Case Law[2023] ZACC 3South Africa
Mfoza Service Station (Pty) Ltd v Engen Petroleum Ltd and Another (CCT 167/21) [2023] ZACC 3; 2023 (4) BCLR 397 (CC); 2023 (6) SA 29 (CC) (1 February 2023)
Constitutional Court of South Africa
1 February 2023
Headnotes
Summary: Petroleum Products Act 120 of 1977— section 12B(4)(a) — powers of an arbitrator — awarding of damages as a remedy
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Constitutional Court
South Africa: Constitutional Court
You are here:
SAFLII
>>
Databases
>>
South Africa: Constitutional Court
>>
2023
>>
[2023] ZACC 3
|
Noteup
|
LawCite
sino index
## Mfoza Service Station (Pty) Ltd v Engen Petroleum Ltd and Another (CCT 167/21) [2023] ZACC 3; 2023 (4) BCLR 397 (CC); 2023 (6) SA 29 (CC) (1 February 2023)
Mfoza Service Station (Pty) Ltd v Engen Petroleum Ltd and Another (CCT 167/21) [2023] ZACC 3; 2023 (4) BCLR 397 (CC); 2023 (6) SA 29 (CC) (1 February 2023)
Download original files
PDF format
RTF format
Links to summary
PDF format
RTF format
Heads of argument BEGIN
Heads of arguments
PDF format
Heads of argument END
make_database: source=/home/saflii//raw/ZACC/Data/2023_3.html
sino date 1 February 2023
CONSTITUTIONAL
COURT OF SOUTH AFRICA
Case CCT 167/21
In
the matter between:
MFOZA
SERVICE STATION (PTY) LIMITED
Applicant
and
ENGEN
PETROLEUM LIMITED
First
Respondent
VINCENT
MALEKA
Second Respondent
Neutral
citation:
Mfoza Service Station (Pty)
Ltd v Engen Petroleum Ltd and Another
[2023] ZACC 3
Coram:
Kollapen J,
Madlanga J, Majiedt J, Mathopo J, Mhlantla J,
Mlambo AJ, Theron J, Tshiqi J
and Unterhalter AJ
Judgments:
Kollapen
J (majority): [1] to [79]
Mhlantla
J (dissenting): [80] to [98]
Heard
on:
17 May 2022
Decided
on:
1 February 2023
Summary:
Petroleum
Products Act 120 of 1977
—
section 12B(4)(a)
— powers of
an arbitrator — awarding of damages as a remedy
ORDER
On
appeal from the Supreme Court of Appeal (hearing an appeal from the
High Court of South Africa, Gauteng Local Division,
Johannesburg):
1.
Leave to
appeal is granted.
2.
The appeal is
dismissed.
3.
The applicant is to pay
the costs of this appeal, including the costs
of two counsel where so employed.
JUDGMENT
KOLLAPEN J
(Majiedt J, Mathopo J, Theron J, Tshiqi J and
Unterhalter AJ concurring):
Introduction
[1]
This
application raises the question whether damages are available as a
remedy under section 12B(4)(a) of the Petroleum Products
Act
[1]
(PPA). Section 12B(4)(a) of the PPA empowers an arbitrator
in proceedings brought under that provision to determine
whether
petroleum wholesalers or retailers have engaged in unfair or
unreasonable contractual practices and, if so, to “make
such
award as he or she deems necessary to correct such practice”.
Background
[2]
The applicant, Mfoza Service Station (Pty) Limited, conducts
the business of a service station and entered into a lease agreement
with the first respondent, Engen Petroleum Limited, a
petroleum wholesaler which owns the premises from which Mfoza
operated its petroleum retail business. The relationship
between the parties was governed by the terms of the lease agreement,
which has since come to an end. The provisions of section 12B
of the PPA also find application as they introduce a standard
of
fairness and reasonableness into the contractual practices of the
parties. Section 12B of the PPA provides:
“
(1)
The Controller of Petroleum Products may on request by a licensed
retailer alleging an unfair
or unreasonable contractual practice by a
licensed wholesaler, or
vice versa
, require, by notice in
writing to the parties concerned, that the parties submit the matter
to arbitration.
(2)
An arbitration contemplated in subsection (1) shall be heard—
(a)
by an arbitrator chosen by the parties concerned; and
(b)
in accordance with the rules agreed between the parties.
(3)
If the parties fail to reach an agreement regarding the arbitrator,
or the applicable
rules, within 14 days of receipt of the notice
contemplated in subsection (1)—
(a)
the Controller of Petroleum Products must upon notification of such
failure, appoint
a suitable person to act as arbitrator; and
(b)
the arbitrator must determine the applicable rules.
(4)
An arbitrator contemplated in subsection (2) or (3)—
(a)
shall determine whether the alleged contractual practices concerned
are unfair or
unreasonable and, if so, shall make such award as he or
she deems necessary to correct such practice; and
(b)
shall determine whether the allegations giving rise to the
arbitration were frivolous
or capricious and, if so, shall make such
award as he or she deems necessary to compensate any party affected
by such allegations.
(5)
Any award made by an arbitrator contemplated in this section shall be
final and binding
upon the parties.”
[3]
Following a dispute between the parties arising from
allegations by Mfoza that it had suffered damages because Engen had
breached
the lease agreement, the Controller of Petroleum
Products (Controller) directed that the parties submit their dispute
to arbitration.
The Controller concluded that the requirements
for a referral to arbitration had been met and referred the matter to
arbitration.
All of the claims of Mfoza in the arbitration were
pleaded as breach of contract claims, and the only relief sought was
the
payment of damages which related to alleged past loss of profit,
loss of goodwill and loss of property value suffered as a result
of
the conduct of Engen.
[4]
There is nothing in Mfoza’s statement of claim that
refers to conduct that would constitute unfair or unreasonable
contractual
practices. The second respondent (Arbitrator) also
understood that what was before him, requiring determination, was an
objection
by Engen that the claim of Mfoza was one for damages and
that this was precluded by the PPA.
Findings
by the Arbitrator
[5]
Arbitration proceedings commenced, during which Engen raised
three preliminary objections – only one of which is relevant in
these proceedings. It objected to the monetary compensation
sought by Mfoza on the basis that such relief amounted to a claim
for
damages. It said damages could not be awarded under the
arbitral jurisdiction conferred upon the Arbitrator, in terms
of
section 12B(4)(a) of the PPA.
[6]
The
Arbitrator found that the dictum in
Business Zone
SCA
,
[2]
that an award of damages was not competent under the remedial
jurisdiction of section 12B(4), was not a proposition of universal
application. He determined that a finding of an unreasonable or
unfair contractual practice arising from a contract may well
be
corrected by way of monetary compensation.
[7]
He
also found that the scope of an arbitrator’s power to make a
corrective award in terms of section 12B(4)(a) is formulated
in
general terms, namely, an award which “he or she deems
necessary to correct such [unfair or unreasonable contractual]
practice”. The Arbitrator took the view that this
included having resort to a range of corrective measures. He
sought to place reliance on the dictum in
Bright
Idea
[3]
in relation to section 12(4)(a) that—
“
[a]
push-pull tension between freedom and constraint similar to
subsection (4)(a) is also built into subsection 4(b).
The
arbitrator’s apparently wide power to ‘compensate any
party’ is restricted to ‘frivolous or capricious’
allegations and only against those who make them to give rise to the
arbitration. An arbitrator is expressly allowed to impose
a
compensation award against a party for frivolous or capricious
referrals.
In
the absence of any similar power to award compensation as a
substantive remedy for unfair or unreasonable contractual practices,
it would be a matter of interpretation of the PPA and the facts
of a particular case, whether an award of compensation would
be an
effective remedy to correct a practice. This is confirmed in
the Constitutional Court’s holding that ‘the
arbitrator’s remedial powers can go no further than correcting
the contractual practice in question.’
”
[4]
(Emphasis added).
[8]
He said that section 12B(4)(a) was to be interpreted to
reflect a purposive and workable interpretation of the arbitral
powers vested
upon an arbitrator and that those would include the
power to award compensation.
[9]
The Arbitrator also found that there is no prohibition to be
found in section 12B against making an award for monetary
compensation
for the purpose of correcting an unreasonable or unfair
contractual practice. He found that there is no justification
or
logic in excluding an award for compensation which has a logical
connection to, and represents a proportional redress against, an
offending contractual practice.
