Case Law[2025] ZAKZDHC 64South Africa
APM Terminals BV v Transnet SOC Limited and Others (Review) (D3052/2024) [2025] ZAKZDHC 64 (10 October 2025)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Kwazulu-Natal High Court, Durban
South Africa: Kwazulu-Natal High Court, Durban
You are here:
SAFLII
>>
Databases
>>
South Africa: Kwazulu-Natal High Court, Durban
>>
2025
>>
[2025] ZAKZDHC 64
|
Noteup
|
LawCite
sino index
## APM Terminals BV v Transnet SOC Limited and Others (Review) (D3052/2024) [2025] ZAKZDHC 64 (10 October 2025)
APM Terminals BV v Transnet SOC Limited and Others (Review) (D3052/2024) [2025] ZAKZDHC 64 (10 October 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAKZDHC/Data/2025_64.html
sino date 10 October 2025
FLYNOTES:
ADMINISTRATIVE
– Tender –
Solvency
threshold
–
Non-compliance
– Purpose of solvency requirement was to ensure financial
capacity – Successful bidder demonstrated
through other
means – Request for qualifications granted Transnet
discretion to waive requirements and assess financial
capacity
holistically – Deviation from solvency formula did not
undermine purpose of requirement – Decision taken
after
extensive internal and external assessments – Rational and
reasonable – Application dismissed.
IN
THE HIGH COURT OF SOUTH AFRICA
KWAZULU-NATAL
LOCAL DIVISION, DURBAN
CASE
NO: D3052/2024
In
the matter between:
APM
TERMINALS
BV
Applicant
and
TRANSNET
SOC LIMITED
First
Respondent
INTERNATIONAL
CONTAINER TERMINAL
SERVICES
INC
Second Respondent
COSCO
SHIPPING PORTS LIMITED
Third Respondent
DP
WORLD LIMITED
Fourth
Respondent
GLOBAL
PORTS SERVICES PTE
LIMITED
Fifth
Respondent
RED
SEA GATEWAY TERMINAL
Sixth
Respondent
MMC
PORT HOLDINGS SDN BHD
Seventh Respondent
TERMINAL
INVESTMENT LIMITED
Eighth
respondent
REMGRO
LIMITED
Ninth Respondent
This
judgment was handed down electronically by circulation of the
parties’ representatives by email and released to SAFLII.
The
date for hand down is deemed to be on 10
TH
October 2025 at
10:00
ORDER
The
following order is granted:
1.
The application is dismissed.
2.
The parties are to bear their own costs, including any costs
reserved.
JUDGMENT –
REVIEW APPLICATION
Chetty J:
[1]
Writing for the Supreme
Court of Appeal (‘SCA’) in
Altech
Radio Holdings (Pty) Ltd and Others v Tshwane City,
[1]
Ponnan JA said the following regarding challenges in the field of
public procurement:
‘
Search
hard enough in public procurement cases such as this, and one will
surely find compliance failures along the way. There will
seldom be a
public procurement process entirely without flaw. But, perfection is
not demanded and not every flaw is fatal. Nor
does every flaw in a
tender process amount to an irregularity, much less a material
irregularity. Public contracts do not fall
to be invalidated for
immaterial or inconsequential irregularities. Indeed, as it has been
put, “(n)ot every slip in the
administration of tenders is
necessarily to be visited with judicial sanction”.’
(Footnote
omitted.)
The
question which arises in this matter is whether a ‘slip’
in the process of the award of a contract of national economic
importance, should be reviewed and set aside at the instance of an
aggrieved bidder, bearing in mind that
judicial
review is a discretionary remedy and it does not necessarily follow
that an invalid act will, in fact, be set aside.
[2]
[2]
The
‘slip’ in question pertains to the successful bidder not
meeting a solvency threshold (under the minimum financial
criteria
section) contained in the responsiveness phase of the tender.
[3]
Notwithstanding, it is common cause that the bidder has the necessary
financial capacity to secure investments for the development
of the
port of Durban, which both the bidder and the procuring entity submit
to be the overarching purpose of the disputed provision.
The
successful bidder trumped the second bidder by a significant margin
in the price duel.
[3]
In
light of the unique nature of the tender and the objectives which
underlie it, the question which arises is whether the non-compliance
should be condoned in light of the materiality test established by
the Constitutional Court in
Allpay
Consolidated Investment Holdings (Pty) Ltd and Others v Chief
Executive Officer, South African Social Security Agency, and
Others
.
[4]
The first part of this judgment concerns the issue of whether the
review application was brought timeously. The second aspect is
devoted to a consideration of the materiality argument.
[4]
The applicant, APM Terminals BV (‘APM’),
is part of the
AP Moller-Maersk Group, an international logistics company. APM has
its principal place of business in the Netherlands
and is engaged in
62 locations throughout the world, developing ports and container
terminals. It was part of a group with nine
other bidders, who
competed for a tender issued by the first respondent, Transnet SOC
Limited (‘Transnet’) for the
development and operation of
the Durban Container Terminal Pier 2 (‘DCT2’) in the Port
of Durban (‘the port’),
South Africa’s main cargo
and container hub.
[5]
This was no ordinary tender by a state-owned entity for
the provision
of goods and services, as is generally the case where an award is
challenged by an aggrieved bidder. Instead, this
tender was aimed at
securing a private partner to collaborate with Transnet, a
state-owned entity, to develop and operate the port
over a period of
25 years. The structure of the transaction is that the business of
DCT2 would be transferred to a special purpose
vehicle (referred to
as ‘NewCo’), in which the successful bidder would become
a 49% shareholder, with Transnet the
remaining shareholder. NewCo
will manage and maintain the operations of DCT2 during the contract
period. Through this process,
Transnet aimed to raise the necessary
capital to address the critical infrastructural crisis at the port,
to upscale its technical
skills and, importantly, generate sufficient
capital to reduce its overall debt, and turn its attention to other
projects.
[6]
There is no dispute that
DCT2 has been plagued for decades by limited operational capacity,
resulting in freight backlogs and congestion
of vessels entering and
leaving the port.
[5]
The chronic
under-performance at the port has had a significant knock-on effect
on the local economy, resulting in an increase
in the costs of goods
moving into and out of the country. Vessels are berthed for longer
than expected, resulting in increased
costs to the shipping
companies, and negatively impacting supply chains, with the increased
costs ultimately borne by the consumer.
There can be no equivocation
that this is a matter which is overwhelmingly in public interest –
DCT2 handles 46% of the country’s
port traffic and serves as a
gateway for the import and export of goods to South Africa and its
neighbouring countries. The magnitude
of its problems, in global
terms, is ominous. The port has lost its regional and global
competitiveness.
[6]
[7]
APM failed to secure the status of the preferred bidder,
that
privilege and the eventual awarding of the tender being bestowed on
the second respondent, International Container Terminal
Services Inc
(‘ICTSI’), a company based in the Philippines and a
global competitor to the applicant. ICTSI is the world’s
largest independent terminal operator, active in six continents and
is ranked eighth as a global terminal operator in terms of
its
capacity.
[8]
APM and ICTSI, having been assessed together with the
other bidders
at a Request for Qualifications stage (‘RFQ’), were then
progressed through to the second round of the
tender, being the
Request for Proposals stage (‘RFP’). This process
involved, what counsel at the hearing euphemistically
referred to as
a ‘straight price shootout’. Simply put, at this stage of
the process, the highest bidder would be awarded
the tender to
develop and operate the port as a shareholder together with Transnet.
ICTSI’s offer exceeded that of APM by
almost R2 billion. APM
was ranked second behind ICTSI.
[9]
APM’s basis for challenging the award is essentially
that ICTSI
failed to comply with the requirement of the tender specifications,
requiring all bidders to establish (at the RFQ stage)
a solvency
ratio equal to or exceeding 0.4, using the formula of total
equity/total assets. Instead of adhering to this formula,
in order to
demonstrate that it had the necessary financial capacity to attract
the required funding for the project over the 25-year
term, ICTSI
proceeded to assure Transnet of its solvency by using the numerator
of market capitalisation (as opposed to total equity)
over assets.
[10]
As I understood the argument and affidavits, market capitalisation
(used by ICTSI) is dependent upon
the share price of a company at any
given time, with solvency being the ability of a company to meet its
financial obligations.
[11]
All the other bidders used ‘total equity’, which
are the figures reflected in the
company’s annual financial
statements, and which are verified by its auditors. The purpose of
the solvency exercise in the
RFQ was to satisfy Transnet of the
bidder’s ability to meet its financial obligations and to
attract investment for the project
over a 25-year period. Transnet
concedes that it was a mandatory requirement that a bidder had to
meet the requirement of establishing
that it had the financial
capacity to attract investors to the project.
[12]
It is common cause that
had ICTSI adhered to the formula of using total equity/total assets
(as did all the other bidders, including
APM), it would have scored
0.24, thereby failing the threshold set out in the bid
specification.
[7]
In contrast,
the metric employed by ICTSI of using market capitalisation as the
numerator instead of total equity (and demonstrating
its financial
capacity), resulted in it achieving a solvency ratio of 1.28. On this
basis, ICTSI progressed, along with nine others,
including APM, to
the RFP stage, with ICTSI ultimately prevailing as the ‘Preferred
Proponent’, a term used in the
bid specification to denote the
successful bidder. It is on this ground, primarily, that APM contends
that the decision to award
the tender to ICTSI for the development
and operation of the port, should be reviewed and set aside. It is
noteworthy that none
of the other unsuccessful bids who progressed to
the RFP stage, contested ICTSI’s selection.. No advantage
accrued to ICTSI
by virtue of the score recorded in the solvency
ranking. This was essentially a vetting stage to ascertain the
responsiveness of
the bidders.
[13]
Against the backdrop of the ailing performance of the port, as
described earlier,
and in light of the government’s intent to
improve the economy, Transnet’s Board approved of the process
for the selection
of an external partner for the development of DCT2.
The procurement of goods and services by Transnet is subject to the
constraints
of s 217(1) of the Constitution, requiring all organs of
state, when contracting for goods or services, to do so ‘in
accordance
with a system which is fair, equitable, transparent,
competitive and cost-effective’.
Section 51(1)
(a)
(iii)
of the
Public Finance Management Act 1 of 1999
echoes this standard
and requires that a public entity adheres to an ‘appropriate
procurement and provisioning system which
is fair, equitable,
transparent, competitive and cost-effective’.
[14]
It is now trite that
public procurement constitutes ‘administrative action’,
as contemplated by the Promotion of Administrative
Justice Act 3 of
2000 (‘PAJA’), although Transnet, in opposing the
interdictory relief sought by APM, alluded to tenders
of this nature,
as they are sanctioned by and aligned with the goals of the
Executive, as being somehow outside the reach of the
courts via
judicial review. This amounted to a separation of powers argument.
When the matter came before me, neither Mr
du
Plessi
s
nor Mr
Ferreira
,
on behalf of Transnet, persisted with that argument, and wisely so.
Counsel did, however, argue for a ‘deserving deference’
[BV1]
to be shown to the
decision maker, in this instance, an organ of state. This is an
argument which I consider elsewhere in this judgment.
[15]
Following the approval of the Board, Transnet issued the RFQ on 11
February
2022 in respect of the search for an equity partner to
develop and operate DCT2. A Cross Functional Assessment Team
(‘CFAT’),
comprising professionals across various
disciplines, including planning, finance and law, would evaluate the
proposals and make
recommendations on the bids. The initial phase of
the RFQ required bidders to submit various documents by a set
deadline. The next
phase required bidders to submit a qualification
declaration and a statement of qualifications, including their
operational and
financial information. This stage was intended to
‘pre-qualify’ bidders, those who complied with all of the
requirements
under this phase of the RFQ were passed through or
progressed to be selected as shortlisted bidders.
[16]
Compliance, or lack of it, with clause 5.2 of the RFQ is the kernel
of this
dispute. Its terms are set out in full:
‘
(d)
Minimum
Financial Criteria
Respondents
must show that they have sufficient financial capacity to attract the
required funding for the envisaged investment
in DCT2.
Each
respondent must submit its most recent five (5) years audited,
consolidated financial statements (including auditors report
and
notes).
A
respondent is deemed to have sufficient financial capacity, when the
following criteria are met (at latest financial year ending):
1.
Solvency is equal to or exceeds 0.4, as calculated
by the following
formula:
Financial
Minimum Criteria 1: Solvency: total equity / total assets equal to or
exceeds 0.4.
2.
Liquidity Ratio is equal
to or exceeds 1.2, as calculated by the following formula:
Financial
Minimum Criteria 2: Liquidity: Source of funds / Uses of Funds equal
to or exceeds 1.2
For which the Sources of
Funds include:
•
Closing Bank Balances
•
Closing Balance of Short
Term Liquid Investments
•
Closing Balance of Short
Term Committed Unutilised Facilities
•
Long Term Committed
Unutilised Facilities
For which the Uses of
Funds include:
•
Loan and Bond Redemptions
for 12 months after latest financial end
Respondents
are required to provide the information required for the Sources of
Funds
and the Uses of Funds in the Statement of Qualification.
2.
The profit, earnings before interest, taxes,
depreciation and
amortisation (EBITDA) and operational free cashflow of each of the
last five years were positive. Where the impact
of COVID has resulted
in a negative result, Transnet will concede the requirement for
positive results in the affected financial
years provided sufficient
explanation of the COVID impact is provided. Transnet reserves the
right to admit Respondents that can
provide a convincing explanation
for a negative profit, EBITDA or operational free cashflow.’
