZAWCHC 515 (7 November 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2025_515.html
sino date 7 November 2025
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case No. 4420/2017
In
the matter between:
ALBERTINO
LORENZO BENNET
Plaintiff
And
PRIMA
TOYS AND LEISURE TRADING (PTY) LTD
First Defendant
FOCUS
ASBESTOS REMOVAL SERVICES CC
Second Defendant
Coram:
Pangarker J
Hearing
dates:
10, 12 - 13 February, 17 March and 29 April 2025
Judgment delivered: 7
November 2025
Summary:
Delict
– Claim for damages against owner of warehouses and asbestos
contractor – Contractor employed to clean warehouse roofs
–
Plaintiff, employed by contractor, fell through roof when he stepped
on a skylight and injured himself – Duty of
care and liability
of defendants distinguished – Contributory negligence of
plaintiff in not wearing fall arrest equipment
while on the roof,
considered
ORDER
a.
The defendants are liable to the plaintiff, jointly and severally,
the one paying
the other to be absolved, for 60% of his proven or
agreed damages.
b.
The defendants are liable to pay the plaintiff’s party and
party costs,
jointly and severally, the one paying the other to be
absolved (counsel’s fees on scale C).
c.
The trial on quantum is postponed
sine die
, pending the
completion of the pretrial and/or case management process on
quantum.
JUDGMENT
PANGARKER
J
Introduction
[1]
On 13 March 2014, the plaintiff, who was
working on an asbestos roof on the first defendant’s warehouse
in Epping 1, fell
through a skylight onto the concrete floor of the
warehouse. He pleads that as a consequence of the fall he sustained
various injuries
to his right elbow, right wrist, pelvis and
lacerations to the face and that as a result of these injuries, he
suffered damages
comprising past and future medical expenses and
general damages, totalling R1 640 000. In view of the
issues in the trial,
it is necessary to set out the pleadings in some
detail. For convenience sake, Prima Toys is referred to as “PT”
and
Focus Asbestos as “FA” and the plaintiff’s fall
through the skylight is referred to as “the incident”.
The
pleadings
[2]
On 9 March 2017, the plaintiff caused a Summons to be issued against
both defendants,
who are sued jointly and severally liable. The
salient averments in his Amended Particulars of Claim are summarised
in the following
paragraphs.
At all material times, the
plaintiff was employed by Johan Fourie who was sub-contracted by the
second defendant, Focus Asbestos
Removal Services (CC) (FA) as a
mandatary as defined in the Occupational Health and Safety Act, 85 of
1993 (OHS Act)
[3]
On
13 March 2017, Mr Fourie instructed him to climb onto the roof of the
plaintiff’s warehouse to paint a section of the asbestos
roof.
The plaintiff, in carrying out the instruction, stepped unknowingly
onto a skylight obscured by dirt and hence fell through
it, onto the
concrete ground below.
[4]
The first defendant, Prima Toys and Leisure Trading (Pty) Ltd (PT)
and/or the second
defendant allowed the plaintiff to work in an
elevated position on the roof when they knew that such work could not
be performed
safely unless the plaintiff had a safety harness and/or
fall arrest lanyard as required by Regulation 8 of the Construction
Regulations
[1]
,
read with Regulations 4, 5 and 7 thereof and
Regulations 6
of the
General Safety Regulations of the
Act. The plaintiff pleads that PT
and/or FA and their employees and/or Mr Fourie (who were acting in
the course and scope of their
employment with the defendants), were
negligent in one or more ways in that they:
8.1
Failed to prepare health
and safety specifications for
the work to be performed
on the
warehouse roof of First Defendant as required by Regulations 4 and 5
of
the Constructions Regulations promulgated under the Act;
8.2
Failed to discuss and negotiate the content of the health and safety
plan contemplated in Regulations 5(1) of the
Act and thereafter to
finally approve the health and safety plan for implementation as
required by Regulation 4(2) of the Construction
Regulations;
8.3
Failed to take reasonable steps to present a suitable health and
safety plan as required by Regulation 5(1)
of the Construction
Regulations and that such plan would be implemented in terms of
Regulation 4(1) (d) of the Construction Regulations
before the work
commenced;
8.4
Failed to stop Plaintiff from executing the work when they knew or
ought to have known that the work was not
being carried out in
accordance with a suitable health and safety plan and the failure to
do so posed a threat to the health and
safety of the Plaintiff as
they were required to do in terms of
Regulation
4(1)(e) read with Regulation 5(1) of the Construction Regulations.
[2]
[5]
It is thus further pleaded that by virtue of
the above, PT and/or FA were guilty of wrongful conduct. They
breached their duty towards
the plaintiff by failing to ensure that
he was not exposed to hazard, when they knew or ought to have known
that it was dangerous
to allow him to work on the roof without the
use of fall arrest equipment to prevent him from falling.
[6]
Furthermore, PT and/or FA failed to take any adequate steps to
prevent the plaintiff
from falling through the roof when they could
and should have done so. As a result of the injuries which he
sustained, the plaintiff
was hospitalized, received medical
treatment, endured pain and suffering and suffered a loss of earning
capacity.
[7]
In its further Amended Plea, PT admits that the plaintiff was working
at its Epping
1 warehouse on 13 March 2014 and that he fell from a
height onto the concrete floor. PT pleads that it has no knowledge of
the
circumstances surrounding the plaintiff’s fall, nor of the
allegations and puts the plaintiff to the proof of his allegations.
In response to the averments in the Amended Particulars of Claim
regarding the provision of adequate fall protection equipment
[3]
,
PT pleads as follows:
7.1A
In amplification of the aforesaid denial, but without derogating from
the generality thereof, the first defendant
pleads as follows:
7.1A.1
Only in the event that it is sought to be affirmatively alleged that
the first defendant and/or second
defendant and/or Johan Fourie,
being obliged to do so, failed to provide the plaintiff with adequate
fall protection equipment,
such allegation is denied.
7.1A.2
On the day in question the plaintiff received from or on behalf of
Johan Fourie adequate fall protection
equipment which he either
failed to wear or otherwise removed prior to his fall.
7.1A.3
The plaintiff’s aforesaid conduct
(a)
Was the proximate cause of his fall,
which broke the causal nexus between any wrongful and negligent
conduct ascribed to the first
defendant in the plaintiff’s
particulars of claim (none of which is admitted) and the plaintiff’s
fall
(b)
Constituted a novus actua
interveniens, which broke the causal nexus between any wrongful and
negligent conduct ascribed to the
first defendant in the plaintiff’s
particulars of claim (none of which is admitted) and the plaintiff’s
fall, and/or
(c)
Constituted a voluntary assumption by
the plaintiff, who at all material times knew of and fully
appreciated the danger, absent
the use of adequate fall protection
equipment, of falling from an elevated position on the roof of the
warehouse and injuring himself
on the floor below, of the risk of so
falling.
7.2 In
further amplification of the aforesaid denial, but without
derogating from the generality thereof, the
first defendant
pleads that it had entered into a contract with the second defendant
in terms whereof the second defendant executed
certain specialised
works at the premises of the first defendant, which works were
executed under the exclusive control of the
second defendant in its
capacity as an independent contractor.
7.3
First and second defendants had entered into a written agreement on
occupational health and safety in accordance
with the provisions of
Section 37(2)
of the
Occupational Health and Safety Act 85 of 1993
in
terms whereof the parties agreed to arrangements and procedures
between them to ensure compliance by the Second defendant in
its
capacity as mandatory with the provisions of the aforementioned act.
A copy of the agreement is annexed hereto, marked annexures
PT1 and
the first defendant prays that it shall please this Honorable court
to incorporate the agreement herein and read the same
herewith.
[8]
Furthermore, the further Amended Plea denies that PT was wrongful but
if the Court
should find that its conduct was wrongful, then in that
event, such wrongful and negligent conduct did not cause or
contribute
to the fall. In the alternative, and only in the event
that it is found that PT was wrongful and negligent and that such
conduct
contributed to the plaintiff’s fall, PT pleads that FA
was contributorily negligent as pleaded in paragraphs 8.1 to 8.4 of
the Amended Particulars of Claim and the plaintiff was contributorily
negligent in the following respect:
8.3.1 He
had, without the knowledge of the second defendant or any of its
representatives, including the mandatory,
removed his personal
protective equipment and safety harness.
8.3.2 He had failed to
keep a proper lookout and in so doing executed a dangerous maneuver
when he stepped onto a skylight.
8.3.3 He
failed to have due regard for his own safety.
8.3.4 He
failed to have regard to issues pertaining to safety and warnings
imparted to him during toolbox talks.
8.3.5 He
failed to avoid the incident when by the exercise of reasonable care
he could and should have done so.
[9]
In respect of the plaintiff’s further
averments as pleaded, PT denies the allegations and puts the
plaintiff to the proof
thereof
The
second defendant
[10]
FA
was legally represented and delivered a Plea
in early 2018. Subsequently in May 2020, its legal representatives
withdrew as attorneys
of record. During pre-trial proceedings, and
while FA still participated in the action, the parties had agreed
that the trial should
proceed on the merits first.
[11]
In the 29 May 2020 pre-trial, it was noted that the correspondent
attorney on behalf of FA withdrew
and that despite attempts by the
plaintiff’s legal representative to enquire about FA’s
position, such attempts proved
unsuccessful. Several pre-trials
followed, and on 7 December 2020 Kusevitsky J granted an order
whereby FA was ordered to furnish
a reply to the plaintiff’s
Rule 35(3) notice within 10 days of service of the order, failing
which the plaintiff was entitled
to apply on the same papers, duly
supplemented, that FA’s defence be dismissed and judgment be
entered in the plaintiff’s
favour. It is evident from the Court
file and its contents that a subsequent application for a dismissal
of the defence in terms
of the order never occurred.
