Case Law[2024] ZAWCHC 260South Africa
Rajah and Another v S (A102/2024) [2024] ZAWCHC 260 (12 September 2024)
High Court of South Africa (Western Cape Division)
12 September 2024
Headnotes
offsite on Winlite's premises.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 260
|
Noteup
|
LawCite
sino index
## Rajah and Another v S (A102/2024) [2024] ZAWCHC 260 (12 September 2024)
Rajah and Another v S (A102/2024) [2024] ZAWCHC 260 (12 September 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_260.html
sino date 12 September 2024
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
REPORTABLE
Case
Number: A102/2024
Regional
Court case number: SH7/28/2020
In
the appeal of
RIDWAAN
RAJAH
FIRST APPELLANT
GOOD
HOPE PLASTERERS t/a
GOOD
HOPE CONSTRUCTION
SECOND APPELLANT
and
THE
STATE
RESPONDENT
JUDGMENT
Date
of hearing: 6 September 2024
Date
of judgment: 12 September 2024
Coram:
Bhoopchand AJ, Kusevitsky J
Bhoopchand
AJ:
1.
This is an appeal against the judgment of the Bellville
Specialised
Commercial Crimes Court. The Appellants are Ridwaan Rajah and Good
Hope Plasterers CC, trading as Good Hope Construction.
The Appellants
were cited as Accused 1 and 2 in the court below. To avoid confusion,
they shall be referred to throughout this
judgment as the First
Appellant and the Second Appellant. The Respondent is the State.
Other significant players in this matter
include the National
Department of Public Works (the DPW) and Winlite Aluminium Windows
and Doors (Pty) Ltd (Winlite), which has
since been liquidated.
2.
The trial in the Regional Court commenced on 2 August
2021. The
Appellants were charged with fraud on count 1 and theft as an
alternative. The charge on count 2 was for theft, and on
count 3, the
First Appellant was charged with perjury, alternatively making a
false affidavit in contravention of section 9 of
the Justices of the
Peace and Commissioners of Oaths Act 16 of 1963. The Appellants
pleaded not guilty on all counts, and the First
Appellant tendered a
plea explanation in terms of
section 115(2)
of the
Criminal Procedure
Act 51 of 1977
. The Appellants were acquitted on count 1 and
convicted on count 2. The First Appellant was convicted on count 3.
3.
In October 2010, the Second Appellant and the DPW concluded
a
contract to renovate buildings in the parliamentary precinct in Plein
Street, Cape Town. The DPW appointed a professional consultant
team,
including an architect as the principal agent, a quantity surveyor,
and an engineer. It also provided a project manager from
its ranks to
oversee the project. The DPW contracted the First Appellant as its
Principal Contractor. The first Appellant tendered
a contract price
of R 7 302 113.16, which the DPW accepted. On completion of
the contract, the contract amount escalated
to R10 820 422.98.
4.
The
contract terms concluded between the First Appellant and the DPW were
largely based on the standard form of the Joint Buildings
Contracts
Committee (JBCC), the standard contract for large projects in the
construction industry. The Second Appellant was required
to appoint
its subcontractors to discharge its obligations under the contract
with the DPW. The Second Appellant appointed Winlite
as a domestic
contractor to construct four curtain screens on the parliamentary
premises. The contract price between Winlite and
the Second Appellant
was R1 368 000.
[1]
5.
The site was handed over to the Second Appellant towards
the end of
2010. There was a delay in commencing the work largely due to the
pace at which police clearance certificates were issued
for the
employees of the contractor and sub-contractors. Winlite anticipated
an increase in the price of the materials it intended
to use to erect
the screens and brought this to the notice of the Second Appellant.
After discussions with the DPW’s project
manager and in an
attempt to avert the price rise, the Second Appellant and the DPW
agreed to an advance payment to cover the costs
of materials that
Winlite would use to construct the curtain screens. The materials
would be held offsite on Winlite's premises.
6.
DPW would
make the advance payment to the Second Appellant to forward to
Winlite, provided certain conditions were met. Of these
conditions,
Winlite would provide a guarantee to the DPW to cover the costs of
the materials kept offsite, despite there being
no contract between
the DPW and Winlite. Winlite provided the guarantee from Lombard
Insurance in favour of the DPW on 1 December
2010. The guarantee was
a bond for unused materials kept off-site.
[2]
The DPW released R519 037.90 on 14 March 2011 to the Second Appellant
to pay its subcontractor, Winlite. The Second Appellant paid
Winlite
R467 131. 11 on 18 March 2011 and retained R51 906.79, or
ten per cent.
7.
The onsite work commenced in March 2011, and Winlite installed
two of
the four screens. The DPW rejected Winlite's work. The implications
were that the two screen curtains had to be dismantled,
reworked, and
reinstalled. Winlite failed to respond to warnings to rectify its
defective work, concurrently ran into financial
problems, and was
liquidated. The DPW duly claimed against the guarantee for the
advance payment it had made. The insurers informed
the DPW that they
would not honour the guarantee as Winlite had no contract with the
DPW.
8.
The work proceeded to completion, with the Second Appellant
appointing another sub-contractor to complete Winlite’s part of
the contract. The final certificate of completion was signed
off on 5
April 2014. A final statement of account was duly processed by the
DPW and signed off by the DPW’s manager, the
principal agent,
and the quantity surveyor on 7 June 2014. On perusing the statement
of account, the First Appellant rejected it
as the DPW had allegedly
omitted or deducted the first advance covering the costs of materials
held offsite by Winlite. The Second
Appellant applied to this court
in September 2015 for an order to include the advance payment in the
final statement.
THE
MOTION PROCEEDINGS
9.
The Second Appellant applied to this court to declare
that
R519 037.90 is to be included in the final account as an amount
due and payable to it. The second Appellant sought consequential
relief. The Respondents (the DPW and the Principal Agent) were
required to amend the final account to include the sum of R519 037.90
in determining the final amount payable by the DPW to the Second
Appellant.
10.
The First
Appellant deposed to the affidavit in the application on behalf of
the Second Appellant. The First Appellant acted as
the sole member of
the Second Appellant.
[3]
The
State relied upon three paragraphs of the founding affidavit, namely
paragraphs 14, 19, and 39, in compiling the charge sheet
against the
Appellants. The material part of paragraph 14 states that the
contract sum agreed upon between Winlite and the Second
Appellant was
R1 900 000 (excluding VAT). In paragraph 19, the First
Appellant stated that the Second Appellant advanced
the sum of
R519 037.90 to Winlite for the materials kept offsite. In
paragraph 39, the First Appellant states that on completion
of the
project, the DPW did not compensate the Second Appellant for the
advance made on the DPW’s behalf for the materials
purchased
and held offsite. The First Appellant stated that the Second
Appellant paid for the materials, which became the property
of the
DPW, and the latter refused to pay.
11.
The content of the following paragraphs, in addition to those
identified
by the State, is relevant to the case preferred against
the Appellants and the determination of this appeal:
11.1.
Paragraph 2: The First Appellant stated that the contents of the
affidavit
fell within his knowledge, unless indicated to the
contrary, and are true and correct,
11.2.
Paragraph 12: The final account excludes the sum of R519 037.90
in respect
of an advance made to Winlite,
11.3.
Paragraph 13: The amount advanced to Winlite rightfully stands to be
included
in the final account,
11.4.
Paragraph 15: The commencement of the project was inordinately
delayed. Winlite
approached the Second Appellant to request that the
DPW pay for the materials it intended to use in the project, which
were kept
off-site,
11.5.
Paragraph 17: The DPW agreed to pay for the materials kept off-site
by Winlite,
provided that a guarantee made out in favour of the DPW
had to be issued.
11.6.
Paragraph 18: the guarantee was provided on 2 March 2011,
11.7.
Paragraph 20: A dispute arose between the Second Appellant and
Winlite over
the quality of the work done by Winlite. Winlite
departed the site and failed to return the materials it held off-site
to the Second
Appellant or the DPW.
11.8.
Paragraph 26: The DPW lodged a claim for the value of the materials
kept off-site
11.9.
Paragraph 28: The insurance company informed the DPW that it would
not honour
the claim as the claim was time-barred and the DPW failed
to submit the claim timeously,
11.10.
Paragraph 29: The First Appellant forwarded several e-mails to the
Respondents advising that
the amount of R519 037.90 had to be
incorporated into the account as the materials belonged to the DPW
and a guarantee was
made out in favour of the DPW,
11.11.
Paragraph 32.2: The Second Appellant objected to the final account
submitted by the Respondents
as the amount of R519 037.90 had been
omitted.
11.12.
Paragraph 32.3: The materials (remaining) offsite were not brought
back to the site for the
construction of the remaining two screens,
11.13.
Paragraph
33: Although the sum had been included in an interim payment
certificate, it was not (?)
[4]
omitted from the final account, which means that the Second Appellant
has not been paid for the said materials,
11.14.
Paragraph 38.1: The DPW did not agree with the understanding of the
guarantee, nor did it agree
that it was liable to pay for the
materials, as the Second Appellant contended.
12.
The DPW did not file an answering affidavit to the Second Appellant’s
founding affidavit. Instead, the DPW opted to agree to an order taken
in this Court on 26 October 2015, in which the amount of
R519 037.90
had to be included in the final statement of account. The DPW duly
paid the Second Appellant the amount of R519
037.90, representing the
amount initially advanced by the DPW for Winlite’s materials
kept off-site.
THE
SIU INVESTIGATION
13.
In terms of Presidential Proclamation R54 of 2014 to the
Special
Investigating Units and Special Tribunals Act 74 of 1996
, the
President of South Africa tasked the Special Investigating Unit to
investigate allegations of the nature of serious maladministration
and unlawful conduct, negligent loss of public money, and corruption,
among others relating to state contracts. The work done at
the
parliamentary precinct, including the tender under scrutiny in this
case, was included in the list for investigation. The investigation
was allocated to the Chief Forensic Investigator Samuel Adams
(“Adams”).
14.