[17]
The RFQ process culminated in the public announcement on 12 August
2022 of
the short-listed candidates, who were subsequently invited to
the second stage – the RFP, which commenced in September 2022.
This stage envisaged a seven-step process in which third party
verification was undertaken by Transnet of the shortlisted bidders
relating to their declared operational qualification criteria and
minimum financial criteria. It is perhaps pertinent to point
out that
during the RFQ stage, ICTSI provided the verification for satisfying
the minimum financial criteria and the solvency ratio,
as set out in
the bid document.
[18]
The verification was undertaken by SyCip Gorres Velayo & Co,
based in the
Philippines, a subsidiary of the global accounting firm,
EY. In particular, the report, dated 17 October 2022, confirms that
it
was prepared to assist ICTSI in assessing their compliance with
the requirements in the RFQ. In respect of the solvency ratio, the
report confirms that ‘the total equity used by the Group
(‘ICTSI’) in the calculation pertains to the group’s
market capitalisation as at December 31, 2021’. The report
further stated that it undertook a recalculation of the solvency
ratio prepared by ICTSI using the market capitalisation as a
numerator and total assets as a denominator and confirmed that the
outcome indicated by ICTSI was indeed correct. A further report
confirming the correctness of ICTSI’s minimum financial
criteria was prepared by Mundy Penfold Limited, a consultancy firm in
the United Kingdom. The process also included a due diligence
exercise on the shortlisted bidders, a documentary requirement
checklist, as well as an evaluation of their business plans.
[19]
Step five of the process entailed a financial evaluation, based on
the price
offered by each shortlisted bidder. In accordance with
clause 39.11 of the RFP, a score of 100% was awarded to the bidder
with
the highest bid, with a resultant 49% stake in the partnership
with Transnet.
[20]
Four bids were received, with ICTSI scoring 100% for its bid of
approximately
R11.1 billion. The second ranked bid, with a score of
83%, was APM, with its offer of R9.2 billion. On 6 April 2023, the
CFAT,
which was responsible for evaluating the bids, requested and
received approval from the Group Executive Committee to recommend
ICTSI as the ‘preferred proponent’ or highest bidder,
with APM recorded as the second ranked bidder.
[21]
After further scrutiny by Transnet’s internal audit department,
which
identified no risks, a letter dated 6 July 2023 was sent to APM
advising it that ICTSI had been selected as the preferred bidder.
The
letter further recorded that ‘in the event the financial
closure fails, Transnet will then seek to finalise the transaction
with the second ranked’. On 3 July 2023, a letter was
dispatched under the signature of the group chief executive of
Transnet,
informing ICTSI of its status as the preferred proponent,
based on its proposal. The letter further set out certain suspensive
conditions and advised that ‘the final award of the tender and
contract to you as the preferred bidder is subject to the fulfilment
of the following suspensive of conditions’.
[22]
These conditions included the satisfactory outcome of a due diligence
exercise,
as well as the payment of the bid price (R11.1 billion)
within 10 days of the offer being made to it, to purchase the shares
in
NewCo. In addition, the final award was subject to the successful
negotiation and execution of all project agreements. In the event
of
ICTSI failing to fulfil the suspensive conditions, the offer would be
rendered null and void and Transnet would be entitled
to award the
tender to, and contract with, the second ranked bidder, APM.
[23]
On 23 July 2023, APM wrote to Transnet requesting reasons for the
decision
to select ICTSI as the preferred bidder, as well as seeking
confirmation that it indeed had been ranked as the second placed
bidder.
APM also requested information pertaining to the third-party
verification of ICTSI’s bid, as well as confirmation that ICTSI
satisfied the minimum financial criteria, specifically the solvency
requirement of 0.4. According to APM, ICTSI's 2022 annual financial
statements disclosed a solvency ratio of 0.24.
[24]
This letter was followed by another letter from APM’s
attorneys, dated
23 August 2023, in which it was recorded that APM
‘harbours serious reservations regarding the lawfulness of the
tender process
which culminated in the selection of the Preferred
Bidder’ and specifically sought a response as to how the
preferred bidder
satisfied the solvency requirement of the tender.
The attorneys for APM further sought an undertaking that Transnet
would not proceed
to conclude an agreement with the preferred bidder.
[25]
Of particular significance, in light of Transnet’s argument
that APM
delayed unreasonably in seeking to challenge the decision to
award the contract to ICTSI, is the acknowledgment by APM’s
attorneys on 23 August 2023 of the 90-day time period in terms of
PAJA within which to review the decision. In a similar vein, Transnet
responded that in the interests of transparency and accountability,
it would supply the additional information sought by APM, mindful
that the 90-day period in terms of s 5(2) of PAJA would expire on or
about 30 September 2023. No extension of the relevant time
frames
under PAJA were agreed upon.
[26]
Transnet then brought to the attention of its attorneys that APM had
queried
whether ICTSI had complied with the requirements of
establishing the minimum financial criteria in the RFQ. An opinion
was sought
from Mettle Corporate Finance (Proprietary) Limited
(‘Mettle’) whether ICTSI had complied with the tender
specifications,
having used market capitalisation as the numerator in
place of total equity. Mettle concluded that the use of market
capitalisation,
which is the price per share of the company
multiplied by the number of shares issued, is not an acceptable means
to ascertain
the solvency of a company.
[27]
Transnet, in accordance with its obligation under the
Constitution to
treat all bidders in a fair and equitable manner,
brought to the attention of ICTSI the concerns raised by APM,
specifically regarding
its declared solvency ratio, having used the
metric of market capitalisation instead of total equity. It was also
recorded that
following receipt of the complaints raised by APM,
Transnet revisited the provisions of the RFQ and RFP, which required
bidders
to establish the solvency of not less than 0.4 using ‘total
equity’ as the numerator. Transnet further noted that, based
on
its recalculation, had ICTSI adopted the use of the same metric as
the other bidders (using total equity as the numerator),
on the basis
of its financial statements as disclosed, it would have generated a
solvency ratio of 0.24.
[28]
Transnet accordingly gave
notice to ICTSI under regulation 14(1)
(a)
and
(b)
of the Preferential
Procurement Regulations, 2017
[8]
of its right to respond to the allegations by APM and provide reasons
why it should not be disqualified for failing to meet the
requirements contained in the RFQ. In response, within days of
receipt of Transnet’s letter, ICTSI provided Transnet with
letters from three major banks confirming ICTSI’s total
available credit facilities in excess of US$400 million, and by
inference, its favourable solvency rating.
[29]
On 2 October 2023, ICTSI responded that it had indeed complied with
the requirements
of clause 5.2(d) of the RFQ, which required that it
demonstrate the existence of sufficient financial capacity to attract
the required
funding for investments in DCT2. It disagreed with
Transnet’s assessment that it failed to meet the threshold of
0.4 and,
in any event, it emphasised that the tender document did not
provide for disqualification in the event of a bidder failing to
achieve
the solvency ratio. In its view, as there was no stipulation
or guidance in the bid documents as to how total equity was to be
determined, it employed market capitalisation, rather than the
nominal equity value contained in its audited statements.
[30]
ICTSI further pointed out
to Transnet that in its response to clause 5.2(d) in the RFQ, it
disclosed to those adjudicating the bid
of its use of market
capitalisation in satisfying the solvency requirement.
[9]
Accordingly, there was no attempt to mislead the bid adjudicators. It
held the view that market capitalisation was an appropriate
means to
calculate solvency for the purposes of the RFQ. In its letter to
Transnet of 2 October 2023, ICTSI asserted that it has
the funding
available for the initial share purchase price, and as evidence of
its solvency, offered to immediately deposit the
amount into an
escrow account. Such proposal would, in my view, be inconsistent with
a company whose solvency was being doubted.
It would therefore
not come as a surprise that the Joint Minute, concluded between the
parties prior to the hearing, recorded that
‘ICTSI has
sufficient capacity to attract the funding required for the envisaged
investments in DCT2’. That put paid,
in my view, to any doubt
as to ICTSI’s solvency to be a suitable partner to Transnet
over 25 years.
[31]
Further letters on 26 October 2023 and 1 November 2023 were addressed
by APM’s
attorneys to Transnet, requesting the urgent supply of
reasons for its decision to appoint ICTSI. As Transnet had not
responded
by the end of October 2023, as it undertook to do, the
stance of APM’s attorneys was that they were instructed ‘to
launch judicial review proceedings imminently to set aside the
appointment decision’, and to ‘approach the court for
a
special allocation so that the matter could be heard on an expedited
basis’.
[32]
Transnet undertook that it would make ‘no decision’ in
relation
to the ‘bidding process’ until it had sufficient
time to consider the issue raised on behalf of APM. Transnet also
adopted the view that any application launched by APM would be
premature. The exchange of correspondence between the respective
attorneys for Transnet and APM continued without further reasons
being furnished and without progression to steps six and seven
of the
tender process, which would culminate in the final award of the
contract to the preferred proponent.
[33]
At the same time, Transnet’s Internal Audit department (‘TIA’)
reviewed APM’s complaint on ICTSI’s use of market
capitalisation in establishing solvency. The TIA concluded that such
procedures were inappropriate and ICTSI failed to meet the minimum
criterion in the RFQ, which could result in a disqualification.
It,
however, cautioned that a legal opinion should first be obtained.
[34]
On 20 November 2023, Transnet’s attorneys wrote to ICTSI
setting out
in some detail the respective views as to whether it had
complied with the solvency ratio specified in the RFQ. Notice was
issued
to ICTSI of its potential disqualification as the preferred
proponent and it was invited to make submissions as to why Transnet
should not proceed with a disqualification.
[35]
ICTSI’s attorneys responded that the use of market
capitalisation was
an acceptable method of establishing its solvency,
notwithstanding that the other bidders had chosen to use total equity
in addressing
this requirement. It stressed that its use of the
specific metric was disclosed at the time of its completion of the
RFQ forms
and that it acted reasonably and transparently in the
entire tender process. Accordingly, it gave notice that it would
oppose any
attempt at disqualification or any review brought by any
party.
[36]
On 12 December 2023, Transnet took a decision to appoint an external
consultant,
GrowthStone Assurance Incorporated (‘Growthstone’)
to test ICTSI’s ‘financial soundness’ through the
methodology of a financial due diligence exercise. Growthstone
released its report in the same month, concluding that from a
financial
perspective, ICTSI was in a ‘good position’ to
raise additional capital for further investment in DCT2.
[37]
On 1 March 2024, Transnet provided a detailed and comprehensive
response to
APM, as to its processes and reasons followed in
verifying ICTSI’s compliance with the requirements in the RFQ
in establishing
its solvency, even though it failed to achieve the
ratio of 0.4 when assessed using the numerator of ‘total
equity’.
Transnet’s position then and throughout is that
the failure to meet the threshold was not material to the achieving
of the
overall purpose of establishing that the chosen bidder had the
necessary financial capacity to finance the project.
[38]
On 3 March 2024, Transnet informed ICTSI in a letter that as the
preferred
proponent, it intended to proceed with the outstanding
steps necessary to finalise the award of the contract to it. The
letter
provided a detailed explanation of all the steps taken by
Transnet in the RFQ and RFP stages of the tender culminating in the
selection
of the preferred proponent.
[39]
Of particular relevance to the dispute before me is the explanation
provided
to APM that at the financial evaluation stage, APM offered
US$515 million – scoring 83% and the preferred proponent,
ICTSI,
offered US$618 million - scoring 100%. ICTSI was accordingly
recommended by the CFAT as the preferred proponent. As to its
engagement
with ICTSI on its financial qualifications, Transnet
advised that while ICTSI was the only bidder to rely on market
capitalisation,
it proactively disclosed the use of market
capitalisation in its solvency ratio, which was confirmed by its
auditors. Transnet
indicated that it was satisfied that ICTSI has a
‘strong balance sheet and high leverage capacity which will
continue as
a strong going concern in the foreseeable future, as it
has done in the past’. In light of this, Transnet concluded
that
ICTSI had the necessary financial capacity to attract the
required funding, even though it failed to meet the 0.4 solvency
ratio.
It adopted the position that the failure to achieve the ratio
was not a material factor in light of ICTSI’s overall financial
capacity.
[40]
In light of the response,
APM launched an urgent application on 11 March 2024
[10]
for interdictory relief preventing Transnet from concluding a final
contract with ICTSI or any other party, pending a review of
the
decision of 1 March 2024 to ‘award the tender’ to ICTSI.
It further sought declaratory relief that it (APM) be
declared the
preferred bidder and that Transnet engage with it in respect of
finalising the contract. Apart from attacking ICTSI’s
failure
to satisfy the solvency threshold, APM contended that Transnet
accorded ICTSI ‘special treatment’ to depart
from the
tender requirements.
[41]
In support of its
application, it enlisted the expert assistance of Professor Wainer of
the University of Witwatersrand’s
School of Accounting. He
reviewed the RFQ and RFP requirements and ICTSI’s use of market
capitalisation in order to satisfy
the minimum financial criteria
section of the RFQ.
[11]
He
opined that market capitalisation is a ‘notional theoretical
indicator of the value of all the issued shares’ and
an
assessment from the perspective of an investor, and not an indicator
of the actual financial position of the company. In Professor
Wainer’s view, market capitalisation does not reflect the
solvency position of a company.