[12]
In a later pre-trial conference on 3 March 2022, it was recorded that
FA had ceased operating
approximately three years prior, that it had
no assets and was in the process of de-registering, hence no further
application to
dismiss its defence would follow. FA also filed a
statement which does not take the form of a Plea. The statement
addressed by
Gerald Pietersen, the member of FA, and dated 29 October
2020, indicates,
inter alia,
that the close corporation ceased
trading two/three years prior and toolbox records from the day of the
incident (the plaintiff’s
fall) were held on site in a safety
file at PT’s warehouse, which was standard practice.
The
trial
[13]
The trial proceeded on the merits. The
plaintiff and Dr Willem Johannes du Toit, an engineer, testified. On
behalf of PT, only Michael
Webster testified, and as anticipated, FA
did not participate in the trial.
The
plaintiff
[14]
The plaintiff testified that he was working for FA for three months
prior to the incident, employed
to paint roofs and remove asbestos,
and was working at the PT site for about two weeks prior to the
incident occurring. He previously
worked at the Paarden Eiland and I
& J sites where he assisted with asbestos removal for FA. At the
I&J project, he worked
at a height of approximately three
storeys.
[15]
The plaintiff was living in Malmesbury and he secured the job with FA
through friends living
in the same area. Transport was arranged from
Malmesbury to PT’s premises and back every working day, and he
explained that
they were about eight to nine employees who worked on
the project.
[16]
On the I&J project, the workers were required to wear a safety
harness when working on the
roof. The harness consisted of straps
which could be secured to a safety line which was anchored or secured
to the building, thus
if the worker fell from the roof, his fall
would be arrested, leaving him hanging in mid-air. A similar safety
protocol was followed
at the Paarden Eiland site.
[17]
At the PT site, which forms the subject of the trial, the workers
(including the plaintiff) were
not required to clean asbestos from
the roofs. His job was to clean fungus from the asbestos roofs and
then paint the roofs. On
the first day, the plaintiff and his
colleagues arrived via bakkie at around 07h00 and they received a
safety briefing which is
referred to as a “toolbox talk”
provided by one Johan Fourie. The purpose of the toolbox talk was to
inform the workers
about their boots, harnesses and safety equipment
which they were required to wear.
[18]
Mr Fourie was concerned about the health and safety of the workers
and gave the only toolbox
chat and demonstrated to them how to wear
the harnesses and clip them onto the safety lines. In
cross-examination, the plaintiff
clarified that during the toolbox
demonstration, there was no safety line as the talk occurred in a
room. The plaintiff nonetheless
knew how to use the hook on the
safety line when wearing a harness as he did so during the I&J
project.
[19]
The plaintiff expected that there would be a safety line on the
building with which he and his
colleagues could use the harnesses but
there were none. He agreed with the statement from PT’s counsel
that it would be absurd
to provide the workers with the safety gear
and harnesses yet not provide a safety line onto which these
harnesses could be attached.
[20]
Providing more detail regarding the safety gear/equipment, the
plaintiff explained that it comprised
of white masks, asbestos safety
hazmat suits and harnesses, and the equipment was stored on site. The
workers would be provided
with a new suit (and presumably masks)
every day and were informed by Mr Fourie that they were always
required to wear the harnesses.
The plaintiff testified that when he
climbed onto the roof he did not clip his harness onto any safety
line because there was no
line available. He explained, when
questioned by his counsel as to the reason why they (the workers)
wore the harnesses when there
was no safety line to which it could be
hooked, that they wore the harness “
so
that we could just have it on”
.
[4]
[21]
The plaintiff was not taken onto the roof to show/demonstrate to him
what needed to be done.
The job entailed scrubbing the roofs with a
wire brush and then painting it. The plaintiff made it clear that he
knew what needed
to be done/what the job entailed because they had
done this kind of work before on other projects.
[22]
When they walked out on site in the morning, the workers wore the
safety harnesses, and to the
best of his recollection, nobody from PT
was present to check on the work which they were doing. On 13 March
2014, the plaintiff
was not wearing a harness because the harnesses
were collected by FA from the site for a job at the harbour, two days
prior. The
plaintiff saw the removal of the harnesses.
[23]
On the day of the incident, the workers went up onto the roof and the
incident/fall occurred
before 10h00. Two of the workers went down the
stairs and the plaintiff returned with a half-full bucket of paint up
the side-stairs
of the building in order to access the roof. He
walked across the roof along the heads and had not walked across that
area of the
roof in the two weeks prior to the incident. As he walked
on the roof in the building marked “X” on Exhibit B, and
put his foot down, his foot “
vanished”
and he fell
through a skylight to the concrete ground below and suffered various
injuries: a cracked pelvis; his elbow and wrist
were injured and he
had knocked his head lightly on the ground. The plaintiff spent a
month in hospital and was not contacted by
PT, Mr Fourie or Mr
Pietersen after his fall. He was aware that someone else fell through
the roof of the building some time prior
to his incident.
[24]
The plaintiff denied that it was his fault that he fell through the
skylight and also denied
PT’s averment that he had not paid
attention to the toolbox chat. Those skylights that had already been
cleaned were not
painted over, and the plaintiff remained steadfast
on this point.
[25]
The plaintiff also denied that he received his fall protection
equipment, including a harness,
from Mr Fourie on the day of the
incident. He had no idea where PT came upon the story that he had
removed his harness prior to
the fall. He reiterated that there was
no safety line attached to the building during the two weeks when he
worked on the roofs.
[26]
The workers spoke amongst each other regarding the fact that they
were unhappy/uncomfortable
about wearing a harness when there was no
safety line to attach it to. In cross-examination, the plaintiff
agreed with counsel
for PT that the harnesses were useless in the
circumstance where there was no safety line to attach them to. They
were unhappy
about this but did not complain to Mr Fourie because
they were simply workers and if there was no work, they would have to
go home.
The foreman was one Recardo, a friend of the plaintiff. The
workers spoke about the lack of a safety line but did not ask Recardo
to take up the issue with FA, at the same time, the plaintiff
testified that he was unaware if Recardo had taken up the issue with
FA.
[27]
Furthermore, the plaintiff denied that it was his fault that he fell
through the skylight because
he had stepped on it. In
cross-examination, he disagreed with PT’s version that point
“Y” on Exhibit B marked
the place where he had fallen
through the skylight. The plaintiff also clarified that point “Z”,
which was diagonally
opposite “X”, was the point where
the workers commenced cleaning and painting the roof after the
toolbox talk. This
area did not have skylights and there were no
safety lines in area “Z”.
[28]
The plaintiff agreed with the first defendant’s counsel that
the harnesses were useless.
The absence of the safety line was not
reported to anyone because they were just workers. He denied that he
could walk on the roof
as allowed by the safety ropes, which is the
version put to him by PT’s counsel.
[29]
The plaintiff also testified that four workers worked on one roof and
the other four co-workers,
were on another roof. The plaintiff did
not have knowledge as to whether there were safety lines/cables in
areas on a roof where
he did not work.
[30]
The plaintiff did not see Mr Webster, PT’s only witness, on the
scene after his fall, and
stated that he also did not see the latter
before the incident occurred. The plaintiff confirmed his version in
chief that on the
day of the fall, he was not wearing the harness
because there were none provided, and the eight workers (including
him) went onto
the roof.
[31]
In re-examination, the plaintiff maintained that the cleaning process
started on point “Z”
[5]
.
The plaintiff was on the roof for three to five days before he fell
and no scaffolding was provided to ascend and descend the
roof.
Dr
Willem du Toit, plaintiff’s expert
[32]
Dr du Toit, an engineer, provided a report dated 15 September 2020
wherein he offered his expert
opinion on the cause of the incident
against the backdrop of the Health and Safety legislation and the
responsibilities and duties
of the parties and Mr Fourie. Dr du
Toit’s credentials and experience as set out in his
curriculum
vitae
were not in issue.
[33]
Two import aspects regarding Dr du Toit’s evidence are
highlighted at the outset of the
summary of his testimony: firstly,
he reported and was of the view that Mr Fourie, as sub-contractor to
FA, was the plaintiff’s
employer. The evidence of the plaintiff
clearly does not support this view and it was accepted at the trial
that FA was his employer.
Secondly, the 2014 Construction Regulations
did not apply to the defendants; rather, it was accepted that the
2003 Construction
Regulations applied. Unless the contrary is
indicated, the reference to “the Regulations” is a
reference to the 2003
Construction Regulations.
[34]
In the matter at hand, PT was the client and FA was the principal
contractor. The relationship
between the contractor and principal
contractor was governed by Regulation 5 which indicates each party’s
duties. Regulation
4 concerns the client’s duties and
obligations. Dr du Toit explained that PT was required to prepare a
baseline risk assessment
for the intended construction work project
to the roofs of the warehouses but failed to do so. In his report he
found that the
methods used to mitigate risks (such as the plaintiff
working on a roof without a safety harness connected to a safety
line) were
not employed on site.
[35]
In respect of the mandatary contract concluded between the
defendants, PT1, Dr du Toit testified
that it was outdated and did
not comply with applicable Regulations at the time.
[36]
Insofar as FA’s first quotation
[6]
to
PT, the asbestos works would be in terms of asbestos Regulations but
there was no reference to working at heights. According
to the
witness, a fall prevention plan and fall arrest equipment were
needed. As to the scope of work to be performed by
FA, guidance
was provided by Mr Webster of PT and information was supplied by the
AIA, Asbestos Inspection Authority
[7]
.
[37]
Dr du Toit was questioned further about FA’s scope of work
[8]
and
was of the view that FA’s second quote contained an asbestos
plan. Furthermore, he was of the view that there was an obligation
on
PT as the client to identify anything that posed a risk on site and
he reiterated that there was no fall arrest plan when working
at
heights.