[10]
In dealing with the dictum of
Business Zone SCA
which
was relied on by Engen, the Arbitrator said that our law
distinguished between a monetary award resulting from a cause
of
action founded upon a contractual or delictual claim for damages, and
other forms of monetary compensation arising from a different
cause
of action. He explained that just and equitable compensation,
expressly provided for in the labour dispute adjudication
of unfair
labour practices, is not expressly prohibited under the open ended
corrective remedial powers of an arbitrator under
section 12B(4)(a)
of the PPA. He found that this is implied from the express
terms of the powers of an arbitrator in
section 12B(4)(a) of the
PPA.
[11]
In his award, the Arbitrator concluded that, as a matter of
principle, there was no bar to an award for monetary compensation
being
made which arose out of an unfair or unreasonable contractual
practice. He found that he had the power, under the broad
rubric
of monetary compensation, to award damages as well as other
forms of compensation. He dismissed the preliminary objection.
Litigation
history
High
Court
[12]
Engen
asked the High Court of South Africa, Gauteng Local Division,
Johannesburg, to review and set aside the award on the
basis that
the Arbitrator committed a material error of law which
constituted a gross irregularity, in that he exceeded his
powers as
contemplated by section 33 of the Arbitration Act.
[5]
The High Court’s stance was that the Arbitrator
incorrectly interpreted the provisions of section 12B(4)(a)
of
the PPA to confer a right upon Mfoza to claim patrimonial
damages.
[6]
It said that
the Supreme Court of Appeal and the Constitutional Court have
held that the jurisdiction conferred in terms
of section 12B(4)(a) is
corrective.
[7]
It relied
on the view taken by the Supreme Court of Appeal in
Business
Zone SCA
that an award of damages is not competent under the corrective
remedial jurisdiction, but only under a compensatory remedial
jurisdiction.
[8]
As such,
the relief sought by Mfoza did not fall within the corrective
remedial jurisdiction of the Arbitrator.
[9]
[13]
The
High Court went further to hold that the Arbitrator was confined by
legislation to the powers that the statute conferred.
[10]
Consequently, it held that an arbitrator acting under the statue
cannot award relief beyond the scope of what the courts
have held
that the statute permits, as this is the essence of the rule of
law.
[11]
[14]
The
High Court explained that the aim of section 12B(4)(a) was to address
the unequal bargaining power between parties, being a
wholesaler and
a licensed retailer.
[12]
It
authorised corrective remedial action prospectively, and as such past
wrongs could not be addressed in the form of a damages
award.
It explained that Engen could be directed to amend its ways in the
future.
[13]
However, the
statute under which the arbitration was convened, and from which the
Arbitrator derived his powers to grant
the specific relief, does not
permit damages claims for past wrongs.
[14]
[15]
The
Court found that the Arbitrator exceeded his powers as contemplated
in section 33(1)(b) of the Arbitration Act and set
aside the
award.
[15]
It found that
damages were not available as a remedy under section 12B(4)(a) of the
PPA and that the Arbitrator was
confined to determining his
jurisdiction on the case pleaded and not on a case that was not
before him. The latter was a
reference to the forms of
compensation other than damages that the Arbitrator made reference to
and which the High Court said
was not before him. The
High Court further directed Mfoza to amend its statement of case
to remove the claim for patrimonial
damages.
Leave
to appeal in the High Court
[16]
Mfoza applied for leave to appeal against the High Court
order and judgment. The High Court was however not
persuaded
that another court might come to a different conclusion and
the application for leave to appeal was dismissed with costs.
Supreme
Court of Appeal
[17]
On 16 March 2021, Mfoza filed an application for leave to
appeal with the Supreme Court of Appeal. The application
was
dismissed with costs on the grounds that there were no reasonable
prospects of success and there was no other compelling reason
why an
appeal should be heard.
In
this Court
Mfoza’s
submissions
[18]
In respect of jurisdiction, Mfoza submits that this
application raises both constitutional issues, as well as an
arguable point
of law of general public importance. Mfoza
submits that constitutional issues arise from the following: (a) the
correct interpretation and ambit of a public power – an
arbitrator’s statutory power; (b) the confirmation or
setting aside of an arbitration award implicating the administration
of justice; and (c) the transformational aspects of the
PPA that
seek to give effect to the right to equality located in section 9
of the Constitution as well as the nature
of the corrective
powers of an arbitrator appointed to promote that purpose.
[19]
The arguable point of law of general public importance is
whether damages or compensation are competent awards under section
12B(4)(a)
of the PPA. The proper interpretation of section
12B(4)(a) is an arguable point of law whose determination transcends
the
interests of the parties as it has implications for the petroleum
industry as a whole. Mfoza submits that its prospects of
success are good and that the public interest that the matter raises
leads to the conclusion that the interests of justice favour
the
granting of leave to appeal.
[20]
On
the merits, Mfoza says that the restrictive interpretation of
section 12B(4)(a) by the Supreme Court of Appeal in
Business
Zone SCA
[16]
is incorrect in that—
(a)
the award of damages or compensation falls within the settled core of
corrective justice and a corrective
jurisdiction. The
Arbitrator’s corrective jurisdiction includes, but is not
limited to, the competence to award damages
or compensation;
(b)
interpreting section 12B(4)(a) as empowering an arbitrator to award
patrimonial damages or compensation to
correct an unfair or
unreasonable practice accords with the transformational purpose of
the PPA, which includes addressing unequal
bargaining power in the
industry; and
(c)
the general competence to make any award so as to correct an unfair
or unreasonable practice is framed in
broad and open-ended terms.
Section 12B(4)(a) confers upon an arbitrator “wide
remedial power”, which does
not exclude damages or
compensation.
[21]
Mfoza also submits that the use of the word “correct”
should not be understood or interpreted narrowly to qualify or
cut
down the provision. The payment of compensation is amongst the
awards that may be necessary to correct a party’s
wrongful -
or, in the context of section 12B, unfair or unreasonable -
practice. It says that in some instances compensation
may,
depending on the circumstances, be the only remedy available to
correct the unfair or unreasonable contractual practice.
[22]
Mfoza
submits that the High Court had no power to substitute the award.
To support this contention, Mfoza states that, unlike
section 172(1)(b) of the Constitution and section 8 of
the Promotion of Administrative Justice Act,
[17]
section 33(1) of the Arbitration Act does not give the
court wide discretionary powers to order any just and equitable
remedy. The section provides for only one remedy: setting
aside. Therefore, the High Court’s substitution
of
the award was not competent and also stands to be set aside.
Engen’s
submissions
[23]
Engen submits that Mfoza’s application for leave to
appeal does not engage the jurisdiction of this Court. It
submits
that Mfoza does not seek to assert any constitutional right.
In addition, it denies that there are good prospects of success
and
argues that it is not in the interests of justice to grant leave to
appeal.
[24]
It submits that a monetary award does not alter, let alone
transform, the structure of the parties’ relationship when they
exercise their rights or carry out their duties – it
does not correct the practice that has been submitted to the
arbitrator. Engen submits that this interpretation is supported
by the text of section 12B, its underlying purpose, and the
statutory
context. Furthermore, it is the interpretation which best gives
effect to the spirit, purport and object of the
Bill of Rights.
[25]
Engen
relies on
Business
Zone SCA,
where the Supreme Court of Appeal distinguished between
corrective remedial jurisdiction under section 12B(4)(a) and
compensatory remedial jurisdiction under section 12B(4)(b), with the
former operating only prospectively. It also says that
in
Business
Zone CC
,
[18]
this Court held that the act of cancellation could in itself
constitute a contractual practice and that this was the only aspect
of
Business
Zone SCA
which was overturned. On that basis, Engen submits that
this Court accepted as correct the fundamental distinction
between corrective remedial jurisdiction under section 12B(4)(a) and
compensatory remedial jurisdiction under section 12B(4)(b).
[26]
In
order to determine the scope of an arbitrator’s power under
section 12B(4)(a) of the PPA, Engen submits that when
interpreting a statutory provision, the point of departure is that
the words employed must be construed in accordance with their
ordinary grammatical meaning. However, Engen further submits
that the interpretative exercise must have regard to both purpose
and
context. Engen relies on the following principles, as set out
in
Goedgeleen
:
[19]
(a) Statutory
provisions should always be interpreted purposively, which purpose
can include the provisions’ social
and historical background.
(b)
The provisions must be contextualised, by situating them in the
scheme of the statute as a whole.
(c)
The
provisions should not only be interpreted, where possible,
consistently with the Constitution, but the interpretation that best
does justice to the spirit of the Constitution should be
preferred.