[42]
At the time of his report, Professor Wainer did not have sight of
ICTSI’s
disclosure of the use of market capitalisation in the
bid document submitted to Transnet. He was also critical of
Transnet’s
reasons for choosing ICTSI based on its ‘strong
balance sheet and high leverage capacity’ contending that these
criteria
are different to the objectively determinable criteria in
the RFQ. He adopted the position that the RFQ did not require bidders
to be assessed for their overall financial capacity.
[43]
The urgent application
was opposed by Transnet and ICTSI.
[12]
The matter served before Mossop J who dismissed the arguments raised
by both Transnet and ICTSI that the review was out of time.
They
contended that the decision which had an external effect on the
rights of third parties was the selection of the preferred
proponent,
which was announced on 6 July 2023. The decision of 1 March 2024 in
which Transnet provided detailed reasons for having
selected ICTSI as
the preferred bidder was explanatory in nature and did not have any
external effect. Transnet contended that
the review, launched on 11
March 2024, was eight months after the date from when the preferred
bidder decision was announced.
[44]
It was further contended
that APM failed to act expeditiously and provided no explanation for
the delay. APM’s founding papers
contain no application for
condonation. ICTSI submitted that APM’s reliance on the 1 March
2024 decision as being the decision
to award the tender, was
misconceived. It maintained, like Transnet, that the decision that
ought to have been the focus of the
review, was the selection of the
preferred bidder on 6 July 2023. Both contend that the decision of 1
March 2024 was seized upon
by APM as a pretext for urgency, which was
self-created in order to stifle the contract awarded to its chief
competitor, ICTSI.
From APM’s perspective, it acted within ten
days of the decision of 1 March 2024 being communicated to it. In its
view, ICTSI,
having failed to comply with a ‘mandatory’
requirement of the tender, ought not to have progressed beyond the
RFQ stage.
[13]
This was a ‘red
flag’ according to Transnet’s internal audit report.
Despite this, ICTSI was progressed to the
RFP stage where it
prevailed on price.
[45]
Mossop J considered that the decision of 1 March 2024 was a ‘final’
decision, and despite the arguments advanced by Transnet and ICTSI as
to the delay, the court found that the matter was inherently
urgent.
In weighing the prospects of success as part of the equation in
determining whether to grant interim relief, Mossop J found
that
ICTSI failed to comply with the requirements of the RFQ when it
resorted to the use of market capitalisation in answering
the
solvency enquiry in the RFQ. In resisting the urgent application,
ICTSI relied on the affidavit of its expert, Professor Maroun,
also
from the University of Witwatersrand’s School of Accounting,
who was of the view that there is no single way to express
total
equity in determining solvency. He went on to add that care should be
taken to avoid creating the impression that solvency
can only be
expressed through one specific ratio.
[46]
The court concluded that the decision in identifying ICTSI as the
preferred
bidder was potentially flawed and
prima facie
unfair
to other bidders. The court expressed no view as to the materiality
of ICTSI’s non-compliance with the precise formula
provided for
in clause 5.2(d) or of Transnet’s position that such
non-compliance did not oblige it to disqualify ICTSI.
[47]
Mossop J was persuaded by
APM’s argument in the urgent application, and interdicted
Transnet from taking any further steps
pursuant to its decision of 1
March 2024 with ICTSI or any other party in relation to the tender
for the development of the port.
APM and Transnet were directed to
pay the costs of the application and made an allowance for preference
to be granted for the urgent
hearing of the review application.
[14]
[48]
Following the interdict, Transnet filed the record of its decision in
terms
of rule 53, to which APM filed a supplementary founding
affidavit. Importantly, APM amended its relief from initially only
challenging
the decision of 1 March 2024 as the ‘impugned
decision’ to now reviewing and setting aside as invalid the
decision
of 1 March 2024. Importantly, it also sought condonation (to
the extent necessary) for the non-compliance with the 180-day time
period in PAJA for the reviewing and setting aside of the decision
made on 12 August 2022 in which ICTSI was short-listed to participate
in the RFP, and of the subsequent decision made or communicated on 6
July 2023 to select ICTSI as the preferred bidder. It sought
a
declaration that it be appointed as the preferred bidder in line with
Transnet’s ranking of it as the second ranked bidder,
and for
Transnet to conduct negotiations with it to finalise the contract.
Alternatively, it sought that the matter be remitted
to Transnet for
reconsideration.
[49]
APM contends that it is
entitled to challenge the earlier short-listing and preferred bidder
decisions
[15]
(in addition to
the ‘final decision’ of 1 March 2024), on the basis that
ICTSI and Transnet maintain that the earlier
decisions constituted
administrative actions that would be reviewable, while at the same
time informing APM in correspondence as
late as November 2023 that no
‘decision’ had been made and that any institution of
action at that time would be premature.
In APM’s mind, the
‘clock started to tick’ only once full and adequate
reasons were furnished by Transnet. This
occurred on 1 March 2024.
For this reason, APM adopts the stance that its challenge, through
the late amendment, is intended as
a ‘belts and braces’
approach in the event of the court finding that those decisions ought
to have been challenged
and not the ‘decision’ of 1 March
2024.
[50]
It is worth noting that
even after the filing of the record and the amended relief, the crisp
issue which remains for determination
is whether Transnet was obliged
to disqualify ICTSI only for the reason that it failed to comply with
a solvency ratio calculated
on the basis of total equity over total
assets. This could also be termed ‘non-responsiveness’,
in that ICTSI is said
not to have passed the initial stage of the
RFQ.
[16]
[51]
Transnet and ICTSI maintain that the challenge is premised on a
‘narrow,
technical ground’ intended to disqualify ICTSI
in the final leg of what is a fair and lawful tender process, in
compliance
with s 217 of the Constitution. In so doing, Transnet
contends that APM intends to secure for itself the winning position
(effectively seeking substitution as the preferred proponent in place
of ICTSI), despite its offer lagging almost R2 billion behind.
[52]
While Transnet emphasised
the financial benefit accruing from the contract concluded with
ICTSI, and the prejudice that would result
if the decision was set
aside, Mr
Maenetje
,
who appeared for APM, submitted that this tender was not a substitute
for an auction to the highest bidder in which the irregularity
overlooked by Transnet could be sanctioned by this court. In the
process, so the argument went, Transnet overlooked the caution
expressed by the TIA as well as an external consultant, opting rather
to accept a contrary view from another external consultancy,
Growthstone, based on criteria different from those to which other
bidders were assessed. In doing so, it acted outside the parameters
of its own tender document, obliging it in terms of s 217 of the
Constitution to act in a fair and equal manner to all bidders.
In
support of the obligation of Transnet to adhere strictly to the
tender provisions, reliance was placed on
Khumalo
and Another v MEC for Education, KwaZulu-Natal.
[17]
[53]
A dispute arose as to
which of the decisions constituted administrative action and whether
all or any of them were subject to challenge
by judicial review.
Section
1(1) of PAJA defines ‘administrative action’ as
‘
a
ny
decision taken, or any failure to take a decision, by …
an
organ of state … which adversely affects the rights of any
p
erson…’.
In
Grey's
Marine
Hout
Bay (Pty) Ltd and Others v Minister of Public Works and Others,
[18]
the
SCA held that the enquiry should be characterised by the effect of
such action and whether it has the capacity to affect legal
rights.
The court said that:
[19]
‘
Administrative
action is rather, in general terms, the conduct of the bureaucracy
(whoever the bureaucratic functionary might be)
in carrying out the
daily functions of the State which necessarily involves the
application of policy, usually after its translation
into law, with
direct and immediate consequences for individuals or groups of
individuals.’ (Footnote omitted.)
[54]
ICTSI was shortlisted along with APM and other bidders to progress
from the
RFQ to the RFP. The RFQ stage, as stated earlier, was
essentially a ‘box-ticking’ exercise to pre-qualify
suitable
bidders to submit bids for the contract to develop the port.
ICTSI contended that the short-listing decision constituted
administrative
action. Transnet made no such claim. I agree with APM
that the short-listing decision has not been shown to adversely
affect any
party’s rights, nor did it have any direct or
immediate consequences for any party concerned. All the bidders were
cited
in this matter, with only APM challenging the eventual
decision. At best, the short-listing was the extension of an
invitation
to various bidders to submit bids. To the extent that
APM’s amended its notice of motion to conditionally challenge
the short-listing
decision, I am of the view that this requires no
further discussion. In my view, it was clearly not a decision which
had any attribute
of finality, and was not challenged by any party
who may have been excluded at this stage. No order needs to be made
regarding
the short-listing decision, which in any event was only
conditionally sought.
[55]
Of critical importance, in my view, is the decision of 6 July 2023 in
which
Transnet conveyed to the other bidders that it had selected
ICTSI as the preferred bidder. APM adopts the position that this
decision
too did not amount to administrative action, as it did not
have the capacity to affect legal rights. Transnet and ICTSI are of
the view that this was in fact the critical decision in the award.
[56]
APM contends that this
decision was provisional in nature and could have been changed by
Transnet, without having to invoke the
remedy of a self-review. It
alluded to a letter dated 27 November 2023 in which Transnet advised
that it had not commenced negotiations
with ICTSI in respect of the
finalisation of the contract. In the mind of APM, no final decision
had been reached or taken in the
awarding of the contract, and
therefore there was nothing to review.
[20]
[57]
Argument was advanced
before me by the applicant that I should take into account that this
decision was communicated differently,
by public communique, as
opposed to the short-listing decision. As I understood this argument,
the difference in the mode of communication
of the two decisions
somehow was indicative or decisive of the finality of the award.
[21]
I am not persuaded that anything turns on the manner or mode of
publication of the respective decisions, in as much as the tender
specifications do not elevate or attach any more weight to one form
of publication over the other.
[58]
APM maintains that the preferred bidder decision did not constitute
administrative
action and places all its weight behind the argument
that the decision of 1 March 2024 constituted administrative action,
and it
was against this decision that a review had to be mounted. Its
amended notice of motion to bring the preferred bidder decision of
6
July 2023 into the review spectrum, in my view, was done primarily as
a precautionary measure. It was submitted that Transnet
in its
answering affidavit conceded that the decision of 1 March 2024
constituted administrative action and could not seek in argument
to
retract this concession, which it contended was binding.
[59]
The argument went along
the lines that it was only in the decision of 1 March 2024 that
Transnet advised of its intention to proceed
to finalise the contract
award to ICTSI, and it was not incumbent of APM to challenge each and
every decision along the way of
a multi-stage tender process. APM
contended that the decision of 1 March 2024 meets the requirements of
administrative action in
that it had the capacity to affect the legal
rights of individuals, and relies on
Allpay
,
[22]
which
held:
‘
First,
tenderers have a right to a fair tender process, irrespective of
whether they are ultimately awarded the tender.
Second,
the subject-matter of the review is the decision to award the
contract to Cash Paymaster,
not
each decision along the way in the process
.
Third, the "no effect" argument wrongly seeks to splinter
the process in asserting that Allpay's rights were not affected.
The
decision to exclude AllPay from the second, pricing stage certainly
affected its rights and legitimate expectations. Because
of its
exclusion we are not in a position to know what the outcome of the
pricing stage would have been; it is mere speculation.
Fourth,
in
Grey's
Marine
it
was stated, with reference to the phrase "adversely affect the
rights of any person" in
s
1
of
PAJA,
that
what "was probably intended [was] rather to convey that
administrative action is action
that
has the capacity to affect legal rights
."
Irregularities in the process, which may also affect the fairness of
the outcome, certainly have the capacity to affect
legal rights.’
(Footnotes omitted and my emphasis.)
[60]
In addition to the issue
of the finality of the decision of 1 March 2024, APM submits that the
clock effectively began ticking only
once Transnet provided proper
reasons for its decision to appoint ICTSI as the preferred bidder.
This argument is bolstered by
Centre
for Child Law and Others v South African Council for Educators and
Others
,
[23]
where it was held that:
‘
The
importance of investigating matters before launching review
applications to set aside administrative action, in order to avoid
unnecessary litigation, was stressed in Joubert Galpin Searle Inc and
Others v Road Accident Fund and Others.
The
appellants cannot be faulted for attempting to obtain reasons before
proceeding with litigation. In the absence of reasons,
the 180-day
period did not even commence before the application was launched.
The
court of first instance misdirected itself when finding that there
was an unreasonable delay in the launching of the application.
’
(Footnote omitted and my emphasis.)
[61]
Apart from both Transnet and ICTSI opposing the relief sought by APM,
both
contest APM’s right to challenge the decision to award the
tender to ICTSI on the basis of an undue delay in launching the
review proceedings. It will be recalled that when the application was
launched, APM cast the decision of 1 March 2024 as the ‘impugned
decision’. It sought to challenge no other decision.
[62]
Transnet and ICTSI
contended that the true target of the review is the decision of 6
July 2023 when ICTSI was selected as the preferred
bidder. They
contend that APM should have timeously approached the court to review
and set aside that decision if it wished to
challenge the award.
[24]
I consider it proper to dispense with this leg of the enquiry first,
in as much as any finding of delay not explained satisfactorily
impacts on this court’s jurisdiction to consider the matter.