[38]
In cross-examination, Dr du Toit agreed with the statement that it
was expected that there would
have been a safety harness hooked to a
safety rope. He had visited the site. With reference to the mandatary
agreement in terms
of section 37(2) of the OHS, he agreed that the
client was concerned about safety,
[9]
but
his view was that PT did not quite get it right.
[39]
Dr du Toit also agreed that when the incident occurred on 13 March
2014, the project had been
up and running for 10 weeks already. He
stated that the Regulations applicable were the 2003 Construction
Regulations and that
at the time of commencement of the project,
there was no obligation on PT to prepare a baseline risk assessment,
because Regulation
5(1) (a) did not exist in the 2003
Regulations
[10]
.
[40]
Additionally, Dr du Toit did not verify the place where the plaintiff
fell through the roof and
no specific place was pointed out to him.
He confirmed that it was not reported to him that according to the
plaintiff, there were
no safety ropes attached to the roof. Had he
known this, he would have included it in his report.
[41]
Furthermore, had he been informed that the PPE equipment (including
harnesses) were removed from
site two days before the incident, as
testified by the plaintiff, he would have referred thereto in his
report. His testimony was
that in those circumstances, “
they”
should have ceased work immediately.
[42]
Dr du Toit confirmed/agreed that PT was not in the business of roof
construction. According to
his professional opinion, if there was a
broken roof sheet and PT was not competent enough in construction
then they should have
appointed an expert in construction to attend
to the damaged roof sheets. He also denied that Ms Cecilia Keet of
the Occupational
Hygiene Monitoring Services CC was the kind of
expert he referred to as she attended to an asbestos risk
assessment
[11]
.
He testified further that if the risk of falling from height was
apparent to the contractor, then it would also have been apparent
to
PT.
[43]
From the AIA Report, Dr du Toit could not infer that a health and
safety report was received.
He had no issue with the asbestos removal
procedures and when questioned about the AIA report, clarified that
it related to asbestos
removal, not construction and was not a health
and safety plan. In respect of the content of a health and safety
plan, the witness
referred in some detail to Regulation 7.
[44]
Furthermore, as PT had failed to discuss and negotiate a health and
safety plan with FA as required
by Regulation 4(2), it had not
absolved PT from complying with Regulation 5(1) in that as client, it
was required to have its own
health and safety plan. Dr du Toit
explained that the contractor, FA, would have had to be given PT’s
health and safety specifications
in accordance with Regulation 5(1)
in order to provide its health and safety plan as the contractor
[12]
.
He agreed that it was FA’s obligation to supervise construction
work and appoint an employee as construction supervisor
as required
by Regulation 6(1).
[45]
On the facts, Ricardo was the foreman of FA, who should have seen
that there were no safety ropes/lines
attached to the roof, and which
led to the plaintiff’s fall. The witness also blamed the
plaintiff for failing to refuse
to work without a harness and added
that the appointment of a construction safety officer in terms of
Regulation 6(6) was the responsibility
of FA and not PT, the client.
He stated that if there were hidden risks, and such officer did
nothing to monitor the site and keep
documentation, then the
responsibility would be that of FA.
[46]
Dr du Toit confirmed that FA was also required to comply with
Regulation 7(4) which called for
the appointment of competent person
to inform, instruct and train workers regarding any hazard and
procedures before work commenced.
It was FA’s responsibility to
have a risk assessment done by a competent person and the failure of
FA to do so, was not to
be blamed on PT. Where the workers (such as
plaintiff) were not adequately trained by a competent person,
[13]
PT
cannot be blamed as the responsibility lay with FA.
[47]
The contractor was required in terms of Regulation 8 to have a fall
protection plan implemented
and the provision of PPE was the
responsibility of FA. Despite efforts to distance PT from Regulation
8, which was clearly the
obligation of FA, PT was required to discuss
a health and safety plan, which included fall protection.
[48]
It was put to the witness that PT provided the AIA report to FA and
regarded it as a health and
safety plan, but Dr du Toit remained
steadfast that such report was in terms of asbestos removal. The
failure to comply with Regulation
8(4) would be that of the
contractor.
[49]
When pressed further Dr du Toit was adamant that he saw no fall
protection plan in terms of Regulation
8(3) and if a proper fall
protection plan had been implemented, the fall would not have
occurred. Dr du Toit could not comment
on whether there was a health
and safety file as he never saw one. As far as the skylights were
concerned, he testified that written
indication should have been
given of the risk associated with skylights
[14]
.
[50]
In re-examination, Dr du Toit stated that Mr Webster, if he walked
around the site and observed
that the workers were not wearing hazmat
suits and masks, was obliged to report it to the contractor.
[15]
Furthermore,
the client was required to stop the contractor from executing
construction work if it was observed that the latter
was not
complying with its own health and safety plan referred to in
Regulation 5(1). He also agreed that fungal growth occurs
on
skylights, and depending on where in the warehouse it occurred, one
may misjudge oneself in that the roof sheets and skylights
may look
similar.
Michael
Webster
[51]
Prima Toys at one stage had several factories dealing with the
manufacturing of toys but due
to the advent of Chinese imported toys,
the factories were forced to close. At the time of the incident, the
business was confined
to warehousing and distribution of toys. Mr
Webster had been employed by PT for 25 years and was retired and
residing in Zimbabwe.
At the time of the incident, he was the loss
control manager and attended to building maintenance.
[52]
On behalf of PT, Mr Webster commissioned Occupational Hygiene
Monitoring Services CC
[16]
to
prepare an asbestos risk assessment in respect of the asbestos roofs
on the PT site. He made enquiries regarding repairs and
cleaning to
the asbestos roofs and was provided with the names of three
companies. Ms Keet’s AIA report was provided to the
competing
companies.
[53]
Focus Asbestos was represented by Gerald Pietersen who visited the PT
site for purposes of a
walking inspection. Mr Webster and Mr
Pietersen conducted an inspection of the premises for one and a half
hours, whereafter the
latter was left on his own to freely inspect
the buildings. Mr Webster testified that he presumed Mr Pietersen
took measurements
and looked at the roofs of the warehouses.
[54]
According to the witness, both men entered the warehouse building
where the plaintiff stated
he had fallen through a skylight.
According to Mr Webster, the incident occurred at point “Y”
[17]
.
Both men looked up at the roof from their vantage positions inside
the warehouse and the roof seemed normal and the skylights
were
clear.
[55]
Mr Webster testified that the skylights in the building in question
were not manufactured of
fibreglass, rather of polycarbonate
[18]
,
and the result was that they were a lot cleaner and clearer than in
the old buildings. According to Mr Webster, the older warehouse
buildings contained fibreglass skylights. After the inspection on 2
June 2012, FA provided a quotation to PT
[19]
.
The scope of the work to be performed by FA as per the June 2012
quotation, included the replacement of dirty fibreglass with
polycarbonate sheets instead.
[56]
Mr Webster had attended other sites where FA performed asbestos
roofing work in order to inspect
their standard of work, and
satisfied himself with the standard of workmanship. Accordingly, he
recommended FA to his supervisor,
after a discussion about the
quotes. Mr Webster was satisfied that FA was a fully certified
asbestos removal business and were
one of the businesses recommended
by Ms Keet who was registered as an asbestos expert with the
Department of Labour.
[57]
In respect of the mandatary agreement, PT1, Mr Webster testified that
FA drafted the contract
which was on PT’s letterhead. Changes
were made thereto and it was signed on 9 April 2013, but work had
already commenced
on the site prior to signature. Mr Webster was
referred to various clauses in the mandatary agreement, all of which
he confirmed.
[20]
The
purpose of the agreement in respect of FA’s employees was to
ensure that the contractor complied with the OHS Act.
[58]
Mr Webster had no knowledge of the 2003 and 2014 Construction
Regulations when concluding the
contract and had only become aware of
them during the trial. He confirmed the June 2012 quote provided by
FA and explained that
a decontamination chamber for the workers’
removal of PPE equipment was built by FA and provision made,
inter
alia,
for
a lock-up garage for storing PPE.
[21]
[59]
Mr Webster signed the mandatary contract on behalf of PT. The terms
were retyped by PT, and despite
some confusion, it was accepted that
FA was the mandatary and PT was the client/principal. On the date the
mandatary agreement
was signed, FA rendered an invoice to PT for a
first payment by PT and payment was subsequently made.
[60]
After FA commenced work on the site, Mr Webster would walk around the
PT site/premises at least
once a day. From ground level, he saw FA
staff on the roof watering, scrubbing and performing various tasks.
As the project progressed,
every three to four weeks, he would climb
up a ladder to roof height and inspect whether the workers were
performing the work they
were required to do.
[61]
He recalled what he observed: the FA workers were dressed in hazmat
suits and masks, wearing
the harnesses which had clasps hooked onto
safety lines which stretched across the building. He explained that
when the workers
arrived in the morning, they donned the hazmat
suits, masks and harnesses before being admitted to the area where
they were required
to work. Mr Webster did not know how the safety
lines were attached to the roofs. He understood that the purpose of
the safety
harness was to allow the workers to move along the roofs.
However, he admitted that there were not safety lines across the
roofs
of the entire complex as shown on Exhibit B.
[62]
Mr Webster also denied the plaintiff’s version that there were
no safety lines and harnesses
and confirmed that there would be no
point having a safety harness if there were no safety lines attached
across the roofs. He
also confirmed that he did not climb up a ladder
to view the roof at point “Y” so did not see if there
were (or were
not) safety lines. He was adamant that point “Y”
on the building complex was where the incident had occurred.
[63]
After being alerted to the incident, Mr Webster proceeded to point
“Y” and found
the plaintiff lying on the ground inside
the warehouse. He called for an ambulance and testified that a first
aider
[22]
attended
to him, but the plaintiff’s injuries were beyond her expertise.
