Case Law[2024] ZAWCHC 361South Africa
Charl Electrical Engineering CC v Integrated Projects Construction (Pty) Ltd (20167/23) [2024] ZAWCHC 361 (11 November 2024)
High Court of South Africa (Western Cape Division)
11 November 2024
Headnotes
Summary Introduction
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 361
|
Noteup
|
LawCite
sino index
## Charl Electrical Engineering CC v Integrated Projects Construction (Pty) Ltd (20167/23) [2024] ZAWCHC 361 (11 November 2024)
Charl Electrical Engineering CC v Integrated Projects Construction (Pty) Ltd (20167/23) [2024] ZAWCHC 361 (11 November 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_361.html
sino date 11 November 2024
IN THE HIGH COURT OF
SOUTH AFRICA
WESTERN CAPE DIVISION,
CAPE TOWN
Case number: 20167/23
In the application
between:
CHARL
ELECTRICAL ENGINEERING CC
Applicant
and
INTEGRATED
PROJECTS CONSTRUCTION (PTY) LTD
Respondent
Before:
The Hon. Mr Acting Justice Montzinger
Hearing:
12 August 2024
Judgment
Delivered electronically: 11 November 2024
JUDGMENT
Montzinger AJ
Summary Introduction
1.
This is an opposed application for the provisional
winding-up of the respondent.
2.
The
applicant, ("Charl Electrical"), instituted this
application, alleging that the respondent, ("Integrated
Projects"),
is unable to pay its debts as envisaged by s 344(f)
read with s 345 of the 1973 Act
[1]
.
It is further alleged that Integrated Projects is deemed insolvent by
virtue of its failure to comply with a demand issued in
terms of s
345(1)(a)(i) of the 1973 Act. Lastly, Charl Electrical alleged that
given the facts and circumstances of this case,
it would in any event
be just and equitable for the court to order Integrated Projects’
provisional winding-up in terms of
s 344(h) of the 1973 Act.
3.
By the time the matter was assigned to me for
hearing, several interlocutory procedural issues remained unresolved.
These included
an objection to the urgency of the application, an
opposition to Charl Electrical’s request for condonation for
the late
filing of its replying affidavit, and Integrated Projects’
interlocutory application to file a further answering affidavit
in
terms of uniform rule 6(5)(e). At the commencement of the hearing,
Mr. Engela for Charl Electrical and Mr. Walters for Integrated
Projects informed me that these issues had been resolved.
Consequently, the objection to urgency was no longer pursued,
Integrated
Projects’ request to file an additional answering
affidavit was no longer contested, and Charl Electrical’s
condonation
application for the late filing of the replying
affidavit, was no longer opposed. An order that provides for these
results will
be issued.
Charl Electrical’s
claim against Integrated Projects
4.
Charl Electrical operates in the construction
industry, regularly acting as a consultant and subcontractor to
provide electrical
services for property development projects. In
November 2022, it alleged to have entered into an agreement with
Integrated Projects
to serve as its electrical subcontractor for the
Kings Corner residential property development. The value of the
contract to render
the electrical services was allegedly
R1,244,088.48. The Kings Corner project was developed by Prospekt
(Pty) Ltd ("Prospekt"),
with Integrated Projects the main
building contractor.
5.
Charl Electrical alleged that under the
subcontractor agreement it performed electrical work at the Kings
Corner development from
December 2022 to June 2023. During this
period, it issued six invoices to Integrated Projects totalling
R522,327.11, of which only
an amount of R103,623.30 was paid.
6.
Due to the non-payment of its invoices, Charl
Electrical in August 2023 served Integrated Projects with a demand in
terms of s 345
of the 1973 Act for payment of R418,703.81. Integrated
Projects failed to satisfy the demand and on 13 November 2023 the
liquidation
application was launched.
7.
Mr. Engela, argued that Charl Electrical have
established the
prima facie
existence of a debt as well as the other
requirements for liquidation. He also argued that the defences raised
in opposition to
the application are without merit. According to Mr.