Adams was mandated to investigate the building works at the
parliamentary
complex under project WCS045653. He looked at aspects
of the tendering, appointment of contractors, consultants, and the
conduct
of state employees, whether there were any irregularities
within their systems and processes and whether there was compliance
with
the provisions of the
Public Finance Management Act 1 of 1999
.
15.
The Special Investigating Unit proceeded to uplift documents relating
to the contract, including the final statement of account and the
application raised by the Second Appellant to compel the DPW to
include an amount omitted from the final account. Adams learnt that
the court had ordered the payment. It became a concern for
him as it
referred to a claim for materials held offsite. The DPW paid the
Second Appellant for offsite materials, but the Second
Appellant paid
Winlite for work in progress. Adams noted that the certificate of
final completion was signed off on behalf of the
Second Appellant.
The Second Appellant had not signed the final statement of account.
The other signatures, including those of
the professional consultant
team and the DPW’s onsite project manager, were affixed by 24
February 2014.
16.
Adams interviewed the director of Winlite (since deceased), the State
Accountant, D Ricketts, the liquidator of Winlite, the administrative
officer Henrietta Amon and the DPW’s legal advisor,
A K
Carriem. Adams found that the Second Appellant had paid Winlite R467
134.11 on 18 March 2011. Adams understood that there was
no
contractual relationship between the DPW and Winlite. He was also
aware that the relationship between Winlite and the Second
Appellant
soured after Winlite produced poor work that the DPW rejected. The
owner of Winlite told Adams that he had not received
the advance
payment. Adams was unaware that the Second Appellant had requested an
advance payment from the DPW or that Winlite
had requested an advance
payment from the Second Appellant. Once Winlite had left the site,
the DPW called up the guarantee, but
it was rejected because the
guarantee incorrectly reflected the employer as the DPW, and Winlite
had no contract with the DPW.
17.
The case presented by Adams became apparent during his examination in
chief by the State. Adams stated that the DPW had made two duplicate
payments of R519 037.90 to the Second Appellant, the first
in
2011 and the second after the court order on 19 November 2015.
Winlite’s invoices indicated that the Second Appellant's
payment was a progress payment, not an advance payment for materials
held offsite. The Appellants stated they were not paid for
the
material offsite and then obtained a court order to force the
department to pay them again. The ten per cent that the Second
Appellant retained was not due to it. The amount retained by the
Second Appellant should have been returned to the DPW as it was
for
the materials kept offsite.
18.
Adams testified that the DPW suffered a loss of R519 034.90 (the
second payment) and a loss of R51 903.49, the 10% retained by
the Second Appellant. The Second Appellant should have returned
both
amounts to the DPW. Adams referred the case for prosecution on the
tenuous premise that the Second Appellant had not paid
its
subcontractor for materials held offsite but for work done onsite.
THE
CHARGES
19.
The First Appellant was summonsed to appear in court on 5 October
2020.
The trial in the matter began on 2 August 2021. The Appellants
were charged with three counts with alternate charges preferred to
counts one and three. The first count was one of fraud with an
alternate charge of theft. The second count was of theft. The third
count related to perjury, alternatively, making a false statement in
an affidavit, thus contravening
section 9
of Act 16 of 1963.
20.
On the first count of fraud, the State alleged that the Appellants
intended
to defraud the DPW of R519 037.90. The date implicated on
this count is 22 September 2015, when the First Appellant deposed to
the founding affidavit. On the alternative theft charge, the State
alleged that on 19 November 2015, the Appellants unlawfully and
intentionally stole R519 037.90 from the DPW. The DPW paid the
Second Appellant R519 037.90 on this date after the court
order
was taken by agreement. Appellants were acquitted on count one,
comprising fraud and theft charges.
21.
On the second count of theft, the State alleged that the Appellants,
over
a period from 9 March 2011 to the date of the trial, unlawfully
appropriated an amount of R519 037.90, the property of or in
the
lawful possession of the DPW intending to deprive the DPW of the
amount permanently.
22.
On the third count of perjury, the State alleged that the First
Appellant
deposed to an affidavit on or about 23 September 2015
wherein the content of paragraphs 14, 19, and 39 contained
misrepresentations,
lies, and false statements. The details contained
in these paragraphs shall be addressed later in this judgment.
THE
PLEA EXPLANATION
23.
The First Appellant explained, among others, that :
23.1.
The DPW paid an amount of R718 867.28 to the Second
Appellant on
14 March 2011, of which R519 037.90 was an advance for materials
held offsite by Winlite. Winlite provided an
insurance guarantee to
the DPW for the materials held offsite,
23.2.
The Second Appellant effected payment of R467 134.11
to Winlite,
representing a 10% deduction of R519 037.90, the value of the
materials held offsite,
23.3.
It is settled practice for a principal contractor to retain
10% of
funds earmarked for payment to the domestic sub-contractor as a
protective measure,
23.4.
The DPW rejected the two screens erected by Winlite, and
the latter
left the site,
23.5.
The amount required to rectify Winlite’s defective
work,
re-install two screens, and install two further screens was about
R600 000 for the Second Appellant’s account,
23.6.
The insurers refused to honour the claim as Winlite was cited
as the
contractor in the guarantee instead of the Second Appellant,
23.7.
The DPW acquired ownership of the offsite materials. Due
to no fault
of the Second Appellant, the DPW failed to recover the materials
offsite or to recoup the resultant loss from the insurer,
23.8.
The Second Appellant paid for the materials and had no other
option
but to approach the High Court for the losses it suffered when the
DPW omitted the payment from the final statement of account,
23.9.
The First Appellant instructed his staff to provide the documents
relevant to the contract, and his attorney drafted the affidavits and
submitted them to Senior Counsel to finalise,
23.10.
The affidavit did not reflect the 10% retention amount being withheld
as
a standard temporary measure. The amount reflected as a payment to
Winlite in paragraph 19 was incorrect, but the last sentence
was
correct,
23.11.
The contract between Winlite and the Second Appellant amounted to
R1 368,000.
The amount reflected in paragraph 14 was incorrect
as it reflected the contract price between the Second Appellant and
the subcontractor
employed to undo and redo Winlite’s defective
work,
23.12.
The First Appellant had provided the proof of payment of 18 March
2011 of
R467 134.11 it made to Winlite at the request of the DPW
on 21 October 2015. The DPW agreed to settle the amount of
R519 037.90
claimed in the application,
23.13.
The amount was lawfully due and received by the Second Appellant. The
First
Appellant denied that he wilfully and intentionally deposed any
untruths in the affidavit to mislead anyone or the court.
CROSS-EXAMINATION
OF ADAMS
24.
Adams
stated that no payments were made for materials kept off-site. He
referred to three invoices issued by Winlite that were marked
as
exhibit ‘S’.
[5]
The
First invoice reflected an amount of R598 272.00.
[6]
The second invoice from Winlite refers to an outstanding amount of
R131 140.89 from the November 2010 invoice. If the latter
amount
is deducted from the amount reflected as owing for November, the
difference is R467 132, the advance amount paid by
the Second
Appellant to Winlite. Adams insisted that the latter was a progress
payment.
[7]
25.
Adams was
confronted with a sequence of facts to challenge whether the payment
was a progress payment or for materials kept offsite.
Winlite and the
Second Appellant signed the contract on 9 February 2011. Winlite
commenced work on the site on 27 March 2011. Winlite
had not done any
work when the first invoice was issued. Adams was shown e-mails from
2 March 2011, which dealt with the off-site
materials. The architect
and the quantity surveyor inspected the materials. Once valued by the
architect and quantity surveyor,
the materials off-site were worth
R519,037.90. Adams had not contacted the architect or the quantity
surveyor. Despite the facts,
Adams declined to concede that the
payment was for materials held offsite.
[8]
Adams insisted that the amount paid to Winlite by the Second
Appellant was for work done.
26.
Adams insisted that the Second Appellant was not entitled to the 10%
retention
on the advance. He stated that it was not applicable, but
when confronted with the building subcontract between Winlite and the
Second Appellant, he indicated it was. He eventually conceded this
point. Adams also accepted that the Second Appellant’s
court
application was settled by agreement.
27.
Adams admitted that his entire investigation was based on the
complaints
received. The complaint was that the amount paid to
Winlite was progress payments, not payments for materials kept
offsite. He
changed his view when presented with the invoice (Exhibit
“V”) issued by Winlite. Winlite invoiced the Second
Appellant
for materials held offsite amounting to R519 037.90
minus ten per cent. Adams then conceded that the advance was for
payment
of the materials held offsite. Winlite’s defective work
was a loss for the Second Appellant, not the DPW. The DPW tried to
claim against the guarantee as they thought it was their loss, not
the Appellants' loss. Adams accepted that someone in authority
in the
DPW was satisfied that the payment had to be made.
28.
Adams could not assist with what was included or excluded in the
final
account. He had not consulted with any relevant personnel from
the DPW or the professional consulting team. Adams was told that
the
final account indicates that the Second Appellant was paid R519
037.90 as part of the contract price. It was put to Adams that
if the
DPW managed to claim the R519 037.90 from the insurance company
which issued the guarantee, then the DPW could not
regard the advance
as a payment made to the Second Appellant. This aspect was further
elucidated. If the DPW hypothetically claimed
against the guarantee
and it was paid, but the amount on the accounts still shows that the
DPW paid that to the Second Appellant,
would Adams not then agree
that the Second Appellant suffered a loss because it paid away the
R519 037.90 to Winlite. Adams agreed.
29.
Adams stated that the invoice changed the case concept (as initiated
against
the Appellants). On questioning from the court, Adams noted
that “the payment on this invoice corresponds with the payment
in Winlite's bank account, and the invoice states it is for materials
off-site. Adams agreed that he might have had a different
view if he
had seen the invoice before. He testified that the R519 037.90
was the Second Appellant’s loss.
30.
It was suggested to Adams that count 1, which related to progress
payments
and not to materials kept off-site, was unsustainable. Adams
declined to comment. It was then suggested that the Second Appellant
was fully within its rights to ask for the final account to be
amended to include the amount it had paid to Winlite for materials
kept off-site. That is why the DPW paid the amount when faced with
the application. Adams agreed.