According to Mr Webster, the plaintiff was not wearing
a mask, hazmat
suit, nor a safety harness and was dressed in normal clothes. The
foreman, who himself was wearing a harness, was
summoned.
[64]
Mr Webster could not address the plaintiff’s testimony that the
PPE equipment suits and
harnesses were removed by FA two days prior
to his fall. He stated that had he been informed thereof, he would
have spoken to Mr
Pietersen or Mr Fourie and halted the work until
the equipment was returned and a safe working environment/ premises
was restored.
Common sense informed him that if you work at heights,
you take certain precautions.
[65]
As for the skylights, he testified that FA had marked off the
skylights with sticky tape across
the skylight. Mr Webster testified
that from underneath
[23]
,
meaning inside the warehouse building, he could see fungal growth on
the skylights and they (the skylights) were lighter in colour
than
the roofs. He admitted that he was not up on the roofs so could not
comment on the plaintiff’s statement that the colour
of the
skylights and roofs were similar. Notwithstanding the latter
testimony, Mr Webster stated that one could not be mistaken
as the
polycarbonate skylights were distinguishable from the roof.
[66]
Mr Webster testified that Mr Pietersen conveyed to him that he would
report the incident as he/FA
was the plaintiff’s employer. Mr
Webster considered that in terms of the mandatary agreement, the OHS
Act would be complied
with.
[67]
During cross-examination, Mr Webster, when questioned about whether
PT had a document in place
in respect of the health and safety
requirements, testified that he did not recall but that PT had
complied with the OHS Act. With
regard to the mandatary agreement, Mr
Webster could not recall whether PT/he were satisfied as to the
budget for health and safety
measures for the duration of the
contract.
[24]
He
could not dispute the plaintiff’s testimony that on some days,
the workers did not have hazmat suits and PPE equipment
though he was
not aware of this.
[68]
Mr Webster explained that initially there was a safety committee on
the premises, but conceded
that the safety and condition of PT’s
roofs was not really a concern of the safety committee which dealt
mainly with “housekeeping”
issues. Furthermore, he was
unable to confirm that the clauses in PT1, were in conformity with
the OHS Act. The introduction of
PT1 was read out to Mr Webster
[25]
and
he was asked about the company’s (PT) health and safety
requirements and rules and regulations and admitted that he was
unsure whether PT had a document setting out the company’s
health and safety requirements.
[69]
Furthermore, Mr Webster did not satisfy himself as to whether the
mandatary had made adequate
financial provision for health and
safety, when he forwarded FA’s quote to PT’s chief
executive officer for approval.
With reference to PT1, Mr Webster
conceded that clause 3 dealing with “warranty of compliance”
was confusing and that
PT had not checked up on FA and/or Mr
Pietersen prior to accepting the quote. He assumed that FA had
performed the kind of work
agreed to many times and that “
they
had everything in order”
[26]
.
[70]
After the plaintiff’s fall, Mr Webster spoke to Recardo (the
foreman) and thereafter to
Mr Pietersen. When he reported to Recardo
and Mr Fourie that the plaintiff was not wearing a hazmat suit and
harness, their response
was that the plaintiff should not have been
on the roof. He testified that Recardo, who came upon the plaintiff
in the warehouse
when alerted to the incident, was wearing a harness.
Mr Webster was unaware whether Mr Petersen reported the plaintiff’s
fall to the factory inspector or whether FA’s investors paid
out on the insurance.
[27]
[71]
Notwithstanding his response that he could not comment on the
plaintiff’s version that
the suits and harnesses were removed
two days prior, Mr Webster’s view was that he found it hard to
believe that the plaintiff
would be happy to go onto the roof without
a harness. He understood though that, as counsel put it, “
the
average man on the side of the road needs to earn his crust”
[28]
.
[72]
Nonetheless, the witness’s view was that as the plaintiff had
worked with FA for quite
some time prior to the fall, he was/would be
aware of FA’s rules and regulations. Mr Webster conceded that
FA’s rules
and regulations (regarding employees, health and
safety) were unknown. As far as supervision, discipline and reporting
were concerned,
[29]
he
presumed the foreman of FA would be responsible therefor.
[73]
Mr Webster and Mr Pietersen signed PT1 on behalf of the respective
defendants, and as for the
quotations, Mr Webster could not explain
why FA’s two quotes were almost a year apart. He understood
that PT was being quoted
for the “
removal
of old dirty fibreglass and yellowed plastic sheets and fitting of
new polycarbonate sheets in their place”.
[30]
The
quotation was for the entire roof area of PT
[31]
.
[74]
According to Mr Webster, Mr Pietersen inspected the roofs of the
buildings shown as situated
between points “A” and “Y”
on Exhibit B. When asked about the “
roof
cleaning”
description
in PT1
[32]
,
he stated that neither he nor the CEO of PT knew what the company’s
working at heights regulations were.
[75]
In respect of the AIA Report, Mr Webster agreed that the report does
not refer to working at
heights nor regulations related thereto.
Furthermore, he agreed with the plaintiff’s counsel’s
statement that the purpose
of such report related to the cleaning and
removal of asbestos.
[76]
With reference to the two quotes, it was put to Mr Webster that it
was unclear why FA quoted
twice: in quote 2 of 29 July 2012,
additional amounts for bird proofing and repairs to vents were
quoted, yet these items/work
were quoted for in the 2 June 2012
quote
[33]
.
Mr Webster was unclear why this was the case.
[77]
With regard to the skylights, and the two quotes, Mr Webster was
unable to indicate when it came
to FA’s attention that it (FA)
were not only removing old, dirty fibreglass and yellowed plastic
sheets and replacing these
with polycarbonate sheeting (quote 1) but
were also to remove and replace broken and damaged fibreglass and
plastic sheets (quote
2).
[78]
Mr Webster stated that he was not initially aware that there were
broken and damaged fibreglass
and plastic sheets on the roofs and
admitted during cross examination that neither he nor PT brought any
broken and damaged fibreglass
or plastic sheet skylights to anyone’s
attention. He clarified that on the day of his visit prior to quoting
for the work,
he showed Mr Pietersen the roofs then left him to do
his assessment.
[79]
Various Regulations were put to Mr Webster and are not repeated in
the judgment for the sake
of brevity. Mr Webster admitted that PT did
not prepare the health and safety specification for the work
[34]
because
PT relied on FA to “
do
a job in terms of whatever regulations were enforceable”
[35]
.
He explained further that PT relied on the fact that FA were a
reputable construction company and had knowledge of the legislation
and relied on FA in respect of issues related to the roofs such as
construction issues and condition.
[80]
In respect of Regulation 4(1)(b)
[36]
,
Mr Webster indicated that the only information brought to the
attention of FA was the AIA report and he admitted that the latter
report did not refer to broken or damaged skylights, not working at
heights and the requirements applicable thereto. Furthermore,
with
reference to Regulation 4(1)(d), Mr Webster also admitted that
monthly audits to ensure that PT’s health and safety
plan were
implemented, were not done officially. There was only unofficial
contact with FA as to the progress of the project.
[81]
In respect of Regulation 5(1) he stated that PT was not provided with
a health and safety plan
by FA. Furthermore, PT did not comply with
Regulation 4(2) in that there was no negotiation with FA regarding
the contents of the
health and safety plan contemplated in Regulation
5(1), nor was there compliance with Regulation 4(3).
[82]
In respect of Regulation 4(4), Mr Webster admitted that he did not
speak to any references nor
previous clients of FA prior to
contracting with the latter. He concluded that FA was a reputable
firm in view of his reliance
on Ms Keet’s reference and the
standard of their work on other projects. Furthermore, Mr Webster
candidly stated that the
Construction Regulations were not complied
with because he was unaware of them at the time and had relied upon
the AIA Report and
FA’s knowledge of the Regulations and their
guidance.
[83]
When pressed, he admitted/conceded that he/PT assumed that FA knew
the Regulations. He agreed
with the plaintiff’s counsel that
the agreement, PT1, did not deal with the Regulations referred to
earlier. He also did
not disagree with the statement that in view of
its failure to address and include the Regulations, therefore the
mandatary agreement
was not in compliance with the OHS Act. Mr
Webster testified that he was unaware at the time, of PT’s
statutory obligations
and relied on FA which was contracted to carry
out a job.
[84]
He also admitted that nobody at PT in the 25 years that Mr Webster
was employed there, had received
training in health and safety. The
reason for obtaining quotes for asbestos removal on roofs was because
he became aware that legislation
regarding asbestos and their risks
had changed and thus he alerted the CEO thereto, and he was given the
green light to source
quotes and obtain an AIA report. He frankly
admitted that PT did not undergo any “conscientizing”
about health and
safety.
[85]
PT was able to afford to comply with the health and safety
Regulations at the time but nobody
at PT ensured that the contract
with FA complied with the Regulations. Initially, when FA started,
Johan Fourie represented the
latter, but Mr Webster was introduced to
the foreman Recardo, who would deal with day-to-day issues. He
confirmed that there were
eight to nine workers and he had on an
occasion seen a worker without a hooked-up harness and took it up
with Recardo which resulted
in the situation being rectified
immediately.
[86]
According to Mr Webster, it was FA’s responsibility to secure
safety lines to the buildings
and to ensure a safe working
environment on the roof. Mr Webster confirmed under cross examination
that he did not inspect the
roof where the plaintiff stated he fell
through nor check to see if there was a safety line attached to that
building
[37]
.
[87]
Mr Webster also conceded that it was never put to Dr du Toit that
there was a hazard tape to
denote the skylights. Mr Webster saw the
tape on the area of the two buildings opposite the building marked
“X”, which
was not where the plaintiff stated that he
fell through the skylight.