[20]
[27]
On that basis Engen argues that the ordinary, grammatical
reading of the section, read with regard to both purpose and
context,
is that the scope of the arbitrator’s remedial power
extends to remedying or putting right the relationship between
contracting
parties. What must be corrected is the manner in which
the parties exercise or enforce their respective contractual rights
and
duties. The purpose of the arbitrator’s remedial
power is limited to correcting an unfair or unreasonable practice.
[28]
Engen says that Mfoza’s complaint that the High Court
exceeded its powers by substituting the award with its own order
is
misplaced. It says that the review application concerned a
discrete legal question regarding the scope of an arbitrator’s
powers. Having found that the Arbitrator was wrong to dismiss
the
in limine
objection, was the end of the matter, and the
order of substitution arose out of the setting aside order and did
not exceed the
power of the High Court sourced in section 33(1)(b) of
the Arbitration Act.
The
issues
[29]
The following issues require determination:
(a)
Is the jurisdiction of this Court engaged?
(b)
Should leave to appeal be granted?
(c)
Does section 12B(4)(a) of the PPA empower an arbitrator to make an
award of damages or compensation
as part of a corrective award
arising out of an unfair or unreasonable contractual practice?
(d)
If not, was the High Court’s order of substitution a competent
order falling within the competence of that
Court?
Jurisdiction
[30]
The
application for leave to appeal engages the jurisdiction of this
Court in that it raises a constitutional matter as well as
an
arguable point of law of general public importance. The power
of an arbitrator constitutes the exercise of public power
pursuant to
empowering legislation – being the PPA – and the
interpretation of the section raises a constitutional
matter.
[21]
The need to pronounce on the scope of the arbitrator’s power in
terms of section 12B(4)(a) transcends the interests
of the
parties and implicates the interests of a significant part of the
general public – this is also an arguable point
of law of
general public importance.
[22]
My view is that our jurisdiction is engaged.
Leave
to appeal
[31]
The
interests of justice in relation to the proper understanding and
interpretation of the PPA would benefit from certainty
regarding
the powers of an arbitrator in terms of section 12B of the PPA.
There are also reasonable prospects of success
which must mean
that leave to appeal should be granted.
[23]
The
merits
The
effect of section 12B on contractual practices in the petroleum
industry
[32]
Section 12B, in general terms, provides that a licensed
retailer or wholesaler in the petroleum products industry may, upon
alleging
an unfair or unreasonable contractual practice by the other
party, request the Controller to submit the matter to arbitration.
The arbitrator must determine whether the alleged practice is unfair
or unreasonable, and in such event, is obliged to make an
award he or
she deems necessary to correct such practice.
[33]
The
section may be seen as novel but has been regarded as a necessary
legislative intervention in the transformation of the petroleum
industry. While this appeal focuses on the powers of the
arbitrator, this Court in
Business Zone CC
said that the most significant innovation brought about by
section 12B was the introduction of a standard of fairness and
reasonableness.
[24]
That
standard would apply in the adjudication of disputes in all such
contracts, regardless of whether they are subject to
statutory
arbitration or litigation in court. In
Crompton
,
[25]
this Court described the creation of the arbitral mechanism in the
PPA as an attempt by the Legislature to address the unequal
bargaining power between wholesalers and retailers in the petroleum
industry.
[26]
It
also
said
that section 12B provides access to arbitration “which may
otherwise not exist possibly due to the unequal bargaining
position
retailers
vis a vis
wholesalers
find themselves in”, and that a purposive interpretation of the
section was required to give effect to this right.
[27]
[34]
Section 12B also operates against the backdrop of a
contractual relationship between the parties that is subject to the
equitable
standard of fairness and reasonableness. To that
extent, it is a far-reaching measure that seeks to achieve a
necessary and
transformative objective in the petroleum industry, but
it is also a measure that brings with it its own challenges. This
Court has in
Business Zone CC
said that there was—
“
no
reason why the specifics of the general standard of fairness and good
faith in the common law of contract should not be given
shape in the
context of petroleum contracts, as is done in the context of labour
or rental housing contracts.”
[28]
[35]
Section
12B(1) is limited to allegations of unfair or unreasonable
contractual
practices.
[29]
An aggrieved party who does not allege unfairness or
unreasonableness will not have access to the section 12B arbitral
system.
[30]
It has been
described as a low threshold, but is nevertheless one that must be
met before a referral by the Controller to
arbitration may take
place. In these circumstances, a party seeking redress outside
of an allegation of an unfair or unreasonable
contractual practice
will only have resort to a court and may not invoke the section 12B
arbitral system.
[36]
In
addition, recourse to arbitration is not mandatory in the sense that
an aggrieved party is not obliged to use it. The Controller’s
power to refer a matter to arbitration must be preceded by a request
from a licensed retailer or wholesaler.
[31]
An aggrieved party may elect not to utilise the provisions of
section 12B but to litigate in court. This Court
has said that
the arbitral system that section 12B creates does not oust the
jurisdiction of the High Court but presents an additional
route for
licensed retailers and wholesalers alike to have their disputes
adjudicated more quickly, within rules and processes
of their own
design.
[32]
[37]
In sum, the features of the section 12B arbitral system
reflects a mechanism that is limited in its scope and application.
It
is confined to dealing only with contractual practices that
are alleged to be unfair or unreasonable and then to correct those
practices. The jurisdiction of the High Court is not ousted by
section 12B, and what emerges are parallel systems whose
scope
and reach may differ but share a common adjudicative standard.
It is within this context that I proceed to deal with
the
interpretation of section 12B(4)(a).
The
interpretation of section 12B(4)(a)
[38]
Business Zone CC
and
Crompton
dealt with various
features of the system created by section 12B but were not
required to deal with the interpretation of
section 12B(4)(a).
[39]
In
Cool
Ideas
,
[33]
Majiedt AJ described the approach to statutory interpretation as
follows:
“
A
fundamental tenet of statutory interpretation is that the words in a
statute must be given their ordinary grammatical meaning,
unless to
do so would result in an absurdity. There are three important
interrelated riders to this general principle, namely
(a)
that statutory provisions should always be interpreted purposively;
(b)
the relevant statutory provision must be properly contextualised; and
(c)
all statutes must be construed consistently with the Constitution,
that is, where
reasonably possible, legislative provisions ought to
be interpreted to preserve their constitutional validity. This
proviso
to the general principle is closely related to
the purposive approach referred to in (a).”
[34]
[40]
Section
12B(4)(a) requires an arbitrator to establish whether the alleged
contractual practices are unfair or unreasonable and,
if so, to
correct such practice by the making of an award. It follows
that all that an arbitrator is required to do is to
make a
determination whether a contractual practice is unfair or
unreasonable. There is no power nor requirement for the
arbitrator to go beyond that and matters of fault, causation, loss,
or damage fall outside of the enquiry. Once an arbitrator
has
made a determination that a contractual practice is unfair or
unreasonable then the arbitrator has wide powers but they
are
confined to correcting the practice. One must therefore
distinguish the limited nature of the determination that an
arbitrator is required to make and the wide powers of redress
following such a determination. The purpose of making the award
is that it must be
necessary
to correct such practice.
[35]
The arbitration model is a creation of statute and the power of the
arbitrator is derived from the PPA. It is a power
that must be
exercised within its lawful parameters and for the purpose it has
been given.
[36]
[41]
It must follow that the award may go no further than
correcting the practice. This is the ordinary meaning that the
section
must attract, and it was not in dispute before us that the
remedial power of the arbitrator is limited to being a corrective
one.
The meaning of what it is to “correct a practice”
is where the parties part ways.
[42]
A
related but important issue is whether the corrective power must also
be applied within an ongoing contractual relationship between
the
parties. The argument is that if the parties’
relationship has come to an end, then there was nothing to correct,
and there can be no basis for a referral to arbitration by the
Controller. This Court in
Business Zone CC
rejected the view that section 12B can only apply against the
backdrop of an ongoing contractual relationship between the
parties
and held that even a single act of cancellation could amount to a
contractual practice under section 12B(4)(a).
[37]
It said, however, that in such an event, the arbitrator’s
powers could extend to correcting the practice by setting
aside the
termination and reinstating the contract. So, it seems like the
notion of “correction” finds application
in the context
of relationships that remain in existence - either in law or in fact.
In both instances, the continued existence
of the relationship
would provide the basis for a corrective award where there continues
to exist a practice that is subject to
correction.
[43]
It follows from this that section 12B is primarily concerned
with relationships, and the need for such relationships to conform to
the principles of fairness and reasonableness. Where either or
both of those standards have been breached through an unfair
or
unreasonable practice, the objective of a remedial award must be to
bring the relationship into conformity with the required
standard by
correcting the practice. The language of section 12B(4)(a)
requires no more of an arbitrator than an award
that would correct
the practice. The correction that the section requires is that
of a practice and a practice, in turn,
is about what the parties are
doing or perhaps not doing.