Engela the denial by Integrated Projects of the existence of the
subcontractor
agreement is baseless as the evidence overwhelmingly
shows that a contractual relationship existed. He argued that since
all the
other requirements for a liquidation have been complied with,
I should grant provisional winding-up order and not exercise my
discretion
against doing so.
8.
In response to my concerns about disputes of facts
in particular on the issue of Integrated Projects’ liability,
Mr. Engela
urged me to "see the wood for the trees," and to
disregard any attempt to create factual disputes.
The basis for opposing
the liquidation application
9.
The case for Integrated Projects is that the
evidence clearly shows there was no privity of contract between it
and Charl Electrical
and that if an agreement existed, it was between
Charl Electrical and Prospekt, the property developer. In support of
its contention
Integrated Projects claims that the written part of
the alleged agreement, on which Charl Electrical relies, is an
Occupational
Health and Safety agreement, which has no relevance to
the electrical work for which payment is claimed.
10.
Furthermore, it is Integrated Projects’ case
that any work performed by Charl Electrical was carried out under the
instructions
of Prospekt and that Charl Electrical mistakenly sent
its invoices to Integrated Projects. The explanation for making the
payments
totalling R103,623.30 to Charl Electrical was done at
Prospekt’s request.
11.
Mr. Walters argued that Charl Electrical failed to
prima facie
establish
the existence of its claim. He added that even if a
prima
facie
claim could be established, it is
disputed on
bona fide
and
reasonable grounds, warranting a dismissal of the application.
The relevant legal
principles
12.
A
creditor seeking a winding-up order of an insolvent company must do
so in terms of the provisions of the 1973 Act
[2]
.
In addition to the aforementioned an applicant must convince the
court that: (i) it is a contingent or prospective creditor of
the
company to be liquidated
[3]
(i.e. the
locus
standi
requirement);
(ii) the respondent company’s registered address is situated in
the Court’s jurisdictional area
[4]
;
(iii) it has established one of the grounds listed in s 344(1)(a –
h) read with s 345 (1)(a – c) of the 1973 Act.
13.
The
Constitutional Court has confirmed that the overarching objective
behind liquidation proceedings is that it is designed to bring
about
a concurrence of creditors to ensure an equal distribution of the
insolvent estate between them. It is for this reason that
liquidation
proceedings are inappropriate to resolve a dispute as to the
existence of a debt
[5]
. The
Court, in the majority judgment, stated the position, with reference
to the
Badenhorst
principle
[6]
,
as follows:
“…
That
principle is less of a principle than a sensible rule of practice.
It says that if you want to claim a debt you know
is disputed, you
should not bring liquidation proceedings to do it. You should
claim the debt by way of action – and
only once your claim has
been established may you, if necessary, seek to liquidate or
sequestrate.”
[7]
14.
With
regards to the threshold an applicant seeking the provisional
liquidation of a respondent company must clear, the position
is that
the applicant must establish its entitlement to an order and the
existence of its claim
[8]
, where
it is disputed,
prima
facie
on
a balance of probabilities with reference to the affidavits
[9]
.
15.
However,
a court should draw a distinction between disputes regarding the
respondent company’s liability to the applicant
and ‘other
disputes’
[10]
. The
‘other disputes’ is a reference to the rest of the
requirements to succeed with a liquidation application, apart
from
the
prima
facie
existence
of the claim. The test to resolve a dispute with regards to the
‘other requirements’ is whether the balance
of
probabilities favours the applicant's version on the papers. If the
liability of the respondent is not established, it matters
not that
the applicant has established the ‘other requirements’.
16.
In
respect of the meaning of the words ‘
prima
facie’
the
court in
Kalil
v Decotex
explained
that it does not mean the same as the term is normally used i.e.:
in the
absence of re-butting evidence.
The
requirement ‘
prima
facie’
rather
means: “…
as
denoting a balance of probabilities on all the affidavits…”
[11]
.
It therefore means that a court having to decide a contested
liquidation application, at the provisional order stage, does not
call into aid the help of the so-called
Plascon-Evans
rule,
which requires a court to accept the allegations by the respondent
unless they constitute bald or uncreditworthy denials or
are palpably
implausible, far-fetched or so clearly untenable that they could
safely be rejected on the papers
[12]
.