[88]
In re-examination, Mr Webster testified that he never felt it
necessary to inform Mr Pietersen
that what he was looking up at, were
skylights and that there was thus a fall hazard there. He assumed
that Mr Pietersen, in his
experience in working at heights, would
appreciate the heights problem, but admitted, that he had made such
assumption as to FA’s
expertise and knowledge.
Material
issues in the matter
[89]
One of the challenges in this matter is that the main role players in
the parties’ versions
were never called as witnesses: Recardo
the foreman, Mr Fourie the supervisor and the first aider on the
scene after the plaintiff’s
fall. I appreciate that Recardo and
Mr Fourie would potentially have been witnesses for the second
defendant, FA, and could have
been subpoenaed, but the absence of
possible corroboration and clarity on certain alleged facts regarding
the fall protection equipment
and safety lines, has been problematic.
[90]
Another difficulty is that the contractor, FA, never participated in
the trial, which created
a situation where the question of the supply
or removal of PPE/harnesses, and the absence or not of safety lines
on the building
where the plaintiff fell through, all turns on what
the most probable version was. This is not a matter where it can be
said that
any of the three witnesses in the trial – the
plaintiff, Dr du Toit and Mr Webster - were bad or evasive witnesses.
The fact
that the plaintiff was unsophisticated has, in my view,
little bearing on my findings as to the acceptance or otherwise of
his
version. Ultimately, as far as the working conditions, state of
the roof(s) and the incident are concerned, one is left with the
testimonies of the plaintiff and Mr Webster. As an expert, Dr du
Toit’s testimony was largely about the relationship between
the
defendants and the obligations in terms of the Regulations. His
testimony is accepted.
[91]
While much was made of the various Construction Regulations, in my
view, the case turns largely
on the following issues: the
probabilities of the plaintiff’s version (as referred to
above), negligence, causation and whether
there was contributory
negligence on the plaintiff’s part. It goes without saying that
the parties were not at liberty to
stray beyond their pleadings.
[92]
The first consideration is whether the plaintiff has managed to prove
on a balance of probabilities,
that he was not provided with adequate
or any fall arrest equipment, and that there was no safety line on
the roof, which resulted
in his fall through the skylight.
Significantly, counsel for the plaintiff, at the commencement of
closing submissions, disavowed
a reliance on the statutory
Construction Regulations as a basis for stating that the defendants
are liable to the plaintiff for
damages which he pleads he incurred
because of the incident.
[93]
The plaintiff’s counsel submitted, however, that the statutory
Regulations must be considered
against the backdrop of the conduct of
the defendants in the matter, and in this respect, I agree with the
submission. That said,
regard must still be had to the basis upon
which the plaintiff pleads that each or both defendants were
negligent, which negligence
resulted in his fall to the ground.
Counsel for the first defendant, on the other hand, submitted
that the first hurdle which
the plaintiff was required to overcome
was to prove on a balance of probabilities that he was not provided
with adequate fall protection
on the day of the incident. This
submission is also correct.
Failure
to provide the plaintiff with fall arrest equipment and a safety
line
[94]
It bears emphasising that the plaintiff’s case, as pleaded, is
that a legal duty was imposed
on the defendants to prepare a health
and safety plan, to discuss and negotiate such plan and to comply
with Regulations 5(1) read
with 4(1)(d) and 4(1)(e) respectively. As
alluded to above, I shall accept that the applicable Construction
Regulations at the
time were the 2003 Regulations.
[95]
It is further pleaded that the defendants breached their duty to the
plaintiff when they failed
to ensure that he was not exposed to
hazards when they knew or ought to have known that it was dangerous
to allow him to work at
an elevated level without fall arrest
equipment. The plaintiff further relies on the common law when he
pleads that PT and/or FA
failed to take any or adequate steps to
prevent him from falling through the roof when they could and should
have done so.
[96]
PT, as the client and owner of the premises, denies that the
contractor failed to provide the
plaintiff with adequate fall arrest
equipment on the day of the incident. Instead, its case is that Mr
Fourie supplied the plaintiff
with such equipment but that he (the
plaintiff) had failed to wear it or removed it prior to his fall and
thus, the plaintiff’s
own conduct was the proximate cause of
his fall; alternatively, it amounted to a
novus
actus interveniens
,
alternatively, it constituted a voluntary assumption of risk
[38]
.
The first defendant pleads further that FA and the plaintiff were
contributorily negligent in the circumstances.
[97]
The plaintiff was the only witness other than Mr Webster regarding
the events of 13 March 2014.
It was undisputed that he was one of
eight or nine workers employed by FA to clean and maintain the roofs
on the PT buildings as
shown on Exhibit B, for the duration of the
project. It was also not disputed that half the team would work on
one building and
the other half would work on another building. A
most crucial part of his case was that the contractor had removed the
harnesses
two days prior to his fall and thus there was no safety
harness to wear while on the roof and furthermore, there was no
safety
line either.
[98]
In my view, it was insufficient for the plaintiff to prove, on a
balance of probabilities that
on other roofs depicted on Exhibit B,
there were no safety lines attached for workers to clip their
harnesses into place. While
this may be relevant in the assessment of
whether he discharged the onus of proof, the plaintiff was required
to prove on the probabilities
that on the morning of the incident,
there was no safety line on the roof he worked and walked on and no
harness worn as they were
unavailable.
[99]
Having ring-fenced what the plaintiff was required to prove, the
assessment as to whether he
discharged this onus resting on him,
follows. Due to his work on other projects for FA, it is accepted
that the plaintiff was familiar
with the fall arrest equipment as he
had worked at heights prior to this incident, and I also accept and
find that he was aware
of the necessity and significance of having to
use such equipment when working at a height on a roof of a building.
[100]
Whether there was only one toolbox talk by Mr Fourie or daily talks
prior to the workers starting their tasks
for the day, the evidence
indicates that FA indeed provided toolbox talks to alert the workers,
including the plaintiff, to the
necessity of using fall arrest
equipment including a harness. The plaintiff’s denial that he
did not heed the toolbox talks,
as pleaded by PT, was consistent, and
there is no further evidence in the trial to suggest that he ignored
Mr Fourie’s explanations
and demonstrations.
[101]
From the evidence considered holistically, it is accepted that the
plaintiff was not wearing a safety harness
on the day he fell. This
version is confirmed by Mr Webster who testified that he arrived on
the scene in the warehouse to find
the plaintiff lying injured on the
ground without a harness and PPE gear, and wearing normal clothes.
The plaintiff also pleads
that he was not wearing fall arrest
equipment on the morning in question.
[102]
The question then arises as to how it came about that the plaintiff
was without a harness on the morning of the
incident. The plaintiff’s
case is that he was not provided with a harness as the harnesses were
removed by the contractor
two days prior and that he witnessed the
removal from the storage area on the site. His version that the fall
arrest equipment
was removed from site was not contradicted by Mr
Webster, who had no knowledge of such removal.
[103]
This is unsurprising as on Mr Webster’s version, even though he
walked around the buildings once a day and
climbed ladders mounted
against buildings every three to four weeks to check the progress of
the roof work, he could not gainsay
the plaintiff’s version
regarding the removal of harnesses. There was also no evidence led to
establish any kind of timeline
as to the whereabouts of Mr Webster on
the day of the incident.
[104]
To add, Mr Webster recalled an incident prior to the plaintiff’s
fall where he saw a worker on the roof
without a harness and he
immediately alerted Recardo about this failure. The work was
immediately halted, the situation rectified
and apologies were
offered to Mr Webster/PT. It is evident from this testimony,
considered with that of the plaintiff, that
there was on PT’s
version, at least one occasion where a harness was not worn by a
worker who was working on a roof, though
the reason is unknown.
[105]
Aside from the above, Mr Webster’s testimony was that removal
of PPE from the site two days prior to the
plaintiff’s fall,
was never mentioned to him either by Mr Pietersen or Recardo. Then
again, Mr Webster was also not informed
that on an occasion, a worker
was allowed on the roof
[39]
without a harness.
[106]
Added to the above factors, the plaintiff’s testimony that on
some days, the workers did not have hazmat
suits and harnesses to
wear remained consistent throughout his testimony including lengthy
and persistent cross examination.
Furthermore,
Mr Webster testified that on arrival at the injured plaintiff, he was
later met by Recardo who was wearing a
harness. The submission by
PT’s counsel was along the line that if Recardo, the foreman,
wore a harness, then the plaintiff’s
version regarding removal
and thus unavailability of harnesses, was questionable.
[107]
On the plaintiff’s version, the removal and unavailability of
PPE and harnesses was raised with other workers
and Recardo. The
plaintiff testified that despite the workers talking about the lack
of provision of safety equipment, Recardo
and/or Mr Fourie seemed not
to have remedied the situation. Once again, there is no evidence to
contradict this version of events,
which leads me to the following
query: if Recardo/Mr Pietersen/Mr Fourie had intervened regarding the
“missing” harnesses
and PPE, by all accounts it would
have been expected that work on the roofs would be halted until the
harnesses were returned or
replaced. Furthermore, had the work been
halted, Mr Webster would have testified so, but aside from one
incident referred to above,
there was no evidence that work was
halted because FA had to obtain replacement harnesses or the like.
[108]
The picture painted by the plaintiff, which was not contradicted, was
that safety equipment was held at a lock
up garage on the PT site and
sporadically provided to the workers, who were at times seen without
harnesses. Mr Webster could not
dispute the plaintiff’s version
that on some days, workers did not have hazmat suits and harnesses.
[109]
This brings me to Mr Webster’s testimony that when he came upon
the injured plaintiff on the warehouse floor,
he later saw Recardo
who was indeed wearing a harness. Counsel for PT has argued that if
regard is had to this evidence, then the
probabilities of the
plaintiff’s version are questionable. In my view, it is not so
straightforward. The evidence of the
two witnesses, must be
considered objectively and holistically, as opposed to focussing on
one aspect to bolster a view that the
plaintiff’s version is
improbable.