[63]
APM, in the urgent application, persuaded the court that the letter
of 1 March
2024 had the effect of changing ICTSI’s status from
that of ‘preferred’ bidder to a ‘successful’
bidder. The court noted that ‘[t]he applicant has specifically
sought relief in relation to the decision of 1 March 2024 and
not the
decision of 6 July 2023’. In light of Transnet considering the
decision of 1 March 2024 to constitute administrative
action, Mossop
J held this decision was a ‘final determination’. The
scope of the review application has now been cast
much wider as a
consequence of the amended relief, conditionally sought, to challenge
the decisions of 12 August 2022 and 6 July
2023. I have already
concluded that the decision of 12 August 2022 to short-list ICTSI, as
a reviewable decision, has no merit.
The remaining focus is on the
decisions of 6 July 2023 and 1 March 2024.
[64]
The starting point is that s 7(1) of PAJA provides:
‘
Any
proceedings for judicial review in terms of section 6(1) must be
instituted without unreasonable delay and not later than 180
days
after the date –
(a)
. . .
(b)
. . . on which the person
concerned was informed of the administrative action, became aware
of
the action and the reasons for it or might reasonably have been
expected to have become aware of the action and the reasons.’
Section 9(1)
(b)
provides that the 180-day period
‘
(b)
…
may
be extended for a fixed period,
by agreement between the
parties or, failing such agreement, by a court or tribunal on
application by the person or administrator
concerned.’
Section 9(2) provides
that such an application may be granted ‘where the interests of
justice so require’.
[65]
As will appear from what follows, there is nothing on record to
gainsay the
assertion of Transnet that from 6 July 2023 to 1 March
2024, despite APM having requested various undertakings, Transnet at
no
stage agreed to waive the period under PAJA for the bringing of
any review application. There is also no dispute that APM knew of
the
preferred bidder decision as of 6 July 2023. I have already found
that the short-listing decision of 12 August 2022, despite
the views
of ICTSI to the contrary, did not constitute administrative action
and there is no need to consider condonation in respect
of that
decision. If there is any substance to the argument of Transnet and
ICTSI of undue delay, this enquiry must now concentrate
on the
preferred bidder decision, announced on 6 July 2023.
[66]
The letter of 6 July 2023 to APM reads in part:
‘
[F]ollowing
the evaluation of the proposals received in response to the Request
for Proposals for DCT2, Transnet has selected International
Container
Terminal Service, Inc, as the preferred bidder. Transnet will proceed
to enter into discussions to finalise the transaction
with
International Container Terminal Service, Inc. In the event that the
financial closure fails, Transnet will then seek to finalise
the
transaction with the second ranked bidder.’
APM’s
response to this decision on 13 July 2023
[25]
was to seek specific details as to whether ICTSI satisfied the
solvency ratio of 0.4, as according to its published financial
statements, ICTSI would only have scored 0.24. Of particular
importance is that this letter was written fully cognisant of APM’s
rights in terms of the Constitution and PAJA. APM recorded in the
letter that Transnet’s decision to award the contract to
ICTSI
‘materially and adversely affects APM Terminals as a
participant’.
[67]
The point emphasised by Transnet is that by this time, APM knew
exactly what
decision to attack, as the grounds for its challenge
were articulated with clarity and referred to the relevant
legislative framework.
On 15 August 2023, Transnet provided reasons
to APM for the selection of the preferred bidder, confirming that it
had carried out
the third-party verification on the technical and
financial criteria set out in the RFQ, as well as the due diligence
process,
which confirmed no issues arising from the
Prevention and
Combating of Corrupt Activities Act 12 of 2004
or Politically
Influential Persons. The letter further informed APM that the
assessment of the bidders to the RFP was performed
by the CFAT, which
confirmed that ICTSI scored the highest points on pricing.
[68]
What then followed were a series of letters exchanged between APM and
Transnet,
and later between their respective attorneys, over a period
of almost eight months from the date of the decision when ICTSI was
selected as the preferred bidder. While an applicant intending to
pursue a review application is entitled to reasons for the decision
being challenged, there is nothing which emerges from a textual
reading of PAJA that permits a party to delay the challenge until
it
is furnished with what it considers full and proper reasons.
[69]
Transnet submits that if APM was not satisfied with the reasons for
the decision
provided on 15 August 2023, little more than a month
after the decision, it could have utilised the provisions of
rule
53(4)
to obtain further reasons once the review was launched. The
point emphasised by Transnet and ICTSI is that APM had everything in
its arsenal within weeks of the decision to launch a review of the
preferred bidder decision of 6 July 2023. It is worth pointing
out
that in its letter of 13 July 2023, to which I have already referred,
APM articulated very much the same grounds of review
it relied upon
almost eight months later when it eventually launched its urgent
application. Throughout this entire period, APM
was cognisant that
the conclusion of the tender in question (which admittedly had been
on the proverbial backburner for over 20
years) was by its very
nature urgent, particularly in light of the continuing inefficiencies
at the port and is attendant impact
on the broader economy in the
country.
[70]
The letters from APM’s attorneys to Transnet indicate that APM
had ‘serious
reservations’ regarding the lawfulness of
the selection of the preferred bidder. It was argued that APM was
content to bide
its time and engage in correspondence with the
decision maker in the hope that it would resile from its decision and
disqualify
ICTSI. This is indeed what almost transpired, resulting in
ICTSI’s attorneys on 20 November 2023 accusing Transnet of
being
‘influenced’ by an unsuccessful bidder when it
issued the notice of the intention to disqualify ICTSI.
[71]
Not having received a response from Transnet that was palatable,
despite several
letters being exchanged from 6 July 2023 onwards, on
1 November 2023, APM’s attorneys repeated the averment made on
23 August
2023, alleging that APM still ‘harboured serious
reservations regarding the lawfulness of the tender process…
which
culminated in the selection of ICTSI’. The letter went on
to add that they had been instructed to launch review proceedings
‘imminently’ to set aside the appointment decision and
demanded certain undertakings that Transnet would not proceed
with
certain discussions with ICTSI directed at finalising the contract.
[72]
Apart from informing the
attorneys that such an application would be premature, no
undertakings were provided by Transnet. APM was
at all times alive to
the issues which it wished to challenge but for reasons which are not
apparent from the papers, it chose
not to act. ICTSI and Transnet
accuse APM of engaging in a ‘wait and see game’, hopeful
that Transnet would disqualify
ICTSI. Reliance was placed on what
Rogers J said in
SMEC
South Africa (Pty) Ltd v City of Cape Town and Others; SMEC South
Africa (Pty) Ltd v City of Cape Town and Others
,
[26]
that if a party to a tender considered the functionality component to
have been unlawful, it was bound to launch a timeous judicial
review.
Rogers J was critical of the applicant in that case (SMEC) which,
despite the tender being issued on objectionable terms,
elected to
participate in the process to the end, and launched its review
application only after it failed in its quest to be the
successful
bidder.
[73]
Transnet and ICTSI argue
that this epitomises the approach of APM in this matter. It chose to
wait and engage in letter writing
in the hope of persuading Transnet
to disqualify ICTSI. When that failed, APM launched its application
within days of the decision
of 1 March 2024.
[27]
Moreover, ICTSI further contended that waiting for further or better
reasons is not a justifiable basis to delay the launching
of a review
application, especially in circumstances where APM would later argue
for urgent interim relief, despite waiting almost
eight months from
the date when the decision, against which it had ‘serious
reservations’, was taken.
[28]
[74]
Accepting that APM fired the initial salvo on 14 July 2023 when it
wrote to
Transnet complaining that the selection of ICTSI as the
preferred bidder adversely and materially affected its rights under
PAJA
and requested information as to whether ICTSI had satisfied
various aspects of the RFQ, including the solvency ratio, this
information
was supplied without much delay. When its attorneys wrote
to Transnet on 23 August 2023, APM already had misgivings regarding
the
lawfulness of the process and had already articulated them.
[75]
In my view, it was at
this time that the matter was ripe for launching. Instead, APM waited
until March 2024 – seven months
later. As Rogers J in
SMEC
noted:
[29]
‘
In
principle, it seems undesirable that a bidder should be at liberty to
“take a chance” in the hope that it will be
awarded the
tender, keeping in reserve an attack on the validity of the tender
terms should it be unsuccessful in winning the bid.’
As
I had alluded to earlier, when APM launched its review application
seeking urgent interim relief, the target decision was that
of 1
March 2024. It did not challenge the decision of 6 July 2023 and on
that basis did not consider that condonation was at all
necessary.
[76]
Turning to the decision
of 1 March 2024 and whether it constituted administrative action,
Transnet initially conceded this point
yet appeared to retreat from
it in argument. APM hung its case unequivocally on the contention
that this was the ‘target
decision’ to be set aside.
[30]
I have already alluded to the background facts leading to the
decision by Transnet to make the final award to ICTSI. It only did
so
after having tested ICTSI’s
financial
soundness through the appointment of Growthstone, an independent
service provider, which conducted a financial due diligence,
and
concluded that:
‘
Based
on the financial due diligence review, ICTSI is expected to be a
robust participant in the Durban Container Terminal Pier
2 private
sector participation project. From the financial risk standpoint, the
Company is in a very strong position to add value
to the project,
while being able to withstand volatilities in both global and local
scenes by means of its strong balance sheet,
well-diversified
business portfolio, and extensive access to capital across a broad
range of sources. Coupled with effective capital
management practices
and well-crafted gearing strategy, ICTSI is positioned to be a strong
and reliable strategic partner to Transnet
at DCT2 operation.’
[77]
Transnet was criticised for procuring the services of Growthstone to
conduct
this exercise, particularly as it obtained two audit reports,
including its own internal audit, which were averse to ICTSI and
highlighted ICTSI’s non-compliance. It will be recalled that
after these reports, Transnet wrote to ICTSI giving it notice
to show
why it should not be disqualified. ICTSI responded, after which
Transnet engaged Growthstone.
[78]
APM
further criticised the use of Growthstone, which it described as a
‘small audit firm in Johannesburg’ to test the
financial
soundness of ICTSI
.
[31]
APM says that the use of this criterion was nowhere to be found in
the RFQ or the RFP, and accordingly, ICTSI was evaluated on
criteria
different to of the other bidders, which flies in the face of the
provisions of s 217 of the Constitution and a host of
judicial
authority.
[79]
When Transnet was alerted to a different numerator used by
ICTSI in the solvency ratio, it sought opinions internally and
externally
to determine whether there had been material
non-compliance with the solvency ratio requirement. Included amongst
these was an
opinion from Growthstone, who were tasked with
ascertaining whether ICTSI has sufficient financial capacity to
attract the required
funding for the project. It will be recalled
that Growthstone conducted a ‘
financial
due diligence’ on ICTSI and found it to be a ‘robust
participant’ with a ‘very strong position’
from a
risk perspective able to ‘withstand volatilities’ both
globally and at home. In arriving at this conclusion,
it considered
its ‘strong balance sheet, diversified business portfolio and
access to capital’ from various sources.
Growthstone found
ICTSI to be a ‘strong and reliable strategic partner to
Transnet’. APM contends that none of the
other bidders were
submitted to this measure of assessment, both quantitatively and
qualitatively.
[80]
The letter of 1 March 2024 to APM was a detailed explanation
of the rigorous exercise undertaken by Transnet in assessing each bid
and thereafter to investigate the ‘serious reservations’
which APM had expressed regarding the lawfulness of the award.
The
letter states that it is ‘intended to provide an explanation’
for its decision to select ICTSI as the preferred
proponent, which
was taken and communicated in the letter of 6 July 2023. It recorded
in the letter of 1 March 2024 that ‘ICTSI
has a strong balance
sheet and high leverage capacity and a sound market position, which
will continue as a strong going concern
in the foreseeable future, as
it has done in the past’. Transnet was therefore satisfied that
it had made the correct choice
of a long-term partner to operate the
port for the next 25 years. The conclusion expressed by Growthstone
has not been shown to
be contrived, nor was it seriously challenged
in any way by APM.
[81]
APM submits that the real reason for the progression of ICTSI was
that it was
found to be financially capable by Transnet only after
the findings by Growthstone, which only emerged on 1 March 2024.
Therefore,
in APM’s mind, the clock only then started to tick
for the launching of the review application after ‘real and
adequate
reasons’ had been furnished.
[82]
This conclusion is factually and legally flawed. In the letter of 1
March 2024,
Transnet made it clear that ‘ICTSI was therefore
recommended by the CFAT as the Preferred Bidder’. This decision
was
made and communicated in the letter of 6 July 2023. APM now
contends that the administrative action which is reviewable is that
of 1 March 2024 (now conditionally, the earlier decisions being those
of 6 July 2023 and August 2022). If one has regard to the
facts of
the matter, APM’s focus throughout the application was on the
decision of 6 July 2023.
[83]
When it launched the urgent application, it cast its sights on the
letter of
1 March 2024 as being the target decision. This argument
resonated with Mossop J, who granted APM interim relief holding that
this
‘decision’ constituted administrative action. If
that was the case, it begs the question why APM in its letter to
Transnet
dated 14 July 2023 (days after being informed of the
selection of ICTSI as the preferred bidder) stated in clear terms,
with reference
to the statutory framework, that the decision taken by
Transnet had a material and adverse effect on it as a bidder? The
ineluctable
conclusion to be drawn is that APM was referring to the
decision communicated on 6 July 2023.
[84]
If there was any doubt that this was the decision to challenge, one
need only
have regard to the letters written by APM’s attorneys
in which they repeatedly threaten the launching of review
proceedings,
stemming back to 23 August 2023, and again on 1 November
2023, when it threatened that proceedings were ‘imminent’.