Although the
Plascon-Evans
rule
is available to the court at the final order stage of the liquidation
proceedings
[13]
.
17.
In
determining the probabilities on all the affidavits I follow the
well-established approach as set out in
Govan
v Skidmore
[14]
to:
“…
select
a conclusion which seems to be the more natural, or plausible,
conclusion from amongst several conceivable ones, even though
that
conclusion be not the only reasonable one”.
This
being motion proceedings I also stay clear from any credibility
findings to determine the probabilities. This is consistent
with the
approach that was endorsed in
National
Employers
[15]
where the court held that it is possible to arrive at a decision
simply on the probabilities without having to make specific findings
on the credibility of the witnesses
[16]
.
18.
If an
applicant can
prima
facie
establish
its claim a respondent can dispute the claim
bona
fide
and
on reasonable grounds
[17]
.
With regards to evaluating the
bona
fides
and
reasonableness of a respondent’s opposition to an applicant’s
claim, the legal position is that
bona
fides
in
the (true) sense of good faith has nothing to do with the matter, as
bona
fides
(genuineness)
is on any reckoning not on its own sufficient to make a finding that
the claim is disputed on substantial (i.e. reasonable)
grounds
[18]
.
19.
Therefore
a court faced with an opposed liquidation application first determine
whether the respondent is indeed indebted to the
applicant. If so, it
would mean that the applicant has
prima
facie
established
the claim. Thereafter, the court considers whether the claim is
bona
fide
disputed
on reasonable grounds with reference to the
Badenhorst
rule
[19]
.
If the claim cannot be disputed in terms of the applicable test, the
rest of the requirements for a liquidation is then considered.
However, should a court find that the applicant could not
prima
facie
establish
its claim because there is a real and genuine factual dispute
regarding the respondent’s indebtedness, an applicant
can ask
the court to refer the disputed issues to oral evidence
[20]
.
However, if a court finds that the applicant should have anticipated
the factual dispute
[21]
a
referral to oral evidence would not serve any purpose and dismissal
of the application will be the most likely result
[22]
as the applicant would have no
locus
standi
to
further pursue the liquidation application.
20.
In
concluding on the applicable legal principles, Mr. Walters submitted
that while it is generally accepted that the applicant,
in a
liquidation application, bears the onus of establishing its claim
prima
facie
,
there is uncertainty and conflicting authority regarding how a court
should resolve disputes of facts at the provisional order
stage. I do
not find it necessary to engage in this debate or contribute to any
perceived uncertainty, to the extent that there
is such a debate. In
my view the approach articulated in
Kalil
v Decotex
remains
the guiding framework how a court should determine whether an
applicant has established its claim
prima
facie
.
This approach has been confirmed, with minor adjustments, in various
subsequent judgments
[23]
.
21.
Accordingly,
I understand the approach at the provisional stage to be, where the
respondent’s indebtedness is disputed, that
a court should take
a holistic view of all the allegations and supporting evidence
presented in the affidavits to make a finding
on the probabilities
whether the applicant has
prima
facie
established
the respondent’s indebtedness. Only once a court is satisfied
on the probabilities that the respondent’s
liability to the
applicant exists does it consider whether the respondent has raised a
bona
fide
dispute
of its liability to pay and did so on reasonable grounds
[24]
.
Evaluation
22.
After reviewing the various affidavits filed in
this matter, I am of the view that the application has to fail having
regard to
at least two hurdles that Charl Electrical failed to clear.
Firstly, it has failed to establish a
prima
case
of Integrated Projects’
liability in its founding affidavit. Secondly, even if the first
hurdle could be cleared, it has failed
to establish, on the
probabilities, a
prima facie
case demonstrating that it has a claim against
Integrated Projects.
Case not made out in
the founding affidavit
23.
Since,
I am dealing with an opposed motion, as per
Room
Hire
[25]
and
Telcordia
[26]
,
the applicant must still make out a case in the founding affidavit.