[44]
The
focus of the enquiry is therefore, not whether “correct”
may have a wide or narrow meaning and may include damages
but rather
what is necessary to correct a practice with the emphasis being on
practice
.
An award of compensation may address the consequences of an
unfair or unreasonable practice but not necessarily conformity
by a
party with a standard of conduct which entails performance. The
power to correct a practice is inextricably linked to
addressing and
bringing the relationship between the parties to the standard of
fairness and reasonableness that section 12B demands.
The
section was never intended to address all of the disputes and claims
between the parties that may arise out of their
contractual
relationship. In particular, regard being had to the dicta of
this Court in
Business
Zone CC
,
the corrective power could be exercised where no relationship existed
between the parties that was capable of being corrected.
[38]
In that situation, all that would be before the arbitrator would be a
historical contractual practice. In those instances,
there
would be no practice to correct by an arbitral award even though the
consequences of such a practice, if constituting a breach
of contract
and resulting in loss, may be the basis for an action in the courts.
[45]
In that event, the aggrieved party would be required to prove
the requirements that would normally attach to such an action
including
breach, loss, and factual and legal causation. Section 12B
however contemplates a much simpler process – a
determination whether a contractual practice is fair or reasonable
and, if not, the making of an award to correct that practice.
The
limited arbitral system therefore represents a deliberate legislative
choice to deal with only correcting the conduct
of a party to an
unfair or unreasonable contractual practice.
[46]
In
this context “to correct a practice” is therefore about
restoring the relationship by identifying the contractual
practice
that imperils the relationship, and then making an award that will
end the practice in question. It would, in such
circumstances,
be an intervention that was essentially forward-looking and
corrective in the sense of putting right a relationship.
In
Business
Zone SCA
,
the Supreme Court of Appeal distinguished, in the context of section
12B(4), what it termed the corrective remedial jurisdiction
and the
compensatory remedial jurisdiction, concluding that corrective
remedial jurisdiction can only operate prospectively.
[39]
[47]
This Court overturned that part of the Supreme Court of
Appeal’s judgment, which found that an ongoing relationship was
a
prerequisite to access the arbitral system in section 12B.
It did so, however, to the limited extent that the corrective
power
could be used to reinstate such a relationship, and in that scenario,
a relationship would have come into existence.
It also left
intact the Supreme Court of Appeal’s analysis and conclusion on
the difference between corrective and compensatory
jurisdictions and
when they were applicable.
[48]
Mfoza takes the view that section 12B is not about
relationships but contractual practices. However, this really
is a distinction
without a difference as those practices that the
section identifies as the basis for arbitration exist within a
relationship -
not in isolation. It is those relationships that
this Court has identified as manifesting an imbalance in power and it
is
those relationships that require fixing. That is the
innovation that section 12B introduces.
[49]
Mfoza argued that “to correct” should not be
confined to dealing with a contractual practice and making a
forward-looking
award, without at the same time dealing with the past
consequences of that practice. It said that dealing with its
consequences
was integral to correcting it and takes the view that
this approach supports an interpretation of the section that includes
the
power to award compensation.
[50]
Engen’s stance was that the Arbitrator was confined to
making an award necessary to correct an unfair or unreasonable
contractual
practice. My view is that the limited role “to
correct a practice” does not extend to addressing the
historical
effect or consequences of that practice, as that is not
what is required to correct the practice. One is reminded that
the
determination an arbitrator is required to make is confined to
whether a contractual practice is unfair or unreasonable. This
in itself limits the scope of the arbitrator’s powers which do
not extend to making an award of compensatory damages.
There is
a significant difference between correcting a practice as opposed to
addressing the consequence of a practice. An
award of
compensation that deals with the consequences of an unfair or
unreasonable contractual practice may compensate but leave
a practice
uncorrected – this is not what section 12B(4)(a) has in mind.
It will be recalled that all that section 12B(4)
requires
to trigger a referral to arbitration is an allegation of an unfair or
unreasonable contractual practice which would then
require
correction. The question of loss and the compensation for loss
falls outside of the section 12B process.
[51]
I
have already made reference to the overall scheme of the section and
the limited purpose for its introduction in the industry.
If
that purpose is limited to correcting an unfair or unreasonable
contractual practice, then there is no basis to interpret
the power
of an arbitrator to make a compensatory award for past loss when such
an award is not necessary to correct the unfair
or unreasonable
contractual practice. In
Chisuse
,
[40]
this Court said that “in legal interpretation, the
ordinary understanding of the words should serve as a vital
constraint
on the interpretative exercise, unless this interpretation
would result in an absurdity”
[41]
and, further that “[t]he purposive or contextual interpretation
of legislation must, however, still remain faithful to the
literal
wording of the statute”.
[42]
That constraint must find application here.
[52]
Although
section 12B(4)(a) does not expressly exclude compensation, it
would have to be shown then that the power under this
section would
be necessary to correct the practice and that it cannot be exercised
if the power to award compensation under section 12B(4)(a)
does
not also exist. In
Amabhungane
,
[43]
Madlanga J said:
“
This
case presents us with an opportunity to deal not with the common and
oft dealt with necessary or ancillary implied
power (which
I will simply call the ancillary implied power), but with what I
would call a primary implied power. . . . An
ancillary implied
power arises where a primary power – whether express or implied
– conferred by an Act cannot be exercised
if the ancillary
implied power does not also exist.”
[44]
[53]
The question then is whether the power to award compensation
under section 12B(4)(a) is necessary without hollowing out the
PPA as a whole, rendering the section inoperable. In my view,
no ancillary implied power arises as the primary power of the
arbitrator to correct can be given effect to, without the power to
make an award of compensation under section 12B(4)(a).
[54]
If
the section is interpreted as Mfoza would have it, then the
arbitrator would have unlimited powers. Those powers would
include the power to make a prospective award to correct an unfair or
unreasonable contractual practice, the power to award compensation
for past loss arising out of an unfair or unreasonable contractual
practice, and the power to make a compensatory award for allegations
giving rise to arbitration that were frivolous or capricious.
This Court reminded us in
Business Zone
CC
that
the remedial powers of the arbitrator are limited.
[45]
However, the interpretation which Mfoza seeks would place no
limitation on those powers. Such a stance is not sustainable
and does not accord with the idea of an arbitrator exercising limited
remedial corrective powers as section 12B requires.
[55]
There are other reasons why the term “to correct”
cannot have the meaning that Mfoza contends for.
[56]
The Legislature, in conferring the powers of the arbitrator in
section 12B(4)(b), gives the arbitrator the power to make a
compensatory award arising out of frivolous or capricious
allegations, while the language of section 12B(4)(a) makes no
reference
to a compensatory award. It must be clear that the
Legislature sought to carefully demarcate the remedial powers of the
arbitrator
to the different situations contemplated by the PPA.
The choice of language and the scope of the power of the arbitrator
provides evidence of a clear intent to invest the arbitrator with
different powers in the different circumstances contemplated
by
subsections (4)(a) and (4)(b) of section 12B. That
demarcation suggests that if the lawmaker intended the arbitrator
to
have the power to make a compensatory award in terms of section
12B(4)(a), it would have simply done so as it did in the context
of
section 12B(4)(b). That it chose not to do so is evidence
of a deliberate legislative choice and one that fits into
the overall
scheme of the PPA and must be respected.
[57]
The
structure of section 12B(4) also invokes the maxim
inclusio
unius est exlusio alterius
(the
specific inclusion of one implies the exclusion of the other).
Through its specific inclusion and exclusion of different
kinds
of remedial powers, the Legislature intended to provide different
regimes of arbitral intervention. In particular,
the inclusion
of the power to compensate in section 12B(4)(b) and the
exclusion of a similar power in section 12B(4)(a)
must activate
the maxim. This supports the conclusion that the power to make
a compensatory award is excluded from section 12B(4)(a).
In
Pickfords
,
[46]
Majiedt J said that the maxim is not a rigid rule of statutory
construction and must be applied with caution. At the
same
time, he referred to the maxim as a principle of “common
sense”.
[47]
[58]
A further reason why “to correct” does not lend
itself to the generous interpretation Mfoza seeks, is that the very
nature of the arbitral system created by section 12B may not be
suited to the making of a compensatory award. The arbitral
system of section 12B is not arbitration by agreement, which is a
common feature of most arbitration processes. There are
a
number of features of the section 12B system that are
fit-for-purpose and fall into the limited scope of the arbitral
system.