31.
On
re-examination, Adams stated further that when Exhibit “V”
was presented for the first time, he had seen a document
stating that
Winlite had invoiced for the material offsite. Exhibit “V”
also indicated that the Second Appellant suffered
the loss.
[9]
Adams testified that if he had known of exhibit “V,” the
investigation would not have proceeded. The State’s
position
concerning exhibit “V” is captured in its submissions on
conviction. Alarmingly, the State submitted that
it “begs to
differ” with Adams, a witness it called when he stated that the
invoice showed the Second Appellant had
suffered a loss.
32.
The impression the Court obtains from reading Adam's testimony is
that
he formed a cursory opinion on perusing the documents presented
to him. He pursued an investigation of the Appellant upon the tenuous
premise that the payment made by the Second Appellant to Winlite was
a progress payment and not for materials held offsite. Adams
was
largely influenced by the owner of Winlite, who denied receiving
payment for materials held offsite. Adam did a curtailed
investigation and failed to interview some important personnel
involved in the project. The Appellant's description of Adam’s
capitulation, when confronted with exhibit ‘V’ during
cross-examination as his Damascus moment, is apt. The Court considers
the testimony of Adams elicited during his cross-examination to be
crucial to the guilt or otherwise of the Appellants. Yet, it
did not
warrant a mention in the Regional Court’s judgment.
TESTIMONY
OF THE OTHER STATE WITNESSES
33.
David Andrew Ricketts, the State Accountant employed by the DPW,
testified
that the project manager verified the amounts paid to
contractors. The payments made to the Second Appellant were already
authorised
when he received them. He did not investigate the amounts
reflected on the certified invoices, as this was not part of his job.
Ricketts could not confirm or refute that a double payment was made
to the Second Appellant, nor could he comment on the final
statement
of account.
34.
Henrietta Amon, a senior administrative officer in the legal services
section of the DPW, confirmed that Lombard Insurance declined to
honour the guarantee as there was no contract between the DPW and
Winlite. The DPW had erred by not checking this aspect when receiving
the guarantee.
35.
Amon was asked about the litigation dealing with the amount omitted
from
the final account. She could not assist. The court asked whether
Amon was involved in processing the final account and asked her
whether the DPW owed the Second Appellant a further R519 037.90.
Amon responded that she was not involved in computing the
final
account. When the Court further questioned her, Amon stated that the
DPW disagreed that it owed the Second Appellant a further
R519 037.90.
36.
Mohamed Suaad Carriem, the legal advisor to the DPW, was asked about
the
amount retained by the Second Appellant, i.e., R51 903. 79.
Carriem was asked whether the Second Appellant was entitled
to retain
10% of the amount paid for materials off-site. He stated that the
retention amount was for works completed, not for materials
to be
supplied. Carriem bore no independent knowledge of any payments that
were made.
37.
Carriem could not assist the court in determining whether the series
of
payments were correctly computed or calculated. Nor could Carriem
comment on the accuracy or completeness of the final payment
certificate. Carriem initially stated that the quantity surveyor
would be the best person to comment on the accuracy or completeness
of the final statement of account. However, he later stated that he
could not answer that question. It was put to Carriem that
an advance
was requested to avoid price increases in materials. Carriem
testified that Ms Van Den Hoven had informed him that the
DPW would
be liable if the materials were brought onsite. This was why the DPW
settled with the Second Appellant after the latter
launched the
application. Regarding the guarantee, the DPW, including Carriem,
overlooked that Winlite had no contract with the
DPW. Carriem did not
know that the Appellant and his brother informed the project manager
that the guarantee the DPW insisted on
having with Winlite was
incorrect. Carriem asserted that the guarantee should have come from
the Second Appellant.
38.
Carriem testified that the 10% retention is for latent defects. It
was
put to Carriem that the First Appellant would testify they were
compelled to bring the application. The DPW paid the Appellants
R519 037.90 to forward to Winlite, of which R467 000 was
paid. When the DPW computed the final account, they omitted
the
R519 037.90 because they could not recoup this amount from the
guarantee. The amount omitted is a subtraction from the
amount due to
the Appellants. It was paid initially, but in the end, the DPW took
it away from the final statement. Carriem had
no comment on the
proposition put to him. Carriem repeated that, in his opinion, the
Second Appellant was not entitled to retain
the 10% and hang onto it
even after the matter had been settled. Carriem could not think of
any lawful grounds on which the Second
Appellant retained the 10%.
39.
The crucial part of Carriem’s evidence is related to the
advance
payment and the guarantee. Carriem was not involved in the
computation of the final statement of account and could not assist
the
Regional Court in this respect. Carriem testified that the
advance payment to the Appellants subcontractor was exceptional and
that the State would not normally make advance payments. The
incorrect and ineffective guarantee obtained from Winlite escaped his
scrutiny, and he accepted responsibility for it.
40.
Adams did not consult with Neeltjie Clasina Van Der Hoven (Van Der
Hoven),
the DPW’s head of building projects. The State
indicated they intended to call Van Der Hoven to explain the final
statement
of account but reneged. The failure to call Van Der Hoven,
the project manager, or any member of the professional consulting
team
meant that the State would flounder in its attempt to prove that
the Appellants stole the amounts as charged.
41.
An analysis of the witness testimony at the close of the State’s
case indicates that the State had not provided proof at all, let
alone proof beyond a reasonable doubt that the State should prevail
on the theft charges as formulated in the charge sheet. The State
failed to call any witness who could explain why the DPW had
settled
the application to compel the DPW to include the advance payment of
R519 037.90 in the final statement of account.
The State
intended to call Van Der Hoven, the DPW’s head of building
projects. It reneged on that intention.
42.
The witnesses who testified confirmed that the DPW erroneously
obtained
a guarantee for the advance payment from Winlite. None of
them could explain the computation of the final statement of account.
The State had yet to prove the element of intention required to
prevail on the fraud, theft, and perjury charges. The State would
require the Appellants to incriminate themselves on the fraud and
theft charge and the First Appellant to admit an intention to
perjure
himself in his founding affidavit.
THE
SECTION 174 APPLICATION
43.
The State closed its case at the end of Carriem’s testimony.
The
State did not consider it necessary to lead competent evidence on
the final statement of account by any personnel who knew how the
account was computed. Although the State indicated it would call Van
Der Hoven, it did not follow through with this intention.
44.
The Appellants raised a section 174 application for their discharge.
The
Appellants surveyed the evidence of the State. They asserted that
the State did not disprove their contention that the DPW omitted
and
thus deducted the advance from its final statement of account. The
Appellants tendered a plea explanation for the errors made
in the
founding affidavit. They submitted that the only reasonable prospect
of conviction would be if the First Appellant testified
and confessed
to doing so wilfully and intentionally.
45.
The State conceded in argument that the advance payment made to
Winlite
by the Second Appellant on behalf of the DPW was for
materials held offsite. The State submitted that the Appellants could
not
use the guarantee to impute liability onto the DPW. The DPW
provided the advance payment, and the result was that the DPW
suffered
a loss of R519 037.90. The Second Appellant paid R467 134.11
to Winlite, i.e. 10% less than the actual amount received as an
advance towards Winlite. Carriem had testified that the Second
Appellant had no basis for retaining the 10% as it defeats the
purpose of the DPW advancing such payment. The subcontract agreement
makes provision for the retention of 10%, but that is for work
completed. Carriem also testified that the Appellants should have
disclosed that they retained 10% of the advance payment (R51 903.79).
The Appellants had this amount and did not disclose it to the DPW.
The Appellants were involved in negotiations for 14 months and
never
thought of returning the 10% retained to the DPW. The purpose was to
deprive the DPW of this amount permanently.
46.
It is thus apparent that the State concentrated on proving that the
Appellants
had stolen the 10% they retained and did not subsequently
disclose or return to the DPW. From the tenor of the submissions
made,
the State knew it failed to prove that the Appellants intended
to steal R519 037.90 from the DPW.
47.
The rationale of a section 174 application is to avoid wasting
valuable
court time and to protect the Appellant’s
constitutional rights to a fair trial. The Regional Court found that
the State
had proved a prima facie case, which the Appellants had to
answer. The court came to this decision based on the admissions made
by the First Appellant concerning the errors in the founding
affidavit. The Regional Court referred to the admissions as
misrepresentations
made by the First Appellant. This was incorrect.
48.
The Regional Court referred to the 10% retention, the state of mind
of
the First Appellant in so far as the proof of intention was
required for the charges. The Regional Court suggested that the First
Appellant was in the best position to explain why the errors were not
committed intentionally. The Regional Court quoted Hiemstra
in
stating that if there is a suspicious atmosphere about the case, it
is not wrong to keep the finality of the discharge in abeyance.
The
section 174 application was dismissed.
THE
TESTIMONY OF THE ACCUSED AND HIS BROTHER
49.
The First Appellant, a Quantity Surveyor, testified that the DPW
agreed
to pay Winlite the money to procure the materials for the
curtain walls and to mitigate the predicted rise in costs. Winlite
could
either provide a construction guarantee or agree to a 10%
deduction from every payment held in a retention fund until the
contract
is completed. Winlite opted for the 10% retention. Winlite
would have received the amount retained at the end of their contract,
provided there were no defects in their work. Provision of security
by the contractor or sub-contractor by either guarantee or
retention
is practised by every company involved in the building industry in
South Africa and the world. The 10% the Appellants
retained from the
advance was to cover any damages it suffered against Winlite.
50.
The First Appellant testified that his brother and the manager had
noticed
that the DPW had omitted the payment they had made for the
materials held offsite by Winlite from the final statement of
account.
The DPW had unfairly omitted the R519 037.90 from the
final account. From February 2014 to September 2015, they tried
extensively
in an amicable way to convince the DPW that the guarantee
the DPW obtained from Winlite was not the Appellants' fault. The
Appellants
were lawfully entitled to include the amount in the final
statement of account.