Instead, it sat back in the hope that Transnet would disqualify
ICTSI. The letter of 1 March 2024 is detailed and explanatory in
nature in respect of a decision taken eight months prior and
announced on 6 July 2023. The letter had no capacity, alternatively
no greater capacity, to affect legal rights than those already
impacted by the letter of 6 July 2023, bearing in mind that APM
was
the only bidder which sought to challenge the selection of ICTSI. It
is that decision which had the direct, external legal
effect on APM’s
rights.
[85]
In light of my finding
that the true decision to be challenged was that of 6 July 2023, APM
has also, through a belated amendment
in terms of rule 53(4), sought
to set this decision aside. The amendment was challenged as an
attempt to ‘plug’ the
gaps exposed by ICTSI and Transnet
in the interim application and more particularly, that nothing new
emerged from the record that
was not already known to APM regarding
the short-listing and preferred bidder decisions. ICTSI contends that
the amendment is a
misuse of rule 53(4) in that APM strategically
waited until after it secured the interim relief to introduce the
amendment.
[32]
Had it done so
earlier, its contention that the target decision was that of 1 March
2024 would have been undermined, as would its
grounds for urgency.
[86]
Despite the opposition to the amendment by ICTSI, I am satisfied that
the amendment
should be allowed and that ultimately, a consideration
and assessment of the tender would straddle at the very least the
‘preferred
bidder’ decision and the ‘award
decision’ of 1 March 2024. I am not persuaded that there are
good reasons to
refuse the amendment.
[87]
Turning to the amendment and the decisions sought to be reviewed, in
its explanation
for seeking condonation APM, states that the
short-listing decision was patently not a final decision, and that
the preferred bidder
decision was equally ‘provisional’.
It has persistently adopted this view in the papers, contending that
these do not
constitute administrative action and are incapable of
being judicially reviewed.
[88]
I have already found that the short-listing decision was not
administrative
action. However, as regards the critical decision of 6
July 2023, APM provides no clear or compelling reason as to why it
waited
more than 16 months (until 1 November 2024) before applying
to, through the amended notice of motion, review and set aside
the decision. Other than placing emphasis on the decision maker being
under a duty to supply reasons for the decision and that
it acted
within days of receiving the letter on 1 March 2024, APM avers that
it acted diligently in waiting until adequate reasons
were supplied.
[89]
As stated earlier, APM
was aware of the commercial urgency in respect of any challenge to
the decision. Mossop J found that commercial
urgency, as in the
present tender, justified the intervention of the court. The delay in
challenging the preferred bidder decision
is significant. In my view,
APM fell woefully short of a satisfactory explanation. It is trite
that condonation is not there for
the asking. The factors that must
be considered in deciding whether it is in the interests of justice
to condone a delay depend
entirely on the facts and circumstances of
each case. These include
[33]
‘
the
nature of the relief sought; the extent and cause of the delay; its
effect on the administration of justice and other litigants;
the
reasonableness of the explanation for the delay, which must cover the
whole period of delay; the importance of the issue to
be raised; and
the prospects of success.’
[90]
APM contends that it did not unreasonably delay in challenging the
preferred
bidder decision, which it maintains was provisional in
nature. Its grounds for condonation are essentially a repetition of
the
timeline in respect of the letter writing between its attorneys
and Transnet, based on its quest for ‘adequate reasons’
for the decision. As pointed out earlier, APM made repeated requests
to Transnet for undertakings that no decision would be made
in
relation to the
implementation
of the preferred bidder
decision, and in response, Transnet updated APM that it was still in
the process of engaging with ICTSI
and that it was still
investigating the matter.
[91]
APM’s explanation
for not launching its application sooner was that it was ‘careful
not to abuse the court process and
obstruct any lawful award of the
Tender’ and that it ‘acted very diligently in trying to
get adequate reasons’
and to ‘satisfy itself that its
right to a lawful, reasonable, and procedurally fair administrative
action has not been infringed’.
This explanation does not hold
up to the threshold requirement for condonation set out in
Aurecon
.
APM relied on
Centre
for Child Law
[34]
where the SCA held that the ‘clock
begins
to tick from the date on which the reasons for the administrative
action became known’. In this case, reasons were
given by
Transnet in August 2023. Despite that, APM was content to engage in
letter writing, asking for more and better reasons.
The application
was eventually launched in March 2024, following a detailed
explanation from Transnet for ICTSI’s election
on 1 March 2024.
[92]
I know of no authority,
nor have I been referred to any, which permits a litigant, aggrieved
that a decision has had an adverse
effect on its rights, to wait
until ‘adequate’ reasons have been furnished before
instituting a review application.
Nugent JA in
Gqwetha
v Transkei Development Corporation Ltd and Others
[35]
held
that ‘it is important for the efficient functioning of public
bodies . . . that a challenge to the validity of
their decisions by
proceedings for judicial review should be initiated without undue
delay’.
[93]
The
approach adopted by APM is inconsistent with the SCA’s views in
Opposition
to Urban Tolling Alliance v South African National Roads Agency
Limited
[36]
regarding condonation:
‘
At
common law, application of the undue delay rule required a two-stage
enquiry. First, whether there was an unreasonable delay
and, second,
if so, whether the delay should in all the circumstances be condoned
(see eg
Associated
Institutions Pension Fund and others v Van Zyl and
others
2005 (2) SA 302 (SCA)
at paragraph 47. Up to a point, I think, section 7(1) of
PAJA requires
the same two-stage approach. The difference lies, as I
see it, in the Legislature’s determination of a delay exceeding
180
days as
per
se
unreasonable.
Before the effluxion of 180 days, the first enquiry in
applying section 7(1) is still whether the delay
(if
any) was unreasonable. But after the 180-day period the issue of
unreasonableness is pre-determined by the Legislature; it
is
unreasonable
per
se
.
It follows that the court is only empowered to entertain the review
application if the interest of justice dictates an extension
in terms
of section 9. Absent such extension the court has no
authority to entertain the review application at all. Whether
or not
the decision was unlawful no longer matters. The decision has been
“validated” by the delay (see eg
Associated
Institutions Pension Fund
(
supra
)
at paragraph 46). That of course does not mean that, after the
180-day period, an enquiry into the reasonableness of the applicant’s
conduct becomes entirely irrelevant. Whether or not the delay was
unreasonable and, if so, the extent of that unreasonableness
is still
a factor to be taken into account in determining whether an extension
should be granted or not…
.’
On
the basis of the above, APM’s delay is per se unreasonable, if
the correct target decision to be reviewed is the decision
of 6 July
2023. An applicant would have to show that it would be in the
interests of justice to grant condonation.
[94]
Despite APM’s
contention that it would be in the public interest and in the
interests of justice that it be granted condonation,
there is, on the
contrary, a public interest element in the finality of administrative
decisions and the exercise of administrative
functions.
[37]
Transnet’s papers set out the prejudice that is occasioned on a
daily basis as a result of the delay in the contract for
DCT2 being
challenged. This is not challenged. Moreover, it cannot be disputed
that the sooner plans for the development of the
port are finalised
(and the end of all litigation concerning DCT2), the ripple benefits
would cascade to all those dependent on
the speedy movement of goods
through the port.
[38]
Delays
in a dispute such as this would also cause potential investors to
doubt whether the project would be worth the risk.
[95]
As part of the enquiry as to whether condonation should be granted,
APM contends
that this court must also have regard to the merits in
determining the prospects of success. This enquiry focuses primarily
on
whether the failure by ICTSI to meet the solvency threshold, by
strict adherence to the formula of applying total equity over total
assets, constitutes a ground for its disqualification. Transnet
submits that once the issue of ICTSI’s non-compliance was
raised, it acted as a diligent public entity is obliged to, guided by
the prescripts in
Allpay.
[96]
Turning to the provisions
of the tender document, the contention advanced by APM is that the
language in clause 5.2(d) ‘speaks
for itself’ and that
its real import cannot ‘be tucked away, apart from its
terms’.
[39]
As I
understood this leg of the argument, the wording in the RFQ conveys
to the bidders what they are to establish to satisfy Transnet
that
they have sufficient financial capacity to attract investment to fund
the project. The dispute from the perspective of ICTSI
is that
neither the RFQ nor the RFP provides any elaboration as to how ‘total
equity’ is to be calculated. According
to ICTSI, bidders are
‘deemed’ to have met the requirement of establishing
sufficient financial capacity when they
achieve the solvency
threshold of 0.4 and above. The point of departure is that ICTSI and
Transnet submit that although the RFQ
specified the manner in which
the solvency ratio was to be met, that in itself was not the only
indicator of ‘sufficient
financial capacity’. It is not
disputed that ICTSI would not have met the threshold using the metric
of total equity over
total assets. ICTSI says that notwithstanding,
its proof of satisfying this specific requirement is met in
other
ways, and points to its
ability to attract investments and its strong balance sheet as
fundamental criteria in meeting the overall
purpose of this
requirement in the RFQ.
[97]
Viewed differently, if both APM, ICTSI and any other bidder all
achieved a
ratio of 0.4 and above at the RFQ stage, all that this
would mean is compliance with a requirement under the responsive
stage of
the tender, and advancement to the next stage of the
process. It would not matter if ICTSI scored 0.4 and APM 0.45. The
party with
the higher solvency ratio did not garner any advantage. It
is also important in understanding the materiality argument of
Transnet
as to why the ratio of 0.4 was specified, as this is the
same threshold which Transnet itself is generally required to satisfy
when borrowing money from creditors.
[98]
Transnet conceded in its papers that the solvency ratio was a
mandatory requirement,
although it attempted during the course of
argument to retreat from this concession. Both Transnet and ICTSI
adopt the position
that the requirement of establishing sufficient
financial capacity in clause 5.2(d) of the tender was not restricted
to solvency
alone, but also included proof of liquidity, as well as
earnings before interest and taxes (EBITDA). In so far as Transnet
and
ICTSI’s contention that it was permissible to interpret
clause 5.2(d) as permitting the use of market capitalisation to
calculate
the solvency ratio, Mossop J concluded that ICTSI had in
fact ‘varied’ the ratio calculation. As I understood
ICTSI’s
position, while it is not disputed that the tender
specifications stipulated the method for calculating the solvency
ratio, it
used a different metric in establishing this requirement.
There is nothing before me to suggest that ICTSI’s
modus
of using a different denominator was a stratagem to prevent it from
being declared a non-responsive bidder.
[99]
Mossop J, in the context of the interim application, found that
compliance
with the solvency ratio was a mandatory requirement, and
that there was nothing in the tender document that would have drawn
to
the bidders attention that it was not necessary for them to comply
with any one or more of the requirements, as specifically conveyed
in
the specifications, including compliance with the solvency ratio
calculation. On this basis, the court concluded that Transnet
permitted ICTSI to ‘pervert the solvency ratio calculation’,
acting unfairly in the process.
[100]
Despite arguments to the contrary by counsel for Transnet, I am
satisfied that the solvency
ratio was indeed a mandatory requirement
in the tender. Counsel submitted that the court considering the
interim application made
no attempt to engage with its argument
premised on
Allpay,
namely whether the non-compliance was
material, since a review brought on s 6(2)(
b
) of PAJA requires
that both a
mandatory and material procedure
or condition
prescribed by an empowering condition was not complied with.
[101]
The point of departure
between the conclusions in the interim judgment (which do not bind
me)
[40]
and the submissions on
behalf of Transnet, is that
Allpay
directs that whether the
provisions in the tender document were mandatory or directory is not
the enquiry. Rather, as I see the
enquiry in the present matter, the
non-compliance must be assessed, not only in light of the purpose of
clause 5.2(d), but also
the tender document as a whole, including the
objectives for the development of DCT2. The Constitutional Court in
Allpay
explained the position as
follows:
[41]
‘
Assessing
the materiality of compliance with legal requirements in our
administrative law is, fortunately, an exercise unencumbered
by
excessive formality. It was not always so. Formal distinctions were
drawn between “mandatory” or “peremptory”
provisions on the one hand and “directory” ones on the
other, the former needing strict compliance on pain of
non-validity, and the latter only substantial compliance or even
non-compliance. That strict mechanical approach has been
discarded. Although a number of factors need to be considered in
this kind of enquiry, the central element is to link the
question of
compliance to the purpose of the provision. In this court O'Regan J
succinctly put the question in
ACDP
v Electoral Commission
as
being “whether what the applicant did constituted compliance
with the statutory provisions viewed in the light of their
purpose”. This is not the same as asking whether
compliance with the provisions will lead to a different result.’
(Footnotes
omitted.)
[102]
The contention on behalf of APM is that the plain language of clause
5.2(d) requires each bidder
to comply with all three components of
the section – solvency, liquidity and earnings before interest
and taxes. There is
no allowance for non-compliance in the bid
document, nor any latitude that any of the criteria can be
differently met, other than
in the terms specified. To the extent
that Transnet and ICTSI contend otherwise, APM relies of
Firechem
,
submitting that nothing in the language of clause 5.2(d)
supports the interpretation contended for by Transnet and ICTSI.
[103]
This argument leads to Transnet and ICTSI’s reliance on the
deeming provision contained
in clause 5.2(d), which provides: ‘A
respondent is deemed to have sufficient financial capacity, when the
following criteria
are met…’. APM submits that the
provision is exhaustive and conclusive as to what was required from a
bidder. If Transnet
wished to leave it up to the parties as to how
they should meet the criteria, APM states it would not have specified
the specific
formula to be employed in establishing solvency. If this
were the case, with reference to
Firechem
, it was submitted
that Transnet would not be able to fairly compare the respective bids
if compliance were to be determined having
regard to criteria that
were not objectively clear and concise from the plain language in the
tender documents.