[110]
To clarify, it must be remembered that while Mr Webster did a daily
walk-about, he also stated that he only climbed
a ladder every three
to four weeks to check the progress of the work and did not climb
onto the roofs. Secondly, there is no evidence
to suggest that Mr
Webster saw Recardo earlier the morning on the building “X”
where the plaintiff says he was when
he fell. Thirdly, the workers
worked in two teams, with one team on one building and the other team
on another building.
[111]
No evidence was presented that Recardo was on the same roof (and
therefore the same work team) as the plaintiff.
In fact, the
testimony of Mr Webster that he called Recardo from the warehouse
when he was alerted to the plaintiff’s fall,
supports the more
probable view that Recardo and the plaintiff were not on the same
building prior to the plaintiff’s fall.
The point is that it
cannot simply be concluded that because Recardo was seen to be
wearing a harness, therefore there must have
been a harness available
for the plaintiff and he either failed to wear it or removed it prior
to the fall.
[112]
In view of the above assessment of the evidence, I find that the
plaintiff’s version as to the removal of
harnesses prior to the
incident is the more probable version and cannot be discounted. While
counsel for PT argued that it would
make no sense for the contractor
to remove this equipment given the contract concluded with PT, the
submission is unsubstantiated
by any evidence presented at the trial
and opens the door to speculation. Furthermore, Mr Webster’s
version that Recardo
and Mr Fourie made certain utterances to him
about the plaintiff being on the roof without a harness, was never
independently corroborated.
[113]
In respect of the plaintiff’s version that there was no safety
lines attached to the building, Mr Webster,
during his walk-abouts,
observed that there were safety lines but not attached to all
the buildings forming part of the complex
seen on Exhibit B. Mr
Webster did not have independent knowledge of safety lines and thus,
could not, in my view, dispute the plaintiff’s
version that at
the building marked “X”, where he maintained he fell, no
safety lines were attached to the building.
[114]
Aside from the plaintiff agreeing that there would be no point in
wearing a harness if there was no safety line
to attach it to, there
is no other evidence to gainsay the plaintiff’s version
regarding no safety lines on building “X”.
At the same
time, and despite the potentially illogical (though dangerous)
situation where a worker would wear a harness knowing
that there was
no safety line to which he was to attach it, if the probabilities
indicate that PPE was removed to take to another
site, then it is not
a far stretch to conclude on the probabilities that it was not
strange that some buildings would not have
safety lines.
[115]
In the normal course of working at heights the suggestion of “no
harness but a safety line”, and
vice versa,
seems
illogical but in the circumstances of this matter and having the
benefit only of Mr Webster and the plaintiff, whose version
was not
so improbable when considered against the peculiar facts of the case,
the conclusion does not seem so unrealistic.
[116]
I agree with PT’s submission that it would have made little
sense for FA to have complied with its legal
duty to provide fall
arrest equipment to workers on some days, but not on others, but the
problem is that there is no version from
the contractor to shed more
light on the issue. Mr Webster was clearly not available 24/7 to
check on the workers, and on his own
admission, stated that safety
lines were not attached to all the buildings.
[117]
On the aspect of Dr du Toit’s lack of knowledge that the
plaintiff had no harness (due to its removal from
the site) and there
being no safety lines attached to building “X”, it is
correct that he was only made aware of this
during the trial, for
reasons unknown to the Court. However, I accept that had he been
aware of these aspects of the plaintiff’s
case, Dr du Toit
would have included it in his report.
[118]
As the essential averment and facts upon which the plaintiff relies
in respect of liability against FA is that
he was not provided with
adequate fall arrest equipment by them at the time of the incident,
in view of the above discussion, and
the pleadings, I find that the
plaintiff has proved on a balance of probabilities that no fall
arrest equipment (harness) was supplied
or made available to him by
FA on the morning of the incident and no safety lines were secured on
the building on which he fell
through the roof.
The
contractor’s liability
[120]
I agree with the submission by PT’s counsel that from the
plaintiff’s pleadings, the liability of
FA is simply that it
failed to provide him with fall arrest equipment. As set out above,
having found that his version is the more
probable, and hence it
follows that the plaintiff has established that FA failed in its duty
to him as pleaded in paragraph 9 of
the amended Particulars of Claim.
In this regard, the plaintiff has succeeded in showing a wrongful
omission by FA toward him.
[121]
In the result, it is found that the plaintiff has proved on a balance
of probabilities that FA breached its duty
toward him by allowing him
to work at a height and in an elevated position on the roof of a
building and thus exposing him to hazards
in such an environment,
without the use of fall arrest equipment to prevent him from
falling.
[40]
Accordingly, the
further finding is that the plaintiff has established that FA failed
to take any or adequate steps to prevent
him from falling through the
skylight of the roof when it could and should have done so.
Accordingly, the plaintiff’s claim
against the second defendant
on the merits, succeeds.
The
liability of Prima Toys
[122]
In respect of the first defendant, the position is slightly
different. The plaintiff’s pleaded case on the
reliance of the
Construction Regulations and breach of the OHS Act does not create
liability in delict although, in terms of section
37(1) of the Act,
there may be criminal sanction upon conviction. While FA was an
independent contractor, PT cannot be held vicariously
liable for the
conduct of the contractor
[41]
.
[123]
The liability, if any, which PT has is a personal liability which
relates to, generally, a failure to prepare
health and safety
specifications, the failure to have a health and safety plan in place
and the breach of a common law legal duty
towards the plaintiff to
ensure that he was not exposed to hazards while on the roof. In
respect of PT, as owner of the premises,
the hazard relates to the
danger caused by skylights which were covered by dirt and moss as the
plaintiff pleads and broken and
damaged skylights and the consequence
of stepping on such skylight.
[124]
A defendant owes a duty of care to a plaintiff if he is a person in
respect of whom harm may reasonably be foreseen
[42]
.
The parties referred to
Langley
Fox Building Partnership (Pty) Ltd v De Valence
[43]
,
a
judgment in which the SCA considered the contractual relationship
between a building contractor and sub-contractor but where the
principles largely also apply to the relationship between a
principal/employer and an independent contractor. In applying the
test to determine the existence of a duty of care in a particular
case, Goldstone AJA
[44]
stated
the following:
“
In
my opinion, it follows from the aforegoing that in a case such as the
present, there are three broad questions which must
be asked,
viz:
(1)
Would a reasonable man have foreseen the risk of danger in
consequence of the work he employed
the contractor to perform? If so,
(2)
Would a reasonable man have taken steps to guard against the danger?
If so,
(3)
Were such steps duly taken in the case in question?
Only
where the answer to the first two questions is in the affirmative
does a legal duty arise, the failure to comply with which
can form
the basis of liability.
It
follows from the aforegoing that the existence of a duty upon an
employer of an independent contractor to take steps to prevent
harm
to members of the public will depend in each case upon the facts. It
would be relevant to consider the nature of the danger,
the context
in which the danger may arise, the degree of expertise available to
the employer and the independent contractor, respectively,
and the
means available to the employer to avert the danger. This list is in
no way intended to be comprehensive. It does follow,
however, that
the duty of an owner of premises such as the present may not be the
same as that of the building contractor employed
by him to do the
work. That question, too, must be answered with due regard to the
facts.”
[125]
Considering the above test in
Langley Fox
, and the
facts of the matter, the reasonable owner of the premises would have
foreseen the risk of working at heights on the roofs
of its buildings
in consequences of the cleaning work which it employed FA to do. This
is especially so knowing that in terms of
the quotes, FA was required
to remove old dirty fibreglass and yellow plastic sheets and in terms
of the second quote, it was also
to remove and replace broken and
damaged fibreglass and plastic sheets.
[126]
The very nature of the work at a height was dangerous but the added
danger lurked in having old, damaged, broken
and moss-covered
skylights and roof panels on the roofs where the workers generally
and plaintiff particularly, worked. A reasonable
owner of the
buildings in the first defendant’s position, in my view,
applying the
Langley Fox
test, would have foreseen the
risk of danger inherent in stepping on such skylights.
[127]
Would a reasonable owner in the place of PT have taken steps to guard
against the danger? In my view, the answer
must be in the
affirmative. It was insufficient to simply pass off the
responsibility of diverting the danger of working on the
roofs, to
the contractor. The contractor’s role, as seen above, was to
ensure that the protocol for working at heights was
met and that it
performed the work as contracted: toolbox talks, demonstrations of
the use of harnesses and safety lines, provision
of PPE, securing
safety lines to the building, ensuring that workers wore the PPE,
supervising the work and acting in accordance
with the Regulations.
[128]
In respect of the second question, the reasonable owner of the
premises would have taken steps to guard against
the danger. Aside
from employing a contractor to do the dangerous work, it would have
disclosed the dangers of potentially slippery
and moss-covered
fibreglass skylights which were old and damaged. Accepting, in view
of the earlier finding, that the plaintiff
was on the roof without a
harness, the undisputed fact is that he fell through the roof when he
stepped on a moss-covered skylight.
There is no contrary evidence
that the skylight was not obscured by moss and/or was not dirty.
[129]
The moss-covered, clearly old and possibly broken and damaged
skylight posed a risk to anyone who walked on the
roof and stepped on
the skylight, whether an employee of FA or not, and whether he wore
PPE or not. PT’s role and responsibility
related to the
skylights is evident in the evidence by Mr Webster: he did not go up
onto the roofs, did not point out the fibreglass
skylights to Mr
Pietersen and his/PT’s actions were limited to standing in the
warehouse and looking up at it. At the risk
of repeating what was
stated when summarising his testimony, Mr Webster confirmed that he
saw from inside the warehouse(s) that
there was moss on the
skylights. This confirms not only the plaintiff’s testimony,
but also his case as pleaded in the amended
Particulars of Claim.