51.
The founding affidavit correctly refers to the DPW, excluding
R519 037.90
from the final statement of account. The First
Appellant admitted that the amount reflected in the founding
affidavit as a payment
to Winlite was incorrect. The contract price
with Winlite was also incorrect. All information relating to the
matter was given
to the attorneys. The amounts appeared to be correct
when he saw the affidavit. The Second Appellant was engaged in many
contracts
when the affidavit was finalised. The First Appellant was
assured by his attorney that the figures were correct. He contended
that
the amount reflected in paragraph 19, i.e., R519 037.90,
was the value of the materials held offsite. The First Appellant
testified that the allegation made in paragraph 39 of the affidavit
that the Appellants had not been compensated for the advance
made on
behalf of the DPW for the materials purchased and held offsite was
correct. Senior Counsel drafted the affidavit. The DPW
had requested
proof that Winlite had been paid before it agreed to include the
R519 037.90 in the final statement of account
and paid the
amount. The proof of payment was provided to the DPW.
52.
Under cross-examination, the First Appellant confirmed that only one
payment
was made to Winlite for materials kept offsite. The
subcontract did not make provisions for advance payments. The advance
payment
to Winlite was processed as a progress for work completed.
Winlite acknowledged that the payment qualified for a 10% deduction.
It was unfair to expect the Appellants to warn the DPW that the
guarantee should have been between the Appellants and Winlite,
not
between Winlite and the DPW. The contract between the Appellants and
the DPW allowed for advance payments, but the agreement
between the
Appellants and Winlite did not. The subcontract with Winlite was not
amended to allow for the advance payment that
was made. The guarantee
created an obligation on the part of the insurer to pay upon the
happening of an event, which included
loss of the materials. The
guarantee required by the DPW had an impact on the subcontract
between the Appellants and Winlite. The
Appellants got together with
Winlite and agreed that the advance payment would be a progress
payment. These instances occur frequently
in the construction
industry and are not always regulated.
53.
Further, under cross-examination, the First Appellant testified that
the
Appellants did not need to inform the DPW that they had retained
10% of the amount paid for the materials held offsite. The DPW
was
not entitled to the 10% retained as they had the guarantee to cover
them for any loss relating to the materials. The 10% retained
was to
cover any damages the Appellants suffered due to Winlite’s
defective work.
54.
It was a mistake not to deduct the retention from the amount
reflected
in the affidavit. Neither was it a misrepresentation. The
First Appellant admitted that the amount paid to Winlite in paragraph
12 of the affidavit was also incorrect. The statement in paragraph 39
was correct. Paragraph 39 contained the allegation that the
Appellants had completed the project but had not been compensated for
the advance made on behalf of the DPW. The First Appellant
explained
that the DPW deducted this amount from the money paid to them. The
full amount of R519 037.90 was claimed and paid
by the DPW. The
10% that was retained was spent. The Appellants were getting it back
from the DPW. Winlite went into liquidation
after they left the site.
The 10% retention was used towards getting a new contractor. The full
amount was not due to Winlite because
of the retention policy. If the
10% retention was due to anybody, it was due to Winlite and not the
DPW.
55.
The brother of the First Appellant testified. He is a financial
accountant
and the contracts director of the second appellant. He was
responsible for the overall financial management of the building
sites
and dealt with contractual matters that arose. He testified
that the DPW had the right to claim the guarantee. The DPW was
incapable
of securing itself properly. The DPW paid for and owned the
materials off-site. The DPW bore the risk if Winlite defaulted, and
the materials did not come onsite.
56.
The brother testified that the JBCC contracts permit a
risk-associated
security position that comprises either a variable
guarantee or a reduction in the monthly payments as a cash retention.
The Second
Appellant opted for monthly retention of payments made by
the DPW. The Second Appellant, in turn, followed suit by implementing
a similar security provision with their subcontractors.
57.
It was put to the brother that the DPW suffered losses, as in this
case.
The brother replied that any loss suffered by the DPW occurred
through their error in demanding a guarantee from Winlite. The
Appellants
did not inform the DPW of the retained amount, nor did
they return it to the DPW. It was put to the brother that the
Appellants
had a legal and contractual duty to disclose to the DPW
that the Second Appellant would retain 10% of the advance payment
regarding
materials offsite. The DPW paid out an additional amount of
R51 903.70. The brother disagreed.
58.
The brother testified that the State misunderstood contractual
matters
in the construction industry. The Second Appellant had a
contract with Winlite that allowed it to deduct the 10% retention,
which
it duly did and which Winlite accepted. The Second Appellant
had the right to set off costs once Winlite abandoned its obligation.
Due to Winlite's default, the Second Appellant was saddled with an
additional cost of about R1 300 000. The brother explained
that the JBCC contract permitted the Second Appellant to deduct 10%
of the contract sum for contracts exceeding R1 million. It
was,
therefore, legal and agreed to between the Second Appellant and
Winlite.
59.
The claim against the DPW occurred due to their failure to act on the
guarantee they required. The State suggested to this witness that the
First Appellant testified that he had made a mistake when
he failed
to deduct the 10%. The State incorrectly made the latter proposition.
The First Appellant had testified that it was a
mistake not to
explain this in his affidavit as the amount paid to Winlite. The
brother testified that the Second Appellant would
have been able to
claim their loss to the maximum of what was paid to Winlite if the
DPW had asked the Appellants to provide the
guarantee to them.
60.
After perusing the final statement of account, the brother testified
that
he noticed that the DPW had removed their payment of the amount
for materials held offsite. The professional consultant team was
informed that the Appellants did not agree with removing the item
from the final statement of account. There were numerous emails
between the Appellants and the DPW's Van Der Hoven. The Department’s
onsite representative, Eric Williams, agreed that the
item's removal
was wrong. The brother repeated this explanation under
cross-examination. The DPW had deducted the R519 037.90.
The
Second Appellant had suffered a loss of about R1,3 million and could
only claw back the R519 037.90 from the DPW.
61.
The testimony of the First Appellant and his brother were consistent
on
the facts material to this matter. Although the Regional Court has
the advantage of observing the demeanour of the witnesses when
they
testify, there is nothing in the trial transcript to suggest that
they were dishonest, unreliable, or unprofessional. They
repeatedly
stressed that the Prosecutor did not understand the building industry
and that there were practices peculiar to the
industry. It is unclear
how the Regional Court concluded that their testimony, especially
about the defences they raised, were
all lies.
THE
JUDGMENT AND CONVICTION
62.
The
Regional court found that both Appellants acted unlawfully in their
dealings with the DPW. The DPW released R519 037.90
on 8 March
2011 to the Second Appellant for payment to Winlite for materials
kept offsite after the Lombard guarantee was issued.
The advance
payment was for the materials required for curtain walls three and
four.
[10]
The Second Appellant
paid an amount of R467 134.11 to Winlite. Winlite erected just
two of the four screens before it went
into liquidation. The
materials kept offsite were never recovered or returned to the DPW.
63.
The First Appellant stated in his founding affidavit that the final
account
presented for the Second Appellant’s approval excluded
the amount of R519,037.88. The First Appellant falsely stated in his
affidavit that R519 037.30 constituted an advance paid by the
First Appellant to Winlite for goods manufactured and kept offsite.
Twenty-four days after the High Court order, i.e., on 19 November
2015, DPW paid (or paid again) R519 037.30 to the Second
Appellant. The Second Appellant did not pay the full amount to
Winlite (the first time around). The First Appellant also falsely
stated in his affidavit that the contract sum with Winlite was about
R1 900 000.
64.
The Regional Court summarised the case for the Defence. The Defence
had
claimed that, at most, the Appellants acted negligently. The
Second Appellant retained 10% of the advance payment as it was
contractually
entitled to do as a protective measure. There was no
legal duty to reveal the latter to the DPW. The Second Appellant
believed
it was legally entitled to set off the 10% against the
R600 000 in additional costs incurred through the
sub-contractor’s
malperformance. It was put to the state
witness Carriem that the DPW was mistaken about the format or nature
of the Lombard guarantee.
Exhibit “V”, an invoice from
Winlite, proved that Winlite was also under the impression that the
10% retained was legally
in order. Winlite fully agreed to the
retained amount, knowing that the materials held offsite were
sponsored (or paid for) by
the DPW. The defence raised included the
contention that the incorrect figures amounted, at most, to possible
negligence as the
Appellants did not intend to commit any crime. The
State proved no commission of a crime beyond a reasonable doubt. To
understand
the defence raised, the court had to consider other
contracts relevant to the sub-contract with Winlite.
65.
The
Regional Court cited the relevant law before assessing the witnesses.
All four State witnesses impressed the Magistrate as professional,
unbiased, honest, and reliable witnesses. She qualified the
observation by saying that they were not perfect. The First Appellant
and his brother did not impress her. They were not entirely honest
and reliable. They admitted to including serious and erroneous
figures in their affidavits in the High Court application. They
indicated that these were mere mistakes, which at most, amounted
to
negligence. Their legal team prepared the documents. They conceded at
the end of the trial that there was no contract between
the DPW and
their domestic sub-contractor.
[11]
They could not explain why the 10% retention was not revealed in the
affidavit. The Regional Court referred to the First Appellant
and his
brother’s educational status. They had tertiary qualifications.
They were both in the business world but could not
distinguish a
company from a close corporation or determine how many members
constituted their close corporation. The Appellants
could not provide
any reason for failing to return the money to the DPW.
[12]
66.
The court’s evaluation of the evidentiary material followed.
The
court reminded itself that the legal elements of the crimes the
State required convictions had to be proven beyond reasonable doubt.
In addition, it reminded itself that it may only convict on the
reasonableness and reliability of the evidentiary material.
67.
The court
considered the undisputed evidence and stated that it assisted in
reaching a verdict. The First Appellant is tertiary
qualified. The
First Appellant admitted the DPW paid an advance of R519 037.90 for
offsite material on 8 March 2011.