[104]
The same argument is advanced with regard to
how
the tender
specified that financial capacity had to be demonstrated – it
expressly said that this was to be met through the
financial
statements – not any other source document or criteria, as
appears in the Growthstone report. APM emphasised that
Transnet
conceded in its answering papers that it did not use ICTSI’s
market capitalisation to determine whether it had the
required
financial capacity to attract funding for the project. Instead, it
made its assessment based on ‘all the information
available to
it’.
[105]
In the letter dated 1
March 2024, Transnet’s Group Chief Executive wrote that
Transnet determined that ICTSI has a ‘strong
balance sheet and
high leverage capacity and a sound market position’. The
complaint of APM is that it was therefore assessed
differently, or on
criteria not specified, in the RFQ and RFP, compared to ICTSI. The
reasons eventually proffered, so the argument
went, were based on the
Growthstone report, which were based on new facts and criteria
nowhere to be found in the RFQ or RFP.
[42]
This, it was contended, undermines the importance of fairness in the
process, which is a value in itself, irrespective of the outcome.
[106]
Transnet relies on the
deeming provision in clause 5.2(d), contending that the clause should
not be narrowly interpreted to mean
that ‘sufficient financial
capacity’ could not be established in other ways to that
specified in the document. As I
understood this assertion, in which
Transnet relied on
Eastern
Cape Parks and Tourism Agency v Medbury (Pty) Ltd t/a Crown River
Safari
[43]
and
Electoral
Commission of South Africa v Umkhonto Wesizwe Political Party
(Council for the Advancement of the South African Constitution
and
others as amici curiae)
,
[44]
it is argued that the satisfaction of the criteria in clause 5.2(d)
merely facilitated proof of the necessary
financial
capacity to attract investors to the project, as opposed to strict or
actual compliance being conclusive of the requirement
of the clause.
It further contends that there is nothing in the RFQ which stipulates
that strict non-compliance with any one of
the criteria would result
in disqualification.
[107]
In respect of APM’s reliance on
Firechem
and the
submission that non-compliance by ICTSI with the solvency ratio
entails that other bidders were treated differently to
ICTSI, at odds
with s 217 of the Constitution, it was submitted by Mr
Ferreira
,
who dealt with this aspect of the argument on behalf of Transnet,
that at this particular stage of the process, there was in fact
no
comparison of competing bids. It was purely to determine
‘responsiveness’ in terms of verifying qualifications.
The assessment of bids only arose at the RFP stage. As pointed out
earlier, even if ICTSI achieved a lower solvency ratio than
APM at
this stage of the process, it would have no bearing on the eventual
price shoot-out. The process at the RFQ stage was to
‘pre-qualify’
bidders. The compliance required at this stage was to only
demonstrate financial capacity to attract
funding for the project.
[108]
Turning to the argument
as to whether non-compliance with a tender requirement constitutes a
ground of review,
Millennium
Waste
Management
(Pty) Ltd v Chairperson, Tender Board: Limpopo Province and
Others
[45]
affirmed
that s 217 of the Constitution requires that
contracts
for the supply of goods and services must be ‘fair, equitable,
transparent, competitive and cost-effective’.
In
Allpay
,
[46]
the Constitutional Court held that ‘[c]ompliance with the
requirements for a valid tender process, issued in accordance with
the constitutional and legislative procurement framework, is thus
legally required. These requirements are not merely internal
prescripts that SASSA may disregard at whim’. Of importance to
the present dispute is what the Constitutional Court alluded
to in
the same paragraph of its judgment:
‘
Deviations
from the
procedure
will be assessed in terms of those norms of procedural fairness.
That
does not mean that administrators may never depart from the system
put in place or that deviations will necessarily result in procedural
unfairness. But it does mean that,
where
administrators depart from procedures, the basis for doing so will
have to be reasonable and justifiable, and the process
of change must
be procedurally fair.
’
(Footnote omitted and my emphasis.)
[109]
In determining whether
the non-compliance with the solvency requirement in clause 5.2(d)
of the tender should have resulted
in ICTSI’s disqualification,
Allpay
dictates
that the materiality of compliance with legal requirements depends on
the extent to which the purpose of the requirements
is attained.
[47]
ICTSI’s financial strength and its position as a global
terminal operator are undisputed. It is for this reason that
Growthstone
correctly concluded that ICTSI would add value to the
DCT2 project. This was evidenced by ICTSI being prepared to pay the
contract
price immediately into an escrow account. The price that it
offered for the contract to develop the port far outstrips that of
APM.
[110]
In the context of dealing with the issue of materiality, the
provisions of clause 5.3(b) of
the RFQ are relevant. It reads,
in parts, as follows;
5.3
SOLE DISCRETION, NO LIABILITY
Transnet
shall be the sole judge of each Respondent’s conformity with
the requirements of this RFQ and the merits of each
Statement of
Qualifications. Transnet reserves the right, subject to applicable
laws, to:
…
(b)
Waive any requirements of this RFQ.
…
Transnet may exercise
any such rights at any time, without notice or liability to any
Respondent, Participant or other parties for
their costs, expenses or
other obligations incurred in the preparation of a Statement of
Qualifications or otherwise; and to waive
any condition or modify any
provision of this RFQ with respect to one or more Respondents.”
This
clause accords to Transnet, on a plain reading, the privilege of
being the sole judge of each bidder’s conformity with
the
requirements of the RFQ and grants it the power to waive
any
requirement of the RFQ. In deciding not to disqualify ICTSI
once it became apparent that they had failed to achieve the solvency
ratio of 0.4, Transnet was entitled, so the argument went, to secure
the best financial deal for itself and to secure a long-term
partner
to develop the port. This entitlement was permitted in terms of the
tender itself, allowing non-compliance with
any
provision of
the RFQ.
[111]
Transnet emphasised that once ICTSI’s non-compliance with the
solvency ratio was brought
to its attention, it acted in a fair and
responsible manner by engaging with the complainant, APM, and
conducted a thorough investigation
into the matter. As set out
earlier, it requested a report from its internal audit department, an
external report from Mettle and
finally, a report from Growthstone.
The latter engagement, which produced a result favourable to ICTSI,
was criticised by APM as
being a ‘private engagement’
outside of the processes permitted by the RFP. The point emphasised
by Transnet is that
it proceeded, acutely aware of the consequences
arising from the disqualification of a bidder following a complaint
lodged by a
competitor, seeking to act in accordance with s 217 of
the Constitution.
[112]
A primary feature of the transaction to engage a private partner to
develop the port was carefully
considered, with the intention being
to enable Transnet to use the proceeds from the transaction to settle
its debts and reduce
its finance costs. This is considered in detail
by the Group CEO of Transnet, Ms Phillips, in her memorandum dated 7
February 2024,
addressed to the Transnet Board, prior to the
announcement of the decision to award the contract to ICTSI.
[113]
The memorandum considered the impact of ICTSI’s R11.2 billion
investment in the project,
the impact on Transnet’s overall
book debt, and the effect on the share of profits of NewCo, amongst
other variables. It
also included a discussion of APM’s
complaint in relation to the solvency ratio, the steps taken to
address the matter and
took into account the views expressed by the
TIA, as well as an opinion taken from counsel. Finally, the Board
considered the findings
of Growthstone, who after completing a
financial due diligence on ICTSI, confirmed their financial capacity
to implement the project,
and that it was in a sound financial
position to raise the additional capital required.
[114]
In light of the contents of the memorandum, it was recommended to the
Transnet Board that it
‘proceed with the implementation of the
financial close[d] process arising from the award of the Preferred
Bidder status’
to ICTSI. It is noteworthy, having regard to the
earlier debates as to the appropriate decision to be reviewed, that
Transnet was
clearly of the view that the decision of 1 March 2024
was the ‘
implementation
’ of the award of the
preferred bidder decision of 6 July 2023. This is in tandem with my
conclusion that the decision of
6 July 2023 ought to have been the
target of the review.
[115]
The memorandum also contained an annexure which narrated in detail
the tender process, from
inception to the final awarding of the
contract. In this context, it is important to note the workings of
the CFAT and its adherence
to the Framework, which served as a guide
in the assessment of the bids received. Clause 9.2.4 of the Framework
(which is referred
to in the annexure) provides that:
‘
9.2.4
Bidder qualification and evaluation criteria must be carefully
designed and documented so as to –
9.2.4.1
maximise
the level of market interest;
9.2.4.2
minimise the risk of unwarranted disqualification and
preserve
maximum flexibility
for Transnet.’ (Emphasis added.)
[116]
It was apparent that
those entrusted with drawing up the tender document clearly
contemplated that the purpose of the tender was
to maximise the
financial potential from a public/private sector partnership.
[48]
In doing so, Transnet was granted maximum flexibility and latitude to
ensure that bidders were not disqualified for non-compliance
with
criteria that were not material to the overall purpose of the
project.
[117]
Transnet made no secret of its intention to achieve maximum financial
yield from the establishment
of NewCo, especially as this would be a
once in 25-year opportunity. The point which appears to elide APM is
that Transnet was
seeking a long-term partner to operate a national
enterprise, crucial to the national economy. ICTSI’s financial
standing
and its operational capacity is not gainsaid by APM.
[118]
Having satisfied itself
through a vast and expansive process, including due diligence
exercises, Transnet was satisfied with its
choice of ICTSI, even
after the complaint of it not meeting the solvency ratio was raised.
The investigations which followed provided
it with further evidence
of the suitability of ICTSI as a partner. It is in this vein that
Transnet argues for ‘due deference’
to be shown by this
court for the choice of a business partner.
[49]
[119]
This was not a routine tender for services at the lowest price.
Transnet, more than any competing
bidder, would be best suited to
understand the purpose and meaning of its own tender process, and
more importantly, the specific
characteristics it is looking for in a
suitable business partner. Again, it bears repeating that this is not
a case where the spectre
of corruption and malfeasance lingers over
the choice of the successful bidder.
[120]
The point repeatedly emphasised during argument is that the solvency
ratio played no role in
the determination of the successful bidder.
Transnet contends that what APM is seeking to achieve, via the review
application,
is to unseat ICTSI’s bid worth R11.2 billion and
impose APM as the preferred proponent with an offer of R9.2 billion.
This
would undermine the fundamental purpose of the tender and cannot
be said to be rational.
[121]
Similarly, Transnet was criticised for engaging the services of
Growthstone and is accused of
engaging with ICTSI in seeking its
views on the non-compliance with the solvency ratio, as well as
evaluating its bid on criteria
different to that on which APM was
evaluated. As regards the criteria used by Growthstone, even if they
are nowhere to be found
in the bid specifications, Growthstone was
not performing an exercise under the auspices of the RFQ or RFP. That
was the mandate
of the CFAT, who were guided by the Framework for
Joint Investment, approved by Transnet’s Board. The CFAT had
already passed
ICTSI through the RFQ, as it was satisfied that ICTSI
had met the minimum financial criteria solvency ratio.
[122]
Apart from denying these assertions against Growthstone and ICTSI, ,
Transnet’s Framework,
which guided the CFAT in its assessment
of the bids, provides in clause 9.3.3 that in qualifying a bid and
evaluating criteria,
Transnet has the right to ‘extract further
information from bidders’ and ‘seek clarification from
bidders’.
[123]
This is exactly what
Transnet contends it did when faced which the complaint from APM. Mr
du
Plessis
submitted
that it acted in a rational and reasonable manner, in accordance with
the prescripts of
Allpay
–
describing
its approach as the ‘gold standard’ when caught in the
predicament it faced. The obligation to investigate
a potential
irregularity, or to correct any unlawfulness, was underscored in
Khumalo
.
[50]
[124]
Further evidence of the latitude granted to Transnet to waive the
requirements of the RFQ or
to require ‘supplemental statement
of information from any respondent’ and being the ‘sole
judge’ of any
bidder’s conformity with the requirements
of the RFQ, can be sourced in clause 5.3 of the RFQ. On this score, I
can find
no basis for the contention that Transnet operated outside
the parameters of the tender document by engaging with ICTSI, as it
invited their representations to the complaint of APM, and even gave
notice that it contemplated disqualifying them for the failure
to
meet the solvency ratio.
[125]
Having regard to the record, I agree with Transnet that there was
nothing suggestive of untoward,
unlawful or irrational conduct on its
part, following APM’s complaint. It should also be borne in
mind that Transnet was
in frequent communication with both APM and
ICTSI on the solvency ratio complaint, and there can be no
insinuation that Transnet
adopted a partisan approach to either party
during this period.
[126]
The test to determine
whether the procedure followed by Transnet in ultimately awarding the
contract to ICTSI must be measured against
the threshold set in
Allpay
,
where the following was stated:
[51]
‘
The
proper approach is to
establish,
factually, whether an irregularity occurred. Then the irregularity
must be legally evaluated to determine whether it
amounts to a ground
of review under PAJA. This legal evaluation must, where appropriate,
take into account the materiality of any
deviance from legal
requirements, by linking the question of compliance to the purpose of
the provision, before concluding that
a review ground under PAJA has
been established.’