They include the following:
(a)
The parties are obliged to submit to arbitration upon a referral by
the Controller
(there is a limited right of appeal to the
Minister only).
(b)
Any award made by the arbitrator is final and binding upon the
parties.
[59]
The
effect of this is that, on the interpretation that Mfoza contends
for, a party who has to meet a claim for damages under section
12B(4)(a) would be deprived of the protections afforded by the
ordinary legal process, including a right of appeal, and that may
infringe a party’s right of access to courts as enshrined in
section 34 of the Constitution.
[60]
If the power of the arbitrator is seen as a limited one
confined to correcting forward looking conduct, it would largely
fall
into the fit-for-purpose limited scope of section 12B.
It may stray somewhat from the ordinary access to court guarantees
but that may be justified if regard is had to the limited power of
the arbitrator and the transformative objective of the section.
[61]
It is a different matter, however, when an arbitrator makes a
final and binding compensatory award. When the outward effect
of the award on a party is considerably greater, the demand for the
constitutional guarantee of access to court must be more pressing.
A
non appealable award falls considerably short in meeting those
access to court guarantees. It is for these reasons
as well
that I take the view that the arbitral model that section 12B
introduces was never intended to deal with claims of
compensation.
The design of the system simply does not lend itself to the proper
adjudication of such claims. Absent
the protection of the
ordinary rules of litigation and absent a normative framework that is
defined in advance, it is too great
a risk to the constitutional
values of equality and fairness to permit a final and binding
compensatory award to be made in those
circumstances with no right of
appeal to a court.
[62]
Another reason why section 12B(4)(a)
cannot have the meaning Mfoza contends for is that it may lead to
disparate outcomes and consequences,
which conflicts with the
constitutional values of fairness and equality.
[63]
In
Crompton
,
Mhlantla J, in dismissing a claim that section 12B ousted the
jurisdiction of the High Court, said:
“
The
provisions of section 12B and the
Petroleum Products Act, in
general,
do not assign jurisdiction exclusively to the arbitrator over
disputes between licensed retailers and wholesalers in the
petroleum
industry. Nor do they provide that the dispute resolution
mechanism in
section 12B
is mandatory, or that it must be exhausted
before parties may approach the High Court where there are
allegations of unfair or
unreasonable contractual practices.
.
. .
Clearly,
the parties have a choice between the
section 12B
arbitration and
High Court litigation and both forums must apply the fairness
standard.”
[48]
[64]
The effect of this holding is that a
court or an arbitrator will be equally competent to enquire into
allegations of unfair or unreasonable
contractual practices arising
out of
section 12B
and make an award necessary to correct such a
practice. And, while the same adjudicative standard will apply
in both settings,
the differences in the nature of the two settings
are significant in the consequential rights of the parties.
[65]
An
award made by an arbitrator is final and binding and subject to
limited review – largely to misconduct, irregularity
or impropriety in obtaining the award.
[49]
An award made by the High Court would ordinarily be appealable
subject to leave being granted. This impacts on the
equality
before the law guarantee as well as the right of access to courts
found in section 34 of the Constitution.
[66]
This significant difference in
consequence is a further reason why the arbitral power should not be
construed as wide as Mfoza would
have it, as it could lead to
disparate outcomes to allow a compensatory award to be made in terms
of section 12B(4)(a).
It would mean that a party who is
obliged to submit to statutory arbitration faces the risk of a
non-appealable award of damages.
Section 40 of the
Arbitration Act provides
:
“
This
Act shall apply to every arbitration under any law passed before or
after the commencement of this Act, as if the arbitration
were
pursuant to an arbitration agreement and as if that other law were an
arbitration agreement: Provided that if that other law
is an Act of
Parliament, this Act shall not apply to any such arbitration in so
far as this Act is excluded by or is inconsistent
with that other law
or is inconsistent with the regulations or procedure authorized or
recognized by that other law.”
[67]
While
the Arbitration Act refers to an arbitration agreement, the form of
arbitration created by section 12B of the PPA is not by
agreement
between the parties. Courts should generally tread with caution
when defining the scope of the arbitration or the
powers of an
arbitrator under such circumstances. This is particularly so in
the context of the dispute before us where a
party to the arbitration
may face the risk of a non-appealable award of damages if it was
found that the arbitrator had the power
to award such damages. In
the absence of clear language by the Legislature to that effect the
interpretative exercise should
proceed with some caution and an
interpretation which is more consistent with recognising and
protecting the rights of the parties
should be preferred against one
that places those rights at risk. In
Wary
Holdings
,
[50]
Kroon AJ said the following regarding competing interpretations
of a statute:
“
This
Court has not yet been called upon to deal with the situation where
two conflicting interpretations of a statutory provision
could both
be said to promote the spirit, purport and objects of the Bill of
Rights and the decision to be made is whether the
one interpretation
is to be preferred above the other. It seems to me that it
cannot be gainsaid that this Court is required
to adopt the
interpretation which better promotes the spirit, purport and objects
of the Bill of Rights. That would, after
all, be a more
effective ‘[interpretation] through the prism of the Bill of
Rights’. By the same token, where
two conflicting
interpretations of a statute could both be said to be reflective of
the relevant structural provisions of the Constitution
as a whole,
read with other relevant statutory provisions, the interpretation
which better reflects those structural provisions
should be
adopted.”
[51]
[68]
There would of course be instances where the consequence of an
unfair or unreasonable contractual practice may result in loss or
damage. A party in such a situation may have recourse to court
to pursue a damages claim. Given that the contract between
the
parties is underpinned by the normative framework of fairness and
reasonableness, the breach of such a standard could form
the basis of
an action for damages before the courts. That the Legislature
has opted for a limited arbitral model as evidenced
in section 12B
is entirely consistent with the need for an efficient and
cost effective mechanism to correct unacceptable
contractual
practices. That it does not extend beyond that is also a
legislative choice that makes good sense for the reasons
I have
given, and is a choice that must be honoured.
[69]
The suggestion that the arbitrator may, as part of a
corrective award, make an award of damages simply does not fit into
any interpretation
of the section. An award of damages, if one
is competent, must be preceded by a determination of a breach of
contract or
some other basis to justify an award of damages. The
difficulty is that the arbitrator is not empowered to stray into
those
areas as the power given to the arbitrator in terms of
section 12B(4)(a) is limited as I have indicated.
[70]
In summary, the purpose of the section is confined to
determining whether a practice is unfair or unreasonable and then, if
it is,
to make an award to correct it. There is simply no room
for any suggestion of an award of damages, and the determination that
must precede it, in this carefully constructed innovation to the PPA.
To suggest otherwise would be to give the arbitrator
a power
that does not accord with the PPA.
[71]
I have
had the pleasure of reading the second judgment penned by my
Sister Mhlantla J, in which she concludes that the
powers
of the arbitrator in terms of section 12B(4)(a) are wide enough
to include compensation and awarding damages. I
deal briefly
with the basis on which she arrives at this conclusion:
(a)
The wide nature of the arbitrator’s powers. I have argued
that while the arbitrator enjoys
wide powers of correction, they are
limited to correcting an unfair or unreasonable contractual practice.
It cannot be suggested
that those wide remedial powers have the
effect of increasing the scope of the determinative powers of the
arbitrator.
(b)
There is nothing in section 12B(4)(a) that excludes compensation
or damages as a corrective award.
While, on the face of it,
that may well be so, if regard, however is had to the language,
purpose and context of the section
then everything militates against
the interpretation that section 12B(4)(a) contemplates such a
process and such a power.
There are no separate and distinct concepts
of “compensation” in section 12B(4)(a) and (b), as
the second judgment
suggests, as section 12B(4)(a) is silent on
compensation.
(c)
Interpreting
section 12B(4)(a) to exclude compensatory awards would render
the scheme of the PPA nugatory, as it would
then only be
available “for those few cases where the unfair or unreasonable
contractual practice is a premature termination
of a contract and
where such a contract still subsists when the matter is
arbitrated”.
[52]
This is not the case. The mechanism and the remedy of an award
would be available in all instances where there is an
unfair or
unreasonable contractual practice which is capable of being
corrected. Of course, if a relationship has come to
an end
there would be nothing by way of a practice to correct. In
those instances, however, the remedy of damages may well
be pursued
through the courts. Damages are, however, a different matter
from correcting an unfair or unreasonable contractual
practice.
Substitution
[72]
The
High Court made the following order:
“
43.1
The award of the second respondent which appears in paragraph 33.2 of
the
arbitration Award dated 3
April 2019, is reviewed and set aside.