[13]
Winlite requested the Second Appellant to approach the DPW before 8
March 2011 for upfront payments for materials held offsite.
It was
also common cause that the advance payment was for materials kept
offsite, i.e., curtain walls 3 and 4, which Winlite never
installed.
The Second Appellant paid Winlite R467 134.11 on 18 March 2011
for the materials.
68.
The purpose of the application to the High Court was to compel the
DPW
and Mr Sean Logie, the Architect and Second Respondent in the
application, to include the sum of R519 037.90 in the relevant
final account. The First Appellant included materially incorrect
figures in paragraphs 14 and 19 of his affidavit.
69.
The
Regional Court then identified three main aspects of the dispute.
[14]
These were whether the Appellants intentionally committed fraud
and/or theft and perjury, whether or not the First Appellant
unlawfully
and intentionally made a misrepresentation in his founding
affidavit for purposes of civil proceedings. The Appellants alleged
that they had paid over the full amount of R519 037.90 to Winlite on
18 March 2011, knowing they did not. The Regional Court asked
itself
whether the incorrect figures in the founding affidavit occurred
through negligence or were made intentionally.
70.
The Regional Court found that the Appellants had not committed fraud
pursuant
to count 1. The DPW paid the Second Appellant R519 037.90
pursuant to a court order. The court order was taken by agreement.
Neither the DPW nor the High Court were induced to act to their
detriment through the misrepresentations perpetuated by the
Appellants.
71.
The Regional Court acquitted the Appellants on the alternative to
count
1, i.e., theft. The Appellants did not intend to steal the
amount of R519 037.90 twice. The court reasoned that a double
contract that existed simultaneously with the intent to steal
was not proven beyond a reasonable doubt. The Regional Court observed
that the State did not charge the Appellants with theft of
only
R51 903.74.
72.
The
Regional Court assessed the Appellants' culpability under count 2
involving the standalone theft charge. The Magistrate asked
rhetorically whether the State had proved all the “illegal”
[15]
elements of the crime, especially the intention to steal. The court
then proceeded to analyse the errors in the founding affidavit
to
determine whether the First Appellant had made a mistake, was merely
negligent, or had the intention to commit a crime. The
court found at
least four instances in the affidavit where the First Applicant
signed off incorrect information of a material nature
as correct. The
Magistrate specified two of them. The Second Appellant claimed it had
paid R519 037.44 to Winlite when the amount
was R467 134.11.
This payment did not accord with the terms of the subcontract. The
Appellants claimed that their contract
price with Winlite was
R1 900 000, knowing well that it was only for R1368 000, a
difference of about R532 000.
73.
The First Appellant and his brother had tertiary qualifications. Both
operated in a field dealing with monies and contracts. The First
Appellant had more than one opportunity to read the affidavit.
The
First Appellant should have understood the importance of making
correct averments in an affidavit. There was a higher duty
to be
accurate when interacting with a minister or a senior figure. There
was no room for errors in these circumstances unless
the Appellants
wanted to. The Appellants could not blame anyone else for the errors
in the affidavit. The Magistrate wondered whether
the Appellants
would have persisted in using the same attorney as they did if the
attorney was responsible for the errors. The
Regional Court found
that the First Appellant did foresee the errors and reconciled
himself to the fact that the affidavit consisted
of
misrepresentations.
74.
The
Regional Court then considered whether the Appellants intended to
benefit illegally and financially from their contract and
the High
Court application and found in the affirmative. That was the sole
purpose of the application. The incorrect numbers amounted
to
hundreds of thousands of rands. The First Appellant knew that making
a misrepresentation with fraudulent intent was a crime.
He knew that
theft was a crime; he knew that to lie under oath in his affidavit in
civil proceedings was a crime. The First Appellant’s
knowledge
of these crimes and his intent to act criminally was never placed in
dispute during the trial.
[16]
75.
The Regional Court found that the Appellants unlawfully and
intentionally
stole R519 037.90 from the DPW. The amount was not
due to them for at least three reasons. The DPW had already paid the
amount
to the Second Appellant shortly after Winlite had requested
the advance. Winlite was the Second Appellant’s sub-contractor,
and the Department had no contract with Winlite. The Appellants knew
the amount requested in the application was not due to them.
The
proof they had was their business account, which reflected the
payment from the DPW and Winlite’s invoice date. The Regional
Court found further that the Second Appellant could not retain the
10% of R519 037.90 for itself. The DPW had paid for materials,
and once Winlite defaulted, the Second Appellant should have returned
the ten per cent to the DPW.
76.
On the perjury charge, the Regional Court found that the First
Appellant
had, in addition to paragraphs 14 and 19, included
incorrect facts in paragraphs 39 and 40 of the affidavit. The First
Appellant
had included the wrong facts to commit theft of the DPW’s
funds. The First Appellant had intentionally chosen to claim an
amount exceeding the invoice. The court found that the State had
proved all legal elements of this crime beyond reasonable doubt.
77.
The Regional Court reflected on the proven facts and weighed them
against
the versions of the First Appellant and his brother. The
court found that their versions were not reasonably possibly true.
They
were all rejected as lies. Their defence of fault in the form of
negligence was also not reasonably possibly true. The court said
it
was a lie. The First Appellant acted with intent to steal and lie
under oath. The Regional Court provided three reasons for
finding the
First Appellant guilty of perjury and theft. In the affidavit, the
First Appellant misrepresented the amount claimed
from the DPW and
why it was due to them. The First Appellant contended that the Second
Appellant paid what the DPW was supposed
to pay and that the DPW
never paid them, knowing that both these accusations were false. The
Appellants misrepresented the amount
due to them from the DPW and the
amount they paid to their subcontractor. The Appellants admitted that
the purpose of the application
was to get additional funds or to
force the DPW to pay additional thousands of rands to the Second
Appellant. Both the theft and
the perjury were committed on different
days. The First Appellant did not deny that he was asked whether he
understood the contents
of his declaration, had any objection to
taking the prescribed oath, and considered the prescribed oath to be
binding on his conscience.
He did not state that he was denied the
opportunity to read his statement again. He did not claim that he was
in haste to sign
the affidavit.
78.
The Regional Court found that the First Appellant lied under oath to
gain
financially. He lied as to why he wanted to claim. He lied about
the amount and the purpose as to why he wanted to claim. He lied
as
to the substantial amount he wanted to obtain. The First Appellant
never checked the correctness of the amount because he knew
the
misrepresentations would allow the Second Appellant to gain
financially.
79.
The Regional Court acquitted the Appellants on the first count of
fraud
or theft, convicted them on the second count related to theft,
and convicted the First Appellant of perjury. The court was careful
not to convict the Appellants of a lesser amount on the theft charges
as it was not included in the charge sheet.
GROUNDS
OF APPEAL
80.
The Appellants raised more than 20 grounds of appeal. These included
findings
of fact or rulings of law in which the Magistrate erred and
misdirected herself in that she:
80.1.
Accepted the evidence presented by the State proved that the crimes
set out in the charge sheet had been committed,
that it proved the
guilt of the Appellants beyond a reasonable doubt, that the charges
did not amount to a duplication of offences,
and that the second
count of theft the charge as to time and place was not vague and
embarrassing,
80.2. Failed
to take into consideration the lie told by Winlite on which the
States case was built (i.e., that the Second
Appellant had not made
an advance payment for materials held offsite by Winlite), failed to
consider the evidence of Adams that
had he known of exhibit “V”,
no charges would have been levelled against the Appellants, accepted
the evidence of the
State witnesses without examining or analysing
their evidence, ignoring the collaborating evidence of innocence,
acquitting the
Appellants of theft on count one but convicting them
on the same charge of theft on count two.
80.3. By
finding that the fraud charge that no misrepresentation was made and,
therefore, the Appellants were not guilty
yet finding on the same
facts that the crime of perjury had been committed as an intentional
misrepresentation had been made, that
the High Court order directing
the DPW to lawfully pay the Second Appellant the money described in
the charge sheet was obtained
by intentional misrepresentations, by
making the latter finding without recourse to any evidence as to why
the order was agreed
to considering that there were witnesses the
State could have called to indicate whether the order was made by
intentional misrepresentation
or not,
80.4. Ignored
the High Court’s order with the consent of the DPW, which order
was not rescinded, and which directed
the DPW to pay the money
described in the charge sheet,
80.5.
Concluded the evidence that was not supported by the facts and which
evidence allowed for conclusions other than
guilt,
80.6. Failed
to consider the probabilities and surrounding facts that supported a
finding of innocence, not finding
and detailing exactly what was
stolen in the theft charge, when it was stolen, how it was stolen and
by whom it was stolen, finding
that the two payments that were
allegedly stolen were made to the Second Appellant,
80.7.
Rejected the evidence that the statement on which the perjury charge
was based was not material, was a mistake
and was never made to
supply false information,
80.8.
Rejected the Appellant's claim that they lacked the
mens rea
to commit the crime of theft and perjury and failed to explore,
analyse, or take cognisance of the relevant probabilities,
corroboration,
and surrounding facts that confirmed their defence.
THE
LAW APPLICABLE TO APPEALS
81.
The appeal
in this matter arises from alleged errors and misdirections on the
part of the Regional Court in its findings of fact
and rulings of
law.
[17]
A court of appeal
will be slow to interfere with the trial court's findings of fact
without proof of a material misdirection. Its
powers to interfere are
limited.
[18]
In the absence of
a verifiable and material misdirection by the trial court, its
findings of fact are presumed to be correct. They
will only be
disregarded if the recorded evidence shows they are wrong. When an
appeal is lodged against the trial court’s
findings of fact,
the appeal court should appreciate that the trial court was in a more
favourable position than itself to form
a judgment because it was,
among others, able to observe the witnesses during their questioning
and was absorbed in the atmosphere
of the trial.
[19]
82.
An appeal
court will be deferential and slow to interfere with a trial court's
credibility findings.
[20]
The
deference afforded to a trial court’s credibility findings must
not be overstated. If it emerges from the record that
the trial court
misdirected itself on the facts or that it came to a wrong
conclusion, the appellate court is duty-bound to overrule
the factual
findings of the trial court to do justice to the case.