[127]
In answering the
Allpay
test in this matter, it cannot be
disputed (applying the rigours of strict compliance) that an
irregularity occurred by Transnet
overlooking ICTSI’s failure
to satisfy the 0.4 solvency ratio, and by applying the formula as
stipulated in clause 5.2(d)
of the RFQ. It used a formula not
prescribed by the RFQ. At the same time, although all the remaining
bidders used the formula
as set out in the RFQ to establish
compliance with the solvency ratio, the RFQ did
not
inform
bidders that the
only
way in which total equity could be
established was through the company’s audited financial
statements for the current year,
as opposed to the metric of using
market capitalisation, or that this would be met with
disqualification.
[128]
In contrast, part 5(2) of the Assessment of Statements of
Qualifications under the RFQ, expressly
sets out certain exclusionary
criteria, such as where a bidder has been subject to bankruptcy;
insolvency; or where directors of
the parent company have been found
guilty of fraud or corruption. The absence of the exclusionary
criteria in s5(2)(d) support
the interpretation favoured by Transnet
and ICTSI.
[129]
Having regard to all of the facets of the tender and its subsequent
investigations into ICTSI’s
standing, Transnet was satisfied
with ICTSI’s financial status as a long-term business partner,
even without it complying
with the solvency ratio. The tender
framework permitted Transnet to condone non-compliance with certain
requirements, and it acted
accordingly, without prejudice to any
losing bidder, especially APM, whose bid was 17% less than that
received from ICTSI.
[130]
To have disqualified ICTSI for its failure to achieve a solvency
ratio (based on a specified
formula), would have been to disqualify a
meritorious tenderer, and open the way for a significantly lower bid
to have prevailed.
This would be contrary to the purpose of the
tender and the financial objectives of Transnet. It would also have
the effective
of retarding, rather than promoting the value of
‘competitiveness’ which is referred to in s 217 of the
Constitution.
[131]
As Transnet emphasised throughout its argument, the issue of ICTSI
failing to comply with the
solvency ratio had no bearing on the
ultimate purpose of the RFQ, notwithstanding that such requirement
was found to be mandatory.
The RFQ process, of which the minimum
financial criteria formed part, was intended to pre-qualify bidders
before entering the competitive
phase in which the bidders submitted
their offers for a 49% stake in NewCo. Transnet ultimately selected a
business partner, in
a globally competitive market, based on ICTSI’s
sound financial credentials and the ability to raise the necessary
funding
for the project. ICTSI’s financial standing has never
been placed in dispute by APM.
[132]
Hence, to advance the
argument of its non-compliance with the solvency ratio as a basis for
its disqualification, would be to unjustifiably
elevate form over
substance, even in relation to a mandatory requirement. It would be
reminiscent of cases which advocated for
formalism and strict
adherence to tender requirements.
[52]
The author, Peter Volmink,
[53]
points out that in determining whether a bid can be regarded as
responsive
‘…
calls
for a careful weighing up of multiple factors through a process of
fair-minded reasoning, rather than the adoption of a narrow,
rigid or
pedantic approach. The consequences of non-compliance may vary
depending on the purpose and materiality of the bid requirement
in
question, the language of the request for proposals (RFP), whether
there had been substantial compliance etc.’
[133]
This was not a case where another bidder had been excluded from
progressing to the RFP stage
for non-compliance with the solvency
formula, or that ICTSI had been accorded different treatment, and
been allowed to proceed.
When APM and ICTSI entered the RFP stage,
they were on an equal footing together with the other bidders who
submitted financial
offers to Transnet.
[134]
The inquiry, since
Allpay
, has shifted to materiality. As
stated earlier, there has been no suggestion or a dint of evidence to
suggest that ICTSI would
not be an appropriate fit for a long-term
business relationship with Transnet. It must be emphasised that this
court, in finding
no basis to unseat ICTIS, should not be seen to be
rubber-stamping Transnet’s decision, fortified as it was by the
Growthstone
report. In reaching the decision I have, consideration
has been given to the purpose of the solvency ratio in the context of
bidders
being required to satisfy minimum financial criteria under
clause 5.2 of the RFQ, and the overall objective of the tender.
[135]
In the result, I
conclude, having had regard to the submissions of the parties and the
extensive record, that Transnet’s decision
in awarding the
contract for the operation of DCT2 to ICTSI did not fall foul of the
tender provisions, nor did it constitute a
reviewable irregularity
under s 6(2) of PAJA or under the principle of legality. Transnet
approached the complaint under the
Allpay
test and adopted a
‘purposive’ approach in ensuring that the steps taken
were in compliance with the provisions of the
tender, in light of
their overall purpose.
[54]
[136]
My finding on the merits also informs my decision as to whether
condonation should be granted
for the review of the preferent
proponent decision of 6 July 2023. In respect of the application for
condonation, I have already
concluded that the delay was unreasonable
and that the primary target, as far as APM was concerned, was the
decision or explanation
that eventuated on 1 March 2024. APM was
mistaken in its strategy to wait until it received the explanation
from Transnet on 1
March 2024. Nothing prevented it from instituting
its application to challenge the decision to select ICTSI as the
preferred proponent
bidder, a decision which had a direct, external
effect on the rights of third parties. The explanation that APM was
holding out
until it received better or fuller reasons from Transnet
is neither satisfactory nor convincing. Despite the apparent
commercial
urgency and knowing the consequences that delays have for
various industries associated with the port, the failure to launch
the
review application timeously is fatal.
[137]
For all of the above reasons, I am not persuaded that condonation
should be granted for the
delay in instituting the review
application. If I am wrong in this regard, I am of the view that the
review in any event falls
to be dismissed on the merits.
[138]
On the aspect of costs,
it bears noting that APM was granted costs of two counsel at the
stage of the interim application. In this
court, APM similarly asked
for costs in the event of it succeeding, with both Transnet and ICTSI
adopting a similar stance in the
event of them prevailing. It is
trite that this is an aspect in which I exercise my discretion. None
of the parties appeared to
consider that
Biowatch
Trust
v Registrar, Genetic Resources, and Others
[55]
or
Harrielall
v
University of KwaZulu-Natal
[56]
were of application in this case, despite APM bringing its challenge
primarily on the grounds that Transnet’s conduct offended
the
provisions of s 217 of the Constitution, and s 6(2) of PAJA. I
assume this approach was informed by the view that the
matter related
to a tender, was essentially of a commercial nature and devoid of any
‘public interest’ component.
[139]
The Constitutional Court in
Harrielall,
however, stated that
the review of the exercise of public power is now controlled by the
Constitution and legislation enacted to
give effect to it. The
application brought by APM, though unsuccessful, cannot be described
as frivolous or vexatious, to strip
it of the protection afforded by
Biowatch
where parties engage in constitutional litigation.
Mossop J found that APM had made out a
prima facie
case for
urgent interim relief. At the heart of this matter, despite Transnet
labelling APM’s case as an attempt to snatch
a R2 billion
bargain by attempting to unseat ICTSI as the successful tenderer, the
dispute nonetheless hinged on whether Transnet,
as a public entity,
adhered to s 217 of the Constitution and the rigours set out by the
Constitutional Court in
Allpay
. The matter is of significant
public interest, albeit not in the sense of involving the
determination of socio-economic rights.
[140]
Rogers J in
SMEC
was faced with a similar
predicament and considered
[57]
‘
Whether
a carve-out should be recognised for commercially inspired review
proceedings in general, or for reviews by disappointed
tenderers in
particular, is a question for a higher court.’
[141]
I am satisfied that APM’s litigation falls within the
Biowatch
net and to that extent, it is insulated from costs in this court,
notwithstanding the award of costs in its favour in the interim
application.
[142]
I accordingly make the following order:
1.
The application is dismissed.
2.
The parties are to bear their own costs, including
any costs
reserved.
CHETTY J
Counsel
for the applicant:
Mr N
H Maenetje SC and Mr M Z Gwala
Instructed
by: Webber Wentzel
Sandton
Johannesburg
Locally
represented by:
Johnston
and Partners
Umhlanga
Rocks
Counsel
for the first respondent:
Mr M
du Plessis SC, Mr N Ferreira and
Mr M
Salukazana
Instructed
by: ENS Africa
Sandton
Johannesburg
Locally
represented by:
ENS
Africa
Umhlanga
Rocks
Counsel
for the second respondent:
Mr
A Stein SC and Ms T Palmer
Instructed
by:
Bowman
Gilfillan Incorporated
Johannesburg
Locally
represented by:
Bowman
Gilfillan
Westville
Durban
Date
reserved:
29
th
& 30
th
April 2025
Date
of delivery:
10
October 2025
[1]
Altech Radio Holdings
(Pty) Ltd and Others v Tshwane City
[2020]
ZASCA 122
;
2021 (3) SA 25
(SCA) para 54.
[2]
Oudekraal Estates
(Pty) Ltd v City of Cape Town and Others
2004
(6) SA 222
(SCA) para 36.
[3]
Generally,
a bid only qualifies as responsive if it meets all the
requirements as set out in the tender documents,
without
material deviation or qualification
.
These requirements usually relate to compliance with regulatory
prescripts, bid formalities, or functionality/techical criteria,
pricing and empowerment requirements.
[4]
Allpay
Consolidated Investment Holdings (Pty) Ltd and Others v Chief
Executive Officer, South African Social Security Agency,
and Others
[2013]
ZACC 42
;
2014 (1) SA 604
(CC) (
Allpay
).
[5]
According
to Transnet, the concept of the introduction of private sector
partners in the operation of the port has long been a
priority of
national government, stemming back to 2002, when the first plan to
fast track private sector inclusion was mooted
in the Commercial
Ports Policy. For reasons which are not apparent from the papers,
the investment in port infrastructure and
the provision of a more
efficient and higher quality of port services, appear to have
slipped the national focus. After a hiatus
of almost 19 years, the
issue of the ailing infrastructure of the port was resurrected as
part of the government’s Economic
Reconstruction and Recovery
Plan, with the intention to expand the capacity of the port, funded
by private sector involvement,
as Transnet lacked the financial
resources to do so.
[6]
In
2022, the World Bank's Container Port Performance Index (CPPI)
ranked the port at 341
st
out
of 348 ports globally, reflecting its poor performance. The
answering affidavit of Transnet refers to a ranking of 365
th
out
of 370 ports. Nothing turns of the discrepancy,
[7]
This
arose from a recalculation by Transnet of the solvency ratio using
the formula of total equity/total assets, applied to the
annual
financial statements disclosed by ICTSI in the RFQ and RFP stages.
[8]
Preferential
Procurement Regulations, 2017, GN R32,
GG
40553,
20 January 2017. These regulations have since been repealed by the
Preferential Procurement Regulations, 2022, GN 2721,
GG
47452,
4 November 2022, which came into effect on 16 January 2023.
[9]
This
emerges from a perusal of the completed RFQ by ICTSI and is
confirmed in appendix A.1 to the letter from SyCip Gorres Velayo
&
Co in a footnote, which reflects ICTSI’s market capitalisation
as at 31 December 2021, 2022 and June 2023. It notes
further that
‘
Total
equity is based on market approach following General Standards IVS
105, Valuation and Approaches and Methods of the International
Valuation Standards published by the International Valuation
Standards Council’.
[10]
The application was
launched within ten days of being informed of the decision by
Transnet and comprised 320 pages. At the time
when the matter was
argued for the interim order, the papers comprised close to 1 400
pages, and eventually over 14 500
pages when the final review
was heard.
[11]
Transnet
conceded that ICTSI did not meet the 0.4 threshold when using book
equity as the numerator in the formula set out in
clause 5.2(d) of
the RFQ.
[12]
Terminal
Investment Limited (the eighth respondent) filed a notice to oppose
but no affidavit. Its opposition was confined to
a point of law.
This opposition was dismissed. The eighth respondent plays no part
in the present review proceedings.
[13]
APM
relied on the wording in clause 5.2(d) providing for ‘minimum
financial criteria’ which states that bidders ‘
must
show
that
they have sufficient financial capacity to attract the required
funding…’.
[14]
The judgment in the
interim application was handed down on 11 October 2024 after two
days of hearing argument. An application
for leave to appeal was
refused.
[15]
The
applicant relied on
Helen
Suzman Foundation v Judicial Service Commission
[2018]
ZACC 8
;
2018 (4) SA 1
(CC) para 13, which held in relation to rule
53 that:
‘
The
requirement in rule 53(1)
(b)
that
the decision-maker file the record of decision is primarily intended
to operate in favour of an applicant in review proceedings.
It helps
ensure that review proceedings are not launched in the dark. The
record enables the applicant and the court
fully
and properly to assess the lawfulness of the decision-making
process. It allows an applicant to interrogate the decision
and, if
necessary, to amend its notice of motion and supplement its grounds
for review
.’
Transnet
and ICTSI opposed the amended relief, contending that APM had known
from the outset of the need to challenge the earlier
decision but
opportunistically latched onto the 1 March 2024 decision as the
basis for launching the urgent application.
[16]
In
terms of
s
1
of the
Preferential Procurement Policy Framework Act 5 of 2000
, an
‘acceptable tender’ is defined as one ‘which, in
all respects, complies with the specifications and conditions
of
tender as set out in the tender document’.
Chairperson,
Standing Tender Committee and Others v JFE Sapela Electronics (Pty)
Ltd and Others
2008
(2) SA 638
(SCA) para 11 held that ‘
[t]he
acceptance by an organ of State of a tender which is not
“acceptable” within the meaning of the Preferential
Act
is therefore an invalid act and falls to be set aside. In other
words, the requirement of acceptability is a threshold
requirement’
.