43.2
The award in paragraph 33.2 is substituted with the following:
‘
The
second objection is upheld. An arbitrator acting in terms of
section 12B(4)(a)
of the
Petroleum Products Act No. 120 of 1977
as amended, has no jurisdiction to grant patrimonial damages to a
claimant in terms of
section 12B(4)(a)
, in this case, Mfoza.
Mfoza is directed to amend its Statement of Case so as to remove the
claim for patrimonial damages,
and to do so within 10 days of this
award.
43.3
By virtue of the expiry of the 10 day period referred to in paragraph
43.2 of this order, Mfoza is
directed to amend its statement of case
within 10 days of receipt of this order by mail or such further
period authorised
by the second respondent or agreed to by
Engen.
43.4
Mfoza is to pay the costs of this application.”
[53]
[73]
Mfoza
also challenges the order of the High Court by saying that it erred
in substituting the award of the Arbitrator. It
says that even
if the High Court was correct in finding that the Arbitrator exceeded
his powers, it could only—
(a)
set aside the award in terms of section 33(1)(b) of the
Arbitration Act; and
(b)
in terms of section 33(4) of the Arbitration Act and at the request
of either party, submit
the dispute to a new arbitration panel
constituted in the manner directed by the Court.
[74]
The
High Court did not act in terms of section 33(4) of the
Arbitration Act, nor was there a request by any of the parties
to that effect. It did, however, say that there was no case
made out that the Controller should appoint a new arbitrator
as it
concluded that, even though the Arbitrator had erred, he was
“perfectly well intentioned and
bona fide
”.
[54]
That largely disposes of the argument located in section 33(4)
of the Arbitration Act as, absent a request by the
parties to
the Court, the provisions of section 33(4) are not activated.
[75]
Was
the High Court entitled to make the order it did beyond setting aside
the award? Mfoza relies on the
dicta
in
Hos+Med
Medical Aid Scheme
[55]
to argue that the High Court’s order of substitution went
beyond the remit of section 33(1)(b) of the Arbitration Act.
In this case, the Supreme Court of Appeal held:
“
Where
neither party requests that the matter be referred back to the
arbitrator, or appeal tribunal, then an award made in excess
of its
powers should simply be set aside by the court in terms of section 33
of the Arbitration Act. Equally, because of
the peremptory
wording of section 33(4), a court does not have the discretion to
substitute its own order for that of the appeal
tribunal.”
[56]
[76]
The
orders which Mfoza describes as orders of substitution, and which
indeed are styled that way in the order of the High Court
are, on
careful scrutiny, no more than an explanation of the setting
aside award. The order contained in paragraph 43.2
of the
High Court judgment is no more than a restatement of the main
finding of the High Court that an arbitrator does
not have the
jurisdiction in terms of section 12B of the PPA to award
patrimonial damages. In addition, and arising
out of that, the
High Court ordered Mfoza to amend its statement of case.
[77]
It
cannot be said that the order of the High Court evidences
substitution of its own order in place of the award of the
Arbitrator.
The order read in its entirety, simply sets aside
the award and having done so explains the effect of the setting
aside.
It does not constitute an order of substitution and does
not in any manner violate the provisions of section 33(1)(b) of the
Arbitration Act.
Conclusion
[78]
The
appeal falls to be dismissed and costs should follow the result. The
costs of two counsel are justified.
Order
[79]
The following order is made:
1.
Leave to appeal is granted.
2.
The appeal is dismissed.
3.
The applicant is to pay the costs of this appeal, including the costs
of two
counsel where so employed
MHLANTLA J
(Madlanga J and Mlambo AJ concurring):
[80]
I have had the pleasure and benefit of reading the
comprehensive judgment penned by my Brother Kollapen J (first
judgment).
I agree that this matter engages the jurisdiction of
this Court and that leave to appeal should be granted. However,
I disagree
with the first judgment’s interpretation that the
arbitrator’s remedial powers under section 12B(4)(a) of the PPA
are
narrow and not inclusive of compensation.
[81]
The point of departure must be a consideration of section
12B(4) of the PPA. Section 12B(4) provides:
“
An
arbitrator contemplated in subsection (2) or (3) –
(a)
shall determine whether the alleged contractual practices concerned
are unfair
or unreasonable and, if so, shall make
such award as he or she deems necessary
to correct such practice;
and
(b)
shall determine whether the allegations giving rise to the
arbitration were
frivolous or capricious and, if so, shall make such award as he or
she deems necessary to compensate any party affected by such
allegations.”
[82]
From
a reading of section 12B(4) a few things become apparent, the first
being that the arbitrator’s remedial powers are wide.
Section 12B(4)(a) gives the arbitrator the power to “determine
whether the alleged contractual practices concerned are unfair
or
unreasonable” and, if the arbitrator has made a positive
determination on that aspect, the section mandates the arbitrator
to
“make such award as he or she deems necessary to correct such
practice”.
[57]
[83]
The
operative phrase in section 12B(4)(a) is “such award as he or
she deems necessary”. In this regard, the statute
clearly
denotes broad and discretionary powers. Furthermore, the plain
text of the section does not exclude compensation.
This Court
has also implicitly recognised that the arbitrator’s powers
under section 12B(4)(a) are wide.
[58]
When comparing the powers of the Controller under section 12B(1)
and the powers of the arbitrator under section 12B(4),
this Court
remarked “[t]hat the Controller’s discretionary threshold
is a low one is clear when consideration is had
to the mandate and
powers of the arbitrator under section 12B(4)”.
[59]
[84]
Second,
a reading and assessment of section 12B(4)(a) demonstrates that
compensation is not disqualified from the corrective remit
of the
arbitrator. My Brother takes the view that section 12B(4)(a)
excludes monetary compensation in all its forms as part
of the
corrective remedial jurisdiction of an arbitrator and that, by
conferring the power to make a compensatory award arising
out of
frivolous or capricious allegations in section 12B(4)(b), while
making no reference to a compensatory award in section 12B(4)(a),
the
Legislature did not intend to vest compensatory powers in the
arbitrator under section 12B(4)(a).
[60]
I respectfully disagree with that view.
[85]
The
fact that compensatory powers were not explicitly included in the
range of powers conferred on the arbitrator under section
12B(4)(a)
cannot be construed as indicative or demonstrative of the legislative
intention to exclude compensatory awards from the
arbitrator’s
remit. This is more so in view of the broad and general terms
in which section 12B(4)(a) has been framed.
[61]
Further, insofar as “compensation” is concerned,
parallels cannot be drawn between the framing of section 12B(4)(a)
and section 12B(4)(b) as contemplated by the first judgment, bearing
in mind the distinct purposes and functions of both subsections.
[86]
As I
see it, section 12B(4)(a), in the first instance, concerns the power
to determine whether an unfair or unreasonable contractual
practice
has taken place and, in the second instance, the power to make an
award that the arbitrator deems necessary to correct
the practice
once it has been determined that an unfair or unreasonable
contractual practice has taken place. In
Business
Zone
,
this Court elucidated that section 12B(4)(a) concerns the
mandate given to the arbitrator to “enter into and interrogate
the merits of the alleged contractual practice in order to make a
determination into the unfairness or unreasonableness thereof”.
[62]
On the other hand, section 12B(4)(b) comes into play where it
has been determined that allegations that led to the arbitration
were
“frivolous or capricious” and it grants the arbitrator
the powers to “make such award as he or she deems
necessary to
compensate any party affected by such allegations”. This
Court correctly interpreted section 12B(4)(b)
to be a “legislative
safeguard to prevent frivolous and capricious use of the section 12B
referral mechanism”.
[63]
It thus becomes apparent that section 12B(4)(a) is meant to be
remedial, while section 12B(4)(b) is meant to be a deterrent
against exploitation or abuse of process.
[87]
In the light of the distinction that must be drawn between the
objects and functions of section 12B(4)(a) and section 12B(4)(b),
it naturally follows that “compensation” under both
provisions is distinct. Under section 12B(4)(a),
compensation
is remedial in nature. Essentially, compensation
in this context takes the place of a contractual remedy, not unlike
restitution,
specific performance and contractual damages. By
contrast, compensation under section 12B(4)(b) is meant to be
punitive or
retributive. In this context, compensation
functions as a sanction and not a remedy in the same sense as in
section 12B(4)(a).
The section 12B(4)(b) compensation is,
to a large extent, akin to a costs order, more specifically a
punitive costs order.