[21]
Where a court of appeal is convinced that the conclusion reached by
the trial court is wrong, it will reverse it.
[22]
83.
In criminal
proceedings, the state bears the onus to prove the accused’s
guilt beyond reasonable doubt
[23]
.
The accused bears no onus to prove their innocence.
[24]
The
accused’s version cannot be rejected because it is improbable,
but only once the trial court has found, on credible
evidence, that
the explanation is false beyond a reasonable doubt.
[25]
The corollary is that if the accused’s version is reasonably
possibly true, the accused is entitled to an acquittal. An
Appellant’s conviction will be sustained if his version of
events is considered false after considering all the evidence.
[26]
84.
Splitting
of charges and duplication of convictions should be avoided. The
underlying ratio for the rule is to prevent multiple
convictions
arising from culpable facts which constitute one offence only.
[27]
Common sense and fairness should prevail when the rule is
applied.
[28]
Section 83
of the
Criminal Procedure Act authorises
the State to put to an accused as
many charges as possible, as may be justified by the facts, either in
the form of main charges
or alternatives. The court must ensure no
duplication of convictions at the end of the trial.
[29]
85.
With the
efflux of time, three tests have been developed by our courts as a
practical guide to determine whether there has been
a splitting of
offences and duplication of convictions, namely the ‘single
intent test’,
[30]
the
‘continuous transaction test’
[31]
and the ‘evidence test’.
[32]
No general test has been developed.
[33]
Thus, in instances where the offences may have been carried out with
the same single intent or formed part of a single continuous
‘transaction’ or course of conduct, or where the same
evidence which was required to prove the one offence would
necessarily
also prove the other, charging the accused with all these
offences was considered to amount to an impermissible so-called
‘splitting
of charges’ which could potentially result in
a duplication of convictions, and consequently the accused would only
be charged
with (or convicted of) one of them.
[34]
86.
As a
further aid in applying the “intent test”, the court will
have regard to the essential elements of the crime to
prove each
charge. The ‘intent test’ is applied if there are two
acts, and each would constitute a separate or different
act, but
there is only one or a single intent; where both acts seem to be
committed to achieving or attaining this single intent,
there is only
one offence.
[35]
The SCA held
that the tests are nothing more than guidelines. In each matter, to
determine whether there might be an improper splitting
of charges and
a resultant duplication of convictions, a Court must adopt a common
sense approach in light of the fundamental requirement
of fairness to
an accused.
[36]
EVALUATION
87.
The overarching impression is of five elements that permeate this
case,
each pivotal to the charges levelled against the Appellants.
They are the advance payment, the guarantee, the ten per cent
retention,
the founding affidavit, and the final statement of
account. The court shall examine each of them.
88.
An advance payment, or prepayment, is a financial transaction in
which
a payer provides funds to a payee before goods or services are
delivered. This is typically done to secure a product or service
in
advance. On behalf of the Appellants, it was argued that the advance
was an amount paid to Winlite by the DPW in terms of a
separate
agreement between Winlite and the DPW underscored by a guarantee
supplied by Lombards. It was related to ‘materials
offsite’,
meaning money was required to fund the purchase and work on screens
offsite intended for the building work. This
submission does not
accord with the evidence.
89.
The evidence supports the conclusion that the advance payment was
forwarded
against the Second Appellant’s tender price. Due to
delays in the commencement of the building project occasioned by the
slow pace of police clearances, Winlite asked the Second Appellant to
approach the DPW for a payment in advance to secure materials
to be
used in the offsite manufacture of curtain screens. Winlite feared an
imminent increase in the price of the materials. The
Second Appellant
obliged, and the DPW acceded to the request on condition that Winlite
provided security for the value of the materials.
90.
There was no contract between Winlite and the DPW. The DPW
appreciated
the need to curtail costs but erred in requiring the
guarantee from Winlite. The guarantee should have come from the
Second Appellant.
Payment of R519 037.90 was made into the Second
Appellant’s bank account, the Appellants deducted ten per cent
from the advance,
and the Appellants objected to its omission from
the final statement of account. Counsel for the Appellants conveyed
to the State
witness Adams that the advance was made against the
tender price. The DPW settled the application to reinstate the item
in the
final statement of account. This interpretation accords with
the evidence.
91.
State witness Carriem described the advance as ‘exceptional’
as the State rarely makes this payment, let alone to a domestic
subcontractor. The JBCC defines an advance payment guarantee as
a
guarantee at call obtained by the contractor from an institution
approved by the employer in the amount as stated in the contract
data. The JBCC contracts allowed for two methods of transitional
security to ensure that work by contractors and subcontractors
was
properly done, i.e., the provision of a guarantee by an insurer or
the retention of a percentage of payments due. The guarantee
was
provided for the DPW to secure the value of the goods kept off-site.
The DPW erroneously demanded that Winlite provide the
guarantee
despite having no contract with the Appellants’ subcontractor.
92.
Carriem testified that the DPW assesses all guarantees, but this
particular
guarantee escaped their scrutiny. It was an oversight on
his part. Through its error, the DPW failed to realise that the
guarantee
obtained by Winlite cited Winlite as the contractor and the
DPW as the employer. Winlite erected two screens, which the DPW
rejected.
Winlite subsequently abandoned the site and defaulted on
its contract with the Second Appellant. The Second Appellant had to
appoint
another subcontractor at an increased cost to dismantle the
work done by Winlite and complete the installation of four curtain
screens on the parliamentary premises. The DPW thought they had
secured the materials held offsite by holding the guarantee. Lombard
Insurance rejected the claim as the document reflected Winlite as the
contractor and the DPW as the employer. When the DPW failed
to secure
payment, they chose to omit the item for materials held offsite from
the Second Appellant’s final statement of
account.
93.
As the DPW made the advance against the Second Appellant’s
contract
price, the Second Appellant was entitled to retain ten per
cent of the advance it paid to Winlite against the subcontract price.
The invoice issued by Winlite to the Second Appellant dated 8
February 2011 (“exhibit V”) confirms that Winlite
accepted
that the Second Appellant was entitled to retain ten per
cent of the amount invoiced. Winlite opted for this form of security
to
ensure its work was properly executed.
94.
Whilst it is correct that the subcontract between the Second
Appellant
and Winlite did not cater for a percentage retention of
payments made for materials held offsite, it must be remembered that
State
witness Carriem described the advance as an exceptional
payment. The First Appellant testified that they approached their
subcontractor
and agreed to process it as a progress payment. The
subcontract with Winlite for about R1.3m included the cost of
materials supplied
by Winlite. If the Appellants had paid Winlite in
the normal course of the subcontract, the payment would have been
part of a progress
payment. State witness Adams failed to grasp this
aspect of the subcontract and investigated the Appellants on the
tenuous basis
that the advance was for work done and not for
materials held offsite. Much time and effort was expended at the
trial in debating
this issue.
95.
The First Appellant insisted that it was common practice in the
building
industry for the contractor to retain a percentage of
payments made to its sub-contractors, the amount of which would be
reimbursed
if they executed their contractual obligations properly.
Had the contract with Winlite run its course, the Second Appellant
would
have retained ten per cent of all payments against the
subcontract tender price of R 1 368 000, i.e., R136 800.
The Second
Appellant would have returned the amount retained if
Winlite had completed its obligations properly or deducted an
appropriate
amount for defective work. The ten per cent retained was
the Appellant's money, paid to them by the DPW against the contract
price.
They did not have to declare the amount retained to the DPW or
return it when Winlite defaulted.
96.
Winlite did default, and the Appellants suffered considerable loss
for
their account in appointing another subcontractor to dismantle
Winlite’s defective work on the two screens, redo the
installation
and install the other screens afresh. The First
Appellant testified that the ten per cent retained had been used
towards the costs
of the new subcontractor. The DPW had deducted the
full amount it paid to the Appellants as an advance from the final
statement
of account as the guarantee had been rejected. The First
Appellant testified that if anyone was entitled to receive the ten
per
cent retention, it could have only been Winlite. However, Winlite
defaulted, costing the Appellants much more than the contract
price
with Winlite to rectify Winlite’s defective work.
97.
On completion of the work, the DPW and the Principal Agent compiled
the
final statement of account. The First Appellant and his brother
testified that the DPW had omitted the line item, i.e., the advance
payment for materials held offsite. The omission, in effect, amounted
to a subtraction of the advance amount from the final tender
price.
The DPW attempted to short-change the Appellants for an error they
perpetrated and admitted to regarding the guarantee.
They could not
use the guarantee to reclaim the amount expended on the remaining
materials for the third and fourth screens. None
of the State
witnesses could testify to the final statement of account and whether
the payment for materials held offsite was omitted
from the account
or whether the DPW had subtracted the amount from the Appellants'
tender price.
98.
There is a logical explanation for the Appellants’ contention
that
the DPW had, by omitting the item for materials held offsite,
effectively deducted R519 037.90 from the contract price. The
final account is defined in the JBCC as a document prepared by the
principal agent which reflects the contract value of the works
at
final completion or termination. A statement of account in the
context of a building contract would list the services provided
by
the contractor and the payments made by the employer. It reconciles
the two to determine whether a balance is owed or an overpayment
is
made. The DPW deleted the line item for materials advanced to the
Appellants as it had already paid for it. Suppose one understands
the
testimony of the First Appellant that the omission amounted to a
deduction. In that case, it means that whilst the DPW deleted
the
line item, it retained its payment for the materials held offsite.
Proper accounting would have required the DPW to deduct
the
R519 037.90 from its payments to achieve an equitable
reconciliation of services provided against payments made.
99.
The computation of the final statement of account supports the First
Appellant’s
allegation in paragraph 33 of the founding
affidavit. He contended, "Although the sum had been included in
an interim payment
certificate, it was not omitted from the final
account, which means that the Second Appellant has not been paid for
the said materials”.
As alluded to, an equitable reconciliation
would have necessitated the DPW omitting the payment of R519 037.90
from the final
statement if it omitted the line item for the cost of
materials held offsite.