In this matter the founding affidavit presented a case that
the
parties allegedly concluded a partly written, partly verbal agreement
for electrical work to be performed at the King’s
Corner
development for the total sum of R1,247,088.48, payable by way of
monthly progress claims. Reliance was placed on invoices
that were
issued to Integrated Projects, by a quantity surveyor, to the value
of R522,327.11 and of which an amount of R103,623.20
was paid.
24.
Integrated Projects filed a comprehensive
answering affidavit. It disclosed information which was within the
knowledge of Charl
Electrical and which should have formed part of
the allegations in the founding affidavit. In its replying affidavit,
which was
filed significantly late, the reason for the late filing
was because Charl Electrical: “…
was
not aware of the mammoth task that would be involved in preparing its
replying affidavit
and also because its
attorneys had to: “…
consult
not only Prospekt and its attorney, but to consult with other
professionals on the project in order to obtain documentary
evidence
which illustrates the extent of the contrived position adopted in the
answering affidavit…”
Charl
Electrical ultimately filed a detailed replying affidavit, which
prompted Integrated Projects to apply for leave to submit
a
supplementary answering affidavit. This, in turn, led to Charl
Electrical filing an additional replying affidavit.
25.
The consequence of all the affidavits filed was
that Charl Electrical relied on allegations and evidence not included
in its founding
affidavit to persuade the court that it has a
prima
facie
claim against Integrated
Projects. From the contents of the replying affidavit, the written
heads of argument, and oral submissions,
it is clear that Charl
Electrical requires the court to accept at least the following to
establish its claim against Integrated
Projects:
25.1
The existence of the JBCC agreement and that all
sub-contractors would have been appointed by Integrated Projects.
25.2
Also, that the JBCC agreement provides that there
shall be no privity of contract between Prospekt and a subcontractor
appointed
by Integrated Projects.
25.3
a WhatsApp message from Mr Heunis (obo Prospekt)
to Mr Cloete of Quansur on 15 December 2022 that presupposes an
obligation on Integrated
Projects to pay Charl Electrical when it is
appointed as a sub-contractor.
26.
The JBCC agreement therefore emerged as a central
document in this case. Charl Electrical placed considerable reliance
on it, not
only to counter the defences raised by Integrated Projects
but effectively to "complete its cause of action." Charl
Electrical
with hindsight advanced the case that the JBCC agreement
imposed an obligation on Integrated Projects to appoint
subcontractors
and precluded any direct contractual relationship
between a subcontractor and the developer (Prospekt).
27.
All this means that Charl Electrical has presented
its case in a manner that left Integrated Projects unclear about the
case it
needed to answer. This is evident from the multiple sets of
affidavits filed.
28.
The
application must therefore fail because Charl Electrical has not made
out a case in its founding affidavit. It appears that
Charl
Electrical mistakenly relied on the principle that a court must
determine whether an applicant has established its entitlement
to an
order and the existence of its claim
[27]
on a balance of probabilities with reference to the affidavits.
However, in the context of an opposed liquidation application,
"reference to affidavits" does not absolve an applicant
from the obligation to set out its case fully in the founding
affidavit. The notion that a party can present an incomplete case in
its founding papers, supplement it through an extensive replying
affidavit, and then rely on the court's duty to consider "all
the affidavits" is untenable. Such an approach would undermine
the purpose of liquidation proceedings, allowing for an endless
exchange of affidavits in an attempt to build a claim retroactively,
and would ultimately make a mockery of the process.
29.
I am therefore not persuaded that Charl Electrical
has made out its case in the founding affidavit. Consequently, this
on its own
justifies a dismissal of the application.
The existence of a
prima facie claim
30.
Considering, my finding on the deficient founding
affidavit I do not have to continue any further to consider the
application. However,
to the extent that I may be wrong, or be
criticised for a strict application of the
Room
Hire
and
Telcordia
requirement in motion proceedings, I in any event
will now consider all the affidavits and consider whether Charl
Electrical has
established on the probabilities whether it has a
claim against Integrated Projects.
31.
Charl Electrical must make out a
prima
facie
case on the probabilities that a
subcontractor agreement was concluded between it and Integrated
Projects. I am not convinced that
the probabilities support such a
conclusion.