[17]
Khumalo
and Another v MEC for Education, KwaZulu-Natal
[2013] ZACC 49
;
2014 (5)
SA 579
(CC)
(
Khumalo
)
para 29 held as follows:
‘
The
rule of law is a founding value of our constitutional democracy. It
is the duty of the courts to insist that the state,
in all its
dealings, operate within the confines of the law and, in so doing,
remain accountable to those on whose behalf it
exercises power. The
supremacy of the Constitution and the guarantees in the Bill of
Rights add depth and content to the rule
of law. When upholding the
rule of law, we are thus required not only to have regard to
the strict terms of regulatory provisions
but so too to the values
underlying the Bill of Rights.’ (Footnote omitted.)
[18]
Grey's
Marine Hout Bay (Pty) Ltd and Others v Minister of Public Works and
Others
[2005] ZASCA 43
;
2005
(6) SA 313
(SCA) paras 23-24.
[19]
Ibid
para 24.
[20]
See
Association
of Meat Importers and Exporters v International Trade Administration
Commission and Others
[2024]
1 All SA 106
(GP) para 21:
‘…
the decision to continue
the imposition of anti-dumping duties on the product was a three
tiered/stage process which only became
binding on its completion.
ITAC’s final recommendation, although called “final”
in itself, possessed no finality
as it was subject to the Trade
Minister’s approval and if not approved, remittance or
rejection. The Trade Minister’s
approval of ITAC’s final
recommendation also possessed no finality as such approval did not
complete the decision process.’
[21]
See
Independent
Regulatory Board for Auditors and Others v East Rand Member District
of Chartered Accountants and Others
[2024]
ZASCA 114
;
[2024] 4 All SA 23
(SCA) para 42.
[22]
Allpay
para
60.
[23]
Centre
for Child Law and Others v South African Council for Educators and
Others
[2024]
ZASCA 45
;
2024 (4) SA 473
(SCA) (
Centre
for Child Law
)
para 11.
[24]
Transnet and ICTSI place
reliance on the rule16A notice issued by APM, which identifies the
decision of 6 July 2023 (the preferred
bidder decision) as the
target of the challenge. Not mention is made of the decision on 1
March 2024.
[25]
It is not clear whether
this letter is dated 13 or 14 July 2023. The record simply bears
reference to ‘July 2023’.
[26]
SMEC South Africa
(Pty) Ltd v City of Cape Town and Others; SMEC South Africa (Pty)
Ltd v City of Cape Town and Others
[2022]
ZAWCHC 131
(
SMEC
)
para 91.
[27]
See
Chairman,
State Tender Board v Digital Voice Processing
(
Pty
)
Ltd
;
Chairman,
State Tender Board v Sneller Digital
(
Pty
)
Ltd and
Others
[2011]
ZASCA 202
;
2012 (2) SA 16
(SCA) para 20 where the SCA held:
‘
Generally
speaking, whether an administrative action is ripe for challenge
depends on its impact and not on whether the decision-maker
has
formalistically notified the affected party of the decision or even
on whether the decision is a preliminary one or the ultimate
decision in a layered process . . . Ultimately, whether a decision
is ripe for challenge is a question of fact, not one of dogma.’
[28]
See
Vukani
Gaming Free State (Pty) Ltd v Pillay and Others
[2021] ZASCA 137
where
the SCA said the following regarding the supply of reasons for
decisions:
‘
[35]
As pointed out by Hoexter “. .
. reasons are not really reasons unless they
are properly
informative. They must explain
why
action
was taken or not taken; otherwise they are better described as
findings or other information”. The rationale
for giving
reasons is to enable an aggrieved party to understand the reasoning
behind the decision and decide whether or not
to challenge it.
Reasons should constitute more than mere conclusions. They should
refer to the relevant facts, the applicable
law and the processes
leading to the conclusions. Recently in
Maxrae
Estates (Pty) Ltd v Minister of Agriculture, Forestry and Fisheries
& Another,
this
Court held that the mere mention that a “discretion has been
exercised for the given purpose was not sufficient. The
court was
constrained to intervene where the decision maker had ignored the
relevant factors and taken into account irrelevant
considerations”.
What factors the Board took into account in this instance, it is not
clear.
[36]
The importance of reasons was highlighted in
Koyabe v
Minister of Home Affairs
as follows:
“
63.
Although the reasons must be sufficient, they need not be specified
in minute detail, nor is it necessary to show how every
relevant
fact weighed in the ultimate finding. What constitutes adequate
reasons will therefore vary, depending on
the circumstances of
the particular case. Ordinarily, reasons will be adequate if a
complainant can make out a reasonably substantial
case for a
ministerial review or an appeal.
64. In
Maimela
, the
factors to be taken into account to determine the adequacy of
reasons were succinctly and helpfully summarised as guidelines,
which include –
“
[t]he
factual context of the administrative action, the nature and
complexity of the action, the nature of the proceedings leading
up
to the action and the nature of the functionary taking the action.
Depending on the circumstances, the reasons need not always
be “full
written reasons”; the “briefest
pro
forma
reasons
may suffice”. Whether brief or lengthy, reasons must, if
they are read in their factual context, be intelligible
and
informative. They must be informative in the sense that they convey
why the decision-maker thinks (or collectively think)
that the
administrative action is justified”.
The purpose for which
reasons are intended, the stage at which these reasons are given,
and what further remedies are available
to contest the
administrative decision are also important factors. The list, which
is not a closed one, will hinge on the facts
and circumstances of
each case and the test for the adequacy of reasons must be an
objective one.”’ (Footnotes omitted.)
[29]
SMEC
para 92.
[30]
APM
in its heads contended that t
he
‘shortlisting decision, provisional preferred bidder decision,
and award decision ….are all being challenged in
this
application, although APMT’s challenge is primarily against
the award decision and the other two are challenged only
in the
alternative and to the extent necessary’.
[31]
Whatever
criticism APM may have of Transnet, ICTSI or Growthstone, it must be
noted that nowhere in the papers or in argument
has there been any
suggestion that the process in selecting ICTSI as the successful
bidder was attributable to malfeasance or
corrupt activity by any
party.
[32]
See
Premier
of KwaZulu-Natal and Others v KwaZulu-Natal Gaming and Betting Board
and Others and a Related Matter
[2019]
3 All SA 916 (KZP).
[33]
Aurecon
South Africa (Pty) Ltd v Cape Town City
[2015]
ZASCA 209
;
2016 (2) SA 199
(SCA) (
Aurecon
)
para 17.
[34]
Centre
for Child Law and Others v South African Council for Educators and
Others
[2024]
ZASCA 45
;
2024
(4) SA 473
(SCA)
para
10.
[35]
Gqwetha
v Transkei Development Corporation Ltd and Others
2006
(2) SA 603
(SCA) (
Gqwetha
)
paras 22.
[36]
Opposition to Urban
Tolling Alliance v South African National Roads Agency Limited
[2013] ZASCA 148
;
[2013]
4 All SA 639
(SCA) (
OUTA
)
para 26.
[37]
Wolgroeiers
Afslaers (Edms) Bpk v Munisipaliteit van Kaapstad
1978
(1) SA 13
(A) (
Wolgroeiers
Afslaers
) at
41E-F.
[38]
In
Gqwetha
para
23, relying on
Wolgroeiers
Afslaers
at
42C, the following is stated: ‘proof of actual prejudice to
the respondent is not a precondition for refusing to entertain
review proceedings by reason of undue delay, although the extent to
which prejudice has been shown is a relevant consideration
that
might even be decisive where the delay has been relatively slight’.
[39]
See
Premier,
Free State, and Others v
Firechem
Free State (Pty) Ltd
2000
(4) SA 413
(SCA) (
Firechem
)
para 30: ‘
One
of the requirements … is that the body adjudging tenders
be presented with comparable offers in order that its
members should
be able to compare. Another is that a tender should speak for
itself. Its real import may not be tucked away,
apart from its
terms. Yet another requirement is that competitors should be treated
equally, in the sense that they should all
be entitled to tender for
the same thing. Competitiveness is not served by only one or some of
the tenderers knowing what is
the true subject of tender …
That would deprive the public of the benefit of an open
competitive process
.’
[40]
See
Economic
Freedom Fighters v Gordhan and Others
[2020]
ZACC 10
;
2020 (6) SA 325
(CC) para 47: ‘…the grant of
an interim interdict does not, and should not, affect the review
court’s decision
when making its final decision and should not
have an effect on the determination of the rights in the main
application’.
[41]
Allpay
para
30.
[42]
Transnet accepted that
Growthstone was not mandated to confirm the RFQ requirements or to
assess ICTSI’s compliance with
the solvency ratio. It was
directed to conduct a due diligence on ICTSI as the preferred
proponent.
[43]
Eastern Cape Parks
and Tourism Agency v Medbury (Pty) Ltd t/a Crown River Safari
[2018]
ZASCA 34
;
2018 (4) SA 206
(SCA).
[44]
Electoral Commission
of South Africa
v
Umkhonto Wesizwe Political Party
(Council
for the Advancement of the South African Constitution and others as
amici curiae)
[2024]
ZACC 6; 2024 (7) BCLR 869 (CC).
[45]
Millennium Waste
Management
(
Pty
)
Ltd v
Chairperson, Tender Board: Limpopo Province and Others
[2007]
ZASCA 165
;
2008 (2) SA 481
(SCA) para 4.
[46]
Allpay
para 40.
[47]
Allpay
para 62 states the
following:
‘
What
one is left with is non-compliance with what the request for
proposals regarded as mandatory. This means that a mandatory
condition prescribed by an empowering provision was not
complied with, which is a ground for review under s 6(2)
(b)
of
PAJA. But the subsection also requires that the non-compliance must
be of a material nature. The purpose of separate bids for
the
provinces was surely to enable SASSA to assess whether the bidder
would be able to provide the necessary services in each
of the
provinces for which it bid. This purpose was attained. The
irregularity was not material. No ground for review under
PAJA
exists.’
[48]
Contained in clause
1.4(h) of the RFQ.
[49]
See
Bato
Star Fishing (Pty) Ltd v Minister of Environmental Affairs and
Tourism and Others
[2004]
ZACC 15
;
2004 (7) BCLR 687
(CC), where reference is made to the
article by Professor Hoexter entitled ‘The Future of Judicial
Review in South African
Administrative Law’
(2000) 117
SALJ
484 at 501-502 where
judicial deference was explained as follows:
‘
(A)
judicial willingness to appreciate the legitimate and
constitutionally-ordained province of administrative agencies;
to admit the expertise of those agencies in policy-laden or
polycentric issues; to accord their interpretation of fact and
law due respect; and to be sensitive in general to the
interests legitimately pursued by administrative bodies and the
practical and financial constraints under which they operate.’
[50]
Khumalo
para 35.
[51]
Allpay
para
28.
[52]
See
Minister
of Environmental Affairs and Tourism and Others v Pepper Bay Fishing
(Pty) Ltd; Minister of Environmental Affairs and
Tourism and Others
v Smith
2004
(1) SA 308
(SCA) in which applications for fishing rights had been
disqualified for non-compliance with peremptory lodging
requirements.
[53]
P
Volmink ‘
Legal
Consequences of Non Compliance with Bid Requirements’ (2012) 1
African
Public Procurement Legal Journal
41
at 44.
[54]
The
author goes on to
offer
the following explanation of the ‘purposive approach’ at
52:
‘
Thus,
if the purpose of the bid requirement was achieved despite the fact
that the provision was not fully complied with, the
bidder should be
regarded as sufficiently compliant and not be disqualified. The
purposive approach is less formalistic as it
focuses attention away
from the classification of a requirement as “mandatory”
or “permissive” and instead
engages with the more
fundamental question as to whether the bid requirement in question
is material (whether it serves an important
purpose) and whether
that purpose was in fact achieved, despite the imperfect
compliance.’
[55]
Biowatch Trust v
Registrar, Genetic Resources, and Others
[2009]
ZACC 14
;
2009 (6) SA 232
(CC) (
Biowatch
).
[56]
Harrielall v
University of KwaZulu-Natal
[2017]
ZACC 38
;
2018 (1) BCLR 12
(CC) (
Harrielall
).
[57]
SMEC
para
143.
sino noindex
make_database footer start
Similar Cases
APM Terminals BV v Transnet SOC Limited and Others (D3052/2024) [2024] ZAKZDHC 69 (9 October 2024)
[2024] ZAKZDHC 69High Court of South Africa (KwaZulu-Natal Division, Durban)100% similar
APM Terminals BV v Transnet SOC Limited and Others (Leave to Appeal) (D3052/2024) [2024] ZAKZDHC 90 (11 December 2024)
[2024] ZAKZDHC 90High Court of South Africa (KwaZulu-Natal Division, Durban)100% similar
Transnet National Ports Authority v Umhlatuze General Sales and Services (Pty) Ltd t/a KZN Sales and Services and Others (D9748/22) [2024] ZAKZDHC 85 (20 November 2024)
[2024] ZAKZDHC 85High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Transnet SOC Ltd v Govender and Others (D528/2023) [2024] ZAKZDHC 16 (26 April 2024)
[2024] ZAKZDHC 16High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar
Transnet SOC Ltd v Kings Rest Container Park (Pty) Ltd (13410/2017) [2024] ZAKZDHC 53 (27 August 2024)
[2024] ZAKZDHC 53High Court of South Africa (KwaZulu-Natal Division, Durban)98% similar