100.
The final statement computed by the Principal Agent is complex,
including additional payments,
inflationary adjustments, and other
omissions. It required explaining by the personnel qualified to
explain it. The State opted
not to call any of these personnel,
although the State indicated its intention to call Ms Van Den Hoven
from the DPW. Van Den Hoven
would have been able to indicate why the
DPW agreed to pay the amount of R519 037.90 after the Second
Appellant instituted
an application in this court and had taken an
order by agreement to this effect. Ms Van Den Hoven would have been
in a position,
together with any of Mr Williams, the project manager,
Mr Logie, the Principal Agent, or the Quantity Surveyor, to interpret
the
final statement of account. None of the witnesses called by the
State, i.e., Adams, Ricketts, Amon, or Carriem, could comment on
the
final statement of account. The analysis thus far is in sync with the
evidence.
101.
This court then turns to deal with the appeal. At first blush, the
judgment of the Regional
Court strikes the reader as a well-written
and reasoned treatise. It is structured into logical parts and quotes
ample caselaw
and legal writers supporting the conclusions reached.
It summarises the case for the State and the Defence. It provides a
theoretical
framework for the types of theft, the evaluation of
witness testimony, and quotes excerpts of the evidence to support its
findings.
There is nothing to fault the judgment in these respects.
The judgment follows the tenor of the Regional Court's control over
the
proceedings during the trial.
102.
The Regional Court granted the Appellants leave to appeal against
their convictions on
counts two and three. The Appellants did not
appeal the sentence imposed. The Magistrate provided her reasons for
granting leave
to appeal. The Magistrate surveyed her judgment and
concluded that she may have erred on one aspect, i.e., the ambit of
the theft
charge.
103.
The Regional Court stood by its reasons for the judgment on count 2
of theft. It referred
to the reasons for rejecting the First
Appellant’s defence of negligent mistake regarding perjury. It
rejected the First
Appellant’s further defence that he did not
properly read his affidavit before he signed it. The Regional Court
then referred
to the State’s opinion that a reduced amount was
stolen, not the amount mentioned in count 2 of the charge sheet. The
Regional
Court believed that justice must be seen to be done, and
open justice enhances confidence in the South African Criminal
Justice
process. Because of a possible assets forfeiture application
arising from the theft charge, the Regional Court accepted a slight
possibility that an appeal court may take a different view on the
Regional Court’s judgment on the findings of fact or the
conclusions of law.
104.
This court takes its cue to determine this appeal from the concession
that the Regional
Court makes, i.e. the extent to which the State had
whittled the amount involved in the second count of theft. As alluded
to in
the earlier part of this judgment, the fact that the State had
changed its focus from obtaining a conviction on the theft of
R519 037.90
to just ten per cent of it had become apparent at
the
section 174
hearing. At that juncture, The State conceded that
the DPW had made an advance payment for materials held offsite. The
failure
of the State to call witnesses to testify to the final
statement of account and the State’s written argument gave the
first
hint that it could not prove the full extent of the theft
charge on count two. The State's failure to prove that the Appellants
stole R519 037.90 from the DPW became manifest in its
cross-examination of the First Appellant and his brother and its
final
submissions on conviction and sentence. The Regional Court
inexplicably failed to detect this shift in the State’s case.
105.
During oral argument, the State Prosecutor readily conceded that she
failed to prove the
theft charge per the charge sheet. She conceded
further that the State had abandoned proving the full ambit of count
two of the
theft charge as early as the close of the State’s
case in the trial. The State Prosecutor, however, maintained that the
Appellants
had been convicted of theft of ten per cent of the
advance. This submission cannot be sustained. The charge sheet did
not provide
for a charge of theft on a lesser amount, nor was there
any attempt to amend it. The Regional Court noted that the State did
not
charge the Appellants for the theft of R51 903. 70 and
declined to convict them for the theft of the ten per cent of the
advance
they allegedly retained. The State did not cross-appeal the
judgment.
106.
Is this a material error and misdirection of the Regional Court? The
answer has to be in
the affirmative. The Regional Court found the
Appellants guilty of a crime that the State could not prove, let
alone prove beyond
a reasonable doubt. The charge of theft on count 2
has to be overturned. It is a misdirection of fact and law. The
Regional Court
erred in its assessment of the evidence and the
application of the law in determining whether the Appellants were
guilty of theft.
The misdirection is serious and would be prejudicial
to the Appellants and an injustice if the conviction on count 2 is
not overturned.
The State has to shoulder some, if not all, blame for
the conviction. The State had the opportunity to spell out its
position and
categorically disclose that it had not proven the count
of theft per the charge sheet.
107.
What of the other grounds of appeal raised by the Appellants? There
is much merit in almost
all of them. This court must remark on the
other errors and misdirections manifest in the Regional Court’s
judgment and will
do so briefly. It does not mean this court finds
sufficient merit in each ground, but cumulatively, there would have
been sufficient
grounds to overturn the conviction of theft even if
the State’s concession had not been forthcoming.
108.
The
Regional Court’s failure to analyse the evidence of the First
Appellant and his brother before rejecting them as lies
is strikingly
evident. The evidence of the First Appellant and his brother were
credible and consistent with each other. They protested
that the
State Prosecutor did not understand the building industry and its
idiosyncrasies. They consistently maintained that the
DPW omitted the
item for materials from the final statement of account and had
thereby deducted the amount of R519,037.90 from
the amount due to
them. The State Prosecutor was unable to unsettle their evidence in
this crucial aspect. The Regional Court's
finding that the defence
raised by the Appellants was all lies is an error. The Regional Court
concentrated on all the elements
that pointed to their guilt in
analysing the charges but failed to grasp or consider the
probabilities or those indicative of their
innocence.
[37]
109.
The Regional Court’s finding that the Appellants were not
entitled to the ten per
cent retention is also an error. It did not
accord with the evidence. The State and the court failed to grasp the
significance
of Carriem’s testimony that the State is reluctant
to make advance payments. The payment made to the Appellants
contractor
was exceptional. The court should have viewed the ten per
cent retained by the Appellants for materials held offsite in that
context.
The contract between the Appellants and Winlite did not make
provision for the advance payment, which eventuated from the delayed
police clearances and which was intended to benefit the DPW in
reduced costs. The Appellants' contract with Winlite included the
costs of materials used. The payment for the materials would have
been included as a progress payment had it occurred in the normal
course of the building works. The Appellants were entitled to
withhold ten per cent of the advance paid, as the First Appellant
and
his brother confirmed in testimony.
110.
The failure of the Regional Court to deal with the concession made by
State witness Adams
about exhibit “V” and the
implications of that testimony was also an error. Adams testified
that the investigation
would not have proceeded had he known of the
Winlite invoice. Adams’ investigation was cursory. He failed to
interview the
key personnel to determine whether the DPW had omitted
the item for materials held offsite. The Defence’s presentation
of
the invoice elicited a capitulation in his stance. The Appellants
described this part of the cross-examination as a Damascus moment
for
Adams. The court cannot disagree with the characterisation. Adams’
investigation proceeded on a tenuous basis, i.e.,
whether the payment
made to Winlite was a payment for materials held offsite or a
progress payment. He saw the papers in the application
and concluded
that it was a double payment without interrogating why the DPW had
agreed to settle the matter.
111.
The conviction on the second count of theft was based entirely upon
the amount realised
pursuant to the application. The charge sheet
framed the charge as ongoing from 2011 to 2015. This is yet another
reason why the
theft charge would have been unsustainable. The
Magistrate paid little attention to material aspects of the evidence,
including
the significance of exhibit “V” and Adams's
testimony that the SIU’s investigation would have been
abandoned
if he had sight of this invoice. The Magistrate failed to
deal with Adams' sources of information, particularly the input from
Winlite, which proved incorrect. As alluded to, the evidence of the
State witnesses escaped critical scrutiny by the lower court.
The
Magistrate found that the Appellants did not intentionally
misrepresent the errors in the founding affidavit in the context
of
the fraud count. Still, they intentionally misrepresented the errors
for the conviction on the theft charge. The findings are
contradictory.
112.
The court turns to deal with the conviction on count 3, the perjury
charge. The First Appellant
was charged with perjury, alternatively,
making a false statement in an affidavit in contravention of
section
9
of Act 16 of 1963. The State relied upon the same three paragraphs
of the founding affidavit, namely 14,19 and 39, to prove the
perjury
charge. The State elaborated on the count by contending that the High
Court would not have granted the order had the misrepresentation
and
lies not been made in the First Appellant’s founding affidavit.
It is inconceivable how the State intended to prove this
facet of the
charge. We do know that it did not.
113.
In its reasons for conviction on this count, the Regional Court
referred to the reasons
it gave in its judgment for rejecting the
First Appellant’s defences, which amounted to him making a
negligent mistake and
that he did not properly read his affidavit
before he signed it. The court reminded itself of the elements of the
crime, namely
that the perpetrator (i) made a declaration that is
(ii) false, (iii) under oath, (iv) in the course of judicial
proceedings,(v)
that was unlawful, and that he had the intent to do
so.
114.
The First Appellant alleges that the Regional Court erred and
misdirected itself by rejecting
the evidence that the statements on
which the perjury charge was based were not material, were mistakes,
and were never made to
supply false information. The Appellants
argued that “the High Court order was never rescinded and
accordingly if it is accepted
that the High Court order excused any
underlying lie and theft, the Appellants should have been acquitted
on all charges”.
The Appellants seek to draw a conclusion from
two premises. The Appellants' foray into syllogisms is a non
sequitur. A more considered
view would be that if the application ran
its course, the DPW would have had to submit an answering affidavit.
As they were
au fait
with the facts, the errors would have
probably been exposed and corrected in reply.
115.
The State argued that the judgment accords with the proven facts on
the count of perjury.