32.
Firstly,
it was alleged that a ‘partly written, partly, oral agreement’
was concluded between the parties in November
2022. The allegations
in respect of the agreement did not have regard to how an agreement
is ordinarily pleaded
[28]
as
provided for in uniform rule 18(6). It was not clear which terms of
the agreement were ‘written’, and which were
‘oral’.
There were also no allegations throwing light on who represented the
parties at the time the agreement was
concluded during November 2022
and or June 2023, or where the alleged oral and written parts of the
agreement were respectively
concluded.
33.
I am
mindful of the fundamental distinction between a cause of action
[29]
for the recovery of a debt and the factual basis required to
establish an enforceable claim for the liquidation of a company
[30]
.
However, in this case, where liability is not admitted and the court
must be guided by the probabilities to determine whether
the
applicant’s claim has been
prima
facie
established,
Charl Electrical’s failure to adequately set out the facts
supporting the existence of the alleged subcontractor
agreement in
its founding affidavit is detrimental to its case.
34.
Secondly, the written portion of the agreement was
concluded on 15 June 2023. It seems to me that on the probabilities
this document
is rather intended to regulate Charl Electrical’s
obligations in terms of the Occupational Health and Safety Act, 85 of
1993
(the “OHSA”), if regard is had to the following:
34.1
The document is identified as an agreement on
occupational health and safety in terms of the provisions of s 37(2)
of the OHSA.
34.2
The purpose of the document is described as
follows:
“
The
Contractor acknowledges that this agreement constitutes an agreement
in terms of Section 37(2) of the OHSA, whereby all responsibility
for
health and safety matters relating to the work the Contractor and its
workers or sub-contractors to perform on the premises
in terms of the
scope of work shall be the obligation of the Contractor.”
34.3
The only reference that may be helpful to Charl
Electrical is the fact that the document identifies the scope of work
as ‘Electrical
Installation’. However, the remainder of
the document does not support a conclusion that it has anything to do
with a sub-contractor
agreement to render electrical consultant
services at the Kings Corner development.
34.4
There is no reference to the alleged contract
value of R1,244,088.48 and the payment terms.
34.5
Although the document is not counter signed it
does appear to envisage a signature by the ‘client’.
Integrated Projects
alleged that the ‘client’ was
Prospekt, the developer. On the probabilities this seems correct as
otherwise it would
have rather made mention of ‘the
contractor’.
35.
Third, on 26 June 2023, Ms. Marieda Olivier
(“Olivier”), acting on behalf of Charl Electrical, sent
an email to representatives
of Integrated Projects requesting payment
of outstanding invoices. This was just 11 days after the alleged
conclusion of the written
portion of the agreement between Charl
Electrical and Integrated Projects. Notably, the email makes no
reference to the existence
or conclusion of the subcontractor
agreement, nor does it mention that such an agreement had allegedly
been formalised 11 days
earlier.
36.
Fourth, the full context of an email dated 14
August 2023 was not provided. The founding papers include only an
email from Mr. Chris
Heunis (“Heunis”) of Prospekt to
Olivier, in which Heunis states that “CE was appointed by the
builder.”
There is no explanation as to why Heunis felt the
need to clarify Charl Electrical’s appointment. It appears that
Olivier
sought clarification from Heunis, and he responded
accordingly. If an agreement had been concluded in November 2022 and
formalised
in June 2023, there would have been no need for such
clarification. Moreover, the probative value of Heunis’s
statement that
Charl Electrical was appointed by Integrated Projects,
as the builder, is significantly diminished by his immediate
confirmation
that he had instructed his PA to contact Charl Visser,
representing Charl Electrical, to arrange for payment, clearly on
behalf
of Prospekt. This indicates that Prospekt acknowledged a
responsibility or liability for payment to Charl Electrical.
37.