[130]
To the extent that PT wished to convey that the skylights were marked
and noticeable to all who worked on the
roof, my view is that it
failed to establish such averment or fact in the trial.
Notwithstanding disputed versions as to which
building’s roof
the plaintiff fell from, the plaintiff was consistent in his
testimony that he could not distinguish between
roof sheets/tiles and
the skylight. In my view, it then befell PT to prove on a balance of
probabilities that indeed the skylights
on the roof the plaintiff
fell from, were clearly marked and distinguishable, thus presenting a
warning to all who worked and walked
on that roof. PT failed to do
so.
[131]
The significance of this cannot be underplayed for the following
reasons: firstly, in terms of the 2003 Regulations,
the first
defendant was required to have a health and safety specification in
accordance with Regulation 4(1) (a) read with Regulation
1, which
entailed a documented specification of
all
health
and safety requirements related to the cleaning and painting of the
roofs in order to ensure the health and safety of all
persons. In my
view, the reference to “
persons”
[45]
includes the workers such as the plaintiff. Furthermore, “
all
health and safety requirements
”
would
entail a reference to all hazards, including those related to the
skylights. The Regulations are considered against the backdrop
of the
duty of care and compliance with Regulation 4 was compulsory for the
client, PT.
[132]
Thus, having regard to
Langley Fox
and Regulations 4
read with Regulation 5, PT had a legal (common law) and also
statutory duty to the plaintiff in respect
of ensuring health and
safety on its premises
.
Furthermore, Dr Du Toit’s view
was that there was a duty on PT as the client to identify anything
that posed a risk and certainly,
on my understanding, there was a
risk of harm associated with the skylights and roof panels.
[133]
Langley
Fox
recognises
that the duty of an owner of a premises (such as PT) may not be the
same as the duty of the contractor
[46]
.
This was clearly the case here. Mr Webster and/or PT were aware of
the foreman and workers on the roofs and aware of the inherent
danger
which the damaged, old and moss-covered skylights posed. The fact
that the defendants concluded a mandatary agreement, does
no absolve
it of its common law duty and added statutory duty toward persons on
its premises, such as the plaintiff. It was admitted
by Mr Webster
that the contract was outdated and defective for want of
non-compliance with the health and safety legislation at
the time and
this view is confirmed by Dr du Toit. Clearly, the mandatary
agreement did not disclose the safety issues related
to the roof and
skylights, nor did the AIA report, which was ultimately irrelevant in
this matter as it concerned asbestos, which
is not what this dispute
turns on.
[134]
Having regard to the above discussion, and in answer to the first two
questions in
Langley Fox
, firstly, a reasonable
client/owner of the premises would have foreseen the risk of danger
in consequence of the work on the roofs
which it employed the
contractor to perform; and secondly, a reasonable client would have
taken steps (as set out above) to guard
against it. As the two
questions are answered in the affirmative, I am satisfied that the
client, PT, owed the plaintiff a legal
duty and a secondary statutory
duty of care.
[135]
In
Chartaprops
16 (Pty) Ltd and Another v Silberman
[47]
the SCA recognised the category of cases where the reasonable person
in the employer/client’s position is expected to ensure
that
reasonable precautions are taken to avoid harm from befalling the
plaintiff. As discussed in
Chartaprops
[48]
,
which
considered the liability and duty of care of a shopping mall owner
vis
a vis
the
cleaning contractor, in the circumstances which ensued (water
spillage) it was reasonable to expect Chartaprops to take precautions
to keep the floors safe and it would be liable if those precautions
were not taken by the contractor. It was found that Chartaprops
owed
a legal duty to shoppers and on the basis set out in the judgment it
was found to be liable.
[136]
In this matter, the duty of care owed by each of the defendants
toward the plaintiff is different. The existence
of the first
defendant’s duty to prevent harm depends on a consideration of:
the nature of the danger, which was that someone
could slip and walk
on a moss-covered, old, damaged and broken fibreglass skylight on
the roof; the danger could arise
when someone working on
the roof walks on/upon the skylight which in all probability would
have been vulnerable due to age,
breakages, wear and tear; the
client was in a position to afford to pay for a roofing or
construction expert to attend to an assessment
of the roof, roof
tiles and skylights, but failed to do so; and, the client had the
means available to avert the danger by providing
a report on the
conditions of the roof, by pointing out the skylights, by itself
inspecting the roof and by clearly marking the
dangerous areas on the
roof. The first defendant failed to acquit itself of its duty to the
plaintiff in these circumstances.
[137]
I agree with the plaintiff’s counsel that the liability of the
first defendant comes down to an issue of
foreseeability.
Furthermore, the defendants were clearly pre-occupied with working
with asbestos, yet as far as the first defendant
went, no
consideration was given to the unsafe conditions on the roof, as
described above. Having regard to
Langley
Fox, Chartaprops
and
Cenprop
Real Estate v Hotlzhausen
[49]
,
this is a case where, having regard to the roofing and skylight
conditions and the dangers it posed, the client was personally
at
fault. The duty of care related to the latter conditions did not rest
with the contractor.
[138]
In my view, the failure to alert the plaintiff and other workers to
the risks on the roofs including slippery
tiles and dangerous
skylights, in circumstances where, according the
Cenprop
[50]
,
the
client/principal was clearly wrong, leads me to conclude that the
first defendant was negligent in relation to the plaintiff’s
harm or injury. Accordingly, I also agree with the plaintiff’s
submission that the nature of the danger was proceeding on
a roof
where skylights looked virtually identical to the roof sheets. The
application of tape to identify the skylight was not
visible to the
plaintiff on the top of the roof so does not assist the first
defendant.
[139]
The plaintiff led evidence on the roof conditions, and not merely
non-compliance with the Regulations. If anything,
the non-compliance
with the Regulations certainly supports the view that PT had a
general disregard for the safety issues related
to the state of the
roof. The reasonable person in the position of Mr Webster/ Prima Toys
would have foreseen the dangers posed
by walking and working on the
unsafe roofs, but it did highlight this in its agreement with
the contractor.
[140]
In failing to act positively as set out above, PT’s conduct
amounted to an omission which is wrongful
[51]
.
In determining whether PT was negligent, regard is had to the test
for negligence as set out in
Kruger
v Coetzee
[52]
:
liability of the defendant arises if a
diligens
paterfamilias
in
the position of PT would foresee the reasonable possibility of his
conduct injuring another and causing him patrimonial loss;
and would
take reasonable steps to guard against such occurrence and the
defendant failed to take such steps.
[141]
In my view, the above questions must be answered in the affirmative.
As the owner of the building, and having
regard to the Regulations
referred to, PT ought to have known that there were broken, damaged
and old fibreglass skylights covered
in moss, and would have foreseen
the reasonable possibility that its failure to point these out to
workers such as the plaintiff
and people on the roof, created the
risk of harm or injury when someone walked upon the skylights. A
reasonable owner in PT’s
place would have alerted the plaintiff
thereto and PT did not do so. It simply left the roof in its entirety
to the contractor,
which was not a roofing expert nor construction
expert, but an asbestos cleaning business. In light of the discussion
and findings
above, the harm to the plaintiff (and others) was
foreseeable and PT, in not taking the various precautionary
measures to
ward off the harm to the plaintiff, acted negligently in
relation to the plaintiff.
[142]
The enquiry does not end there because causation must be considered.
PT pleads that it is the plaintiff’s
conduct in removing the
PPE or failing to wear it which was the proximate cause of his fall
which broke the causal
nexus
between
any wrongful and negligent conduct ascribed to it and the plaintiff’s
fall
[53]
. Furthermore, such
conduct constituted a
novus
actus interveniens
and/or
a voluntary assumption of risk by the plaintiff, who at all material
times knew of and fully appreciated the danger of falling
from an
elevated position on the roof in the absence or wearing fall
protection equipment. In so doing, he voluntarily assumed
the risk of
falling.
[143]
Is there a causal connection between PT’s negligent conduct in
failing to alert/highlight/draw attention
to the risks associated
with the old, moss-covered, damaged and broken skylights, and the
plaintiff’s injuries? In
Minister
of Police v Skosana
[54]
the SCA identified factual causation as relating to “
the
question whether the negligent act or omission in question caused or
materially contributed to… the harm giving rise
to the
claim”
[55]
If it did, then the second question is whether the negligent act or
omission is linked to the harm directly or sufficiently close
enough
for legal liability to follow or whether the harm is too remote.
[56]
[144]
Insofar as factual causation is concerned, the “
but for”
test applies. In this respect, I have to enquire whether the harm to
the plaintiff would nonetheless have ensued even if the omission
(PT’s failures regarding the condition of the roof and
skylights) had not occurred. This presupposes applying a hypothetical
scenario as to what probably would have happened but for the wrongful
conduct of PT. Here, I am required to super-impose PT’s
unlawful conduct/omission for (its) lawful conduct and ask whether,
in such a case, the plaintiff’s fall would have occurred
or
not.
[145]
Applying this exercise: if PT had alerted the plaintiff and/or
pointed out the conditions on the roof, including
the slippery, old,
broken and damaged skylights and included these references in PT1 and
in a health and safety plan for working
at heights, and clearly
marked out the skylights, would the plaintiff’s loss have
ensued or not? The answer must be No. The
plaintiff would have been
alerted to the clearly identified skylights covered in moss, which
would have been distinguished from
the roof tiles. In such a
hypothetical scenario, and had he been keeping a proper lookout as to
where he was walking, the plaintiff
would not have stepped on a
skylight, and had he not stepped upon it, his step or impact thereon
would not have caused it to give
in/break and he would not have
fallen through the roof.
[146]
The second enquiry is whether the wrongful act/omission is
sufficiently closely or directly linked to the loss
for legal
liability to arise or whether the loss is too remote.