This court cannot agree. The First Appellant
admitted in his plea explanation that the amount the Second Appellant
paid to Winlite
and the amount reflected as the tender price under
the subcontract was incorrect. There are mitigating factors relating
directly
to these errors. The Appellants ultimately wanted to be paid
the R519 037.90 that was omitted and deducted from the final
account statement. This court’s findings on the computation of
the final statement of account lend credence to the amount
claimed by
the Appellants.
116.
The First Appellant explained that he had erred in stating that the
subcontract price amounted
to R1 900 000. The subcontract
price was R1 368 000. The price tendered by the
subcontractor replacing Winlite
was R1 900 000. The
incorrect amount reflected in the founding affidavit can be accepted
as an error. In paragraph 39
of the affidavit, the First Appellant
alleged that the DPW had not compensated the Appellants for the
advance made on its behalf.
The computation of the final statement of
account indicates that the allegation is correct.
117.
In the context of the findings made by this Court on the theft count,
the explanation for
the mistakes seems more credible. The information
in the founding affidavit was provided by the First Appellant’s
brother
and manager. The Appellants were engaged in many other
contracts when the affidavit was drafted. Accepting the First
Appellant's
reasons for the errors contained in the founding
affidavit does not mean that this court condones errors of the nature
evident
in the founding affidavit or the adoption of a cavalier
attitude towards drafting affidavits. The First Appellant testified
that
his attorney drafted the affidavit based on documents provided
to him. He testified further that Senior Counsel finalised the
affidavit.
He repeatedly testified that the errors were not
misrepresentations and that the Appellants did not intend to defraud
the DPW.
There is no reason to disbelieve him. Counsel for the
Appellants submits that this is a more probable explanation for the
errors.
The lawyers must share some or much blame for the facts in
the First Appellant’s affidavit.
118.
The Regional Court erred in convicting the First Appellant on the
third count of perjury.
The First Appellant did not have the
mens
rea
to misrepresent the allegations in the founding affidavit.
The conviction on count 3 cannot stand.
119.
The charge sheet distinguished the different counts and their
alternatives by attributing
dates to them. An overall analysis of the
facts underlying each conviction indicates that they were all based
on the errors in
three paragraphs of the allegations in the founding
affidavit. The acquittal on the fraud charge was based on the alleged
misrepresentations
in the founding affidavit. The Regional Court
found that the DPW was not induced to pay the Second Appellant as the
order stipulating
the decision to pay was taken by agreement.
120.
The alternative theft charge in count one is related to the payment
made following the
application. The acquittal on this charge occurred
because the Regional Court found that the payment following the court
order
was not duplicated. The conviction of theft on count two was
based entirely upon the errors in the founding affidavit, and so was
the perjury charge. The Appellants correctly identified these charges
as duplicate charges.
121.
The Regional Court acquitted the Appellants on the fraud charge based
upon the errors contained
in the founding affidavit but charged the
Appellants on the theft charge in count two and the perjury charge in
count three with
intentional misrepresentation on the same set of
errors in the founding affidavit. The charge sheet framed the second
count of
theft as an ongoing offence from March 2011 to the trial
date. The conviction was entirely premised on the founding affidavit
deposed
in September 2015. Whether the court of appeal applies the
single intent, continuous transaction, or the evidence tests to the
acquittals and convictions, it comes to the same conclusion. There
was a duplication of charges requiring the attention of the Regional
Court before it convicted the Appellants. Common sense, as the SCA
advocates, would have militated against double convictions that
flow
from the same narrow set of facts.
122.
Considering all the evidence rendered by the State witnesses, the
First Appellant, and
his brother, the concessions made by the State
Prosecutor, and the misdirections and errors evident in the Regional
Court’s
judgment, this court finds that the appeal should be
upheld. It follows that the conviction on sentence must fall away.
ORDER
123.
The appeal is upheld.
124.
It follows that the sentence on conviction cannot stand.
Bhoopchand
AJ
I
agree, and it is so ordered.
Kusevitsky
J
Judgment
was handed down on Thursday, 12 September 2024, and delivered to the
parties by e-mail.
Appellant’s
Counsel: W King SC
Instructed
by S Pienaar, Enderstein Van der Merwe Attorneys,
Respondents
Counsel: State Advocate R Harmse
Specialised
Commercial Crimes Unit, Bellville.
[1]
Two other types of sub-contractors are referred to in the JBCC
agreements, namely nominated and selected sub-contractors.
[3]
The Notice of Motion is dated 22 September 2015. First Appellant’s
wife became a member of the CC on the 15 April 2015
and his brother,
a member on the 9 December 2016.
[4]
The word “not” is correct, as the evaluation later in
this judgment reveals.
[5]
Invoice 1, dated 19 November 2010, was for R598 272 for a
progress claim for November 2010; invoice 2 was dated 19 April
2011
and reflected an amount of R166 946.65 and an outstanding
amount of R131 140.89 from Nov 2010. The difference
between the
amount invoiced for November 2010 and the outstanding balance from
November 2010 amounts to R467 131.11- the
advance amount paid
by the Second Appellant to Winlite. The first invoice of R598272 was
the amount reflected in the guarantee.
[6]
The evidence reflected that the materials kept off-site were
initially valued at R598 272, but on inspection of the
materials
by the Project Manager and Quantity Surveyor, the value of
materials was reduced to R519 037.90
[7]
Adams probably suggested that the Second Appellant had pocketed the
advance made for materials and had not paid its sub-contractor.
[10]
This is incorrect. The advance payment for materials held off-site
was for all four screens.
[11]
This is incorrect, as the brothers pointed out that the DPW had no
contract with Winlite. Hence, Winlite approached them to ask
the DPW
for an advance ahead of the anticipated increase in the price of the
materials.
[12]
The brothers testified repeatedly that the amounts were legally due
to them.
[13]
This is incorrect. The First Appellant testified that the payment
was made on the 14 March 2024. The Appellants bank statements
confirms the payment date as the 14 March 2011.
[15]
This is probably a typing or transcribing error.
[16]
The evidence led at the trial contradicts this finding.
[17]
A concise summary of the principles relating to an appeal on the
findings of fact is provided in Lehloka v S (A213/21)
[2022] ZAWCHC
34
(16 March 2022) (“Lehloka”) (unreported) at para 12
[18]
R v Dhlumayo and Another
1948
(2) SA 677
(A) at 705-706, : S v Francis
1991
(1) SACR 198
(A) at 204E
[19]
S v Monyane and Others
2008
(1) SACR 543
(SCA)
[20]
R v Dhlumayo and Another
1948 (2) SA 677
(A) at 706; S v Kebana
2010
(1) All SA 310
(SCA) para 12, S v Pistorius
2014 (2) SACR 315
(SCA)
par [30]
[21]
Makate v Vodacom Ltd 2016 (4) SA 121 (CC)
[22]
See CWH Schmidt and H Rademeyer
Law
of Evidence
(Services Issue 21, May 2023) at 3-40, and the cases cited
[23]
S v Mbuli
2003
(1) SACR 97
(SCA) at 110D-F; S v Jackson
1998
(1) SACR 470
(SCA) and S v Schackell
2001
(4) SACR 279
(SCA)
[24]
S v Combrinck
2012
(1) SACR 93
(SCA) at para 15, Lehloka (Supra)
[25]
S v V
2000
(1) SACR 453
(SCA) at 455B, Lehloka (Supra)
[26]
S v Sithole and Others
1999
(1) SACR 585
at 590, Lehloka (Supra)
[27]
State v Sarah Prins
(D997/2002)
[2003] ZAWCHC 40 (29 August 2003)
,
S v Grobler en ʼn Ander
1966 (1) SA 507
(A) at 523B; S v Tantsi
1992 (2) SACR 333
(TK) at 334f; S v Davids
1998 (2) SA 313
(C) at
316B
[28]
R v Kuzwayo
1960 (1) SA 340
(A) at 344B
[29]
S v Grobler (supra) at 513G
[30]
R v Sabuy : 1905 TS 170
[31]
Bam v S (A144/18)
[2020] ZAWCHC 68
;
[2020] 4 All SA 21
(WCC);
2020
(2) SACR 584
(WCC) (20 July 2020)
[32]
R v Gordon 1909 EDC 214
[33]
R v Johannes
1925 TPD 782
, Ex Parte Minister of Justice: In re Rex v
Moseme
1936 AD 52
; S v Grobler en ʼn Ander (supra) at 518AF; S v
Wehr
1998 (1) SACR 99
(C) at 100
[34]
Hoexter, Cowling et al SA Criminal Law & Procedure Vol 3 Chp 3,
C2-C3 as cited in Bam v S (supra) at paragraph 33
[35]
S v Nyumbeka
2012 (2) SACR 367
(WCC)
[36]
S v BM
2014
(2) SACR 23
(SCA) at para [3] followed in S v McRae & Ano 2014 (2) SACR 215
(SCA)
[37]
S v Tshabalala,
2003
(1) SACR 134
(SCA) at page 140 A-B
sino noindex
make_database footer start
Similar Cases
R.B and Another v S (Bail Appeal) (A74/2024) [2025] ZAWCHC 216 (23 May 2025)
[2025] ZAWCHC 216High Court of South Africa (Western Cape Division)98% similar
Reggio and Another v Regional Magistrate, Bellville and Another (Leave to Appeal) (18554/23) [2025] ZAWCHC 538 (20 November 2025)
[2025] ZAWCHC 538High Court of South Africa (Western Cape Division)98% similar
C.H v A.C and Others (13612/2024) [2024] ZAWCHC 245 (4 September 2024)
[2024] ZAWCHC 245High Court of South Africa (Western Cape Division)98% similar
Reggio and Another v Regional Magistrate, Belville Specialised Commercial Crimes Court (Mrs Sonnenberg) and Others (18554/2023) [2025] ZAWCHC 50 (14 February 2025)
[2025] ZAWCHC 50High Court of South Africa (Western Cape Division)98% similar
S.P v S.B and Another (Leave to Appeal) (2025/054457) [2025] ZAWCHC 528 (14 November 2025)
[2025] ZAWCHC 528High Court of South Africa (Western Cape Division)98% similar