Fifth, the existence of the JBCC Principal
Building Agreement, concluded between Prospekt and Integrated
Projects on 8 August 2022,
was not disclosed in the founding
affidavit. Moreover, Charl Electrical’s role as a party or
signatory to that agreement,
whether as an agent or an electrical
service consultant, was also omitted. Charl Electrical should have
disclosed this agreement
and clarified its relevance to its claim of
being appointed as a subcontractor two months later. The only
reasonable inference
from its failure to disclose the JBCC agreement
in the founding affidavit, which was within its knowledge, is that
Charl Electrical
anticipated difficulties in reconciling its alleged
subcontractor relationship with Integrated Projects while
simultaneously maintaining
a direct relationship with Prospekt.
38.
Sixth, Charl Electrical failed to disclose in its
founding affidavit that it had submitted a direct design and costing
quote for
the Kings Corner development to Prospekt. This omission
suggests that Charl Electrical was concerned that revealing this
information
might support Integrated Projects’ contention that
a direct contractual relationship existed between Charl Electrical
and
Prospekt for the electrical work.
39.
Seventh, Charl Electrical failed to disclose the
minutes of the site meetings, which indicate that it was far more
involved in the
construction project than its claimed role as a
subcontractor suggests. The disclosure would have cast doubt on Charl
Electrical’s
assertion of being a subcontractor, as according
to the JBCC agreement subcontractors are not required to attend site
meetings
unless invited.
40.
The seven difficulties outlined above,
which are by no means exhaustive, are
sufficient to cast doubt on Charl Electrical’s case.
Therefore, having regard
to the probabilities, and without making any
credibility findings either way, I find that the most natural,
plausible, and reasonable
conclusion from the range of conceivable
ones is that Charl Electrical did not have a subcontractor agreement
with Integrated Projects.
It has therefore failed to establish that
it has a
prima facie
claim
and therefore lacks
locus standi
to pursue Integrated Projects’ liquidation.
The application must therefore fail. I see no reason to deviate from
the general
rule that, having been unsuccessful, Charl Electrical
should bear the costs.
Conclusion
41.
For all the reasons set out above, I make the
following order:
41.1
The late filing of Charl Electrical’s
replying affidavit is condoned.
41.2
Integrated Projects’ application for leave
to file a supplementary answering affidavit is granted.
41.3
The application for the provisional winding-up of
Integrated Projects is dismissed with costs, including the costs of
counsel on
scale B from 12 April 2024.
A MONTZINGER
Acting
Judge of the High Court
Appearances:
Applicant’s
counsel:
Mr. R Engela
Applicant’s
attorney:
Enderstein Malumbete Inc.
Respondent’s
counsel:
Mr. A Walters
Respondent’s
attorney:
Kemp Nabal Inc.
[1]
Companies
Act 61 of 1973 (the “1973 Act”)
[2]
In
terms of item 9(1) of Schedule 5 of the 2008 Companies Act, the
provisions of Chapter XIV of the 1973 Act continue to apply
to the
winding-up of companies under the 2008 Companies Act until the
Minister, by notice in the
Gazette
,
determines a date on which it shall cease to have effect.
Accordingly, in terms of section 343 of the 1973 Act, a
company may still be wound-up either by the Court, or voluntarily by
way of a creditors’ or a members’ voluntary
winding-up,
except for “solvent” companies mentioned in item 9(2) of
Schedule 5 of the 2008 Companies Act.
[3]
S
346(1)(b) of the 1973 Act
[4]
S 1, dealing with the
definition of court read with 12(1) of 1973 Act;
Wild
& Marr (Pty) Ltd v Intratek Properties (Pty)
Ltd
2019 (5) SA 310 (GJ)
at pars [13] and [14]
[5]
Trinity
Asset Management (Pty) Ltd v Grindstone Investments (Pty) Ltd
2017
(12) BCLR 1562
(CC) par 145 (“
Trinity
”
)
[6]
This
rule states that winding-up proceedings are not to be used to
enforce payment of a debt that is disputed on
bona
fide
and
reasonable grounds.