[57]
From the facts of this matter, the conduct of PT amounted largely to
omissions and had it acted positively (and pro-actively, as
opposed
to supinely relying on an AIA report and an asbestos cleaning
contractor), the plaintiff would not have walked onto the
skylight
and fallen through.
[147]
There would, in my view, have been no situation where he would step
onto a dangerous, unreliable and possibly
fragile skylight, which
gave way under the plaintiff’s weight. He explained that his
leg had vanished, indicating that likely,
the skylight was not only
moss-covered, but probably old and damaged. In the event that PT had
employed an expert in roofing or
construction or even an expert in
skylights, the risks would have been identified, assessed and been
known. It did not do so. In
the circumstances, I am satisfied that
the omissions are closely linked to the plaintiff’s loss for
legal liability to arise.
Contributory
negligence of the plaintiff
[148]
There remains the issue of the plaintiff’s conduct in entering
upon the roof without fall arrest gear. I
do not repeat my findings
regarding the issue of the gear which on the probabilities, I found
were not made available to him and
so too the absent safety line. It
is, in my view, a useless exercise to ask “
what would have
happened had the plaintiff not been on the roof”?
[149]
The authorities referred to above and the academic work referenced in
a footnote, make it clear that causation
must be approached logically
and with reference to the peculiar facts and circumstances of a case.
The fact is that the plaintiff
was on the roof without PPE gear and
walked upon a skylight, the conditions of which should have been made
aware to him, and had
he not been on the roof in the first instance,
there would have been no claim.
[150]
In my view, the issue is not that the plaintiff voluntarily assumed
the risk when he was on the roof without a
safety harness, nor that
the failure to wear fall arrest equipment constituted a
novus
actus interveniens.
The issue is, and the conclusion reached, is
that even if he wore a harness attached to a safety line, he would
still have (hypothetically
speaking) walked upon an obscured, dirty
and probably damaged or broken skylight, which would have given in
under the impact of
his weight and he would still have gone through
the skylight and the roof.
[151]
The safety harness, had it been worn and attached to a safety line as
required, would have arrested his
fall and stopped the
plaintiff from plunging to the ground below and landing on the cement
floor, which resulted in injury. However,
it must be emphasised that
even wearing a harness, the plaintiff would have plunged through the
skylight, though (logically-speaking)
certainly not as far down to
the cement ground as was the case. How far he would have plunged and
whether he still would have sustained
minor injuries is unknown and
calls for speculation.
[152]
It must be remembered, even in the circumstance where I have found on
the probabilities that no fall arrest equipment
was made available to
the plaintiff on the morning of the incident and no safety line was
secured, the plaintiff certainly knew
that he was not allowed to work
at an elevated position without fall arrest equipment. Yet,
notwithstanding the absent safety gear,
knowing the dangers of
working at heights due to his experience in similar jobs, and having
been privy to toolbox talks, the plaintiff
forged ahead and entered
the roof without protective gear.
[153]
There is no evidence to indicate that the plaintiff failed to keep a
proper lookout on the roof and there is no
basis to infer such
conduct from the evidence. The plaintiff’s conduct, in entering
the roof area when he had no safety gear
available to him, was
negligent and this negligence was causally connected to the loss
which he had suffered and certainly contributed
to it
[58]
.
[154]
Ultimately, there is no evidence to contradict the plaintiff’s
version as to the state of the roof including
the skylights. In
comparing the respective degrees of negligence of the first defendant
and plaintiff, the extent of each of these
parties’ negligence
in causing the damages to the plaintiff has been discussed above. The
defendants’ omissions as
described above bear a slightly
greater portion of the liability in the circumstances and an
appropriate apportionment follows.
Costs
[155]
Lastly, on the issue of costs, the matter in my view, was by no means
straight forward and has certainly been
challenging, especially
having regard to the issue related to the Regulations, the
differentiation between the defendants’
liability and the
consideration of the plaintiff’s own conduct.
[156]
Having regard to Rule 67A and the observations and findings of Wilson
J in
Mashavha
v Enaex (Pty) Ltd
[59]
,
the
matter certainly presented some complex issues, and I am of the view
that an award of costs, jointly and severally, with counsel’s
fees on scale C is warranted.
Order
[157]
Accordingly, the following order is granted:
a.
The defendants are liable to the plaintiff, jointly and severally,
the one paying
the other to be absolved, for 60% of his proven or
agreed damages.
b.
The defendants are liable to pay the plaintiff’s party and
party costs,
jointly and severally, the one paying the other to be
absolved (counsel’s fees on scale C).
c.
The trial on quantum is postponed
sine
die
,
pending the completion of the pre-trial and/or case management
process on
quantum.
M
PANGARKER
JUDGE OF THE HIGH
COURT
Appearances
For
Plaintiff:
Adv P Eia
Instructed
by: A
Batchelor Attorneys
Cape Town
For
Defendant: Adv T R Tyler
Instructed
by: Dicks van
der Merwe Attorneys
Cape Town
[1]
In
terms of the Act
[2]
Par
8, Amended POC
[3]
Para
7, Amended POC
[4]
Transcript,
10 February 2025
[5]
Exhibit
B
[6]
First
quote, 2 June 2012
[7]
Dr du Toit testified that he did not see such information in AIA
report
[8]
See
p52
[9]
Dr
du Toit could not comment that PT1 was prepared by FA.
[10]
The
2014 Regulations were published in GG 37305 of 7 February 2014, at a
time when the project of PT had already commenced.
[11]
Ms
Keet’s report could only be referred to insofar as it
referenced a factual scenario and not insofar as what it purported
to be.
[12]
Regulation
5(1), 2003 Regulations
[13]
Regulation
7(4), 2003
[14]
Presumably
by the client, PT
[15]
Regulation
4(1)(e), 2003
[16]
Exhibit
A, p55-75
[17]
It
is noted that there remained a dispute as to the place where the
plaintiff fell through the skylight: according to the plaintiff,
it
occurred at point “X” and according to Mr Webster, the
fall occurred at point “Y”
[18]
Point
“y” on Exhibit B.
[19]
,
Quotation, p50, Exhibit A
[20]
Clauses
3,5,6,8,11 and 20
[21]
Point
A on Exhibit B
[22]
The
first aider was on the PT premises
[23]
Inside
the warehouse building
[24]
Exhibit
A, PT1, par 3, p35
[25]
Exhibit
A, p35
[26]
Transcript,
p481
[27]
Exhibit
A, p47 (FA’s Old Mutual policy)
[28]
Transcript,
p484
[29]
Par
6, PT1, p35
[30]
First
quote, Exhibit A, p50
[31]
This
includes all the buildings, and points A, X, Y and Z, Exhibit B
[32]
PT1,
Exhibit A, p52
[33]
PT1,
Items (b) and (e), p50
[34]
Regulation
4(1)(a), 2003 Regulations
[35]
Transcript,
p512
[36]
The
client shall promptly provide the principal contractor/its agent
with any information which might affect the health and safety
of any
person at work carrying out construction work.
[37]
Identified as the building marked with “X”, Exhibit B
[38]
Further
Amended Plea, A15-A16
[39]
Presumably
with other workers as they were split into two teams
[40]
Dr
du Toit’s evidence, which is accepted, is that FA was required
to appoint a construction safety officer in terms of Regulation
6(6)
which it failed to do; and it was required to do a risk assessment
in respect of working at heights, which it also failed
to do.
[41]
See
Law of Delict Seventh Edition Neethling Potgieter Visser p391
[42]
Premier
of the Province of the Western Cape v Faircape Property Developers
(Pty) Ltd
2003 (2) All SA 465
(SCA) par [42]
[43]
1991(1)
SA 1 (AD) 37-40 (Saflii version)
[44]
As he was
[45]
Regulation
1
[46]
Langley
Fox, p13 C
[47]
[2008}
ZASCA 115
para [14]-[15]
[48]
Par
[18]
[49]
2023
(3) SA 54
(SCA) par [26]
[50]
Supra
[51]
Principles
of Delict, p84
[52]
1966(2)
SA 430 E-G
[53]
Par
7.1A.3, A15, Further amended Plea
[54]
1977(1)
SA 31 (A) 34-35
[55]
34-35
[56]
Principles
of Delict, Third Ediiton, JC van der Walt andJR Midgley, p197;
International Shipping Co (Pty) Ltd v Bentley 1990(1)
SA 680 (A) 700
[57]
International
Shipping Company (Pty) Ltd v Bentley
[1990] 1 All SA 498(A)
700E-701A
[58]
South
British Insurance Co Ltd v Smit 1962(3) SA 826(A); Amler’s
Pleadings, Tenth Edition, LTC Harms and MR Townsend p278
[59]
2025(1)
SA 466 (GJ) par [25]-[27]
sino noindex
make_database footer start
Similar Cases
Bennett v Curro Holdings Limited (2024/141557) [2025] ZAWCHC 505 (31 October 2025)
[2025] ZAWCHC 505High Court of South Africa (Western Cape Division)97% similar
Bengston and Others v Preuss NO and Another (17699.2018) [2025] ZAWCHC 432 (16 September 2025)
[2025] ZAWCHC 432High Court of South Africa (Western Cape Division)97% similar
Bewley v Minister of Home Affairs and Another (2025/019372) [2025] ZAWCHC 477 (15 May 2025)
[2025] ZAWCHC 477High Court of South Africa (Western Cape Division)97% similar
Liv Padel (Pty) Ltd and Another v Executive Mayor of Knysna Municipality and Others (2025/242003) [2025] ZAWCHC 590 (18 December 2025)
[2025] ZAWCHC 590High Court of South Africa (Western Cape Division)97% similar
Barnard v Peregrine Plaza (Pty) Ltd (14475/20) [2025] ZAWCHC 48 (18 February 2025)
[2025] ZAWCHC 48High Court of South Africa (Western Cape Division)97% similar