This much was said in
Business Zone
,
where this Court held that—
“
the
arbitrator is not only mandated to determine frivolity and
capriciousness, but is empowered to make a compensatory award, which
imposes remedial and punitive costs beyond that of an ordinary costs
award. This provides a strong deterrent for parties
seeking to
exploit the section 12B(1) arbitration mechanism.”
[64]
[88]
To
illustrate this point, reference must be made to the facts of this
matter and the aims of section 12B(4)(a). As I understand
the
case, the qualifier in section 12B(4)(a) is “such award as
he or she deems necessary
to
correct such practice
”.
[65]
Therefore, the arbitrator’s duty is to issue an award that will
effectively correct the unfair or unreasonable practice.
In
order to fully appreciate what is meant by “to correct”,
the term must be dissected. As it is not defined
in the PPA,
reference must be made to its ordinary definition or meaning.
[66]
By deductive reasoning, “correct” in this context is used
as a transitive verb. The Oxford Dictionary defines
“correct”
as “to make something right or accurate”.
[67]
According to the Collins Dictionary, “[i]f you correct a
problem, mistake, or fault, you do something which puts it
right”.
[68]
The Cambridge Dictionary as well as the Merriam Webster
Dictionary contain similar definitions.
[69]
[89]
The central question then is: what type of awards fall in the
category of corrective measures? In my view, an award of
compensation
would be an effective remedy to correct a practice and
thus would fall within the category of corrective measures.
[90]
A
positive finding that compensatory remedial action falls within the
ambit of corrective measures would not be controversial or
tantamount
to reinventing the wheel as, under the general law of contracts,
compensation has already been recognised and confirmed
as performing
a corrective function. It is widely accepted that contractual
damages fall under the category of contractual
remedies that serve a
compensatory function.
[70]
This much was confirmed by the Supreme Court of Appeal in
Basson
.
[71]
There is a wealth of jurisprudence on the employment of damages to
“right a wrong”. In
Victoria
Falls & Transvaal Power Co Ltd
,
[72]
the Appellate Division, when discussing the assessment of
compensation for breach of contract, held:
“
The
sufferer by such a breach should be placed in the position he would
have occupied had the contract been performed, so far as
that can be
done by the payment of money, and without undue hardship to the
defaulting party.”
[73]
The
same principle has been espoused in
Novick
,
[74]
Bellairs
,
[75]
Freddy
Hirsch Group (Pty) Ltd
[76]
and
Basson
.
[77]
[91]
If it is accepted that damages are aimed at “making
something right” – ergo serving a corrective role –
and that damages are a form of recompense, by transitive reasoning it
follows that compensation qualifies as a corrective measure.
[92]
From the factual matrix of the matter before us, the cause of
complaint that led to arbitration was Engen’s alleged
frustration
of Mfoza’s business operations by delivering fuel
late and failing to honour its contractual obligations. Under
these
circumstances, if the arbitrator makes a finding to the effect
that Engen’s conduct amounts to an unfair contractual practice,
it would be expected that the arbitrator would issue an award that
effectively orders Engen to refrain from frustrating Mfoza’s
business operations and that compels Engen to observe the terms of
the contract. However, Mfoza did not ask for that remedy
(presumably because the contract had since terminated), but it has
alleged that it had suffered financial loss and thus claimed
an award
of compensation. Under the circumstances, an award of
compensation would be an effective remedy to correct the practice
as
the relationship between the parties had broken down and the
arbitrator would not be able to compel the parties to work together
again.
[93]
As
to the question whether the power to make such arbitral awards falls
within the arbitrator’s remedial remit, parallels
can be drawn
between this matter and labour law cases, specifically with reference
to the Commission for Conciliation, Mediation
and Arbitration
(CCMA). Section 193(1)(c) of the Labour Relations Act
[78]
empowers a CCMA arbitrator to make an order of compensation as a
remedy for unfair dismissal and unfair labour practice.
[79]
The nature of an arbitrator’s powers at the CCMA may be viewed
as analogous to the arbitrator’s in the present
case.
[94]
Additionally,
it is imperative to view the scope of the arbitrator’s powers
in the light of the broader legislative scheme
and intention.
As has been aptly and correctly observed by my colleague in the first
judgment,
[80]
and by this Court in several cases,
[81]
the primary objective of section 12B is to transform the petroleum
and liquid fuels industry by levelling the playing field as
it
relates to the bargaining power between wholesalers and retailers,
and by introducing the standard of fairness and reasonableness
in the
contractual relationships between petroleum wholesalers and
retailers.
[82]
[95]
If the arbitrator’s powers are constrained to remedial
action that only operates prospectively – to the exclusion of
compensatory awards as proposed by the first judgment – then
section 12B(4)(a) and the greater scheme of the PPA would be
rendered
nugatory. Essentially, there would be virtually no effective
remedy available for the vast majority of retailers
or litigants who
experience unfair or unreasonable contractual practices, save for
those few cases where the unfair or unreasonable
contractual practice
is a premature termination of a contract and where such a contract
still subsists when the matter is arbitrated.
This result
cannot reasonably be what the Legislature envisaged.
[96]
Further, it is worth noting that section 12B of the PPA has
been the subject of numerous judgments of this Court in the last
decade
alone and that the PPA has been amended approximately six
times, with the last amendment being the insertion of section 12B
itself in 2005. Given the wide saturation of the PPA in our
legal order, it can be said that if the primary legislative intention
was to restrict and limit the scope of the arbitrator’s powers
to only encompass prospective remedial action, thereby excluding
an
award of compensation from the scope of corrective measures under
section 12B(4)(a), the Legislature would have said as
much in
explicit terms by now. However, as it currently stands, the
text of section 12B(4)(a) tells a different story.
[97]
Consequently, in my view, the arbitrator’s remedial
powers under section 12B(4)(a) of the PPA are considerably
broad.
The arbitrator is left with an open ended range of
corrective measures from which to choose and there is no express
prohibition
of an award of monetary compensation. Therefore,
there is no basis to say that compensation is excluded. It is
included
in the wide inventory of awards that an arbitrator may make
under section 12B(4)(a) of the PPA to remedy unfair and/or
unreasonable
contractual practices.
[98]
Accordingly, had I commanded the majority, I would have made
an order granting leave to appeal and upheld the appeal with costs.
For
the Applicant:
G
Quixley and M De Beer
instructed
by Seton Smith and Associates
For
the First Respondent:
G
Marcus SC, M Desai and M Mbikiwa
instructed
by Govender Patel Dladla Incorporated
[1]
120 of 1977.
[2]
Engen
Petroleum Limited v The Business Zone 1010 CC t/a Emmarentia
Convenience Centre
[2015] ZASCA 176.
[3]
Bright
Idea Projects 66 (Pty) Ltd v Former Way Trade and Invest (Pty) Ltd
t/a Premier Service Station
2018
(6) SA 86 (KZP).
[4]
Id at para 33.
[5]
42 of 1965.
[6]
Engen
Petroleum Limited v Mfoza Service Station (Pty) Limited
,
unreported judgment of the High Court of South Africa, Gauteng
Local Division, Johannesburg, Case No 2019/17400 (5 October 2020)
(High Court judgment) at para 23.
[7]
Id at para 24.
[8]
Id.
[9]
Id.
[10]
Id at para 23.
[11]
Id.
[12]
Id at para 26.
[13]
Id at para 32.
[14]
Id.
[15]
Id at para 39.
[16]
Business
Zone SCA
above n 2.
[17]
3 of 2000.
[18]
Business
Zone 1010 CC t/a Emmarentia Convenience Centre v Engen Petroleum
Limited
[2017] ZACC 2; 2017 (6) BCLR 773 (CC).
[19]
Department
of Land Affairs v Goedgelegen Tropical Fruits (Pty) Ltd
[2007] ZACC 12; 2007 (6) SA 199 (CC); 2007 (10) BCLR 1027 (CC).
[20]
Id at para 53.
[21]
Pharmaceutical
Manufacturers Association of SA: In re Ex parte President of the
Republic of South Africa
[2000] ZACC 1
;
2000 (2) SA 674
(CC);
2000 (3) BCLR 241
(CC) at para
20.
[22]
Paulsen
v Slip Knot Investments 777 (Pty) Ltd
[2015] ZACC 5
;
2015 (3) SA 479
(CC);
2015 (5) BCLR 509
(CC) at para
26.
[23]
S v
Boesak
[2000]
ZACC 25
;
2001 (1) SA 912
(CC);
2001 (1) BCLR 36
(CC) at para 12.
[24]
Business
Zone CC
above
n 18 at para 48.