Badenhorst
v Northern Construction Enterprises (Pty) Ltd
1956
(2) SA 346
(T) at 347 – 348
[7]
Trinity
par
86
[8]
Orestisolve (Pty) Ltd
T/A Essa Investments v NDFT Investments Holdings (Pty) Ltd and
Another
2015
(4) SA 449
(WCC)
(“Orestisolve”)
par 7
[9]
Kalil
v Decotex (Pty) Ltd
1988
(1) SA 932
(A) at 975J-979F(“
Kalil
v Decotex
”
)
[10]
Payslip
Investment Holdings CC v Y2K Tec Ltd
2001
(4) SA 781
(C) at 783G-I (“
Payslip
Investment
”
)
[11]
Kalil
v Decotex
par
60
[12]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
[1984] ZASCA 51
;
1984
(3) SA 623
(A) at 634D-635D
[13]
Orestisolve
par
9
[14]
Govan
v.
Skidmore
,
1952 (1) S.A. 732
(N) at p. 734; Also
Ocean
Accident and Guarantee Corporation Ltd v Koch
[1963]
3 All SA 329 (A)
[15]
National
Employers’ General Insurance Co Ltd v Jagers
1984 (4) SA 437
(ECD (“National Employers”))
[16]
National
Employers 440 G - H
[17]
Orestisolve
par 8
[18]
Orestisolve
par
13
[19]
Note
6
[20]
As
per
Kalil
v Decotex
[21]
Adbro
Investment Company Ltd v Minister of Interior
1956
(3) SA 345
(A) at 350A
[22]
Freshvest Investments
(Pty) Ltd v Marabeng (Pty) Ltd (1030/2015)
[2016] ZASCA 168
(24
November 2016)
par
11
[23]
Afgri
Operations Ltd v Hambs Fleet (Pty) Ltd
2022
(1) SA 91 (SCA)
[24]
Hülse-Reutter
& Another v HEG Consulting Enterprises (Pty) Ltd
1998
(2) SA 208
(C) at 218D-219C as endorsed in
O
restisolve
par 8
[25]
Room Hire Co (Pty)
Ltd v Jeppe Street Mansions (Pty) Ltd
1949
(3) SA 1115
(T) at p 1163. (“
Room
Hire
”
)
[26]
Telcordia
Technologies Inc v Telkom SA Ltd
[2006] ZASCA 112
;
2007
(3) SA 266
(SCA) at par 32 (“
Telcordia”
)
[27]
Orestisolve
par
7
[28]
A
party who in his or her pleading relies upon a contract shall state
whether the contract is written or oral, and when, where
and by whom
it was concluded, and if the contract is written a true copy thereof
or of the part relied on in the pleading shall
be annexed to the
pleading.
[29]
As
per A
brahmse
& Sons v SA Railways and Harbours
1933 CPD 626
at 633:
Which
requires a party to allege:
the
entire set of facts which give rise to an enforceable claim and
includes every fact which is material to be proved to entitle
a
plaintiff to succeed in his claim. It includes all that a plaintiff
must set out in his declaration to disclose a cause of
action
”
[30]
The
Standard Bank of South Africa Ltd v Tsheola Dinare Tours and
Transport Brokers (Pty) Ltd
(22011/2021)
[2022] ZAGPJHC 311 (6 May 2022)
sino noindex
make_database footer start
Similar Cases
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (Leave to Appeal) (17470/2014) [2025] ZAWCHC 453 (3 October 2025)
[2025] ZAWCHC 453High Court of South Africa (Western Cape Division)98% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2025] ZAWCHC 292 (14 July 2025)
[2025] ZAWCHC 292High Court of South Africa (Western Cape Division)98% similar
Technical Systems (Pty) Ltd and Another v RTS Industries and Others (17470/2014) [2024] ZAWCHC 2 (2 January 2024)
[2024] ZAWCHC 2High Court of South Africa (Western Cape Division)98% similar
South African Legal Practice Council v Nonxuba and Another (16777/2023) [2024] ZAWCHC 410 (4 December 2024)
[2024] ZAWCHC 410High Court of South Africa (Western Cape Division)98% similar
South African Legal Practice Council v Gonzales (1949/2024) [2024] ZAWCHC 412 (6 December 2024)
[2024] ZAWCHC 412High Court of South Africa (Western Cape Division)98% similar