[25]
Crompton
Street Motors CC t/a Wallers Garage Service Station v Bright Idea
Projects 66 (Pty) Ltd t/a All Fuels
[2021] ZACC 24; 2022 (1) SA 317 (CC); 2021 (11) BCLR 1203 (CC).
[26]
Id at para 42.
[27]
Id. See also
Business
Zone CC
above n 18 at para 58.
[28]
Business
Zone CC
above
n 18 at para 55.
[29]
Emphasis added.
[30]
Business
Zone CC
above
n 18
at para 61.
[31]
Section 12B(1) of the PPA.
[32]
Business
Zone CC
above n 18 at para 58. Section 12B(2) of the PPA allows
the parties to a section 12B arbitration to determine
the rules
in accordance with which the arbitration will be conducted as well
as the choice of arbitrator before whom the arbitration
will
proceed.
[33]
Cool
Ideas 1186 CC v Hubbard
[2014] ZACC 16; 2014 (4) SA 474 (CC); 2014 (8) BCLR 869 (CC).
[34]
Id at para 28.
[35]
Emphasis added.
[36]
Minister
of Public Works v Haffejee N.O
.
[1996] ZASCA 17
;
1996 (3) SA 745
(SCA) at para 11.
[37]
Business
Zone CC
above n 18 at para 76.
[38]
Business
Zone CC
above
n 18 at para 76.
[39]
Business
Zone SCA
above
n 2 at para 45.
[40]
Chisuse
v Director-General, Department of Home Affairs
[2020] ZACC 20
;
2020 (6) SA 14
(CC);
2020 (10) BCLR 1173
(CC).
[41]
Id at para 47.
[42]
Id at para 52.
[43]
Amabhungane
Centre for Investigative Journalism NPC v Minister of Justice and
Correctional Services
[2021] ZACC 3; 2021 (3) SA 246 (CC); 2021 (4) BCLR 349 (CC).
[44]
Id at para 63.
[45]
Business
Zone CC
above n 18 at para 92.
[46]
Competition
Commission of South Africa v Pickfords Removals SA (Pty) Ltd
[2020] ZACC 14; 2021 (3) SA 1 (CC); 2020 (10) BCLR 1204 (CC).
[47]
Id at para 50.
[48]
Crompton
above n 25 at paras 26 and 28.
[49]
Section 33(1) of the Arbitration Act provides:
“
Where—
(a)
any member of an arbitration tribunal has misconducted himself
in
relation to his duties as arbitrator or umpire; or
(b)
an arbitration tribunal has committed any gross irregularity
in the
conduct of the arbitration proceedings or has exceeded its powers;
or
(c)
an award has been improperly obtained,
the
court may, on the application of any party to the reference after
due notice to the other party or parties, make an order
setting the
award aside.”
[50]
Wary
Holdings (Pty) Ltd v Stalwo (Pty) Ltd
[2008] ZACC 12; 2009 (1) SA 337 (CC); 2008 (11) BCLR 1123 (CC).
[51]
Id at paras 46-7.
[52]
See the second judgment at [95].
[53]
High Court judgment above n 6 at para 43.
[54]
Id at para 39.
[55]
Hos+Med
Medical Aid Scheme v Thebe Ya Bophelo Healthcare Marketing &
Consulting (Pty) Ltd
[2007]
ZASCA 163; 2008 (2) SA 608 (SCA).
[56]
Id at para 43.
[57]
Section
12B(4)(a) expressly states that an arbitrator “
shall
make such award as he or she deems necessary to correct such
practice”. The use of the word “shall”
denotes a mandate.
[58]
Crompton
above
n 25 at para 45, where this Court held:
“
Although
the above was said in the context of private contractual
arbitration, it applies equally to statutory arbitration in
terms of
section 12B, which must be understood as arbitration ordinarily is
in the law of contract. The benefits of arbitration
outlined
in
Lufuno
are
evident from the text of section 12B itself and were considered in
Business Zone
.
Among others, the parties can choose both a specialised
arbitrator and the rules of procedure which that arbitrator is
to
follow,
the arbitrator has wide
remedial powers to remedy the unfair or unreasonable contractual
practice and make compensatory awards
;
and, the arbitrator’s award is final and binding,
which avoids the ordinary appellate
processes applicable to litigation, and thus saves time and
resources
”. (Emphasis added).
[59]
Business
Zone CC
above
n
18 at para 62.
[60]
Id at [56]
[61]
Section
12B(4)(a) does not provide a list of remedial awards that may be
made by the arbitrator.
[62]
Business
Zone CC
above
n
18 at para 63.
[63]
Id.
[64]
Id.
[65]
Emphasis
added.
[66]
See
Independent
Institute of Education (Pty) Limited v Kwazulu-Natal Law Society
[2019] ZACC 47
;
2020 (2) SA 325
(CC);
2020 (4) BCLR 495
(CC) at para
18.
[67]
Oxford Advanced Learner's Dictionary “Correct
verb
”, available at
https://www.oxfordlearnersdictionaries.com/definition/american_english/correct_2
.
[68]
Collins Dictionary “Correct”, available at
https://www.collinsdictionary.com/dictionary/english/correct
.
[69]
See Cambridge Dictionary “Correct”, available at
https://dictionary.cambridge.org/dictionary/english/correct
and
Merriam Webster Dictionary “Correct”, available at
https://www.merriam-webster.com/dictionary/correct.
[70]
See Hutchison et al
The
Law of Contract in South Africa
1 ed (Oxford University Press Southern Africa, 2009) at 310 and
Stuart-Steer “Reconsidering an Understanding of Damages
as a
Surrogate of Specific Performance in South African Law of Contract”
(2013)
Responsa
Meridiana
65.
[71]
Basson
v Hanna
[2016] ZASCA 198
;
2017 (3) SA 22
(SCA) at para 22.
[72]
Victoria
Falls & Transvaal Power Co Ltd v Consolidated Langlaagte Mines
Ltd
1915 AD 1.
[73]
Id at 22.
[74]
Novick
v Benjamin
1972 2 SA 842
(A) at 860A-B.
[75]
Bellairs
v Hodnett
1978 1 SA 1109
(A) at 1146H.
[76]
Freddy
Hirsch Group (Pty) Ltd v Chickenland (Pty) Ltd
[2011] ZASCA 22
;
2011 (4) SA 276
(SCA) at para 26.
[77]
Basson
above n 73 at para 26.
[78]
66 of 1995.
[79]
Section 193(1) and (4) provides:
“
(1)
If the Labour Court or an arbitrator appointed in terms of this Act
finds
that a dismissal
is
unfair, the Court or the arbitrator may—
(a)
order the employer to reinstate the employee from any date not
earlier than
the
date of dismissal;
(b)
order the employer to re-employ the employee, either in the work
in
which
the
employee was employed before the dismissal or in other reasonably
suitable work on any terms and from any date not earlier
than the
date of dismissal; or
(c)
order the employer to pay compensation to the employee.
.
. .
(4)
An arbitrator appointed in terms of this Act may determine any
unfair labour practice
dispute
referred to the arbitrator, on terms that the arbitrator deems
reasonable, which may include ordering reinstatement, reemployment
or compensation.”
[80]
See the
first
judgment at [33] - [34].
[81]
See
Crompton
above
n
25
and
Business
Zone CC
above
n 3.
[82]
See the
first
judgment at [34].
sino noindex
make_database footer start
Similar Cases
Seebed CC t/a Siyabonga Convenience Centre v Engen Petroleum Limited (CCT 290/20) [2022] ZACC 28; 2023 (12) BCLR 1535 (CC) (20 July 2022)
[2022] ZACC 28Constitutional Court of South Africa98% similar
Tholo Energy Services CC v Commissioner for the South African Revenue Service (CCT 252/24) [2026] ZACC 1 (16 January 2026)
[2026] ZACC 1Constitutional Court of South Africa97% similar
Transnet SOC Limited v Total South Africa (Pty) Limited and Another (CCT 114/21) [2022] ZACC 21; 2023 (3) BCLR 333 (CC) (21 June 2022)
[2022] ZACC 21Constitutional Court of South Africa97% similar
Esorfranki Pipelines (Pty) Ltd v Mopani District Municipality (CCT 222/21) [2022] ZACC 41; 2023 (2) BCLR 149 (CC); 2023 (2) SA 31 (CC) (30 November 2022)
[2022] ZACC 41Constitutional Court of South Africa97% similar
Merifon (Pty) Limited v Greater Letaba Municipality and Another (CCT 159/21) [2022] ZACC 25; 2022 (9) BCLR 1090 (CC) (4 July 2022)
[2022] ZACC 25Constitutional Court of South Africa97% similar